Upload
liza-khanam
View
232
Download
0
Embed Size (px)
Citation preview
7/28/2019 COST CH6 Standard Cost
1/74
7/28/2019 COST CH6 Standard Cost
2/74
7/28/2019 COST CH6 Standard Cost
3/74
7/28/2019 COST CH6 Standard Cost
4/74
StandardA standard is a benchmark or norm for measuringperformance.
Standard are widely used in managerial accounting wherethey relate to the quantity & cost of inputs in manufacturing
goods & providing services.
Quantity standards specify how much of an input should beused to make a product or provide a service.
Cost or price standards specify how much should be paid for
each unit of input.
7/28/2019 COST CH6 Standard Cost
5/74
Standard CostA standard cost is a planned or pre-determined cost
which is calculated from managements standard of
efficient operation & the relevant necessary expenditure.
7/28/2019 COST CH6 Standard Cost
6/74
Standard Costing Standard costing is the preparation of standard costsand applying them to measure the variations from
actual costs and analyzing the causes of variations
with a view to maintain maximum efficiency in
production.
It can be used as a process of measuring and
correcting actual performance to ensure that the plans
are properly set and implemented
7/28/2019 COST CH6 Standard Cost
7/74
Purpose of Standard Costing Establishing budgets. Controlling costs, directing and motivating employees
and measuring efficiencies.
Promoting possible cost reduction.
Simplifying costing procedures and expediting costreports.
Assigning costs to materials, work in process, andfinished goods inventories.
Forming the basis for establishing bids and contractsand for setting sales prices
7/28/2019 COST CH6 Standard Cost
8/74
Procedures of standard costing system
Set the predetermined standards for sales margin and productioncosts
Collect the information about the actual performance
Compare the actual performance with the standards to arrive at
the variance
Analyze the variances and ascertaining the causes of variance
Take corrective action to avoid adverse variance
Adjust the budget in order to make the standards more realistic
7/28/2019 COST CH6 Standard Cost
9/74
Functions of standard costing system
Valuation
Assigning the standard cost to the actual output
Planning
Use the current standards to estimate future sales
volume and future costs
Controlling
Evaluating performance by determining how efficiently
the current operations are being carried out
7/28/2019 COST CH6 Standard Cost
10/74
Functions of standard costing system
Motivation
Notify the staff of the managements expectations
Setting of selling price
7/28/2019 COST CH6 Standard Cost
11/74
Ideal Standard Ideal standards are those that can be attained onlyunder the best circumstances.
These can be achieved through the best possible
combination of factors i.e. maximum output atminimum cost.
Assumption:
Extremely tight & do not provide
for waste & inefficient in any
forms.
No material is wasted.
No units are spoiled.
No idle time.
Operators work at predeterminedspeed.
The available capacity is fully
utilized
7/28/2019 COST CH6 Standard Cost
12/74
Practical Standard Practical standards are those standards that are tightbut attainable.
Assumption:
Allow for normal machine downtime
Employee rest period.
Practical standards are used in
Using signaling abnormal condition Forecasting cash flows
Planning inventory
7/28/2019 COST CH6 Standard Cost
13/74
Setting Standard Past records of purchase prices and input usage can help insetting standards.
Setting price and quantity standards requires the combinedexpertise of all persons who have responsibility over input
prices and over effective use of inputs.
The standards should be designed to encourage efficient
future operations, not a repetition of past inefficient
operations.
7/28/2019 COST CH6 Standard Cost
14/74
Setting Standard Standard must be established for a definite period of
time so that they can be effective in performance
evaluation, control & analysis of costs.
Standards are developed for-
Materials
Labor
Overhead
7/28/2019 COST CH6 Standard Cost
15/74
Connotation of Standard
Standard
Price
Quantity
Material
Price
Quantity
Labor
Rate
Hour
Overhead
Rate
Hour
7/28/2019 COST CH6 Standard Cost
16/74
Object Matrix
Object
AP
SP
AQ
AQ*AP
AQ*SP
SQ
--
SQ*SP
AQ=Actual QuantityAP=Actual PriceSQ=StandardQuantitySP=Standard Price
7/28/2019 COST CH6 Standard Cost
17/74
Factors in Setting Price Standard Purchase Price
Freight
Receiving & handling
Purchase discount
7/28/2019 COST CH6 Standard Cost
18/74
Factors in Setting Quantity Standard
Basic materials input i.e. materials
requirement as specified in the bill of
material.Allowance for waste & spoilage
Allowances for rejecting defective materials
Evaporation
Leakage
7/28/2019 COST CH6 Standard Cost
19/74
Factors in Setting Rate Standard
Basic wage rate per hour
Employment taxes
Fringe benefit
Union negotiation
Experience of the worker
7/28/2019 COST CH6 Standard Cost
20/74
Factor in Setting Time(Hour) Standard
Basic labor time
Allowance for breaks & personal needs
Allowance for cleanup & machine downtime
Allowance for reject
Allowance for set-up time
Allowance for fatigue
Waiting time of operator
7/28/2019 COST CH6 Standard Cost
21/74
Variance analysis
A variance is the difference between the
standards and the actual performance
When the actual results are better than the
expected results, there will be a favorable
variance (F).
If the actual results are worse than the expected
results, there will be an adverse variance (A).
7/28/2019 COST CH6 Standard Cost
22/74
Profit variance
Selling andadministrativeCost variance
Total productionCost variance
Sales Variance
Sales variance basedon turnover Sales Variancebased on Margin
Materialscostvariance
LaborCostvariance
VariableOverheadvariance
FixedOverheadvariance
Overhead variance
7/28/2019 COST CH6 Standard Cost
23/74
Three types of cost variance
Material cost variance
Labor cost variance
Overheads variance
Variable overheads variance
Fixed overheads variance
7/28/2019 COST CH6 Standard Cost
24/74
Materials cost variance(AQ*AP SQ*SP)
Material Price varianceAQ*AP AQ*SP Material Usage VarianceAQ*SP SQ*SP
Mix Variance Yield Variance
Actual Units
Produced*SQ P/U
7/28/2019 COST CH6 Standard Cost
25/74
Labor Cost VarianceAH*AR SH*SR
Rate VarianceAH*AR AH*SR
Mix Variance Yield Variance
Idle Time VarianceSR*Hours Lost
Efficiency VarianceAH*SR SH*SR
Actual UnitsProduced*SH
P/U
7/28/2019 COST CH6 Standard Cost
26/74
Overhead CostVariance
Variable OverheadVariance
Fixed OverheadVariance
7/28/2019 COST CH6 Standard Cost
27/74
Variable Overhead variance
(AH*AR
SH*SR)
VOExpenditure/Spending/
Budget Variance
AH*AR
AH*SR
VO EfficiencyVariance
AH*SR SH*SR
Actual Units
Produced*SVMO P/U
7/28/2019 COST CH6 Standard Cost
28/74
Fixed Overhead varianceAOC SH*SFOR
Fixed O/H Expenditure VarianceAFOH - SFOH
Fixed O/H Volume variance(AP
SP)*SFOHR PU
EfficiencyvarianceCalendervariance CapacityVariance
7/28/2019 COST CH6 Standard Cost
29/74
Sales Value Variance(AQS*ASP SQS*SSP)
Sales Price VarianceASP* AQS SSP*AQS
Sales Volume VarianceAQS *SSP SQS*SSP
Sales Mix Variance Sales Quantity Variance
7/28/2019 COST CH6 Standard Cost
30/74
Total sales margin variance(Actual Profit Budgeted Profit)
Sales Margin PriceVariance
(AMPU
SSMPU)*AQ
Sales Margin VolumeVariance
(AQ
SQ)*SSMPU
Sales Margin QuantityVariance
Sales Margin MixVariance
(SSPPU
SCPU)(ASPPU
SCPU)
P bl
7/28/2019 COST CH6 Standard Cost
31/74
Problem
Direct Materials
Direct Labor
VariableManufacturingO/H
Total Standard Cost
Standard
Quantity OrHour
Standard
Price or Rte
Standard
Cost
ZB Company produce a single product. Variablemanufacturing overhead is applied to products on thebasis of direct-labor-hours. The standard costs for one unitof product are as under:
2.5 Hours Tk. 3 Tk. 7.5
Tk. 54.50
2.5 Hours Tk. 14 Tk.35
3 Pound Tk. 4 Tk.12
7/28/2019 COST CH6 Standard Cost
32/74
Direct Materials
Direct Labor
VariableManufacturing
O/H
Actual QuantityOr Hour
ActualPrice or
Rate
ActualCost
During June, 2011, 2000 units were produced. The costs associatedwithJunes operations were as under
5400 Hours Tk. 2.85 Tk.15390
5400 Hours Tk. 13.75 Tk.74250
6500 Pound Tk. 3.80 Tk.24700
7/28/2019 COST CH6 Standard Cost
33/74
2. Compute & Comment on the Labor variance.3. Compute & Comment on Manufacturing Overhead
Variance.
Requirements:1. Compute & Comment on the material variance ifI. All of the material purchased was used during June.II. 5000 units of materials is used during the period of
to produce 1600 units of products
Requirement: 01 (i)
7/28/2019 COST CH6 Standard Cost
34/74
Material Price Variance = (AP SP)*AQ= (Tk.3.80 Tk.4)*6500 pounds
= Tk.1300 F
Requirement: 01 (i)
Data Derived:Standard Quantity (SQ) = SQ Per Unit * Units Produced
= 3 Pounds * 2000 Units= 6000 Pounds
Material Quantity Variance = (AQ SQ)*SP
= (6500 6000)* Tk.4= Tk.2000 USince actual quantity is more than standard quantity toproduce 2000 units of product, material quantity variance
is unfavorable.
Requirement: 01 (ii)
7/28/2019 COST CH6 Standard Cost
35/74
In this situation material price variance is not computed.This is because it is calculated when materials are
purchased by purchase manager. Here only quantityvariance will be calculated.
Requirement: 01 (ii)
Here AQ = 5000 units
SQ = 3 pounds * 1600 units = 4800 poundsMaterial Quantity Variance = (AQ SQ)*SP
= (5000 4800)* Tk.4= Tk.800 U
Since actual quantity is more than standard quantity toproduce 1600 units of product, material quantity varianceis unfavorable.
Requirement: 02
7/28/2019 COST CH6 Standard Cost
36/74
Labor Rate Variance = (AR SR)*AH= (Tk13.75 Tk.14)*5400 hours
= Tk.1350 F
Requirement: 02
Data Derived:Standard Hour (SH) = SH Per Unit * Units Produced
= 2.5 hrs * 2000 Units= 5000 Hours
Labor Efficiency Variance = (AH SH)*SR
= (5400
5000)* Tk.14= Tk.5600 USince actual hours is more than standard hours to produce2000 units of product, so material quantity variance is
unfavorable.
Requirement: 03
7/28/2019 COST CH6 Standard Cost
37/74
Variable O/H Variance = (AR SR)*AH= (Tk.2.85 Tk.3)*5400 hours
= Tk.810 F
Requirement: 03
Data Derived:Standard Hour (SH) = SH Per Unit * Units Produced
= 2.5 hrs * 2000 Units= 5000 Hours
Variable O/H Efficiency Variance = (AH SH)*SR= (5400 5000)* Tk.3= Tk.1200 U
Since actual hours is more than standard hours to produce2000 units of product, so material quantity variance is
unfavorable.
7/28/2019 COST CH6 Standard Cost
38/74
Reasons for variances
Material price variance
Price changes in market conditions
Change in the efficiency of purchasing dept. to obtain
good terms from suppliers
Purchase of different grades or wrong types of materials
Non-availability of quantity discount
Freight cost changes & changes in purchasing &
storekeeping costs.
7/28/2019 COST CH6 Standard Cost
39/74
Materials usage variance
More effective use of materials/ wastage arising from
the efficient production process
Purchase of different grade or wrong types of materials
Wastage by the staff
Change in production methods
Poor material handling
Reasons for variances
7/28/2019 COST CH6 Standard Cost
40/74
Labor rate variance Non-controllable market changes in the basic wage
rate
Use of higher/lower grade of workers
Unexpected overtime allowance paid
Labor strike leading to utilization of unskilled help
Change in labor rate within industry
Reasons for variances
7/28/2019 COST CH6 Standard Cost
41/74
Labor efficiency
variance Purchase of different grade
or wrong types ofmaterials
Breakdown of machinery
High/low labour turnover
Changes in production
method
Introduction of newmachinery
Reasons for variances
Poor working condition
Assignment wrong type of
worker to work
Adequacy of supervision
Changes in workingcondition
Change in motivation
methods
Poor supervision
Insufficient training of
workers
7/28/2019 COST CH6 Standard Cost
42/74
Variable overheads expenditure variance
It may be caused by the non-controllable change in
the price level of indirect wages or utility rates sincethe predetermined rate is set
It is meaningless to interpret this kind of variance on
its own. One should look various components of the
fixed overheads
Reasons for variances
7/28/2019 COST CH6 Standard Cost
43/74
Variable overheads efficiency variance
Both the variable overheads and direct
labor cost vary with the direct labor hours
worked
Reasons for variances
7/28/2019 COST CH6 Standard Cost
44/74
Fixed overheads expenditure
It is meaningless to interpret this kind of
variance on its own.
It may be caused by the change in the price
levels of rent, rates and other fixed
expenses
Reasons for variances
7/28/2019 COST CH6 Standard Cost
45/74
Fixed overhead volume variance
When the level of activity is higher than
the budgeted level, there is a favourable
variance
Reasons for variances
7/28/2019 COST CH6 Standard Cost
46/74
Sales margin price variance
Change in the pricing strategies of the company
Response to the change of pricing policies of itscompetitors
Higher profit margin with growing demand for
the product Lower profit margin for simulating sales
Reasons for variances
7/28/2019 COST CH6 Standard Cost
47/74
Sales margin volume variance
Change in prices and demand
Change in the market share of its competitors
Reasons for variances
7/28/2019 COST CH6 Standard Cost
48/74
Responsibility for cost Variance
MPV Purchasing Agent/Manager
MQV Plant Superintendent, Departmental Supervisor,
Production Manager, Machine Operator
LRV HRD, Departmental Supervisor, Plant Superintendent
LEV Plant Superintendent, Departmental Supervisor,
Production Manager, Machine Operator
OSV
OVV
7/28/2019 COST CH6 Standard Cost
49/74
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
50/74
The Balanced Scorecard (BSC) was published in 1992 by
Robert Kaplan and David Norton.
A Balanced scorecard consists of an integrated set of
performance measures that are derived from the
companys strategy & that support the companys strategy
throughout the organization.
The Balanced Scorecard evaluates the firm's efforts for
future improvement using process, customer, and learning
and growth metrics.
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
51/74
The term "scorecard" signifies quantified performance
measures and "balanced" signifies that the system is
balanced between:
short-term objectives and long-term objectives
financial measures and non-financial measures
lagging indicators and leading indicators
internal performance and external performance
perspectives
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
52/74
The Balanced Scorecard is a management system that
maps an organization's strategic objectives into
performance metrics in four perspectives:
financial performance,
internal processes,
customers, and
learning and growth.
7/28/2019 COST CH6 Standard Cost
53/74
Balanced Score Card Framework
Financial Performance
ObjectivesMeasures
Targets
Initiative
Learning & Growth
Objectives
Measures
Targets
Initiative
CustomersObjectives
Measures
Targets
Initiative
Internal ProcessObjectives
Measures
Targets
Initiative
Strategy
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
54/74
The financial perspective addresses the question of
how shareholders view the firm and
which financial goals are desired from the
shareholder's perspective.
The specific goals depend on the company's stage in the
business life cycle.
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
55/74
The customer perspective addresses the question of
how the firm is viewed by its customers and
how well the firm is serving its targeted customers
in order to meet the financial objectives.
Generally, customers view the firm in terms of time,
quality, performance, and cost.
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
56/74
Internal business process objectives address the
question of
which processes are most critical for satisfying
customers and shareholders. These are the processes in which the firm must
concentrate its efforts to excel.
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
57/74
Learning and growth metrics address the question of
how the firm must learn, improve, and innovate in
order to meet its objectives.
Much of this perspective is employee-centered.
Balanced Score Card
7/28/2019 COST CH6 Standard Cost
58/74
Within each of the Balanced Scorecard financial,customer, internal process, and learning perspectives, thefirm must define the following:
Strategic objectives - what the strategy is to achieve in
that perspective.
Measures - how progress for that particular objective
will be measured.
Targets - the target value sought for each measure.
Initiatives - what will be done to facilitate the reaching
of the target.
The Process of Building A Balanced Score Card
7/28/2019 COST CH6 Standard Cost
59/74
g
7/28/2019 COST CH6 Standard Cost
60/74
7/28/2019 COST CH6 Standard Cost
61/74
Step-one: Assessment
Assessment of the organizations Mission & Vision,
challenges (pains), enablers & values.
Preparing a change management plan for the
organization & conducing a focused communication
workshop to identify messages, media outlets, timing, &
messengers.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
62/74
Step Two: Strategy
In Step Two, elements of the organizations strategy,
including Strategic Results, Strategic Themes, and
Perspectives, are developed by workshop participants to
focus attention on customer needs and the organizations
value proposition.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
63/74
Step Three: Objectives In Step Three, the strategic elements developed in Steps
One and Two are decomposed into Strategic Objectives,
which are the basic building blocks of strategy and define
the organization's strategic intent.
Objectives are first initiated and categorized on the
Strategic Theme level, categorized by Perspective, linked
in cause-effect linkages (Strategy Maps) for each StrategicTheme, and then later merged together to produce one set
of Strategic Objectives for the entire organization.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
64/74
Step Four: Strategy Map
In Step Four, the cause and effect linkages between the
enterprise-wide Strategic Objectives are formalized in an
enterprise-wide Strategy Map.
The previously constructed theme Strategy Maps are
merged into an overall enterprise-wide Strategy Map that
shows how the organization creates value for its customers
and stakeholders.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
65/74
Step Five: Performance Measures
In Step Five, Performance Measures are developed for
each of the enterprise-wide Strategic Objectives.
Leading and lagging measures are identified, expected
targets and thresholds are established, and baseline and
benchmarking data is developed.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
66/74
Step Six: Initiatives
In Step Six, Strategic Initiatives are developed that support
the Strategic Objectives.
To build accountability throughout the organization,
ownership of Performance Measures and Strategic
Initiatives is assigned to the appropriate staff and
documented in data definition tables.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
67/74
Step Seven: Automation In Step Seven, the implementation process begins by
applying performance measurement software to get the
right performance information to the right people at the
right time. Automation adds structure and discipline to implementing
the Balanced Scorecard system, helps transform disparate
corporate data into information and knowledge, and helps
communicate performance information.
In short, automation helps people make better decisions
because it offers quick access to actual performance data.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
68/74
Step Eight: Cascade In Step Eight, the enterprise-level scorecard is cascaded
down into business and support unit scorecards, meaning
the organizational level scorecard (the first Tier) is
translated into business unit or support unit scorecards (thesecond Tier) and then later to team and individual
scorecards (the third Tier). Cascading translates high-level
strategy into lower-level objectives, measures, and
operational details. Cascading is the key to organization
alignment around strategy. Team and individual scorecards
link day-to-day work with department goals and corporate
vision.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
69/74
Cascading is the key to organization alignment around
strategy. Performance measures are developed for all
objectives at all organization levels.
As the scorecard management system is cascaded downthrough the organization, objectives become more
operational and tactical, as do the performance measures.
Accountability follows the objectives and measures, as
ownership is defined at each level.
An emphasis on results and the strategies needed to produce
results is communicated throughout the organization.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
70/74
Step Nine: Evaluation
In Step Nine, an Evaluation of the completed scorecard is
done. During this evaluation, the organization tries to
answer questions such as, Are our strategies working?,
Are we measuring the right things?, Has our
environment changed? and Are we budgeting our money
strategically?.
The Process of Building A Balanced Scorecard
7/28/2019 COST CH6 Standard Cost
71/74
Benefits of the Balanced Scorecard system
Translation of strategy into measurable parameters.
Communication of the strategy to everybody in the firm.
Alignment of individual goals with the firm's strategicobjectives - the BSC recognizes that the selected
measures influence the behavior of employees.
Feedback of implementation results to the strategic
planning process.
7/28/2019 COST CH6 Standard Cost
72/74
Pitfall of the Balanced Scorecard system
Lack of a well-defined strategy: The Balanced
Scorecard relies on a well-defined strategy and an
understanding of the linkages between strategicobjectives and the metrics. Without this foundation,
the implementation of the Balanced Scorecard is
unlikely to be successful.
7/28/2019 COST CH6 Standard Cost
73/74
Pitfall of the Balanced Scorecard system
Using only lagging measures: Many managers believe
that they will reap the benefits of the Balanced
Scorecard by using a wide range of non-financial
measures. However, care should be taken to identify
not only lagging measures that describe past
performance, but also leading measures that can be
used to plan for future performance.
7/28/2019 COST CH6 Standard Cost
74/74
Use of generic metrics: It usually is not sufficient simply
to adopt the metrics used by other successful firms. Each
firm should put forth the effort to identify the measures
that are appropriate for its own strategy and competitive
position.
Pitfall of the Balanced Scorecard system