EGLINTON CROSSTOWN Cedarvale-Forest Hill Construction Liaison Committee February 28, 2018
2
Agenda
• Cedarvale Station Update • Forest Hill Station Update
3
Cedarvale Station Updates
Ongoing • Shoring and traffic deck installation on the south side of Eglinton • Backfill of crossover section
Upcoming • Water main relocation on Eglinton Avenue West at Allen Road North • Water main relocation on Marlee Avenue and laneway north of Eglinton
Avenue between Marlee and Fairleigh – 8-10 weeks; 5-6 weeks occupying a lane on Marlee
• Allen Road South utility relocation – New sewer main – Confirmed weekend closure (midnight Friday – 5am Monday) of the Allen for March 17/18
• Stage 2 shoring on the north side of Eglinton Ave – South Allen Road realignment – Planning a weekend closure (midnight Friday – 5am Monday) of the Allen planned for March
24/25, April 7/8, or April 14/15
4
Cedarvale Station Shoring Stage 2 – 2018
5
Marlee Water Main Works
6
Construction Progress Picture Final pour at east
entrance
7
Construction Progress Picture
Shoring at Everden Road
8
Construction Progress Picture
Backfill at the crossover
Forest Hill Construction Updates
Forest Hill Station Update
ACTIVITY LOCATION APPROXIMATE DURATION
WINTER & SPRING 2018
Support of Excavation – SW Station Box Eglinton Ave W, west of Bathurst St Ongoing through June 2018
Support of Excavation – SE Station Box Eglinton Ave W, east of Bathurst St Ongoing through fall 2018
Wet Utilities Relocation Bathurst St and Eglinton Ave W Ongoing through 2018
Support of Excavation – Main Entrance Northwest corner of Bathurst St and Eglinton Ave W Week of Feb 5 through May 2018
Roof Slab Pour – SW Station Box
Eglinton Ave W, west of Bathurst St Southbound curb lane on Bathurst St, south of Eglinton Ave W
March 3, 2018
Traffic Change – Temporary Bridge Works See map March 8, 2018 (overnight)
Traffic Change – Support of Excavation See map Late April 2018
Road Reinstatement Works – SW Station Box: Eglinton Ave W, west of Bathurst St April through June 2018
Roof Slab Pour – March 3
• Saturday March 3, 2018
beginning at 7:00 a.m.
• Southbound curb lane
south of Eglinton Ave W will
be occupied for concrete
truck staging
• Concrete trucks will exit site
from Peveril Hill
TRUCK EGRESS
Current Construction Staging
Week of February 5 to March 8, 2018
Upcoming Traffic Staging March 8, 2018 through Late April 2018 Activities: Support of Excavation, Temporary Bridge Works & Wet Utilities
Upcoming Traffic Staging Late April 2018 to June 2018 Activities: Support of Excavation, Road Reinstatement & Wet Utilities
15
Forest Hill Station Construction Progress
15
SOUTHWEST STATION BOX AREA
16
Forest Hill Station Construction Progress
16
MAIN ENTRANCE PILING
17
Forest Hill Station Construction Progress
17
SHORING BOX FOR WET UTILITIES
18
Forest Hill Station Construction Progress
SHORING BOX FOR WET UTILITIES
19
Forest Hill Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
20
Local Area Map