CMLC• Created in 2007 to implement the Rivers District Revitalization Plan –
489 acres; East Village represents 49 acres
• Rivers District Revitalization plan is an infrastructure improvementprogram
• 20 year master plan to revitalize East Village
East Village
• In February 2016 the City of Calgary as CMLC’s sole Shareholder expanded company mandate;
• Previously, CMLC was focused on completing work and projects within the Rivers District; were limited by CRL financial parameters;
• New mandate: CMLC, created and owned by the City of Calgary, exists to achieve the City's objectives for urban densification and community renewal, infrastructure investment and placemaking
Preparing for the Decade Ahead
Preparing for the Decade Ahead
• In 2017 CMLC entered the final 10 year term (indeed, the half way mark) of CRL capture,infrastructure investment and development within EV and the Rivers District;
• To prepare the corporation for its final decade of work, we initiated a multi-phased strategic planning process to examine our progress against the EV Master Plan vision and Rivers District Revitalization Plan
EV Master Plan Vision• 11,500 people; 3900 residential units
• Master planned community; across 15 city blocks
• Heavy pedestrian focus: bridges, mews, dedicated streets
• Mid and High rise
• Amenity rich and mixed-use designated
Master Plan math – 6.8 million• Residential 4,300,000 sq. ft | 63%
• Office 650,000 sq. ft. | 10%
• Live/Work 570,000 sq. ft. | 8%
• Hotel 340,000 sq. ft. | 5%
• Retail + F&B 285,000 sq. ft. | 4%
• Leisure & Community 353,000 sq. ft.| 6%
• Parking 230,000 sq. ft. | 3%
• Flexible Frontage 81,000 sq. ft. | 1%
Where we are so far…
• 10 years into our 20 year plan
• CMLC has invested $357 million into the redevelopment of East Village
Where we are so far…
• Since 2007, CMLC has attracted over $2.7 Billion in private sector investment
Where we are so far…
• Over 800 new homes have been completed in East Village between 4 residential towers
Infrastructure
• Investment into streetscapes development and critical connections in order to facilitate the master plan vision and accommodate growth in the community
Public Space Development
• Completion of public spaces like RiverWalk, St. Patrick’s Island and smaller urban parks have been instrumental in the delivery of our placemaking efforts
Retail Development
• CMLC has stewarded the development of the retail strategy for East Village
• Urban and Village format retail is now unfolding in East Village
Coming soon…
• There are 7 active constructions sites in East Village; Boutique Hotel, RioCan urban format grocery store, market and rental residential buildings, and New Central Library
Current Active Projects: New Central Library
Project highlights for the next 12 months:
• Building is weather tight
• Final phase of construction
• Interior fit n’ finish of the building now underway
• Public Ream and streetscaping program to provide interface between East Village,
the New Central Library and the downtown core
• Project to be delivered over multiple phases and years
Current Active Projects: 3rd Street SE
Current Active Projects: 9 Avenue Parkade
• Design team of Kasian Architecture (Calgary) with 5468796 Architecture (Winnipeg).
• The parkade, which will serve visitors to the New Central Library, National Music Centre and
other East Village, Victoria Park and downtown destinations; approximately 500 stalls.
• East Village Experience Centre (EVEC) continues to be the main interface with potential buyers, perspective developers, retailers and the public; educates on progress and vision of community
• Co-operative marketing campaigns funded by EV developers allows CMLC to continue sharing and expanding the East Village story
• Continue to engage with residents to foster sense of community and steward community identity
Community Engagement
Programming and Events
• CMLC will continue to develop and deliver compelling programs and events to immerse Calgarians in the East Village lifestyle and real estate story
• Anticipating 100,000 visitors to East Village & St. Patrick’s island each year 2017-2019- East Village Junction- Beat Beethoven - Joint New Central Library/National Music Centre programs
Victoria Park
Rivers District Master Plan
• We honed our placemaking expertise in East Village and are now preparing to take on the balance of the Rivers District
• In February 2017 CMLC kick-started the creation of the Rivers District Master Plan• The focus of the master plan will determine the investment of $150 million towards Victoria
Park and the Stampede Ground representing the balance of the Rivers District
Public Engagement
• In 2018 CMLC will engage the Calgary community to inform what amenities and infrastructure projects are most important
Future Projects
• 17th Avenue Extension
• Greenline Interface
• Stampede Trail
• RiverWalk, Stage 2
Thank You