19
Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

Embed Size (px)

Citation preview

Page 1: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

1

Construction Materials Industry ConferenceDelivering Australia’s Pipeline

Jennifer Westacott

20 September 2012

Page 2: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

2

Overview of presentation

Key growth challenge – pipeline or pipe dream?

• Australia’s investment opportunity

• Australia’s project performance

• Challenges and solutions

• COAG and BCA reviews

Page 3: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

3

Australia’s Investment Opportunity

Page 4: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

4

The project pipeline

Source: Deloitte Access Economics.

Australia’s $921b Investment pipeline – projects by status

Under

Committed, $66

Under consideration

$192b

Possible $279b

Under construction

$384b

Committed $66b

Page 5: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

5

Pipeline facts

Projects unprecedented in size

Projects unprecedented in number

Remoteness

Narrow sector base

Page 6: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

6

This matters

Source: Deloitte Access Economics using real investment and GDP data.

Investment and exports as a percentage of GDP, Australia

10

15

20

25

30

35

10

15

20

25

30

35

1991-92 1996-97 2001-02 2006-07 2011-12 2016-17 2021-22

Investment (total)

Exports

Per cent of GDPPer cent of GDP

Projections

Page 7: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

7

Risks to delivery

Pipeline delivery risks

• Revenue risk

• Cost and time blowouts

• Missed opportunities due to project deferral or abandonment

Page 8: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

8

Australia’s Project Performance

Page 9: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

9

Critical question

How well do we deliver projects?

Page 10: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

10

Data on project performance

Note: cost premium is calculated in US dollars

Source: Resources projects data by Independent Project Analysis; other data from Turner & Townsend, International Construction Costs Survey 2012. Note: Turner & Townsend sourced costs are US dollar relativities per m2.

40% 26% 43%62%

90%

0%

20%

40%

60%

80%

100%

0%

20%

40%

60%

80%

100%

Resources projects

Schools Large shoppingcentres

Hospitals Airports

Cost premium Cost premium

Page 11: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

11

How do we perform?

Project performance

• Lack of robust data for infrastructure projects

• Need to understand cost drivers

• Better measurement can help lift performance

• Warnings in global project data

Page 12: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

12

Challenges and Solutions

Page 13: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

13

Barriers to project delivery

Community concerns

Capacity constraints

Efficiency problems

Timely funding and delivery of public infrastructure

Investor confidence

Page 14: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

14

Solutions

1. Build higher levels of community understanding and acceptance for projects

2. Expand Australia’s capacity to deliver multiple capital projects

Page 15: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

15

Solutions

3. Improve the efficiency of project delivery in Australia

4. Adequate provision of economic and social infrastructure

Page 16: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

16

Solutions

5. Build the confidence of investors

6. Supportive government institutions, policies and programs

Page 17: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

17

BCA and COAG reviews

Page 18: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

18

BCA/COAG reviews

What’s next

• COAG review of construction costs

• BCA review of project costs

Page 19: Construction Materials Industry Conference Delivering Australia’s Pipeline Jennifer Westacott 20 September 2012 1

19

The four steps to recovery

• Commonwealth to amend EPBC Act – give states authority to assess/approve projects

• State governments to fast-track major development approvals

• Amend Fair Work Act – include employer-only agreements on greenfield projects so work can start sooner

• Cease tinkering with the tax system