Upload
others
View
16
Download
0
Embed Size (px)
Citation preview
M/S MEGHMANI FINECHEM
LTD.
Draft EIA & EMP Report for Expansion in Power Plant Capacity from 65 MW to 132 MW at Plot No. CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat
JANUARY, 2018
ACCREDITATION DETAILS
NABET Certificate No. NABET/EIA/1316/RA 004 valid from 04-10-2013 upto 18-09-2016;
Accreditation Extension Letter extending the validity up to 04-04-2017 in response to KEC’s
application dated 15-09-2016;
NABET Certificate No. NABET/EIA/1619/RA 0042, Issued on 28-03-2017, Valid upto 26-05-2019.
Kadam Environmental Consultants
w w w . k a d am e n v i r o . c o m
E n v i r o n m e n t f o r D e v e l o p m e n t
E: [email protected]; T:+91-265-6131000
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW
TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT QUALITY CONTROL
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 2
M/S MEGHMANI FINECHEM LTD.
Draft EIA & EMP Report for Expansion in Power Plant Capacity from 65 MW to 132 MW at Plot No. CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat. © Kadam Environmental Consultants (‘Kadam’), January, 2018
This report is released for the use of the M/S. Meghmani Finechem Ltd, Regulators and relevant stakeholders solely
as part of the subject project’s Environmental Clearance process. Information provided (unless attributed to
referenced third parties) is otherwise copyrighted and shall not be used for any other purpose without the written
consent of Kadam.
QUALITY CONTROL
Name of Publication EIA & EMP Report for Expansion in Power Plant Capacity from 65 MW to 132 MW at Plot No. CH-
1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat.
Project Number 1521721306 Issue No. 1 Revision No. 1 Released January, 2018
CONTACT DETAILS
Vadodara (Head Office)
871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
E: [email protected]; T:+91-265-6131000
Delhi / NCR
Spaze IT Park, Unit No. 1124, IIth Floor, Tower B3, Sector 49, Near Omaxe City Centre Mall, Sohna Road, Gurgaon, Haryana,
INDIA - 122002.
E: [email protected]; T: +91-124-4242430 to 436; F:+91-124-4242433
Images on front page:
1. Greenbelt near Admin building 2. Representative photo of Turbine & Generator
3. Greenbelt near Existing Power Plant 4. Representative photo of Power Transmission Line
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW
TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT QUALITY CONTROL
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 3
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW
TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT QUALITY CONTROL
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 4
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW
TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT QUALITY CONTROL
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 5
Declaration by the Head of the Accredited Consultant Organization:
I, Sangram Kadam, hereby confirm that the referred experts have prepared the EIA & EMP Report for Expansion in
Power Plant Capacity from 65 MW to 132 MW at Plot No. CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch,
Gujarat. I also confirm that Kadam shall be fully accountable for any mis-leading information mentioned in this
statement.
Signature :
Name : Sangram Kadam
Designation : Director (Consultancy Department)
Name of EIA Consultant Organization : Kadam Environmental Consultants, Vadodara, Gujarat.
NABET Certificate No. & Issue Date : 1) NABET/EIA/1619/RA 0042, Issued on 28-03-2017, Valid upto 26th
May, 2019.
2) Accreditation Certificate No. NABET/EIA/1316/RA 004 valid from 04-
10-2013 up to 18-09-2016.
3) Accreditation Extension Letter extending the validity up to 04-04-
2017 w.r.t KEC’s application dated 15-09-2016.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 6
CONTENTS
1 INTRODUCTION ....................................................................................................... 21
1.1 PURPOSE OF THE REPORT ......................................................................................... 21
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT ..................................................... 21
1.2.1 Identification of Project ....................................................................................... 21
1.2.2 Project Proponent .............................................................................................. 21
1.3 BRIEF DESCRIPTION OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY & REGION ......... 22
1.3.1 Brief Description of the Project .............................................................................. 22
1.3.2 Justification / Importance of Project to the Country and the Region .................................. 22
1.4 REGULATORY FRAMEWORK ....................................................................................... 22
1.4.1 Environmental Clearances, CC&A & Closure / Show Cause Notice for Existing Unit ................ 23
1.4.2 Statutory Clearance as Other Permissions ................................................................. 24
1.5 SCOPE OF THE STUDY .............................................................................................. 25
2 PROJECT DESCRIPTION ............................................................................................ 31
2.1 TYPE OF PROJECT ................................................................................................... 31
2.2 NEED FOR THE PROJECT ........................................................................................... 31
2.3 LOCATION OF THE PROJECT ...................................................................................... 31
2.3.1 General Location of the Site .................................................................................. 31
2.3.2 Location Map ................................................................................................... 31
2.3.3 Project Boundary ............................................................................................... 34
2.3.4 Approach to the Project Site ................................................................................. 38
2.4 SIZE OR MAGNITUDE OF OPERATION ........................................................................... 39
2.4.1 Production Capacity ........................................................................................... 39
2.4.2 Cost of the Proposed Project ................................................................................. 40
2.5 PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION ............................................ 40
2.6 TECHNOLOGY AND PROCESS DESCRIPTION ................................................................... 40
2.6.1 Existing 65 MW – Captive Power Plant ..................................................................... 40
2.6.2 Proposed 67 MW – Captive Power Plant ................................................................... 41
2.6.3 Coal Handling System ......................................................................................... 43
2.6.4 Ash Handling System .......................................................................................... 43
2.6.5 Resource Optimization/ Recycling and Reuse ............................................................. 43
2.6.6 Feasibility of Water Cooled Condensers .................................................................... 43
2.7 UTILITIES ............................................................................................................ 44
2.7.1 Power Requirement ............................................................................................ 44
2.7.2 Fuel Requirement .............................................................................................. 44
2.7.3 Water Requirement ............................................................................................ 44
2.7.4 Storage Details pertaining to the Proposed Project ...................................................... 44
2.7.5 Manpower ....................................................................................................... 45
2.8 PROPOSED INFRASTRUCTURE FOR THE PROJECT ............................................................ 45
2.8.1 Industrial Area (Processing Area) ........................................................................... 45
2.8.2 Non-Processing Area .......................................................................................... 45
2.9 AIR EMISSIONS & ONLINE MONITORING SYSTEMS ........................................................... 45
2.9.1 Point Source Emissions & Control (Action Plan to Achieve NAAQS) ................................... 45
2.9.2 Design details of Proposed APCMs .......................................................................... 46
2.9.3 Area Source Emissions & Control ............................................................................ 47
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 7
2.9.4 Line Source Emissions & Control ............................................................................ 47
2.9.5 Fugitive Emissions & its Control ............................................................................. 47
2.9.6 Online Monitoring Systems ................................................................................... 48
2.10 NOISE GENERATION ............................................................................................. 48
2.11 WATER CONSUMPTION, WASTE WATER GENERATION & DISPOSAL DETAILS ......................... 49
2.11.1 Water Consumption and Wastewater Generation ...................................................... 49
2.11.2 Wastewater Treatment & Disposal Facility .............................................................. 53
2.11.3 Wastewater Treatment & Disposal Facility – After Expansion of Power Plant ..................... 54
2.12 SOLID AND HAZARDOUS WASTE IDENTIFICATION, QUANTIFICATION, STORAGE AND DISPOSAL 55
2.13 PROJECT LAYOUT AND COMPONENTS ........................................................................ 56
2.14 MITIGATION MEASURES AT DESIGN STAGE ................................................................. 57
2.15 ASSESSMENT OF NEW AND UNTESTED TECHNOLOGY ..................................................... 57
3 DESCRIPTION OF THE ENVIRONMENT ........................................................................ 58
3.1 STUDY AREA ......................................................................................................... 58
3.2 PERIOD ............................................................................................................... 58
3.3 COMPONENTS ....................................................................................................... 58
3.4 METHODOLOGY ..................................................................................................... 58
3.4.1 Primary data Collection ....................................................................................... 58
3.4.2 Secondary Data Collection .................................................................................... 61
3.5 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENTAL COMPONENTS ......................... 61
3.5.1 Long Term Meteorology ...................................................................................... 61
3.5.2 Site Specific Meteorology ..................................................................................... 63
3.5.3 Land Use ........................................................................................................ 66
3.5.4 Ambient Air Quality ............................................................................................ 73
3.5.5 Noise ............................................................................................................. 79
3.5.6 Hydrology and Ground Water ................................................................................ 81
3.5.7 Geological Environment ....................................................................................... 92
3.5.8 Soil ............................................................................................................... 93
3.5.9 Ecology & Biodiversity ......................................................................................... 97
3.5.10 Socio-Economics ........................................................................................... 102
4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ....................... 111
4.1 INVESTIGATED ENVIRONMENTAL IMPACTS DUE TO THE PROPOSED PROJECT ....................... 111
4.2 AIR ENVIRONMENT ............................................................................................... 114
4.2.1 Emission Rates & Predicted GLCs ......................................................................... 116
4.2.2 Incremental Traffic .......................................................................................... 120
4.3 NOISE ENVIRONMENT ........................................................................................... 123
4.4 WATER ENVIRONMENT .......................................................................................... 130
4.4.1 Mitigation Measures for Impacts on Surface Water .................................................... 130
4.5 LAND ENVIRONMENT ............................................................................................. 132
4.5.1 Land Acquisition leading to change in Land Use / Cover .............................................. 132
4.5.2 Site Preparation .............................................................................................. 132
4.5.3 Green Belt Development .................................................................................... 132
4.5.4 Mitigation Measures for Impact on Land Use / Land Cover ........................................... 132
4.6 ECOLOGY & BIODIVERSITY ..................................................................................... 134
4.6.1 Ecological Impact Assessment Methodology ............................................................ 134
4.7 SOCIO-ECONOMIC ENVIRONMENT ............................................................................ 136
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 8
4.7.1 Occupational Health and Risk to Surrounding Communities .......................................... 136
4.7.2 General Safety Measures ................................................................................... 138
4.7.3 Mitigation Measures ......................................................................................... 138
5 ANALYSIS OF ALTERNATIVES ................................................................................... 139
5.1 SITE SELECTION .................................................................................................. 139
5.2 EXISTING SITE .................................................................................................... 139
6 ENVIRONMENTAL MONITORING PROGRAM ................................................................ 140
6.1 AIR ENVIRONMENT ............................................................................................... 140
6.2 NOISE ENVIRONMENT ........................................................................................... 140
6.3 WATER ENVIRONMENT .......................................................................................... 140
6.4 LAND ENVIRONMENT ............................................................................................. 140
6.5 ECOLOGY & BIODIVERSITY ..................................................................................... 140
6.6 ENVIRONMENTAL MONITORING AND MANAGEMENT COST ............................................... 147
6.7 SOCIO-ECONOMIC ENVIRONMENT (CSR/ESC ACTIVITIES) ................................................ 148
7 ADDITIONAL STUDIES ............................................................................................. 149
7.1 PUBLIC CONSULTATION ......................................................................................... 149
7.2 RISK ASSESSMENT ................................................................................................ 149
7.2.1 Consequence Analysis ....................................................................................... 149
7.2.2 Methodology of Risk Assessment .......................................................................... 149
7.2.3 Hazard Identification ........................................................................................ 149
7.2.4 Disaster Management Plan (Overall Complex including Power Plant) ............................... 151
7.2.5 Traffic Risk Assessment ..................................................................................... 170
7.2.6 Training Rehearsal and Records ........................................................................... 173
8 PROJECT BENEFITS ................................................................................................. 175
8.1 PHYSICAL INFRASTRUCTURE ................................................................................... 175
8.2 SOCIAL INFRASTRUCTURE ...................................................................................... 175
8.3 EMPLOYMENT POTENTIAL ....................................................................................... 175
8.4 OTHER TANGIBLE BENEFITS .................................................................................... 175
9 ENVIRONMENTAL COST BENEFIT ANALYSIS ............................................................... 176
10 ENVIRONMENTAL MANAGEMENT PLAN ................................................................... 177
10.1 INTRODUCTION ................................................................................................ 177
10.2 PURPOSE OF EMP ............................................................................................... 177
10.3 ENVIRONMENT MANAGEMENT PLAN ........................................................................ 177
10.3.1 Air Environment ........................................................................................... 178
10.3.2 Noise Environment ........................................................................................ 179
10.3.3 Water Environment ....................................................................................... 179
10.3.4 Solid and Hazardous Waste Management ............................................................. 180
10.3.5 Soil Environment .......................................................................................... 180
10.3.6 Ecology and Biodiversity Environment ................................................................. 180
10.3.7 Concept of Waste Minimization, Recycle, Reuse / Recovery ....................................... 184
10.3.8 Environmental Management Cell ....................................................................... 185
10.3.9 Reporting mechanism of Non-Compliance / Violations of Environmental Norms ............... 186
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 9
11 SUMMARY & CONCLUSION .................................................................................... 187
11.1 PROJECT DESCRIPTION ....................................................................................... 187
11.1.1 Company and Project Proponent ....................................................................... 187
11.1.2 Proposed Project .......................................................................................... 187
11.1.3 Location of the Project ................................................................................... 188
11.1.4 Project Cost ................................................................................................ 188
11.1.5 Raw Materials and Source ............................................................................... 188
11.1.6 Utilities ...................................................................................................... 188
11.1.7 Process ...................................................................................................... 188
11.1.8 Waste Water ............................................................................................... 189
11.1.9 Air Emissions ............................................................................................... 189
11.1.10 Hazardous and Other Solid Wastes ..................................................................... 189
11.2 DESCRIPTION OF THE ENVIRONMENT ..................................................................... 189
11.2.1 Study Period and Area .................................................................................... 189
11.2.2 Land use and Land cover ................................................................................ 189
11.2.3 Meteorology ................................................................................................ 189
11.2.4 Ambient Air Quality ....................................................................................... 190
11.2.5 Existing Stack Emissions ................................................................................. 191
11.2.6 Traffic Survey .............................................................................................. 191
11.2.7 Noise ........................................................................................................ 191
11.2.8 Surface Water and Ground Water Quality ............................................................. 192
11.2.9 Soil ........................................................................................................... 192
11.2.10 Biological Environment ................................................................................... 197
11.2.11 Socio-Economic Environment ............................................................................ 197
11.3 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ............................ 198
11.3.1 Air Environment ........................................................................................... 198
11.3.2 Traffic ....................................................................................................... 198
11.3.3 Noise Environment ........................................................................................ 198
11.3.4 Water Environment ....................................................................................... 199
11.3.5 Biological Environment ................................................................................... 199
11.3.6 Land Environment ......................................................................................... 199
11.3.7 Socio-Economic Environment ............................................................................ 199
11.4 ENVIRONMENTAL MONITORING PROGRAMME ............................................................ 200
11.4.1 Environmental Monitoring, Management Cost ........................................................ 200
11.5 ADDITIONAL STUDIES ......................................................................................... 200
11.5.1 Risk Assessment ........................................................................................... 200
11.6 PROJECT BENEFITS ............................................................................................ 201
11.7 ENVIRONMENT MANAGEMENT PLAN ........................................................................ 201
11.8 CONCLUSION .................................................................................................... 201
12 DISCLOSURE OF CONSULTANTS ............................................................................. 202
12.1 BRIEF RESUME AND NATURE OF CONSULTANCY (KADAM) .............................................. 202
12.2 EIA TEAM MEMBERS ........................................................................................... 203
13 STATUS OF COMPLIANCE OF EXISTING EC CONDITIONS ........................................... 205
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 10
LIST OF ANNEXURES
Annexure 1: IMS Certifications ....................................................................................................................... 219
Annexure 2: Integrated Management System Policy – MFL .............................................................................. 221
Annexure 3: Land Possession & Transfer Letters ............................................................................................. 222
Annexure 4: Application for ToR to SEAC, Gandhinagar ................................................................................... 226
Annexure 5: Terms of Reference (ToR) from SEAC, Gujarat received on 30.11.2017 ......................................... 227
Annexure 6: Copy of EC received on 9th August, 2007 ..................................................................................... 233
Annexure 7: Copy of Transfer EC dated 9th September, 2008 ........................................................................... 239
Annexure 8: Copy of EC Received on 12th September, 2012 ............................................................................. 241
Annexure 9: Copy of CCA dated 25.07.2014 ................................................................................................... 248
Annexure 10: Copy of Amended CCA dated 17.04.2015 ................................................................................... 257
Annexure 11: Copy of Amended CCA dated 24.06.2016 ................................................................................... 259
Annexure 12: Copy of NOC for Hydrogen Peroxide dated 01.05.2017 ............................................................... 261
Annexure 13: Copy of NOC for Name Change dated 23.01.2008 ...................................................................... 264
Annexure 14: GIDC Letter for Plot Transfer .................................................................................................... 265
Annexure 15: Show Cause / Closure Notice and Response from MFL to GPCB ................................................... 267
Annexure 16: Compliance of Corporate Responsibility for Environmental Protection (CREP) ................................ 305
Annexure 17: Fire Hydrant Network ............................................................................................................... 307
Annexure 18: Assurance Letter from GIDC for Supply of Additional Water......................................................... 308
Annexure 19: Assurance Letter from GIDC for Discharge of Additional Effluent ................................................. 309
Annexure 20: Analysis Results/Quality of Treated Effluents taken by GPCB ....................................................... 310
Annexure 21: Coal Analysis Report................................................................................................................. 312
Annexure 22: Willingness Letter for Coal Supply from Adani ............................................................................ 313
Annexure 23: Online Monitoring Data of MFL as linked with GPCB & CPCB Servers ............................................ 314
Annexure 24: Copy of Acceptance Letter from M/s BEIL for Hazardous Waste ................................................... 319
Annexure 25: Contract for Fly Ash Utilization .................................................................................................. 321
Annexure 26: Long Term (IMD) Meteorological Data for Broach (Bharuch) District ............................................ 322
Annexure 27: National Ambient Air Quality Standards ..................................................................................... 324
Annexure 28: Work Place Monitoring Reports ................................................................................................. 326
Annexure 29: Land Use/Cover Classification ................................................................................................... 335
Annexure 30: Ecology and Biodiversity Assessment ......................................................................................... 340
Annexure 31: Impact Assessment Methodology .............................................................................................. 347
Annexure 32: Detailed Results of Ambient Air Quality Monitoring ..................................................................... 356
Annexure 33: Air Dispersion Modeling Results and Isopleths ............................................................................ 363
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 11
Annexure 34: Air Dispersion Details considering Partial & Complete Failure of ESP ............................................ 372
Annexure 35: Detailed Traffic Survey Sheets .................................................................................................. 376
Annexure 36: Methodology of Risk Assessment and Hazard Identification ......................................................... 386
Annexure 37: Medical Examination Summery Report - 2016 ............................................................................ 391
Annexure 38: Certified Compliance Report by RO, MOEF&CC for Previous ECs .................................................. 393
Annexure 39: NABET Certificates & Letters – Kadam Environmental Consultants ............................................... 410
Annexure 40: KEC Laboratory Certificates ....................................................................................................... 413
Annexure 41: Undertaking for Not Constructing Ash Pond for Proposed Power Plant .......................................... 419
Annexure 42: Undertaking by MFL ................................................................................................................. 420
Annexure 43: Undertaking by Kadam for TOR Compliance ............................................................................... 421
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 12
LIST OF TABLES
Table 1-1: Details of IMS Certifications ............................................................................................................. 21
Table 1-2: List of Directors and their Designations ............................................................................................ 22
Table 1-3: Brief Description of the Project ........................................................................................................ 22
Table 1-4: Details of Notice/Directions issued to MFL during Last Three Years..................................................... 23
Table 1-5: Statutory Clearances / Permissions & Applicable Legislations / Notifications / Acts / Rules .................... 24
Table 1-6: Compliance with the Terms of Reference .......................................................................................... 25
Table 2-1: Co-ordinates of Project Boundary..................................................................................................... 34
Table 2-2: Area Breakup – Entire Site .............................................................................................................. 34
Table 2-3: Area Breakup – Proposed Power Plant .............................................................................................. 35
Table 2-4: Details of the Site Connectivity ........................................................................................................ 38
Table 2-5: List of Existing Products .................................................................................................................. 39
Table 2-6: Existing and Proposed Capacities – Power Plant ................................................................................ 39
Table 2-7: Cost Break-up ................................................................................................................................ 40
Table 2-8: Project Implementation Schedule..................................................................................................... 40
Table 2-9: Details of Power Requirement ......................................................................................................... 44
Table 2-10: Details of Main Raw Material Quantity and Means of Storage ........................................................... 44
Table 2-11: Water Requirement (Existing Units & Proposed Power Plant) ........................................................... 44
Table 2-12: Details of Stacks and APCM – Existing ............................................................................................ 46
Table 2-13: Details of Stacks and APCM – Proposed .......................................................................................... 46
Table 2-14: Technical Details of Proposed ESP .................................................................................................. 46
Table 2-15: Details of Existing & Proposed Online Monitoring Systems ............................................................... 48
Table 2-16: Details of Water Consumption from Existing and Proposed Unit ........................................................ 49
Table 2-17: Details of Wastewater Generation from Existing and Proposed Unit .................................................. 49
Table 2-18: Design Inlet and Outlet Characteristics of Existing ETP .................................................................... 53
Table 2-19: List of Existing ETP units with Capacity ........................................................................................... 53
Table 2-20: Adequacy of Existing ETP .............................................................................................................. 53
Table 2-21: Details of Existing and Proposed Hazardous & Non Hazardous Wastes .............................................. 55
Table 2-22: Identification of Other Waste ......................................................................................................... 55
Table 2-23: Operational Controls at Design Stage ............................................................................................. 57
Table 3-1: Predominant/Mean Wind Direction IMD – Bharuch ............................................................................ 61
Table 3-2: Average Meteorological Condition at IMD Bharuch ............................................................................ 62
Table 3-3: Monitoring Methodology of Meteorological Data ................................................................................ 63
Table 3-4: Mean Site Specific Meteorological Data – Winter Season .................................................................... 64
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 13
Table 3-5: Collation of Primary Meteorological data with Secondary Data (IMD) .................................................. 66
Table 3-6: GPS readings within Study Area ....................................................................................................... 67
Table 3-7: Area Statistics for Land Use / Land Cover Categories in the Study Area .............................................. 68
Table 3-8: List of Major Industries ................................................................................................................... 69
Table 3-9: Important Feature within the Study Area .......................................................................................... 71
Table 3-10: Methodology of Ambient Air Monitoring .......................................................................................... 73
Table 3-11: Ambient Air Quality Monitoring Location Details .............................................................................. 73
Table 3-12: Ambient Air Monitoring Results ...................................................................................................... 74
Table 3-13: Flue Gas Stack Monitoring Results .................................................................................................. 76
Table 3-14: Process Vents/Stacks Monitoring Results ........................................................................................ 76
Table 3-15: Results – Work Place Monitoring .................................................................................................... 78
Table 3-16: Monitoring Methodology ................................................................................................................ 79
Table 3-17: Standards for Ambient Noise Level ................................................................................................. 79
Table 3-18: Noise Level Monitoring Locations ................................................................................................... 79
Table 3-19: Noise Level Monitoring Results ....................................................................................................... 80
Table 3-20: Analysis Methodology of Ground Water and Surface Water .............................................................. 81
Table 3-21: Surface Water Sampling Location (Pond and River) ......................................................................... 83
Table 3-22: Surface Water Analysis Results ...................................................................................................... 85
Table 3-23: Classification of Water ................................................................................................................... 85
Table 3-24: Analysis Result of River (Estuary) Water Samples ............................................................................ 86
Table 3-25: Ground Water Sampling Locations ................................................................................................. 87
Table 3-26: Analysis Results of Groundwater Samples ....................................................................................... 89
Table 3-27: Regional Geology .......................................................................................................................... 92
Table 3-28: Analysis Methodology of Soil .......................................................................................................... 94
Table 3-29: Soil Sampling Locations ................................................................................................................. 94
Table 3-30: Soil Analysis Results ...................................................................................................................... 96
Table 3-31: Details of Rivers and Ponds of Buffer Zone ..................................................................................... 98
Table 3-32: Details of Nearest Creeks in the Buffer Zone ................................................................................... 98
Table 3-33: Status of Phytoplankton in Various villages of the Study Area ......................................................... 101
Table 3-34: Status of Zooplankton in Various villages of the Study Area ........................................................... 101
Table 3-35: Demographic Status of the Study Area ......................................................................................... 103
Table 3-36: Sex Ratio of the Study Area ......................................................................................................... 104
Table 3-37: Stratification (Age Wise) of Vadadala Village ................................................................................. 104
Table 3-38: Details of SC/ST Population in the Study Area ............................................................................... 105
Table 3-39: Educational Facilities in the Study Area ......................................................................................... 105
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 14
Table 3-40: Literacy rate within the study area ............................................................................................... 105
Table 3-41: Literacy level of Vadadla Village ................................................................................................... 106
Table 3-42: Health Facilities in the Study Area ................................................................................................ 106
Table 3-43: Drinking water facilities within the Study Area............................................................................... 107
Table 3-44: Housing Condition in the Surveyed Village .................................................................................... 107
Table 3-45: Toilet Facility in the Surveyed Village............................................................................................ 107
Table 3-46: Occupational status of the Study Area .......................................................................................... 108
Table 3-47: Type of Livelihood Activity in the Core Impact area (0 – 3 Kms) ..................................................... 109
Table 3-48: Number of villages having Transportation Facilities........................................................................ 109
Table 4-1: Aspect-Impact Identification from Proposed Project ........................................................................ 112
Table 4-2: Impact Scoring and Mitigation Measures for Air Environment ........................................................... 115
Table 4-3: Assumptions of Sulphur & Ash Content in the Fuel (Worst Case) ...................................................... 116
Table 4-4: Emission Estimate from Flue Gas Stacks (As per Fuel Analysis) ........................................................ 117
Table 4-5: Emission Estimate from Flue Gas Stacks (As per the Norms) ............................................................ 117
Table 4-6: Emission Estimate from Volume Source (Coal Storage Yard) ............................................................ 117
Table 4-7: Summary of Air Dispersion Modeling for Proposed Stacks ................................................................ 119
Table 4-8: Incremental GLC from Proposed Project ......................................................................................... 119
Table 4-9: Incremental Hourly Average Traffic on Bharuch to Dahej ................................................................. 121
Table 4-10: Incremental Hourly Average Traffic on Dahej to Bharuch ............................................................... 121
Table 4-11: Impact Scoring and Mitigation Measures for Noise Environment ..................................................... 124
Table 4-12: Sources of Noise with their Sound Pressure Levels ........................................................................ 125
Table 4-13: Noise level at receptor locations ................................................................................................... 128
Table 4-14: Mitigation Measures .................................................................................................................... 129
Table 4-15: Impact Scoring and Mitigation Measures for Water Environment .................................................... 131
Table 4-16: Impact Scoring and Mitigation Measures for Solid & Haz. Waste and Land Environment ................... 133
Table 4-17: Impact Scoring and Mitigation Measures for Ecology & Biodiversity Environment ............................. 135
Table 4-18: Issues Raised by the Respondents of the Core Zone ...................................................................... 136
Table 4-19: Impact Scoring and Mitigation Measures for OH, Community Health and Safety .............................. 137
Table 6-1: Budgetary Environment Monitoring Plan for Air Environment............................................................ 141
Table 6-2: Traffic Management Plan .............................................................................................................. 142
Table 6-3: Budgetary Environment Monitoring Plan for Noise Environment........................................................ 143
Table 6-4: Budgetary Environment Monitoring Plan for Water Environment ....................................................... 144
Table 6-5: Budgetary Environment Monitoring Plan for Solid & Hazardous Waste Management and Land
Environment ................................................................................................................................................ 145
Table 6-6: Budgetary Environment Monitoring Plan for Ecology and Biodiversity ................................................ 146
Table 6-7: Environmental Monitoring and Management Cost ............................................................................ 147
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 15
Table 6-8: Summary of Post EC Environmental Monitoring Plan........................................................................ 147
Table 6-9: Enterprise Social Commitment (Initial 5 Years) ............................................................................... 148
Table 7-1: Properties of Hazardous Material to be Handled .............................................................................. 150
Table 7-2: Safety Equipment Details .............................................................................................................. 152
Table 7-3: Details of Fire Extinguisher ............................................................................................................ 154
Table 7-4: Details of Key Personnel of the Emergency Team and their Duties ................................................... 154
Table 7-5: Do’s and Don’ts of Various Activities / Emergency ........................................................................... 160
Table 7-6: Siren Codes during Emergency Situation ........................................................................................ 162
Table 10-1: Environmental Management Plan ................................................................................................. 177
Table 10-2: Environmental Management Plan ................................................................................................. 178
Table 10-3: Area Breakup for Rainwater Calculations ...................................................................................... 179
Table 10-4 Rainwater Available Per Annum ..................................................................................................... 179
Table 10-5: Soil Environment ........................................................................................................................ 180
Table 10-6: Existing Floral species reported from Green Belt Area .................................................................... 180
Table 10-7: Plant Species Suggested for Greenbelt and Landscaping at Various Locations .................................. 182
Table 10-8: Budget for Proposed Greenbelt Development within Project Site .................................................... 182
Table 10-9: List of plant species for plantation in LIZ Area ............................................................................... 183
Table 10-10: Budget for Additional Greenbelt / Habitat Improvement Programme ............................................. 184
Table 11-1: List of Existing Products .............................................................................................................. 187
Table 11-2: Existing and Proposed Capacities – Power Plant ............................................................................ 188
Table 11-3: List of Utilities............................................................................................................................. 188
Table 11-4: Ambient Air Quality Data ............................................................................................................. 190
Table 11-5: Noise Monitoring Results ............................................................................................................. 191
Table 11-6: Surface Water Quality in Study Area - Summary............................................................................ 192
Table 11-7: Ground Water Quality in Study Area - Summary ............................................................................ 192
Table 11-8: Surface Water (River) Analysis Results ......................................................................................... 193
Table 11-9: Analysis Result of River (Estuary) Water Samples .......................................................................... 194
Table 11-10: Analysis Results of Groundwater Samples ................................................................................... 194
Table 11-11: Soil Analysis Results .................................................................................................................. 196
Table 11-12: Summary of Environment Monitoring Plan................................................................................... 200
Table 12-1: EIA Team Member ...................................................................................................................... 203
Table 13-1: Summary Not complied, Partly Complied, Agreed to Comply EC Conditions ..................................... 205
Table 13-2: Action Plan for Complying Not-Complied Conditions of Previous EC ................................................. 206
Table 13-3: Action Plan for Complying Partially-Complied Conditions of Previous EC .......................................... 209
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 16
LIST OF FIGURES
Figure 2-1: Pie Chart – Area Breakup of Proposed Power Plant .......................................................................... 35
Figure 2-2: Process Flow Diagram – Proposed Power Plant ................................................................................ 42
Figure 2-3: Typical Drawing showing Operation of Power Plant .......................................................................... 42
Figure 2-4: Water Balance Diagram – Existing Unit ........................................................................................... 50
Figure 2-5: Water Balance Diagram – Proposed Power Plant Unit ....................................................................... 51
Figure 2-6: Water Balance Diagram – Combined (After Expansion) ..................................................................... 52
Figure 2-7: Process Block Diagram of Existing ETP ............................................................................................ 54
Figure 2-8: Process Block Diagram of Proposed Wastewater Treatment .............................................................. 54
Figure 3-1: Windrose Diagram for Winter Season, 2016-17 ................................................................................ 65
Figure 3-2: Pie Chart – Landuse of Study Area .................................................................................................. 69
Figure 4-1: Data Flow in AERMOD Modeling System ........................................................................................ 118
Figure 4-2: Isopleth of Day Time ................................................................................................................... 126
Figure 4-3: Isopleth of Night Time ................................................................................................................. 127
Figure 7-1: Emergency Control Organization Chart .......................................................................................... 151
Figure 10-1: Hierarchy of Environment Management Cell ................................................................................. 185
Figure 10-2: Reporting Mechanism................................................................................................................. 186
LIST OF MAPS
Map 2-1: General Location Map of Project Site .................................................................................................. 32
Map 2-2: Project Site on Toposheet ................................................................................................................. 33
Map 2-3: Project Boundary Map ....................................................................................................................... 36
Map 2-4: Project Site Layout Map .................................................................................................................... 37
Map 3-1: Study Area Map ................................................................................................................................ 59
Map 3-2: Sampling Location Map ..................................................................................................................... 60
Map 3-3: Land Use / Land Cover Map .............................................................................................................. 72
Map 3-4: Map showing Noise Monitoring Locations ........................................................................................... 80
LIST OF PHOTOGRAPHS
Photograph 2-1: Photographs showing Existing and Proposed Site ..................................................................... 38
Photograph 3-1: Photographs of Meteorological Station Setup ........................................................................... 63
Photograph 3-2: Various Land Cover of Study Area ........................................................................................... 67
Photograph 3-3: Photographs of AAQ Sampling Stations.................................................................................... 74
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 17
Photograph 3-4: Noise Level Monitoring Locations ............................................................................................ 80
Photograph 3-5: Surface Water Sampling Locations .......................................................................................... 83
Photograph 3-6: Groundwater Sampling Locations ............................................................................................ 88
Photograph 3-7: Soil Sampling Locations .......................................................................................................... 95
Photograph 3-8: Floral species at Core Zone/Project Site ................................................................................... 99
Photograph 3-9: Housing Condition and Sanitary Toilet Facility ........................................................................ 108
Photograph 3-10: Type of Livelihood Activity .................................................................................................. 109
Photograph 10-1: Existing Greenbelt and Landscaping Within Project Premises ................................................. 181
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 18
ABBREVIATIONS AND ACRONYMS
APHA : American Public Health Association
AAQM : Ambient Air Quality Monitoring
AFAU : Aquatic Fauna
AFLO : Aquatic Flora
AMS : American Meteorological Society
APCM : Air Pollution Control Measures
BDL : Below Detectable Level
BMCR : Boiler Maximum Continuous Rating
BOD : Biochemical Oxygen Demand
BIS : Bureau of Indian Standards
CAGR : Compound Annual Growth Rate
CARE : Credit Analysis and Research Ltd.
CCA : Consolidated Consent and Authorization
COD : Chemical Oxygen Demand
CEC : Cation Exchange Capacity
CETP : Central Effluent Treatment Plant
CFBC : Circulating Fluidized Bed Combustion
CMD : Cubin Meter per Day
CPCB : Central Pollution Control Board
CPP : Captive Power Plant
CPA : Critically Polluted Area
Cr. : Crore
CSR : Corporate Social Responsibility
CGWB : Central Ground Water Board
DC : Differential Count
DCS : Distributed Control System
D.G : Diesel Generator
DGH : Directorate General of Hydrocarbons
D.M : Dimeralized
DMP : Disaster Management Plan
EAC : Expert Appraisal Committee
ECC : Emergency Control Centre
EC : Environment Clearance
EC (soil) : Electrical Conductivity
ECG : Electro Cardiogram
EER : Evacuate, Escape and Rescue Plan
EHS : Environmental Health and Safety
EIA : Environmental Impact Assessment
ENVIS : Environmental Information System
EMP : Environmental Management Plan
EPRG : Emergency Response Planning Guidelines
ESP : Exchangeable Sodium Percentage
ESP : Electro Static Precipitator
ESR : Erythrocyte Sedimentation Rate
ETP : Effluent Treatment Plant
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 19
FGD : Focus Group Discussion
GCV : Gross Calorific Value
GIDC : Gujarat Industrial Development Corporation
GLC : Ground Level Concentration
GoI : Government of India
GPCB : Gujarat Pollution Control Board
GSI : Geological Survey of India
Ha : Hectare
HAZOP : Hazard and Operability Study
HDPE : High Density Polyethylene
HFO : Heavy Fuel Oil
HOD : Head of Department
HRD : Human Resource Development
HSD : High Speed Diesel
HSE : Health and Safety Executive
IAA : Impact Assessment Authority
IDLH : Immediately Dangerous to Life or Health
IMD : Indian Meteorological Department
IMS : Integrated Management System
ISCST-3 : Industrial Source Complex Short Term-3
IUCN : International Union for Conservation of Nature
IWPA 1972 : Indian Wild Life Protection Act, 1972
KCAL : Kilo Calorie
KLD : Kilo Liter per Day
Km : Kilometer
Kwh : Kilo Watt Hour
LCLo : Lethal Concentration Low
LEL : Lower Flammability Limits
LIZ : Likely Impact Zone
MCLS : Maximum Credible Loss Scenarios
MoEF&CC : Ministry of Environment and Forest and Climate Change
MEE : Multi Effect evaporator
MFL : Meghmani Finechem Limited
MFLO : Marine Flora
MFNA : Marine Fauna
MLSS : Mixed Liquor Suspended Solids
MLVSS : Mixed Liquor Volatile Suspended Solids
MoM : Minutes of Meeting
MSDS : Material Safety Data Sheet
MSIHC : Manufacture, Storage and Import of Hazardous Chemical
MSW : Municipal Solid Waste
MTPA : Metric Tonne Per Annum
MT : Metric Tonnes
MW : Mega Watt
NABET : National Accreditation Board for Education and Training
NBSS & LUP : National Bureau of Soil Survey and Land Use Planning
NMHC : Non Methanated Hydrocarbons
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 20
OSHA : Occupational Safety and Health Administration
OHS : Occupational Health and Safety
PCU : Per Car Unit
PDCR : Plan, Do, Check, Act
PEL : Permissible Exposure Limits
PP : Project Proponent
PM : Particulate Matter
PPE : Personal Protection Equipment
RA : Risk Assessment
RBC : Red Blood Cells
RCC : Reinforced Cement Concrete
RO : Reverse Osmosis
SAR : Sodium Absorption Ratio
SC : Soil Conservation
SDU : Sludge Dewatering Unit
SEAC : State Level Expert Appraisal Committee
SH : State Highway
SHW : Solid Hazardous Waste
SLF : Secured Landfill Facility
SMC : Site Main Controller
SOP’s : Standard Operating Procedures
SPL : Sound Pressure Level
SST : Secondary Settling Tank
STP : Sewage Treatment Plant
TC : Total Count
TDS : Total Dissolved Solids
TSDF : Treatment storage and disposal facility
TFLO : Terrestrial Flora
TFAU : Terrestrial Fauna
TCLo : Toxic Concentration Low
TLV : Threshold Limit Value
ToR : Terms of Reference
UFL : Upper Flammable Limits
UF : Ultra Filtration
USEPA : United States Environmental Protection Agency
VOCs : Volatile Organic Compounds
WBC : White Blood Cells
WHC : Water Holding Capacity
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 21
1 INTRODUCTION
Meghmani Finechem Limited (MFL) proposes an Expansion in its Power Plant Capacity from 65 MW to 132 MW at
Plot No. CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat.
MFL has also applied for Environment Clearance for Expansion of Existing products and new product manufacturing
from MoEF&CC having File No. J-11011/13/2014-IA II(I) from MoEF&CC. As the power plant capacity is less than
500 MW, MFL is seeking environment clearance from SEIAA, Gujarat, it being a category ‘B’ project.
1.1 PURPOSE OF THE REPORT
Purpose of the report is to identify environmental aspects, impacts arising out the activities due to operation of
Power Plant and suggesting mitigation measures. This EIA report is made as per Terms of References (ToRs) issued
by State Level Expert Appraisal Committee –Gujarat, in their Letter Ref: SEIAA/GUJ/TOR/1(d)/1258/2017 dated
30.11.2017 and seek Environmental Clearance.
This report is prepared based on ‘General Structure of EIA’ given in Appendix III and IIIA of EIA Notification, 2006
as amended till date.
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
1.2.1 Identification of Project
The proposed project falls under 1(d), Thermal Power Plant in the ‘Project or Activities’ listed within the Schedule to
the EIA Notification dated September 14th, 2006 (amended till date). This project is classified as Category “B”
project, as already mentioned.
1.2.2 Project Proponent
Proposed expansion unit is promoted by M/s. Meghmani Finechem Limited, which is managed by top management
as described in Table 1-2. Meghmani group is a leading group of India operating in a range of diversified
industries viz. Pigments, Agro Chemicals, Dyestuffs and Caustic Chlorine.
The flagship company, Meghmani Organics Limited (MOL) is a listed public limited company and is regarded as one
of the leading producers of pigments and agrochemicals in the country. The group has set up a state of the art
Caustic Chlorine Complex (CCC Complex) under Meghmani Finechem Ltd. (MFL) at Dahej in the state of Gujarat.
The group companies house a large R&D Laboratory and Technical Competence Center with facilities for testing.
The group companies are equipped with the latest instrument required for product development and work in close
conjunction with customers meeting their requirements. The other expansion is expected of existing products and
new product manufacturing. For the same, power requirement will be fulfilled from the proposed 67 MW CPP.
Certification
Integrated Management System (IMS) certification for MFL, Dahej is given in Table 1-1.
Table 1-1: Details of IMS Certifications
Systems Certification
Integrated Management System for :
Quality Management System
Environmental Management System
ISO 9001:2008
ISO 14001: 2004
The certificates for the Integrated Management System are attached as Annexure 1.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 22
About Directors of MFL
The company is headed by Chairman, Managing Director and Directors. List of their top management is tabulated in
Table 1-2.
Table 1-2: List of Directors and their Designations
S. No. Name Designation
1 Shri Maulik J. Patel Chairman & Managing Director
2 Shri Kaushal A. Soparkar Managing Director
3 Shri Ankit N. Patel Executive Director
4 Shri Karana R. Patel Executive Director
5 Shri Darshan A. Patel Executive Director
1.3 BRIEF DESCRIPTION OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY &
REGION
1.3.1 Brief Description of the Project
The brief description of the project is given in Table 1-3.
Table 1-3: Brief Description of the Project
S No. Details Description
1 Nature Expansion in Power Plant.
2 Size
Total Plot Area: 5,33,470 m2. Plot area of the proposed project consists of 3,702 m2.
Power Plant Capacity increase from 65 MW to 132 MW is proposed. Existing product details
are mentioned in Chapter 2, Section 2.4.1.
3 Location Plot No.: CH-1/ CH-2, Dahej – ll, Industrial Estate, Bharuch, Gujarat. Land possession
documents is provided in .
4 Cost of the project ~ INR 230 Crore
1.3.2 Justification / Importance of Project to the Country and the Region
The promoters are interested in setting up the project considering the following technical and economical features
of the project:
Project will generate employment and state revenue.
CSR activities will be made for upliftment of the socio economic status of nearby villages.
During the construction phase, around 250 workers will be employed. Local skilled and semi-skilled workers will
be engaged during construction phase. The positive impact includes enhanced indirect employment
opportunities for transporters of raw material and finished goods.
1.4 REGULATORY FRAMEWORK
As a part of Environmental Clearance process, MFL uploaded and submitted Form – 1 (as per the EIA Notification,
2006, as amended), along with a Pre-feasibility Report and Proposed Terms of Reference (ToRs) for carrying out
Environmental Studies, to the State Expert Appraisal Committee (SEAC), Gujarat on 25th August, 2017 vide letter
dated 24th August, 2017 as attached as Annexure 4. Based on the information contained in the documents
submitted and the ToR presentation made during the on 06th October, 2017, SEAC finalized ToRs to be
incorporated whilst conducting the Environmental Impact Assessment (EIA) & Environmental Management Plan
(EMP) studies, vide its letter: SEIAA/GUJ/TOR/1(d)/1258/2017 dated 30.11.2017 as attached as Annexure 5.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 23
1.4.1 Environmental Clearances, CC&A & Closure / Show Cause Notice for Existing Unit
Environmental Clearances from MoEF&CC / SEAC
MFL has received following Environmental Clearance from MoEF&CC, New Delhi:
EC No.: J-11011/06/2007-IA II(I) dated 09.08.2007 for manufacturing of Chlor-Alkali and other products at
GIDC Estate, Dahej, Bharuch, Gujarat by M/s Meghmani Organics Ltd.-Environmental Clearance regd. The copy
of EC is attached as Annexure 6.
EC No.: J-11011/06/2007-IA II(I) dated, 09.09.2008 for transfer of EC in the name of M/s Meghmani Finechem
Limited from M/s Meghmani Organics Limited located at GIDC. Estate, Dahej, Bharuch, Gujarat- Environmental
Clearance regd. The copy of EC is attached as Annexure 7.
EC No.: J-11011/259/2011 – IA dated 12.09.2012 for adding pesticides manufacturing unit & expansion in
power plant capacity from 45 MW to 65 MW. Copy of the same is attached as Annexure 8.
A certified copy of compliance status by RO, MoEF (Bhopal) for the existing EC conditions is attached in Annexure
38. Its action plan for not complied and partially compliance points is provided in Chapter 13.
CC&A, CTE / NOC from SPCB
MFL has received following CC&A, CTE / NOC from State Pollution Control Board, Gujarat:
CC&A Order No. AWH-62734, dated 25.07.2014 issued vide Letter No. GPCB/BRCH-B-CCA-1233(3)/ID
32979/219906 with validity upto 18/02/2019. The copy of CC&A is attached as Annexure 9.
CC&A Amendment, dated 17.04.2015 issued vide Letter No. GPCB/BRCH-B-CCA-1233(4)/ID 32979/310984. The
copy of the same is attached as Annexure 10.
CC&A Amendment, dated 24.06.2016 issued vide Letter No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/360636.
The copy of the same is attached as Annexure 11.
CTE Amendment, dated 01.05.2017 issued vide Letter No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/411050. The
copy of the same is attached as Annexure 12.
NOC for the name change, dated 23.01.2008 issued vide Letter No. GPCB/BRCH/NOC-3426/2029. The copy of
NOC is attached as Annexure 13.
CTE for manufacturing of Hydrogen Peroxide 1,200 MT/Month vide Letter No. GPCB/BRCH-B-CCA-1233(4)/ID-
32979/411050, dated 01.05.2017 issued by GPCB.
Litigation Pending / Show Cause / Closure Notice from GPCB & Response
There is no litigation pending against the project and / or any direction / order passed by any Court of Law against
the project.
Details of the notice/show cause notice and response in the last three years is provided in Annexure 15 and
summarized in Table 1-4.
Table 1-4: Details of Notice/Directions issued to MFL during Last Three Years
S.
No.
Notice/SCN
issued
Date of
issue
Points raised by
GPCB Reply submitted by MFL and Action taken
1
Notice under
section 33A of
Water Act
18-11-2017
Alkaline water in
storm water
drainage
Additional outlet
noticed near
reservoir
Quality of waste
water not meeting
with norms
We have not discharge alkaline water which is found in
outside storm water line.
We have repaired minor leakages form storm water
drainage and only treated effluent water is being
discharged in GIDC drain.
At present we blocked our storm water drainage by
cement concrete to avoid leakages/spillage of water. We
assure that we will take care of to avoid any kind of
industrial effluent discharged in to storm water drainage
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 24
S.
No.
Notice/SCN
issued
Date of
issue
Points raised by
GPCB Reply submitted by MFL and Action taken
and GIDC open surface drainage We have already lifted
water from storm water drainage and informed GPCB on
dated 11.10.2017. Discharge of waste water in GIDC
storm water drain has never happened by MFL.
2
Notice under
section air 31 A
of Act 981
16-03-2017
Poor Coal handling
Poor housekeeping
Opacity meter not
working
Contaminated
water in storm
water drainage
We have shifted entire quantity of coal in existing coal
yard having water sprinkling system and wind braking
wall for control of dusting.
We have taken all necessary actions for improvement of
housekeeping within premises.
We have repaired opacity meter and it is working
properly.
We have lifted water from storm water drainage into ETP
and treated before disposing to GIDC Drain.
3 Show Cause 19-04-2016
New Cooling
Tower installed
Chlorine Gas
smells sensed.
The old cooling tower is not working properly, so we have
construct new cooling tower against old one.
We have provided hood to control chlorine smell.
4 Show Cause 10-03-2016
Analysis report of
the sample
collected during
visit is not meeting
with norms of the
Board.
The high value of COD & BOD may be reported due to
chloride content that may interfere with COD & BOD
result. We are giving sufficient settling time to settle
down suspended solid in collection pit as well as in
holding pit to maintain standard norms of board.
We are manufacturing inorganic chemicals (Chlor-Alkali)
and not using any organic solvent, so no possibilities of
high value of COD & BOD.
1.4.2 Statutory Clearance as Other Permissions
MFL shall obtain required statutory permission and clearances from concerned authorities. Details of permits and
clearance as applicable to this project are provided in Table 1-5.
Table 1-5: Statutory Clearances / Permissions & Applicable Legislations / Notifications / Acts / Rules
S. No. Legal Instruments
1 Factory License
2 The Factories Act, 1948
3 Gujarat State Factories Rules, 1963/1995
4 The Water (Prevention and Control of Pollution) Act, 1974 and Rules 1975 as amended to date.
5 The Water (Prevention and Control of Pollution) Cess Act, 1977, and Rules, 1978, as amended to date.
6 The Air (Prevention and Control of Pollution) Act, 1981 and Rules, 1982 as amended to date
7 The Manufacture, Storage and Import of Hazardous Chemical rules, 1989, as amended to date
8 The Hazardous Waste (Management, Handling and Trans boundary Movement) Rules, 2016 as amended to date
9 Guidelines and Check-list for evaluation of MSW Landfills proposals with Information on existing landfills, 2008
10 The Environment (Protection) Act, 1986 and Rules,1986, as amended to date
11 Chemical accidents (Emergency Planning, preparedness and response) Rules, 1996
12 The Motor Vehicles Act, 1988 & The Central Motor Vehicle Rules, 1989
13 The Public Liability Insurance Act and Rules, 1991, as amended to date
14 The Petroleum Act, 1934 and Rules, 2002
15 The Explosive Act, 1884 and Rules, 1983, as amended to date
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 25
S. No. Legal Instruments
16 The Gas Cylinders Rules, 2004
17 The Static and Mobile Pressure Vessels (Unfired) Rules, 1981
18 The Noise Pollution (Regulation and Control) Rules, 2000 as amended to date
19 E-waste (Management and Handling) Rules, 2011 as amended to date
20 Electricity Rule, 2005
21 Consents from GPCB
22 Environmental Impact Assessment Notification, 2006 as amended to date
1.5 SCOPE OF THE STUDY
As per the ToR letter, scope of work for this EIA studies and preparation of detailed EIA/EMP report including
collection of baseline data with respect to major environmental components, viz. Air, Noise, Water, Land, Biological
and socio-economic components for one season, not older than three years.
This EIA report complies with Terms of Reference given by the State Expert Appraisal Committee. Summarized
details of the same are tabulated in Table 1-6.
Table 1-6: Compliance with the Terms of Reference
S. No. ToR Compliance in Report
1
Executive summary of the project – giving a prima facie idea of the
objectives of the proposal, use of resources, justification, etc. In
addition, it should provide a compilation of EIA report including EMP
and the post-project monitoring plan in brief.
Executive summary: Chapter 11, Pg. 187.
Justification of the project: Chapter 1,
Section 1.3.2, Pg. 22.
2 Present land use pattern of the study area shall be given based on
satellite imagery.
The land use / land cover map of 10 km
radius: Chapter 3, Section 3.5.3, Map
3-3, Pg. 72.
Toposheet Map: Chapter 2, Section 2.3,
Map 2-2, Pg. 33.
Site Location Map: Chapter 2, Section
2.3.2 , Map 2-1, Pg. 32.
High-resolution satellite image: Chapter 3,
Section 3.4.1, Map 3-1, Pg. 59.
3 Geological features and geo-hydrological status of the study area.
Geological features and geo-hydrological
status of the study area is provided in
Chapter 3, Section 3.5.7, Pg. 92.
4
Demarcation of proposed activities in layout of the existing premises.
Provision of continuous unobstructed peripheral open path within the
project area for unobstructed easy movement of the emergency
vehicle/fire tenders without reversing back. Mark the same in the
plant layout.
Project site layout plan showing proposed
activities in existing premises: Chapter 2,
Section 2.3.3, Map 2-4, Pg. 37.
Coordinates of plant site: Chapter 2,
Section 2.3.2, Table 2-1, Pg. 34.
5 Explore feasibilities to go for air cooled condensers instead of water
cooled condensers in order to reduce the raw water requirement.
Feasibilities for air cooled condensers instead
of water cooled condensers in order to
reduce the raw water requirement were not
and found that air cooled condensers are not
feasible for the proposed power plant
project. Air cooled condensers will be used
against water cool condensers. Reasons for
the same is provided in Chapter 2, Section
2.6.6, Pg. 43.
6 Technical details of the proposed power plant along with details of
strategy for implementation reuse/recycle and other cleaner
Technical details of the proposed power
plant: Chapter 2, Section 2.6, Pg. 40.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 26
S. No. ToR Compliance in Report
production options for reduction of wastes. Generation of waste gases
and utilization of waste heat have to be set out.
Reuse/recycle: Chapter 2, Section 2.6.5,
Pg. 43.
Generation of waste gases: Chapter 2,
Section 2.9.1, Pg. 45.
Utilization of waste heat will be done by air
preheater & economizer: Chapter 2,
Section 2.6.1, Pg. 43.
7 Details of the ETP units including its capacity, size of each unit,
retention time and other technical parameters.
ETP Units: Chapter 2, Section 2.11.2,
Table 2-19, Pg. 53.
8 Work out the maximum reuse plan for treated wastewater within the
premises instead of discharging into the GIDC drainage.
Treated waste water generated from the
proposed 67 MW unit will be fully reused for
dust suppression at Ash & Coal handling
unit. Thus, zero liquid discharge will be
achieved for the proposed 67 MW power
plant.
Methods adopted for water conservation by
rain water harvesting: Chapter 10, Section
10.3.3, Pg. 179.
9
Application wise break-up of treated effluent quantity to be recycled /
reused in various applications like sprinkling on roads, coal storage
yard and greenbelt development etc.
Water Consumption & Waste water
generation breakup : Chapter 2, Section
2.11.1, Pg. 49.
10
Assessment of source of the water supply with adequacy of the same
to meet with the requirements for the project. Copy of letter of
permission obtained from the concerned authority for supply of
additional raw water for the proposed activities.
Water Supply: Dahej GIDC
Permission letter by GIDC: Annexure 18,
Pg. 308.
11
Detailed water balance (including reuse-recycle, if any) along with
qualitative and quantitative analysis of each waste stream to be
generated from all sources including Boilers, Cooling Towers, D.M.
Plant etc. Details of methods to be adopted for the water
conservation.
Water balance diagrams: Chapter 2,
Section 2.11, Pg. 49.
Water Conservation Measures: Chapter 10,
Section 10.3.3, Pg. 179.
12
Details of the treatment facilities proposed for the effluent to be
generated from the power plant including existing project. Details of
the ETP units including its capacity (KL/day), size of each unit,
retention time and other technical parameters and details about up-
gradation in the existing ETP (if any proposed) to take care of the
waste water to be generated from the proposed activities.
Treatment facilities from proposed power
plant: Chapter 2, Section 2.11.2, Pg. 54.
Details of the ETP units: Chapter 2,
Section 2.11.2, Pg. 53.
13
Characteristics of untreated and treated waste water. A detailed
effluent treatability study vis-à-vis the adequacy and efficacy of the
treatment facilities proposed for the wastewater to be generated
along with adequacy and efficacy report. The characteristics on which
treatability is based shall also be stated.
Characteristics of untreated and treated
waste water: Chapter 2, Section 2.11.2,
Table 2-18, Pg. 53.
Adequacy of ETP: Chapter 2, Section
2.11.2, Pg. 53.
14
Site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall shall be
provided.
Site specific micro-meteorological data:
Chapter 3, Section 3.5.2, Pg. 63.
15
Anticipated environmental impacts due to the proposed
project/production may be evaluated for significance and based on
corresponding likely impacts VECs (valued Environmental
Components) may be identified. Baseline studies may be conducted
within the study area of 10 km for all the concerned/identified VECs
and likely impacts, likely impacts have to be assessed for their
magnitude in order to identify mitigation measures.
Anticipated environmental impacts is covered
in Chapter 4, Pg. 111.
Baseline studies for the period of winter
2016-17, was carried out and represented in
Chapter 3, Pg. 58.
16 One complete season base line ambient air quantity data (except Ambient air quality monitoring details:
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 27
S. No. ToR Compliance in Report
monsoon) to be given along with the dates of monitoring. The
parameters to be covered shall be in accordance with the revised
National Ambient Air Quality Standards as well as project specific
parameters. Locations of the monitoring stations should be so decided
so as to take into consideration the pre-dominant downwind direction,
population zone and sensitive receptors. There should be at least one
monitoring station in the upwind direction. There should be at least
one monitoring station in the pre dominant downwind direction at a
location where maximum ground level concentration is likely to occur.
Chapter 3, Section 3.5.4, Pg. 73.
Selection of the AAQM station based on the
prescribed criteria is provided in Chapter 3,
Section 3.5.4, Table 3-11, Pg. 73.
17
Impact of the project on the AAQ of the area. Details of the model
used and the input parameters used for modeling should be provided.
The air quality contours may be plotted on a location map showing
the location of project site, habitation, sensitive receptors, if any. The
wind roses should also be shown on this map. Air quality modeling to
be carried out considering the partial and complete failure of the ESP.
Impact of project on AAQ of area: Chapter
4, Section 4.2.1, Pg. 119.
CPCB approved AERMOD software is used
for dispersion modelling. Air quality contours
showing windrose are provided in Annexure
33, Pg. 363. Air quality modelling for partial
and complete failure of the ESP is mentioned
in Annexure 34.
18
Quantity of the fuel requirement, its source and transportation,
storage, handling and management along with the environmental
management to be adopted for this. Fuel analysis to be provided
(Sulphur, ash content and heavy metals including Pb, Cr, As and Hg).
Quantity of the fuel requirement & its source
and transportation: Chapter 2, Section
2.7.2, Pg. 44.
Fuel analysis: Annexure 21, Pg. 312.
19 A confirmed fuel linkage along with the supportive documents for long
term supply of coal for the project requirements should be provided. Fuel Linkage: Annexure 22, Pg. 313.
20
Specific details of (i) details of the utilities required (ii) Quantity and
characteristics of each fuel along with analysis report and its source
(iii) Flue gas emission rate from each utility (iv) Air Pollution Control
Measures proposed to each of the utility along with its adequacy.
Details of the utilities: Chapter 2, Section
2.7, Pg. 44.
Fuel Details: Section 2.7.2, Pg. 44.
Emission rates: Section 4.2.1, Pg. 116.
Proposed APCM: Section 2.9.1, Pg. 45.
21
Technical details of ESP proposed to be installed as air pollution
control system along with its adequacy, details of its operational
controls with DCS, system for online monitoring of the pollutants from
the stack etc. Details of provisions to be kept in ESP to ensure that in
any case the air emission does not cross the GPCB norms including
provision of standby field in the ESP, preventive maintenance, failure /
tripping control system, guarantee from the ESP supplier, alternative
arrangements in case of the failure / tripping of the ESPs etc. ESP
should be designed to achieve GPCB norms at the outlet.
Technical Details of ESP: Chapter 2,
Section 2.9.2, Pg. 46.
Action Plan to control AAQ: Refer Chapter
2, Section 2.9.1, Pg. 45.
22
List of all the sources of fugitive emission. Detailed plan for prevention
and control of fugitive emission / dusting at each and every stage of
fuel handling including unloading / loading at port, transportation from
port to plant, unloading / loading / stacking / conveyance / transfer at
plant etc. Detailed specifications and schematic diagram of water
sprinkling system including number of sprinklers to be installed, pipe
diameter and nozzle diameter of the sprinklers, quantity of water to
be consumed by sprinklers etc.
Fugitive emissions details: Chapter 2,
Section 2.8, Pg. 47.
Details for prevention and control of fugitive
emission (sprinkling system): Chapter 2,
Section 2.6.1, Pg. 43.
23
Impact on local transportation infrastructure due to the project such
as transportation of fuel, ash etc. Baseline status of the existing
traffic, projected increase in truck traffic as a result of the project in
the present road network, impact on it due to the project activities,
carrying capacity of the existing roads and whether it is capable of
handling the increased load. Arrangement for improving the
infrastructure like road etc. if any should be covered. Whether any
additional infrastructure would need to be constructed and the agency
Impact due to road transport: Chapter 4,
Section 4.2.2, Pg. 122. Carrying capacity
of road is sufficient to take additional load.
Baseline status of the existing traffic:
Chapter 3, Section 3.5.4, Pg. 76.
Already developed infrastructure like road,
drainage network etc. is available at site,
hence, no additional infrastructure is
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 28
S. No. ToR Compliance in Report
responsible for the same with time frame. required to be constructed.
24
Details and time bound program for installation of online monitoring
system in the existing as well as proposed plants for monitoring of the
pollutants from the stacks and process vents with software and an
arrangement to reflect the online monitored data on the company’s
server, which can be accessed by the GPCB on real time basis.
Existing & proposed online monitoring
systems: Chapter 2, Section 2.9.6, Pg.
48.
25
Provision of Continuous Ambient Air Quality Monitoring Station
[CAAQMS] within premises, with an arrangement to reflect monitored
data on the company’s server, which can be accessed by the GPCB on
real time basis.
CAAQMS details: Chapter 2, Section
2.9.6, Pg. 48.
26 Details of measures proposed for the noise pollution abatement and
its monitoring.
Measures for noise pollution abatement:
Chapter 4, Section 4.3, Pg. 128.
27
Details of management of hazardous wastes to be generated from the
project stating details of storage area for each type of waste, its
handling, its utilization and disposal etc. How the manual handling of
the hazardous wastes will be minimized.
Solid and Hazardous waste Management:
Chapter 10, Section 10.3.4, Pg. 180.
28
Detailed plan of ash evacuation, handling, storage and utilization
should be provided. Undertaking stating that ash pond shall not be
constructed and it shall be stored in closed silos only should be
incorporated.
Fly ash utilization plan: Chapter 2, Section
2.6.4, Pg. 43 & Section 2.12, Pg. 55.
Undertaking regarding Ash Pond: Annexure
41.
29 Details of seismic design aspects to be adhered to in the project. Ref. Chapter 2, Section 2.8, Pg. 45.
30 Technical details of conveyor belts and mitigation measures to ensure
that there will be no dust emission from conveyor belts.
Details of conveyor belts: Chapter 2,
Section 2.9.3, Pg. 47.
31 Details of proposed disposal of solid wastes that may generate due to
spillage of materials.
Details of proposed disposal of solid wastes:
Chapter 2, Section 2.12, Pg. 56.
32 Specific safety measures proposed at storage yard/warehouse and
conveyor belts.
Specific safety measures proposed at storage
yard: Chapter 7, Section 7.2.4, Pg. 166-
168.
33
Details of firefighting system including provision for flame detectors,
temperature actuated heat detectors with alarms, automatic sprinkler
system, location of fire water tanks & capacity, separate power
system for firefighting, details of qualified and trained fire personnel &
their job specifications, nearest fire station & time required to reach
the proposed site. Submit line diagram of the fire hydrant network.
Details of safety measures are provided in
Chapter 7, Section 7.2.4, Table 7-2, Pg.
152.
Line diagram of the fire hydrant network:
Annexure 17, Pg. 307.
34 Copy of membership certificate of Common Environmental
Infrastructure like TSDF, if any taken should be incorporated.
Copy of membership certificate of TSDF:
Annexure 24, Pg. 319.
35
Details of 100% fly ash utilization plan as per latest fly ash utilization
notification of GOI along with firm agreements / MoU with contracting
parties including other usages etc. shall be submitted. The plan shall
also include disposal method / mechanism of bottom ash.
Fly ash utilization plan: Chapter 2, Section
2.6.4, Pg. 43 & Section 2.12, Pg. 55.
Mutual Agreement for utilization of fly ash:
Annexure 25, Pg. 321.
36
A detailed EMP including the protection and mitigation measures for
impact on human health and environment as well as detailed
monitoring plan and environmental management shall proposed for
implementation and monitoring of EMP. The EMP should also include
the concept of waste-minimization, recycle/reuse/recover techniques,
energy conservation, and natural resource conservation. Total capital
cost and recurring cost/annum earmarked for environment pollution
control measures.
Detailed EMP are covered in Chapter 6, Pg.
140.
37
Occupational health impacts on the workers and mitigation measures
proposed to avoid the human health hazards along with the personal
protective equipment to be provided to the workers. Provision of
industrial hygienist and monitoring of the occupation injury to workers
Occupational health impacts on the workers
and mitigation measures: Chapter 4,
Section 4.7.1, Pg. 136.
Occupational Heath checkup: Chapter 7,
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 29
S. No. ToR Compliance in Report
as well as impact on the workers. Plan for periodic medical checkup of
the workers exposed. Details of work zone ambient air quality
monitoring plan as per Gujarat Factories Rules.
Section 7.2.4, Pg. 169.
Work zone ambient air quality monitoring:
Chapter 3, Section 3.5.4, Pg. 77.
38
Risk assessment including prediction of the worst-case scenario and
maximum credible accident scenario related to fire and explosion
issues due to storage and use of fuel should be carried out. The
worst-case scenario should take into account the maximum inventory
of storage at site at any point in time. The risk contours should be
plotted on the plant layout map clearly showing which of the activities
would be affected in case of an accident taking place. Based on the
same, proposed safeguard measures including On-site/Off-site
emergency plan should be provided. Measures to guard against fire
hazards including details of automatic fire detection and control
system & detailed fire control plan showing hydrant pipeline network,
provision of DG Sets, fire pumps, jockey pump, toxic gas detectors
etc. should also be provided.
Maximum Credible Loss Scenarios were not
considered due to the following reasons:
• Proposed project is for expansion of 67
MW power plant, which only requires coal &
limestone, which are non-hazardous. All
other hazardous chemicals handled at site
were already considered in previous EIA
studies for which EC is granted.
• Auxiliary power will be sourced from
existing power plant / grid. Thus, no DG sets
are proposed for startup of proposed unit.
• On the basis of chemical properties like
flash point, phase of chemical, operating
conditions and total inventory etc., it is
noted that in the proposed power plant unit,
there are no such storage of flammable raw
materials which can lead to uncontrolled
release of hazardous material causing
hazard.
Onsite Emergency Plan: Section 7.2.4, Pg.
163.
Offsite Emergency Plan: Section 7.2.4, Pg.
169.
Measures to guard against fire hazards:
Section 7.2.4, Pg. 166.
39
Provisions for water supply, fuel (kerosene or cooking gas), lighting,
sanitation etc. to the construction work force so as to avoid felling of
trees/mangroves and pollution of water and the surroundings. Details
of personal protective equipment’s to be provided to construction
workers at the site.
Local workforce will be hired. Hence,
Provisions for water supply, fuel (kerosene
or cooking gas), lighting, sanitation etc. is
not required.
40
Submit checklist in the form of Do’s & Don’ts of preventive
maintenance, strengthening of HSE, manufacturing utility staff for
safety related measures.
Refer: Chapter 7, Section 7.2.4, Pg. 160.
41
Public hearing shall be carried out as per the MoEF&CC’s OM dated
04/04/2016. A tabular chart for the issues raised and addressed
during public hearing/consultation and commitment of the project
proponent on the same should be provided. An action plan to address
the issues raised during public hearing and the necessary allocation of
funds for the same should be provided.
Public hearing will be carried out.
42
Detailed five year greenbelt development program including annual
budget, types & number of trees to be planted, area under green belt
development [with map], budgetary outlay; along with commitment of
the management to carry out the tree plantation activities outside the
premises at appropriate places in the nearby areas and elsewhere.
33% of greenbelt will be maintained within
premises. Budget, types & number of trees
to be planted, area under green belt
development is provided in Chapter 10,
Section 10.3.6, Pg. 180.
43
Proposal of socio-economic development activities including
community welfare program most useful in the project area for the
overall improvement of the environment. Submit a detailed plan for
social corporate responsibilities, with appropriate budgetary provisions
for the next five years and activities proposed to be carried out;
specific to the current demographic status of the area.
Socio-economic development activities:
Chapter 6, Section 6.7, Pg. 148.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 1. INTRODUCTION &
BACKGROUND
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 30
S. No. ToR Compliance in Report
44 Plan for compliance of the EP Rules and CREP guidelines for the
proposed power plant.
Compliance of the EP Rules will be done
once the CTE/CTO is received for the
proposed project and Compliance of CREP
guidelines: Annexure 16, Pg. 305.
45
Compliance status of the existing unit with respect to various
conditions given in the Environmental Clearance and CC&A orders
obtained for the existing plants.
Compliance status of the existing unit,
previous EC: Chapter 13, Pg. 205.
46
Records of any legal breach of Environmental Laws i.e. details of
show-cause notices, closure notice etc. served by the GPCB to the
existing unit in last three years and actions taken then after for
prevention of pollution.
Details of show-cause notices, closure notice
etc. served by the GPCB: Chapter 1,
Section 1.4.1, Pg. 23.
47
Copy of Environmental Clearance obtained for the existing project and
a certified report of the status of compliance of the conditions
stipulated in the environmental clearance for the existing operation of
the project by the Regional Office of the MoEF&CC.
Details of previous EC: Chapter 1, Section
1.4.1, Pg. 23.
Compliance status of the existing unit,
previous EC: Chapter 13, Pg. 205.
48
Details of fatal/non-fatal accidents, loss of life or man hours, if any,
occurred in the existing unit in last three years and measures
proposed to be taken for avoiding reoccurrence of such accidents in
future.
No fatal/non-fatal accidents, loss of life or
man hours have occurred in the existing unit
in last three years.
49
Any litigation pending against the project and / or any direction /
order passed by any Court of Law against the project, if so, details
thereof.
No litigation pending against the project.
50
Does the company have a well laid down Environment Policy approved
by its Board of Directors? If so, it may be detailed in the EIA report.
Does the Environment Policy prescribe for standard operating process
/ procedures to bring into focus any infringement / deviation /
violation of the environmental or forest norms / conditions? If so, it
may be detailed in the EIA.
Integrated Management Policy including
environment aspect: Annexure 2.
IMS Certificates (ISO 9001:2008 & ISO
14001:2004): Annexure 1.
51
What is the hierarchical system or administrative order of the
company to deal with the environmental issues and for ensuring
compliance with the EC conditions. Details of this system may be
given.
Hierarchical system: Chapter 10, Section
10.3.8, Pg. 185.
52
Does the company have a system of reporting of non-compliances /
violations of environmental norms to the Board of Directors of the
company and / or shareholders or stakeholders at large? This
reporting mechanism should be detailed in the EIA Report.
Reporting structure: Chapter 10, Section
10.3.8, Pg. 185.
53 Certificate of accreditation issued by the NABET, QCI to the
environmental consultant should be incorporated in the EIA Report.
Regarding Certification of the Environmental
Consultant, Refer Chapter 12, Pg. 202.
54
An undertaking by the Project Proponent on the ownership of the EIA
report as per the MoEF&CC OM dated 05/10/2011 and an undertaking
by the Consultant regarding the prescribed TORs have been complied
with and the data submitted is factually correct as per the MoEF&CC
OM dated 04/08/2009.
Undertaking by MFL: Annexure 42.
Undertaking by Kadam: Annexure 43.
55 All documents to be properly referenced with index and continuous
page numbering. Noted & Complied.
56 Compliance of the emission standards as mentioned in the Notification
by MoEF&CC vide no. S.O. 3305 (E) dated 07/12/2015.
Emissions / Discharge (ZLD) is as per the
mentioned Notification by MoEF&CC.
57 A tabular chart with index for point-wise compliance of the above. TOR Compliance Status: Chapter 1,
Section 1.5, Pg. 25.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 31
2 PROJECT DESCRIPTION
This chapter provides a condensed description of those aspects of the project likely to cause environmental effects.
Details are described in following sections with regards to type, need, location, size or magnitude of project
operations, technology and other related activities.
2.1 TYPE OF PROJECT
The project is for Expansion of Power Plant. Classification of the project is as mentioned in Chapter 1, Section
1.2.1.
2.2 NEED FOR THE PROJECT
The proposed power plant is required to cater to the internal power & steam requirement.
2.3 LOCATION OF THE PROJECT
2.3.1 General Location of the Site
The project site is situated on Plot No.: CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat,
admeasuring an area of 53.347 hectares (5,33,470 m2). Plot area of the proposed project consists of 3,702 m2.
Dahej Industrial Estate is an existing industrial area developed by the Gujarat Industrial Development Corporation
(GIDC), categorized as chemical zone for setting up chemical industries.
2.3.2 Location Map
Location map showing general location is given in Map 2-1. Map showing specific location of proposed project on
Toposheet is given in Map 2-2.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 32
Map 2-1: General Location Map of Project Site
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 33
Map 2-2: Project Site on Toposheet
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 34
2.3.3 Project Boundary
The co-ordinates of the project site are given in Table 2-1. Map showing project Boundary is given in Map 2-3.
Table 2-1: Co-ordinates of Project Boundary
Code Latitude Longitude
A 21°42'56.66"N 72°36'59.91"E
B 21°42'58.56"N 72°36'36.52"E
C 21°43'3.40"N 72°36'37.08"E
D 21°43'3.97"N 72°36'31.66"E
E 21°43'19.99"N 72°36'33.37"E
F 21°43'20.24"N 72°36'41.13"E
G 21°43'26.48"N 72°36'41.31"E
H 21°43'26.87"N 72°36'54.25"E
I 21°43'10.90"N 72°36'56.75"E
J 21°43'10.92"N 72°36'57.82"E
K 21°43'1.49"N 72°36'59.11"E
Land Distribution at Site and Project Site Layout
Total plot area of the project is 5,33,470 m2 area. Area required for the proposed expansion within the site will be
3,702 m2. Land distribution of the entire site & proposed power plant are tabulated in Table 2-2 & Table 2-3
respectively. Site layout map of the project is shown in Map 2-4.
Table 2-2: Area Breakup – Entire Site
S.
No. Description
Area Details (m²)
Existing Units Proposed Power Plant Total % of Total Area
1 Plant Facilities – Power Plant (65 MW) 15,150 -- 15,150 2.8%
2 Plant Facilities – Power Plant (67 MW) -- 3,702 3,702 0.7%
3 Process Area 25,000 -- 25,000 4.7%
4 Storage for Raw Materials 10,100 -- 10,100 1.9%
5 Storage for Products 3,500 -- 3,500 0.7%
6 Storage for Water 17,160 -- 17,160 3.2%
7 Utilities 3,500 -- 3,500 0.7%
8 Approach Road(s) 17,000 -- 17,000 3.2%
9 Solid Waste Pit area (SLF) 14,000 -- 14,000 2.6%
10 Office 2,000 -- 2,000 0.4%
11 Parking 61,000 -- 61,000 11.4%
12 ETP 2,500 -- 2,500 0.5%
13 Hazardous Waste storage -- 50 50 0.01%
14 Area for future expansion 88,948 88,948 16.7%
15 Open to Sky 93,760 93,760 17.6%
16 Total Green Belt Area 1,76,100 1,76,100 33.0%
TOTAL 5,33,470 100
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 35
Table 2-3: Area Breakup – Proposed Power Plant
S
No. Description
Area for Expansion unit
(m2)
% of Total area of
Proposed Power Plant Remark
1 Turbo Generator building 900 24 -
2 Coal storage 0 - Existing Yard is sufficient
3 Road 300 8 -
4 Green belt 0 - 33% of plot area is
already provided
5 Water Cooling Condensers 1,000 27 -
6 Boiler 1,200 32 -
7 Open space 302 9 -
Total 3,702 100
Pie chart showing area breakup of the proposed power plant within the factory premises is presented in Figure 2-1.
Figure 2-1: Pie Chart – Area Breakup of Proposed Power Plant
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC
DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 36
Map 2-3: Project Boundary Map
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 37
Map 2-4: Project Site Layout Map
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 38
Photographs of the existing and proposed site are shown in Photograph 2-1.
Photograph 2-1: Photographs showing Existing and Proposed Site
EIAC at Existing MFL Site Hydrogen Holder
Existing Coal Based Power Plant
Proposed Site
2.3.4 Approach to the Project Site
The project site is approachable and the details are provided in Table 2-4.
Table 2-4: Details of the Site Connectivity
S. No Description Aerial Distance in Km Direction from Project Site
Road
1 SH-6 (Dahej-Bharuch) 0.19 S
Rail
1 Dahej Railway Station
(Samni-Dahej section) 2.4 WSW
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 39
S. No Description Aerial Distance in Km Direction from Project Site
2 Bharuch Railway Station 39 ESE
Airports
1 Surat 66.7 SSE
2 Vadodara 91 NE
Waterways
1 Adani Port 10 WSW
2.4 SIZE OR MAGNITUDE OF OPERATION
2.4.1 Production Capacity
Existing Capacity
MFL is currently manufacturing products as mentioned in Table 2-5 at their existing facility. For the same
EC/CTE/CC&A as mentioned in Chapter 1, Section 1.4.1, is already received. Certified Compliance report of the
EC is also provided as Annexure 38. Action plan for the same is provided in Chapter 13.
Table 2-5: List of Existing Products
S.
No. Products Capacity (MTPM) As per EC / CTE / CC&A
A Chlor - Alkali Units
1
Caustic Soda 16,800 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
OR
Caustic Soda 15,000 CC&A Amendment, dated 24.06.2016 issued vide Letter
No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/360636 Caustic Potash 1,800
2 Chlorine Gas 14,885 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
3 Hydrogen Gas 420 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
4 78 % Dilute Sulphuric Acid 653 EC: J-11011/259/2011 – IA dated 12.09.2012
5 30 % Hydrochloric Acid 7,583 EC: J-11011/259/2011 – IA dated 12.09.2012
6 Sodium Hypochlorite 1,458 EC: J-11011/259/2011 – IA dated 12.09.2012
7 Hydrogen Peroxide 1,200* CTE Amendment, dated 01.05.2017 issued vide Letter
No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/411050
B Synthetic Organic Units
1 Meta Phenoxy Benzaldehyde Alcohol 200** EC: J-11011/259/2011 – IA dated 12.09.2012
* Not being produced at the site as on date, construction work going on, accordingly CC&A will be amended.
** Not being produced at the site as on date, accordingly CC&A is already amended on 24.06.2016.
Proposed Capacity
The details of proposed capacity of the power plant is given in Table 2-6.
Table 2-6: Existing and Proposed Capacities – Power Plant
S.
No. Particular Unit
Existing
Capacity
Additional
Proposed
Total After
Expansion
1 Power Plant MW 65 67 132
2 Steam (including process & power) TPH 290 360 650
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 40
2.4.2 Cost of the Proposed Project
The project cost would be INR ~ 230 Crore. The break-up of the total cost is given in Table 2-7.
Table 2-7: Cost Break-up
S. No. Particulars Total Amount (INR in Crores)
1 Turbine Generator with their Auxiliaries and Utility 49.9
2 Boiler House including ESP , Ash Handling and other Auxiliaries 106.9
3 Fuel Handling plant 11.3
4 Automation, Instrumentation 8.2
5 Electrical Installations 18.7
6 Civil Work 21
7 Painting and Insulation 1.0
8 Engineering & Consultancy Expenses 1.3
9 Statutory expenses 0.5
10 IDC & Overheads 11.0
Total – Approx. 230
2.5 PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION
Project implementation schedule describing various activities from finalization of site to project commissioning is
described in Table 2-8.
Table 2-8: Project Implementation Schedule
S. No. Activities Start Finish
1 EC Approval August, 2017 April, 2018
2 Detailed Engineering July, 2017 March, 2018
3 Procurement and Delivery May, 2018 January, 2019
4 Construction at Site (Buildings, Mech., Piping, Elec., Inst etc.) May, 2018 June, 2019
5 Pre Commissioning June, 2019 July, 2019
6 CTO Approval June, 2019 July, 2019
7 Process Startup and Stabilization July, 2019 August, 2019
2.6 TECHNOLOGY AND PROCESS DESCRIPTION
2.6.1 Existing 65 MW – Captive Power Plant
A thermal power plant is an energy conversion center that converts the heat of coal to electricity, designed on a
large scale for continuous operation.
The feed water used in the steam boiler is a means of transferring heat energy from the burning coal fuel to the
mechanical energy of the spinning steam turbine. The total feed water consists of recalculated condensed steam,
referred to as condensate, from the steam turbines plus purified makeup water. Because the metallic materials it
contacts are subject to corrosion at high temperatures and pressures, the makeup water is highly purified before
use in D. M. Water plant. The boiler has a rectangular furnace. Its walls are made of a web of high pressure steel
tubes. Coal is prepared for use in boiler by crushing the rough coal to pieces less than 6 mm in size. Prepared coal
is air-blown into the furnace from fuel nozzles and it is combusted in such a manner that maximum combustion
efficiency can be achieved. This heats the water that circulates through the boiler tubes. The water circulation rate
in the boiler is three to four times the throughput and is typically driven by pumps. As the water in the boiler
circulates it absorbs heat and changes into steam. It is separated from the water inside a drum at the top of the
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 41
furnace. The saturated steam is introduced into superheat pendant tubes that hang in the hottest part of the
combustion gasses as they exit the furnace. Here the steam is superheated to required temperature to prepare it
for the turbine.
The turbine generator consists of a steam turbine, Gear Box, Generator, Condenser, Steam ejectors, Condensate
extraction system, to generate the required power.
The generator contains a stationary stator and a spinning rotor, having magnetic properties produce electricity
when it is rotated by Turbine. The electricity thus produced is used to run the various equipment.
The required steam for process is being drawn from turbine at required pressure and the balance exhaust steam
from the low pressure turbine enters condenser-tube bundles that have cooling water circulating through them.
Typically the cooling water causes the steam to condense.
From the bottom of the condenser, powerful pumps recycle the condensed steam (water) back to the feed water
heaters for reuse. The heat absorbed by the circulating cooling water in the condenser tubes must also be removed
to maintain the ability of the water to cool as it circulates. This is done by pumping the warm water from the
condenser through either natural draft, forced draft or induced draft cooling towers that reduce the temperature of
the water, by evaporation. As the combustion flue gas exits the boiler it is routed through a rotating flat basket of
metal mesh which picks up heat and returns it to incoming fresh air as the basket rotates, This is called the air pre
heater. The gas exiting the boiler is laden with fly ash, which are tiny spherical ash particles. The fly ash is removed
by electrostatic precipitators to achieve exhaust gas quality as required by the statute.
2.6.2 Proposed 67 MW – Captive Power Plant
The Imported Coal (~4,200 Kcal/Kg GCV) will be fed to furnace of the CFBC Boilers (2 x 180 TPH) through feeders
from the Coal storage. Coal will be mixed with Limestone to reduce SOx emission. This mix will be fired in the
furnace by means of FD-Fan air. The saturated steam is generated in the Boiler drum and passed to the Primary,
Secondary & final super heaters to get the superheated steam @ 535°C & 109 ata from the Boilers. The
superheated steam is fed to the Steam Turbine and it rotates the steam Turbine which is coupled with Generators
(2 Nos). The power of 67 MW will be generated in the Generators and distributed in house. Flue gas shall meet the
statutory norms. To comply emission norms, necessary dosing of lime stone shall be done via feeder. Design of
ESPs will be as per the state government norms & MoEF&CC guidelines / standards. General process flow diagram
of power plant is given in Figure 2-2.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 42
Figure 2-2: Process Flow Diagram – Proposed Power Plant
Diagram showing process of typical power plant operation is presented in Figure 2-3.
Figure 2-3: Typical Drawing showing Operation of Power Plant
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 43
Sprinkling System for Prevention and Control of Fugitive Emission & Fire Hydrant Network
All the covered coal storage shed shall be provided with water sprinkling arrangement to avoid dust emission during
handling of coal for feeding and unloading. Proposed grizzle hoppers will be equipped with dust suppression
system. Coal conveyors will be adequately covered with hoods and water mist system will be provided at loading
and discharge end of the conveyor. Two numbers of transfer towers, crusher house and bunker top area will be
equipped with DE (Dust Extraction) system. After detail engineering, specific quantification and specifications will be
provided.
After detail engineering the line diagram of fire hydrant network for proposed expansion project will be similar to
existing plant which is shown in Annexure 17.
Air Preheater & Economizer
To reutilize waste heat, air preheater & economizer will be provided. Technical specifications of the same will be
available after the detailed engineering is carried out after the receipt of environmental clearance.
2.6.3 Coal Handling System
Coal from dumper will be unloaded in grizzle hopper in coal handling plant. This coal will be transported to coal
crusher house through conveyor belt. Screen coal will be transported to boiler coal bunker through covered
conveyor belt. From coal bunker the crushed coal will be transported through pipe to boiler furnace and necessary
dust arrestor and dust suppression system are already provided in coal handling plant.
2.6.4 Ash Handling System
The fly ash produced from combustion will be collected at various locations such as economizer, air preheater,
electrostatic precipitators, etc. along with bottom ash and shall be transported pneumatically with the help of dense
phase pneumatic pumps to closed storage silos. The Fly Ash shall be sold to nearby Cement Industries / brick
manufacturers. Mutual purchase agreement with brick manufacturer is provided in Annexure 25. Bottom Ash is
partly recycled after screening and balance will be sold to the cement industry. Steel / RCC silos will be provided
having storage capacity of 3 days to store Fly Ash.
Dust collection system will be installed at transfer tower, crusher house, top of silo & bunker tower. Adequate
capacities of bag filters will be provided to avoid dusting.
2.6.5 Resource Optimization/ Recycling and Reuse
Steam condensate will be recycled back into the process. There will not be any generation of process effluent.
Boiler blow down will be directly used for cooling tower make up water while other effluents will be collected into
collection tank where pH correction will be carried out if required. Then the treated wastewater will be used for
dust suppression, in coal handling and & in existing ash handling unit. ZLD concept will be achieved for proposed
power plant. Thus water consumption will be minimal.
2.6.6 Feasibility of Water Cooled Condensers
MFL prefers water cooled condenser as against air cooled condenser for following reasons:
Space constraints as air cooled condenser require 3 times more space than water cooled system.
More utilization of energy available in steam as exhaust pressure of turbine will be lower than air cooled
condenser. Increase in expansion of steam will reduce steam consumption by 24 MT which results in coal
saving of 4.5 MT/Day.
Reduction in coal consumption will reduce CO2 emission by 6.5 MT/Day.
Adequate quantity of water is available from GIDC and overall water consumption will still be less than 2.5
m3/MWHr as per new norms.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 44
2.7 UTILITIES
The estimated list of utilities required for the new project (67 MW) is as given below:
2.7.1 Power Requirement
For the existing units, power requirement of 65 MW is sourced from own Captive Power Plant.
To operate power plant, details of auxiliary power requirement is tabulated in Table 2-9. It will be sourced from
DGVCL and will be used as standby back-up supply for emergency conditions & safe shutdown of power plant in
case of main power failure.
Table 2-9: Details of Power Requirement
S. No. Type Requirement (MW)
Existing Proposed Total
1 Auxiliary Power 1.65 1.70 3.35
2.7.2 Fuel Requirement
During operation phase, Imported Coal will be used as fuel. Details of fuel along with the quantity and means of
transportation is given in Table 2-10.
Table 2-10: Details of Main Raw Material Quantity and Means of Storage
S.
No.
Name of
Fuel
Quantity of Fuel (MTPD) Source
Means of
Transportation
Means of
Storage Existing Proposed Total
1 Imported
Coal 777 1,380 2,157
Open Market, Mainly
Adani Trucks Existing Silos
2 Limestone - 125 125 Open Market Trucks Closed Silos
Fuel Quality & Linkage
Proximate analysis of the imported coal is as provided in Annexure 21. Assurance letter for supply of imported
coal for the proposed project is provided as Annexure 22.
2.7.3 Water Requirement
Water requirement for existing industrial & domestic purposes is fulfilled through GIDC. Metering system has been
provided for measurement of water intake.
Due to various recycle and reuse schemes like higher COC operations of cooling towers, fresh water requirement
for power plant will be 9,506 KLD due to the proposed expansion project. Letter from GIDC for water supply of
11,356 KLD (3.00 MGD) is availed and provided as Annexure 18.
Water consumption for existing units and proposed power plant is given in Table 2-11.
Table 2-11: Water Requirement (Existing Units & Proposed Power Plant)
Type Quantity (KLD)
Existing Units Proposed Power Plant Total after Expansion
Water Consumption 5,633 3,873 9,506
2.7.4 Storage Details pertaining to the Proposed Project
Coal & Limestone Storage
Storage space of 8,912.79 m2 is already available for storing Coal. Limestone can also be accommodated in the
same storage area.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 45
Fly Ash Storage
Steel / RCC silos will be provided having storage capacity of 3 days of storage of Fly Ash.
2.7.5 Manpower
During the construction phase around 250 workers will be employed. Local skilled and semi-skilled workers will be
engaged during construction phase. During operation phase, Existing manpower (~570) is sufficient to operate
proposed expansion unit. The positive impact includes enhanced indirect employment opportunities for transporters
of raw material and finished goods.
2.8 PROPOSED INFRASTRUCTURE FOR THE PROJECT
Project area is categorized in the seismic zone III, as per Seismic Zoning Map of Gujarat by Institute of
Seismological Research (ISR), which is classified as having a Moderate Damage Risk Zone. The structure design will
be as per codes to negate the threat of damages due to earthquake.
No major infrastructure is required for the proposed unit as the existing facilities are already in place.
2.8.1 Industrial Area (Processing Area)
The captive power Co-generation power plant will consist of the following plant / equipment.
Boiler House consisting of High Pressure CFBC Boilers (two nos).
Turbo – Generator (TG) Sets (two sets): Turbine Generator with auxiliaries.
Pressure Reducing and De superheating Station.
Coal handling and supply system.
Condenser along with condensate extraction pumps, piping & valves.
Compressed Air System for instrumentation and utilities.
Ash handling system.
Pollution control equipment.
Chimney.
Electrical and Electrical Distribution System.
Instrumentation and control system (DCS) for Boilers and Turbine.
Cooling tower and cooling water pumps for lube oil cooler and other Auxiliaries.
D.M. plant for boiler feed water.
Adequate storage space for fuel storage, hazardous and other solid waste is already available. Additional storage
space will be provided as per the requirement.
2.8.2 Non-Processing Area
Existing non processing area includes Weighbridge, Administrative Building, Laboratory, Security cabins, Workers
restroom, Vehicle Shed, Water reservoirs for raw water and fire hydrant system, Temporary storage sites, Works
block etc. will be used for the proposed unit also.
2.9 AIR EMISSIONS & ONLINE MONITORING SYSTEMS
2.9.1 Point Source Emissions & Control (Action Plan to Achieve NAAQS)
Point source emissions of pollutants into air from the proposed project will be through flue gas stacks attached to
boilers. The principal air pollutants arising due to the project are SPM, NOx & SO2. Adequate stack height and
proper pollution control equipment will be provided for all flue gas stacks.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 46
From the existing facility point source emissions are identified as 2 flue gas stacks and 4 process stacks/vents.
Proposed plant shall have additional 2 flue gas stacks. Details of existing & proposed stacks and APCM to control
emissions are tabulated in Table 2-12 and Table 2-13.
Table 2-12: Details of Stacks and APCM – Existing
S
No. Stack Attached to
Pollutant as per
Consent Order APCM
Stack
Height Remarks/ Technical Specification
C1 C2 C3 C4 C5 C6
Flue Gas Stacks
1 Power Plant Boiler (40
MW CPP) SPM, SO2, NOx ESP 95 Round Stack top, Exit Velocity 10 m/s.
2 Power Plant Boiler (25
MW CPP) SPM, SO2, NOx ESP 65 Round Stack top, Exit Velocity 10 m/s.
Process Stacks /
Vents
1 Hypo Plant HCl, Cl2 Alkali Scrubber 30 Round Stack top, Exit Velocity 1.0 m/s.
2 HCl Synthesis HCl, Cl2 Water Scrubber 30 Round Stack top, Exit Velocity 1.0 m/s.
3 Flakers Plant HCl, Cl2 Bag Filter 40 Round Stack top, Exit Velocity 1.5 m/s.
4 Depleted air from
Solvent recovery unit VOC
Activated Carbon
Adsorption column 32 Round Stack top, Exit Velocity 1.5 m/s.
Table 2-13: Details of Stacks and APCM – Proposed
S
No. Stack Attached to
Expected
Pollutants APCM
Stack
Height Remarks/ Technical Specification
C1 C2 C3 C4 C5 C6
Flue Gas Stacks
1 Common stack for Boilers -
(2 Nos of 180 TPH each) SPM, SO2, NOx ESP 65 Round Stack top, Exit Velocity 12.5 m/s.
2.9.2 Design details of Proposed APCMs
ESP
ESP for the proposed boilers will be designed for firing design fuel at 100% Boiler Maximum Continuous Rating
(BMCR) and in case of tripping of any one of the fields the entire dust load will be catered by remaining fields and
emission norms of < 30 mg/Nm3 will be maintained as per GPCB guidelines.
Online SPM meter will be installed and remain connected to DCS for continuous monitoring of emission and alarm
limits will be set for necessary corrective action to be carried out when exceeding the limit. ESP collecting efficiency
shall be 99.9%.
ESP performance will be guaranteed from supplier for meeting emission norms set by the GPCB even in case one
field is not in operation. Necessary PG test shall be conducted and ensure the performance from the supplier. Since
supplier is not identified till date, the required performance guarantee will be obtained at the time of placing the
work order.
Technical specifications of ESP are given in Table 2-14.
Table 2-14: Technical Details of Proposed ESP
S. No. APCM Equipment Specifications Exit Emission Rate (mg/Nm3)
1 ESP
Flue gas temp. at ESP inlet °C: 140
Flue gas temp. at ESP outlet °C: 138
No. of fields: Multi Field
SPM: 30
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 47
2.9.3 Area Source Emissions & Control
From the proposed project, area source is identified as open storage of coal. Additional coal shall be stored in the
existing facility of coal storage yard. From the proposed project, area source emitting SPM is identified as open
storage of coal. Water sprinkling as per the requirement will be carried out.
Coal Handling System
Three numbers of covered coal shed with water sprinkling arrangement to avoid dust emission during handling of
coal for feeding and unloading. Proposed grizzle hoppers will be equipped with dust suppression system. Coal
conveyors will be adequately covered with hoods and water mist system will be provided at loading and discharge
end of the conveyor. Two numbers of transfer towers, crusher house and bunker top area will be equipped with DE
(Dust Extraction) system.
Usage of coal in the proposed project shall involve following steps:
Coal will be conveyed by trucks covered with HDPE sheets and it will be unloaded and stored in the long
covered shed;
It will be taken from stacks to hopper by dumpers, 250 meter away from the storage yard;
From hopper, coal is fed to boilers vial belt conveyors;
Water sprinklers will be provided over the belt conveyors to prevent any fugitive emission during handling of
coal;
Coal crusher will also be provided with dust collector. Bag filter will also been provided at vibrating screen,
crusher area and transfer tower;
Developed green belt around the plant boundary and along the internal road;
The trucks will be covered with HDPE sheets to prevent the coal ash from spilling / creating an air pollution
nuisance;
Maintenance and monitoring of equipment will be strictly adhered to as per the preventive maintenance
schedule of the plant;
Prescribed Guidelines for coal handling units will be followed.
Conveyor Belts
All conveyor belts along the length will be covered with hoods and mist system at both ends of conveyor will be
provided.
2.9.4 Line Source Emissions & Control
During construction phase, vehicular emissions will be from use of construction machinery and vehicles. Apart from
it, application of heavy machinery and earth movers will generate emissions. Suitable dust suppression techniques
such as water sprinkling will be taken at these times as relevant.
Approximately, 100 trucks per day carrying coal, lime stone & fly ash shall be using the state highway connecting
Bharuch and Dahej. Existing employees and contract workers shall use the same route during peak hours.
2.9.5 Fugitive Emissions & its Control
Dusting in the material handling section, fugitive emission of Lime stone dust, coal dust, fly ash dust are possible.
To control these emissions, following steps will be taken:
Enclosed conveyors for the transportation of the solid fuel;
Water sprinkling system in the material storage yard to suppress the dusting due to winds;
Storage of the fly Ash only in closed silo;
Transportation of the fly ash in bunkers.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 48
2.9.6 Online Monitoring Systems
Existing
MFL has installed online monitoring system in their existing facilities. Details of the same are as tabulated in Table
2-15. Recent online data for the parameters which are being monitored online and which are linked with GPCB &
CPCB servers are provided in Annexure 23.
Proposed
Online monitoring system (Continuous Ambient Air Quality Monitoring system & sensors on flue gas stacks) shall be
provided with the data connected to the GPCB site before the receipt of Consent to Operate for the proposed unit.
Table 2-15: Details of Existing & Proposed Online Monitoring Systems
S.
No. Name of Plant
Type of
Monitoring
System
Process
Attached
Parameter
Monitored Device Make
Certified
Agency
Existing Systems
1 Power Plant (Coal Based)
– 2 stacks Emission Boiler
SPM DURAG TUV
SO2 & NOx PRIMA TUV & CE
2 Chlor-Alkali Plant Emission Alkali Scrubber Chlorine PRIMA TUV
3 Chlor-Alkali Plant Emission Water Scrubber Chlorine & HCl PRIMA TUV
4 Chlor-Alkali Plant Effluent ETP pH Yokogawa TUV
5 Chlor-Alkali Plant Effluent ETP Flow Endress +
Hauser TUV
6 Chlor-Alkali Plant Effluent ETP TSS Insite
Instrument USA TUV
Proposed Systems
1 New Power Plant (Coal
Based) – 1 stacks Emission Boiler
SPM DURAG TUV
SO2 & NOx PRIMA TUV & CE
2
Continuous Ambient Air
Quality Monitoring
system
AAQ Nr. Security
Gate
PM10, PM2.5, SO2,
NOx Not finalized Yet
2.10 NOISE GENERATION
From the proposed project, noise shall be generated from the various activities. Source of noise generation are:
Heavy machinery like crane, dumper, roller, bulldozers etc. will be used during daytime of construction phase;
Operation of turbine, DG set , cooling tower, pumps, FD-ID Fans & compressor;
Vehicle movement for transportation of raw material.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 49
2.11 WATER CONSUMPTION, WASTE WATER GENERATION & DISPOSAL DETAILS
2.11.1 Water Consumption and Wastewater Generation
The principal area of water consumption in the proposed project will be in Process, Washing, Boiler, Cooling,
Domestic & Gardening purpose. The breakup of water consumption from existing and proposed unit is presented in
Table 2-16.
Table 2-16: Details of Water Consumption from Existing and Proposed Unit
S.
No. Particulars
Water Consumption (KLD)
Existing Units Proposed Power Plant Total after expansion
1 Domestic 35 0 35
2 Gardening 500 0 500
3 DM Plant 0 15 15
4 Process / Boiler 1,579 0 1,579
5 Boiler 290 734* 1,024
6 Softener 0 97 97
7 Cooling 3,574 3,112 6,686
8 Washing 155 0 155
Total Water demand 6,133 3,959 10,092
Recycled Water 500 86 586
Fresh Water Demand 5,633 3,873 9,506
* Additional capacity of boiler is reserved for future process steam requirement.
Wastewater generation from the existing and proposed unit is presented in Table 2-17.
Table 2-17: Details of Wastewater Generation from Existing and Proposed Unit
S.
No. Particulars
Wastewater Generation (KLD) Remark
Existing Proposed Total
1 Domestic 35 0 35 To Existing ETP
2 DM Plant 0 15 15 Use for dust, Ash and coal handling
3 Process 778 0 778 To Existing ETP
4 Boiler 15 86 101 15 KLD to Existing ETP and 86 KLD to use
as make up water for Cooling Tower
5 Softener 0 97 97 Use for dust, Ash and coal handling
6 Cooling 1,564 308 1,872 1,564 KLD to Existing ETP and 308 KLD
Use for dust, Ash and coal handling
7 Washing 155 0 155 To Existing ETP
Total Wastewater
Generation and
Treatment Facility
2,547 507 3,054
86 KLD to Cooling Tower, 421 KLD
use for dust, ash & coal Handling for
proposed PP & 2,547 to Existing ETP
Water balance diagram for existing units, proposed power plant and combined (after expansion) is provided in
Figure 2-4, Figure 2-5 & Figure 2-6 respectively.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 50
Figure 2-4: Water Balance Diagram – Existing Unit
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 51
Figure 2-5: Water Balance Diagram – Proposed Power Plant Unit
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 52
Figure 2-6: Water Balance Diagram – Combined (After Expansion)
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 53
2.11.2 Wastewater Treatment & Disposal Facility
Existing Facility
The effluent generated from the existing plant is about 2,547 KLD which is treated in existing ETP of capacity 2,500
KLD having adequate additional design margin of 10%. The treated water from the ETP is reused for gardening and
rest is discharged into GIDC drain as per GPCB consent. Permission for discharge is provided as Annexure 19.
Wastewater Generation, Segregation & Treatment Facility
The effluent coming from the various areas like caustic soda plant, power plant, domestic sewage and other utilities
blow downs is collected into the collection tank and then transferred to neutralization tank. Lime dosing is carried
out to neutralize the effluent. Neutralized effluent is then directly collected in final treated water tank. From final
collection tank, effluent is discharged into GIDC drain for sea disposal.
Online flow meter & pH meter is installed at final disposal point before treated water is disposed into GIDC drain.
Sludge will be collected in sludge drying beds, dried it and then disposed at approved TSDF site.
Design Basis Inlet & Outlet Characteristics for Existing ETP
Characteristics of untreated and treated waste water is shown in Table 2-18.
Table 2-18: Design Inlet and Outlet Characteristics of Existing ETP
S. N. Parameter Unit Design Inlet Characteristics for ETP Design Outlet Characteristics of ETP
1 Design Flow m3/day 2,500 2,500
2 COD mg/l 250 <250
3 BOD mg/l 100 <100
4 TDS mg/l 35,000 -
5 SS mg/l 250 <100
List of Existing ETP Units
An effluent treatability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the
wastewater to be generated along with adequacy was carried out. The list of existing ETP units with capacity is
given Table 2-19.
Table 2-19: List of Existing ETP units with Capacity
S. No. Unit Name No. of Unit Size (m) Total Capacity (m3)
1 Collection Tank 1 20 x 15 x 2 600
2 Neutralization Tank 2 5 x 5 x 2.5 62.5
3 Final Treated Water Tank 2 25 x 40 x 1.5 1,500
4 Sludge Drying Beds -- -- --
Adequacy of Existing ETP
Adequacy in terms of hydraulic load is given in Table 2-20.
Table 2-20: Adequacy of Existing ETP
S. N. Unit Name No. of
Unit
Volume
(m3)
Total Capacity
(m3)
Flow
(m3/day)
Retention
Time (hr) Remarks
1 Collection Tank 1 600 600 2,500 5.76 Adequate
2 Neutralization Tank 2 62.5 125 2,500 1.2 Adequate
3 Final Treated Water Tank 2 1,500 3,000 2,500 28.8 Adequate
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 54
Process block diagram of Existing ETP is given in Figure 2-7.
Figure 2-7: Process Block Diagram of Existing ETP
Treated water Quality at Lagoon/Final Outlet Point
Analysis Results/Quality of Treated Effluents taken by GPCB are given in Annexure 20. It is noted that the quality
of treated effluent is well within the discharged limits given by GPCB report.
2.11.3 Wastewater Treatment & Disposal Facility – After Expansion of Power Plant
After Proposed Expansion the effluent generated from the existing unit (Chlor alkali plant & Power Plant -65 MW
capacity) will be treated as described above in existing wastewater treatment facility and treated water will be
discharged into GIDC drain after matching with discharge norms as per GPCB consent conditions.
Zero liquid discharge will be achieved for proposed 67 MW CPP.
67 MW Power Plant (Zero Liquid Discharge)
From the proposed power plant, the wastewater will be mainly generated form utilities blow downs like cooling
tower, boiler DM plant and Softener unit. Boiler blow down will be directly used for cooling tower make up water
while other effluents will be collected into collection tank where pH correction will be carried out, if required. Due to
pH correction with caustic, there will be no sludge formation. The salts formed will be carried away as a part of the
treated water, which will be then used for dust suppression, in coal handling and & in existing ash handling unit.
Thus, zero effluent discharge criteria for new power plant will be met. Rest of the effluent from other plants will be
treated in existing ETP and will be disposed to GIDC Drain after meeting the GPCB effluent discharge norms.
Process block diagram of proposed waste water treatment is given in Figure 2-8.
Figure 2-8: Process Block Diagram of Proposed Wastewater Treatment
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 55
2.12 SOLID AND HAZARDOUS WASTE IDENTIFICATION, QUANTIFICATION, STORAGE AND
DISPOSAL
Quantification and Categorization of Waste
Quantification and Categorization of Existing and Proposed Solid Hazardous and Non-Hazardous Waste Generation
related to power plant is given in Table 2-21. For the other units, hazardous waste is stored and disposed as per
the valid CC&A.
Table 2-21: Details of Existing and Proposed Hazardous & Non Hazardous Wastes
S. No
Waste Name
Category Quantity / Month (unless mentioned)
Source Disposal Method Existing Proposed Total
Hazardous Waste
1 Used Oil 5.1 1.7 KL 0.3 KL 2 KL Process
Will be collected, stored and reused as
low grade lubrication and left over
quantity (if any) sold to an authorized
dealer or reprocessor.
Non-Hazardous Waste
1 Fly Ash -- 1,890 MT 4,968 MT 6,858 MT CPP
Sold to brick manufacturer / Cement
industries. Permission is attached as
Annexure 25.
Identification of Solid and Other waste
Solid waste and other waste generated from the processes are tabulated in Table 2-22.
Table 2-22: Identification of Other Waste
Category Waste and Disposal method
Municipal Solid Waste
Other solid wastes generated would include kitchen waste, cardboard, paper, plastic and garden wastes
which are hand over to authorize vendors or sent to nearest municipal waste collection site for disposal
as MSW.
Industrial Solid Waste Scraps, paper bags, cardboards.
Plastic Waste Plastic bags etc.
E-waste
Generated from the computer lab and administrative buildings. E-Waste comprises of discarded
computers, copiers, fax machines, inverters, cell phones, CD’s, LAN Cables, Keyboards, Mouse, SMPS,
Fuses, Data cables, mobile/laptop peripherals like earphones, chargers, circuit boards, printer
cartridges etc. Electronic wastes will be handled as per the provisions of the E-Wastes (Management
and Handling) Rules, 2011.
Storage of Waste (Proposed Power Plant)
The storage area for Hazardous waste generated from the proposed power plant will be 50 m2.
Treatment of Waste
MFL possess Secured Landfill Facilities within the premises. MFL will also get memberships from the M/s BEIL for
Common Solid Waste Disposal Facility and Common Incinerator Facility for the disposal of waste whenever
required. The acceptance letter from M/s. BEIL is attached as Annexure 24.
Decontamination of discarded drums/ containers
There are numbers of chemicals used in manufacturing process many of these chemicals will be brought in the
plastic or MS drums. After the use of these chemicals, drums will be sent back to the suppliers for refilling or it is
decontaminated and sell to approve authorized recycler. Decontamination mainly done by washing and generated
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 56
water will be treated with effluent in the ETP. Unit is maintaining the record of generation of drums/carboys & final
disposal to registered venders for reuse recycle through log books.
Ash Handling System
Disposal of ash will be directly on ash tanker through spout arrangement. 400 m3 RCC silo for fly ash & bed ash of
capacity 100 m3 shall be provided.
Fly ash generated due to usage of existing coal is handled and disposed as per the following steps:
The quantity of fly ash from the flue gases of the different zones viz furnace, bank tubes, economizer & bag
filters are collected and conveyed to common bunker by Dense Phase conveying system;
The fly ash from the common bunker is conveyed to storage silo;
The whole system is totally enclosed and no emission will be generated;
Bag filter is provided to the common silo having adequate capacity;
The fly ash is given to cement manufacturer, brick manufacturing unit and for road construction.
Fly-Ash Utilization Plan
As per fly ash notification, 1999 amended till date, company is distributing generated fly ash for brick or cement
making process. Mutual Purchase Agreement with Satyam Enterprise is obtained and attached as Annexure 25.
Handling of Solid and Hazardous Wastes
All waste is being handed with proper PPEs like hand gloves, organic mask, gum boots/ safety shoes, dust mask/
nose mask will be provided to workers and drivers involved in handling and transportation of hazardous waste. The
wastes are handed in drums, cans and plastic bags and further transferred at the storage location in the Solid cum
Hazardous Waste Storage. Brine and ETP sludge will be transported through specially designed trolleys to the
secured landfill facility.
Transportation of Waste
The transport of the hazardous wastes will be in accordance with the provisions of The Hazardous Waste
(Management, Handling and Trans boundary Movement) Rules, 2016 as amended to date and the rules made
by the Central Government under the Motor Vehicles Act. 1988.
Manifest system will be followed in accordance to Form 10 of Hazardous Waste Management (Management
Handling and Trans boundary Movement) Rules, 2016 as amended till date.
TREM card will be provided to the transport drivers as per Form 11 of Hazardous waste Management
(Management Handling and Trans boundary Movement) Rules, 2016 as amended till date.
Fly ash will be transported in Covered trucks.
Waste recycling
The domestic waste will be utilized for gardening purpose.
The generated Fly ash will be raw material for Cement industries / Brick manufacturing industries.
2.13 PROJECT LAYOUT AND COMPONENTS
The project layout map is shown in Map 2-4. The components of the project along with the Area break-up are
shown in Table 2-2 & Table 2-3 respectively.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 2. PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 57
2.14 MITIGATION MEASURES AT DESIGN STAGE
Description of operational control incorporated into the project to meet environmental standards, environmental
operating conditions at design stage are given in Table 2-23.
Table 2-23: Operational Controls at Design Stage
S.
No.
Name
of Plant Parameters
Operational Controls at Design Stage
Air Water Solid / Hazardous Waste
Air (Prevention &
Control of Pollution)
Act – 1981
Water (Prevention &
Control of Pollution)
Act – 1974
MSW rules and Hazardous
Waste (Management Handling
& Trans Boundary Movement)
Rules, 2008
1 Power
Plant
Energy Energy efficiency will be considered during technology selection
SPM ESP -- --
SO2 Limestone dosing,
Adequate Stack Height -- --
NOX CFBC Technology, low
temperature operations -- --
Waste Water -- Treated waste water will
be fully recycled. --
Solid Waste -- --
Waste will be given to authorized
vendors and recyclers as per the
SHW rules as per the requirements.
Fly ash will be given to cement
manufacturer, brick manufacturing
unit and for road construction.
2.15 ASSESSMENT OF NEW AND UNTESTED TECHNOLOGY
No new and untested technology is being proposed. World-wide tested technology shall be used for this project.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 58
3 DESCRIPTION OF THE ENVIRONMENT
3.1 STUDY AREA
The study area is considered within 10 km radius of the project site at Dahej. Study area map of proposed project
is shown in Map 3-1.
3.2 PERIOD
Monitoring surveys of the study area has been carried out in December 2016 – February 2017 (1st December, 2016
– 28th February, 2017).
3.3 COMPONENTS
Baseline environmental qualities of valued components like air, noise, water, land, flora, fauna and socio-economic
are an important and integral part of the environment. The baseline data forms the basis for predicting/assessing
the environmental impacts of the proposed project. The baseline environmental quality is assessed through field
surveys within the impact zone as well as secondary data for various components of the environment.
3.4 METHODOLOGY
The methodology for conducting the baseline environmental survey has been obtained from the guidelines given in
the EIA Manual of the MoEF. Baseline information with respect to air, noise, water and soil quality in the study area
was collected by conducting primary data collection which includes sampling/field studies, survey & secondary data
collection.
Field monitoring for meteorological conditions, ambient air quality, water quality, noise quality, soil quality etc. has
been carried out, which constitutes major portion of the baseline environmental studies. In addition to these
important parameters, certain aspects like land use, socio-economic studies, ecological and biodiversity studies etc.
are covered during the study period. This information is based on secondary information sources and constitutes
remaining part of the baseline environmental studies.
The entire data has been collected through actual physical surveys and observations, literature surveys, interaction
with locals, government agencies and departments.
3.4.1 Primary data Collection
Primary Data collected includes:
Sampling/Field Studies Survey
Ambient air quality
Noise
Ground water/Surface water quality
Soil Quality
Land Use Pattern
Flora and Fauna
Socio Economic
Kadam’s laboratory at Vadodara has been utilized for the analysis of collected samples. The lab is both, accredited
to NABL as per BIS/ISO 17096 & is a Gazetted laboratory under the Environment Protection Act. Certificate &
Recognition letters are provided in Annexure 40.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 59
Map 3-1: Study Area Map
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 60
Map 3-2: Sampling Location Map
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 61
3.4.2 Secondary Data Collection
This includes review of secondary/published information on:
Long Term Meteorological Data from IMD;
Socio-Economic profile from Primary Census Abstract;
Sensitive area as reserve forests, sanctuaries, places of historical, archeological, tourist’s importance, etc. if
any.
3.5 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENTAL COMPONENTS
Establishment of baseline for valued environmental components, as identified in the scope;
Base maps of all environmental components.
3.5.1 Long Term Meteorology
The climate of the study area is based on information from the most recent published long-term climatological
tables (1961 – 1976) by Indian Meteorological Department (IMD), for Broach (Station ID: 42841). After 1976, this
station is not in operation.
The observatory was situated in the compound of the District Local Board Office. The place was in a low lying area
with tall trees all around. The Narmada flows nearby. Wind instruments were on the topmost terrace of the office
building. Observatory was then situated at K.G. Polytechnic, Bharuch.
A copy of the long-term climatological data is enclosed as Annexure 26. These tables give useful information
about a region’s weather, since they are collected over a 15-year period.
Temperature
The mean daily maximum and minimum temperatures recorded were 39.9°C (in the month of April) & 11.3°C (in
the month of January) respectively. The highest temperature recorded was 47.8°C on 20th May, 1955. The lowest
temperature recorded was 4.0°C on 22nd January, 1962.
During the winter season, i.e. for months of December, January and February mean daily maximum and minimum
temperatures remain between 11.3 – 33.5ºC.
Wind
Long term wind direction data is presented in Table 3-1. Overall for the whole year, first predominant wind
directions are from SW Direction (45 %), second predominant wind direction is from NE (22.5 %) and third
predominant wind direction is from NW Direction (13 %).
During the study period, i.e. winter period (December – February), first predominant wind direction is from NE
direction (48.5 %), second predominant wind direction is from SW Direction (16.2 %) and third predominant wind
direction is from NW Direction (13.5 %).
Table 3-1: Predominant/Mean Wind Direction IMD – Bharuch
Month
Predominant Wind
First Second Third
Morning Evening Morning Evening Morning Evening
January NE NE SW SW SE NW
February NE NE NW SW SW NW
March SW SW NE NW SE NE
April SW SW NW NW SE NE
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 62
Month
Predominant Wind
First Second Third
Morning Evening Morning Evening Morning Evening
May SW SW NW NW SW SE
June SW SW SW NW W/NW SE
July SW SW S SE W S/NW
August SW SW W NW S/NW SW/W
September SW SW NW NW W W
October SW SW NE NE SE SE
November NE NE SW SW SE SE
December NE NE SE SE/SW SW NW
Rainfall
The distribution of rainfall in the region, which includes the study area, is regular. Annual total rainfall in the region
is 912.1 mm.
Distribution of rainfall by season is 860.7 mm in monsoons (June, July, August, September), 38.7 mm in post-
monsoons (October – November), 2.8 mm in winter (December, January, February) and 9.9 mm in summer
(March, April, May). About 94.4 percent of the annual rainfall in the region is received during the monsoon months
i.e. June to September. July is the rainiest month.
Maximum rainfall in any one month was recorded in the month of September in year 1954 which was about 790.1
mm. July is having maximum number of rainy days i.e. 13.5.
Cloud Cover
The area remains cloudy between June - September, which is the active period of the monsoon season. Generally
cloud cover ranges from 1.5 to 6.7 OKTAS during this monsoon season.
In the winter season, cloud cover ranges from 0.1 to 1.1 OKTAS.
Humidity
Most humid conditions are found in the monsoons, followed by summer, post-monsoons, and winter in that order.
Mornings are more humid than evenings and relative humidity ranges from a high of 81-90% in monsoon mornings
to a low of 34-44% in winter evenings.
During winter season, relative humidity during morning and evening remains between 64 – 74 % and 34 – 44%
respectively. Average meteorological condition is given in Table 3-2.
Table 3-2: Average Meteorological Condition at IMD Bharuch
Month Mean Daily Temperature Rainfall (mm)
Monthly Total
No. of
Rainy
days
Relative Humidity
(%), (Morning)
Relative Humidity
(%), (Evening) Max Min
January 31.2 11.3 1.2 0.2 71 38
February 33.5 14 1.4 0.1 64 34
March 37.7 18.6 0.2 0 65 29
April 39.9 23.1 0.5 0.1 66 31
May 39.6 25.8 9.2 0.4 74 39
June 35.7 26.3 108.5 4.9 81 58
July 32.1 25.3 290.4 13.5 89 74
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 63
Month Mean Daily Temperature Rainfall (mm)
Monthly Total
No. of
Rainy
days
Relative Humidity
(%), (Morning)
Relative Humidity
(%), (Evening) Max Min
August 31.4 24.9 279.1 12.7 90 79
September 32.5 24.4 182.7 7.8 87 68
October 35.9 21.9 16.8 0.8 76 46
November 34.7 16.7 21.9 0.7 73 42
December 31.5 12.6 0.2 0 74 44
Total -- -- 912.1 41.2 -- --
Average 34.6 20.4 -- -- 76 49
3.5.2 Site Specific Meteorology
Baseline meteorological data has been collected hourly by installing automatic meteorological station at roof top of
SEZ office, which is ~ 8.30 Km in W direction from the project site. Photographs showing Meteorological Station set
up is given in Photograph 3-1.
Photograph 3-1: Photographs of Meteorological Station Setup
Meteorological Station at rooftop of SEZ Office
Methodology for Collection of Meteorological Parameters
Methodology for meteorological data collection is given in Table 3-3.
Table 3-3: Monitoring Methodology of Meteorological Data
S.
No.
Sampling
Parameters
Sample collection Total
Sampling
Period
Sampling
Frequency Methodology
Sampling equipment
Sensitivity/
Detection
Limit
1 Wind Speed Anemometer cup
counter (0 to 65 m/s) 0.25 m/s
December,
2016 to
February, 2017
Hourly
USEPA Document
No. EPA-454/R-99-
005, Feb 2000
(Meteorological
Monitoring Guidance
for Regulatory
Modelling
Applications)
2 Wind Direction Wind vane
(0° to 357°) 1°
3 Temperature Thermometer
(-40° to 60°) 0.1°C
4 Humidity
Relative Humidity
meter
(0-99%)
3%
5 Rainfall Rain gauge 0.5 mm
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 64
S.
No.
Sampling
Parameters
Sample collection Total
Sampling
Period
Sampling
Frequency Methodology
Sampling equipment
Sensitivity/
Detection
Limit
6 Cloud Cover -- -- 4 Hourly Visual Inspection by
the observer.
Winter 2016-17’s Site Specific Meteorological Data
Compiled mean meteorological data is represented in Table 3-4.
Table 3-4: Mean Site Specific Meteorological Data – Winter Season
Time Temp °C Relative
Humidity %
Wind Speed
(m/sec)
Wind
Direction
Cloud Cover,
Octas
Rainfall,
mm
0:00 22.2 55.6 2.8 NE 3.1 0.0
1:00 21.4 57.0 2.7 NE 2.8 0.0
2:00 20.7 59.2 2.6 NE 2.8 0.0
3:00 20.0 60.9 2.6 NE 2.9 0.0
4:00 19.3 63.4 2.4 NE 2.8 0.0
5:00 18.7 65.4 2.5 NE 2.9 0.0
6:00 18.2 67.0 2.5 NE 3.0 0.0
7:00 17.8 68.2 2.5 NE 3.0 0.0
8:00 18.8 67.3 2.7 NE 2.9 0.0
9:00 20.9 61.2 3.1 NE 3.0 0.0
10:00 23.3 54.2 3.3 NE 2.8 0.0
11:00 25.4 48.3 3.5 NE 3.0 0.0
12:00 27.1 43.0 3.6 NE / NW 3.1 0.0
13:00 28.1 40.8 3.7 NW 3.1 0.0
14:00 28.6 40.5 4.0 NW 3.1 0.0
15:00 29.3 37.7 3.9 NW 3.3 0.0
16:00 29.1 36.6 4.0 NW 3.1 0.0
17:00 28.6 37.5 3.7 NW 3.0 0.0
18:00 27.4 41.6 3.1 NW 2.9 0.0
19:00 26.1 46.2 2.9 NW 2.7 0.0
20:00 25.2 49.3 2.9 N 2.6 0.0
21:00 24.4 52.2 3.0 N 2.6 0.0
22:00 23.7 53.7 2.8 NE 2.7 0.0
23:00 22.9 55.5 2.7 NE 2.8 0.0
Mean /
Predominant 23.6 52.6 3.1 NE 2.9 0.0
Site-specific meteorological data shows that:
Average wind speed was 3.1 m/sec and mostly the morning hours are windier.
Average temperature recorded was 23.6°C and average relative humidity was 52.6%.
Wind blows predominantly from NE to SW direction (27 %). Calm condition is 0.79%. Windrose diagram is
shown as Figure 3-1.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 65
Figure 3-1: Windrose Diagram for Winter Season, 2016-17
Collation of Site Specific Data with Secondary Data of IMD
Site specific Meteorological data is compared with IMD’s secondary data as shown in Table 3-5.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 66
Table 3-5: Collation of Primary Meteorological data with Secondary Data (IMD)
S.
No. Parameters
Winter Season’s Data (1st December 2016 – 28th
February, 2017) Remarks
Site Specific; (24 hours) Long term IMD Data; (8.30
and 17.30 hours only)
1 Wind Speed Average Wind Speed is 11.0
Km/Hr.
Average Wind Speed is 6.0
Km/Hr.
Difference is probably ascribable
the fact that IMD readings are
only taken in the morning and
evening while site specific data is
for 24 hour readings. Also the
Site is closer to Gulf of Khambhat
compared to the Bharuch IMD
station.
2 Wind Direction
Wind blows predominantly
from NE to SW direction.
Calm Conditions: 0.79 %
Wind blows predominantly
from NE to SW direction.
Calm Conditions: 0.3 %.
Generally similar, minor
divergences noted can be
ascribed to locational differences,
differences in number of
readings and duration of studies
(one season v/s long term).
3 Temperature Max.: 36.7°C
Min.: 12.2°C
Max.: 33.5°C
Min.: 11.3°C
4 Relative Humidity Max.: 94.2%
Min.: 14.2 %
Max.: 74 %
Min.: 34 %
Sampling location map within the study area is shown in Map 3-2.
3.5.3 Land Use
Methodology Adopted for Land Use / Land Cover Study
Land Use and Land Cover classification methodology is described in Annexure 29. The project area was placed,
based on co-ordinates taken on the site, on satellite imagery and determined the study area for the proposed
project. The resulting satellite data of study area was interpreted through onscreen visual interpretation using basic
elements of interpretation resulting in the combined land use/cover map for the proposed project.
To accomplish the objective the following steps were undertaken:
Study and collection of relevant documents and maps
Interpretation of satellite data
Ground truth study/Field survey
Final map preparation
Study and Collection of Relevant Documents and Maps
This covers:
Downloading of remote sensing data using the licensed software, Google Earth Pro having high resolution
(<1.0 m) imagery.
Topographical maps as base map.
Reconnaissance survey of the study area to get a general feel of the entire ground area which can aid in the
preliminary interpretation of the data.
Interpretation of Satellite Data
The downloaded satellite imagery was imported to software and geo referencing of the imagery was done by
registering it to the SOI maps through identification of common points between the map and the image.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 67
Considering the basic elements of interpretation, such as tone, size, shape, texture, pattern, location, association,
shadow, aspect and resolution along with ground truth and ancillary information collected during the preliminary
reconnaissance survey, the interpretation was accomplished.
Ground Truth Studies/Field survey
A detailed ground truth study was carried out to check the accuracy of the interpreted data. It comprises of data
collection of ground features along with the respective geographical position in terms of latitudes and longitudes.
The aim of ground truth studies is to confirm whether the interpreted land use / cover are correct thus improving
the quality of the output. Interaction was done with local people to gather background information.
The field survey consisted of traversing the study area, cross-checking of unidentified features. Field notes were
kept in the form of log sheets recording information pertaining to co-ordinates, photographs and identified land
use/cover. Additional features identified or remarks made against existing interpretation were also recorded.
Table 3-6 & Photograph 3-2 enumerates the land features in the study area and its corresponding GPS readings
of all the ground truthing locations verified.
Table 3-6: GPS readings within Study Area
S. No. Latitude (N) Longitude (E) Location Classes
1 21°43’54.1’’ 72°36’57.3’’ Dahej Scrub, scattered Prosopis sp. and Canal along road
2 21°42’54.7’’ 72°37’03.1’’ Dahej Industrial Area
3 21°43’32.2’’ 72°37’08.5’’ Dahej Scrub and Canal along road
4 21°42’55.9’’ 72°39’19.7’’ Jolwa Village
5 21°40’48.6’’ 72°35’39.3’’ Ambetha Mudflat
6 21°44’03.0’’ 72°32’48.6’’ Dahej Along creek - Mangroves
7 21°47’09.5’’ 72°36’17.7’’ Padariya Grassland
8 21°45’55.6’’ 72°38’43.5’’ Kadodara Village
9 21°43’41.4’’ 72°38’01.3’’ Vadadala Wasteland
10 21°43’08.3’’ 72°41’41.5’’ Atali Grassland
Photograph 3-2: Various Land Cover of Study Area
Dahej Industrial area Scattered Prosopis and canal along the
road Dahej Industrial area
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 68
Mangroves along Creek at Dahej Mudflat
Class Wise Area Statistics
The area statistics of these classes are presented in Table 3-7.
Table 3-7: Area Statistics for Land Use / Land Cover Categories in the Study Area
S.
No.
Primary
Classification Secondary Classification
Area, Secondary Class Area, Primary Class
km2 Ha. ~% km2 Ha. ~%
1 Built-up Land or
Habitation
Residential / Commercial 3.3 334 1.0 21.2 2,124 6.2
Industrial 17.9 1,790 5.2
2 Agricultural Land Crop Land/Fallow Land 55.9 5,592 16.2
56.1 5,609 16.3
Plantation 0.2 17 0.1
3 Wastelands Land without Scrub 22.8 2,279 6.6
66.6 6,658 19.3 Mudflat 43.8 4,379 12.7
4 Water Bodies
Reservoir / Lakes / Ponds /
Tanks 3.4 342 1.0
55.5 5,547 16.1
River 52.1 5,205 15.1
5 Vegetation Cover
Scrub 60.5 6,051 17.5
100.7 10,067 29.2
Open Vegetation 22.4 2,240 6.5
Close Vegetation 4.3 426 1.2
Marshy Vegetation 1.9 193 0.6
Mangroves 11.6 1,157 3.4
6 Forest Area
Scrub (Forest) 1.4 137 0.4
5.1 508 1.5 Open Forest 1.3 127 0.4
Close Forest 2.4 244 0.7
7 Others
Salt Pans 38.2 3,822 11.1
40.1 4,005 11.6 Grass Cover 0.0 1 0.0
Creek 1.8 182 0.5
Total 345.18 34,518 100.0
Note: Roads, Railways, Canals are not calculated separately in area statistics
Pie chart of the landuse distribution in study area is shown in Figure 3-2.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 69
Figure 3-2: Pie Chart – Landuse of Study Area
Site History
As per discussion with MFL officials, the site was barren and having scrubs which was not in use for a long time.
Land was bought from farmers by GIDC, after which plotting was done. No history of previous owner was available
as on date for the survey numbers of the site. The proposed site was then taken by Meghmani Organics on
14/12/2006. It was transferred to Meghmani Finechem Limited 18/12/2007.
Conclusion
The most observed category in the region was agriculture followed by scrub as per area covered.
The proportional presence of different land uses and land cover in terms of statistical percentages is derived for the
study area. This concludes the land use identification and description of component of study.
List of Major Industries within Study Area
The list of major industries along with the type and name is provided in Table 3-8.
Table 3-8: List of Major Industries
S. N. Name Type of Industry
1 Meghmani Unichem Ltd. Pharmaceutical
2 Meghmani Chemtech Ltd. Pigment
3 Meghmani Organics Ltd. Agrochemical
4 Pidilite Industries Ltd. Pigment
5 M/s Neesa Infrastructure India Pvt. Ltd. Fabrication
6 DIC. Finnechemical Pvt. Ltd. Pigment
7 M/s Sarju Impex Ltd. Cylinder manufacturing
8 M/s Torrent Energy Ltd. Power
9 Firenish Aromatic Prod. Ltd. Perfumery and Flavour
10 Indofil Chemicals Company Fungicide
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 70
S. N. Name Type of Industry
11 Gujarat Floro Chemicals Ltd. Refrigerant Gas and Flourospeciality chemicals
12 Steerling Auxiaries Pvt. Ltd. Synthetic Organic Chemicals
13 Noicil Ltd. Rubber Chemicals and Rubber chemical Intermediates
14 Deepak Nitrat Ltd. Synthetic Organic chemicals
15 ONGC Petro Additions Ltd. Petrochemical
16 Pushpa Polymer Pvt. Ltd. Polymer
17 Hindalco Industries Ltd. Copper smelting
18 Hindustan Salts Ltd. Salt
19 Gujarat Chemical Port Terminal Company Limited Port and Stoarge Terminal
20 Rallis India Ltd. Fertilzers and Pesticides
21 Firmenta Biotech Ltd. Synthetic Organic Chemicals
22 Glenmark Pharma Ltd. Pharmaceutical
23 Torrent Pharmaceuticals Ltd. Pharmaceutical
24 LNG Dahej Gas Storage Terminal and Port
25 IPCL Reliance Ltd. Petrochemical
26 ABG Shipyard Ship Building Yard
27 Astral Biochem Alcohol and Derivatives
28 Bharat Rasayan Ltd. Insecticide
29 Gandhar Petrochemicals Petrochemical
30 Vishal Organic Synthetic Organic Chemicals
31 Panoli Intermediates Ltd. Synthetic Organic Chemicals and Pharmaceutical
32 Indocat Pvt. Ltd Additives and Catalysts
33 Sajjan India Ltd. Synthetic Organic Chemicals
34 Insecticides Ltd. Insecticide
35 Gujarat Polybutines Pvt. Ltd. Petrochemical
36 Borex Moraji Ltd. Boron
37 Mehta Petrochem Pvt. Ltd Petrochemical
39 Ronak Builwell Pvt. Ltd Infrastructure
40 Welspun Pipes Manufacturing
41 First Carbon Technologies Pvt. Ltd. Carbon distributor
42 Kaneria Granito Ltd Tiles Manufacturing
43 Sun Pharma Ltd. Pharmaceutical
44 M/s Siggachi Cellulos Pvt. Ltd Pharmaceutical intermediates
45 M/s P&G Cretechem Food Processing
Source: GIDC, Bharuch Office
Final Map preparation
The proportional presence of different land uses and land cover in terms of statistical percentages was derived for
the study area. Appropriate legends were used to represent the various categories of land use and land cover, and
were then written on the prepared land use and land cover maps. The image classified into the all classes for
different regions of interest are given in Map 3-3.
Important Features within the Study Area
There is no biosphere reserve, national park, and sanctuary within the study area. However, details of the
important features in the study area are provided in Table 3-9.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 71
Table 3-9: Important Feature within the Study Area
S.
No. Features
Name and Distance (Within 10 km of Study
Area unless otherwise mentioned)
1 Distance to Critically Polluted Areas from project site None
2 National Park/Wildlife Sanctuary None
3 Tiger Reserve/Elephant Reserve / Turtle Nesting Ground None
4 Core Zone of Biosphere Reserve None
5 Reserved / Protected / Social Forests Dahej Reserved Forest: 7.0 km towards W
Lakhigam Reserved Forest: 7.8 km towards WSW
6 Core Zone of Biosphere Reserves None
7 Habitat for migratory birds None
8 Estuary/Sea/Lakes/Reservoir/Dams/streams/River ~21 water bodies are located in the study area.
9 Inland, coastal, marine or underground waters Narmada Estuary: 3.8 km towards S
10 Mangroves Afforested Mangroves: 7.3 km towards WNW
11 Mountains/Hills None
12 Archaeological Sites (as per ASI) None
13 Defense Installation None
14 Industries Yes, since the proposed site is located in Industrial
Estate
15 Airports None
16 Railway Lines Dahej Railway Station: 2.4 km towards SW
17 National/ State Highway SH-165: 0.2 km towards S
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 72
Map 3-3: Land Use / Land Cover Map
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 73
3.5.4 Ambient Air Quality
Ambient Quality Monitoring was conducted at Eight (8) different locations within the study area.
Sampling Frequency
The frequency of monitoring was 24 hours twice a week at each station spread over the entire season.
Parameters Monitored and Methods Used
The parameters monitored were PM10, PM2.5, Sulphur Dioxide (SO2) & Nitrogen Oxides (NOx). The detailed
monitoring methodology for ambient air is given in Table 3-10.
Table 3-10: Methodology of Ambient Air Monitoring
Sampling
Parameters Sampling equipment
Analytical
Equipment
Sensitivity/Detection
Limit Methodology
PM10 Respirable Dust Sampler with
Cyclone & Flow measurement Electronic balance 10 µg/m3
Gravimetric IS: 5182
(Part 23) 2006
PM2.5 Fine Particulate Sampler Electronic Balance 2 µg/m3 Gravimetric
SO2 Gaseous Flow (Impinger with
TCM) with RDS Spectro photometer 3.7 µg/m3
Colorimetric IS: 5182:
(Part II) 2001
NOX
Gaseous Flow (Impinger with
Sodium Hydroxide (0.1 N)
Media) with RDS
Spectro photometer 6 µg/m3 Colorimetric IS: 5182:
(Part VI) 2006
Selected Sampling Stations
The locations for Ambient Air Quality Monitoring were decided based on the prescribed guidelines1. For this EIA, the
purpose is to ascertain the baseline pollutant concentrations in ambient air. Accordingly, the criterion was selected
to ascertain quality of air at important human settlements (residential areas).
Details of ambient air quality monitoring locations and justification for selecting these stations are presented in
Table 3-11 and Photograph 3-3.
Table 3-11: Ambient Air Quality Monitoring Location Details
Code Location Distance from Site
(Km) Direction Justification
AA01 At Project Site 0 - Core
AA02 At GLC Area (Nr. GACL – Plot 3) ~ 1.09 SW Downwind
AA03 At Vadadla Village ~ 1.4 NE Upwind
AA04 At Vadadla Crossing ~ 2.19 SE 1st Crosswind
AA05 Nr. Salt Pan Area ~ 3.2 NW 2nd Crosswind
AA06 Nr. Forest Area ~ 8.0 WSW Sensitive Area
AA07 At Vav Village ~ 4.13 NE 2nd Upwind
AA08 At Jolva Village ~ 3.75 E 3rd Crosswind
--------------------------------------------------------------------- 1 As per Guidelines for Ambient Air Quality Monitoring by CPCB, MoEF Published as SERIES: NAAQMS/ …/2003-04, April, 2013
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 74
Photograph 3-3: Photographs of AAQ Sampling Stations
At Vadadla Village At GLC Area (Nr. GACL – Plot 3)
At Jolva Village At Vav Village
Ambient Air Quality Results
Detailed results of AAQM are given in Annexure 32. Complied average data are represented in Table 3-12.
Table 3-12: Ambient Air Monitoring Results
Station
code
All stations are in
Industrial, Residential,
Rural & Other Areas
(CPCB)
Parameters & Results
Note: All units are in µg/m3. Figures in brackets are CPCB limits. Minimum
Reportable Readings are 8 µg/m3 for SO2, 10 µg/m3 for NOX.
PM10 PM2.5 SO2 NOX
(100) (60) (80) (80)
[24 Hours] [24 Hours] [24 Hours] [24 Hours]
AA1 At Project Site
Maximum 103 41 15.6 33.7
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 75
Station
code
All stations are in
Industrial, Residential,
Rural & Other Areas
(CPCB)
Parameters & Results
Note: All units are in µg/m3. Figures in brackets are CPCB limits. Minimum
Reportable Readings are 8 µg/m3 for SO2, 10 µg/m3 for NOX.
PM10 PM2.5 SO2 NOX
(100) (60) (80) (80)
[24 Hours] [24 Hours] [24 Hours] [24 Hours]
Minimum 65 26 8.0 10.6
Average 82 33 9.8 17.3
AA2 At GLC Area
Maximum 110 63 15.6 36.5
Minimum 50 21 8.0 10.6
Average 74 30 9.5 18.0
AA3 At Vadadla Village
Maximum 112 50 9.8 21.4
Minimum 54 21 <8.0 13.0
Average 86 35 8.3 17.1
AA4 At Vadadla Crossing
Maximum 123 63 14.6 36.5
Minimum 52 25 <8.0 16.2
Average 96 38 10.0 24.5
AA5 Nr. Salt Pan Area
Maximum 68 32 10.2 28.6
Minimum 42 15 <8.0 10.2
Average 57 25 8.2 16.5
AA6 Nr. Forest Area
Maximum 72 37 9.1 21.7
Minimum 47 22 <8.0 <10
Average 63 29 8.2 17.2
AA7 At Vav Village
Maximum 107 27 10.4 25.3
Minimum 26 6 8.0 14.7
Average 68 16 8.8 19.4
AA8 At Jolwa
Maximum 102 25 10.3 23.4
Minimum 17 8 8.0 14.7
Average 61 18 8.9 18.6
The comparison of the results with the permissible limits provided by CPCB (Ref. Annexure 27) indicates:
Average concentration of PM10 recorded ranged from minimum 42 µg/m3 (Nr. Salt Pan Area) to maximum 123
µg/m3 (At Vadadala Crossing);
Average concentration of PM2.5 recorded raged from minimum 15 µg/m3 (At Salt Pan Area) to maximum 63
µg/m3 (At Vadadala Crossing);
It is noted that the PM10 results exceeds the permissible limits of 100 µg/m3 for 24 Hrs. at all the locations
except Nr. Salt pan and Nr. Forest Area which could be due to:
Industrial & infrastructure development activities in study area (PCPIR & residential projects);
Influence of windy conditions in coastal area;
Vehicular movement on the “kaccha” roads of the villages;
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 76
Rural activities like burning of cow dung for household purposes like using it in “chullas”.
The concentration of SO2 (8.0 – 15.6 µg/m3) & NOx (10.0 – 36.5 µg/m3) are within permissible limits as
prescribed by CPCB.
Traffic Survey
Traffic Survey was carried out on SH – 6 in S direction of the proposed site, road connecting site to Dahej &
Bharuch on 14th July, 2017. The road width of this road is 15 meters, which is a 3 Lane (One Way) Arterial Road2.
Peak hours are considered from 08:00 – 12:00 Noon and 16:00 – 20:00 Hours. Average peak hourly traffic on this
route i.e. from Bharuch to Dahej and from Dahej to Bharuch is 531 and 570 PCU respectively as tabulated in Table
4-9 and Table 4-10.
Traffic Survey sheets are given in Annexure 35.
Stack Monitoring
Stack emissions, for the parameters as prescribed in latest Gujarat State Pollution Control Board’s Consent to
Operate and Authorization, were monitored for 2 flue gas stacks and 3 stacks attached to process vents.
It was found that all the parameters are well within the prescribed standards.
Monitoring results were compared with Latest Audit Report and past (latest available) GPCB’s monitoring data. No
abnormal emissions were reported in secondary data. Details of these results are given in Table 3-13 and Table
3-14.
Table 3-13: Flue Gas Stack Monitoring Results
S
No.
Stack
Attached to
Monitoring Agency
(Date)
Parameters (Units as mentioned in GPCB Limit, unless
mentioned)
SPM Sulphur Dioxide
(SO2)
Oxide of Nitrogen
(NOx)
GPCB
Limit Results
GPCB
Limit Results
GPCB
Limit Results
1
Boiler of
Captive Power
Plant – 1
Audit Report, 2016
(Range) 50 mg/Nm3
21 – 61 100
ppm
22.4 –
104 50 ppm
24.4 - 64
GPCB (08.04.2015) 21 2.28 11.83
Kadam (05.12.2016) 35 18 24
2
Boiler of
Captive Power
Plant – 2
Audit Report, 2016
(Range) 50 mg/Nm3 17 – 57 100
ppm
33 – 92 50 ppm
19 – 52.12
Kadam (06.12.2016) 55 21 36
Table 3-14: Process Vents/Stacks Monitoring Results
S
No.
Stack
Attached to Monitoring Agency (Date)
Parameters (Units as mentioned in GPCB Limit, unless
mentioned)
HCl Cl2
GPCB Limit Results GPCB Limit Results
1
Reactor of
Hypo Plant and
De-Chlorination
System
Audit Report, 2016 (Range)
20 mg/Nm3
0.56 – 9.33
9 mg/Nm3
2.30 – 3.69
GPCB (08.04.2015) NA 0.2
Kadam (06.12.2016) 2.74 0.9
2 Reactor of HCl Audit Report, 2016 (Range) 20 mg/Nm3 3.12 – 7.47 9 mg/Nm3 BDL
--------------------------------------------------------------------- 2 As per The Indian Road Congress - Guideline for capacity of roads in urban Area. (IRC:106-1990), Table-2, Recommended Design
Service Volumes, page – 11.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 77
S
No.
Stack
Attached to Monitoring Agency (Date)
Parameters (Units as mentioned in GPCB Limit, unless
mentioned)
HCl Cl2
GPCB Limit Results GPCB Limit Results
Synthesis GPCB (08.04.2015) 1.54 BDL
Kadam (06.12.2016) 7.56 0.24
3 Reactor –
Flakers plant
Audit Report, 2014 (Range) 20 mg/Nm3
NA 9 mg/Nm3
NA
Kadam (06.12.2016) 1.24 0.56
NA – Not Available
Workplace Monitoring
MFL is carrying out work place monitoring at various locations of the plant at regular intervals. The monitoring
reports of the same are given in Table 3-15.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 78
Table 3-15: Results – Work Place Monitoring
S. N. Place / Location Date of
Monitoring Monitoring Agency
Parameter, Limit & Results in µg/m3
PM10 PM2.5 SO2 NOx HCl Cl2 Hydrocarbon
100 60 80 80 200 100 160
1 Nr. Admin Building
19.12.2016 Supreme Envirocare, Ahmedabad 30.9 26 16.4 20.5 5.2 4.6 ND
03.01.2017 Supreme Envirocare, Ahmedabad 35.9 28 14 10.5 5.2 2.4 ND
04.08.2017 SAL College of Engineering, Ahmedabad 50.26 26.7 14.31 15.38 - - -
2 Terrace of Admin Building 03.08.2017 Excel Enviro tech, Ahmedabad 56.84 28.96 13.22 16.99 ND ND ND
3 Nr. Canteen Area 04.08.2017 SAL College of Engineering, Ahmedabad 29.31 13.52 15.18 19.33 - - -
05.08.2017 Excel Enviro tech, Ahmedabad 56.34 27.11 8.88 11.14 ND ND ND
4 Near Power Plant 03.08.2017 Excel Enviro tech, Ahmedabad 69.57 33.24 26.87 20.44 3.24 5.99 1.05
5 Packing Section Area 19.12.2016 Supreme Envirocare, Ahmedabad 35.3 29.2 18 22 2.6 4.2 ND
04.01.2017 Supreme Envirocare, Ahmedabad 39.5 27 19.2 10 4.9 2.5 ND
Detailed workplace monitoring sheet is attached as Annexure 28.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 79
3.5.5 Noise
The objective of noise level monitoring in study area is to establish baseline noise level to identify impact due to
proposed project activities.
Monitoring Methodology for Noise Level
Monitoring of noise is done by identifying suitable number of noise quality monitoring locations. Background noise
quality is monitored in dB (A) Leq(d) and dB (A) Leq(n) at the selected locations.
Methodology for monitoring of noise levels is given in Table 3-16.
Table 3-16: Monitoring Methodology
Env.
Component
Sampling
location Sampling Frequency Methodology
Sample collection Sampling
Parameter Sampling
equipment Detection Limit
Ambient
Noise
5
Locations
Once during the study
(Hourly reading for 24
hours at each location)
Sound Level
Measurement
(SLM)
Noise Level
Meter 0.1 dB (A)
Decibels –
dB (A)
Standards for Ambient Noise level
Standards for Ambient Noise level as per CPCB guidelines are given Table 3-17.
Table 3-17: Standards for Ambient Noise Level
Ambient Air Quality Standards in
Respect of NOISE
Area
Code Category
Limits in dB(A) Leq*
Day Time Night Time
THE NOISE POLLUTION
(REGULATION AND CONTROL) RULES,
2000
A Industrial 75.0 70.0
B Commercial 65.0 55.0
C Residential 55.0 45.0
D Silence 50.0 45.0
Note: Day Time: 6:00 AM to 10:00 PM; Night Time: 10:00 PM to 6:00 AM
dB (A) Leq*: denotes the TWA of the level of sound in decibels on scale A which is relatable to human hearing.
Noise Level Monitoring Locations
Locations selected for Noise Level monitoring are presented in Photograph 3-4. Noise monitoring location is given
in Table 3-18 and Map showing monitoring location is shown in Map 3-4.
Table 3-18: Noise Level Monitoring Locations
Station
Code Noise Monitoring Location
Date of
Monitoring
Category
Area/Zone
Distance
wrt site in
km
Direction
w.r.t Project
Site
Rationale
NL1 Nr Security gate (At Site) 15.02.17 Industrial -- --
Source of Noise NL2 At project site (NW) 15.02.17 Industrial -- --
NL3 Near Cooling Tower (At Site) 16.02.17 Industrial -- --
NL4 Near Utility area (At Site) 16.02.17 Industrial -- --
NL5 Vadadala village 18.02.17 Residential 1.83 NE
Major habitation
within 3 Km of
source of noise
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 80
Map 3-4: Map showing Noise Monitoring Locations
Photograph 3-4: Noise Level Monitoring Locations
At Cooling Tower Nr. Utility Area
Noise Level Results
Noise readings were taken at Five (5) different locations within the study area including existing plant unit. The
average noise level for study area are tabulated Table 3-19.
Table 3-19: Noise Level Monitoring Results
Location
Code Location
Category
Area/Zone
CPCB Limits in dB (A) Average Noise levels in dB (A)
Day Time Night Time Day Time Night Time
NL1 Nr Security gate Industrial 75.0 70.0 65.2 55.9
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 81
Location
Code Location
Category
Area/Zone
CPCB Limits in dB (A) Average Noise levels in dB (A)
Day Time Night Time Day Time Night Time
NL2 At project site (NW) Industrial 75.0 70.0 64.7 56.0
NL3 Near Cooling Tower Industrial 75.0 70.0 72.5 64.5
NL4 Near Utility area Industrial 75.0 70.0 71.3 62.7
NL5 Vadadala village Residential 55.0 45.0 54.4 44.4
Observation
Noise level during day time and nighttime, in Industrial area was observed within the CPCB standards i.e.
industrial area (75 dBA (d) & 70 dBA (n)).
Noise level during daytime and nighttime, in Residential area was observed within the CPCB standards i.e.
residential area (55 dBA (d) & 45 dBA (n)).
3.5.6 Hydrology and Ground Water
Hydrology
Sources of Water
The source of raw water in the study area includes the following:
Pond / Lake
Ground Water
River Water
Analysis Methodology
The samples were collected as grab samples, from each location, once during the study period and the analysis
methodology is given in Table 3-20.
Table 3-20: Analysis Methodology of Ground Water and Surface Water
S. No Parameters Methodology
Parameters
Analyzed in
Ground and
Surface water
Samples
Parameters
Analyzed in
River water
samples
Minimum
Detection
Limit
1 pH APHA: 4500-H+ B(22nd Edition), pH meter √ √ 1
2 Color APHA: 2120 (22nd Edition), Visual
Comparison √ 1 Pt-Co
3 Temperature APHA: 2550 B (22nd Edition), Standard
Thermometer √ 1 Deg C
4 Turbidity APHA: 2130 B (22nd Edition), Nephelometric √ 4 NTU
5 TDS APHA: 2540C (22nd Edition), Gravimetric √ √ 20 mg/l
6 Electrical
conductivity
APHA: 2510 B (22nd Edition), Conductivity
meter √ √ 1µmoh/cm
7 COD APHA: 5220 B (22nd Edition), Titrimetric
Open reflux method √ <5 mg/l
8 BOD IS: 3025(part-44), Iodometric √ √ <3 mg/l
9 Chlorides APHA:4500Cl- B (22nd Edition) ,
Titrimetric √ √ 1.5 mg/l
10 Phenol APHA: 5530-D(22nd Edition), colorimetric √ 0.001 mg/l
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 82
S. No Parameters Methodology
Parameters
Analyzed in
Ground and
Surface water
Samples
Parameters
Analyzed in
River water
samples
Minimum
Detection
Limit
11 Sulphates APHA:4500-E as SO4 2-(22nd Edition),
Turbid metric √ √ < 1 mg/l
12 Total Hardness APHA: 2340-C (22nd Edition),
Titrimetric(EDTA method) √ √ < 10 mg/l
13 Ca++
Hardness
APHA: 3500-B-Ca (22nd Edition)
Titrimetric,(EDTA method) √ √ < 4 mg/l
14 Mg++
Hardness
APHA: 3500-B-Mg (22nd Edition), By
difference √ √ 8 mg/l
15 Total Alkalinity APHA: 2320 B (22nd Edition), Titrimetric √ <10 mg/l
16 Nitrate IS:3025 (part-34),3.3 , colorimetric √ √ <0.1 mg/l
17 Fluoride APHA:4500 F-D(22nd Edition),Colorimetric √ √ <0.1 mg/l
18 Sodium APHA:3500 Na-B (22nd Edition), Flame
emission Photometric √ <1 mg/l
19 Potassium APHA: 3500 K-B (22nd Edition) Flame
emission Photometric √ <1 mg/l
20 Calcium APHA Edition 22 (3500 Ca- B) Titrimetric
(EDTA Method) √ 1 mg/l
21 Magnesium APHA Edition 22 (3500 Mg- B), by difference √ 3 mg/l
22 Salinity APHA: 2520 B (22nd Edition), Electrical
Conductivity method √ -
23 Total Nitrogen APHA: 4500 N Org, Micro Kjeldhal Distillation
(22nd Edition), Titrimetric √ 0.06 mg/l
24 Total
Phosphorous APHA: 4500 P-C (22nd Edition), colorimetric √ <1 mg/l
25 Dissolved
Oxygen APHA: 4500O-C(22nd Edition), Iodometric √ √ 0.5 mg/l
26 Ammonical
Nitrogen
APHA: 4170-B (22nd Edition) / IS:3025(part-
34), 1988, Distillation and colorimetric √ √ <0.01 mg/l
27 SAR Flamephotmetric and EDTA method √ √ -
28 Heavy Metals - - -
a Arsenic (as As) APHA: 3500-As-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition) √ √ <0.002 mg/l
b Cadmium (as
Cd)
APHA: 3500-Cd-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition √ √ <0.003 mg/l
c Chromium (as
Cr) APHA: 3500-Cr-B(22nd Edition), colorimetric √ √ <0.003 mg/l
d Copper (as Cu)
APHA: 3500-Cu-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition)
IS:3025(part42):1992
√ √ <0.05 mg/l
e Cyanide (as
CN)
APHA: 4500 CN- D & E(22nd Edition),
colorimetric √ √ 0.003 mg/l
f Iron (as Fe) APHA: 3500-Fe-B (22nd Edition), colorimetric √ √ <0.1 mg/l
g Lead (as Pb) APHA: 3500-Ld-A (22nd Edition) / APHA: √ √ <0.01 mg/l
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 83
S. No Parameters Methodology
Parameters
Analyzed in
Ground and
Surface water
Samples
Parameters
Analyzed in
River water
samples
Minimum
Detection
Limit
3111-B(AAS)(22nd Edition)
h Mercury (as
Hg)
APHA: 3500-Hg-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition) √ √ <0.001 mg/l
i Manganese (as
Mn)
APHA: 3500-Mn-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition) √ √ <0.04 mg/l
j Nickel (as Ni) APHA: 3500-Ni-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition √ <0.02 mg/l
k Zinc (as Zn) APHA: 3500-Zn-A (22nd Edition) / APHA:
3111-B(AAS)(22nd Edition) √ √ <0.08 mg/
l Boron (as B) APHA: 4500 B-C (22nd Edition), colorimetric √ <0.02 mg/l
29 Total Coliform APHA: 9221-B (22nd Edition), Multiple Tube
Fermentation √ √ 1.8 MPN/100ml
30 Fecal Coliform APHA: 9221-E (22nd Edition), Multiple Tube
Fermentation √ 1.8 MPN/100ml
Surface Water Sampling
Surface water samples were collected from Eight (8) different locations within the study area and they are given in
Table 3-21. Sampling locations are shown in Map 3-2, Photographs of sampling location is given in Photograph
3-5.
Table 3-21: Surface Water Sampling Location (Pond and River)
Code Location Date of
Sampling Source
Distance
from Project
Site in Km
Direction
w.r.t
Project Site
Justification
SW 1 Jolwa 20.01.2017 Pond 3.6 ESE To check the water quality of
stagnant water body SW 2 Vav 20.01.2017 Pond 4.5 NE
SW 3 Kadodara 20.01.2017 Pond 3.5 NE
SW 4 Vadadla 20.01.2017 Pond 1.8 ENE To check the water quality of at
Downstream direction SW 5 Dahej 20.01.2017 Pond 2.6 WSW
SW 6 Rahiyad 20.01.2017 Pond 6.4 ESE To check the water quality of at
Upstream direction
SW 7 Narmada River
(D/s) nr. Ambetha 20.01.2017 Estuary 4.3 SSW
To check the water quality of
stagnant water body
SW 8 Narmada River
(U/s) nr. Koliyad 20.01.2017 Estuary 9.1 ESE
To check the water quality of
flowing water body
Photograph 3-5: Surface Water Sampling Locations
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 84
Vadadla Pond Kadodara Pond
Vav Pond Jolwa Pond
Surface water results for ponds and river (estuary) are tabulated in Table 3-22 & Table 3-24.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 85
Table 3-22: Surface Water Analysis Results
S. No.
Parameters Unit
Classification of Water Sample Details
SW1 (Jolva) SW2 (Vav) SW3 (Kadodara) SW4 (Vadadla) SW5 (Dahej) SW6 (Rahiyad)
A B C D E Pond Pond Pond Pond Pond Pond
20.01.2017 20.01.2017 20.01.2017 20.01.2017 20.01.2017 20.01.2017
1 pH pH Scale 6.5 to 8.5 6.5 to 8.5 6.0 to 9.0 6.5 to 8.5 6.5 to 8.5 7.36 7.29 7.29 7.43 7.33 7.75
2 Total Dissolved Oxygen mg/l 6 5 4 4 NS 3.8 3.6 4.2 3.2 3.9 7.75
3 Total Dissolved Solids mg/l 500 NS 1500 NS 2100 1,352 568 812 720 324 776
4 Electrical Conductivity μmhos/cm NS NS NS 1000 2250 2122 686 1092 1035 548 984
5 BOD mg/l 2 3 3 NS NS 13 10 20 8 12 15
6 Total Hardness mg/l 300 NS NS NS NS 200 320 320 320 270 380
7 Ca++ Hardness mg/l 200 NS NS NS NS 188 194 100 80 114 92
8 Mg++ Hardness mg/l 100 NS NS NS NS 12 126 220 240 156 288
9 Copper mg/l 1.5 NS 1.5 NS NS <0.05 <0.05 <0.05 <0.05 <0.05 <0.05
10 Iron mg/l 0.3 NS 50 NS NS <0.1 <0.3 <0.3 <0.3 <0.3 <0.3
11 Manganese mg/l 0.5 NS NS NS NS <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
12 Chlorides(as CL) mg/l 250 NS 600 NS 600 692 102 270 251 86 211
13 Sulphates mg/l 400 NS 400 NS 1000 70 64 57 60 15 46
14 Nitrate (as NO3) mg/l 20 NS 50 NS NS 13.6 13.9 23.35 9.28 11.85 5.5
15 Fluoride mg/l 1.5 1.5 1.5 NS NS 0.79 0.74 0.83 0.75 0.36 0.39
16 Phenolic Compound mg/l 0.002 0.005 0.005 NS NS <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
17 Mercury mg/l 0.001 NS NS NS NS <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
18 Cadmium mg/l 0.01 NS 0.01 NS NS <0.03 <0.03 <0.03 <0.03 <0.03 <0.03
19 Arsenic mg/l 0.05 NA 0.2 NS NS <0.002 <0.002 <0.002 <0.002 <0.002 <0.002
20 Cyanide mg/l 0.05 0.05 0.05 NS NS <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
21 Lead mg/l 0.1 NS 0.1 NS NS <0.01 <0.01 <0.01 <0.01 <0.01 <0.01
22 Zinc mg/l 15 NS 15 NS NS <0.08 <0.08 <0.08 <0.08 <0.08 <0.08
23 Chromium mg/l 0.05 1 0.05 NS NS <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
24 Sodium Absorption Ratio mg/gm NS NS NS NS 26 10.29 0.59 2.64 4.27 0.39 0.33
25 Total Coliform MPN/100ml 50 500 5000 NS NS 170 78 330 110 170 170
NS: Not Specified, NR: No Relaxation
Classification of river water as per their intended use is described in given in Table 3-23.
Table 3-23: Classification of Water
S. No. Class Intended Use
1 A Drinking water source without conventional treatment but after disinfection
2 B Outdoor bathing (organized)
3 C Drinking water source with conventional treatment followed by disinfection
4 D Propagation of wild life, fisheries
5 E Irrigation, industrial cooling etc.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 86
Table 3-24: Analysis Result of River (Estuary) Water Samples
S. No. Parameters Unit Classification for Coastal Water Marine (CPCB)
Sampling Locations
SW7 SW8
Narmada Estuary (D/s)
Nr. Ambetha
Narmada Estuary (U/s)
Nr. Koliyad SW-I SW-II SW-III SW-IV SW-V
1 pH - 6.5 to 8.5 6.5 to 8.5 6.5 to 8.5 6.0 to 9.0 6.0 to 9.0 7.55 7.73
2 Total Dissolved Oxygen mg/l 5.0 4.0 3.0 3.0 3.0 4.1 4.0
3 Colour and Odour - No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
4 Floating Matters mg/l None None None 10 - None None
5 Suspended Solids mg/l None from Sewage or
Industrial waste Origin - - - - 30 27
6 Turbidity NTU - 30 30 - - 2.5 2.3
7 BOD mg/l - 3 - 5 - 4 5
8 Oil and Grease
(including Petroleum Products) mg/l 0.1 - - - - <0.4 <0.4
9 Mercury (as Hg) mg/l 0.001 - - - - <0.001 <0.001
10 Lead (as Pb) mg/l 0.001 - - - - <0.01 <0.01
11 Cadmium (as Cd) mg/l 0.01 - - - - <0.001 <0.001
12 Dissolved Iron (as Fe) mg/l - - 0.5 - - <0.1 <0.1
13 Dissolved Manganese (as Mn) mg/l - - 0.5 - - <0.04 <0.04
14 Faecal Coliform ml (MPN) - 100/100 500/100 500/100 500/100 310 170
15 Sludge Deposits, Solid refuse floating
Solids, Oil Grease and Scum - - - - -
None except for treated
Sewage and Industrial
waste Effluent
None None
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 87
Quality of Surface Water
It is observed that:
Parameters such as BOD, Total Hardness, Mg++ Hardness crossed the prescribed limits in all sample while
Chlorides exceeded the limit only at Jolva Pond, there by requiring necessary treatment if utilized for drinking
purposes;
Pond water of Jolwa, Vadadla & Kadodara can be used for Propagation of wild life, fisheries;
Pond water of Vav, Dahej & Rahiyad can be used for irrigation and industrial activities;
The quality of Narmada Estuary falls with Class SW-I as per coastal water marine standards.
Ground Water
Sample was collected from Eight (8) different locations to find ground water quality within study area which is
shown in Table 3-25. Analysis Methodology of Ground Water is given in Table 3-20.
Table 3-25: Ground Water Sampling Locations
Code Location Source Date of
Sampling
Distance from
Project Site in
Km
Direction
w.r.t Project
Site
Justification
GW 1 Jolwa Bore well 06.02.2017 1.57 SW To check groundwater quality
within study area.
GW 2 Vadadla Bore well 06.02.2017 3.01 West To check groundwater quality
within study area.
GW 3 Vav Bore well 06.02.2017 3.42 NW To check groundwater quality
within study area.
GW 4 Galenda Bore well 06.02.2017 2.12 NE To check groundwater quality
within study area.
GW 5 Atali Bore well 06.02.2017 4.16 E To check groundwater quality
within study area.
GW 6 Rahiyad Bore well 06.02.2017 3.00 SE To check groundwater quality
within study area.
GW 7 Lakhigam Bore well 06.02.2017 7.00 SW To check groundwater quality
within study area.
GW 8 Dahej Bore well 06.02.2017 3.00 SW To check groundwater quality
within study area.
Sampling location map is shown in Map 3-2. Photographs of Groundwater sampling is shown in Photograph 3-6.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 88
Photograph 3-6: Groundwater Sampling Locations
Bore well at Galenda Village Bore well at Rahiyad Village
Bore well at Vadadla Village Bore well at Jolwa Village
Bore well at Atali Village Bore well at Vav Village
Ground water analysis results of collected samples is given in Table 3-26.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 89
Table 3-26: Analysis Results of Groundwater Samples
Sampling Location Jolwa Vadadla Vav Galenda Atali Rahiyad Lakhigam Dahej
S.
No. Parameters Unit
IS 10500 Standard Limits for
drinking water GW1 GW2 GW3 GW4 GW 5 GW 6 GW 7 GW 8
Acceptable
limit
Permissible
limit Bore well Bore well Bore well Bore well Bore well Bore well Bore well Bore well
1 pH pH scale 6.5-8.5 NR 7.32 7.70 7.45 7.50 7.55 7.67 7.98 7.88
2 Temperature oC - - 30 29 29 29 29 29 30 30
3 Turbidity NTU 1 5 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
4 TDS mg/lit 500 2,000 1,132 656 812 384 1,168 1,028 274 845
5 Electrical
conductivity µmho/cm - - 1,900 1,214 1,324 710 2,200 1,812 415 1,417
6 COD mg/lit - - <2 <5 <5 <5 <5 <5 <2 <2
7 BOD mg/lit - - <4 <3 <3 <3 <3 <3 <4 <4
8 Phenol mg/lit 0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
9 Chlorides mg/lit 250 1,000 453 169 256 67 333 362 72 265
10 Sulphates mg/lit 200 400 34 183 115 3 182 123 4 67
11 Total Hardness mg/lit 200 600 290 180 220 340 350 480 200 340
12 Ca++ Hardness mg/lit - - 176 26 64 72 136 108 54 70
13 Mg++
Hardness mg/lit - - 114 154 156 268 155 170 146 270
14 Total Alkalinity mg/lit 200 600 110 180 130 140 150 180 240 220
15 Nitrate mg/lit 45 NR 38.87 3.5 23.8 23.8 73.9 58.0 9.66 38.1
16 Fluoride mg/lit 1 1.5 2.27 0.93 1.33 0.41 0.70 0.79 0.71 0.71
17 Sodium mg/lit - - 221.7 75 165 15.4 214 235 35.2 132.4
18 Potassium mg/lit - - 11.3 10 15.6 23.6 16.5 10 7.80 15.6
19 Calcium mg/lit 75 200 70.54 10.4 128.2 28.8 54.5 43.3 21.64 28.06
20 Magnesium mg/lit 30 100 27.7 37.4 37.9 65.1 52.0 90.4 35.48 65.61
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 90
Sampling Location Jolwa Vadadla Vav Galenda Atali Rahiyad Lakhigam Dahej
S.
No. Parameters Unit
IS 10500 Standard Limits for
drinking water GW1 GW2 GW3 GW4 GW 5 GW 6 GW 7 GW 8
Acceptable
limit
Permissible
limit Bore well Bore well Bore well Bore well Bore well Bore well Bore well Bore well
21 Salinity mg/lit - - 816.65 304 460 122 599 651 130.32 477.83
22 Total Nitrogen mg/lit 0.5 NR 8.94 0.79 4.70 4.42 17.45 13.96 2.39 8.96
23 Total
Phosphorous mg/lit - - <1 <1 <1 <1 <1 <1 <1 <1
24 Dissolved
Oxygen mg/lit - - 2.7 4.0 3.2 3.5 3.4 3.2 2.3 2.9
25 Ammonical
Nitrogen mg/lit NS NS <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
26 SAR - - - 5.64 2.4 3.28 0.36 3.6 3.36 1.08 3.11
27 Heavy Metals
a Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.002 <0.002 <0.002 <0.002 <0.002 <0.01 <0.01
b Cadmium (as
Cd) mg/l 0.003 NR <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
c Chromium (as
Cr) mg/l 0.05 NR <0.05 <0.003 <0.003 <0.003 <0.003 <0.003 <0.05 <0.05
d Copper (as Cu) mg/l 0.05 1.5 <0.03 <0.05 <0.05 <0.05 <0.05 <0.05 <0.03 <0.03
e Cyanide (as
CN) mg/l 0.05 NR <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
f Iron (as Fe) mg/l 0.3 NR <0.05 <0.1 <0.1 <0.1 <0.1 <0.1 <0.05 <0.05
g Lead (as Pb) mg/l 0.01 NR <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01
h Mercury (as
Hg) mg/l 0.001 NR <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
i Manganese (as
Mn) mg/l 0.1 0.3 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
j Nickel (as Ni) mg/l 0.02 NR <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 91
Sampling Location Jolwa Vadadla Vav Galenda Atali Rahiyad Lakhigam Dahej
S.
No. Parameters Unit
IS 10500 Standard Limits for
drinking water GW1 GW2 GW3 GW4 GW 5 GW 6 GW 7 GW 8
Acceptable
limit
Permissible
limit Bore well Bore well Bore well Bore well Bore well Bore well Bore well Bore well
k Zinc (as Zn) mg/l 5 15 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08
28 Total Coliform MPN/100ml Shall not be detectable
in any 100 ml sample Absent Absent Absent Absent Absent Absent Absent Absent
29 Faecal
Coliforms MPN/100ml
Shall not be detectable
in any 100 ml sample Absent Absent Absent Absent Absent Absent Absent Absent
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 92
Quality of Ground Water
This aquifer is in the close proximity of sea. The aquifer comprises of saline water containing high TDS. Only those
wells which are located near the surface water bodies are yielding relatively good quality water. Dilution in water
quality is likely after monsoon. Fluorides also observed above the permissible limit in Jolva, village. The saline water
yielded from wells is used for domestic purposes other than drinking water.
3.5.7 Geological Environment
Methodology
The methodology adopted for the study of baseline environment started with desk study followed by secondary
data collection. Secondary data like recent Google imagery, District Resource Map, information published by GSI
studies, to collect basic information on Geology, Hydrogeology, aquifers, identification of Topography and Structural
features of site and surrounding area.
A field visit was conducted to study site specific geological and hydrogeological conditions includes lithology,
drainage patterns, water bodies, ground water condition and any possible impact to the environmental setting due
to project.
Regional Geology
A concise description of Geology is given by Geological Survey of India is given in Table 3-27.
Table 3-27: Regional Geology
Formation / Group Lithology Geological Age
Younger alluvium Soils and blown sand Holocene
Older Alluvium Highly weathered red colored Alluvium with kanker and calc crusts Pleistocene
Jhagadia Formation Agate conglomerate Pliocene to Middle Miocene
Kand Formation Clay, marl, Limestone, Sandstone, siltstone and conglomerate Lower Miocene
Babaguru Formation Ferruginous sandstones, Clay pebbly sandstone and conglomerate -
Tarakeshwar Formation Bentonite clay, clay stone and sandstone Lower Eocene to Oligocene
Nummulite Formation Argillaceous Limestone and clay with Nummulite Lower to Upper Eocene
Vadadkhol Formation Clay Friable sandstone pebbly sandstone and Conglomerate Lower Eocene
Deccan Volcanics Basics Dykes, Plugs Rhyolite and Basalt etc. Upper Cretaceous to Eocene
Bagh Beds Sandstone, limestone and clay Middle to Upper Cretaceous
Geology of the project site
Dahej GIDC is located on west of Bharuch at Gulf of Khambhat. Topographically, the area is almost flat with gentle
slope toward west to southwest i.e. toward Gulf. Geologically, entire area is covered with recent age deposits of
fluvial and marine origin. Major part of the study area is covered with gray to yellow colored silty loam.
Topography and Geomorphology
Topographically, the entire area is almost flat with gentle dipping toward west. Geomorphologic ally, coastal area is
covered by tidal and mud flats. Drainages have acquired a pattern of deltaic condition.
Hydro geological conditions
Owing to geological conditions, the Groundwater is saline and only used for general purpose. The formation is
having low storativity since it is made up of fine sand and silt thus supply will always be limited. As per discussion
with local people and well owners, depth to water level, within study area is 8 to 10 m and total depth of wells
ranging from 15 to 20 m. Drinking water is supplied by tankers or pipe lines in most of the villages at vicinity of
GIDC and SEZ area.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 93
In past, most of the wells located near the surface water bodies like pond, streams were in use for drinking
purpose. After commencement of water supply for drinking purpose from Narmada canal/pipeline these became
redundant.
Seismicity of the study area
Gujarat is categorized in the seismic zone III as shown in the Maps 3-1, which is classified as having a fairly high
probability of earthquake shocks measuring 5 or 6 on the Richter scale, low probability of shocks of 6 or 7 on the
Richter scale.
Maps 3-1: Seismic Map of Gujarat
Source: www.gujarat.earthquake.gov.in
3.5.8 Soil
Objectives
To identify physical and chemical properties of soils
To identify soil pollution and suggest mitigation measures
To give monitoring plan for improving soil quality
Methodology
A field visit was conducted to study site-specific existing soil quality and conditions which includes soil color,
texture, mineralogical content and plasticity in order to identify the possible impact on the environmental setting
after the proposed project.
Regional Soil profile
The project area falls under South Gujarat Agro-climatic Zone II and Agro-ecological region-21.The annual average
rain fall is 985 mm. The soils are predominantly of trap origin deep black soils (63%), however coastal black (14%)
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 94
and loam soils (23%) are also present. Taxonomically these soils are classified as Vertisols. The soils at the GIDC
site are also clayey having very high water holding capacity and porosity, but permeability is very low. The soil
depth is > 100 cm and soil slope is 1-3 %. The average rainfall received in the area is around 700-800 mm. As the
area is in the proximity of sea, waters and soils are likely to be saline/alkaline. The ground water table is around 7-
8 m, indicating that ground water recharge is not feasible. The main source of water is Narmada canal as bore
wells are not feasible in the GIDC. The crops of the surrounding areas are paddy, cotton and sugarcane and in
winter sorghum and wal are grown. The cropping intensity of the area is 117%.
Soil sample collection Methodology
The locations for soil sample collection were randomly selected. The soil samples from 0-15 cm depth were
collected by using spade and pawada. The samples were homogenized and about 1 Kg soil sample was collected in
the polythylene bag, labeled with sample ID which includes site numbers and project name. The samples were
brought to the laboratory for analysis of physical (porosity, water holding capacity, permeability, particle size
distribution and chemical properties (cation exchange, electrical conductivity, sodium adsorption ratio, pH, Ca, Mg,
Na, K).
Analysis Methodology
Soil analysis methodology is given Table 3-28.
Table 3-28: Analysis Methodology of Soil
Sampling Parameters Sample
collection Analytical Equipment Methodology Remarks
Porosity
Manual
sample
collection
using
hammer and
container
tube for
collecting
undisturbed
top soil.
- IS: 2720 Part 7
Trial pit method for
topsoil sample collection;
disturbed samples
Water holding capacity Keen Apparatus HMSO, UK
Permeability - IS: 2720 Part 17
Moisture content Electronic Balance IS: 2720 Part 2
Texture - IS: 2720 Part 4
Particle size Distribution Glass wares IS: 2720 Part 4
5% Leachate to be made
and analyzed as per
APHA, “Standard
Methods”
All method numbers are
as per APHA “Standard
Methods” (21st edition,
2005)
Cation Exchange Capacity Centrifuge IS: 2720 Part 24 (1976)
SAR F. Photometer (Na, K)
Titration (Ca & Mg) Calculation
pH pH Meter 4500 H+B
Electrical Conductivity Conductivity Meter As per IS 14767 -2000
Calcium Glass wares 3500 Ca B
Magnesium Glass Wares 3500 Mg B
Sodium (Na) F. Photometer 3500 Na B
Potassium F. Photometer 3500 K B
Soil Sampling Locations
Soil sampling was carried out at 6 (six) locations are given in Table 3-29.
Table 3-29: Soil Sampling Locations
Code Location Date of
Sampling Source
Distance from
Project Site in
Km
Direction
w.r.t Project
Site
Justification
S1 Jolwa 06-02-2017 Cultivated land 1.57 SW To check the physical and
chemical properties around
the site
S2 Vav 06-02-2017 Cultivated land 3.01 West
S3 Vadadala 06-02-2017 Cultivated land 3.42 NW
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 95
Code Location Date of
Sampling Source
Distance from
Project Site in
Km
Direction
w.r.t Project
Site
Justification
S4 Galanda 06-02-2017 Cultivated land 2.12 NE
S5 Atali 06-02-2017 Cultivated land 4.16 East
S6 Rahiyad 06-02-2017 Cultivated land 3.00 SE
Locations selected for soil sampling are shown in Map 3-2, and photographs of sampling locations are given vide
Photograph 3-7.
Photograph 3-7: Soil Sampling Locations
Sampling at Galenda Village Sampling at Rahiyad Village
.
Sampling at Vadadla Village Sampling at Vav Village
Soil sample Analysis Results
Analysis results of soil samples of different locations are given in Table 3-30.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 3. DESCRIPTION OF THE ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 96
Table 3-30: Soil Analysis Results
S.
No Parameter Unit
Sampling Locations
S1
Jolwa
S2
Vav
S3
Vadadala
S4
Galenda
S5
Atali
S6
Rahiyad
1 Porosity % 56 56 59 60 61 60
2 Water Holding Capacity % 55.20 61.30 62.30 52.40 60.80 57.36
3 Permeability mm/hr. 7.4 9.44 10.7 2.24 2.55 1.33
4 Particle Size Distribution -
a Sand % 36.00 27.00 23.00 25.00 28.00 26.00
b Clay % 29.00 32.00 36.00 12.00 12.00 21.00
c Silt % 35.00 41.00 41.00 63.00 60.00 53.00
6 Texture - Clay loam Clay loam Clay loam Silty loam Silty loam Silty loam
7 Cation Exchange Capacity meq/100gm 36.00 42.00 47.00 40.00 34.00 42.00
8 Electrical Conductivity μmhos/cm 285 140 294 800 265 281
9 Sodium Absorption Ratio (SAR) - 1.32 1.06 1.73 3.08 0.31 0.32
10 Exchangeable sodium % 0.69 0.31 1.28 3.17 <0.1 <0.1
11 pH - 8.10 7.87 8.36 7.85 7.72 7.63
12 Calcium gm/kg 0.46 0.85 0.32 0.52 0.43 0.72
13 Magnesium gm/kg 0.25 0.21 0.29 0.41 0.42 0.39
14 Sodium gm/kg 0.64 0.60 0.80 1.74 0.17 0.19
15 Potassium gm/kg 0.10 0.12 0.10 0.16 0.36 0.16
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 97
Quality of Soil
It is observed that at different locations:
The porosity ranged from 56% (Jolwa & Vav village) to 61% (Atali village) and WHC varied from 52.4%
(Galenda village) to 62.3 % (Vadadala village);
The soil permeability was low to medium which ranged from 1.33 mm/hr (Rahiyad village) to 10.7 mm/hr
(Vadadala village);
The EC of soil ranged from 140 dS/m (Vav village) to 800 dS/m (Galenda village), while ESP varied from 0.19
(Koliyad village) to 1.78 (Suva village);
These soils are neither saline nor sodic as ESP is < 5.0;
The pH of soil ranged from 7.63 (Rahiyad village) to 8.26 (Jolwa village), which indicates that soils are neutral
to slightly alkaline.
The overall soil quality indicates that soils are normal as the area is located in GIDC and not under cultivation since
long and whatever salts were there are washed off or leached down due to rain water over the years.
3.5.9 Ecology & Biodiversity
This section represents existing biodiversity status of the project site (core zone) and its surrounding environ of the
study area (buffer zone).
Field Visit
Primary field visits was done during June, 2015 by FAE, EB.
Ecology & biodiversity survey was again conducted during baseline data collection in February, 2017. It was
found that no major ecological changes took place within this preceding two years.
Ecological Sensitivity / Habitats of the Study Area
Buffer zone encompasses following different ecologically important features within 10 km radius of project site.
Forest /National Park / Sanctuary
No National Park or Sanctuary falls within buffer zone. However, Reserve Forest (RF) areas falls in the buffer zone
of the study area near Dahej & Lakhigam. These forest areas encompass mainly common species like Prosopis
juliflora (invasive species) and shrubs like Datura metel, Calotropis gigantea and Lantana camera are common.
According to the Champion and Seth (19683) Classification of Indian Forests, the natural vegetation of the survey
area represents the following forest-types:
Type 4A/L1 (Sub-type L1 – Littoral Forest of Sub-group A – Littoral Forests of Group 4 – Littoral and Swamp
Forests)
These occur along the coast wherever there is a fair width of sandy beach, including sandbars on the sea-face of
river-deltas. The dominant canopy is formed by scattered small evergreen trees along with a few deciduous trees.
There are many shrubs. Where the undergrowth is light, maritime grasses and surface-creepers are conspicuous,
binding the sand. In depressions where water accumulates, dense salt-tolerant undergrowth usually develops.
Characteristic species of this forest include trees such as Barringtonia asiatica, Borassus flabellifer, Calophyllum
inophyllum, Casuarina equisetifolia, Cerbera odollam, Cordia rothii, Erythrina variegata, Hibiscus tiliaceus, Ixora sp.,
Morinda citrifolia, Phoenix sp., Pongamia pinnata, Terminalia catappa, Thespesia populnea and Vitex negundo.
Shrubs such as Caesalpinia bonduc, Clerodendrum inerme and Pandanus sp. and herbs such as Crotalaria spp.,
Heliotropium spp., Ipomoea pes-caprae, Oryza coarctata and Spinifex squarrosus.
--------------------------------------------------------------------- 3 Champion, H. G. and Seth, S. K. (1968). A Revised Survey of Forest Types of India, Govt. of India Press, New Delhi, p. 404.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 98
Type 4B/TS1 (Sub-type TS1 – Mangrove scrub of Type B – Tidal Swamp Forests of Group 4 – Littoral and Swamp
Forests)
These occur where there is a maze of tidal creeks, in and out of which the tide flows daily. It is a fairly dense but
low forest, made up of few but gregarious species, all evergreen. Under natural conditions, as soil-deposition
progresses, the mangrove scrub is likely to evolve into first a mangrove forest, then a salt-water mixed forest, and
eventually, a brackish-water mixed forest. Characteristic species in this forest include trees such as Aegiceras
corniculata, Avicennia alba, Avicennia marina, Excoecaria agallocha and Sonneratia apetala; and shrubs such as
Acanthus ilicifolius.
Rivers and Ponds
Details of Rivers and Ponds in the Buffer Zone are given in Table 3-31.
Table 3-31: Details of Rivers and Ponds of Buffer Zone
S. No. Rivers/Pond Distance from Site Boundary Direction
1. Vadadla Pond 1.3 ENE
2. Dahej Pond 3 WSW
3. Jolva Pond 3.6 SSE
4. Vav Pond 3.8 NE
5. Ambetha Pond 4.8 SW
6. Kadodara Pond 4.9 NNE
7. Galenda Pond 5.4 ENE
8. Suva Pond 5.4 SSE
9. Sambethi Pond 5.6 ENE
10. Samatpor Pond 5.8 ENE
11. Rahiyad Pond 5.9 SE
12. Padariya Pond 6.4 NNE
13. Jageshwar Pond 6.9 SW
14. Lakhigam Pond 7.3 WSW
15. Janiadara Pond 7.4 NE
16. Paniadara Pond 8.2 NNE
17. Koliyad Pond 8.3 SE
18. Luvara Pond 8.4 WSW
19. Narnavi Pond 8.6 NE
20. Atali Pond 8.6 ESE
21. Akhod Pond 9.2 ENE
Creeks
Table 3-32: Details of Nearest Creeks in the Buffer Zone
S. No. Features Distance Direction
1 Creek 3.8 S
Mangroves
Nearest patch of mangrove from the project site boundary falls at a distance of 7.3 km towards WNW direction.
Mudflat
Nearest distance of from the project site boundary is 4.8 km. towards South direction.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 99
Methodology
Desktop Literature Review
Secondary information on ecology and biodiversity has been collected from District Forest Department, Bharuch.
Primary data has been verified based on the available secondary information.
Field Data Collection / Inventory
Terrestrial Ecology
Since project site falls in the industrial area and no natural vegetation exists at site, efforts have been made to
enlist existing species. Similarly, the buffer zone is mainly dominated with crop / fallow land while forest area is
entirely invade by an invasive species Prosopis juliflora (monoculture) which does not require quantification. So,
secondary data from various EIA reports have been extracted and verified through ground surveys.
Aquatic Ecology
Samples for Phytoplankton and Zooplankton have been collected in the various water bodies in the study area and
in the preparation of the same is given in Table 3-33.
Threat Assessment Criteria
Indian wild Life Protection Act, 1972, ENVIS Database, IUCN Database, Red Data Book etc.
Terrestrial Ecosystem
Flora
Core Zone / Project site
Project site has well developed greenbelt reported with 22 common species of flora / plants which includes
Subabul, Nilgiri, Neem, Gulmohar, Karanj, Penta, Badam, Saru, Jambu, Chickoo, Mehendi, Guvava, Jasud, Cycus,
Pam, Saptaparmi etc. Detailed taxonomic account for all life forms is tabulated inTable 1 of Annexure 30.
Photographs showing floral species at Core zone/project site are provided in Photograph 3-8.
Photograph 3-8: Floral species at Core Zone/Project Site
Plantation at the periphery of the site
Plantation within the project site
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 100
Buffer Zone
Buffer zone has been reported with 155 floral species, which includes 53 species of trees (25 families), 30 species
of Shrubs (21 families), 50 species of herbs (27 families), 8 species of grasses (one family) and 14 species of
climbers (6 families). Detailed taxonomic account for all life forms is tabulated in Table 2, Annexure 30.
Fauna
Herpetofauna
Core Zone / Project Site
No herpetofauna reported from the project site.
Buffer Zone
Overall 8 herpetofaunal species which includes Common garden lizard, Common rat snake, Common Indian
Monitor, Yellow-Green House Gecko, Fan-Throated Lizard, Spectacled Cobra, Russell’s Viper, and Common Indian
Krait known by their common names have been reported from the buffer zone. Detailed taxonomic account is
provided in Table 3, Annexure 30.
Avifauna
Core Zone
Only 4 common species of birds which includes Cattle Egret, Common Babbler, House Crow and Red-vented Bulbul
known by their common names were reported from the project site (flying across site). Bird activity was very poor
in adjacent area. Detailed taxonomic account is provided in Table 4, Annexure 30.
Mammals
Core Zone
No direct or indirect evidences of mammals were reported from the site.
Buffer Zone
Total 9 species from six families have been enlisted from buffer zone of the project area which includes Common
Langur, Indian Fox,Jungle cat, Common Mongoose, Indian Hare, Indian field mouse, Black rat, Five striped Palm
squirrel and Nilgai. Detailed taxonomic account is provided in Table 6, Annexure 30.
Agriculture and Horticulture
The Tuver (Cajanus indica), Wheat (Triticum aestivum) and Cotton (Gossypium herbaceum) are cultivated as major
crops in this area. Bajra (Pennisetum typhoides) and Jowar (Sorghum bicolar) are cultivated in few pockets
immediately after monsoon period.
Major Crops: Major crops in the study area are Tuver (Cajanus indica), Wheat (Triticum aestivum) and Cotton
(Gossypium herbaceum).
Minor crops: The minor crops of this region are Bajra (Pennisetum typhoides), Jowar (Sorghum bicolar) and Divel
(Ricinus communis)
Vegetables: The vegetables grown in the study area are, Rigan (Solanum melongena), Tomato (Lycopersicon
lycopersicum) and Val, Valpapadi (Lablab purpureus).
Major horticultural crops: Horticulture activity is very less. Keri (Mangifera indica), Chikoo (Manilkarazapota),
Papaya (Carica papaya) and Banana (Musa Paradisiaca).
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 101
Aquatic Ecosystem
Status of fishery, mangroves and phytoplankton & zooplanktons of the study area buffer zone is described below:
Fishery: Marine and Narmada Estuary
Bombay duck (Harpadon nehereus) constitutes the dominant fishery in the Bharuch region of the total marine
catch. The coastal water also serves as the migratory route for the clupeid Hilsa (Tenualosa ilisha) on their way to
the Narmada River for breeding and the outward route for the newly hatched juveniles and some of the adults. This
makes Hilsa fishery an important activity inside the Gulf and the estuarine region of Narmada.
Water near confluence is heavily silted and turbid. No commercial fishery takes place in river or along the coast due
to strong water currents. Pagadiya type fishing is operational in intertidal zones. Very few fishing boats present
coastal villages which operate only during rainy season when large fishes are available.
Mangrove and Other Coastal Vegetation
Mangrove flora is dominated by Avicennia marina and Rhizophora mucronata. Healthy growth of mangroves has
been reported from the banks of Ban Khadi and Ghugar Khadi. However, no mudflats sustaining dense growth of
mangroves have been reported. Similarly, obligate halophytes like Sueda maritima and Salichornia brachyata are
very common in the coastal area.
Phytoplankton and Zooplankton
Status of phytoplankton and zooplankton in various village water bodies is provided in Table 3-33 and Table
3-34.
Table 3-33: Status of Phytoplankton in Various villages of the Study Area
S. No. Genera Village Names
1 Cladophora Jolwa, Vadala, Ambheta
2 Coelastrum Suwa, Jolwa
3 Desmium Jolwa
4 Gonatozygon Jolwa, Ambheta, Suwa, Vadala
5 Melosira Suwa, Jolwa
6 Microspora Kadodara, Vadala
7 Nitschia Jolwa, Kadodara, Ambheta, Suwa, Vadala
8 Pediastrum Suwa
9 Penium Suwa
10 Phormidium Jolwa, Suwa, Vadala
11 Protococcus Kadodara, Vadala
12 Richterella Jolwa
13 Scenedesmus Jolwa, Kadodara, Ambheta, Suwa, Vadala
14 Spirulina Jolwa, Vadala
15 Synedra Suwa, Jolwa
16 Zygnema Jolwa, Kadodara, Ambheta, Vadala
Table 3-34: Status of Zooplankton in Various villages of the Study Area
S. No. Genera Village Names
1 Bosmina Suwa
2 Branchionus Suwa, Kadodara, Ambheta, Jolwa, Vadala
3 Canthocampus Suwa, Jolwa, Vadala
4 Ceriodaphnia Suwa, Jolwa
5 Cyclops Jolwa, Kadodara, Ambheta, Suwa, Vadala
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 102
S. No. Genera Village Names
6 Daphnia Jolwa, Kadodara, Ambheta, Suwa, Vadala
7 Diaphanosoma Suwa
8 Diaptomus Jolwa, Suwa, Vadala
9 Eubranchionus Jolwa, Vadala
10 Leptodora Jolwa, Kadodara, Ambheta, Suwa, Vadala
11 Limnocalamus Suwa, Jolwa, Ambheta, Vadala
12 Macrothrix Suwa
13 Monas Suwa
14 Nauplius Suwa, Jolwa, Vadala
15 Polyphemus Suwa
16 Sida Vadala
Status of Threatened and Endemic Biodiversity
Among floral species, Citrulus colocynthis (Cucurbataceae) vernacularly / locally known as Indravarna is enlisted in
the Red Data book (threatened species). For faunal species, threat status as per IWPA-1972 and IUCN has been
given in respective tables. Among herpetofauna, Common Indian monitor is a Schedule-I species as per IWPA-
1972. Reported birds also includes two Schedule-I species i.e. Peacock and Shikra. Among recorded faunal species,
none of the species can be designated as an endemic4.
Conclusion
Proposed project site is located in the GIDC Industrial Estate and does not support any species of conservation
significance and also not forms critical habitat. All flora and fauna species reported are common component of the
buffer zone. So, removal of these common floral species from core zone will not result in the loss of floral diversity
in true sense and will not have significant / permanent impact on the species diversity and habitat structure of
associated faunal diversity. However, buffer zone area encompasses some Schedule-I species, so conservation may
have been prepared for biodiversity improvement of the area. Flora and fauna components will not get affected in
normal function of the project and its associated activities by implementation of proper safety measures and control
devices. Being an industrial area, considering cumulative impacts due to other adjacent industries, strict
implementation of EMP / mitigation measures are required to ensure that the biodiversity of the study area should
not impacted negatively.
3.5.10 Socio-Economics
Methodology
Desktop Review
Gathering secondary data from sources like Census of India 2011.
Field Visit
Primary field visits was done during 23rd to 24th December, 2015 during which a structured household survey
format focusing on population, household composition, education levels, general health status, livelihood
strategies, employment, income level, stakeholder consultation, meeting the Village Sarpanch, focus group
discussions considering the origins and movements of the local population and social concerns/issues in relation
to the proposed project.
--------------------------------------------------------------------- 4 Venkataraman, K., Chattopadhyay, A. and Subramanian, K.A. (Editors). 2013. Endemic Animals of India (Vertebrates):1–235+26 Plates.
(Published by the Director, Zoological Survey of India, Kolkata)
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 103
The second visit to verify the collected data was done from 11th to 13th February, 2017. It was found that no
major demographic changes took place within this preceding two years.
Documentation
Preparation of fact sheets based on the field survey.
Secondary Data Collection/ Baseline Status
The proposed project is coming in PCPIR, the focus sector of it being chemical and petrochemical. The leading
companies in the PCPIR are Reliance Industries Limited, OPAL, ONGC, Petronet LNG Limited, and GSPC etc.
Social Profile
Population Distribution
The project study area consists of a section of the population whose land has been acquired for SEZ. Due to
decrease of agricultural activity in recent past people work as daily wage and contractual labours to carve out their
livelihood. Fishermen community exists in the study area villages who live on a daily earn and spent life style.
Table 3-35: Demographic Status of the Study Area
S.
No. District Subdistt Name Distance
No_HH
(2001)
TOT_P
(2001)
No_HH
(2011)
TOT_P
(2011)
1 Bharuch Vagra Vadadla 0-3 Kms 142 606 201 822
Total 142 606 201 822
2 Bharuch Vagra Vav 3-5 Kms 133 676 155 727
3 Bharuch Vagra Jolva 3-5 Kms 171 814 338 1,442
4 Bharuch Vagra Ambheta 3-5 Kms 293 1,330 347 1,552
5 Bharuch Vagra Dahej 3-5 Kms 1,551 6,846 3,426 13,495
6 Bharuch Vagra Kadodara 3-5 Kms 353 1,811 420 1,995
Total 2,501 11,477 4,686 19,211
7 Bharuch Vagra Padariya 5-7 kms 131 569 131 647
8 Bharuch Vagra Sambheti 5-7 kms 67 391 82 416
9 Bharuch Vagra Samatpor 5-7 kms 69 332 79 367
10 Bharuch Vagra Galenda 5-7 kms 95 513 120 611
11 Bharuch Vagra Rahiad 5-7 kms 269 1,315 355 1,694
12 Bharuch Vagra Suva 5-7 kms 325 1,664 413 1,920
Total 956 4,784 1,180 5,655
13 Bharuch Vagra Paniadara 7-10 Kms 460 2,330 514 2,563
14 Bharuch Vagra Narnavi 7-10 Kms 131 596 151 692
15 Bharuch Vagra Janiadara 7-10 Kms 129 621 150 729
16 Bharuch Vagra Akhod 7-10 Kms 133 669 174 831
17 Bharuch Vagra Atali 7-10 Kms 215 1145 239 1,150
18 Bharuch Vagra Koliad 7-10 Kms 120 535 152 676
19 Bharuch Vagra Jageshwar 7-10 Kms 346 1,465 383 1,571
20 Bharuch Vagra Luvara 7-10 Kms 276 1,393 385 1,663
21 Bharuch Vagra Lakhigam 7-10 Kms 640 3,357 1,217 4,938
Total 2,450 12,111 3,365 14,813
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 104
S.
No. District Subdistt Name Distance
No_HH
(2001)
TOT_P
(2001)
No_HH
(2011)
TOT_P
(2011)
Grand Total 6,049 28,978 9,432 40,501
Source: Primary Census Abstract 2001 and 2011
From Table 3-35 it can be inferred that the households number and population have increased respectively by
approximately 60% and 40% in the last decade. The household size has decreased by approximately 20% in the
last ten years.
Sex Ratio
The Sex Ratio of the study area is given in Table 3-36.
Table 3-36: Sex Ratio of the Study Area
Distance 2001 2011 Sex Ratio
Male Female Male Female 2001 2011
0-3 Kms 305 301 419 403 987 962
3-5 Kms 6,175 5,302 11,355 7,856 859 692
5-7 Kms 2,452 2,332 2,897 2,758 951 952
7-10 Kms 6,612 5,499 8,273 6,540 832 791
Total 15,544 13,434 22,944 17,557 864 765
Source: Primary Census Abstract 2001 and 2011
The above table reveals that the sex ratio has got reduced to 765 in 2011 from 864 in 2001. Dahej and Lakhigam
villages accounts for such a decrease that lies in the region 3-5 and 7-10 kms kilometers aerial distance from the
project site respectively. The sex ratio of this particular region (3-5 Kms) got reduced by approximately 19% and
that of Dahej village by 25% and the sex ratio of study area lying within 7-10 kms where Lakhigam village is
situated there the decrease in the sex ratio is by 5% approximately and that of the Lakhigam village is by 22%
approximately.
Age Stratification
The Age wise stratification is given in Table 3-37.
Table 3-37: Stratification (Age Wise) of Vadadala Village
Age Group Percentage
0-6 Years 8.0
7-14 Years 16.1
15-35 Years 46.0
36-60 Years 22.7
60+ Years 7.2
Total 100
Source: Primary Household Survey- 2015
The above table shows that the maximum population of Vadadala village lies within the age group of 15-35 years
which can be considered as the active work force. This population may be focused for providing skill training
programs in order to equip them to get jobs. The age group of 0-14 years which can be considered as the students
which may be focused for providing primary school education, stationaries and uniforms. The age group of 60+
years can be considered as the senior citizens or aged people which may be focused for providing Health centers
and health camps facilities.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 105
Vulnerable Groups
SC/ST population in the study area has been shown in Table 3-38.
Table 3-38: Details of SC/ST Population in the Study Area
Distance 2001 2011
% Scheduled Caste % Scheduled Tribe % Scheduled Caste % Scheduled Tribe
0-3 Kms 9.9 52.8 9.2 41.5
3-5 Kms 5.4 21.1 4.8 16.8
5-7 Kms 3.7 14 3.6 13.5
7-10 Kms 8.9 18.1 3.9 26.2
Overall 6.7 19.4 4.4 20.3
Source: Primary Census Abstract 2001 & 2011
This group of people can be focused for skilled labour program and various skill development programs can be
provided to them.
Educational Facility
The statistics regarding the educational facilities within the study area is given in Table 3-39.
Table 3-39: Educational Facilities in the Study Area
Distance
Government Private
Primary
School
Middle
School HSC SSC College
Primary
School
Middle
School HSC SSC College
0-3 Kms 3 0 1 1 1 1 0 0 0 0
3-5 Kms 5 0 1 0 0 0 0 0 0 0
5-7 Kms 7 0 1 0 0 0 0 0 0 0
7- 10 Kms 8 0 1 0 0 0 0 0 0 0
Total 23 0 4 1 1 1 0 0 0 0
Source: Primary Census Abstract 2011
From the above table it can be inferred that the Primary School facility is present in all the villages of the study
area. In the core area there is 1 Primary School, no Secondary School and higher educational facilities available.
The highest educational facility available is till Secondary School that are 4. For further higher education people go
to Bharuch and nearby cities of Gujarat.
A important parameter to focused to be done on providing facilities of primary school, stationary, computer skills,
sports activities, Scholarships and upgrading of existing schools.
Literacy Rate
An important parameter to evaluate the situation of the society is literacy rate. It has been shown in Table 3-40.
Table 3-40: Literacy rate within the study area
Distance % Literacy rate in Year 2001 % Literacy rate in Year 2011
0-3 Kms 64.95 73.84
3-5 Kms 59.67 74.02
5-7 Kms 63.31 79.23
7-10 Kms 59.19 69.46
Overall 61.9 74.35
Source: Primary Census Abstract 2001 and 2011
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 106
The literacy rate of the study area in 2001 and 2011 is approximately 56 and 74 percent respectively. The males
have higher literacy rate than the females. In the core zone the literacy rate has increased from 47.5 percent in
2001 to 73.2 percent in 2011. The female literacy rate has improved in 2011 in comparison to 2001 Census data in
all the villages of the study region.
Primary Data Collection for the Literacy level of Vadadla village
The Literacy level of Vadadla village is given in Table 3-41.
Table 3-41: Literacy level of Vadadla Village
S. No. Literacy Status Percentage
1 Illiterate 29.5
2 Anganwadi/Balwadi 3.8
3 Standard 1-6 29.5
4 Standard 7-9 25.2
5 SSC 10.0
6 HSC 1.0
7 ITI/Diploma 1.0
8 Graduate 0.0
9 Post Graduate 0.0
Total 100
Source: Primary Household Survey-2015
According to the sample size study it depicts that there are 70.5% of the literates and 29.5% of the illiterates in the
core zone village. The illiterates are those who are unable to read and write.
Table 3-41 reflects 3.8% of the students in the Anganwadi/Balwadi, 29.5% in who have studied between 1-6th
standard and 25.2% between 7-9th standard. The SSC qualified accounts to be 10% whereas the SSC passed are
1%. For attaining higher studies students travel to Bharuch and nearby cities.
Around 20.4% of the total population are students who are presently pursuing their studies in schools, colleges and
technical institutes.
Health Facilities
Health Facilities in the study area is given in Table 3-42.
Table 3-42: Health Facilities in the Study Area
Distance Primary Health
Centre
Primary Health
Sub Centre
Veterinary
Hospital
Mobile
HC
Family Welfare
Centre
Private Medical
facility
0-3 Kms 1 1 1 0 0 7
3-5 Kms 0 1 0 0 0 3
5-7 Kms 0 1 0 0 0 2
7- 10 Kms 0 1 0 0 0 1
Total 1 4 1 0 0 13
Source: Primary Census Abstract, 2011
From Table 3-42, it can be inferred that the medical facilities are limited in the study area villages. Apart from
Dahej most of the villages are devoid of the health facilities. Primary Health Centre is present only in the Dahej
village.
Due to the absence of government medical facilities the people are left with the only option to go to Bharuch for
their treatment. Dahej and Lakhigam villages are having private medical facilities but due to high fees people prefer
to go to the city itself.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 107
Drinking Water Facilities
Details of drinking water facilities is given in Table 3-43.
Table 3-43: Drinking water facilities within the Study Area
Distance Tap Water
Untreated
Covered
Well
Uncovered
Well
Hand
Pump
Tube
Wells
River/
Canal
Tank/ Pond/
Lake Others
0-3 Kms × × × ×
3-5 Kms
5-7 Kms
7-10 Kms
Source: Primary Census Abstract, 2011
Well and tank facilities are sufficiently present in the study area villages but the water requirement of the village is
not adequately supported because of it being saline unsuitable for the drinking purpose. Tube well facility is present
only at the Padariya village that lies within 3-5 kilometers zone from the project site.
Due to the absence of tube well facility the cultivators totally depend on rain water for the agricultural purpose. In
the study area villages main source of drinking water is supply through pipe line and water tanker provided by
GIDC.
Housing Condition and Sanitation Facility
Housing Condition
The housing condition of the surveyed households is given in Table 3-44.
Table 3-44: Housing Condition in the Surveyed Village
Type of Housing Number of Household
Pucca 18
Semi Pucca 7
Kutcha 15
Shanty 1
Total 41
Source: Primary Household Survey-2015
Table 3-44 shows that out of the 41 household survey done 18 were having Pucca houses, 7 Semi Pucca, 45
Kutcha whereas 1 house was shanty.
The houses that were pucca were mostly those who had primary and secondary sources of income and had some
land being acquired by the SEZ.
Photograph provided in Photograph 3-9.
Sanitary Toilet Facility
The type of toilet facility present in the surveyed village is given in Table 3-45.
Table 3-45: Toilet Facility in the Surveyed Village
Type of Toilet Facility Total No.
In house Toilet Facility 16
Open Defecation 25
Source: Primary Household Survey-2015
Table 3-45 reveals that open defecation is practiced in Vadadala village. The people having pucca houses
generally had the toilets built in their house. The people who were living in Indira Awas or in kutcha houses were
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 108
generally not having the toilet facility available at their homes. The vulnerable groups had got their toilet build
under the Government Scheme/private but they were not in working condition so they were left with no other
option but to defecate in open. Photograph provided in Photograph 3-9.
Photograph 3-9: Housing Condition and Sanitary Toilet Facility
Kutcha Houses at Kadodara Toilet made under Government Scheme
Economic Profile
Agriculture
Agriculture is totally depended on monsoons in the study area. The major crops grown are Wheat, Cotton, Pulses
and Bajri. Agriculture provides employment in the form of daily wage labour during the harvesting season. People
who have less or no land do labour in others field on daily wage basis. The average wage for the male is Rs. 300
per day and for the female is Rs. 250 per day.
Industries/Factories
PCPIR located at Dahej, is spread over the blocks of Vagra and Bharuch, South Gujarat. This region has been
specifically delineated Investment Region planned for the establishment of production facilities for petroleum,
chemicals and petrochemicals. Vagra Taluka is the place where the proposed project is coming. The major company
that are there in GIDC Dahej Phase II are tabulated in Table 3-8.
Employment Status
The occupational status has been shown in Table 3-46.
Table 3-46: Occupational status of the Study Area
Distance
% Occupational Status (2001) % Occupational Status (2011)
Cu
ltiv
ato
rs
Ag
ricu
ltu
ral
La
bo
r
Ho
use
ho
ld
Wo
rke
rs
Oth
ers
Ma
rgin
al
Wo
rke
rs
Cu
ltiv
ato
rs
Ag
ricu
ltu
ral
La
bo
r
Ho
use
ho
ld
Wo
rke
rs
Oth
ers
Ma
rgin
al
Wo
rke
rs
0-3 Kms 9.34 22.11 0.34 61.65 6.57 2.55 1.64 0.25 82.45 13.11
3-5 Kms 23.41 17.37 0.50 19.25 41.24 16.30 7.36 2.28 41.87 32.19
5-7 Kms 15.50 10.20 0.19 58.82 16.10 10.46 5.43 0.57 73.26 9.24
7-10 Kms 27.04 11.34 0.67 33.47 27.48 15.25 14.69 0.40 32.41 37.24
Total 18.99 14.74 0.42 43.96 22.49 9.85 6.61 0.71 61.55 21.01
Source: Primary Census Abstract, 2001 & 2011
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 109
Table 3-46 reveals that the cultivators and agricultural labours have decreased in the study area in the last
decade. . The percentage of the agriculture labour has decreased in 2011 to 6.6% from 14.7% in 2001 in the study
area. The bulk of the population belongs to the others category both in 2001 and 2011. The reason behind is that
the study area is situated in the SEZ/GIDC Estate that has many industries.
The type of livelihood is given in Table 3-47.
Table 3-47: Type of Livelihood Activity in the Core Impact area (0 – 3 Kms)
S. No. Type of Livelihood Frequency Percentage
1 Agriculture 2 2.7
2 Daily Wage Labors 32 43.8
3 Pvt. Company Contractual Labour 14 19.2
4 Government Job 1 1.4
5 Electrician 2 2.7
6 Fishermen 6 8.2
7 Pension Holder 1 1.4
8 Mason 3 4.1
9 Driving 5 6.8
10 Business 5 6.8
11 Livestock 2 2.7
Total 73 100
Source: Primary Household Survey-2015
From the above table it can be inferred that the bulk of the population falls in the daily wage earner category
working in as agricultural labour or in the private companies as the contractual labour.
In the primary household social survey it was found that there is presence of the electrician, driver, mason and
fishermen in Vadadala village. 6.8% of the population were having stationary, grocery, tea stalls etc.
About 2.7% of the population were earning from the livestock. Even though livestock was owned by many in the
village but it was for self use and no monetary was gain from it. Photograph provided in Photograph 3-10.
Photograph 3-10: Type of Livelihood Activity
Animal Husbandry Agricultural Field at the Study area
Means of Transportation
The transportation facilities with in the study area are shown in Table 3-48.
Table 3-48: Number of villages having Transportation Facilities
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 3. DESCRIPTION OF THE
ENVIRONMENT
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 110
Distance
Pu
bli
c B
us
Se
rvic
e
Ra
ilw
ay S
tati
on
Au
to/M
od
ifie
d
Au
tos
Ta
xi
Va
ns
Tra
cto
rs
Ca
rts D
rive
n b
y
An
ima
ls
0-3 Kms ×
3-5 Kms × × ×
5-7 Kms × ×
7-10 Kms × ×
Source: Primary Census Abstract, 2001
Table 3-48 shows that all the villages are having the government bus facility whereas the railway facility is present
in only core zone. Bharuch and Dahej are the nearest railway station present for the study area villages.
Availability of Power Supply
The Government of Gujarat supplies power to all the households in the study area villages.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 111
4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION
MEASURES
In this chapter, we:
Identify project activities that could beneficially or adversely impact the environment;
Predict and assess the environmental impacts of such activities;
Examine each environmental aspect-impact relationship in detail and identify its degree of significance;
Identify possible mitigation measures for these project activities and select the most appropriate mitigation
measure, based on the reduction in significance achieved and practicality in implementation;
In case impact are low or moderate and can be suitably managed by SOP’s / OCP’s, to minimize / control the
consequences, no specific management plans are prescribed;
• If consequences are high / indicating significant impact, implementation of mitigation measures requires
specific management plan, these are prescribed.
4.1 INVESTIGATED ENVIRONMENTAL IMPACTS DUE TO THE PROPOSED PROJECT
Details of investigated environmental impacts due to project location, possible accidents, project design, project
construction, regular operations and final decommissioning are discussed in this section.
Key Definitions, identification of impacts, methodology of component wise risk assessment is described in
Annexure 31. This methodology is used in this chapter for preparing impacts and their listing evaluation.
Mitigation measures are formulated based on the significance of the impact.
A programme to implement all mitigation measures is then prepared and presented as an Environmental Monitoring
Program and Environmental Management Plan, presented in Chapter 6 & Chapter 10 respectively.
Impact on environment have been identified, based on an assessment of various environmental aspects associated
with the project activities and has been summarized in Table 4-1.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 112
Table 4-1: Aspect-Impact Identification from Proposed Project
S
No. Project Activity Identified Aspect
N /
AN
/ E
Potential Impacts
Air Water Land Ecology & Biodiversity Resource
Depletion Social
AP /
AQ NV SW GW
Effluent /
Sewage
LU /
LC Soil HW ISW MSW TER. AQUA. RD Infrastructure Economic
OH /
(H&S)
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 C19 C20
1 Project Location
1.1 Site selection Increase in traffic on state highways and internal
roads in study area N • • (+ve) •
2 Project Design
2.1
Design & selection of
technology, equipment / site
layouts, etc.
Non-compliance of Environmental standards due
to failure in designs of the following:
1) Air Pollution Control Equipment
AN
• •
2) Boilers / Compressors / Other utilities • •
3) Settling tank & Hazardous waste storage area • • • • • • •
4) Fuel, Limestone, Fly ash Storage facilities • •
5) High Energy Consuming devices •
3 Project Construction
3.1
Excavation and paving of site,
Movement of JCBs, other
machinery, workers / labors
etc.
Generation of Debris N •
Noise Generation N •
Site specific disturbance to faunal species N •
Dust Generation N • •
Fall in pit, land sliding from sidewalls AN •
3.2
Heavy fabrication work for
erecting major plant
equipment including operation
of equipment like crane,
concrete mixtures, vibrators
etc.
Generation of Scraps N • •
Emission of Heat Radiation N • •
Noise Generation N • •
Breaking of pulley, chains of cranes during lifting
of equipment AN •
3.3 Influx of Construction Workers
Employment generation for construction workers N • (+ve)
Domestic wastewater generation N •
Sewage Sludge generation N •
3.4
Vehicular movement for
transportation of materials and
equipment
Dust generation and emission of HC & CO N • •
Noise Generation N • •
4 Power Plant Operation
4.1 Procurement of Coal &
Limestone
Generation of dust due to truck movement N • • •
Spillage of Material on road AN •
Establishment of ancillary activity N • (+ve) • (+ve)
4.2 Coal & Limestone storage and
stock pilling
Generation of dust N • • • •
Emission of PM, SO2 from burning of Coal in case
of Fire. E • • •
Wastewater Generation (From excess water
hydrant during fire) E •
4.3 Handling and Crushing of Coal
& Limestone Generation of dust N • • •
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 113
S
No. Project Activity Identified Aspect
N /
AN
/ E
Potential Impacts
Air Water Land Ecology & Biodiversity Resource
Depletion Social
AP /
AQ NV SW GW
Effluent /
Sewage
LU /
LC Soil HW ISW MSW TER. AQUA. RD Infrastructure Economic
OH /
(H&S)
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 C19 C20
4.4 Operation of DM Plant Wastewater Generation (Acidic / Alkaline waste
water including resins) N •
4.5 Operations of Boilers &
Turbines
Emission of PM, SO2, NOx N • • • •
Wastewater Generation (Boiler blow down) N •
Noise Generation N • •
Generation of Bottom and Fly Ash N •
4.6 Handling of Fly Ash
Generation of dust N • • •
Wastewater Generation (excess water sprinkling
in Ash pond) AN •
5 General & Utilities
5.1
Vehicular movement for
transportation of raw
materials, Industrial Waste.
SPM generation and emission of HC & CO. N • • • (+ve) •
Noise Generation N •
5.2
Handling of Material, and
operation of heavy machineries
like dumpers, trucks, etc.
Generation of Dust N • •
5.3
Operation of other utilities like
Cooling Tower, Compressor,
Pumps, Blowers etc. & Floor
Washing.
Wastewater generation (Cooling tower blow
down, shaft leaks, washings etc.) N • • • (+ve)
Leakages in HSD tank AN •
Noise Generation AN •
Generation of Used/spent oil, waste/residue
containing oil, contaminated hand gloves,
discarded containers / barrels / bags
N • •
Acidic and alkaline waste water N
5.4 Operation of ETP (settling
tank)
Spillage of effluent AN •
Overflow of excess effluent generated due to
abnormal operation/ breakdown of settling tank. AN •
5.5 Operation of STP Overflow of domestic waste water (due to
abnormal operation/ breakdown of STP) AN •
5.6 Equipment maintenance Generation of scraps, used spares, cotton waste,
hand gloves etc. N •
5.7 Analysis in laboratory
Waste water generation N •
Generation of Broken Glassware AN • •
Injury due to splash of acid/alkali on chemist AN •
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 114
4.2 AIR ENVIRONMENT
As discussed earlier, environmental aspects and impacts have been identified based on an assessment of environmental
aspects associated with the project, which include emissions:
During Project Design Stage;
During Project Construction;
During Project Operation;
During General Operation phase of Utilities.
For the purpose of impact predictions on air environment, emission sources can be classified into point and area
sources. Whilst no area sources have been identified as part of the project, point sources have been identified and
these include stacks attached to various units.
The impact assessment methodology is given in Annexure 31.
Potential impacts on Air Environment /Nearby Ambient Air Quality are tabulated in Table 4-2.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 115
Table 4-2: Impact Scoring and Mitigation Measures for Air Environment
S No. Project Activity Identified Aspect
N /
AN
/ E
Legal
Impact Scoring Significance /
Consequence Operation Controls / Mitigation Measures
EMP
Required Severity,
S
Probability,
P
Final Score,
S x P
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11
1 Project Design
1.1 Design & selection of technology,
equipment / site layouts, etc.
Non-compliance of Environmental standards due to
failure in designs of Air Pollution Control Equipment AN No 5 1 5 Less Severe
Approved and standard designs of air pollution control equipment & other
equipment like Boiler, Turbine, ESP etc. will be procured from Authorized vendors
to meet environmental standards.
No
2 Project Construction
2.1
Excavation and paving of site,
Movement of JCBs, other
machinery, workers / labors etc.
Dust Generation N No 1 5 5 Less Severe Barricading will be done wherever required. Water sprinkling is carried out as and
when required. No
2.2
Heavy fabrication work for erecting
major plant equipment including
operation of equipment like crane,
concrete mixtures, vibrators etc.
Emission of Heat Radiation N No 1 5 5 Less Severe Properly certified, tested and calibrated equipment will be used. No
2.3
Vehicular movement for
transportation of materials and
equipment
Dust generation and emission of HC & CO N No 2 5 10 Moderate Severe PUC Certified vehicles will be used. Traffic management will be ensured. No
3 Power Plant Operation
3.1 Procurement of Coal & Limestone Generation of dust due to truck movement N No 1 5 5 Less Severe Barricading will be done wherever required. Water sprinkling is carried out as and
when required. No
3.2 Coal & Limestone storage and
stock pilling
Generation of dust N No 1 5 5 Less Severe Barricading will be done wherever required. Water sprinkling is carried out as and
when required. No
Emission of PM, SO2 from burning of Coal in case of
Fire. E No 2 1 2 Less Severe
Onsite and Offsite emergency plan will be followed. Fire fighting & emergency
response team will be at place. Preventive maintenance schedule in place. No
3.3 Handling and Crushing of Coal &
Limestone Generation of dust N No 2 5 10 Moderate Severe
OCPs will be followed. Water sprinkling will be done. Dust extraction system will
be provided at crusher house No
3.4 Operations of Boilers & Turbines Emission of PM, SO2, NOx N Yes -- -- -- Significant
ESP will be provided. Limestone dosing will be done to control SO2 emissions.
Stack height of 65 m will be provided for proper dispersion. Online meter for PM,
SO2 & NOx will be provided.
Yes
3.5 Handling of Fly Ash Generation of dust N No 3 5 15 Highly Severe
Ash Handling and Management plan will be prepared and followed. Dust collection
system will be installed at transfer tower, crusher house, top of silo & bunker
tower.
Yes
4 General & Utilities
4.1
Vehicular movement for
transportation of raw materials,
Industrial Waste.
SPM generation and emission of HC & CO. N No 3 5 15 Highly Severe Water sprinkling will be done. PUCC Certified vehicles will be used. Traffic
management will be ensured. Yes
4.2
Handling of Material, and operation
of heavy machineries like dumpers,
trucks, etc.
Generation of Dust N No 2 5 10 Moderate Severe Regular clean-up activities shall be done. No
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 116
4.2.1 Emission Rates & Predicted GLCs
Point Source Emissions
As per the discussions with MFL officials, following relevant data were collected to calculate emission rates of relevant
pollutants from point source due to proposed activities during operation phase:
Quantity of fuel;
Fuel analysis;
Stack details: Internal diameter at top, height*, exit gas velocity, temperature.
* Stack Height is calculated based on the sulphur content in Coal (Indian/Lignite/Imported), considering worst case, i.e.
when all APCM fails.
Assumptions for calculating emission estimates for point source are as following:
Emission rates from the new stack (67 MW unit) of relevant parameters as provided in Emission standards for TPP
units to be installed from 1st January, 2017 are considered.
By having Sulphur reduction efficiency of >95.77% (Lime dosing in CFBC boilers) & ESP Efficiency of
>99.89%, the prescribed norms will be met.
In actual, the emissions will be lesser than it is calculated for and it is unlikely to cause significant increase in GLCs.
Online monitoring system will be provided at stack exhaust, which, if exceeds the limit of 30 mg/Nm3, will trigger
the alarm and plant load will be lowered/ESP field will be switched/ Plant will be shut down. Online monitoring
system will be connected with CPCB & GPCB servers also. Operation of power plant in such case is not practical.
However, air quality modeling was carried out considering the partial (50% efficiency) and complete failure of the
ESP. Details are provided in Annexure 34.
Details of proposed stacks & APCM are given in Table 2-13. Assumptions of Sulphur & Ash Content in the Fuel is
tabulated in Table 4-3. Emissions rates (As per fuel analysis & As per Norms) from proposed flue gas stacks are shown
in Table 4-4 & Table 4-5.
Table 4-3: Assumptions of Sulphur & Ash Content in the Fuel (Worst Case)
S. No. Fuel Type Sulphur Content, % Ash Content, % Source
1 Imported Coal 0.5 12.0 Coal Analysis report, Annexure 21.
Area Source Emission
From the proposed project, area source emitting SPM is identified as open storage of coal. Emissions rates from coal
stock piles is calculated and shown in Table 4-6.
Line Source Emissions
Additional vehicular movement of approximately 125 trucks per day is envisaged on road connecting Site to Bharuch (in
S Direction) which involves vehicular air emissions, majorly CO & HC’s.
This road is a six lane, “pakka” road having 18 m width. Hence, line source emissions are not considered for the
modelling purpose.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 117
Table 4-4: Emission Estimate from Flue Gas Stacks (As per Fuel Analysis)
Stack
No.
Stack Attached
to
Required
Stack
Ht., m
Stack
Ht., m
Stack
Dia.
(Top),
m
Stack
Exit
Velocity,
m/s
Stack
Exit
Temp, oK
Stack
Exhaust,
Nm3/s
Fuel
Consumption
(TPH)
Sulphur
Content
in Fuel,
%
Sulphur
Emitted,
kg/hr
SO2
Emitted,
kg/hr
SO2
Emitted,
gm/sec
APCM SO2
Reduction
Efficiency
SO2
Emitted
After
APCM,
gm/sec
Ash
Content
in Fuel,
%
PM10
Emitted,
kg/hr
PM10
Emitted,
gm/sec
APCM PM
Reduction
Efficiency
PM
Emitted
After
APCM,
gm/sec
NOx
Emitted,
mg/Nm3
NOx
Emitted
After
APCM
gm/sec
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 C19 C20 C21 C22
1 Boiler 1 & 2 64.1 65 3.2 12.5 443 67.6 57.50 0.5 287.5 575 160 95.8% 6.76 12.0 6900 1917 99.9% 2.03 100 6.76
Table 4-5: Emission Estimate from Flue Gas Stacks (As per the Norms)
Stack
No. Stack Attached to
Required
Stack Ht.,
m
Stack Ht.,
m
Stack Dia.
(Top), m
Stack Exit
Velocity,
m/s
Stack Exit
Temp, oK
Stack
Exhaust,
m3/s
Stack
Exhaust,
Nm3/s
Fuel
Consumption
(TPH)
SO2
Emission,
mg/Nm3
SO2
Emitted,
kg/hr
SO2 Emitted
After APCM,
gm/sec
PM
Emission,
mg/Nm3
PM10 Emitted
After APCM,
gm/sec
NOx
Emitted,
mg/Nm3
NOx Emitted
After APCM,
gm/sec
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17
As per MOEF's New Emission standards for power plant dated 07.12.2015.
1 Boiler 1 & 2 36.5 65 3.2 12.5 443 100.5 67.6 57.50 100 24.3 6.76 30 2.03 100 6.76
Table 4-6: Emission Estimate from Volume Source (Coal Storage Yard)
S. No. Storage
Yard type
Maximum Working Pit
Dimensions, m Area
(m2)
Volume
(m3)
Stowage
factor
Max.
Quantity
Stored,
MT
Density of
Coal,
Kg/m3
Max.
Quantity
Handled,
TPD
Air Pollution
Generating Activity
(as per USEPA
Terminology)
Emission Factor as Per
USEPA Fire Model
Coal
Handled,
Ton/Hr
Emission
Factor
PM
Emission,
lb/Hr
PM
Emission,
gm/sec
PM
Emission,
gm/m2/sec Length Width Height
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18
1 Coal Storage 135.0 65.0 3.0 8,775 26,325 1.4 18,804 800.00 1,380 Handling 3.000 E-3 Lb per Tons Material
Throughput 57.50 0.003 0.173 0.022 2.4769E-06
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 118
Dispersion Modeling
Emissions from all the stacks were analyzed for their impacts on the GLC for various distances using the dispersion
modeling guidelines of AERMOD, developed by the AERMIC (American Meteorological Society (AMS)/United States
Environmental Protection Agency (USEPA), as directed by CPCB.
About AERMOD
AMS/EPA Regulatory Model (AERMOD) is a steady-state plume model. It is designed to apply to source releases and
meteorological conditions that can be assumed to be steady over individual modeling periods (typically one hour or
less). AERMOD has been designed to handle the computation of pollutant impacts in both flat and complex terrain
within the same modeling framework.
The American Meteorological Society/Environmental Protection Agency Regulatory Model Improvement Committee
(AERMIC) was formed to introduce state-of-the-art modeling concepts into the EPA's air quality models. Through
AERMIC, a modeling system, AERMOD, was introduced that incorporated air dispersion based on planetary boundary
layer turbulence structure and scaling concepts, including treatment of both surface and elevated sources, and both
simple and complex terrain.
AERMET is an input data processor that is one of the regulatory components of the AERMOD modeling system. It
incorporates air dispersion based on planetary boundary layer turbulence structure and scaling concepts. Data flow in
Aermod modeling system is shown in Figure 4-1.
Figure 4-1: Data Flow in AERMOD Modeling System
Meteorological Parameters
The hourly meteorological data considered were wind speed, wind direction, ambient atmospheric temperature, cloud
cover, humidity & rainfall.
Other Assumptions
The dispersion modelling assumptions considered are as follows:
The terrain of the study area was considered as FLAT;
Stability class and Atmospheric inversion level is based on software’s database.
Since, no AAQ norms of SPM is available, it is assumed the entire PM emitted from flue gas stack is PM10.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 119
Results
Air dispersion modeling results with predicted GLC (Isopleths) from proposed activity of all parameters are provided in
Annexure 33 . Maximum 24 hourly average GLC’s for PM10, SO2 & NOx are tabulated in Table 4-7.
Table 4-7: Summary of Air Dispersion Modeling for Proposed Stacks
S
No. Parameters
Number of
Sources
Maximum GLC
Concentration, µg/m3 Distance, m Direction
1 PM10 2 0.51 750 SW
2 SO2 1 1.71 750 SW
3 NOx 1 1.71 750 SW
The worst combined environmental situation is predicted as the sum of average baseline monitored value of a
parameter and the incremental GLC at the monitoring location. It indicates maximum GLC’s due to the proposed
activities / emissions as tabulated in Table 4-8.
Table 4-8: Incremental GLC from Proposed Project
S
No.
Name of Village
(Distance in
km/Direction)
Pollutant CPCB Limit
Concentration
Baseline
Concentration
(Avg)
Incremental
GLC
Total Predictive
GLC due to
proposed project
1 At Project Site ( 0.0
/ --)
PM10 100 82 0.51 82.51
SO2 80 9.8 1.71 11.51
NOx 80 17.3 1.71 19.01
2
At GLC Area (Nr.
GACL – Plot 3) (1.1
/ SW)
PM10 100 74 0.26 74.26
SO2 80 9.5 0.60 10.1
NOx 80 18.0 0.60 18.6
3 At Vadadla Village
(1.4 / NE)
PM10 100 86 0.21 86.21
SO2 80 8.3 0.71 9.01
NOx 80 17.1 0.71 17.81
4 At Vadadla Crossing
(2.19 / SE)
PM10 100 96 0.18 96.18
SO2 80 10 0.76 10.76
NOx 80 24.5 0.60 25.1
5 Nr. Salt Pans (3.20 /
NW)
PM10 100 57 0.21 57.21
SO2 80 8.2 0.70 8.9
NOx 80 16.5 0.70 17.2
6 Nr. Forest Area (8.0
/ WSW)
PM10 100 63 0.08 63.08
SO2 80 8.2 0.27 8.47
NOx 80 17.2 0.27 17.47
7 At Vav (4.13 / NE)
PM10 100 68 0.07 68.07
SO2 80 8.8 0.25 9.05
NOx 80 19.4 0.25 19.65
8 At Jolva (3.75 / E)
PM10 100 61 0.03 61.03
SO2 80 8.9 0.17 9.07
NOx 80 18.6 0.11 18.71
All Values in µg/m3
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 120
Conclusion
Comparing the incremental ground level concentrations of pollutants with the CPCB limits, it can be concluded the
following:
Maximum Incremental GLC’s for all parameters remain within 750 m from the project site;
Due to the proposed project, GLC’s will remain within the prescribed limit;
Air impacts are not expected to cause any effect on vegetation and human settlements in the vicinity of the project
site.
Mitigation Measures
Mitigation measures for air quality impacts are:
Adequate height of at least 65 m will be provided as per the statutory requirements;
Well-designed ESP having atleast 99.9 % efficiency will be provided to control PM emissions;
Limestone dosing in CFBC Boilers will be done to achieve sulphur reduction efficiency of atleast 95.8%;
Since the proposed technology is of CFBC, temperature will be controlled to prevent NOX generation.
Online sensors for SPM, SO2 & NOx shall be provided with flue gas stacks which will be attached to CPCB & GPCB
servers;
Regular Work place monitoring will be done;
CAAQMS will be placed near admin building;
Adequate Bag filters will be installed in ash handling unit & coal yard;
Effective water spraying will be done on the access roads to control re-entrained dust during dry season (if
required);
Proper operating procedures will be followed during startup and shutdown;
Proper PPE like dust masks will be provided to workers and its use will be ensured.
4.2.2 Incremental Traffic
From the proposed facility, approximately on daily basis, approximately, 100 trucks per day carrying coal, limestone, fly
ash, etc. shall be using the state highway (SH-6) connecting Bharuch and Dahej.
Summary of traffic survey (peak hourly) are given in Table 4-9 and Table 4-10. Summary of traffic survey (peak
hourly) are given in Peak hours are considered from 08:00 – 12:00 Noon and 16:00 – 20:00 Hours. Detailed traffic
Survey sheets are attached in Annexure 35.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 121
Table 4-9: Incremental Hourly Average Traffic on Bharuch to Dahej
Type of Vehicle From Bharuch to
Dahej
% of Total
Stream
Equivalent PCU
Factor5 Converted PCUs
Additional Vehicles
per day
Additional PCUs per
Hr.
Total PCUs
After Proposed Project
Two wheeler 106 27% 0.75 79 0 0 79
Three wheeler 26 7% 1.2 31 0 0 31
Car/Jeeps 101 26% 1 101 0 0 101
Truck/Buses/Tractors 143 37% 2.2 314 100 22 336
Non Motorable vehicles 12 3% 0.4 5 0 0 5
Total 388 100 531 100 22 553
Table 4-10: Incremental Hourly Average Traffic on Dahej to Bharuch
Type of Vehicle From Dahej to
Bharuch
% of Total
Stream
Equivalent PCU
Factor Converted PCUs
Additional Vehicles
per day
Additional PCUs per
Hr.
Total PCUs
After Proposed Project
Two wheeler 112 29% 0.75 84 0 0 84
Three wheeler 29 8% 1.2 35 0 0 35
Car/Jeeps 100 26% 1 100 0 0 100
Truck/Buses/Tractors 158 41% 2.2 347 100 22 369
Non Motorable vehicles 10 3% 0.4 4 0 0 4
Total 409 100 570 100 22 592
--------------------------------------------------------------------- 5 As per The Indian Road Congress - Guideline for capacity of roads in urban Area. (IRC:106-1990), Table-2, Recommended Design Service Volumes, page – 10.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 122
Based on the traffic survey conducted on SH-6, it is noted:
Average peak hourly traffic on this route is 531 and 570 PCU respectively;
From the proposed project, additional 22 PCU’s will be required;
As per IRC, carrying capacity of this approach road is 3,600 PCU;
Thus, the maximum PCU on the road will be 553 (Bharuch to Dahej) and 592 (Dahej to Bharuch).
Thus, the road is capable of carrying the excess traffic due to the proposed project.
Impacts due to Road Transportation
Increase in transportation will lead to increase in road traffic;
Generation of dust from trucks;
Emission of pollutants like HC, SO2, CO, CO2;
Noise generation from vehicular movement;
Spillage or leak of raw materials during transportation.
Mitigation Measures
Trucks with be covered with HDPE before traveling on public roads;
No overloading is done shall be ensured;
Vehicle manifest shall be maintained;
PUC Certified vehicles will be used;
Traffic management will be ensured as mentioned in Chapter 6, Section 6.1, Table 6-2.
Traffic Risk Assessment & safety during transportation details are provided in Chapter 7, Section 7.2.5.
The engines and exhaust systems of all vehicles and equipment used will be maintained as such, that exhaust
emissions are low and do not breach statutory limits set for the concerned vehicle/equipment type.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 123
4.3 NOISE ENVIRONMENT
The proposed project related activities will lead to generation of noise that may have minor impact on the surrounding
communities in terms of minor increase in noise levels. The potential impacts on noise level may arise out of the
following:
Noise from Machinery/Equipment
For site preparation, during construction phase operation of equipment like crane, dumper, roller, bulldozers etc. will be
used. The equipment will be used during daytime and will emit noise within permissible limits. Thus, there will not be
any adverse impact on nearby habitation due to proposed activity.
Noise from Vehicle /Traffic
Vehicle movement for transportation of materials and work force to the site will cause minor noise emission as the
frequency of vehicular movement is few times in a week.
Noise from Equipment etc.
Noise generated from Turbine, Cooling Tower, Pumps, FD-ID Fans & Compressor will have a permanent effect, if they
will work for more hours in a day continuously.
Based on the identified project activities impact on noise environment is accessed. The methodology for the Impact
Assessment is provided in Annexure 31. Scoring of the same is done. Mitigation measures based on these scores are
tabulated in Table 4-11.
Vibration from Equipment / Piping etc.
Source of major vibrations due to the proposed power plant project are as follows:
Turbine;
HP Steam pipes;
Compressors;
ID fans;
Other machines having bearings & gearboxs.
These will be reduced by providing proper dampening space & pipes will be insulations with required MOC.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 124
Table 4-11: Impact Scoring and Mitigation Measures for Noise Environment
S
No. Project Activity Identified Aspect
N /
AN
/ E
Legal
Impact Scoring
Significance /
Consequence Operation Controls / Mitigation Measures
EMP
Required Severity,
S
Probability,
P
Final Score,
S x P
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11
1 Project Design
1.1 Design & selection of technology,
equipment / site layouts, etc.
Non-compliance of Environmental standards due to faulty design of Boilers / Compressors / Other
utilities AN No 5 1 5 Less Severe Process equipment meeting environmental noise standards shall be procured. No
2 Project Construction
2.1
Heavy fabrication work for erecting major plant equipment including
operation of equipment like crane, concrete mixtures, vibrators etc.
Noise Generation N No 1 5 5 Less Severe Properly certified, tested and calibrated equipment will be used. Proper PPE like Ear
Plugs & ear muffs will be provided and its use shall be ensured. No
2.2 Vehicular movement for
transportation of materials and equipment
Noise Generation N No 2 5 10 Moderate
Severe PUCC Certified vehicles will be used. No
3 Power Plant Operation
3.1 Operations of Boilers & Turbines Noise Generation N Yes -- -- -- Significant
Provision of Silencer in main stream line safety valve, and before turbine for steam
venting during startup of turbine. PPE like Ear Plugs & ear muffs will be provided and
its use shall be ensured. No operators shall be allowed to do two continuous shifts.
Yes
4 General & Utilities
4.1 Vehicular movement for
transportation of raw materials, Industrial Waste.
Noise Generation N No 2 5 10 Moderate Severe
PUCC Certified vehicles will be used. No
4.2 Operation of other utilities like
Cooling Tower, Compressor, Pumps, Blowers etc. & Floor Washing.
Noise Generation N No 3 5 15 Highly Severe SOP's, OCP and OEP will be followed during startup. Acoustic enclosures will be built-
in with equipment by technology provider. PPEs like Ear Plugs & ear muffs will be provided and its use shall be ensured.
Yes
Based on this above identification of impacts, environmental indices that are likely to be impacted due to the project are:
1. Impact due to vehicle movements during site preparation, construction facility, during Operation phase
2. During operation of Turbine, DG set, cooling tower, Pumps, FD-ID Fans & Compressor.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 125
Assessment of Noise using SoundPLAN
Noise modeling study was done using the Software tool called “Sound Plan” which predicts the Noise Map generated
due to the sources present at the project site, and predicts the Noise Levels at various receiver points due to the
sources present at the project site.
To analyze the Noise Map of the project site, first, the geometrically coordinated Google Earth images of the Project
site were imported into the software. Various Sources of noise were added with their approximate Sound Pressure
Levels, and the “Receiver points” were added at various locations where Noise Monitoring was conducted.
“Sound Plan” generates the Noise Map with colored pattern isopleths, which indicate whether or not the SPL in that
particular region is above the limits mentioned by CPCB or not. If the Limit for Sound Pressure Level indicated by CPCB
for that particular area is 75 dB during the day, and if the predicted SPL is below that, the Noise Map will show Green
color for that area. But if the SPL is above the “user set” allowable limit, the same will be shown in Red color depending
upon the Difference between then Predicted SPL and the Allowable SPL, and the “Conflict” in SPL is mentioned in the
table if any conflict is predicted.
Consideration during the analysis
The sources considered at the project site for the analysis with their approximate Sound Pressure Levels are considered
slightly on the higher side for more critical analysis. The sources of noise considered are given in Table 4-12.
Table 4-12: Sources of Noise with their Sound Pressure Levels
S.
No. Sources
Levels dB(A)
Day Night
1 Turbine 100 100
2 Pumps 85 85
3 FD-ID Fan 85 85
4 Cooling Tower 85 85
5 Compressor 100 100
Using above consideration the Isopleth generated during daytime and nighttime shown in Figure 4-2 and Figure 4-3.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC
DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 126
Figure 4-2: Isopleth of Day Time
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC
DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 127
Figure 4-3: Isopleth of Night Time
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 128
Observations
The project site is located in a designated industrial area, where the CPCB limits defined for Noise Levels are 75 dB
during the day and 70 dB during the night. However, sound pressure levels are considered on higher side for more
critical analysis.
Since the sources of noise are present within the project site, near boundary wall of the project site being present,
increase beyond 75 dB at the site was not observed.
From Figure 4-2 and Figure 4-3, it can be observed at project site, noise is predicted in the range of 60 dB (A) -
70 dB(A) which is within the permissible limit for industrial area.
The predicted noise levels along with the conflict are as given in Table 4-13.
Table 4-13: Noise level at receptor locations
S.
No. Receiver Name Category
CPCB Limits
in dB (A)
Baseline
Average Noise
levels in dB
(A)
SPL predicted
at Receiver by
Proposed
Activities (dB)
Predicted
Cumulative
incremental
increase in
Noise level dB
(A)
Incremental
increase in
Noise level dB
(A)
Day Night Day Night Day Night Day Night Day Night
1 Nr. Security gate Industrial 75.0 70.0 65.2 55.9 51.6 44.4 65.4 56.2 0.2 0.3
2 At project site
(NW) Industrial 75.0 70.0 64.7 56.0 43.3 42.3 64.7 56.2 0.0 0.2
3 Nr. Cooling
Tower Industrial 75.0 70.0 72.5 64.5 46.1 41.6 72.5 64.5 0.0 0.0
4 Nr. Utility area Industrial 75.0 70.0 71.3 62.7 47.9 47.0 71.3 62.8 0.0 0.1
5 Vadadala village Residential 55.0 45.0 54.4 44.4 42.3 40.3 54.4 44.5 0.0 0.1
As given in the Table 4-13, during the day time only 0.3 dB increase are noticed in the nearby Industrial area. i.e. No
increase to maximum increase of 0.2 dB which is negligible considering that the minimum increase noticeable by a
human ear is 0.5 dB. Another factor to be considered, is that SoundPlan analysis is carried out assuming that there are
no obstructions (such as trees, buildings, walls etc.) in between the receiver locations and the sources of sound, which
is not true in real conditions. Therefore, the actual results are going to be much lower than SoundPLAN’s predicted
results, and hence increase of 0.1 to 0.3 dB is not likely to be noticed at any of the noise monitoring locations.
Conclusion
The Predicted increase is maximum 0.2 dB during the day and 0.3 dB during the night in Industrial area and 0.2 dB
during the day and 0.3 dB during the night time in Residential area according to SoundPlan analysis. This increase is
negligible considering that the minimum noticeable increase by a human ear is 0.5 dB hence it can be concluded that
due to noise generated from the proposed project there will not be any impact on the surrounding area.
Mitigation Measures
Although there was no increase beyond the allowable limit predicted at any of the noise monitoring locations outside
the project site, the noise environment also includes the people who are working within the project site, and who may
face permanent hearing damage in case they face the Noise Dosage beyond the allowable level of Noise. Therefore, it
is important to implement the following mitigations given in Table 4-14, in order to avoid any permanent hearing
damage to the people working inside the project site.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 129
Table 4-14: Mitigation Measures
S.
No. Source of Noise
Sound Pressure Level
(dB) Mitigations suggested
1 Compressors 85 dB
The noise level of the Compressor Often exceeds 100 dB if not covered with
a canopy.
If the Compressors are installed with an Acoustical Canopy by default, no
further mitigations are required.
If there are no Acoustical Canopy for the compressor, Acoustical Enclosure
with 30 dB Transmission Loss is recommended for the compressor.
If Multiple Compressors (with canopies) are kept together, it is likely that
their combined SPL when all of them are running may exceed 90 or 95 dB.
It is recommended in such a case that Room Acoustical treatment be done
for the compressor houseroom.
2 DG Sets 100 dB
The limit set by CPCB for DG Sets is 75 dBA for a spatial average of 16
readings taken surrounding the DG Set. It is often observed that the Noise
generated by the DG set exceeds the CPCB limit.
In the above case, Acoustical Enclosure with 30+ dB should be
implemented for the Acoustical Enclosure.
3 Cooling Tower 85 dB
The main source of noise in cooling tower is the noise generated of falling
water. In order to overcome the same, a noise barrier shall be constructed
to reduce the noise levels.
Also the pumps used in the cooling tower shall be provided with Acoustic
enclosures.
4 Vehicular
Movement < 70 dB
The SPL for regular vehicle movement is below 70 dB and no mitigations
are necessary for this source of noise.
5 Trucks Movement < 85 dB
Trucks can get noisy and generate SPL up to 90 dB. The only mitigation
possible for this source is to do regular maintenance of the trucks and keep
their Sound Levels at lowest possible levels.
In case any kind of Loading/Unloading is involved, the loading/unloading
should not be done during the night time, during which it may cause more
disturbance to the surrounding.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 130
4.4 WATER ENVIRONMENT
A number of sources in production of proposed products can cause potential impacts on water environment namely
ground water, surface water and effluent generation, which include impacts:
During Pre-construction phase
During Commissioning stage
During Operation phase
Based on the identified project activities impact on water environment is accessed. Scoring of the same is done based
on the methodology provided in Annexure 31.
Mitigation measures based on these scores are tabulated in Table 4-15.
4.4.1 Mitigation Measures for Impacts on Surface Water
Ground water is not abstracted for any plant activities since the water supply will be available on continuous and
uninterrupted basis from GIDC. The plant will be paved, therefore the likelihood of contaminants entering groundwater
and harming the same is improbable (i.e. unlikely).
Following mitigation measures will be implemented to reduce surface water related impacts:
Coal yard will be provided with proper bunds to avoid run-off contamination.
Maximum condensate will be recovered from the boiler to reduce the fresh water demand;
Rain water harvesting will be adopted for the conservation of water;
Regular maintenance of effluent treatment plant will be done to ensure smooth operation;
No discharge of untreated waste water on land;
Zero effluent discharge criteria for proposed 67 MW power plant will be met. Rest of the effluent from other plants
will be treated in existing ETP and will be disposed to GIDC Drain after meeting the GPCB effluent discharge norms.
Separate drains for storm water and effluent will be provided for proposed expansion project to avoid any
contamination of surface water sources;
All chemical and fuel storage and handling areas will be provided with proper bunds & dyke walls to avoid run-off
contamination during rainy season.
The overall impact on surface water quality will be negligible by followed all precautionary measures as mentioned in
mitigation measures.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 131
Table 4-15: Impact Scoring and Mitigation Measures for Water Environment
S
No. Project Activity Identified Aspect
N /
AN
/ E
Water
Legal
Impact Scoring Significance /
Consequence Operation Controls / Mitigation Measures
EMP
Required SW GW Effluent /
Sewage
Severity,
S
Probability,
P
Final Score,
S x P
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14
1 Project Design
1.1 Design & selection of technology,
equipment / site layouts, etc.
Non-compliance of Environmental standards due
to failure in designs of settling tank AN • • • Yes 5 1 5 Less Severe
Proper design of settling tank shall be done to meet the
environmental standards. No
2 Project Construction
2.1 Influx of Construction Workers Domestic wastewater generation N • Yes -- -- -- Significant Sewage will be disposed into soak pit and septic tank.
Regular cleaning will be carried out. Yes
3 Power Plant Operation
3.1 Coal & Limestone storage and stock
pilling
Wastewater Generation (From excess water
hydrant during fire) E • No 2 1 2 Less Severe
Onsite and Offsite emergency plan will be followed. Fire
fighting & emergency response team will be at place.
Preventive maintenance schedule in place.
No
3.2 Operation of DM Plant Wastewater Generation (Acidic / Alkaline waste
water including resins) N • No -- -- -- Significant
Effluent will be diverted to settling tank via properly
designed channel. Yes
3.3 Operations of Boilers & Turbines Wastewater Generation (Boiler blow down) N • No -- -- -- Significant Effluent will be diverted to settling tank via properly
designed channel. Yes
3.4 Handling of Fly Ash Wastewater Generation (excess water sprinkling
in Ash pond) AN • No -- -- -- Significant
Effluent will be diverted to settling tank via properly
designed channel. Yes
4 General & Utilities
4.1
Operation of other utilities like Cooling
Tower, Compressor, Pumps, Blowers
etc. & Floor Washing.
Wastewater generation (Cooling tower blow
down, shaft leaks, washings etc.) N • No -- -- -- Significant
Effluent will be diverted to settling tank via properly
designed channel. RHW will be implemented. Yes
Leakages in HSD tank AN • No 5 1 5 Less Severe
Dyke wall will be provided to avoid run-off contamination
and leaked fuel shall be immediately transferred to the
spare tank. Use of spill control measures, mechanical
handling, PPE’s shall be mandatory while handling the
chemicals to avoid spillages.
No
4.2 Operation of ETP (Settling tank)
Overflow of excess effluent generated due to
abnormal operation/ breakdown of ETP (settling
tank)
AN • No 5 1 5 Less Severe Plant will be shut down. No
4.3 Operation of STP Overflow of domestic waste water (due to
abnormal operation/ breakdown of STP) AN • No 5 1 5 Less Severe
Domestic waste water is collected in Septic Tanks/Soak
Pits and shall be treated in STP No
4.4 Analysis in laboratory Waste water generation N • No 1 3 3 Negligible -- No
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 132
4.5 LAND ENVIRONMENT
Impact Assessment for proposed project is carried out based on the methodology described in Annexure 31.
Potential impacts on land use and land cover are described in following section:
4.5.1 Land Acquisition leading to change in Land Use / Cover
The project is expansion project within the boundary of existing plant so there will not be further land acquisition.
4.5.2 Site Preparation
Clearance of land
The land use pattern of the project site will not get affected since it is within factory premises. But land cover gets
affected typically from conversion of scrub, open vegetation, land without scrub to build up land i.e. industrial use.
Preparation of Access Roads
The project site approach roads are developed so there will be no land acquisition. But the internal roads within the
project boundary will be developed, this aspect is being considered in construction of site.
Excavation and Paving of Site
Excavation and paving of site to allow for the impact loads due to construction activities will lead to minor impacts on
land use. This may change the ground level and affect the topography. The excavated soil will be used for leveling the
premises and care should be taken for disposal of the remaining.
4.5.3 Green Belt Development
Due to the well-developed and maintenance of green belt within project premises, a positive impact is envisaged during
operation phase. Aesthetic looks of project site will be enhanced.
Considering the above impacts and operating and other conditions mentioned in Section 4.5.1 to Section 4.5.4, the
impact scores on land environment are likely to be as mentioned in Table 4-16.
4.5.4 Mitigation Measures for Impact on Land Use / Land Cover
Mitigation measures for conserving land use and land cover will include the following:
The vegetation cover clearing will only be done on which construction is to take place;
Reuse of earth material generated during excavation will be done;
Optimization of land requirement through proper site lay out design will be done;
Fly ash will be given to cement manufacturer, brick manufacturing unit and for road construction;
Storage areas for hazardous waste, fuel & raw material will be impervious and will be designed to prevent Leachate
penetration;
Generated hazardous wastes during project operation will be transported to an authorized TSDF operator.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 133
Table 4-16: Impact Scoring and Mitigation Measures for Solid & Haz. Waste and Land Environment
S
No. Project Activity Identified Aspect
N
/
AN
/
E
Land
Legal
Impact Scoring
Significance /
Consequence Operation Controls / Mitigation Measures
EMP
Required LU /
LC Soil HW ISW MSW
Severity,
S
Probability,
P
Final Score,
S x P
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16
1 Project Design
1.1 Design & selection of technology,
equipment / site layouts, etc.
Non-compliance of Environmental
standards due to failure in designs
of the Hazardous waste storage
area.
• • • No 5 1 5 Less Severe
Properly designed storage area for hazardous waste with adequate
capacity will be ensured. Prior permissions for TSDF will be taken
and prior agreements with authorized vendors shall be made.
No
2 Project Construction
2.1
Excavation and paving of site,
Movement of JCBs, other machinery,
workers / labors etc.
Generation of Debris N • No 2 5 10 Moderate Severe Debris will be used as filling material at low lying areas. No
2.2
Heavy fabrication work for erecting
major plant equipment including
operation of equipment like crane,
concrete mixtures, vibrators etc.
Generation of Scraps N • No 2 5 10 Moderate Severe Scraps will be handles as per rules and sold to authorized vendors No
2.3 Influx of Construction Workers Sewage Sludge generation N • 2 5 10 Moderate Severe Proper disposal of sewage sludge will be carried out as per rules. No
3 Power Plant Operation
3.1 Coal & Limestone storage and stock
pilling Generation of dust N • No 1 5 5 Less Severe Water Sprinkling will be carried out as and when required No
3.2 Operations of Boilers & Turbines
Deposition of PM, SO2, NOx
emitted from stacks N • No 1 5 5 Less Severe
SOP’s will be followed. Based on APCM, PM & SO2 shall remain well
within the CPCB standards. No
Generation of Bottom and Fly Ash N • No -- -- -- Significant Ash will be used in cement plant or it will be sold to brick
manufacturers. Yes
4 General & Utilities
4.1
Operation of other utilities like
Cooling Tower, Compressor, Pumps,
Blowers etc. & Floor Washing.
Generation of Used/spent oil,
waste/residue containing oil,
contaminated hand gloves,
discarded containers / barrels /
bags
N • Yes -- -- -- Significant
Used/spent oil will be sold to authorized Recyclers, Waste/residue
containing oil disposed off to CHWIF. Contaminated hand gloves,
discarded containers / barrels / bags shall be sold to authorized
vendors.
Yes
4.2 Operation of ETP (settling tank) Spillage of effluent AN • No 4 2 8 Moderate Severe Dyke wall with proper flooring shall be made. SOP’s will be
followed. No
4.3 Equipment maintenance Generation of scraps, used spares,
cotton waste, hand gloves etc. N • Yes -- -- -- Significant
Scraps, used spares, cotton waste, contaminated hand gloves,
discarded containers / barrels / bags shall be sold to authorized
vendors.
Yes
4.4 Analysis in laboratory Generation of Broken Glassware AN No • No 3 2 6 Less Severe Collected, stored and disposed as per HW rules amended till date. No
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 134
4.6 ECOLOGY & BIODIVERSITY
4.6.1 Ecological Impact Assessment Methodology
Impacts on ecological components are identified by various methodologies which are explained in detail in Annexure
31.
Possible Impacts
During construction phase, increase in deposition of dust and dust settling on the vegetation may alter or limit
plant’s abilities to photosynthesize and / or reproduce;
Habitation fragmentation due to clearance of existing scrub cover during site preparation;
Mitigation measures to conserve Ecology and Biodiversity
Since the proposed project is located within the existing factory premises there will be no significant or permanent
impact on the habitat structure of associated faunal diversity.
As the emissions from the plant will be regulated and minimal with respect to the specified norms, and with a very
healthy existing developed greenbelt at the site in the form of several species, the biological environment will be
protected.
Every year survival rate of the plantation within project site will be monitored and accordingly greenbelt will be
maintained.
Considering the above mitigation measures the impact scores on biological environment are likely to be as mentioned in
Table 4-17.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 135
Table 4-17: Impact Scoring and Mitigation Measures for Ecology & Biodiversity Environment
S.
No.
Project Aspect
Description
Likely Impacts on Ecology
and Biodiversity (EB)
Impact Consequence - Probability
Description / Justification Legal
Impact Scoring Significance /
Consequence Mitigation Measures
EMP
Required Severity,
S
Probability,
P
Final Score,
S x P
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11
1. Construction Phase
1.1
Noise generation due to
movement of JCBs, other
machinery, Heavy
fabrication work &
Vehicular Movement
Site specific disturbance to
faunal species
Species reported from project site and
buffer zone are common / generalist
species of the local environment and not
very sensitive to the routine activities of the
urban and peri-urban area, so there will be
no threat of facing disturbance. However,
its site specific and temporary impact.
No 1 5 5 Less Severe
Operation subject to periodic monitoring / surveillance.
However, all species reported from project site are common and
well adapted to the routine urban activities, so they will not face
significant impact on their normal movements. However,
greenbelt development will help to recall these temporary
displaced species.
No
2. Project operation Phase
2.1
Emission of dust due to
vehicular movement,
Handling and Crushing of
Coal, Limestone & Fly ash.
Emission of PM, SO2, NOx
operation of Boilers.
Impact on surrounding
vegetation and associated
biodiversity.
Though the emission levels of all pollutants
will be kept within permissible limits,
considering cumulative impact, minor short
term impacts are expected on surrounding
flora and associated fauna which may be
resilient. In case of leakage proper Disaster
management plan has been prepared by
the company and immediate action will be
taken.
Yes -- -- -- Significant
Operation subject to management by operational controls.
Emission levels of all pollutants will be kept within permissible
levels through various engineering control measures. However,
green belt development with suitable species will help to
mitigate likely cumulative impacts.
Yes
2.2
Noise Generation (due to
operation of boilers,
generators, compressors,
pumps, blowers)
3. General Utilities
3.1
Generation of SPM and
emission of HC & CO due
to vehicular movement
Impact on surrounding
vegetation and associated
biodiversity.
Though the emission levels of emitted
pollutants will kept within permissible limits,
considering cumulative impact, minor short
term impacts are expected on surrounding
habitats and associated biodiversity which
may be resilient.
No 2 5 10 Moderate Severe
Operation subject to management by operational controls.
Emission levels of all pollutants will be kept within permissible
levels through various engineering control measures. However,
green belt development with suitable species will help to
mitigate likely cumulative impacts.
No
3.2 Mixing of contaminated
water into storm water
Contamination of surrounding
water bodies and associated
aquatic biodiversity.
Also, all the potential contaminant (solid
and liquid) will be stored in closed area, so
that rain water / storm water will not get
contaminated.
No 1 5 5 Less Severe Operation subject to periodic monitoring / surveillance. No
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 136
4.7 SOCIO-ECONOMIC ENVIRONMENT
Based on the socio-economic survey and stakeholder consultation the following social concerns have been identified
with respect to the general condition of the nearby residents / villages of study area. The suggestive mitigation
measures has been reflected in Table 4-18.
Table 4-18: Issues Raised by the Respondents of the Core Zone
Social Component Issues raised/Problems Community Welfare/Enhancement Measures by
the Project Proponent
Health and Hygiene
Open defecation by the villagers.
The medical/health facilities are limited in the
study area.
The Project Proponent will take the initiative to ensure
to put up health checkup camps and doctor’s visit at
regular intervals.
Drinking Water
Scarcity of potable water in the surrounding
villages.
Lack of potable water in primary schools.
The project proponent in co-ordination with local bodies
will monitor regular supply of drinking water.
Proper co-ordination and follow up will be carried out
by the project proponent with PCPIR & SEZ for regular
supply of safe drinking water.
Education
Lower literacy rate of the females.
Construction/renovation of school rooms is
required.
Construction of toilet is required.
Renovation of Anganwadi & Primary School
buildings is required.
The project proponent will ensure to do its part
according to the funds available and on the priority
basis.
Sanitation & Drainage
System Inadequate household toilets.
The project proponent will give its contribution in the
construction of sanitary toilets for households.
Employment
Employment Generation for local population.
The daily wage earners are in substantial
number present in the study villages.
Skill development programme will be organized by the
project proponent at regular interval and accordingly
the local population will be given preference in the job
opportunities.
Construction/Renovation
Construction/up gradation of the internal village
road is required.
Dahej Awas Yojna, 2015 for the SC & ST is
under process.
As part of Community Welfare Program the project
proponent will consider to contribute for the mentioned
works of construction and renovation.
Source: Community Consultation-2016.
4.7.1 Occupational Health and Risk to Surrounding Communities
A detailed risk assessment and consequence analysis study is carried out in Chapter 7, Section 7.2. This includes
Hazards Identification, Selection of Potential Loss Scenarios, Simulation of release source model and Plotting of contour
maps.
On the basis of this risk assessment study MLCs have been selected and studied. A detailed impact scoring was under
taken and presented in Table 4-19, including the general safety measures and mitigation measures.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 4. ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 137
Table 4-19: Impact Scoring and Mitigation Measures for OH, Community Health and Safety
Code Impacting Activity Impact Scoring
Basis of Scoring Mitigation Measures C P C × P
1 Chlorine (Cylinder)
1 mm leak
-3 2 -6
C=3 as IDLH is low
P=2 as sufficient safety
measures
Alternate Level Indicator Transmitters, Pressure
Gauges and Flow switches have been provided
Fire Fighting system (Fire Hydrant system, Water
Curtain)
Chlorine Scrubber System with double efficient
blower
Specific Chlorine Detector Alarm panel with
localized Hooter will be provided
2 mm leak
2 HSD
Leak
-2 2 -4
C=2 as Flash point is
low
P=2 as sufficient safety
measures
Respective Control Room Catastrophic Rupture
C: Consequence; P: Probability; C x P: Final Score
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT
4. ANTICIPATED
ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 138
4.7.2 General Safety Measures
Considering the various chemicals handled and stored at site, following safety measures are already provided at the
site.
Requisite personnel protective equipment is provided. Instruction/Notice to wear the same is displayed.
Further, it is insisted to use the same while at work.
Provision of safety shower with eye washer.
MSDS of all hazardous chemicals is available at office and with responsible persons.
Antidotes for all chemicals being used as per MSDS is available at the site.
Regular training programme for safety awareness.
Provisions of First Aid Box and trained person in first aid.
Prohibition on eating, drinking or smoking at work-area.
Any leakage/spillage of liquid chemical is immediately attended.
Work area is monitored to maintain work environment free from any dust/chemicals-fumes/vapours and to
keep well within below permissible limit.
Provision of adequate Fire Extinguishers at site and training is imparted to the workers also.
Maintaining the Fire-Protection System adequately.
Availability of Self Breathing Apparatus at site.
Provisions of immediate accident/incident reporting and investigation.
Instructions on Emergency/Disaster is displayed.
Safety Posters and slogans is exhibited at conspicuous places.
Arrangement of Periodical Training to workers and supervisors.
Work permit systems is strictly followed.
Safety Committee is constituted and safety, health and environmental matters/issues are discussed in the
meeting and enlighten the participants in these respect.
4.7.3 Mitigation Measures
Spill management plan to prevent risk of spill which may cause health problem.
Emergency management system (off-site & onsite emergency plan) will be followed to tackle any emergency
situation for proposed facilities.
Medical checkup would be carried out at an regular intervals;
During site preparation proper care would be taken by MFL, appropriate PPEs will be provided to site workers
and staff members;
Appropriate personnel protective clothing to be used to prevent skin contact;
Safety Goggles will be used to prevent eye contact;
Hand gloves of natural rubber, neoprene, and polyvinyl chloride will be used as and when required.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 5. ANALYSIS OF ALTERNATIVES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 139
5 ANALYSIS OF ALTERNATIVES
5.1 SITE SELECTION
The proposed expansion will be carried out within the existing factory premises. Hence, no analysis of alternatives
has been carried out.
5.2 EXISTING SITE
The existing site offers the following specific advantages:
Sufficient land is available for setting up the project and allied facilities;
Water storage infrastructure;
Internal communication facilities;
Well connected with national and state highway;
Availability of existing go downs, storage tank and storage sheds;
Close proximity to market;
Availability of coal in close proximity;
Located in GIDC Industrial Estate of Dahej.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL
MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 140
6 ENVIRONMENTAL MONITORING PROGRAM
Based on the identified aspects from the proposed activities on air, noise, water, land, ecology and biodiversity and
socio-economic environment, scoring were done based on its severity and probability as discussed in Chapter 4.
Thus, monitoring program is required for each environment based on its consequence. The preliminary budgetary
monitoring plans are as discussed in this chapter. These EMPs are based on the technical aspects of monitoring the
effectiveness of mitigation measures (incl. Measurement methodologies, frequency, location, data analysis,
reporting schedules, emergency procedures, detailed budget & procurement schedules).
Main objective of environmental monitoring program is to:
Measure effectiveness of operational procedures;
Confirm statutory and mandatory compliance;
Identify unexpected changes.
6.1 AIR ENVIRONMENT
Budgetary environment monitoring plan for air environment is given in Table 6-1. Traffic Management Plan is
given in Table 6-2.
6.2 NOISE ENVIRONMENT
Budgetary environment monitoring plan for Noise environment is given Table 6-3.
6.3 WATER ENVIRONMENT
Budgetary environment monitoring plan for Water environment is tabulated in Table 6-4.
6.4 LAND ENVIRONMENT
Budgetary environment monitoring plan for Land environment as Land use / Land cover, solid hazardous waste
management and soil conservation are tabulated in Table 6-5.
6.5 ECOLOGY & BIODIVERSITY
Budgetary environment monitoring plan for Ecology and biodiversity is tabulated in Table 6-6.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 141
Table 6-1: Budgetary Environment Monitoring Plan for Air Environment
Impacting
Activity
Operation Controls /
Mitigation Measures
Implementation and Management
Remark Data Analysis
Measurement
Methodology Frequency Location
Reporting
Schedule /
Responsibility
Emergency
Procedure
Budget for
Mitigation Measure
- (in INR Crores)
Approximate
Recurring Cost –
(in INR Crores)
Procurement
Schedule
Power Plant Project Operation
Operations of
Boilers &
Turbines
ESP will be provided.
Limestone dosing will be
done to control SO2
emissions. Stack height of 65
m will be provided for proper
dispersion. Online meter for
PM, SO2 & NOx will be
provided.
PM, SO2, NOx in
stack.
Online PM, SO2 & NOx Continuous Stacks attached
to Boilers Power Plant Manager
ERP will be
followed &
Mandatory
inspection of
each equipment
shall be done as
per the
requirements.
Capital Cost:
1) Stack = 2.5
2) ESP = 3.0
3) Online monitoring
system = 0.5
Recurring Cost:
Cost of maintaining
the same =
0.05+0.75+0.05 =
0.85
During operation
phase
Capital Cost: Cost of
Stack, APC like ESP, online
monitoring systems.
Recurring Cost: Cost of
maintaining the same.
Stack monitoring by
Isokinetic sampling IS:
11255.
Monthly Stacks attached
to Boilers Power Plant Manager
CAAQMS Online PM10, PM2.5, SO2 &
NOx Continuous
Near Admin
Building EHS Head
PM10, PM2.5, SO2,
NOx in ambient
air and within
plant premise
PM10 - Gravimetric IS:
5182 (Part 23) 2006.
Monthly
3 Locations
within site
(Near ETP,
Canteen & Main
Lab)
Third Party
PM2.5 - Gravimetric IS:
5182.
SO2 - Colorimetric IS:
5182: (Part II) 2001.
NOx - Colorimetric IS:
5182: (Part VI) 2006.
Handling of Fly
Ash
Ash Handling and
Management plan will be
prepared and followed. Dust
collection system will be
installed at transfer tower,
crusher house, top of silo &
bunker tower.
Fly Ash
Quantity of fly ash
generation and maintain
the Register
Daily Weigh bridge
browser. Power Plant Manager
Water Sprinkling
will be carried
out.
Capital Cost:
1) Ash Silo = 1.5
Recurring Cost:
1) Ash handling =
0.15
During operation
phase.
Capital Cost: Cost of Silo,
APC like Bag filters.
Recurring Cost:
Maintenance of the APC
equipment and cost of ash
handling.
General & Utilities
Vehicular
movement for
transportation of
raw materials,
Industrial Waste.
Water sprinkling will be
done. PUCC Certified
vehicles will be used. Traffic
management will be
ensured.
PUCC Certificate To ensure Valid PUCC
certificate.
If considerable
emissions
observed during
operations.
With Drivers at
main gate Security Officer
Vehicles without
PUC certificates
will not be used.
-- -- During construction
and operation phase. --
Capital Cost (in INR Crores) 7.5 During Commissioning Phase
Recurring Cost (in INR Crores) 1 During Operation Phase
Total Cost for EMP (in INR Crores) 8.5 --
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 142
Table 6-2: Traffic Management Plan
Objective To ensure that there is smooth traffic both within and outside the facility for the duration of the construction phase and operation phase
Benefit of EMP Smooth and congestion free traffic operation
Impacting Activity Mitigation Measures
Implementation and Management
Remark Data Analysis
Measurement
Methodology Frequency Location Reporting Schedule/Responsibility Emergency Procedure
C1 C2 C3 C4 C5 C6 C7 C8 C14
Movement of vehicles
throughout the
construction phase
and operational phase
Controlled vehicular movement
(preferably with clearly demarcated
entry / exit) with adequate
supervision
Records of No. of
tankers entering and
exiting the site.
Manual Throughout construction and
operation phase Main Gate Security In charge
Route for safe exit will be
in place. --
Segregation of vehicular and
pedestrian area -- --
Throughout construction and
operation phase -- Security In charge
Route for safe exit will be
in place. --
Vehicle entry and exit scheduling so
that traffic congestion is not created
on the public road leading to the
site.
-- -- Throughout construction and
operation phase -- Security In charge
Route for safe exit will be
in place. --
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 143
Table 6-3: Budgetary Environment Monitoring Plan for Noise Environment.
Impacting
Activity
Operation Controls /
Mitigation Measures
Implementation and Management
Remark Data Analysis
Measurement
Methodology Frequency Location
Reporting
Schedule /
Responsibility
Emergency
Procedure
Budget for
Mitigation Measure -
(in INR Crores)
Approximate
Recurring Cost –
(in INR Crores)
Procurement
Schedule
Power Plant
Operation
Operations of
Boilers &
Turbines
Provision of Silencer in
main stream line safety
valve, and before turbine
for steam venting during
startup of turbine.
PPE like Ear Plugs & ear
muffs will be provided and
its use shall be ensured.
No operators shall be
allowed to do two
continuous shifts.
Noise Levels ISLM 100 Once a Month Plant Area Contractor / Third
Party
Regular
Maintenance of
equipment to
be done.
Capital Cost:
1) Installation of
silencers = 0.08
Recurring Cost:
1) Monitoring cost
of regular Noise =
0.01
During operation
phase
Capital Cost: Installation
of silencers.
Recurring Cost:
Monitoring cost of regular
Noise measurements.
General &
Utilities
Operation of
other utilities like
Cooling Tower,
Compressor,
Pumps, Blowers
etc. & Floor
Washing.
SOP's, OCP and OEP will
be followed during
startup. Acoustic
enclosures will be built-in
with equipment by
technology provider. PPEs
like Ear Plugs & ear muffs
will be provided and its
use shall be ensured.
Noise Levels ISLM 100 Once a Month
Utilities Area (2
locations within
plant)
Contractor / Third
Party
Regular
Maintenance of
equipment to
be done.
- Recurring Cost:
1) PPEs = 0.20
During operation
phase
Capital Cost: -
Recurring Cost: Cost of
PPE.
Capital Cost (in INR Crores) 0.08 During Commissioning Phase
Recurring Cost (in INR Crores) 0.21 During Operation Phase
Total Cost for EMP (in INR Crores) 0.29 --
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 144
Table 6-4: Budgetary Environment Monitoring Plan for Water Environment
Impacting
Activity
Operation Controls /
Mitigation Measures
Implementation and Management
Remark Data Analysis
Measurement
Methodology Frequency Location
Reporting
Schedule /
Responsibility
Emergency
Procedure
Budget for
Mitigation Measure -
(in INR Crores)
Approximate
Recurring Cost –
(in INR Crores)
Procurement
Schedule
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12
Project
Construction
Influx of
Construction
Workers
Sewage will be disposed
into soak pit and septic
tank. Regular cleaning will
be carried out.
-- -- -- -- -- -- - - - Existing Sanitation system
is already in place.
Power Plant
Operation
Operation of DM
Plant
Effluent will be diverted to
settling tank via properly
designed channel.
pH, TSS, TDS Manual Twice in a shift Neutralization
Tank
Section Incharge of
Power Plant
Dosing will be
done properly.
Capital cost:
1) Settling tank = 0.5
Recurring cost:
1) Maintenance
cost = 0.1
During operation
phase
Capital Cost: Cost of
Settling tank. Recurring
cost: Maintenance cost
including chemical & dosing
material. Monitoring cost of
effluent & waste water.
Operations of
Boilers &
Turbines
Handling of Fly
Ash Flow / Quantity Water Meter Continuous Ash pond Utility Incharge
Ash Management
plan will followed.
Capital cost:
1) Water Meter =
0.005
- During operation
phase
Capital Cost: Water
meter.
General &
Utilities
Operation of
other utilities like
Cooling Tower,
Compressor,
Pumps, Blowers
etc. & Floor
Washing.
Effluent will be diverted to
settling tank via properly.
RHW will be implemented.
pH, TSS, TDS. Manual Twice in a shift
Various
locations in
Utility Section
Utility Incharge
Dyke walls will be
provided and
leakages shall be
pumped back in
spare tank
Capital Cost:
1) Dyke walls = 0.75
2) RWH = 0.75
Recurring cost:
1) Regular
cleaning = 0.06
During operation
phase
Capital Cost: Upgrading
storm water lines as a part
of RWH, Dyke walls.
Recurring cost:
Maintenance cost to run
common ETP & regular
cleaning of channels.
Capital Cost (in INR Crores) 2.005 During Commissioning Phase
Recurring Cost (in INR Crores) 0.16 During Operation Phase
Total Cost for EMP (in INR Crores) 2.165 --
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 145
Table 6-5: Budgetary Environment Monitoring Plan for Solid & Hazardous Waste Management and Land Environment
Impacting
Activity
Operation Controls /
Mitigation Measures
Implementation and Management
Remark Data Analysis
Measurement
Methodology Frequency Location
Reporting
Schedule /
Responsibility
Emergency
Procedure
Budget for
Mitigation Measure -
(in INR Crores)
Approximate
Recurring Cost –
(in INR Crores)
Procurement
Schedule
Power Plant
Operation
Operations of
Boilers &
Turbines
Ash will be used in
cement plant or it will be
sold to brick
manufacturers.
Fly Ash RG1 Register Daily Weigh bridge
browser. Power Plant Manager
Water
Sprinkling will
be carried out.
Covered in AP Section During operation
phase.
Capital Cost: -.
Recurring Cost: Cost of
ash handling.
General &
Utilities
Records of trucks
carrying HW.
Number of trucks:
Manually.
Weight of truck: Weight
stand.
During dispatch Main Gate Utility and Security
Incharge.
Storage for
atleast 45 days
is provided.
Capital Cost:
1) HW Storage facility
= 0.2
Recurring Cost:
Membership fees
for disposing HW –
0.05
During operation
phase
Capital Cost: Storage silos
& HW facility. Recurring
Cost: Membership fees for
disposing of HW to TSDF
and handling HW and
maintaining the storage
facility.
Operation of
other utilities like
Cooling Tower,
Compressor,
Pumps, Blowers
etc. & Floor
Washing.
Used/spent oil will be sold
to authorized Recyclers,
Waste/residue containing
oil disposed off to CHWIF.
Contaminated hand
gloves, discarded
containers / barrels / bags
shall be sold to authorized
vendors.
Equipment
maintenance
Scraps, used spares,
cotton waste,
contaminated hand
gloves, discarded
containers / barrels / bags
shall be sold to authorized
vendors.
Capital Cost (in INR Crores) 0.2 During Commissioning Phase
Recurring Cost (in INR Crores) 0.05 During Operation Phase
Total Cost for EMP (in INR Crores) 0.25 --
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 146
Table 6-6: Budgetary Environment Monitoring Plan for Ecology and Biodiversity
Impacting Activity
Operation
Controls /
Mitigation
Measures
Implementation and Management
Remark Data
Analysis
Measurement
Methodology Frequency Location
Reporting
Schedule /
Responsibility
Emergency
Procedure
Budget for
Mitigation Measure -
(in INR Crores)
Approximate
Recurring Cost
– (in INR
Crores)
Procurement
Schedule
Project Operation
Emission of dust due to vehicular
movement, Handling and
Crushing of Coal, Limestone & Fly
ash. Emission of PM, SO2, NOx
operation of Boilers. Noise
Generation (due to operation of
boilers, generators, compressors,
pumps, blowers)
Green belt will be
maintained in the
total plot area.
Tree
plantation
Counts &
survival rate
Manual
During start
of
construction
phase
Within plant
premises and
around Likely
Impact Zone
HR Manager
Minimum of
33% Green belt
shall be
maintained.
Capital cost:
1) Saplings = 0.1
Recurring Cost:
1) Greenbelt
Maintenance =
0.002
During Construction
& Operation phase
Capital cost: Cost for
saplings in and around
project site. Recurring
Cost: Maintenance of
Greenbelt
Capital Cost (in INR Crores) 0.10 During Commissioning phase.
Recurring Cost (in INR Crores) 0.002 During Operation phase.
Total Cost for EMP (in INR Crores) 0.102 --
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL
MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 147
6.6 ENVIRONMENTAL MONITORING AND MANAGEMENT COST
Total cost of the project is ~ INR 230 Crore. Expenditure to be incurred by MFL on environmental monitoring and
management including capital and recurring cost (annually) is tabulated in Table 6-7.
Table 6-7: Environmental Monitoring and Management Cost
S
No. Head
Approximate
Capital cost
(INR in
Crores)
Approximate
Recurring cost
per Annum (INR
in Crores)
Basis for Cost Estimates
1
Air Pollution
Control &
Monitoring
7.5 1.0
Capital cost: Cost of Stack, Silos, APC like ESP, Bag filters,
online monitoring systems, Ash handling unit etc.
Recurring cost: Annual Cost for repairs / maintenance of
sensors, all APC equipment, monitoring of AAQM at the
project site for parameters as per CCA by hiring third party
and payment of various statutory fees to regulatory agencies.
2 Noise Pollution
Control 0.08 0.21
Capital cost: Installation of Silencers / acoustic enclosures.
Recurring cost: Cost of PPE, monitoring cost of regular
noise monitoring.
3
Water Pollution
Control &
monitoring
2.005 0.16
Capital cost: Installation of RO, upgrading storm water lines
as a part of RWH, Water meter & Dyke walls.
Recurring cost: Maintenance cost to run RO. Clean-up of
drains. Monitoring cost of effluent and waste water.
4
Solid and
Hazardous waste
management
0.2 0.05
Capital cost: Cost of Upgradation of Storage silos.
Recurring cost: Membership fees for disposing of HW to
TSDF and handling HW and maintaining the storage facility
5 Ecology and
Biodiversity 0.11 0.002
Capital cost: Cost for saplings in and around project site.
Recurring cost: Maintenance of green belt.
Total Amount in
Crores 9.9 1.4
Various environmental parameters to be monitored post EC are summarized in Table 6-8.
Table 6-8: Summary of Post EC Environmental Monitoring Plan
S.
No.
Environmental Component /
Parameter
Frequency of
monitoring Location
1 PM10, PM2.5, SO2, NOx, in ambient air. Continuous (Online) Near Admin Building.
2 PM10, PM2.5, SO2, NOx, in ambient air. Monthly 3 Locations within site (Near ETP, Canteen &
Main Lab)
3 Noise levels Monthly Two locations in each units and Utilities Area
4 Flow (Quantity) Continuous (Online) GIDC Inlet, Plant wise inlets & Effluent outlet to
ETP & at Final disposal point into GIDC Drain
5 pH & TOC Continuous (Online) Final disposal point into GIDC Drain
6 TDS, SS, COD & BOD Monthly ETP Outlet
7 DO, TDS, SS, COD Daily ETP Outlet
9 Quantity of Hazardous waste generated During Dispatch of Trucks
(Once/Twice in a month) Main Gate
10 Soil analysis for EC, pH, permeability
and ESP
Pre & post monsoon / in
the event of accidental
spillage
At Site
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 6. ENVIRONMENTAL
MONITORING PROGRAM
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 148
6.7 SOCIO-ECONOMIC ENVIRONMENT (CSR/ESC ACTIVITIES)
As per the Table 4-18, the major issues in the communities is inadequate supply of drinking water, open
defecation, unemployment etc. Hence MFL has proposed Enterprise Social Commitment (Initial 5 Years). Details of
the ESC are provided in Table 6-9.
Table 6-9: Enterprise Social Commitment (Initial 5 Years)
S.
No. Proposed Activity
Amount (INR/Lakhs) per year
2019-20 2020-21 2021-22 2022-23 2023-24 Total
Amount
1 Education 35 38 42 46 50 211
2 Health Care Services 29 32 35 39 43 180
3 Housing & Sanitation 71 78 86 95 104 434
4 Water facilities 19 21 23 25 28 115
5 Infrastructure Development 35 38 42 46 50 211
Total Amount per Year 189 207 228 251 276 1,150
Total provision for 5 years - Approximately Rupees Eleven Crore Fifty Lacs
Further in case 2% of average reported net profits of the company are in excess of the above figures for any year,
a portion of such funds can be made available for CSR activities within the study area under the Companies Act,
2013.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 149
7 ADDITIONAL STUDIES
7.1 PUBLIC CONSULTATION
This draft EIA report is being submitted for Public Hearing. Thus, this section shall be updated once Public Hearing
Minutes of Meeting from GPCB is available.
7.2 RISK ASSESSMENT
7.2.1 Consequence Analysis
Key issues in Risk Assessment (RA) of the proposed project are discussed in this chapter. The risk assessment
process is intended to identify probable hazards in the work environment and all operations, to quantify the hazards
and to assess the risk levels of those hazards in order to prioritize those that need an immediate attention.
In the unlikely event that an abnormal consequence has occurred, the disaster management kicks in. This includes
prescribing the procedures pertaining to a number of issues such as communication, encounter, rescue,
rehabilitation and further steps to prevent recurrence of such consequence in future. These issues are addressed in
the disaster management plan.
Both, the RA and DMP are living documents and need to be updated whenever there are changes in operations,
equipment or procedures.
7.2.2 Methodology of Risk Assessment
The methodology includes,
Hazard identification,
Selection of potential loss scenarios,
Simulation of release source model on DNV’s PHAST 7.1,
Plotting the damage contour on site map.
These steps undertaken to carry out risk assessment for this project are described in following sections.
7.2.3 Hazard Identification
The project description, and other project related data provided by the client have been comprehensively reviewed
to identify the hazardous operations. Also the information on the hazardous properties (MSDS) of all the chemicals
handled at the site is available at the site.
Maximum Credible Loss Scenarios were not considered due to the following reasons:
Proposed project is for expansion of 67 MW power plant, which only requires coal & limestone, which are non-
hazardous. All other hazardous chemicals handled at site were already considered in previous EIA studies for
which EC is granted.
Auxiliary power will be sourced from existing power plant / grid. Thus, no DG sets are proposed for startup of
proposed unit.
On the basis of chemical properties like flash point, phase of chemical, operating conditions and total inventory
etc., it is noted that in the proposed power plant unit, there are no such storage of flammable raw materials
which can lead to uncontrolled release of hazardous material causing hazard.
Properties of hazardous material to be handled is provided in Table 7-1.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 150
Table 7-1: Properties of Hazardous Material to be Handled
S.
No. Material at Site Formula State Odour
Mol. Wt.
(g/mole)
Flash Point
(°C)
Melting
Point
(°C)
Boiling
Point
(°C)
IDLH
(ppm) Stability Hazard Color
Sp. Gr
(g/cc)
UEL
%
LEL
%
Odour
Threshold
(ppm)
1 Coal - Solid Odourless - - - - - Stable Flammable Black - - - -
2 Hydrochloric Acid HCl Liquid Pungent. Irritating
(Strong.) 36.46 -
−26 °C
(39.17% HCl
in water)
110 °C - Stable Corrosive Colorless to light
yellow
1.16
(32%
HCl)
- - 0.25 to 10
ppm
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 151
7.2.4 Disaster Management Plan (Overall Complex including Power Plant)
Emergency Organization
Introduction
In order to achieve above objectives the role of key personnel is clearly defined to avoid confusion and to meet the
emergency effectively. The Site Controller and the Incident Controller are the personnel for effective control of an
emergency. As per the emergency preparedness chart the success of control of an emergency situation depends
upon their timely action. The action for these persons and Emergency do’s and don’ts are given in this section.
Assembly Point
Assembly points will be earmarked during making of detailed Onsite Emergency Plan on Execution of the Project.
Emergency Control Centre
The Emergency Control Center (ECC) is the Place from where the emergency control operations to handle the
emergency are directed and controlled. It will be attended by Site Main Controller, Key Personnel and Senior
Officers of fire, Police, District Authorities and Emergency Services. The Center is equipped with telephone
Communication facility to keep contact with incident controller and areas of works as well as outside.
Emergency Control Organization is identified as following.
Site Controller,
Incident Controller, EHS Coordinator, Security Personnel,
Key Personnel,
Central Control Room,
Occupational Health Centre.
Figure 7-1: Emergency Control Organization Chart
Members of team will be evenly distributed in all the shifts and eight to ten members are available in the factory at
any point of time to handle the emergency situation. Team members will be given refresher training from time to
time.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 152
Personal Protective Equipment (PPE) Facilities to be maintained in ECC
Breathing Sets
Self-Contained Breathing Sets and spare cylinders will be available at different locations;
Emergency Life Saving Apparatus (ELSA) will be available at plant. Breathing time is 10 minutes for each set.
Eye Wash and Safety Shower
At different locations in the factory Eye wash fountain and safety shower assemblies are installed.
Safety Measures at Site
General safety measures are already discussed in Chapter 4, Section 4.7.2. Safety equipment already available
at Site are tabulated in Table 7-2.
Table 7-2: Safety Equipment Details
S.
No. Description
Available
Quantity Capacity / Type
1 Fire water & Process water 59,707 m3 Reservoir 1 – 31,533 m3, Reservoir 2 – 28,174 m3
2 Fire Hydrants pumps
Main Pump 3 Nos. 273 m3/Hr.
Jockey Pump 01 Nos.
01 Nos.
40 m3/Hr.
70 m3/Hr.
Diesel Pump 01 Nos. 273 m3/Hr.
3 Water sprinkler system
-Hydrogen plant
& dispatch area
-Cable gallery at
CPP plant.
Effective working pressure 1.4 to 7.0 Kg/Cm2
4 Water curtain system
-Surrounding
chlorine bullet
-14 Nos. water
curtain nozzle
Effective working pressure 1.4 to 3.5 Kg/Cm2
5 DCP type portable fire extinguishers 88 Nos. 5 kg
6 DCP type portable fire extinguishers 05 Nos. 10 kg
7 DCP type portable fire extinguishers 05 Nos. 50 kg
8 DCP type portable fire extinguishers 01 Nos. 75 Kg
9 CO2 type portable fire extinguishers 88 Nos. 4.5 Kg
10 CO2 type portable fire extinguishers 04 Nos. 6.5 Kg
11 CO2 type portable fire extinguishers 03 Nos. 22.5 Kg
12 Mechanical foam type fire extinguisher 07 Nos. 9 Ltr.
13 Mechanical foam type fire extinguisher 02 Nos. 50 Ltr.
14 Water Monitor 25 Nos.
15 Single hydrant 80 Nos.
16 Fire escape hydrant 31 Nos.
17 Hose Reel 14 Nos.
18 Fire escape hydrant new [CA] 32 Nos.
19 Fire escape hydrant new [POWER] 05Nos.
20 Emergency Siren 01 Nos. Testing Every Monday At 10.00 Hrs. C A Control
Room Phone No. 2321, 2322 Power Control Room
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 153
S.
No. Description
Available
Quantity Capacity / Type
Phone No. 2202, 2203
21 Emergency Chlorine Kit 02 Nos. Chlorine Bottling
22 Chlorine Detector on line with DCS 20
Chlorine Bottling 06, Chlorine Bullet 02, Hypo
Tower 01, Pump house 01, Coal yard no.3 -01,
ETP 01, Cl2 com 02, Cell house 02, HCL Scrubber
01, De-tower 01, NaOH dechlorination tower 01,
Security cabin 01.
23 Hydrogen Detector on line with DCS 01 Nos. Hydrogen filling area
24 Sulphur dioxide (SO2) Detector on line with DCS 02 Nos. sulphur dioxide (SO2) dosing area
25 Wind sock 05 Nos.
26 Emergency Assembly point 05 No.
27 Air line box 10 Nos.
28 PPE'S Box 06 Nos.
29 SAFETY SHOWER 40 Nos.
30 SLUICE VALVE
31 SCBA SET[self-contained breathing apparatus] 12 Nos.
32 Smoke / Heat Detector 66
33 Safety store 1
34 Fire store 1
35 OHC 1
Fire Fighting Agents
Water can be used when applied in the form of spray and to keep exposed material from being damaged by
the fire. It can be used to sweep the flames off the surface of liquid.
Water or foam may cause frothing when applied on flammable liquids having flash point above 100°C. Water
sprays has to be applied carefully by causing the frothing to occur on the surface and this foaming action
blankets and extinguishes the fire.
Water may be used to blanket fire and accomplish extinguishing. It must be applied gently to the surface of the
liquid.
Water may be ineffective except when applied gently to the surface to blanket and extinguish the fire.
Foam
Alcohol Resistant Foam
CO2
Dry Chemical Powder
First Aid/ Antidotes
Wash affected areas/ eyes with copious amounts of water.
Remove to fresh air/ administer Oxygen.
Artificial respiration.
Give copious drinks of water.
Induce vomiting.
Remove contaminated clothing.
Antibiotics/ steroid eye drops.
Administer portico steroid spray.
Analgesic for pain, antibiotic for prevention of infection.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 154
Fire Extinguisher
Fire extinguishers for emergency, located at strategic positions at each process plant, storage areas, security office
etc. The same area will be easily accessible, marked properly and maintained regularly. Following Fire Extinguishers
are provided;
Table 7-3: Details of Fire Extinguisher
S. No. Type of Fire Extinguisher
1 Carbon Dioxide (CO2)
2 Dry Chemical Powder (DCP)
3 Mechanical Foam (MF)
Fire Hydrant System
Fire Hydrants
Monitors
Hoses
15 m length
7.5 m length
Fire tender:
Water tank
Foam tank
DCP type FE
CO2 type FE
Water Sprinkler System
High velocity water sprinkler system
Fire water Tank
First Aid
Well-equipped first aid boxes made available at different location at site. Appoint trained persons as first aiders and
trained them regularly.
Key Persons of the Emergency Team and their Duties
During general shift, persons designated below will perform the assigned emergency responsibilities. In their
absence, or during the shift, alternate persons designated will assume responsibilities.
Table 7-4: Details of Key Personnel of the Emergency Team and their Duties
S. N. Abbreviated
Form Full Form Who will act
1 SMC Site Main Controller Sr. M/DGM/GM(D)/ED(D) (Senior person available in premises)
Sr. Officer of CCR till arrival of SMC
2 IC Incident Controller Shift In-charge / Dy. M / M (of concerned plant & area)
3 Key Personnel -- All HODs / All Sectional Head / Senior most person available in
respective dept.
4 CCR Central Control Room --
5 OHC Occupational Health Centre --
6 PPE Personal Protective Equipment --
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 155
Alarm Raiser:
No fixed person can be appointed as alarm raiser.
Any person who has observed any abnormal situation such as fire, gas leaks, chemical leak outs etc., can raise
alarm to warn / inform all working in plant.
Shout Danger-Danger
Ring the brass bell and run fast to inform people around by shouting danger
Inform security gate / respective control room about the abnormal situation
If possible attempt to contain / control about the incidence with available resources without risk to life.
Inform the shift in charge.
Nominated Person to Declare Major Emergency
All shift in charges
Unit Head
Plant HOD
Immediately being aware of the emergency (On hearing the Siren of on being about emergency) he will proceed to
the scene / location and on arrival he will:
Assess the scale of emergency and decide if a major emergency exists
Take a decision to declare MAJOR EMERGENCY
Activate the on-site plan and if necessary the Off-Site emergency plan
Inform Site-main controller about shifting down and evacuation of plant and areas likely to be affected by
emergency
Ensure that outside emergency services, including Mutual – Aid have been called
Direct / advise to public address system in charge to activate public address system and to inform / advice Off-
Site population for evacuation and precaution to be observed during emergency.
Site Main Controller:-
Unit Head & Dy. General Manager - Production in general shift & shift in charge of CCP acts as SMC till unit head
arrive the site.
Duties / Functions of SMC: Immediately on being aware of the emergency, he will go to the emergency control
center (ECC) on arrival he will:
Relieve the incident controller of responsibility for overall main control
In consultation with the incident controller decide whether major emergency exists and on declaration of a
major emergency ensure that the outside emergency services and mutual help are called, the off-site plan
activated and if necessary, nearby factories and population are informed.
Ensure that the key personnel are called.
Exercise direct operational control of those parts of the work outside the affected area.
Continuously review and assess possible developments to determine the most probable cause of event.
Direct the safe close down and evacuation of plants in consultation with the incident controller and key
personnel. If necessary arrange for evacuation of neighboring population.
Ensure that causalities are receiving adequate attention. Arrange for hospitalization of victims and additional
help if required. Ensure that their relatives are informed.
Informed and Liaison with police services, instruct emergency authority and the factory inspectorate and
experts on health and safety, provide advice on possible effects on area outside the factory.
In the cases of prolonged emergencies involving risk to outside area by windblown materials, contact
meteorological office to receive early notification of impending changes in weather conditions.
Ensure the accounting for personnel and rescue of missing persons.
Control traffic movement within the factory
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 156
Arrange for a chronological record of the emergency to be maintained.
Where the emergency is prolonged arrange for relief of personnel and the provision of catering facilities.
Issue authorized statements to the news media where necessary, inform head office.
Ensure that proper consideration is given to the preservation of evidence. Arrange for photographs / video.
Control rehabilitation of affected areas and victims on cessation of the emergency. Do not restart the plan
unless it is ensured safe to start and authorized the sounding the "All clear" siren which will be one continuous
long siren for three minutes".
Incident Controller: - All shift In-charge of respective plant / HOD of plant / Unit Head
Dy.Incident Controller: - Sr. Executive / Executive (Prod.)
Duties / functions: - Immediately on being aware of the emergency and its location he will proceed to the scene.
On arrival he will take charge of accident and operate from scene as well as plant control. He will:
Assess the scale of emergency and decide if a minor emergency exists or is likely. On his decision, he will
activate the on-site emergency plan and if necessary the off-site emergency plan.
Inform site main controller and perform as site main controller till his arriving and he will deputed his Dy.
Incident controller on the scene and he will go to the emergency control center. Particularly he will:
Direct the shutting down and evacuation of plan and areas likely to be affected by the emergencies.
Ensure that outside emergency services, including mutual - aid have been called in.
Ensure that key personnel have been called in.
Direct all operations within the affected area with the following priorities:
Secure the safety of the personnel.
Minimize damage to plant, property and the environment.
Minimize loss of material.
Direct rescue and firefighting operation until the arrival of the outside fire brigade, when he will relinquish
control to the head of the fire brigade.
Search for causalities.
Evacuate non-essential workers to the assembly points.
Set up a communication point and established telephone / messenger contact an appropriate with the
emergency controller center.
Give advice and information as requested, to the head of the fire brigade and other emergency services.
Brief the site main controller and keep informed of developments.
Preserved evidence that will be necessary for subsequent inquiry in to the cause of the emergency and
concluding preventive measures.
Safety In charge:-
On being informed about the incident proceed to the scene of incident and assess the situation, report to the site
main controller.
Help the incident controller / site main controller in firefighting / incident control operation by organizing
supervising firefighting / incident control crew. Provide necessary PPE to incident control crew.
Liaison without side emergency services for mutual aid, evacuation shelter, Ambulance, Medical help and
others.
To maintain ECC necessary items, checks and report inadequacy
To carry out / CO- ordinate pre emergency activities for preparedness.
Traffic /Security In charge:-
Security officer
Security supervisor
Stores – Executive
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 157
Maintain list of numbers of contractors employees, visitors present on site.
On hearing the siren inform fire team about location and accompany proceed to the site of incident along
with all the security personnel with the exception of essential at the gate.
Control the traffic movement in the factory premises. Cordon off area as required
Remove unauthorized and untrained persons from the scene of incident and instruct them to report at
assembly point.
Help fire rescue, evacuation team for control.
Not to allow entry / exit without permission of IC/SMC
Keep gate clear for emergency site vehicle, tender from outside.
FIRE TEAM INCHARGE:-
Fire officer
Security officer
Security supervisor
On hearing the siren report to incident site and keep contact with ECC Co-ordination with fire station,
security IC and form fire squad
Organize fire squad and arrange to extinguish the fire / control the incident with the help of trained
personnel
Take charge of fire hydrant pump room and see that fire pumps will work as required.
Provide additional hoses, branch pipes, foam compound and spray nozzles to fire squad
Provide all necessary help / direction to fire / gas control squad
Inform SMC / IC if need of mutual aid is required
To maintain fire protection systems apparatus in working condition.
Leak / Spill Control In charge:-
Officer – Prod
Executive – Eng.
Executive – QAD
On hearing the siren report to ECC and or incident site IC
Follow instructions from incident controller / SMC
Organize squad to control spreading of pollution in to atmosphere etc.
Inform SMC / IC if need of mutual aid is required.
Transport In charge:-
Duty officer
Security supervisor
Asst. Manager – P&A
Arrange transport for evacuated persons to shift to outside shelter.
On being informed about the incident proceed to the emergency control center (ECC)
Take charge of all transport vehicles available on – site and keep drivers ready
Arrange to transfer causalities to nearest hospital
Co-ordinate with the SMC and follow his instructions
To maintain arrangements of transport.
Mechanical Aid In charge:-
Manager – Mech.
Executive – (Eng. / Utility)
Asst. Manager – Instrumentation
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 158
Executive – Instrumentation
Manager – Elec.
Executive – Elec.
On being informed about the incident to the scene of incident and report to ECC
Follow instructions from IC
Ensure that emergency engineering services are in working condition
Render all engineering help to the IC in controlling the incident.
Arrange / provide help for heavy vehicle as per requirement.
First – Aid Medical Treatment Incharge:-
Trained first aiders
Male Nurse
On being informed about the incident proceed to the scene of incident and report to ECC/OHC
Take charge of Ambulance, OHC
Arrange to give first – aid and maintain record
Decide for further treatment & Co-ordinate with transport in charge & keep record
Assess need of extra medical, Ambulance help & co-ordinate with IC / SMC
Maintain arrangements of OHC, Ambulance.
Telephone / Communication In charge:-
Duty officer
Officer – P&A
Telephone operator
On being informed about the incident maintain contact with emergency control room or report to ECC
Take charge of all external telephones
Receives inward message and keep record of it
Arrange and make one or two lines free for inward message
Inform emergency services and make them alert to come on second call. Also keep record of all outward
message on separate paper.
Also record any emergency message for mutual aid, in specified format in detail
Follow instructions from SMC/IC
Assembly point In-charge:-
Officer – QAD
Executive – Inst.
Executive – Eng.
a) On being informed about the incident, proceed to the site and report to site main controller / incident
controller at ECC
b) If evacuation call is given :-
Arrange to record names / department of those persons assembled (evacuated) at assembly points.
Inform SMC about missing personnel if any
Follow instruction from SMC
If required arrange for transport to shift all evacuated persons to shelters in CO- ordination with
transport In-charge.
During extended emergency he will shift all the assembly at another safe area and allow visitor,
contract employee to go out of premises as per instruction of IC / SMC with exit proof signature.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 159
Emergency Response:-
Emergency Response for Chlorine Evaporation Unit at MFL Dahej is as follows:-
Electrically operated fire sirens are provided in the complex. In addition to the above, hand operated sirens are
provided in the plant.
Emergency control organization chart with the duties has been displayed at the Control Room.
Any employee/person (incident informer) noticing a fire will shout "FIRE FIRE" to attract attention of others
nearby. He shall blow the fire alarm at the nearest location or inform to security through intercom for blowing
the fire siren. Any other persons who heard the shouting of "FIRE FIRE" will run to security to inform and for
blowing the fire alarm.
On hearing the fire alarm, Operations Engineer will proceed to affected area and take charge. He will inform
site Controller/Incident Controller immediately.
Site Controller will proceed to control room on hearing alarm on getting report from incident informer/incident
controller.
Firefighting coordinator or alternate will proceed to pump station and start fire water pump.
Power and Utility coordinator will take charge of other utilities and stand by for orders from Incident Controller.
All other officers will carry out the operations as applicable to them and stand by for instructions from Incident
Controller.
Administration Coordinator and Communication Coordinator will proceed to their respective position and await
instructions from incident controller or site controller.
Security supervisor or alternate will take control of the main gate to control traffic and to provide assistance in
firefighting.
Company Doctor on receiving the information will prepare to receive casualties, if any. He will wait for
instructions from incident Controller/site controller to organize external medical and ambulance services.
In case of a major fire due to electricity operations officer will take action to stop electricity.
It is the responsibility of the Head Security Guards to take control of the traffic. He will organize the movement
of employees in such a way that none of the roads within the plant premises are blocked. He will also control
the movement of traffic at all the main gates in order to ensure smooth movement of fire-fighting vehicles or
ambulances, as the case may be.
The incident controller will rush to the scene of fire and organize emergency response activity with the
following three team viz. Fire Combat Team, Rescue Team and Auxiliary Team. Each team shall have a
minimum strength of 2 to 3 employees. One employee in each team will be the team in-charge.
The duties of each team is as detailed below:-
Fire combat team:-The team members to go into action as per the specific assignments such as:
Collecting the fire extinguishers, hoses, nozzles and rush to spot of emergency.
Connecting maximum number of fire hoses with the nearby hydrant points.
Operate fire water monitor by setting them properly to the direction of fire.
Use Foam and other means as suitable for firefighting.
Switch on the sprinkler system manually. (Wherever applicable)
Rush to the spot of the fire with all available fire extinguishers and try to put out the fire at the quickest
possible time.
Stop all activities and concentrate only on fire fighting and try to prevent the fire from spreading.
As others rush to the scene of fire, tell them what the type of fire is and what extinguisher is to be used.
Rescue team:-Team members to go into specifically assigned operation such as:-
Inform site controller, communication coordinator about the situation from time to time. Restrict entry of
unauthorized persons to the location.
Remove important documents to a safe location from the scene of emergency. Ensure that trucks are taken out
and they do not block the passage.
Bring stretchers from the dispensary and move the injured/casualties to the dispensary.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 160
Auxiliary team: -The team members to go into action as per specific assignments such as:
Stop all operations in the field.
Close all ROV's and other important valves. Switch off electrical mains as instructed.
Bring additional fire extinguishers and other firefighting equipment for continuous firefighting.
Replace all firefighting equipment used during combating of fire after normalcy is restored.
Emergency Response to All
If you notice the fire first rush to the spot of fire with a fire extinguisher simultaneously shouting “FIRE FIRE”
for help from other employees who will arrange to sound the fire alarm. Inform the location of fire.
Remember “MAXIMUM SAVING, MINIMUM LOSS” while fighting the fire. First three minutes of fire is the most
vital. After this period it spreads beyond control.
Emergency Response to All
If you notice the fire first rush to the spot of fire with a fire extinguisher simultaneously shouting “FIRE FIRE” for
help from other employees who will arrange to sound the fire alarm. Inform the location of fire.
Remember “MAXIMUM SAVING, MINIMUM LOSS” while fighting the fire. First three minutes of fire is the most vital.
After this period it spreads beyond control.
Emergency Do’s and Don’ts
Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related
measures is tabulated in Table 7-5.
Table 7-5: Do’s and Don’ts of Various Activities / Emergency
Do’s Don’ts
Preventive Maintenance
Well qualified supervisors to be hired.
Follow SOP, training manuals etc.
Checklist to be completely filled for maintaining
records.
Poor instruction on maintenance by supervisor.
Do not skip the procedures as mentioned in SOP.
Do not leave any records unfilled to prevent the job
from rework.
Strengthening of HSE
Periodic training for upliftment of skills
Use of PPEs
Do not provide incomplete instructions / training.
Avoid the chance of not wearing PPEs while on site.
Safety Related measures for anyone noticing an emergency
Actuate nearest emergency push button and/ or
inform the Shift in Charge. Get back to your normal
workstation (if safe) or else report to the assembly
point.
Do not panic and avoid running all over the place
prevent others from doing so.
Do not enter the site unless instructed if you are
outside and disaster alarm is heard.
Contractor Personnel
Stop work on hearing alarm and assemble at the
Assembly Point and be ready to evacuate.
Do not enter the site until it is cleared for the normal
work by Incident Controller.
Security
Keep the gate manned.
Keep the road clear for movement of fire tenders.
Control traffic at gates.
Do not allow unauthorized visitors free to enter.
Visitors
Leave the place & assemble at assembly point Do not enter the site if emergency alarm is heard
All other employees on site
On hearing emergency siren
Get back to work place (if safe) and get instructions
from supervisor
Do not panic/ run
Do not go to the scene of emergency unless
specifically instructed by Incident Controller
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 161
Members of emergency response team:
In each shift fire officer collects the name of the team members (10 Nos) from decided areas in consultations with
area supervisor / In-charge. 10 members will work as emergency response team during the shift. To provide urgent
help in the affected area. Emergency response team will come in action after on – site emergency declaration. They
will:
On hearing of first siren keep alert locate place of incident look for wind direction, keep BA Set ready.
On hearing of second siren of advised proceed to the scene of incident with BA Set.
Help incident controller in emergency control activity like fire, gas leak rescue, search and evacuation
operations as per the need and instruction of IC / SMC.
Emergency Evacuation
If it becomes necessary to have an emergency evacuation the decision will be made by the Site Controller/Incident
Controller as the case may be. The following procedure will be adopted during evacuation:-
Personal Evacuation:
Incident Controller/Fire Fighting Coordinator/Shift Operations Officer will give instructions to the employees in
their sections to go to an assembly point. They will keep a list of employees evacuated from their sections.
Shift Operations Officer will contact the Incident Controller if anybody from their department is left behind
needing any special help. Shift Operation Officers will be responsible for evacuating all from different sections.
Incident Controller will organize the special help required to rescue the employees left behind. Shift Operations
Officer will also decide an evacuation route depending on wind direction.
If there are any employees left behind in different sections, the Incident Controller will organize a rescue team
which will go from section to section with proper protective appliance in order to remove all the entrapped
employees.
Decision to allow re-entry into the terminal for resuming operations will be made jointly by Incident
Controller/Site Controller.
In certain situations like a major fire it may become necessary to evacuate the people in the nearby areas. In such
a case following action will be taken.
Incident Controller, in consultation with the Site-Controller, will decide the evacuation plan. While deciding the
evacuation plan, they will keep the following points in mind.
While handling evacuation in case of a major fire, the direction of the wind is extremely important.
The location of the terminal showing the population density in all the directions surrounding the terminal has
been prepared. This will be used to decide number of people to be evacuated.
Depending on the nature of the fire and the wind direction, the Incident and Site-Controller will draw an
evacuation plan.
It is the responsibility of the Incident Controller to contact the Site-Controller after alerting local police-in-
charge and Local Authorities. Site-Controller will inform Collectors Office and organize additional help and
emergency services.
While contacting all the people mentioned above, the Incident-Controller will give information regarding the
wind direction so that help can reach the affected areas without getting affected by the gas.
Incident Controller/Site Controller will alert local hospitals regarding the emergency.
Communication System
Communication is the lifeline of handling an emergency. When an emergency occurs it is necessary to raise the
alarm immediately, to declare an emergency, to inform the emergency controllers, to inform the plant emergency
services and affected areas within the plant as well as outside if necessary.
Therefore, the following facilities are provided in the plant for an effective two way communication:
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 162
Intercoms, public address system, company mobiles and walkie talkie for normal and emergency in-plant
communication
Fire and emergency sirens for raising an alarm for emergency and alerting all essential services
Non-dedicated external telephone for emergency contacts with works emergency controllers, fire brigades,
hospitals and police and for all other contacts including district authorities, Government agencies, neighboring
industries etc.
When the external telephones are not working, an emergency vehicle with a messenger could also be used for
outside communication. Communication to the neighboring public, if necessary, should always be made through
police and their wireless van.
Addition to the above, there will be siren system, which will be sounded for different stages of emergency.
Warning, Alarm and Safety and Security Systems Sirens
1. Motor Operated
Emergency Sirens are installed at heights on the top of the roofs of buildings structures and the push button
switches will be provided at suitably approachable inside the premises.
2. Hand Operated
Hand sirens are installed inside the premises.
Emergency Siren Codes
Table 7-6: Siren Codes during Emergency Situation
Emergency Wailing siren for one minute (e.g. police wailing siren).
Evacuation Wailing siren for three minutes. To be blown only on instructions from SMC.
All Clear Continuous siren for one minute.
Testing Of Sirens/ Security/ Safety Systems
Every Monday at 10.00 hours all the sirens will be sounded for testing purpose. Emergency Alarm is located at fire
hydrant tank pumping station as marked on the site plan.
On hearing siren the Incident Controller will activate the action on Disaster Control Plan by giving proper
instructions or predetermined signals.
Security Systems
Security Officer is in charge of Security. Sufficient numbers of Assistant Security Officers and guards will be
deployed at main gate and other vulnerable areas in each shift. Security staff assists in firefighting and traffic
control during emergencies.
Emergency Response
Incidence observer will communicate the emergency to Site controller & raise the alarm.
On hearing the alarm or getting information about emergency, site controller will proceed to control room &
take charge. He will inform incident controller immediately.
Incident controller will proceed to affected area on hearing alarm or on getting report from Site Controller.
Fire pump attendant will proceed to Fire pump house & start fire water pump. All other persons will stand by
for instructions from incident controller.
Incident controller will organize emergency response activity & emergency response teams. He will also decide
for the need for outside assistance.
F & S officer will proceed to his position & control emergency with the help of Emergency crew personnel.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 163
Administration In-charge will take control of main gate to control traffic. He will guide outside assistance like
fire brigade, ambulance van etc.
Emergency Evacuation
For the purpose of evacuating personnel, safe assembly points are chosen and clearly marked. The assembly
points are selected in the upwind direction / perpendicular to the wind direction so as to eliminate the
downwind hazards due to fire and toxic release. We have an on line weather monitoring station. Wind direction
and wind speed data is recorded and used in case of toxic release to facilitate evacuation and to know
dispersion speed of chemicals
Decision for evacuation of personnel will be taken by Incident Controller, who will ensure that the
Person is to be assigned for each assembly point personnel to be evacuated are informed on public address
system
Injured and trapped personnel are rescued by fire squad equipped with protective gear
Head count is taken with the help of senior most people available at the assembly point and a list of personnel
evacuated is made.
Instructions are given to vehicle drivers on the route to be followed and safe place where the personnel are to be
taken.
All Clear Signal
Investigation to avoid recurrence, recommendations and records – Safety Officer.
Resetting the operations – Incident Controller.
Permission from different Authorities and Final Clearance - Site Controller.
Existing On-Site Emergency Plan
Emergency procedures
Handling of an emergency calls for critical planning and ensuring a state of readiness at all times. Proper handling
of the actual emergency needs certain actions to be taken before the emergency to ensure that all systems are
ready and the emergency can be handled smoothly. Similarly after an emergency rehabilitation and reconstruction
programs are necessary. The actions to be taken before, during and after an emergency are described below:
General Instructions
Leakage of chlorine is the major emergency although other emergencies due to fire, explosion or spillage of
chemicals may occur. Immediate steps should be taken to stop the leak.
The general instructions are as follows:
Chlorine is heavier that air and settles at ground level. It does not diffuse quickly in atmosphere.
Always stand in the upwind direction, while attending the leakages or standing near the leakage.
Always stand in the upwind direction, while attending the leakage or standing near the leakage
The best effort should be made to contain the spilled liquid it should be recovered to the extent possible and
neutralized before it is discharged in to the effluent stream
Effluent treatment plant should be informed immediately to take corrective action.
Only trained employees should be allowed to go near the danger area with proper safety equipment kit to stop
the leak
All other employees should assemble as per the instruction of incident controller.
Actions to be taken before the Emergency
Training programs should be conducted at regular intervals for:
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 164
Use of Personnel Protective Equipment’s
Use of chlorine kit
Fire fighting
First Aid
Drills to be conducted for testing of emergency plans once in a six month
Safe handling procedures (MSDS) for the chemicals handled in the plant should be written and copy made
available in plant area
Actions to be taken during the Emergency
For major emergency situations the various actions to be taken during emergency are as follows:
Emergency Response to Toxic Material Release
Among the hazardous chemicals handled at the entire existing facility, the worst emergency situation will involve
release of chlorine gas. At present 20 Cl2 sensors are placed at various locations within premises as mentioned in
Table 7-2.
A chlorine and Benzene leak is easily detected due to its peculiar odour. As soon as a leak in piping or equipment
handling chemical is noticed, the immediate action should be to evacuate the downwind area and make efforts to
isolate the source of supply.
Personnel performing such emergency operations should wear all personal protective equipment including air line or
self-contained breathing apparatus.
Immediately on report of a leak, the Incident Controller should take following actions.
Declare the EMERGENCY
Evacuate the downwind area. If the consequences are likely to affect outside population, use available means
to inform the public and nearby installations about the incident and possible effects and actions
Instruct to isolate the system supplying chemical to source of leak and arrange safe shutdown of the plant.
If emergency situation permits, attempt repair using necessary precautions
Perform all other responsibilities as per the Emergency Response Plan
The following actions to be taken for the hazardous chemicals handled in the plant:
Emergency Action Plan for Chlorine Leakage
On detection of chlorine leakage inform shift in charge.
The SMS / IC will assess the situation at the site.
Check wind direction and wind speed.
Identify source of leakage by approaching from up wind direction using PPEs like SCBA set, airline respirator,
PVC gloves and gumboot.
SMC / IC will decide for evacuation of affected downwind area and arrange for search and rescue as required.
Stay up wind, cordon off area, and prevent entry of unwanted personnel.
Try to isolate leaky portion of plant, pipeline, and equipment by closing isolation valve on both side of leak.
Consider following points before isolation.
Whether isolation affect the specific plant / equipment operation, then think of safe shut down of that plant /
equipment.
Try to stop / reduce leakage if it can be done without risk using PPEs and special tools and kits or by lowering
pressure / creating negative pressure by available methods.
Start water spray in atmosphere to knock down vapors. Do not spray water on the source of leak.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 165
Tonners:
As soon as there is any indication of the presence of chlorine in the air immediate steps should be taken to
remedy the situation. The leak source can be detected with the help of ammonia torch (a wooden stick with
piece of cloth at one end. It is soaked in ammonia solution. When taken near the leak source, it will give dense
white fumes.) leakages, if any should be immediately reported to the supervisor
Leakage once detected, should be attended immediately, to avoid further deterioration of leakage.
Use personal protective equipment’s such as gas mask with canister, on line air breathing apparatus, self-
contained B.A. set while entering the leakage zone
Leakage point should be preferably approached from higher elevation and upwind direction
Isolate the system as quickly as possible and evacuate the area. Only persons required for combating the
leakage should be allowed to enter the area
Water should never be sprayed on a chlorine leak. To do so will make the leak worse because of the corrosion
action of wet chlorine. Moreover, heat from water increases evaporation rate of chlorine
The severity of a chlorine leak may be lessened by reducing the pressure on the leaking container. These may
be done by absorbing chlorine gas (not the liquid) from the container in a solution of caustic soda, soda ash or
hydrated lime
If there is leakage from the valve seat, valve body or valve inlet threads, use tie rod assembly from tonner
safety kit to plug the leak
If there is hole in the container body, use chain assembly from tonner safety kit.
If the leak cannot be plugged, reduce pressure in the container or remove it to an isolated area
Review spreading of chlorine gas and cloud formation and level of emergency accordingly declare activate on-
site of off-site emergency plan
Arrange for first aid, hospital treatment for affected personnel.
Cut off power supply if required for selected plant / equipment.
Storage Tank
In case the leakage is from below first isolation valve of storage tank which cannot be controlled by isolation
method arrange for emergency transfer in to stand by empty tank from leaky tank.
Create negative pressure in stand by empty tank through Hypo
Keep local exhaust hood near to source of leakage close other exhaust hood to increase effectiveness
If liquid has spilled in dyke area start selected floor exhaust to suck chlorine vapor to hypo.
SMC / IC review effectiveness of action taken and if situation does not come under control decide for safe shut
down of plant
Review spreading of chlorine gas and cloud formation and level of emergency accordingly declare / activate on-
site of off-site emergency plan
Arrange for first aid, hospital treatment for affected personnel.
Cut off power supply if required for selected plant / equipment.
Emergency Action Plan for Leakage/Spillage of HCl/H2SO4/HNO3
For small sprinkle soda ash over spillage and collect it in drum for later disposal to ETP
Wash floor using water in excess quality.
Emergency Action Plan for Caustic Lye
This is a highly reactive liquid and causes burns on contact with skin. Utmost precaution should be taken while
carrying out maintenance jobs or while attending leakages.
Put on all required personal protective equipment’s such as face mask / safety goggles, hand gloves, helmet,
apron, gasmask, gum boots etc. while attending the leakages or approaching to leakage point
Do not attempt to attend leakages on pressurized line/vessel or on running equipment
A small quantity of caustic lye may be diluted with a large quantity of water
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 166
Emergency Response to a Storage Tank Fire/ Coal fire / Explosion
Following possible approach may be used to handle an emergency situation involving a tank fire / coal fire /
explosion:
Assesses the situation and gather required information on the accident including suspected casualties, rescue
operations required, materials involved, tank details, pipe line / flange details, weather conditions and
resources available.
Consider possible alternatives to bring the situations under control and make decisions with reference to line of
action i.e. whether to attempt to extinguish the fire or only to control its spread, requirement of emergency
response personnel or not etc.
Take appropriate response actions :
Isolate the area and remove all nonessential personnel
Isolate / shut off the valve of source of fuel from up wind direction
Switch off all power supply specifically temporary power supply
To stop welding, gas cutting and all hot job in surrounding areas and specifically in down wind direction
Evaluate the area downwind of the fire or possible vapor clouds
If remote isolation of the vessel is possible, provide for doing so, to avoid flammable vapor cloud formation
Attempt to extinguish the fire using the appropriate extinguishing agents and methods
Approach to fire from upwind. The personnel involved should wear appropriate protective equipment
Cool the vessel involved in fire and adjacent vessel with water to prevent spread of the fire
Prevent the overflowing of fire water from dykes and other containment systems
Actions to be taken after the Emergency
After decision has been made by Site Main Controller to call off the emergency, following necessary actions are
recommended:
Analysis of the incident
Rehabilitation of plant and offsite personnel
Repairing the plant machinery and reconstruction of structure
Availability of On-site emergency plan
Safety measures proposed at storage yard/warehouse and conveyor belts
1. Chlorine
Chlorine also has a multitude of industrial uses including making bulk materials like bleached paper products,
plastics such as PVC and the solvents tetra chloromethane, chloroform and dichloromethane. It is also used to
make dyes, textiles, medicines, antiseptics and paints.
MFL comes into MAH (Major Accident Hazards) category due to bulk storage & handling of Cl2 above Threshold
Quantity (THQ).
Chlorine is a toxic gas (B. P. is -34oC). In liquefied form chlorine is a clear amber dense liquid. The gas is greenish-
yellow, about 2.5 times as dense as air, and non-flammable. Liquid chlorine causes severe irritation and blistering
of skin. The gas has a pungent suffocating odour and is irritant to the nose and throat. It is an extremely powerful
vesicant and respiratory irritant.
Hazards:
Irritant: Causes moderate or severe eye and skin irritation.
Aspiration Hazard: May be fatal if swallowed and enters airways.
Very Toxic: The exposure of hazardous chemicals are lower than their permissible exposure limits (PELs)
PEL of Chlorine: 1 ppm (3 mg/m3)
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 167
CEL of Chlorine: 8 ppm
IDLH of Chlorine: 25 ppm
Safety Control Measures:
The enclosed system will be provided for entire process & operation for manufacturing of finished goods & its
derivatives to minimize the emissions.
Compressed Cylinder storage in tested & certified Tonner as per prescribed Compressed Cylinder storage
regulations etc.
Alternate Level Indicator Transmitters, Pressure Gauges and Flow switches have been provided to the system
to find out the accuracy. Auto control (PLC) system with Audio-visual Alarm system will be provided.
Ventilated Separate Fenced Shed provision will be done to prevent un-authorize entry.
Precautionary Tags/ Boards have been displayed in this premises for cautionary intimation among working
personnel.
Fire Fighting system (Fire Hydrant system, Water Curtain) to create fire wall boundary between adjacent
system in case of fire to prevent cylinder explosion by overheating.
Specific Chlorine Detector Alarm panel with localized Hooter will be provided at the centre of plant operational
& storage unit to detect, sense & indicate alarm to draw attention of working personnel.
Chlorine Scrubber System with double efficient blower will be provided to neutralize the Cl2 gas & scrub them.
Regular checkup of Chlorine Safety System done periodically as scheduled frequency by competent authority.
Sufficient Ventilation to the process & operational area will be provided to disperse the fumes in atmosphere.
Specific Personnel Protective Equipment (PPEs) like Safety Shoes, Safety Helmet, Full body PVC Apron, Splash
proof Goggles Respirators & Mask will be provided to working personnel to avoid inhalation, ingestion,
contamination, swallow & dermal exposure etc.
Safety Induction training, First Aid & life Saver training, Hazardous handling & practical training on SOP
provided to the working personnel.
Sufficient & dual alternate Breathing apparatus (SCBA & Airline Mask, Cl2 Cartridge Mask & Gas mask) have
been provided.
Medical examinations camp organized from management periodically to examine the health of entre factory
personnel.
Appointment of Certifying surgeon/ Medical Expert will be done to check up the health of personnel 4 day in
month.
Antidotes, First Aid appliances & Medical facility will be provided in the factory.
Safety Showers have been provided around the plant & on elevated multistory building to decontaminate &
dilute the splashed chemicals in case of exposure on the body.
Sufficient Lighting provision will be provided in the plant.
Sufficient Emergency Exits will be provided to the plant.
EOT crane has installed to lifting shifting the 1.5 T weighted Toners safely.
Double Safety Hoods have kept inside plant at designated point to tackle the Cl2 leakage emergency.
Caustic Tank with dual alternate pump will be provided with Scrubber system to pump the Caustic Solution to
the Top of Scrubber Column to sparer them to neutralize the Cl2.
Provision of online chlorine sensors at various locations and connected with DCS is given in Table 7-2.
Safety System for Chlorine Bottling, Handling and transportation:
Weighing arrangement provided in the each EOT crane to check the weight of receiving / dispatch tonners
Degassing of tonner is done in Sodium Hypochlorite plant.
Hydro testing – Every two years / need basis.
Hydro testing tonners is segregated separately. If wt. loss is more than 5% it is rejected
Auto filling system provided
Load cell provided on each filling post to measure the weight and calibration of load cells done on daily basis
Before dispatch the tonners, it is observed for one day for any abnormality
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 168
Valves are covered with metallic cover hood
Four chlorine sensors are installed. These sensors are connected with DCS. Local hotter also provided.
Suction hood covering complete tonners is provided
Tonner tracking system
2. Hydrogen
Hydrogen is a colorless and odorless gas. It is flammable and explosive gas and result in violent reaction with air. It
forms sensitive explosive mixers with bromine and chlorine. Lower and upper explosive limits of hydrogen gas area
(LEL & UEL) are 4.1 % and 74.2 %, respectively. It can spark by heat, spark or flame. Once ignited it burns with a
pale blue, almost invisible flame.
Safety Control Measures:
On-line monitoring of Hydrogen in Chlorine
In Hydrogen compressors area all electrical appliances shall be flameproof.
Hydrogen gas detectors shall be installed at Hydrogen compressor and activates alarm in case of Hydrogen
leakage
TAC approved fire hydrant system throughout the plant
Water sprinkler provided around transformers
Round the clock availability of full size own fire tender
Mutual aid schemes with the adjoining industries
Other safety measures:
Four levels of communication (Telephone, P A system, Walkie talkie, Siren system)
Incident investigation and corrective system including near-miss cases
3. Safety System for Coal storage and Handling
Coal stock yard shall be minimum 500 meters away from the residential area, school/colleges, Historical
Monuments, Religious Places, Ecological sensitive area as well as forests area
Coal will be stored in such a way that coal heap will not be higher than 5 meter and clear distance between two
adjoining heaps will be 5 meters, so that in case of fire, approach is available
Mechanized loading/ unloading system from the loading /unloading area to the stacking yards and in to the
vehicles will be adopted
Compound wall all along periphery of the premises with minimum 9 meters height will be constructed
Continuous water sprinkling will be carried out on the top of the heap at regular intervals to prevent dusting,
fire & smoke.
To prevent fugitive emission during loading/unloading, fixed pipe network with sufficient water storage and
pump shall be installed.
Water sprinkling shall be carried out at each and every stage of handling to avoid generation of coal dust or
other dust within premises
Regular sweeping of coal dust from internal and main road and also ensure that there is adequate space for
free movement of vehicles.
Dust containment cum suppression system for the coal stack, Loading and unloading
Construction of effective wind breaking wall suitable to local condition to prevent the suspension of particles
from the heaps.
Construction of metal road & RCC Pucca flooring in the plot area/ godown etc.
System for regular cleaning and wetting of the floor area within the premises.
Entire coal storage area/ godown will be covered with permanent weather shed roofing and side walls i.e., in
closed shed, in case of crushing/sieving/grading activity is carried out (i.e. G. I. Sheet) along with adequate
additional APCM.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 169
Three rows plantation with tall growing tress all along the periphery of the coal handling premises, inside &
outside of the premises along with road will be developed
Proper drainage system shall be provided in all coal storage area so that water drained from sprinkling & runoff
is collected at a common tank and can be reused after screening through the coal slit or any other effective
treatment system.
All the engineering control measures and state of art technology including covered conveyer belts mechanized
loading and unloading, shall be provided in addition to the measures recommended in the environmental
guidelines for curbing the pollution.
TAC approved fire hydrant system
Fire tender with firefighting crew
Occupational Health
Well-equipped occupational health center will be manned by qualified MBBS doctor. The work of occupational
health center includes:
For new employees: Pre- employment medical checkup
Six-monthly health check-ups of all the employees (periodic medical examination)
Physical examinations such as height, weight, chest, blood pressure, eye vision and skin test
Lab test such as hemoglobin (TC, DC and ES tests), urine – complete tests (physical examination, macro test,
micro tests like RBC, WBC, crystals, albumin, globulin, sugar)
Spirometry test (lung function) for pulmonary impairment detection.
Audiometry test – for the employees exposed to noise
Counseling with employees for improvement in health conditions
Medical check-up carried out to study the effects of vibration
Regular health survey is carried out with specific objective to address physical, biological and ergonomic issues
of employees
Workplace monitoring survey
Health assessment of Employees after illness/injury
Post-employment medical check up
Off-Site Emergency Plan
Need of the Off-Site Emergency Plan
The off-site emergency plan prepared herein will deal with the incident, the onsite plan which has the potential to
harm persons or the environment outside the boundary of the factory premises.
The most significant risk to outside areas is that associated with a large release of chlorine and Benzene. Spread of
its effected outside the works may require traffic control, evacuation, shelter arrangement.
Off-site emergency plan has been drawn up with a view to mobilize resources and integrate with district
contingency plan for an effective system of command and control in combating the emergency.
Thus the main purpose of the off-site emergency plan is:
To provide the local / district authorities, police, fire brigade, doctors, surrounding industries and the public, the
basic information of risk and environment impact assessment and to appraise them of the consequences and
the protection prevention measures and control plans and to seek their help to communicate with the public in
case of major emergency.
To assist the district authorities for preparing the off-site emergency plan for the district or particulate area and
to organize rehearsal from time to time and initial corrective action based on the lesson learnt.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 170
Structure of the Off-Site Emergency Plan
The off-site emergency plan will be integrated properly with the district contingency plan to tackle any kind of
emergency. The site main controller will keep liaison for this purpose with the district authorities.
External telephone facilities from MFL to GIDC (Fire), will be established for quick communication.
The names of the key persons will be defined to establish contacts and CO-ordinate the activities with the help of
the collectorate and disaster management center in case of major emergency.
An on-site emergency control room will be identified which can be activated / used for emergency control and
manned round the clock.
As far as off-site emergencies are concerned, information shall be received first by the police control room, GIDC,
next information to fire brigade GIDC and to disaster management center. The police / fire brigade control room
shall in turn inform police commissioner, collector and Municipal Commissioner.
7.2.5 Traffic Risk Assessment
Traffic risk assessment for vehicle movement in the plant premises:
A dedicated gate will provided only for Jeeps entry and exit
Speed limits boards (20 kms) are provided to control speed
Roads are RCC type and suitable for heavy vehicle movement
Convex mirrors are installed for easy identification of opposite vehicle movement
Bumpers will be installed for speed control
Main roads are wide and opposite vehicle movement is clearly visible
Traffic movement is controlled by providing additional security guards at various locations
To avoid fire hazard it is ensure that all vehicles entering in the factory have spark arrestors and it will also be
ensured that smoking items and explosives are not being carried inside the factory
It is ensured that no driver enters the plant premises under the influence of Alcohol
Parking area have been defined and sign boards will be provided
No entry signs have been defined will be provided
One way traffic movement routes have been defined will be provided
Zebra crossings will be marked
Pedestrian markings will be provided for personal movement
Following requirements will be ensured for transportation of vehicles carrying hazardous goods:
Spark Arrestor
Manner of display of class labels
Emergency information panels
Class label
Valid registration to carry the said goods
The vehicle is equipped with necessary first aid, safety equipment, toolbox and antidotes as may be necessary
to contain any accident
The driver holds an appropriate driving license, which authorizes him to carry hazardous goods
All relevant information is given to the driver in writing in the form of Transport Emergency Card (TREM)
(Road) and MSDS
Safe routes for transportation of goods are identified
It will be ensured that the vehicle goes out with following documents:
Invoice issued by Sales Coordination Department
Tests reports wherever desired
Material Safety Data Sheet (MSDS)
TREM Card
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 171
HAZCHEM Poster
Logistic Tracking Agency List
Safety during Road Transportation
The Hazard Information System plays an important role in the safe transport of hazardous substances. The Hazard
Information System consist of the following:
Material Safety Data Sheet (MSDS)
Transport Emergency Card (Tremcard)
Hazchem Code
Emergency Information Panel on Vehicles
Drivers Training
The transporter is responsible for the safe transport of Hazardous material by road from the loading point to the
discharge point. Special consideration should be given to the following:
Safe parking
Drivers must ensure that the vehicle is either supervised or is parked in a secure place. No potential source of heat
or fire must exist in the vicinity, and the vehicle must be capable of being easily removed in an emergency. Drivers
must inform the hauler of their overnight parking location. The overnight parking locations must be selected in
accordance with regulations.
Severe weather conditions
When severe weather conditions are experienced during transport, for example rainy roads or poor visibility, the
delivery should be stopped at the next suitable parking place
Delays or accidents
All delays during transport, whether due to severe weather conditions, breakdown or other reasons must be
reported to the consignor as soon as possible. Transport accidents must also be reported to the consignor as soon
as possible.
Pressure and temperature checks
For road transport the pressure and/or temperature of the tank contents should be checked regularly and recorded
on a checklist or in a logbook
Emergency procedure
Drivers should be given precise instructions as to the acceptable pressure and temperature rise during the journey,
and the emergency action to be taken in the event that readings in excess of acceptable levels are observed.
Recommended instructions are given below
If the appropriate transport regulations are complied with, and the requirements set out in this document are
adhered to, the risk of a transport emergency involving material is very small. Nevertheless, it is essential that
drivers should be aware of the appropriate action to be taken should an emergency occur.
1. Increase of temperature or pressure in the tank
During the journey, the temperature of the material should not increase. Normally the pressure in the tank should
not increase, and under normal circumstances will only do so if the temperature increases. If a more rapid rate of
temperature increase is observed, or a significant increase in pressure is observed, apply the following emergency
procedure:
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 172
Do everything possible to drive the vehicle to an open space away from buildings and populated areas. Park
and leave the vehicle, taking with you:
o Any temperature/pressure records,
o The transport emergency card,
o The transport documents.
Alert everybody in the surroundings and keep people away.
Contact immediately the local Police and the Fire Brigade.
Ensure that the consignor is notified as soon as possible and provide detailed information - when the increase
started, how long has the temperature/ pressure been increasing, what is the present temperature/pressure.
Assist the local authorities and hand over the transport emergency card.
2. Vapour/liquid leakages and/or fire
Abandon the vehicle immediately.
Alert everybody in the surroundings and keep people as far away from the vehicle as possible.
Contact immediately the local Police and the Fire Brigade.
Ensure that the consignor is notified as soon as possible.
3. In the case of accident involving injury or immobilization of the vehicle, but no leakage or fire
Contact immediately the local Police.
Ensure that the consignor is notified as soon as possible.
If the vehicle cannot be moved, the emergency flashing lights should be positioned to protect the front and
rear of the vehicle. Checks of the temperature and pressure of the tank should continue to be made and
recorded.
Routine inspection of road tankers and tank containers at loading terminals
If any of the following conditions are not met, the loading operation must be stopped and the situation rectified
before loading is allowed to continue.
1. Before loading
The consignor has to ensure goods carriage has a valid registration to carry the hazardous goods.
The vehicle is equipped with necessary First-aid, Safety equipment and Antidotes.
The transporter or owner of the goods carriage has full and adequate information about the dangerous or
hazardous goods being transported.
The owner of the goods carriage should ensure that the driver holds a driving license as per provisions of the
Central Motor Vehicle Rules.
The driver of the goods carriage is to be trained during transport of such goods.
The owner of the goods carriage carrying dangerous or hazardous goods and the consignor of such goods shall
lay down the route for each trip or permitted otherwise by police authorities.
Are there any visual objections on the truck against safe driving?
For tank containers, is the tank container plate valid?
Are all 'dangerous goods' labels fitted, are the identification numbers attached.
Provide a Tremcard (Transport Emergency Card) contains details regarding the type of cargo, nature of
hazards, emergency action, the protective devices, spillage control, first aid, etc. to driver.
For road transport: is the Tremcard in all required languages on board?
Does the driver possess all the items of protective clothing and safety equipment? (as specified by the
Tremcard)
Determine the maximum payload based on :
tare weight
country of destination
transport mode
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 173
maximum filling degree
Are all the valves closed upon arrival?
Is the tank placed at the correct loading position?
Are the wheels of the tank blocked by wheel blocks or other tools?
Do all valves function correctly?
2. Whilst loading
Is the maximum degree of filling not exceeded?
3. After loading
Is the maximum gross weight not exceeded? (check by weighbridge)
Is a leakage test performed (bottom valve and end valve)?
Are all valves closed and blinded, with all bolts in place or are all dry disconnect couplings / metal caps in
place?
Are all seals or locks in place?
General actions to be taken during emergency
If possible drive out of populated areas.
Identify the cargo, refer labels, TREM Card, instructions.
In case of a major leak of highly inflammable gas/ Vapour, do not start the engine.
Order on lookers to leave the affected area.
Stop pilferage of the leaked substance, it can be dangerous.
Secure the accident area and divert traffic.
Remove affected persons for first aid.
In the event of electrical fire, isolate the battery of the vehicle.
In case of fire, inform Fire Station, avoid inhalation of fumes, and use gas masks if required.
In case of leaks, see if it can be arrested easily.
Contain small spills by covering with sand.
Avoid direct contact with skin, wash with water and use necessary protective clothing like PVC apron.
In case of contact with eyes or skin wash with plenty of water. For any major contamination, remove clothing
immediately
7.2.6 Training Rehearsal and Records
Need for Training and Rehearsal
It is important that every emergency plan, when finalized should be written down and communicated to all
concerned. After making persons aware of such plants, the plan itself should be put to test, preferably in parts, to
begin with, so that the effectiveness can be assessed and alternatives developed. After this more extensive exercise
can be conducted once a year involving outside agencies also. This will not only enable the industrial plant
personnel to enhance their speed of mobilization, but also will help the outside agencies to improve their
effectiveness in responding to emergencies.
These exercises will help to refine the procedures by identifying deficiencies and difficulties. At this stage more
elaborate exercise can be planned to involve the outside services who should be closely involved at the planning
stage services who should be closely involved at the planning stage. Each exercise should be monitored by a
member of independent observers located at various positions.
Mock Drill Records & Observation:
We will carry out mock drill and record of that will be maintained. Observation made during each mock drill will be
recorded and corrective action will be taken to correct any short fall or in action plan. Emergency plan will be
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 7. ADDITIONAL STUDIES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 174
updated based on this deficiencies omissions of short comings identified during the rehearsal will be reviewed and
incorporated in the on-site emergency plan for continual updating of the plan.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 8. PROJECT BENEFITS
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 175
8 PROJECT BENEFITS
8.1 PHYSICAL INFRASTRUCTURE
There will be increase in some small scale businesses like tea stall, catering services/hotels, grocery, confectionery,
sweet marts, cycle shop etc. around the project area.
8.2 SOCIAL INFRASTRUCTURE
Providing RO in households of nearby villages;
Providing solar streetlights in nearby village;
Help to needy children in the schools;
Providing drinking water to nearby villagers;
Helping Gram Panchayat in improving sanitation facilities.
8.3 EMPLOYMENT POTENTIAL
Due to establishment of the proposed project following benefits are envisaged for the locals and country:
During the construction phase around temporary employment will be created for ~250 local skilled and semi-
skilled workers. Existing MFL manpower (~570) is sufficient to operate proposed expansion unit;
The positive impacts include enhanced indirect employment opportunities for transporters;
Increasing other business opportunities for local people as there will be scope of hiring vehicle like tractors &
trolleys, bulldozers, JCB, excavators during construction and operation phase of the project.
8.4 OTHER TANGIBLE BENEFITS
The study area villages lie in the SEZ area of Dahej. This has impacted the lifestyle of the villagers to some extent.
The in-migration of population due to the industries has led way for the apartment system of housing that can be
easily seen in the Jolwa and Dahej villages. Local villagers giving houses on rents have added on to their incomes.
There can be seen blending of certain common attributes like food habits, common practices, lifestyle patterns,
educational preferences etc. of the rural community by coming in contact with in-migrated population in their area.
Due to the coming of the industries now there can be seen hotel/restaurant facilities available in the study area
serving all Indian cuisines like Punjabi, South Indian etc. along with traditional Gujarati Thali.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 9. ENVIRONMENTAL COST
BENEFIT ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 176
9 ENVIRONMENTAL COST BENEFIT ANALYSIS
No recommendation of environmental cost benefit analysis was given during scoping stage, hence it is not carried
out.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 177
10 ENVIRONMENTAL MANAGEMENT PLAN
10.1 INTRODUCTION
The EIA study for the proposed project has identified impacts that are likely to arise during different phases of the
project. The study has also examined the extent to which the adverse impacts identified can be controlled through
the adoption of mitigation measures. The Environment Management Plan describes both generic good practice
measures and site-specific measures, the implementation of which is aimed at mitigating potential impacts
associated with the proposed activities.
10.2 PURPOSE OF EMP
The environment management plan is prepared with a view to facilitate effective environmental management of the
project, in general and implementation of the mitigation measures in particular. The EMP provides a delivery
mechanism to address potential adverse impacts and to introduce standards of good practice to be adopted for all
project works. For each stage of the programme, the EMP lists all the requirements to ensure effective mitigation of
every potential biophysical and socio-economic impact identified in the EIA. For each impact or operation, which
could otherwise give rise to impact, the following information is presented:
Role of MFL and its contractors
A comprehensive listing of the mitigation measures (actions) that MFL will implement
The parameters that will be monitored to ensure effective implementation of the action
The timing for implementation of the action to ensure that the objectives of mitigation are fully met.
10.3 ENVIRONMENT MANAGEMENT PLAN
Details of expected aspect due to Proposed Activities in project and its management plan are given in Table 10-1.
Table 10-1: Environmental Management Plan
S
No.
Expected Aspect due
to Proposed Activity Impact Zones Management Plan Responsibility
Air Environment
1
Fugitive emissions plant
operation and storage of
Coal & Limestone.
Within 100 m
from the
source.
Ensure periodic work place
monitoring of for SPM. Process Head
2 Dust generation due to
Transportation activity.
Nearby villages
& roads.
Transportation of raw materials
and finished goods will be
carried out in covered trucks.
Process Head
Water Environment
1 Effluent generation having high TDS
Inlet and Outlet characteristics of effluent at wastewater
treatment area
Effluent generated during shall be
reused in cooling tower makeup.
ETP In charge / Third Party
2 Waste water generation
from Utilities blow downs
Wastewater generation form the
utilities blow downs shall be
treated in collection tank.
3 Consumption of water
(surface) during process At Intake Point
Fresh water demand shall be
reduced by recycling and reuse of
treated water in plant premises.
Explore the possibility of
condensate recovery from the
boiler which will reduce the fresh
ETP In charge / Third Party
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 178
S
No.
Expected Aspect due
to Proposed Activity Impact Zones Management Plan Responsibility
water demand.
Land Environment
1
Generation of Debris and
scraps during site
preparation/ construction
Within plant
premise
Debris will be used in filling of low
lying area and scraps will be sold to
registered and authorized vendors.
Head, Civil
2 Generation of Fly Ash Within plant
premise
Fly ash will be handled & disposed
as per Fly Ash Notification. It will
be given to cement plant and brick
manufacturers
Head, Civil
3
Generation of Waste
Drums/discarded liners
and containers
Within plant
premise
Will be given to GPCB authorized
vendors Head, Civil
4
Generation of used oil
and lubricants, scraps
and used spares etc.
from Equipment
maintenance
Within plant
premise
Used oil and Lubricants will be
given to authorized refineries as
per HW rules and scraps and used
spares etc. will be given to
authorized vendors
Head process in charge
Noise Environment
1
Noise Generation due to
vehicular movement for
transportation of
construction material and
Industrial Waste
Within plant
premise
PUC Certified vehicles will be
ensured during construction and
operation phase.
Security officer
2
Noise Generation due to
operation of Cooling
towers, DM plant,
pumps, compressors,
blowers, DG sets etc.
Within plant
premise
Proper acoustic enclosures will be
provided
Head Process In charge Proper PPE like ear plugs & ear
muffs will be provided
10.3.1 Air Environment
Properly designed and appropriate air pollution control equipment will be attached to flue gas stacks. Effective
measures will be taken to control fugitive emissions. Emission control measures will be taken to ensure air emission
standards and norms are strictly followed.
The Environment Management Plan focusing on air pollution related impacts due to the project are listed in Table
10-2.
Table 10-2: Environmental Management Plan
S. No. Potential
Impact Action Parameters for Monitoring Timing
1 Air Emissions
All equipment operated within specified
design parameters. (Operational phase) N/A
Duration of
programme. Any dry, dusty materials (chemicals, etc.)
shall be stored in sealed containers.
Absence of stockpiles or open
containers of dusty materials.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 179
10.3.2 Noise Environment
Noise will be regularly monitored around plant boundary for checking compliance against environmental noise
parameters as per CPCB norms. It will also be monitored near noise generating equipment to ensure that all noise
generating equipment do not generate noise in excess of the statutory norms.
All workers will be provided with required set of PPEs like earplug, earmuff etc. during construction and operation
phase activities where noise levels in excess of 80 dBA are regularly generated. For operational purpose, at design
stage, procurement of low noise equipment will be used. Preventive maintenance of noise generating equipment
shall be regularly carried out to ensure that noise levels are minimized to the extent possible.
Greenbelt will be maintained around the site to reduce noise levels.
10.3.3 Water Environment
Storm Water Drainage System
All storm water drains have been designed for adequate size and slope such that there shall not be any flooding in
the site. It will be ensured that no wastewater enter into storm water drainage system.
Raw water and its source
The main source of water is surface water which is met from Dahej GIDC. Meghmani has a permission from GIDC
for raw water supply as per committed quantity. The assurance letter for water supply from the GIDC is attached as
Annexure 18.
Rain Water Harvesting Plan
The proposed expansion project is in close vicinity of sea. The groundwater quality at site and in study area is
saline because of formational properties and hence rainwater recharging will not be advisable. It is suggested to
store maximum rainwater and used for various purposes to reduce use of freshwater consumption.
Collection of Rainwater
Quantity of Rain water collected depends upon average rainfall intensity, catchment area & run-off coefficient.
For rainwater collection calculations, areas like process and storage areas, etc are excluded due to having chances
of rainwater contamination.
The nearest IMD station is Bharuch (Boarch) having maximum rainfall intensity 0.353 m/day and 0.912 m/annum.
Based on IMD data a detailed rain water availability calculation is given in Table 10-3 and Table 10-4. The area
breaks up of site is given in Table 2-2 & Table 2-3.
As per area breakup, only greenbelt and open land is consider for rainwater collection. The detailed calculations for
rainwater collection are as under:
Table 10-3: Area Breakup for Rainwater Calculations
S. No. Land Area in m2
1 Open land 88,496
2 Greenbelt 1,76,100
Total 2,64,596
Table 10-4 Rainwater Available Per Annum
Description Area in m2 Maximum rainfall intensity per
annum in m/annum
Runoff
Coefficient
Total storm water
In m3/annum
Open land 88,496 0.912 0.5 40,354.1
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 180
Green belt 1,76,100 0.912 0.3 32,120.6
Total available Rainwater Per Annum 72,474.7
Conclusion
Annual maximum rainwater available will be 72,474.7 KL. It is suggested to have separate storm water line to
collect rainwater and transfer it to raw water reservoir after necessary treatment to store and use maximum
available rainwater to reduce freshwater consumption.
10.3.4 Solid and Hazardous Waste Management
Hazardous waste from the existing activities includes Used Oil, ETP sludge, Discarded Drums, Containers. This
waste will be collected, stored properly and will be send to authorized TSDF or will be sell to GPCB approved
authorized vendors as per the requirement. The Non- Hazardous waste includes Fly Ash. Fly ash will be handled &
disposed as per Fly Ash Notification. It will be given to cement plant and brick manufacturers.
From the proposed project, only used oil will be generated which will be collected, stored reused as low grade
lubrication and left over quantity (if any) sold to an authorized dealer or reprocessor. Apart from the same, fly ash
will be generated which will disposed as per fly ash notification, as amended till date.
The other solid waste like organic waste from kitchen waste or garden waste will be used as manure in greenbelt
development.
10.3.5 Soil Environment
The EMP for Soil Environment is provided in Table 10-5.
Table 10-5: Soil Environment
S.
No. Potential Impact
Action Parameters for
Monitoring Parameters for Monitoring Timings
1 Soil Erosion
Level the land by cutting &
filling or by importing soil
from out side
Soil WHC & porosity
Prior to vegetation & site
clearance as well as
completion of work
2 Soil contamination Control spillage of
construction materials
EC, pH and ESP (exchangeable
sodium per cent)
Completion of
construction work
3 Soil contamination Use of ETP waste water for
landscape
EC, pH and ESP (exchangeable
sodium per cent)
Before plantation & once
in a year post monsoon
10.3.6 Ecology and Biodiversity Environment
Green Belt Development
Status of Existing Greenbelt
The existing unit already has well developed greenbelt consisting of 1,70,170 m2 (31.7%) against the 25% as per
the Existing EC (Condition No. XIII of Specific Condition of EC dated 09.08.2007). A copy of EC is attached as
Annexure 6. The existing greenbelt possess ~24,000 well developed trees consisting of 22 common species.
Although additional 6,943 m2 (1.3%) within one year will be developed.
The plantation around the periphery is shown in Photograph 3-2 and map is shown in site layout plan as shown
in Map 2-4. Existing Floral species at site are given in Table 10-6.
Table 10-6: Existing Floral species reported from Green Belt Area
S. No. Tree Name / Species Name Common Name
1 Leucaena leucocephala Subabul
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 181
S. No. Tree Name / Species Name Common Name
2 Eucalyptus globulus Nilgiri
3 Azadirachta indica Neem Tree
4 Delonix regia Gulmahor
5 Pongamia pinnata Karanj
6 Ceiba pentandra Penta
7 Terminalia catappa Badam
8 Casuarina equisetifolia Saru
9 Syzygium cumini Jambu
10 Manilkara zapota Chikoo
11 Psidium guajava Guava
12 Alstonia scholaris Saptaparni
13 Lawsonia inermis Red Mahendi
14 Lawsonia inermis Green Mahendi
15 Wodyetia bifurcate Fog Tail Pam
16 Hyophorbe lagenicaulis Bottle Pam
17 Prunus dulcis Alomenda
18 Citrus limon Lemon Tree
19 Hibiscus rosa-sinensis. Jasud
20 Cycas revolute Cycus
21 Ixora coccinea Ixora
22 Ixora chinensis Chinise Exjora
Photograph 10-1: Existing Greenbelt and Landscaping Within Project Premises
Greenbelt around factory premises
Greenbelt around factory premises
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 182
Considering ~ 1,950 trees per hectare of greenbelt area (17.6 Ha), project area should have will have plantation of
~35,000 saplings. It is suggested to plant additional 11,000 trees as per Table 10-7 around periphery, near/
around built-up areas and along internal roads of the project area.
Table 10-7: Plant Species Suggested for Greenbelt and Landscaping at Various Locations
S. No. Scientific Name Common Name Ecological performance Type Location of Plant
1 Aegle marmelos Bel CN, DC Evergreen A
2 Azardirachta indica Neem CN, OGE, DC Evergreen A,B
3 Delbergia sissoo Shesham DC, DR, FR Evergreen A,B
4 Ficus bengalensis Banyan, Vad CN, DC Evergreen B
5 Ficus religiosa Peepal CN, OGE, DC Evergreen B
6 Tamarindus indica Emali CN, OGE, DC Evergreen B
7 Terminalia arjuna Arjun CN, OGE, DC Evergreen B
Ecological performance: CN –Control Noise level, OGE – Absorb Gas Emission (Sexena 1991)6 and (Abbasi & Khan 2000)7, DC -
Dust Controller (CPCB 2007)8.
Location of Plant: A-Around built-up area and along internal road, B-on Project periphery / boundary.
Budget Allocation for Greenbelt within Project Site
Greenbelt around the project site will be developed within five years. Detailed budget break-up is given in Table
10-8.
Table 10-8: Budget for Proposed Greenbelt Development within Project Site
S.
No
Work or
Activity 1st year 2nd year 3rd year 4th year 5th year Budget (INR)
Within Project Site, totally 10,000 saplings will be planted (Approx. Cost @ Rs. 100 per sapling / plant)
Saplings Required 2,200 2,200 2,200 2,200 2,200 11,00,000/-
Amount 2,20,000/- 2,20,000/- 2,20,000/- 2,20,000/- 2,20,000/-
Total Budget 11,00,000/-9
Greenbelt in the LIZ (Likely Impact Zone) within 1 Km. Radius Area
Additional plantation for green belt development will be carried out in the various places (on agriculture hedges) of
LIZ to improve habitat status of the project area. This activity will be carried out as a part of conservation plan of
Schedule-I reported from the study area, so species recommended for plantation and budget allocation for same is
given in the conservation plan section.
Plantation Technique and Care
Following basic procedures need to be followed for greening the area.
Since the project area having poor / slightly saline soil quality, plantation of tree species required approx. 1 m3
pit for soil enrichment;
Pit should be filled with imported soil with 3:1:1 the ratio of sand, silt and form yard manure;
Procure well grown saplings of recommended species from the nearby Forest Department of nursery;
Make 1m diameter ring bund around the planted saplings for water retention;
--------------------------------------------------------------------- 6 Saxena, V.S. 1991. Afforestation as a tool for environmental improvement. In: Executive development program on greening the
townships. Vaniki Prashikshan Sansthan, Jaipur. Pp 13-44.
7 Greenbelts for Pollution Control: Concepts, Design, Applications. 2000. Abbasi, S.A. and F.I. Khan. Discovery Publishing House, New
Delhi.
10 Phytoremediation of particulate matter from ambient environment through dust capturing plant species. Published 2007 by Central
Pollution Control Board (CPCB), Ministry of Environment & Forests, Govt. of India in Delhi.
9 All other costs like labor, soil filling dressing, irrigation etc. costs will be burned by client / proponent.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 183
Watering of sapling is species specific, therefore watering need to be done daily in monsoon and once in 2
days in other seasons for a period of two years.
Monitoring Protocol
The plantations need to be managed by regular watering, soil enrichment work, applying manure, weeding
and provide proper protection.
Replacement of sapling (replanting) required whenever mortality occurs in the plantation during the growth
stage.
Plantation requires after care for a period of minimum five years till the saplings attain matured tree stage.
Any damage to the developed greenbelt due to any natural or cattle activity should be redeveloped and
maintained by the agency.
Biodiversity / Ecological Monitoring
Since the identified impact zone area supports Schedule-I species i.e. Peacock; population of these species will be
monitored. Every year, status survey of these species will be conducted and report will be submitted to the local
forest department. Survival rate of the plantation should be monitored within project boundary (core zone) as well
as other plantation carried out in the LIZ area.
Conservation Plan for schedule-I Species
Conservation plan will be prepared to enhance the population status of this Schedule species as well as overall
improvement of biodiversity which will be implemented in consultation of “Local Farmers and State Forest
Department”.
Likely Impact Zone (LIZ) Description
LIZ area includes five water bodies and has been reported with Schedule-I species i.e. Peacock.
Selection of Plant Species
All the facts considered for species selection are same as facts considered for within project site.
Habitat Improvement through Plantation in LIZ
In identified LIZ area, plantation as per Table 10-9 will be carried out on the agriculture hedges.
Table 10-9: List of plant species for plantation in LIZ Area
S. No. Scientific Name Common Name Ecological performance Locations
1 Aegle marmelos Bel CN, DC
Agriculture Hedges
2 Azardirachta indica Neem CN, OGE, DC
3 Delbergia sissoo Shisham DC, DR, FR
4 Delonix regia Gulmohar DC
5 Ficus bengalensis Banyan, Vad CN, DC
6 Ficus religiosa Peepal CN, OGE, DC
7 Syzygium cumini Jamun, Jambu CN, DC
8 Terminalia catappa Desi Badam CN, OGE, DC
Ecological performance: CN –Control Noise level, OGE – Absorb Gas emission (Sexena 1991)10 and (Abbasi & Khan 2000)11, DC -
Dust Controller (CPCB 2007)12.
--------------------------------------------------------------------- 10 Saxena, V.S. 1991. Afforestation as a tool for environmental improvement. In: Executive development program on greening the
townships. Vaniki Prashikshan Sansthan, Jaipur. Pp 13-44.
11 Greenbelts for Pollution Control: Concepts, Design, Applications. 2000. Abbasi, S.A. and F.I. Khan. Discovery Publishing House, New
Delhi.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 184
The details of budget allocated for additional greenbelt, habitat improvement and conservation of threatened
species of the study area is provided in Table 10-10.
Table 10-10: Budget for Additional Greenbelt / Habitat Improvement Programme
S N Work or Activity 1st year 2nd year 3rd year 4th year 5th year Budget (INR)
1 Plantation on agriculture hedges will be carried out up to five years (Approx. Cost @ Rs. 100 per plant).
Saplings Required 500 500 500 500 500 2,50,000/-
Amount 50,000 50,000 50,000 50,000 50,000
Total Budget 2,50,000/-
(Two Lakhs Fifty Thousand Rupees)13
10.3.7 Concept of Waste Minimization, Recycle, Reuse / Recovery
Waste Minimization
Debris and Excavated Soil:
The excavated soil and debris generated during the construction phase will be used for filling up low lying areas.
Cleaner Production Measures
The maximum utilization of imported coal.
Working area should be impervious to protect the soil contamination.
The vessels/storage tanks/storage drums, etc. should be closed properly.
Proper housekeeping practices make the system easier and less costly.
Checking of all joints/flanges/mechanical equipment should be done at regular interval.
Maintenance of all equipments and utilities should be done at periodical interval.
In case of any spillage/leakages etc. in process and packaging are to be separately collected and disposed off
instead of allowing these to effluent streams. This will reduce load and increase the efficiency of treatment
system.
Rain water harvesting system which will be reused for the gardening within premises therefore, overall fresh
water requirement will be reduced.
Recycle / Reuse and Resource recovery
Water Conservation steps
Exploring the condensate recovery from the boiler.
Reuse of treated sewage from STP for Gardening.
Use of drip irrigation/sprinkling system for green belt development, which will reduce the fresh water demand
Adopting Rain water harvesting methods. Refer Section 10.3.3.
Employees will be trained to avoid wastage of water and use water effectively and an environment will be
developed within the plant premises by also pacing sign boards for conserving water at various locations.
Energy Conservation
Regular energy conservation initiatives are taken to reduce energy consumption.
Major initiatives being installation of VFD’s;
Arresting steam leakage from turbine balance piston;
Installation of additional air pre-heater;
--------------------------------------------------------------------- 12 Phytoremediation of particulate matter from ambient environment through dust capturing plant species. Published 2007 by Central
Pollution Control Board, Ministry of Environment & Forests, Govt. of India in Delhi.
13 All other costs like labor, soil filling dressing, irrigation etc. costs will be burned by client / proponent.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 185
Anti-friction ceramic based coating on wetted part of cooling water pumps.
Natural Resource Conservation
Adopting Rain water harvesting methods. Refer Section 10.3.3.
Development of greenbelt area. Refer Section 10.3.6.
10.3.8 Environmental Management Cell
MFL is having a system of reporting of non-compliances / violations of environmental norms to the Board of
Directors of the company and / or shareholders or stakeholders at large. Environment management cell will be
headed by a senior manager supported by managers and other supporting staff which shall perform the following
functions:
Achieve objectives of the ‘Environment Protection Policy’ of the management;
Collect information from regular monitoring and create a database;
Analyze the data and decide thrust area;
Based on the data collected, decide target for each thrust area;
Carry out ‘Projects’ in each thrust area to arrive at practical solutions to environmental problems;
Discuss the reports of study on environment and disseminate the information;
Work out ‘Action plan’ for implementation of the recommendations made in the reports;
Prepare Management Information System (MIS) reports and budget for environment management program.
Generic hierarchy of Environment Management Cell is shown in Figure 10-1.
Figure 10-1: Hierarchy of Environment Management Cell
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 10. ENVIRONMENTAL
MANAGEMENT PLAN
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 186
10.3.9 Reporting mechanism of Non-Compliance / Violations of Environmental Norms
Reporting mechanism of Non-Compliance / Violations of Environmental Norms to the Board of Directors is given in
Figure 10-2.
Figure 10-2: Reporting Mechanism
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 187
11 SUMMARY & CONCLUSION
This executive summary summarizes the findings of the EIA study undertaken as per SEAC’s ToR letter
SEIAA/GUJ/TOR/1(d)/1258/2017 dated 30.11.2017 in accordance with the EIA guidelines. The summary is intended
to provide an overview of the key environmental issues and also list the measures recommended to attenuate the
impacts and manage the mitigating measures.
11.1 PROJECT DESCRIPTION
11.1.1 Company and Project Proponent
Proposed expansion unit of Meghmani Finechem Limited (MFL) is promoted by Shri Maulik Jayantibhai Patel and
Shri Kaushal Ashish Soparkar. Meghmani group is a leading group of India operating in a range of diversified
industries viz. Pigments, Agro Chemicals, Dyestuffs and Caustic Chlorine.
11.1.2 Proposed Project
Existing Capacity
MFL is currently manufacturing products as mentioned in Table 11-1 at their existing facility.
Table 11-1: List of Existing Products
S.
No. Products Capacity (MTPM) As per EC / CTE / CC&A
A Chlor - Alkali Units
1
Caustic Soda 16,800 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
OR
Caustic Soda 15,000 CC&A Amendment, dated 24.06.2016 issued vide Letter
No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/360636 Caustic Potash 1,800
2 Chlorine Gas 14,885 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
3 Hydrogen Gas 420 EC: J-11011/06/2007-IA II(I) dated 09.08.2007
4 78 % Dilute Sulphuric Acid 653 EC: J-11011/259/2011 – IA dated 12.09.2012
5 30 % Hydrochloric Acid 7,583 EC: J-11011/259/2011 – IA dated 12.09.2012
6 Sodium Hypochlorite 1,458 EC: J-11011/259/2011 – IA dated 12.09.2012
7 Hydrogen Peroxide 1,200* CTE Amendment, dated 01.05.2017 issued vide Letter
No. GPCB/BRCH-B-CCA-1233(4)/ID-32979/411050
B Synthetic Organic Units
1 Meta Phenoxy Benzaldehyde Alcohol 200** EC: J-11011/259/2011 – IA dated 12.09.2012
* Not being produced at the site as on date, construction work going on, accordingly CC&A will be amended.
** Not being produced at the site as on date, accordingly CC&A is already amended on 24.06.2016.
For the existing products EC/CTE/CC&A is already received.
Certified Compliance report of the EC is also provided by RO, MOEF&CC (Bhopal).
Proposed Capacity
The proposed project is for Expansion in Power Plant capacity from 65 MW to 132 MW at GIDC Dahej, Bharuch,
Gujarat. Phase-wise two Power Plants of 33.5 MW capacity will be installed. The capacity for the existing and
proposed power plant is tabulated in Table 11-2.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 188
Table 11-2: Existing and Proposed Capacities – Power Plant
S.
No. Particular Unit
Existing
Capacity
Proposed
Additional Capacity
Total After
Expansion
1 Power Plant MW 65 67 132
2 Steam (including process & power) TPH 290 360 650
The proposed project falls under 1(d), Thermal Power Plant ‘Project or Activities’ listed within the Category to the
EIA Notification dated September 14th, 2006 (amended till date). This project is classified as Category “B” project.
MFL has also applied for Environment Clearance for Expansion of Existing products and new product manufacturing
from MoEF&CC having File No. J-11011/13/2014-IA II(I) from MoEF&CC. As the power plant capacity is less than
500 MW, MFL has seeked environment clearance from SEIAA, Gujarat.
11.1.3 Location of the Project
The project site is situated at Plot No.: CH-1/CH-2, GIDC Dahej, Taluka: Vagra, District: Bharuch, Gujarat,
admeasuring an area of 53.347 hectares (5,33,470 m2). Plot area of the proposed power plant consists of 3,702 m2.
The project falls within the Notified Industrial Estate, Petro Chemical and Petroleum Industrial Region (PCPIR),
developed by GIDC, for which Environmental Clearance is received vide F. No. 21-49/2010-IA-III dated 14th
September 2017. It is categorized as chemical zone for setting up Chemical Industries.
11.1.4 Project Cost
The estimated project cost would be ~ INR 230 Crore.
11.1.5 Raw Materials and Source
Main raw material for Power Plant is Imported Coal which will be sourced from Open market within Dahej, mainly
from Adani.
11.1.6 Utilities
The estimated list of utilities required for the project is as given in Table 11-3.
Table 11-3: List of Utilities
S.
No. Utitlties Unit Existing Proposed Total Source
1
Auxillary Power to
operate power
plant
MW 1.65 1.70 3.35
DGVCL / Existing unit (standby back-up
supply for emergency conditions & safe
shutdown of power plant in case of main
power failure).
2 Water KLD 5,633 3,873 9,506 GIDC Reservoir
3
Manpower
a) Construction
b) Operation
Nos a) –
b) 570
a) 250
b) –
a) 250
b) 570
Local skilled and semi-skilled workers will be
engaged during construction phase. Existing
manpower is sufficient to operate proposed
expansion units.
11.1.7 Process
The Imported Coal (~4,200 Kcal/Kg GCV) will be fed to furnace of the CFBC Boilers (2 x 180 TPH) through feeders
from the Coal storage. Coal will be mixed with Limestone to reduce SOx emission. This mix will be fired in the
furnace by means of FD-Fan air. The saturated steam is generated in the Boiler drum and passed to the Primary,
Secondary & final super heaters to get the superheated steam @ 535°C & 109 ata from the Boilers. The
superheated steam is fed to the Steam Turbine and it rotates the steam Turbine which is coupled with Generators (
2 Nos). The power of 67 MW will be generated in the Generators and distributed in house. Flue gas shall meet the
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 189
statutory norms. To comply emission norms, necessary dosing of lime stone shall be done via feeder. Design of
ESPs will be as per the state government norms and MoEF&CC Guidelines / standards.
11.1.8 Waste Water
Steam condensate will be recycled back into the process. There will not be any generation of process effluent.
Boiler blow down will be directly used for cooling tower make up water while other effluents will be collected into
collection tank where pH correction will be carried out if required. Then the treated wastewater will be used for
dust suppression, in coal handling and & in existing ash handling unit. Thus, zero effluent discharge criteria for new
power plant will be met. Rest of the effluent from other plants will be treated in existing ETP and will be disposed
to GIDC Drain after meeting the GPCB effluent discharge norms.
11.1.9 Air Emissions
Due to the proposed project following types of air emissions are envisaged:
Point Source: SPM, SO2 & NOx from flue gas stacks;
Area Source: SPM emissions from coal stock piles;
Line Source: Vehicular emissions like SPM, CO & HC’s from exhaust of the vehicles;
Fugitive emissions from coal handling & storage are envisaged.
11.1.10 Hazardous and Other Solid Wastes
The following solid / hazardous wastes will be generated during operations:
Hazardous Waste: Used Oil;
Non-Hazardous Waste: Fly Ash;
Domestic Solid Waste: Paper and Food waste;
Small amounts of E-waste and scrap.
These will be managed as per the applicable Rules, mainly, Hazardous Waste (Management, Handling, Storage and
Transboundary) Rules 2016, as amended till date.
11.2 DESCRIPTION OF THE ENVIRONMENT
11.2.1 Study Period and Area
Baseline environmental study was carried out in December 2016 – February 2017 (Winter Season) within 10 Km
radius of the project site. Secondary data, not older than three years, was also used.
Air monitoring was carried out at 8 locations. Noise monitoring was carried out at 5 locations. Surface water
samples from 8 locations including ponds and estuary were collected, ground water samples from 8 location
Borewells/ Openwells and soil samples from 6 locations were collected and analyzed.
11.2.2 Land use and Land cover
There are around 45 major industries in the study area. Land use of study area has been broadly covered by
Vegetation cover (~29.2%), Wasteland (19.3 %), Agricultural land (~16.3%), Water Bodies (16.1%), Habitation
(~6.2%), Forest Area (1.5%) and Others like salt pans, grass cover & creek as (11.6%).
The crops cultivated in the study area are cotton, Castor Chillies and Wheat are grown in this region.
11.2.3 Meteorology
Based on the long-term climatological tables as per Indian Meteorological Department (IMD) for Broach (Bharuch)
(Station ID: 42841), during winter season, the maximum & minimum temperature recorded are 33.5°C & 11.3°C
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 190
respectively. The mean hourly relative humidity recorded during morning, remains between 64 – 74% and in the
evening, remains between and 34 – 44%. Pre-dominant wind direction is from NE (48.5%).
Site specific meteorological data was collected by installing automatic meteorological station at roof top of SEZ
office, which is ~ 8.30 Km in W direction from the project site.
Maximum and Minimum temperature were recorded as 36.7°C (in the month of April) & 15.2°C (in the month of
January) respectively. Mornings are more humid than evenings and relative humidity ranges from 78 – 86% in
monsoon mornings to 34 – 43% in winter evenings. Average wind speed was 3.1 m/sec & Predominant wind
direction was from NE to SW direction (27%) direction.
11.2.4 Ambient Air Quality
It is noted from Table 11-4 that maximum PM10 results exceeds NAAQS at all locations except near forest area and
salt pan and maximum PM2.5 results exceeds NAAQS at Vadadala Crossing which could be due to:
Vehicular movement on the “kaccha” roads of the villages;
Industrial & infrastructure development activities in study area (PCPIR & residential projects);
Rural activities like burning of cow dung for household purposes like using it in “chullas”.
Table 11-4: Ambient Air Quality Data
Station
code
All stations are in
Industrial, Residential,
Rural & Other Areas
(CPCB)
Parameters & Results
Note: All units are in µg/m3. Figures in brackets are CPCB limits. Minimum
Reportable Readings are 8 µg/m3 for SO2, 10 µg/m3 for NOX.
PM10 PM2.5 SO2 NOX
100 [24 Hours] 60 [24 Hours] 80 [24 Hours] 80 [24 Hours]
AA1 At Project Site
Maximum 110 63 15.6 36.5
Minimum 50 21 8.0 10.6
Average 74 30 9.5 18.0
AA2 At GLC Area
Maximum 102 57 13.6 28.5
Minimum 58 21 <8.0 15.6
Average 77 27 9.2 19.9
AA3 At Vadadla Village
Maximum 112 50 9.8 21.4
Minimum 54 21 <8.0 13.0
Average 86 35 8.3 17.1
AA4 At Vadadla Crossing
Maximum 123 63 14.6 36.5
Minimum 52 25 <8.0 16.2
Average 96 38 10.0 24.5
AA5 Nr. Salt Pan Area
Maximum 68 32 10.2 28.6
Minimum 42 15 <8.0 10.2
Average 57 25 8.2 16.5
AA6 Nr. Forest Area
Maximum 72 37 9.1 21.7
Minimum 47 22 <8.0 <10
Average 63 29 8.2 17.2
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 191
Station
code
All stations are in
Industrial, Residential,
Rural & Other Areas
(CPCB)
Parameters & Results
Note: All units are in µg/m3. Figures in brackets are CPCB limits. Minimum
Reportable Readings are 8 µg/m3 for SO2, 10 µg/m3 for NOX.
PM10 PM2.5 SO2 NOX
100 [24 Hours] 60 [24 Hours] 80 [24 Hours] 80 [24 Hours]
AA7 At Vav Village
Maximum 107 27 10.4 25.3
Minimum 26 6 8.0 14.7
Average 68 16 8.8 19.4
98%tile 105 27 10.2 25.1
AA8 At Jolwa
Maximum 102 25 10.3 23.4
Minimum 17 8 8.0 14.7
Average 61 18 8.9 18.6
11.2.5 Existing Stack Emissions
Samples from existing stacks were collected and analyzed. It was found that all the parameters as prescribed in
their valid CTO were within the prescribed standards. Monitoring results were compared with monthly monitoring
reports by MFL, Latest Audit Report and past GPCB’s monitoring data. No abnormal emissions were reported in
secondary data.
11.2.6 Traffic Survey
Traffic Survey was carried out on SH – 6 in S direction of the proposed site, road connecting site to Dahej &
Bharuch on 14th July, 2017. As per IRC:106-1990, the road width of this road is 15 meters, which is a 3 Lane (One
Way) Arterial Road.
Average peak hourly traffic on this route is 531 and 570 PCU respectively.
11.2.7 Noise
Noise level during day time and night time, in Industrial area was observed within the CPCB standards i.e. industrial
area (75 dBA (d) & 70 dBA (n)). Noise level during daytime and night time, in Residential area was observed within
the CPCB standards i.e. residential area (55 dBA (d) & 45 dBA (n)). Noise results are mentioned in Table 11-5.
Table 11-5: Noise Monitoring Results
Location
Code Location
Date of
Monitoring
Category
Area/Zone
CPCB Limits in dB (A) Average Noise levels in dB (A)
Day Time Night Time Day Time Night Time
NL1 Nr Security gate 15.02.17 Industrial 75.0 70.0 65.2 55.9
NL2 At project site
(NW) 15.02.17 Industrial 75.0 70.0 64.7 56.0
NL3 Near Cooling
Tower 16.02.17 Industrial 75.0 70.0 72.5 64.5
NL4 Near Utility area 16.02.17 Industrial 75.0 70.0 71.3 62.7
NL5 Vadadala village 18.02.17 Residential 55.0 45.0 54.4 44.4
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM
65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 192
11.2.8 Surface Water and Ground Water Quality
Surface Water Quality
Based on the results mentioned in Table 11-8 & Table 11-9, surface water quality of the study area is
summarized in Table 11-6.
Table 11-6: Surface Water Quality in Study Area - Summary
Code Location Date of
Sampling Source
Distance
from
Project Site
in Km
Direction
w.r.t
Project
Site
Results Higher than Permissible
Limits
SW 1 Jolwa 20.01.2017 Pond 3.6 ESE BOD, Chlorides
SW 2 Vav 20.01.2017 Pond 4.5 NE BOD, Total Hardness, Mg++ Hardness
SW 3 Kadodara 20.01.2017 Pond 3.5 NE BOD, Total Hardness, Mg++ Hardness
SW 4 Wadadla 20.01.2017 Pond 1.8 ENE BOD, Total Hardness, Mg++ Hardness
SW 5 Dahej 20.01.2017 Pond 2.6 WSW BOD, Total Hardness, Mg++ Hardness
SW 6 Rahiyad 20.01.2017 Pond 6.4 ESE BOD, Total Hardness, Mg++ Hardness
SW 7 Narmada River
(D/s) nr. Ambeta 20.01.2017 Estuary 4.3 SSW
Class SW-I as per coastal water marine
standards SW 8
Narmada River
(U/s) nr. Koliyad 20.01.2017 Estuary 9.1 ESE
Ground Water Quality
Based on the results mentioned in Table 11-10, ground water quality of the study area is summarized in Table
11-7.
Table 11-7: Ground Water Quality in Study Area - Summary
Code Location Source Date of
Sampling
Distance
from Project
Site in Km
Direction
w.r.t
Project Site
Results Higher than Permissible Limits
GW 1 Jolwa Bore well 06.02.2017 1.57 SW TDS, Fluoride
GW 2 Vadadla Bore well 06.02.2017 3.01 West TDS
GW 3 Vav Bore well 06.02.2017 3.42 NW TDS
GW 4 Galenda Bore well 06.02.2017 2.12 NE -
GW 5 Atali Bore well 06.02.2017 4.16 E TDS
GW 6 Rahiyad Bore well 06.02.2017 3.00 SE TDS
GW 7 Lakhigam Bore well 06.02.2017 7.00 SW -
GW 8 Dahej Bore well 06.02.2017 3.00 SW TDS
11.2.9 Soil
It is observed from the Table 11-11, that at different locations:
The porosity ranged from 55 - 61% and water holding capacity varied from 52.40 - 62.30%;
The permeability ranged from 2.24 - 10.7 mm/hr;
The EC of soil ranged from 0.140 - 0.808 dS/m;
The pH of soil ranged from 7.63 - 8.36;
Among water soluble cations predominance of sodium was seen followed by Ca, Mg and K;
Soil texture in all the soil samples was silty clay- clay loam, hence whatever variation observed was mainly due
to variation in organic matter content of soils.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 193
Table 11-8: Surface Water (River) Analysis Results
S.
No. Parameters Unit
Classification of Water Sample Details
SW1 (Jolva) SW2 (Vav) SW3 (Kadodara) SW4 (Vadadla) SW5 (Dahej) SW6 (Rahiyad)
A B C D E Pond Pond Pond Pond Pond Pond
20.01.2017 20.01.2017 20.01.2017 20.01.2017 20.01.2017 20.01.2017
1 pH pH Scale 6.5 to 8.5 6.5 to 8.5 6.0 to 9.0 6.5 to 8.5 6.5 to 8.5 7.36 7.29 7.29 7.43 7.33 7.75
2 Total Dissolved Oxygen mg/l 6 5 4 4 NS 3.8 3.6 4.2 3.2 3.9 7.75
3 Total Dissolved Solids mg/l 500 NS 1500 NS 2100 1,352 568 812 720 324 776
4 Electrical Conductivity μmhos/cm NS NS NS 1000 2250 2122 686 1092 1035 548 984
5 BOD mg/l 2 3 3 NS NS 13 10 20 8 12 15
6 Total Hardness mg/l 300 NS NS NS NS 200 320 320 320 270 380
7 Ca++ Hardness mg/l 200 NS NS NS NS 188 194 100 80 114 92
8 Mg++ Hardness mg/l 100 NS NS NS NS 12 126 220 240 156 288
9 Copper mg/l 1.5 NS 1.5 NS NS <0.05 <0.05 <0.05 <0.05 <0.05 <0.05
10 Iron mg/l 0.3 NS 50 NS NS <0.1 <0.3 <0.3 <0.3 <0.3 <0.3
11 Manganese mg/l 0.5 NS NS NS NS <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
12 Chlorides(as CL) mg/l 250 NS 600 NS 600 692 102 270 251 86 211
13 Sulphates mg/l 400 NS 400 NS 1000 70 64 57 60 15 46
14 Nitrate (as NO3) mg/l 20 NS 50 NS NS 13.6 13.9 23.35 9.28 11.85 5.5
15 Fluoride mg/l 1.5 1.5 1.5 NS NS 0.79 0.74 0.83 0.75 0.36 0.39
16 Phenolic Compound mg/l 0.002 0.005 0.005 NS NS <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
17 Mercury mg/l 0.001 NS NS NS NS <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
18 Cadmium mg/l 0.01 NS 0.01 NS NS <0.03 <0.03 <0.03 <0.03 <0.03 <0.03
19 Arsenic mg/l 0.05 NA 0.2 NS NS <0.002 <0.002 <0.002 <0.002 <0.002 <0.002
20 Cyanide mg/l 0.05 0.05 0.05 NS NS <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
21 Lead mg/l 0.1 NS 0.1 NS NS <0.01 <0.01 <0.01 <0.01 <0.01 <0.01
22 Zinc mg/l 15 NS 15 NS NS <0.08 <0.08 <0.08 <0.08 <0.08 <0.08
23 Chromium mg/l 0.05 1 0.05 NS NS <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
24 Sodium Absorption Ratio mg/gm NS NS NS NS 26 10.29 0.59 2.64 4.27 0.39 0.33
25 Total Coliform MPN/100ml 50 500 5000 NS NS 170 78 330 110 170 170
NS: Not Specified, NR: No Relaxation
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 194
Table 11-9: Analysis Result of River (Estuary) Water Samples
S.
No. Parameters Unit
Classification for Coastal Water Marine (CPCB)
Sampling Locations
SW7 SW8
Narmada Estuary
(D/s)
Nr. Ambetha
Narmada Estuary
(U/s)
Nr. Koliyad SW-I SW-II SW-III SW-IV SW-V
1 pH - 6.5 to 8.5 6.5 to 8.5 6.5 to 8.5 6.0 to 9.0 6.0 to 9.0 7.55 7.73
2 Total Dissolved Oxygen mg/l 5.0 4.0 3.0 3.0 3.0 4.1 4.0
3 Colour and Odour - No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
No Colour
No Odour
4 Floating Matters mg/l None None None 10 - None None
5 Suspended Solids mg/l None from Sewage or Industrial waste Origin - - - - 30 27
6 Turbidity NTU - 30 30 - - 2.5 2.3
7 BOD mg/l - 3 - 5 - 4 5
8 Oil and Grease
(including Petroleum Products) mg/l 0.1 - - - - <0.4 <0.4
9 Mercury (as Hg) mg/l 0.001 - - - - <0.001 <0.001
10 Lead (as Pb) mg/l 0.001 - - - - <0.01 <0.01
11 Cadmium (as Cd) mg/l 0.01 - - - - <0.001 <0.001
12 Dissolved Iron (as Fe) mg/l - - 0.5 - - <0.1 <0.1
13 Dissolved Manganese ( as Mn) mg/l - - 0.5 - - <0.04 <0.04
14 Faecal Coliform ml (MPN) - 100/100 500/100 500/100 500/100 310 170
15 Sludge Deposits, Solid refuse floating Solids, Oil Grease and Scum - - - - - None except for treated Sewage and Industrial waste Effluent None None
Table 11-10: Analysis Results of Groundwater Samples
Sampling Location Jolwa Vadadla Vav Galenda Atali Rahiyad Lakhigam Dahej
S. No. Parameters Unit IS 10500 Standard Limits for drinking water GW1 GW2 GW3 GW4 GW 5 GW 6 GW 7 GW 8
Acceptable limit Permissible limit Bore well Bore well Bore well Bore well Bore well Bore well Bore well Bore well
1 pH pH scale 6.5-8.5 NR 7.32 7.70 7.45 7.50 7.55 7.67 7.98 7.88
2 Temperature oC - - 30 29 29 29 29 29 30 30
3 Turbidity NTU 1 5 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
4 TDS mg/lit 500 2,000 1,132 656 812 384 1,168 1,028 274 845
5 Electrical conductivity µmho/cm - - 1,900 1,214 1,324 710 2,200 1,812 415 1,417
6 COD mg/lit - - <2 <5 <5 <5 <5 <5 <2 <2
7 BOD mg/lit - - <4 <3 <3 <3 <3 <3 <4 <4
8 Phenol mg/lit 0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
9 Chlorides mg/lit 250 1,000 453 169 256 67 333 362 72 265
10 Sulphates mg/lit 200 400 34 183 115 3 182 123 4 67
11 Total Hardness mg/lit 200 600 290 180 220 340 350 480 200 340
12 Ca++ Hardness mg/lit - - 176 26 64 72 136 108 54 70
13 Mg++ Hardness mg/lit - - 114 154 156 268 155 170 146 270
14 Total Alkalinity mg/lit 200 600 110 180 130 140 150 180 240 220
15 Nitrate mg/lit 45 NR 38.87 3.5 23.8 23.8 73.9 58.0 9.66 38.1
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 195
Sampling Location Jolwa Vadadla Vav Galenda Atali Rahiyad Lakhigam Dahej
S. No. Parameters Unit IS 10500 Standard Limits for drinking water GW1 GW2 GW3 GW4 GW 5 GW 6 GW 7 GW 8
Acceptable limit Permissible limit Bore well Bore well Bore well Bore well Bore well Bore well Bore well Bore well
16 Fluoride mg/lit 1 1.5 2.27 0.93 1.33 0.41 0.70 0.79 0.71 0.71
17 Sodium mg/lit - - 221.7 75 165 15.4 214 235 35.2 132.4
18 Potassium mg/lit - - 11.3 10 15.6 23.6 16.5 10 7.80 15.6
19 Calcium mg/lit 75 200 70.54 10.4 128.2 28.8 54.5 43.3 21.64 28.06
20 Magnesium mg/lit 30 100 27.7 37.4 37.9 65.1 52.0 90.4 35.48 65.61
21 Salinity mg/lit - - 816.65 304 460 122 599 651 130.32 477.83
22 Total Nitrogen mg/lit 0.5 NR 8.94 0.79 4.70 4.42 17.45 13.96 2.39 8.96
23 Total Phosphorous mg/lit - - <1 <1 <1 <1 <1 <1 <1 <1
24 Dissolved Oxygen mg/lit - - 2.7 4.0 3.2 3.5 3.4 3.2 2.3 2.9
25 Ammonical Nitrogen mg/lit NS NS <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
26 SAR - - - 5.64 2.4 3.28 0.36 3.6 3.36 1.08 3.11
27 Heavy Metals
a Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.002 <0.002 <0.002 <0.002 <0.002 <0.01 <0.01
b Cadmium (as Cd) mg/l 0.003 NR <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
c Cromium (as Cr) mg/l 0.05 NR <0.05 <0.003 <0.003 <0.003 <0.003 <0.003 <0.05 <0.05
d Copper (as Cu) mg/l 0.05 1.5 <0.03 <0.05 <0.05 <0.05 <0.05 <0.05 <0.03 <0.03
e Cyanide (as CN) mg/l 0.05 NR <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003 <0.003
f Iron (as Fe) mg/l 0.3 NR <0.05 <0.1 <0.1 <0.1 <0.1 <0.1 <0.05 <0.05
g Lead (as Pb) mg/l 0.01 NR <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01
h Mercury (as Hg) mg/l 0.001 NR <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001
i Manganese (as Mn) mg/l 0.1 0.3 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04 <0.04
j Nickel (as Ni) mg/l 0.02 NR <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02
k Zinc (as Zn) mg/l 5 15 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08 <0.08
28 Total Coliform MPN/100ml Shall not be detectable
in any 100 ml sample Absent Absent Absent Absent Absent Absent Absent Absent
29 Faecal Coliforms MPN/100ml Shall not be detectable
in any 100 ml sample Absent Absent Absent Absent Absent Absent Absent Absent
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 196
Table 11-11: Soil Analysis Results
S.
No Parameter Unit
Sampling Locations
S1
Jolwa
S2
Vav
S3
Vadadala
S4
Galenda
S5
Atali
S6
Rahiyad
1 Porosity % 56 56 59 60 61 60
2 Water Holding Capacity % 55.20 61.30 62.30 52.40 60.80 57.36
3 Permeability mm/hr. 7.4 9.44 10.7 2.24 2.55 1.33
4 Particle Size Distribution -
a Sand % 36.00 27.00 23.00 25.00 28.00 26.00
b Clay % 29.00 32.00 36.00 12.00 12.00 21.00
c Silt % 35.00 41.00 41.00 63.00 60.00 53.00
6 Texture - Clay loam Clay loam Clay loam Silty loam Silty loam Silty loam
7 Cation Exchange Capacity meq/100gm 36.00 42.00 47.00 40.00 34.00 42.00
8 Electrical Conductivity μmhos/cm 285 140 294 800 265 281
9 Sodium Absorption Ratio (SAR) - 1.32 1.06 1.73 3.08 0.31 0.32
10 Exchangeable sodium % 0.69 0.31 1.28 3.17 <0.1 <0.1
11 pH - 8.10 7.87 8.36 7.85 7.72 7.63
12 Calcium gm/kg 0.46 0.85 0.32 0.52 0.43 0.72
13 Magnesium gm/kg 0.25 0.21 0.29 0.41 0.42 0.39
14 Sodium gm/kg 0.64 0.60 0.80 1.74 0.17 0.19
15 Potassium gm/kg 0.10 0.12 0.10 0.16 0.36 0.16
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 197
11.2.10 Biological Environment
Project Site / Core Zone
As a part of terrestrial biodiversity study, Project Site has well developed greenbelt reported with 22 common
species of flora / plants. This includes Subabul, Nilgiri, Neem, Gulmohar, Karanj, Penta, Badam, Saru, Jambu,
Chickoo, Mehendi, Guvava, Jasud, Cycus, Pam, Saptaparmi etc. Among faunal diversity, no herpetofauna has been
reported. Among avifauna only 4 common species of birds which includes Cattle Egret, Common Babbler, House
Crow and Red-vented Bulbul were reported from the project site. No direct or indirect evidences of mammals were
reported from the site.
Study Area / Buffer Zone
As a part of terrestrial biodiversity study, buffer zone has been reported with 155 floral species, which includes 53
species of trees (25 families), 30 species of Shrubs (21 families), 50 species of herbs (27 families), 8 species of
grasses (one family) and 14 species of climbers (6 families). Among faunal diversity overall 8 herpetofaunal species
which includes Common garden lizard, Common rat snake, Common Indian Monitor, Yellow-Green House Gecko,
Fan-Throated Lizard, Spectacled Cobra, Russell’s Viper, and Common Indian Krait known by their common names
have been reported. Among mammals, total 9 species from six families which includes Common Langur, Indian Fox,
Jungle cat, Common Mongoose, Indian Hare, Indian field mouse, Black rat, Five striped Palm squirrel and Nilgai
have been reported. Among butterflies, total 6 (six) species which includes Stripped Tiger, Danaid egg fly, Common
bush brown, Common Mormon, Common Grass yellow and White orange tip were reported.
Major crops grown are Tuver Wheat and Cotton, among vegetables Rigan, Tomato and Val, Valpapadi are grown,
and horticulture activity is very less it includes Keri, Chikoo, Papaya and Banana.
Among Fishery Bombay duck constitutes the dominant fishery (13%) of the region.
Mangrove flora is dominated by Avicennia marina and Rhizophora mucronata. Healthy growth of mangroves has
been reported from the banks of Ban Khadi and Ghugar Khadi. Halophytes like Sueda maritima and Salichornia
brachyata are very common in the coastal area.
Marine biodiversity study shows that, buffer zone supports 16 nos. of phytoplankton and zooplankton genera.
11.2.11 Socio-Economic Environment
Social studies were carried out within the study area. Brief highlights are as follows:
Population and its distribution: There are 21 villages, with a total population of 40,501 persons and 9,432
households;
Sex Ratio: The total population of male is 22,944 and female population is 17,557;
Scheduled Caste & Scheduled tribe: SC population is 4.4 %, total ST population is 20.3% of the total
population.
Literacy rate: Average literacy rate is 74.35%;
Educational Facilities: Primary schools are available in all the villages; the highest educational facility available
is till Secondary school;
Medical facilities: Medical facilities are limited. Apart from Dahej most of the villages are devoid of the health
facilities. Primary Health Centre is present only in the Dahej village;
Drinking water: Well and tank facilities are sufficiently present in villages but the water requirement of the
village is not adequately supported because of it being saline unsuitable for the drinking purpose;
Household facility: Out of the 41 household survey done 18 were having Pucca houses, 7 Semi Pacca, 45
Kutcha where as 1 house was shanty;
Transportation Facility: The study area is well connected with road, the nearest railway station is Bharuch and
Dahej;
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 198
Power supply is available in all villages;
Economic Profile: Bulk of the population falls in the daily wage earner category working in as agricultural labour
or in the private companies as the contractual labour 6.8% of the population were having stationary, grocery,
tea stalls etc., 2.7% of the population were earning from the livestock being an industrial area most of the
people as contractual labor in GIDC.
11.3 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
11.3.1 Air Environment
Dispersion modeling (using “AERMOD” modelling software) was carried out for point and area sources only.
This indicates:
Maximum Incremental GLC’s for PM10, SO2 & NOx remain within 750 m from the project site;
Air impacts are not expected to cause any effect on vegetation and human settlements in the vicinity of the
project site.
Mitigation measures for air quality impacts are:
Adequate height of at least 65 m will be provided as per the statutory requirements;
Well-designed ESP having alteast 99.9 % efficiency will be provided to control PM emissions;
Limestone dosing in CFBC Boilers will be done to achieve sulphur reduction efficiency of atleast 95.8%;
Since the proposed technology is of CFBC, temperature will be controlled to prevent NOX generation;
Online sensors for SPM, SO2 & NOx will be provided with flue gas stacks which will be attached to CPCB & GPCB
servers;
Regular Work place monitoring will be done;
CAAQMS will be placed near admin building;
Adequate Bag filters will be installed in ash handling unit & coal yard;
Effective water spraying will be done on the access roads to control re-entrained dust during dry season (if
required);
Proper operating procedures will be followed during startup and shutdown;
Proper PPE like dust masks will be provided to workers and its use will be ensured.
11.3.2 Traffic
From the proposed project, ~100 trucks per day carrying coal, limestone, fly ash, etc. will be using the state
highway (SH-6) connecting Bharuch and Dahej, i.e. additional 22 PCU’s will be required. Based on the traffic survey
conducted on this road, it is noted:
Average peak hourly traffic on this route is 531 and 570 PCU respectively;
As per IRC, carrying capacity of this approach road is 3,600 PCU;
Thus, the maximum PCU on the road will be 553 (Bharuch to Dahej) and 592 (Dahej to Bharuch).
Thus, the road is capable of carrying the excess traffic due to the proposed expansion.
11.3.3 Noise Environment
Using “SoundPLAN” Modelling software, due to the proposed activities it is predicted that 0.2 dB will be
increased during the day and 0.3 dB during the night in Industrial & Residential area.
This increase is negligible considering that the minimum noticeable increase by a human ear is 0.5 dB hence it
can be concluded that due to noise generated from the proposed project there will not be any impact on the
surrounding area.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 199
11.3.4 Water Environment
Ground water is not abstracted for any plant activities since the water supply will be available on continuous and
uninterrupted basis from GIDC. The plant will be paved, therefore the likelihood of contaminants entering
groundwater and harming the same is improbable (i.e. unlikely).
The overall impact on surface water quality will be negligible by taking following precautionary measures:
Coal yard will be provided with proper bunds to avoid run-off contamination.
Maximum condensate will be recovered from the boiler to reduce the fresh water demand;
Rain water harvesting will be adopted for the conservation of water;
Regular maintenance of effluent treatment plant will be done to ensure smooth operation;
No discharge of untreated waste water on land;
Zero effluent discharge criteria for new power plant will be met. Rest of the effluent from other plants will be
treated in existing ETP and will be disposed to GIDC Drain after meeting the GPCB effluent discharge norms.
Separate drains for storm water and effluent will be provided for proposed expansion project to avoid any
contamination of surface water sources;
All chemical and fuel storage and handling areas will be provided with proper bunds & dyke walls to avoid run-
off contamination during rainy season.
11.3.5 Biological Environment
Since the proposed project is located within the existing factory premises there will be no significant or permanent
impact on the habitat structure of associated faunal diversity.
The existing unit already has well developed greenbelt consisting of 1,70,170 m2 (31.71%) against the 25% as per
the Existing EC (Condition No. XIII of Specific Condition of EC dated 09.08.2007). The existing greenbelt possess
~24,000 well developed trees consisting of 22 common species. Although additional 6,943 m2 (1.29%) of green
belt and additional 10,000 trees will be planted. Every year survival rate of the plantation within project site will be
monitored and accordingly greenbelt will be maintained.
As the emissions from the plant will be regulated and minimal with respect to the specified norms, and with a very
healthy existing developed greenbelt at the site in the form of several species, the biological environment will be
protected.
11.3.6 Land Environment
The land use pattern of the project site will not get affected since it is within factory premises. Mitigation measures
for conserving land use and land cover will include the following:
The vegetation cover clearing will only be done on which construction will take place;
Reuse of earth material generated during excavation will be done;
Optimization of land requirement through proper site lay out design will be done;
Fly ash will be given to cement manufacturer, brick manufacturing unit and for road construction;
Storage areas for hazardous waste, fuel & raw material will be impervious and will be designed to prevent
Leachate penetration;
Generated hazardous wastes during project operation will be transported to an authorized TSDF operator.
11.3.7 Socio-Economic Environment
While assessing the socio-economic and sociological impact including health impacts to surrounding population, the
upcoming project will bring job opportunities for the local people.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 200
Focused ESC activities & ESC Cost
The focused ESC activities are Educational activities, Health Care Services, Housing & Sanitation Waste, Water
facilities and recharge/ Harvesting, drinking water, Infrastructure facilities and Infrastructure Development. ESC
expenditure of ~ INR 11.50 Crore for initial 5 years is proposed.
11.4 ENVIRONMENTAL MONITORING PROGRAMME
Various environmental parameters to be monitored are tabulated in Table 11-12.
Table 11-12: Summary of Environment Monitoring Plan
S.
No.
Environmental Component /
Parameter
Frequency of
monitoring Location
1 PM10, PM2.5, SO2 & NOx in ambient air. Continuous (Online) Near Admin Building.
2 PM10, PM2.5, SO2 & NOx in ambient air. Monthly 3 Locations within site (Near ETP, Canteen &
Main Lab)
3 Noise levels Monthly Two locations (Plant area & Utilities area)
4 Flow (Quantity) Continuous (Online) GIDC Inlet & at Final disposal point into GIDC
Drain
5 pH & TOC Continuous (Online) Final disposal point into GIDC Drain
6 TDS, SS, COD & BOD Monthly ETP Outlet
7 DO, TDS, SS, COD Daily ETP Outlet
9 Quantity of Hazardous waste generated During Dispatch of Trucks
(Once/Twice in a month) Main Gate
10 Soil analysis for EC, pH, permeability
and ESP
Pre & post monsoon / in
the event of accidental
spillage
At Site
11.4.1 Environmental Monitoring, Management Cost
Environmental monitoring and management cost is estimated as total capital cost of ~INR 9.9 Crore and recurring
expenditure of ~ INR 1.4 Crore per annum.
11.5 ADDITIONAL STUDIES
11.5.1 Risk Assessment
During operation of the proposed power plant, following activities can pose hazards and risk to human and
surrounding environment:
Storage of Coal;
Contact with hazardous chemicals.
Maximum Credible Loss Scenarios were not considered due to the following reasons:
Proposed project is for expansion of 67 MW power plant, which only requires coal & limestone, which are non-
hazardous. All other hazardous chemicals handled at site were already considered in previous EIA studies;
Auxillary power will be sourced from existing power plant / grid. Thus, no DG sets are proposed for startup of
proposed unit;
On the basis of chemical properties like flash point, phase of chemical, operating conditions and total inventory
etc., it is noted that in the proposed power plant project, there are no such storage of flammable raw materials
which can lead to uncontrolled release of hazardous material causing hazard.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 11. SUMMARY & CONCLUSION
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 201
As a general practice, following mitigation measures will be taken to reduce the risk of workers and staff:
Mitigation Measures
Spill management plan to prevent risk of spill which may cause health problem;
Off-site & Onsite emergency plan will be followed to tackle any emergency situation for proposed facilities;
Medical checkup will be carried out at an regular intervals;
During site preparation appropriate PPEs will be provided to site workers and staff members;
During operations, appropriate PPEs like Safety Goggles, Hand gloves, Clothing etc. will be provided.
11.6 PROJECT BENEFITS
During the construction phase around ~250 local skilled and semi-skilled workers will be employed and Existing
manpower (~570) is sufficient to operate proposed expansion unit;
The positive impacts include enhanced indirect employment opportunities for transporters;
Other tangible benefits include development of various ancillary activities which shall generate indirect
employment to the locals.
11.7 ENVIRONMENT MANAGEMENT PLAN
An Environmental Management Cell with adequate professional expertise and resources is already in place to
discharge responsibilities related to environmental management including statutory compliance, pollution
prevention, environmental monitoring, etc.
EMP for suggested mitigation measures and monitoring plan will include:
Provision of SOPs and Emergency Response Procedures will be ensured;
Deploying experienced EHS head who will directly provide the status report to director on daily basis;
Proper inventory accounting & monthly review of non-compliances by plant head;
Monitoring for compliance of statutory conditions by EHS head;
Internal audit of hazardous waste storage area as per ISO system;
Timely submission of Form 5, Environment Audit Report, Hazardous waste manifest, Compliance of show cause
/ closure notice issued by regulatory authorities, etc.
Sufficient funds towards capital cost and recurring cost per annum will be provided and ensured that it is not
diverted for any other purpose.
11.8 CONCLUSION
The proposed power plant is required to cater to the captive power & steam requirement. The aim of the project is
to reduce dependency on the grid, thus reducing project and manufacturing costs. Based on the EIA study, the
following highlight emerges:
Land is available for setting up proposed plants within their existing premises;
No change in land use is envisaged;
Project has various locational benefits like availability of coal from nearby region;
Safety and environmental norms will be followed;
Recycle & Reuse scheme will be implemented to reduce water consumption;
Provision of air pollution control equipment, will lead to minimum adverse environmental impacts;
The project will generate employment for skilled, semiskilled, unskilled people during construction phase.
In view of this, the project may be considered for grant of Environmental Clearance.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 12. DISCLOSURE OF
CONSULTANTS
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 202
12 DISCLOSURE OF CONSULTANTS
MFL, has appointed Kadam Environmental Consultants (Kadam) for carrying out this Environmental Impact
Assessment Study as per the EIA notification, 2006 as amended till date.
Kadam is accredited EIA Consultant organization by NABET, Quality Council of India under EIA accreditation
scheme as per mandatory requirement of the MOEFCC, Govt. of India for carrying out Environmental Impact
Assessment studies.
Kadam Environmental Consultants have been accredited by NABET as an Accredited Consultant Organization since
25-05-2010 till date without a break.
The time period for all activities of this EIA study was fully covered with NABET Accreditation as witnessed by the
following two NABET certificates and an extension letter:
Accreditation Certificate valid from 04-10-2013 up to 18-09-2016;
Accreditation Extension Letter extending the validity up to 04-04-2017 w.r.t our application dated 15-09-2016;
Accreditation Certificate issued on 28-03-2017 and valid up to 26-05-2019.
Certificates and letter for accreditation from NABET is attached as Annexure 39. Kadam’s Laboratory is accredited
with NABL & recognized by MoEF&CC. Certificate & Recognition letters are provided in Annexure 40.
It has approved EIA coordinators and Field Area Experts for undertaking Environmental and related studies in
Twenty Six (26) approved sectors.
12.1 BRIEF RESUME AND NATURE OF CONSULTANCY (KADAM)
Kadam was established in 1981 and has more than 3 decades of varied experience in the field of environment. The
Group has branch offices at Delhi and other places in Gujarat. The mission of company is providing sustainable
solutions on “Environment for Development”.
The company has a dedicated and experienced team of more than 200 technical staff. The team comprise of
Environmental Planners and Engineers, Chemical and Civil Engineers, Geologist, Socio-Economic Experts,
Microbiologists, Zoologists, Botanists and Industrial / Analytical Chemists. The company’s strength lies in Project
Management, Performing Risk Assessment, Formulating Environmental Disaster Plans, Use of Satellite Imagery in
Impact Assessment, Use of Mathematical Models for Air, Noise and Water Assessment and Expertise in Public
Consultation.
Customer services are mainly categorized into:
Consultancy Services in the field of environmental impact assessment, environmental site assessment and
due diligence, Enviro legal services, statutory environmental audits / statements, risk assessments and HAZOP,
energy audit, environmental health and safety management systems and waste management systems;
Engineering Services for collection and conveyance of liquid and solid wastes, designing and executing
effluent and sewage treatment plants, municipal solid waste studies and solid waste management systems, bio
gas plants, rain water harvesting systems and deep sea marine disposal systems;
Laboratory services in chemical and waste testing, microbiology, soil testing and Field sampling (we have
amongst the highest number of environmental field sampling equipment amongst environmental companies in
the country). The company has a well-equipped laboratory with modern instruments and experienced staff
catering to the need of statutory and advisory environmental testing for air, water and wastewater and
hazardous solid waste.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 12. DISCLOSURE OF
CONSULTANTS
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 203
The group has a varied industrial clientele encompassing Indian and Multinational Companies covering the industrial
and services spectrum viz. Pesticides, Fertilizers, Bulk Drugs and Pharmaceuticals, Paints, Chemicals, Oil and Gas,
Real Estate, Hospitality and Infrastructure sectors.
Kadam has received ISO 9001:2008 certification for its Quality management System from BSI-MS. Kadam’s
laboratory is NABL accredited, MoEF&CC approved under EP Act and has OHSAS 18001:2007 accreditation.
12.2 EIA TEAM MEMBERS
Work presented in this report was carried out by KEC with active co-operation of MFL. The name of the EIA co-
ordinator and FAE’s deployed for the project is mentioned at the start of the report (in Quality Control Section). KEC
team Members (along with their role in the project) is given in Table 12-1.
Table 12-1: EIA Team Member
Name / Role Functional Area Involvement
Task Under Guidance
Mr. Bhavin Jambucha
(TM – EIAC & RH)
EIA team member
Documentation like preparing revised TOR
application (Form – 1, PFR etc.), drafting EIA &
EMP report from FAE reports. Kick-Off meeting
with all EIA team, participating in TOR
Amendment presentation, site visits and
involvement in client meetings for collecting
technical data.
Mr. Sangram Kadam
Risk Assessment &
Hazard Management
(RH)
Collection of secondary data, preparation of layout
plan showing storage areas and contribution to
EMP/RA/DMP Documentation
Mrs. Jitixa Upadhyay
Mr. K. Antani
(TM-SHW)
Water Pollution
Prevention, Control &
Prediction of Impacts
(WP)
Site visit, identification of sampling locations,
evaluation of results of water quality, water
balance preparation for the project, evaluation of
water pollution control management, identification
of impacts, suggestion and finalization of
mitigation measures for WP
Mrs. Kundan Ajudiya
Solid Waste and
Hazardous Waste
Management (SHW)
Site visit, Identification of waste generated from
the industry as per HW Rules and MSW Rules,
Studying existing management practices and
adequacy, Identification of Impact and mitigation
measures for management of hazardous waste
Mrs. Kundan Ajudiya
Ms. Tanu Prasad
(TM – AP & AQ)
Air Pollution
Prevention,
Monitoring & Control
(AP)
Checking air quality data, evaluation of results of
Ambient Air Quality Monitoring (AAQM) Mr. Bhavin Jambucha
Meteorology, Air
Quality Modelling &
Prediction
(AQ)
Running air quality model (AERMOD) and
prediction of GLCs based on results of Ambient Air
Quality Monitoring (AAQM), identification of
possible impacts on AQ
Mr. Bhavin Jambucha
Ms. Aarti Sharma Socio-Economic (SE)
Site Visit, Socio-Economic survey within study
area, collection of secondary data, assisting in
identification of Impacts and mitigation measures,
assisting in preparation of ESMP in FAE report and
contribution to EIA report
Mr. Anil Vishwakarma
Mr. Jayesh Gajjar
(Head – Draftsman) Drawings/Map
As head draftsman, involvement in preparation
and releasing final maps like Land Use, project
location, study area, baseline sampling location,
-
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 12. DISCLOSURE OF
CONSULTANTS
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 204
Name / Role Functional Area Involvement
Task Under Guidance
site layout map & green belt plan prepared by
subordinate draftsman
Mr. Chetan
(Draftsman) Drawings/Map
Preparation of various maps like Land Use, project
location, study area, baseline sampling location,
site layout map & green belt plan using AutoCAD
Mr. Jayesh Gajjar
Mr. Hasmukh (TM –
Lab) Field Monitoring
Collection of air, water, solid & hazardous waste
samples from sampling locations, monitoring noise
levels for baseline study. Conducting traffic survey
Mr. Sangram Kadam, Mr.
Sameer, Mr. Neeraj
Sharma
Mr. Satish Joshi Expert of Report
review Review of the EIA report for improving the quality. -
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF
PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 205
13 STATUS OF COMPLIANCE OF EXISTING EC CONDITIONS
MFL had applied to get Certified Monitoring Report & Certified Compliance Report for conditions as stipulated in
Previous Environmental Clearances as mentioned in Chapter 1, Section 1.4.1 from Regional Officer, MoEF&CC,
(West Zone), Bhopal.
Site visit was carried out by RO-MoEF&CC, Bhopal (West Zone) to verify conditions as stipulated in Previous
Environmental Clearances. Certified Monitoring & Compliance report was received from Regional Office (WCZ) of
MoEF&CC, Bhopal vide letter F.No:5-64/2012 (ENV)/141 on 23rd July, 2014. It is attached as Annexure 38.
Summary of the ton complied, partly complied, agreed to comply & complied conditions as observed by RO,
MoEF&CC, Bhopal is summarized in Table 13-1.
Table 13-1: Summary Not complied, Partly Complied, Agreed to Comply EC Conditions
S.
No. Environmental Clearance Details
EC Conditions
Total Complied Not
Complied
Partly
Complied
Agreed to
Comply
1 EC from MoEF&CC: J-11011/06/2007-IA.II(I)
dated 09.08.2007 23 14 1 5 3
2 EC from MoEF&CC: J-11011/06/2007-IA.II(I)
dated 09.08.2007 40 22 3 14 1
Based on the remarks made by RO – MoEF&CC, Bhopal, action plan for partially complied conditions are as
tabulated in Table 13-2 & Table 13-3.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 206
Table 13-2: Action Plan for Complying Not-Complied Conditions of Previous EC
S. N. Not Complied Condition Observation of RO – Bhopal Progress & Action Plan for complying the Condition
A EC: J-11011/6/2007-IA.II (I) dated 09.08.2007
1 General Condition: 11
The PA shall inform the RO as well as
Ministry, the date of financial closure and
final approval of the project by the
concerned authorities and the date of
start of the project.
The details of financial closure and final
approve of the project were not submitted.
Not Complied.
Progress : Complied
We regret to overlook the valid observation as pointed out by the authority.
But, it is to inform that no loan was taken from any Bank or Financial institutes for the
proposed expansion project. Investment was done in-house. Hence, details as asked is not
applicable.
B EC: J-11011/6/2007-IA.II (I) dated 09.08.2007
1 General Condition 3
The company shall harvest rainwater from
the roof-tops of the buildings and storm
water drains to recharge the ground
water and use the same water for the
process activities of the project to
conserve fresh water.
PA has assured that appropriate actions for
developing rain water harvesting structures
shall be undertaken for recharging of
ground water. PA was directed to prepare a
plan and submit the same within six months
as the similar condition was stipulated in
earlier EC of 2007.
Not Complied.
Progress: Being Complied
Subsequent to the visit of MoEF, the matter was discussed with GPCB officials of Bharuch.
GPCB orally advised that rainwater collected from the industrial area is not advisable for
ground water recharge.
However, factoring into the likely contamination aspect, we have decided to provide separate
storm water line to collect rainwater from roof tops, roads & open area and transfer it to raw
water reservoir after necessary treatment.
We have also decided that sample of the collected rainwater will be given in Laboratory for
pH and chloride analysis. If found usable, it will be transferred through sand filters in process
water tank. Otherwise we will send it to ETP for further treatment.
Detailed calculations for collection of rain water is provided in Chapter 10, Section 10.3.3.
Action plan for developing rainwater harvesting system at site is as follows:
S.
N. Action Plan Period
Amount spent in
Lakhs Status
1
Hiring of expert / consulting
services for developing RHW
structures. This will include upgrade
April,
18 10 Ongoing
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 207
S. N. Not Complied Condition Observation of RO – Bhopal Progress & Action Plan for complying the Condition
conveyance system of roof top to
rain water reservoir.
3
Installation of PVC Pipeline from
rooftop of offices within site, i.e.
admin building & OHS office.
Dec, 18
to Feb,
19
20 Ongoing
4
Storm water drains for transferring
rainwater from rooftop to RHW
pond.
Jan. 19
to May
19
20 Ongoing
Total Amount 50
Please refer Map 2-4 for layout plan of the tentative scheme of storm water line.
2 General Condition: 6
The company shall undertake eco-
developmental measures including
community welfare measures in the
project area for the overall improvement
of the environment.
No efforts have been made to implement
eco developmental measures.
Not Complied.
Progress: Being Complied.
Action Plan for undertaking eco-developmental measures for the nearby community is shown
below:
S. N. Action Plan Period Estimated
Amount
1 Plantation of Neem, Pipal & Badam trees
(total 150 saplings) in Jolva, Galenda & Dahej. July, 18 30,000/-
2 Upgrading 50 toilets in nearby villages as a
part of Swatch Bharat Abhiyan.
June 18 to
March 19 35,00,000/-
3 Replacing old streetlights with solar
streetlights for three Villages.
Jan 18 to
May 18 1,00,000/-
Total Amount 36,30,000/-
In view of the above action plan, we assure you that we will undertake the above mentioned
eco-developmental measures including community welfare measures in the project area for
the overall improvement of the environment by Dec, 2019. In addition to that, we will
continue such activities even in future.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 208
S. N. Not Complied Condition Observation of RO – Bhopal Progress & Action Plan for complying the Condition
3 General Condition: 7
A copy of the clearance letter shall be
sent by the project proponent to
concerned Panchayat, Zila
Parisad/Municipal Corporation. Urban local
Body and the local NGO if any, from who
suggestions / representations, if any,
were received while processing the
proposal.
Observation of RO– Bhopal
PA has not submitted any documentary
evidence in support of implementation of
the condition.
Not Complied.
Progress : Complied
We regret the non-circulation of the EC copy as rightly remarked by the authority. We have
now provided EC copy to Gram Panchayat office of Jolva, Galenda & Dahej.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 209
Table 13-3: Action Plan for Complying Partially-Complied Conditions of Previous EC
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
A EC: J-11011/6/2007-IA.II (I) dated 09.08.2007
1 Specific Condition: 11
At least 25% of the total area shall be
developed as green belt as per the CPCB
guidelines.
PA has intimated that about 22 ha of land have been
brought under green belt. It was observed that few
thousand saplings have been grown as plantation. The
survival rate was observed around 60% to 70%.
However, details on expenditure, density/ha etc. were
not submitted.
Partly Complied.
Progress : Being Complied
Total 42,050 trees like Subabul, Neem, coconut tree, neelgiri, Saptaparni ,
Badam tree, banyans tree, foxtelpalm tree and pento etc. are planted.
Density of the tree plantation is ~ 1,910/Ha.
2 General Condition: 1
The unit shall implement all pollution control
measures as provided in the EIA/EMP report
and recommendation made in risk
assessment report. Disaster management
plan shall be prepared and implemented.
It was submitted and observed during the visit that
adequate pollution control system namely ESP,
scrubbers, ETP etc. have been provided as per EIA/EMP
report. Onsite Emergency Plan has been prepared as per
‘The Major Accident Hazard Control Rules, 1977’. The
implementation of recommendations of DMP & RA was in
progress as claimed. It was observed that assembly
points have been identified; wind socks were placed at
appropriate level. The monitoring of stack & process
emissions, AAQ at three locations & treated effluent has
been carried out on monthly basis but noise level and
VOCs were not monitored as per reports submitted. PA
was directed to monitor noise level and VOCs as per the
condition.
Partly Complied.
Progress : Complied
The implementation of recommendations of DMP & RA is already carried
out. Noise & VOC are being monitored at 3 locations within the plant
premises. Results of the same are as follows:
1) Noise Results:
During Day Time:
S. N. Locations Day Reading in db
Min Max Average
1 Power Plant 74.8 75.1 74.95
2 Admin Area 62.3 65.1 63.7
3 Main gate 58.1 55.2 56.65
4 ETP Plant 68.5 67.4 67.95
During Night time:
S. N. Locations Night Reading in db
Min Max Average
1 Power Plant 69.9 70.1 70.0
2 Admin Area 55.4 53.3 54.35
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 210
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
3 Main gate 53.7 50.1 51.9
4 ETP Plant 64.3 62.1 63.2
2) VOC Results
As such no volatile compounds are being currently used. Still VOCs
are monitored regularly and results are shown below:
S. N.
Locations
Results (permissible limit) & unit in µg/m3
Type PM10
(100)
PM2.5
(60)
SO2
(80)
NOx
(80) VOC (--)
1 Power Plant
Min 69.57 33.24 26.87 20.44 ND
Max 78.54 38.96 32.78 25.8 ND
Avg. 74.0 36.1 29.8 23.12 -
2 Admin Area
Min 50.26 26.7 14.31 15.38 ND
Max 52.5 28.1 15.2 16.12 ND
Avg. 46.9 30.5 13.05 19.12 -
3 Main gate
Min 45.35 28.9 10.8 18.45 ND
Max 48.5 32.1 15.3 19.8 ND
Avg. 51.3 27.4 14.7 15.7 -
4 ETP Plant
Min 29.31 13.52 15.18 19.33 ND
Max 30.45 16.45 15.9 22.2 ND
Avg. 29.8 14.9 15.5 20.7 -
3 General Condition: 8
The company shall undertake social
welfare/community development measures in
the surrounding villages such as health care,
education and drinking water supply facilities.
PA has claimed that CSR activities have been undertaken
for the surrounding villages but details were not
submitted.
Partly Complied.
Progress: Complied.
Breakup of the same is as tabulated below:
S. N.
Year CSR Cost
Spent (Lac) Remarks
1 2008-09 97.29 For Hospital,
education, nearby villages, mentally
disable people etc.
2 2009-10 35.02
3 2010-11 35.0
4 2011-12 60.07
5 2012-13 28.5
Total Amount
255.88
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 211
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
4 General Condition: 9
The implementation of the project vis~a~vis
environmental action plans shall be monitored
by the concerned RO office of
MOEF/SPCB/CPCB. A six monthly compliance
status report shall be submitted to monitoring
agencies and uploaded on the website of the
company.
Regional office of the Ministry has monitored the project.
Six monthly compliance status report were submitted.
The website of the company was scanned for uploading
of the report and the copy of the EC but in vain.
Partly Complied.
Progress :Complied
We are constantly updating the website with uploading the latest six
monthly compliance report along with previous EC copies. The same can be
viewed at http://www.meghmani.com/Environment.html
5 General Condition: 10
The PP shall inform the public that the project
has been accorded EC by Ministry and copies
of the clearance letter are available with the
SPCB/Committee and may also be seen at the
website of the Ministry at http://envfor.nic.in.
This shall be advertised within seven days
from the date of issue of the clearance letter,
at least in the two local newspapers that are
widely circulated in the region of which one
shall be in the vernacular language of the
locality and the copy of the same can be
forwarded to concerned RO of the Ministry.
The grant of EC was published in the newspapers as per
the condition and copies have been submitted. But,
clause of seven days was not followed.
Partly Complied.
Progress: Was not complied
EC was not received within the seven days of the date of issue. Once EC
was received, advertisement of the same was published.
B EC: J-11011/259/2011-IA.II (I) dated 12.09.2012
1 Specific Condition: 1
All the specific conditions and general
conditions specified in the EC letters accorded
vide Ministry’s letter No. J-11011/6/2007.
IA.II (I) dated 9th August 2007 shall be
implemented.
The status of compliance of conditions stipulated in the
EC vide Ministry’s letter No. J-11011/6/2007. IA.II (I)
dated 9th August 2007 have been mentioned above. It
can be seen that major conditions have been complied &
few needs sincere attention.
Progress: Being complied
Status of current status and action plan for previous EC Conditions is already
mentioned above.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 212
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
Partly Complied.
2 Specific Condition: 5
Two stage water followed by alkali scrubber
shall be provided to process vent to control
HCl & Cl2 emissions. The scrubber water
should be sent to ETP for further treatment.
Efficiency of scrubber shall be monitored
regularly and maintained properly. Scrubber
vent shall be provided with online detection
and alarm system to indicate higher than
permissible value of controlled parameters. At
no time, the emission levels shall go beyond
the prescribed standards. The system should
be interlocked with the pollution control
equipment. So that in case of any increase in
pollutants beyond permissible limits, plant
should be automatically stopped. Stack
monitoring shall be done regularly and report
shall be sent to GPCB and the Ministry’s RO at
Bhopal.
Two stage water scrubbers have been provided to
process vent. It was observed from the reports that
parameters are within the limits. However, online
monitor was not provided to the scrubber vent as per the
condition. PA has claimed that APC systems have been
working efficiently which is evident from the analytical
reports submitted. Further, it was assured that in the
event of the failure of pollution control system(s), the
unit shall not be restarted until the control measures are
rectified to achieve the desired efficiency.
Partly Complied.
Progress: Complied
Online monitor is provided to the scrubber vent. Photograph showing the
results of the same are already shown in Annexure 23.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 213
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
3 Specific Condition: 7
In plant control measures for checking
fugitive emissions from all the vulnerable
sources shall be provided. Fugitive emissions
shall be controlled by provided closed
storage, closed handling and conveyance of
chemicals/materials, multi cyclone separator
and water sprinkling system. Dust
suppression system including water sprinkling
system shall be provided at loading and
unloading areas to control dust emissions.
Fugitive emissions in the work zone
environment, product, raw materials storage
area etc shall be regularly monitored and
records maintained. The emissions shall
conform to the limits stipulated by the GPCB.
It was observed during the visit that fugitive emissions
were controlled by implementing measures like covered
storage, closed handling & conveyance of
chemicals/materials, multi cyclone separator and water
sprinkling system etc. preventive maintenance schedule
has also been drawn. Dust suppression system including
water sprinkling system was provided at loading &
unloading areas to control dust emissions as observed
during the visit. Fugitive emission in the work zone
environment, product, raw materials storage area etc.
was regularly monitored as claimed but records were not
submitted. PA was directed to submit fugitive monitoring
reports along with the next compliance status.
Partly Complied.
Progress: Complied
Fugitive monitoring reports were regularly provided in all the compliance
reports. Recent results as below:
S. N.
Locations
Results (permissible limit) & unit in µg/m3
Type PM10
(100)
PM2.5
(60)
SO2
(80)
NOx
(80) VOC (--)
1 Power Plant
Min 69.57 33.24 26.87 20.44 ND
Max 78.54 38.96 32.78 25.8 ND
Avg. 74.0 36.1 29.8 23.12 -
2 Admin Area
Min 50.26 26.7 14.31 15.38 ND
Max 52.5 28.1 15.2 16.12 ND
Avg. 46.9 30.5 13.05 19.12 -
3 Main gate
Min 45.35 28.9 10.8 18.45 ND
Max 48.5 32.1 15.3 19.8 ND
Avg. 51.3 27.4 14.7 15.7 -
4 ETP Plant
Min 29.31 13.52 15.18 19.33 ND
Max 30.45 16.45 15.9 22.2 ND
Avg. 29.8 14.9 15.5 20.7 -
4 Specific Condition: 9
A proper LDAR program for pesticide industry
shall be prepared and implemented as per
CPCB guidelines. Focus shall be given for
prevention of fugitive emissions for which
preventive maintenance of pumps, valves,
pipelines are required. Proper maintenance of
mechanical seals of pumps and valves shall
be given. A preventive maintenance schedule
for each unit shall be prepared and adhered
to.
PA has argued that proper Leak Detection & Repair
(LDAR) program shall be adopted as and when pesticides
are manufactured. Presently, leak detection system has
been developed by means of regular maintenance &
monitoring of all equipment, pumps, pipelines as
observed and learn during the visit.
Partly Complied.
Progress: Will be Complied
As on date, no pesticides are being manufactured. As and when these units
will be installed LDAR system will be adopted.
5 Specific Condition: 10 Progress: Will be Complied
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 214
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
Continuous monitoring system for VOCs, Cl2
and HCl shall be installed at all important
places/area. Effective measures shall be
taken immediately, when monitoring results
indicate above the permissible limits. All
necessary steps shall be taken for monitoring
the chlorine and HCl as well as VOCs in the
proposed plants.
It was observed that continuous monitoring system for
Cl2 and HCl was placed in terms of installation of sensors
at all important places. It was intimated during visit that
presently volatile compounds were not used in existing
manufacturing process and monitoring of VOCs has not
been taken up.
Partly Complied.
As on date, volatile compounds were not used in existing manufacturing
process and monitoring of VOCs will be taken up once such compounds will
be handled at site.
6 Specific Condition: 19
Treated effluent shall be passed through
guard pond. Online continuous pH meter,
TOC analyzer and flow meter shall be
installed to monitor the treated water quality.
Treated waste water has been passed through guard
pond before its discharge. Online continuous pH meter
and flow meter were installed to monitor the treated
water quality as observed. TOC analyzer is yet to be
installed.
Partly Complied.
Progress: Will be Complied
We are manufacturing inorganic chemicals and do not use any kind of
organic solvents, so there is no generation of VOC. Thus, TOC meter is not
required as on date. As and when, the organic units will be established, TOC
meter will be provided.
7 Specific Condition: 24
A copy of agreement with cement plants for
disposal of fly ash shall be submitted to
Ministry’s RO within 1 month from date of
issue of letter.
Although PA has submitted that ash is being sold to
cement manufacturer but copy of agreement with
cement plants for disposal of fly ash has not been
submitted.
Partly Complied.
Progress: Complied
Copy of the agreement with cement plant for disposal of fly ash is shown in
Annexure 25.
8 Specific Condition: 26
Proper utilization of fly ash shall be ensured
as per Fly Ash Notification 1999 as amended
in 2003. Fly ash shall be provided to cement
and brick manufacturers for further
utilization.
Fly ash was sold to cement and brick manufacturers for
further utilization as submitted. Copy of agreement with
cement plants for disposal of fly ash has not been
submitted.
Progress: Complied
Same as mentioned above.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 215
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
Partly Complied.
9 Specific Condition: 27
The company shall undertaking following
waste minimization measures:
a. Metering and control of quantities of active
ingredients to minimize waste.
b. Reuse of by-products from the process as
raw materials or as raw material substitutes
in other processes.
c. Use of automated filling to minimize
spillage.
d. Use of close feed system into batch
reactors.
e. Venting equipment through vapor recovery
system.
f. Use of high pressure hoses for equipment
cleaning to reduce waste water generation.
It was observed that following measures have been
taken:
a. Provided closed handling system for handling of
chemicals.
b. –
c. & d. All acids/chemicals were transferred from storage
tanks to reactions through closed pipelines. Storage
tanks have been provided vents through trap receiver.
e. –
f. PA has assured that possibilities for reduction of water
consumption, raw material consumption & utilization of
byproducts shall be explored for implementation.
However, it was observed from Environmental Audit
Report 2013 that water consumption & generation of
effluent has been increased 9.62% and 31.68%
respectively as compared to EA report 2012.
Partly Complied.
Progress: Complied
Increase of raw water consumption and generation of effluent is due to
the construction work of 20 MW power plant for which EC was received
dated 12th September, 2012. Now, the water consumption & effluent
generation is meeting the quantities as stipulated in latest valid CC&A.
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 216
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
10 Specific Condition: 29
Green belt shall be developed at least 33% of
the plant area in and around the plant
premises to mitigate the effects of fugitive
emissions all around the plant as per the
CPCB guidelines in consultation with DFO.
Thick greenbelt with suitable plant species
shall be developed around the proposed
pesticide unit to mitigate the odor problem.
Selection of plant species shall be as per
CPCB guidelines.
PA has intimated that about 22 Ha of land have been
brought under greenbelt. It was observed that few
thousand saplings have been grown as plantation. The
survival rate was observed around 60% to 70%.
However, details on expenditure, density/ha etc. were
not submitted.
Partly Complied.
Progress : Being Complied
Total 42,050 trees like Subabul, Neem, coconut tree, neelgiri, Saptaparni ,
Badam tree, banyans tree, foxtelpalm tree and pentoetc. are planted.
Density of the tree plantation is ~ 1,910/Ha.
11 Specific Condition: 30
The company shall make the arrangement for
protection of possible fire & explosion hazards
during manufacturing process in material
handling.
Same as above specific condition no. 29.
Progress : Being Complied
12 General Condition: 1
The PA shall strictly adhere to the stipulations
made by the GPCB
Partly Complied.
It was observed that PA has obtained CC&A from GPCB
which is valid upto 30.04.2014. The production,
consumption of water and generation of wastewater and
hazardous waste was found within the limits as per the
details submitted. The monitoring of stack & process
emissions, AAQ at three locations and treated effluent
has been carried out on monthly basis but noise level
and VOCs were not monitored as per reports submitted.
PA was directed to monitor noise level & VOCs and install
TOC meter.
Progress: Will be Complied
We are manufacturing inorganic chemicals and do not use any kind of
organic solvents, so there is no generation of VOC. Thus, TOC meter is not
required as on date. As and when, the organic units will be established, TOC
meter will be provided.
13 General Condition: 5
The company shall also comply with all the
Partly Complied.
Although PA has claimed that a separate EMC has been
Progress : Complied
EMC has been constituted which is headed by General Manager of the plant,
M/S. MEGHMANI FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65 MW TO 132 MW AT GIDC DAHEJ,
BHARUCH, GUJARAT 13. STATUS OF COMPLIANCE OF PREVIOUS EC
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 217
S. N. Partially Complied Condition Observation of RO – Bhopal Progress &Action Plan for complying the Condition
environmental protection measures and
safeguards proposed in the project report
submitted to the Ministry. All the
recommendations made in the EIA/EMP in
respect of environment management, risk
mitigation measures and public hearing
relating to the project shall be implemented.
constituted which is headed by General Manager of the
plant, the process personnel were assigned additional
responsibilities of implementation of environmental
safeguards as observed during the visit. Full-fledged
laboratory has been setup with adequate infrastructure
and equipment within factory premises.
whose one of the responsibility is of implementation of environmental
safeguards.
14 General Condition: 9
The above conditions will be enforced, inter-
alia under the provision of the water
(Prevention & Control of Pollution) Act, 1974,
Air (Prevention & Control of Water Pollution)
Act, 1986 Hazardous Waste (Management,
Handling and Trans-boundary Movement)
Rules 2008 and the PLI, 1991 along with their
amendments and rules.
Partly Complied.
It was observed that PA has obtained CC&A from GPCB
which is valid up to 30.04.2014. The production,
consumption of water & generation of waste water &
Hazardous waste was found within the limits as per the
details submitted. It was also observed during the visit
that adequate pollution control systems have been
provided. Onsite Emergency Plan has been prepared.
The implementation of recommendations of DMP and RA
was in progress. Assembly points have been identified
but escape route was not demarcated on the ground for
which PA was directed to do so. Noise level and VOCs
were not monitored and PA was directed to monitor
noise level and VOCs and install TOC as per the
condition. Copy of the PLC has been submitted.
Progress : Complied
Escape route has been demarcated on the ground.
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 218
ANNEXURES
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 219
Annexure 1: IMS Certifications
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 220
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 221
Annexure 2: Integrated Management System Policy – MFL
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 222
Annexure 3: Land Possession & Transfer Letters
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 223
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 224
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 225
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 226
Annexure 4: Application for ToR to SEAC, Gandhinagar
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 227
Annexure 5: Terms of Reference (ToR) from SEAC, Gujarat received on 30.11.2017
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 228
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 229
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 230
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 231
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 232
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 233
Annexure 6: Copy of EC received on 9th August, 2007
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 234
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 235
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 236
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 237
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 238
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 239
Annexure 7: Copy of Transfer EC dated 9th September, 2008
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 240
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 241
Annexure 8: Copy of EC Received on 12th September, 2012
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 242
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 243
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 244
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 245
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 246
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 247
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 248
Annexure 9: Copy of CCA dated 25.07.2014
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 249
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 250
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 251
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 252
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 253
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 254
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 255
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 256
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 257
Annexure 10: Copy of Amended CCA dated 17.04.2015
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 258
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 259
Annexure 11: Copy of Amended CCA dated 24.06.2016
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 260
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 261
Annexure 12: Copy of NOC for Hydrogen Peroxide dated 01.05.2017
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 262
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 263
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 264
Annexure 13: Copy of NOC for Name Change dated 23.01.2008
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 265
Annexure 14: GIDC Letter for Plot Transfer
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 266
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 267
Annexure 15: Show Cause / Closure Notice and Response from MFL to GPCB
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 268
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 269
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 270
M/S. MEGHMANI
FINECHEM LTD. DRAFT EIA & EMP REPORT FOR EXPANSION IN POWER PLANT CAPACITY FROM 65
MW TO 132 MW AT GIDC DAHEJ, BHARUCH, GUJARAT ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | JANUARY, 2018 271