Upload
avtsdpm
View
214
Download
0
Embed Size (px)
Citation preview
8/17/2019 ELDS-DR-S-02005_01e (020812)
1/59
ELDFISK II 2/7 S JACKET AND BRIDGE SUPPORT
01e 01/08/2012 Issued for Review KK ET LL JGC
01d 23/05/2012 Issued for Construction JI JR ME JGC
01c 25/01/2012 Accepted for Construction JI JR ME JGC
01b 27/07/2011 Issued for Review JI JR AS JGC
01a 24/06/2011 Issued for Review JI JR AS JGC
Rev. Issued
date
Description Made
by
Chk'd
by
Disc.
appr.
Proj.
appr.
Client
appr.
Contractor:
01-65-50-205
Client: Contract No.:
NSBU-085339
Project no:
ELDS
Project title:
ELDFISK II 2/7S JACKET AND BRIDGE SUPPORT
Document sub-
type:
TA
Platform(s):
ELDS
Area(s):
J01
System(s):
850
DFO code:
A2.01a
Tag(s):
N/A
Document title:
SPECIFICATION FOR JACKET UPEND CONTROL SYSTEM
Document no.: Rev.:Page:
ELDS-DR-S-02005 01e 1 of 59
8/17/2019 ELDS-DR-S-02005_01e (020812)
2/59
SPECIFICATION FOR JACKET UPEND CONTROL SYSTEM
2 ELDS-DR-S-02005 Rev. 01e
NSBU- 085339
This page intentionally left blank
8/17/2019 ELDS-DR-S-02005_01e (020812)
3/59
SPECIFICATION FOR JACKET UPEND CONTROL SYSTEM
3 ELDS-DR-S-02005 Rev. 01e
NSBU- 085339
REVISION CHANGE NOTICES
Rev. Location of Change Brief Descrip tion of Change
HOLD LIST
Location of Hold Brief Descrip tion of Hold
8/17/2019 ELDS-DR-S-02005_01e (020812)
4/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 2 of 57Date: 24
th July 2012
CONTENTS
1.0 ABBREVIATIONS AND HOLDS ..................................................................................................................... 6
1.1 ABBREVIATIONS 6 1.2 HOLDS 7 1.3 CHANGES SINCE L AST REVISION 7
2.0 INTRODUCTION .............................................................................................................................................. 8
2.1 PURPOSE & SCOPE OF THIS DOCUMENT 8 2.2
ELDFISK II FIELD DEVELOPMENT 8 2.3 DEFINITIONS 9 2.4
CODES AND STANDARDS 10 2.4.1
General ................................................................................................................................................................ 10
2.4.2
Order of Precedence ........................................................................................................................................... 10
2.4.3
Company Specifications ..................................................................................................................................... 10
2.4.4 Project Specifications ......................................................................................................................................... 10 2.4.5 International Codes and Standards ..................................................................................................................... 11
3.0
SCOPE OF WORK ......................................................................................................................................... 12
3.1 INTRODUCTION 12
3.2
NOMINATED SUB-SUPPLIERS 15
4.0 BASIC DESIGN INFORMATION ................................................................................................................... 16
4.1 DESIGN LIFE 16 4.2 ENVIRONMENTAL/INSTALLATION D ATA 16
5.0 2/7S JACKET TECHNICAL REQUIREMENTS ............................................................................................ 17
5.1
GENERAL 17 5.2
J ACKET CONFIGURATION 18 5.3 FLOODING SYSTEM 19
5.3.1
Operating Requirements ..................................................................................................................................... 19
5.3.2
Jacket Legs and Flotation Tanks ........................................................................................................................ 19
5.4 VENTING SYSTEM 19
5.4.1
Jacket Legs and Flotation Tanks ........................................................................................................................ 19 5.5 FLOTATION T ANK RECOVERY 20
5.5.1 Release from Jacket ............................................................................................................................................ 20 5.5.2
Draining and Securing ........................................................................................................................................ 20
5.6 J ACKET LEGS AND FLOTATION T ANKS – STATUS MONITORING SYSTEM 20 5.6.1
Status Monitoring Display ................................................................................................................................. 21
5.6.2 Jacket Legs & Flotation Tanks Flood / Vent Valve Status ............................................................................... 21 5.6.3
Jacket Leg Ballast Compartment Content ......................................................................................................... 21
5.6.4 Flotation Tank Compartment Pressure Monitoring ........................................................................................... 21 5.6.5
Jacket Depth Measurement ................................................................................................................................ 22
5.6.6 Seabed Clearance................................................................................................................................................ 22
5.7 DECK CONTROL CENTRE (DCC) 22 5.8 UMBILICAL INTERFACE P ANELS (UIP) 22
5.9
UMBILICAL 23 5.9.1 Primary Electro-Hydraulic Umbilical ................................................................................................................ 23
5.9.2 Back-up Hydraulic Umbilical ............................................................................................................................ 23 5.9.3 Primary Electrical Umbilical .............................................................................................................................. 23 5.9.4
Back-up Electrical Umbilical ............................................................................................................................. 23
5.10 TUBING/TUBE FITTINGS AND TUBE BUNDLE 23 5.11 TESTING AND COMMISSIONING 23 5.12
FLUSHING AND CLEANING 24
6.0 DATA REQUIREMENTS ............................................................................................................................... 25
6.1
GENERAL 25 6.2 SDRL 25 6.3
REPORTS AND ACCEPTANCE CERTIFICATES 25
7.0 PACKING AND PRESERVATION FOR TRANSPORT ............................................................................... 26
7.1 GENERAL 26 7.2 PRESERVATION 26 7.3
P ACKAGING FOR TRANSPORT 26
8/17/2019 ELDS-DR-S-02005_01e (020812)
5/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 3 of 57Date: 24
th July 2012
8.0 QUALITY MANAGEMENT ............................................................................................................................ 27
8.1 GENERAL 27 8.2
QUALITY M ANAGEMENT 27
8.3 SUPPLIERS INSPECTION AND TEST PLAN 27 8.4
CERTIFICATION DOCUMENTS 27 8.5 WEIGHT D ATA 27
9.0
EXPORT CONTROLS REQUIREMENTS..................................................................................................... 28
APPENDIX 1 – DECK CONTROL CENTRE (DCC) ............................................................................................. 29
1.0 INTRODUCTION ............................................................................................................................................ 29
2.0 DESIGN ........................................................................................................................................................... 29
2.1 LIFTING 29
3.0 FABRICATION ............................................................................................................................................... 29
4.0
CONTROL PANEL ......................................................................................................................................... 29
4.1
DCC M AIN CONTROL P ANEL 29
5.0 HYDRAULIC SYSTEM ................................................................................................................................... 29
6.0
ELECTRICAL SYSTEM ................................................................................................................................. 30
6.1
DCC POWER SUPPLY UNIT 30 6.2 F ABRICATION SITE POWER SUPPLY 30 6.3 INSTALLATION VESSEL POWER SUPPLY 30
7.0 PROTECTIVE COATING ............................................................................................................................... 31
8.0 TESTING ......................................................................................................................................................... 31
8.1
FLUSHING 31 8.2 PRESSURE TESTING 31 8.3 ELECTRICAL TESTING 31
APPENDIX 2 – UMBILICAL INTERFACE PANELS (UIP) .................................................................................. 32
1.0
INTRODUCTION ............................................................................................................................................ 32
2.0 DESIGN ........................................................................................................................................................... 32
2.1
LOCATION 32 2.2 L AUNCH FORCES 32 2.3
TRANSPORTATION CRITERIA 32 2.4 MONITORING C ABLES 33
3.0 TESTING ......................................................................................................................................................... 33
3.1 PRESSURE TESTING 33 3.2 ELECTRICAL TESTING 33
APPENDIX 3 – HYDRAULICALLY ACTUATED BALL VALVES ....................................................................... 34
1.0 INTRODUCTION ............................................................................................................................................ 34
2.0 DETAILED SPECIFICATION ........................................................................................................................ 34
2.1 M ANUFACTURER 34 2.2 V ALVE BODY 34 2.3 V ALVE TRIM 34 2.4 V ALVE ACTUATOR 34 2.5 V ALVE POSITION MONITOR 36
3.0 VALVE TESTING ........................................................................................................................................... 36
3.1
INSPECTION AND TESTING STANDARDS 36
3.2
PERFORMANCE 36
3.3
HYDROSTATIC OPEN BODY TEST 36 3.4 OPERATIONAL TORQUE TEST 36
3.5 HYDROSTATIC SEAT TEST 37 3.6
AIR SEAT TEST 37
4.0 ACTUATOR TESTING ................................................................................................................................... 37
8/17/2019 ELDS-DR-S-02005_01e (020812)
6/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 4 of 57Date: 24
th July 2012
4.1 ACTUATOR SHELL AND SEAL TEST 37 4.2
OPERATIONAL TEST 37 4.3 LEAK TEST 37
5.0 VALVE/ACTUATOR ASSEMBLY TEST ...................................................................................................... 37
5.1 OPERATIONAL BENCH TEST 37
6.0 VALVE POSITION MONITORING TEST ...................................................................................................... 37
7.0 IDENTIFICATION ........................................................................................................................................... 38
8.0
PAINTING ....................................................................................................................................................... 38
9.0 PACKAGING AND PROTECTION................................................................................................................ 38
APPENDIX 4 – MANUALLY / ROV OPERATED BALL VALVES ...................................................................... 39
1.0 INTRODUCTION ............................................................................................................................................ 39
2.0 DETAILED SPECIFICATION ........................................................................................................................ 39
2.1 M ANUFACTURER 39 2.2 V ALVE BODY 39 2.3
V ALVE TRIM 39
2.4
V ALVE OPERATION 39
3.0 VALVE TESTING ........................................................................................................................................... 40
3.1 INSPECTION AND TESTING STANDARDS 40 3.2 PERFORMANCE 40 3.3 HYDROSTATIC OPEN BODY TEST 40 3.4 OPERATIONAL TORQUE TEST 40 3.5 HYDROSTATIC SEAT TEST 40 3.6
AIR SEAT TEST 40
4.0 IDENTIFICATION ........................................................................................................................................... 40
5.0 PAINTING ....................................................................................................................................................... 40
6.0
PACKAGING AND PROTECTION................................................................................................................ 41
APPENDIX 5 – UMBILICALS, STORAGE WINCHES & HPU’S ......................................................................... 42
1.0 INTRODUCTION ............................................................................................................................................ 42
2.0 UMBILICALS SPECIFICATION .................................................................................................................... 42
3.0 UMBILICAL WINCHES SPECIFICATION .................................................................................................... 43
4.0 HPU SPECIFICATION FOR UIP ................................................................................................................... 44
APPENDIX 6 – PRESSURE & VALVE POSITION MONITORING SYSTEM / HYDROSTATICPRESSURE MEASURING INSTRUMENTATION ................................................................................................ 46
1.0 INTRODUCTION ............................................................................................................................................ 46
2.0
SYSTEM PERFORMANCE SPECIFICATION.............................................................................................. 46
3.0 TRANSDUCER SPECIFICATION ................................................................................................................. 47
3.1
J ACKET 47 3.2 FLOTATION T ANK 47
4.0 READOUT DEVICES AND POWER SUPPLIES ......................................................................................... 48
5.0 INSPECTION AND TESTING........................................................................................................................ 48
APPENDIX 7 – MONITORING CABLE ................................................................................................................. 49
1.0 INTRODUCTION ............................................................................................................................................ 49
2.0
CABLES.......................................................................................................................................................... 49
3.0
MULTI-CORE CABLES ................................................................................................................................. 49
4.0 CABLE JOINTS .............................................................................................................................................. 49
5.0 CABLE TESTING ........................................................................................................................................... 50
6.0 PACKAGING AND PROTECTION................................................................................................................ 50
8/17/2019 ELDS-DR-S-02005_01e (020812)
7/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 5 of 57Date: 24
th July 2012
APPENDIX 8 – TABLES / TECHNICAL DATA .................................................................................................... 51
1.0 INTRODUCTION ............................................................................................................................................ 51
2.0 LAUNCH CRITERIA....................................................................................................................................... 51
2.1 M AXIMUM VELOCITIES DURING L AUNCH 51
3.0
TRANSPORTATION CRITERIA ................................................................................................................... 52
3.1
M AXIMUM ACCELERATIONS AT UIP DURING TRANSPORTATION 52
APPENDIX 9 - DELETED ...................................................................................................................................... 53
APPENDIX 10 - FLOTATION TANK HYDRAULIC PIN RELEASE .................................................................... 54
1.0 INTRODUCTION ............................................................................................................................................ 54
2.0
DESIGN ........................................................................................................................................................... 54
2.1
L AUNCH FORCES 54 2.2 TRANSPORTATION CRITERIA 54
3.0 WEDGE RELEASE JACK SPECIFICATION ............................................................................................... 54
4.0 JACKET WEDGE RELEASE PANEL SPECIFICATION............................................................................. 55
5.0
FLOTATION TANK WEDGE RELEASE ROV CROSS-FLOW PANEL SPECIFICATION ....................... 55
APPENDIX 11 - BRIDGE SUPPORT JACKET SLING RETAINER / RELEASE HYDRAULICMECHANISM FOR UPPER TRUNNION ............................................................................................................... 56
1.0 INTRODUCTION ............................................................................................................................................ 56
2.0 SCOPE OF SUPPLY ...................................................................................................................................... 56
8/17/2019 ELDS-DR-S-02005_01e (020812)
8/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 6 of 57Date: 24
th July 2012
1.0 ABBREVIATIONS AND HOLDS
1.1 Abbreviations
Abbreviat ion Explanation
ANSI American National Standards Institute API American Petroleum Institute
ASTM American Society for Testing and Materials
ATEX Atmosphere Explosive
BS British Standard
CE Conformite’ Europeenne (European Conformity Mark for Safety)
DC Direct Current
DCC Deck Control Centre
DNV Det Norske Veritas
E&I Electrical & Instrumentation
EN Euro NormEPC Engineering, Procurement & Construction
EU European Union
GRP Glass Reinforced Plastic
HPU Hydraulic Power Unit
Hz Hertz
ICU Independent Certifying Unit
ISO International Organisation for Standardisation
ITP Inspection and Test Plan
IV Installation Vessel
LAT Lowest Astronomical Tide levelM&E Mechanical & Electrical
MTO Material Take-Off
NB Nominal Bore
NDT None Destructive Testing
NPT National Pipe Thread (American)
NOBO Notified Body
OCS Operator Control Station
PC Personal Computer
PED Pressure Equipment Directive
PMC Portable Monitoring ConsolePO Purchase Order
ROV Remotely Operated Vehicle
SAE Society of Automotive Engineers
SCADA Supervisory Control and Data Acquisition
SDRL Supplier Data Requirements List
SWL Safe Working Load
UCS Upending Control System
UIP Umbilical Interface Panel
U.K. United Kingdom
U.S. United States
8/17/2019 ELDS-DR-S-02005_01e (020812)
9/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 7 of 57Date: 24
th July 2012
1.2 Holds
APPENDIX 5 -3.0 UMBILICAL WINCHES SPECIFICATION
Air Consumption Available: 1530m3/hour at 2.3 MN/m2
(HOLD - Dragados to confirm)
1.3 Changes Since Last Revision
Rev Details
05 General update to reflect change of control methodology from manual toPLC based.
HOLD removed in Appendix 1-6.2 Fabrication Site Power Supply
8/17/2019 ELDS-DR-S-02005_01e (020812)
10/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 8 of 57Date: 24
th July 2012
2.0 INTRODUCTION
2.1 Purpose & Scope of this Document
This Specification defines the minimum technical requirements for the design; manufacture,testing and commissioning of the Jacket Upend Control System (UCS) on the Eldfisk II 2/7SJacket structure and the supply of 4 No. ROV operated flood valves for the Bridge SupportJacket structure
The 2/7S Jacket is an 8-leg structure with 2 No. Flotation Tanks. All jacket legs will be floodedduring installation to achieve upending and obtain on-bottom stability. The 4 main legs will besubdivided into 3 compartments. The 4 internal legs will not be subdivided. Each of theFlotation Tanks will be subdivided into 15 compartments. The structure is designed to bebarge launched.
The Bridge Support Jacket is a 4-leg structure, which is designed to be lift installed. All jacketlegs have single compartments and will be flooded during installation to assist on-bottomstability.
Note: This document primarily specifies the technical requirements for the UCS on the 2/7SJacket structure
The technical requirements for 4 No. ROV operated flood valves and for the sling retainer /release hydraulic mechanism for upper trunnion required for the Bridge Support Jacketstructure are detailed in Appendix 4 and Appendix 11 of this Specification.
Both jackets will be installed in the Norwegian sector of the North Sea; the approximate waterdepth at the offshore installation site is -75.0m.
2.2 Eldfisk II Field Development
ConocoPhillips, on behalf of the PL018 license, plans to design, construct and install thefollowing new facilities at the Eldfisk Field:
A new wellhead, process and accommodation platform designated 2/7Ssupported by a steel jacket,
A new bridge system linking the 2/7S platform to the existing 2/7E platform. Thebridge system comprises two bridges and an intermediate bridge support. Thebridge support comprises a jacket sub-structure and Topside with flare facilities,
Modifications necessary on the existing Eldfisk Complex installations, Eldfisk 2/7Band Embla 2/7D to facilitate continued operations of exiting facilities and for theintegration of the new 2/7S platform,
New pipeline connections from 2/7S to the existing oil and gas export pipelinesdownstream of 2/7B to Ekofisk Complex,
New subsea power and control cable between 2/7S and an external source.
The new 2/7S platform will be the new field control centre for Eldfisk Complex. The existingplatforms at the Eldfisk Complex will be converted to not normally manned facilities, to beoperated and controlled from the new 2/7S platform.
The illustration below gives an indication of the new facilities and the existing Eldfisk Fieldfacilities.
8/17/2019 ELDS-DR-S-02005_01e (020812)
11/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 9 of 57Date: 24
th July 2012
KBR shall perform the Engineering and Procurement Assistance for the EPC on behalf ofDragados Offshore SA of the 2/7S Jacket and Bridge Support Structure.
2.3 Definitions
The following definitions apply throughout this document:
“Owner” ConnocoPhillips
“Purchaser” Dragados Offshore.
“Supplier” The person, firm or company to whom theenquiry or purchase order is issued.
“Inspection Authority” Inspection Authority is defined as theorganisation which verifies that the material orequipment supplied by the Supplier has beendesigned, constructed, inspected and tested instrict accordance with the requirements of theapplicable design code.
Verification Contractor Verification Contractor is defined as the
organisation that verifies that the material orequipment supplied by the Supplier has beendesigned, constructed, inspected and tested instrict accordance with the requirements of theapplicable design code.
Manufacturer Manufacturer who is contracted to beresponsible for planning, execution anddocumentation of manufacturing.
2/7B
2/7A
2/7FTP
2/7E
P o w e r &
C o n t r o l
C a b l e
I n j . w a t e r t o E k o f i s k
C o m p l e x
I n j . w a t e r
a n d l i f t
g a s
t o 2 / 7 B
O i l a n d g
a s e x p o r t t o
E k o f i s k C o m
p l e x
O i l
, w a t e
r a n d
g a s
f r o m 2 / 7 D
Bridge Supportand Flare
2/7S
8/17/2019 ELDS-DR-S-02005_01e (020812)
12/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 10 of 57Date: 24
th July 2012
2.4 Codes and Standards
2.4.1 General
The equipment shall be designed, manufactured, tested and delivered in accordance with thisSpecification and the regulations, Project documents, and codes listed below. It is theSupplier’s responsibility to ensure their compliance and that of their Sub-suppliers.
2.4.2 Order of Precedence
In the event of conflict between the requirements of this Specification and other referenceddocuments, the Supplier shall request written clarification from the Purchaser. The order ofprecedence will normally be:
Norwegian Government Legislation and Statutory Guidelines,
EU Directives,
National and International Codes and Standards,
This Specification,
Other Project Specifications,
Data Sheets,
Purchase Order.
Any deviations from these documents shall be agreed with the Purchaser prior toimplementation.
Compliance by the Supplier with the provision of this Specification does not relieve them oftheir responsibility to furnish equipment and accessories of a proper mechanical design suited
to meet the specified service conditions and/or local codes governing health and safety.2.4.3 Company Specifications
ELDS-DR-Q-00007 External Subcontractor/Auxiliary Company Coordination
ELDS-DR-Q-00008 Quality Surveillance at Vendors and Subcontractors
ELDS-DR-Q-00013 Vendor and Subcontractor Evaluation
ELDS-DR-G-00006 Material Management and Control Procedure
ELDS-DR-G-00037 Material Traceability
ELDS-DR-G-00042 Technical Queries Procedure
2.4.4 Project Specifications
ELDS-DR-G-00060 Submission of documentation by Vendors/Suppliers
ELDS-DR-G-00038 Packing and Preservation Specification
ELDS-DR-K-00006 Structural Steel Specification
ELDS-DR-K-00005 Structural Steel Fabrication Specification
ELDS-DR-K-00007 General Coating Specification for Fabrication Sites
8/17/2019 ELDS-DR-S-02005_01e (020812)
13/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 11 of 57Date: 24
th July 2012
2.4.5 International Codes and Standards
All equipment supplied shall be designed, manufactured and tested in accordance with therelevant sections of the following Codes Standards and Regulations including any addenda,supplements or revisions applicable at date of issue of enquiry.
ANSI B16.5 Pipe Flanges and Flanged Fittings
API 6D Pipeline Valves
ANSI B16.11Standard for Forged Steel Fittings Socket Welding andThreading
ASTM A36 Specification for Carbon Structural Steel
ASTM A105Specification for Forgings, Carbon Steel for PipingComponents
ASTM D 412 Tensile Properties of Rubber/Elastomers
ASTM D 2240 Standard Test Method for Rubber Property – DurometerHardness
BS PD 970 Specification for Wrought Steel
BS ISO 4406:1999 Method for coding the level of contamination of solid particles
BS EN 12079 Offshore Containers
EN 10204 3.1 Metallic products – types of Inspection Documents
SAE 517 100R Series Hydraulic Hoses
SAE J343Test and Test Procedures for 100R Series Hydraulic Hose and
Hose Assemblies
All reference codes and standards shall be the latest edition.
This Specification takes precedence over any conflicting requirements with the above.
8/17/2019 ELDS-DR-S-02005_01e (020812)
14/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 12 of 57Date: 24
th July 2012
3.0 SCOPE OF WORK
3.1 Introduction
The Supplier’s scope includes design calculations, drawings and documentation, provision ofall materials, manufacture, inspection, non-destructive examination, trial assembly, testing andcommissioning of the UCS in accordance with this Specification. Refer to drawing No: ELDS-DR-S-00099.001 and ELDS-DR-S-00154-001 for the Jacket Flooding Schematic of the 2/7SJacket and Bridge Support Jacket respectively.
The Supplier should draw upon their existing pre-engineered or standard designs as far as ispracticable in order to satisfy the functional and technical requirements described within thisSpecification and referenced documentation.
A full listing of the UCS hardware is detailed below. Note: Exact final lengths will vary and shallbe determined by the Purchaser prior to purchase order award, however for estimatingpurposes the following estimated lengths shall be assumed:
2/7S JACKET UCS SCOPE OF WORK
ItemNo.
Quantity Unit Descrip tion
1 1 EADeck Control Centre (DCC), supplied in accordance with Appendix 1
2 2 EAUmbilical Interface Panel (UIP), supplied in accordance with Appendix 2
3 14 EA100mm (4") x 150# single acting (spring return to close)hydraulically actuated full-bore ball valves (c/w all flange
gaskets, nuts and bolts) supplied in accordance with Appendix 3
4 14 EA
150mm (6") x 150# single acting (spring return to e closeposition) hydraulically actuated full-bore ball valves (c/w allflange gaskets, nuts and bolts) supplied in accordance with Appendix 3
5 0 - DELETED
6 28 EA
100mm (4") x 150# ROV operated full-bore ball valves (c/w allflange gaskets, nuts and bolts) supplied in accordance with Appendix 4.
Note: 4 No ROV operated valves for use on the Bridge SupportJacket structure have been deducted from the total quantity andincluded in the Bridge Support Scope of Work table.
7 2 EA100mm (4") x 150# MANUALLY operated full-bore ball valves(c/w all flange gaskets, nuts and bolts) supplied in accordancewith Appendix 4
8 1 EAHydraulic Power Unit (HPU) for the DCC system, supplied inaccordance with Appendix 5
10 1 EA Primary Electro-Hydraulic Umbilical x 170m long, supplied inaccordance with Appendix 5
11 1 SetJumper hoses and fittings for connecting items 1 & 10 x 10mlong
8/17/2019 ELDS-DR-S-02005_01e (020812)
15/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 13 of 57Date: 24
th July 2012
ItemNo.
Quantity Unit Descrip tion
12 1 EABack-up Electro-Hydraulic Umbilical x 170m long, supplied on aWooden Reel, supplied in accordance with Appendix 5
13 VTA EA Umbilical Floats to suit items 10 & 12
14 2 EA Air Driven Storage Winch to suit item 10, supplied in accordancewith Appendix 5
15 0 - DELETED
16 1 SetJumper cable(s) and connectors between items 1 & 10 x 10mlong
17 1 SetPower supply jumper cable(s) and connectors between items 1& external power supply x 10m long
18 0 - DELETED
19 0 - DELETED
20 0 - DELETED
21 1 LotJacket and Flotation Tank position and compartment pressuremonitoring cable system, supplied in accordance with Appendix7
22 16 EAJacket leg compartment pressure monitoring sensors supportbrackets & mounting attachments supplied in accordance with Appendix 6
23 30 EAFlotation Tank compartments pressure monitoringsensors/fixings and mounting flange plates, supplied inaccordance with Appendix 6
24 1 LotComplete set of cable assemblies for connecting valve positionmonitoring system and Umbilical Interface Panel (all legs andflotation tanks), supplied in accordance with Appendix 7
25 1 EA Laptop (Back-up for HMI)
26 1 EA Portable Monitoring Console (PMC – System Monitoring Laptop)
27 1 LotHydraulic tube bundle assembly - 2 pass of ½” (12.7mm) O.D. x0.064” (1.65mm) WT. Total length 2850m
28 1 LotFittings, mounting clamps and consumables for interconnectingall the hydraulically actuated ball valves to tube bundles
29 VTA Liters MacDermid Canning HW540E hydraulic fluid
30 VTA EAHydraulic tube bundle and electrical/monitoring nylon cablesecuring ties
31 VTA M
6 mm wide hydraulic tube bundle and electrical/monitoring
stainless steel “Band-It” type securing strapping C/W 2000buckles & 2 each Hand tools (or equivalent).
8/17/2019 ELDS-DR-S-02005_01e (020812)
16/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 14 of 57Date: 24
th July 2012
ItemNo.
Quantity Unit Descrip tion
32 VTA M20 mm wide hydraulic tube bundle and electrical/monitoringstainless steel “Band-It” type securing strapping c/w 3000buckles & 2 each Hand tools (or equivalent).
33 VTA EAmonitoring cable(s) for Jacket legs and Flotation Tankcompartments. Cable(s) and connectors to be suitable for wetimmersion in sea water, supplied in accordance with Appendix 7
34 1 LotDesign drawings, calculations and documentation in accordancewith the SDRL
35 1 Lot
Upend and Control System equipment testing, inspection,commissioning, flushing and cleaning at place of manufactureprior to shipment (exception – flushing and cleaning of hydraulictube bundles).
36 1 Lot Tagging / identification of equipment
37 1 Lot Weighing of completed packages
38 1 Lot Preservation, packing, marking and preparation for shipment
39 12 EA150mm (6") x 150# double acting hydraulically actuated full-boreball valves (c/w all flange gaskets, nuts and bolts) supplied inaccordance with Appendix 3
40 40 EA1" NPT x 3000# couplings 80mm long carbon steel body toconnect hydraulic tubing through legs A1, A2, D1 & D2 asdetailed on drawing no. ELDS-DR-S-00104-001 & -003.
41 80 EA1" NPT male plugs for insertion into 1" NPT couplings duringwelding as specified on drawing no. ELDS-DR-S-00104-001 & -003.
42 4 EA200mm x 40 thk insert plate to suit electrical penetrators on legs A1, A2, D1 & D2 as detailed on drawing no. ELDS-DR-S-00104-001 & -003.
43 2 EA
Flotation Tanks Hydraulic Pin Release, including hydraulic jackswith diverter sheave assemblies, mechanical pull wire systems(incl. 75m long pull wire) and interconnecting hydraulic tubefittings, supplied in accordance with Appendix 10.
44 1 EAJacket Wedge Release Interface Panel, supplied in accordancewith Appendix 10.
45 2 EAFlotation Tank Wedge Release ROV Cross Flow Panel.Incorporating ROV Grab Bar, supplied in accordance with Appendix 10.
46 1 EABack-up system for opening vent valves on legs A1, A2, D1 & D2including hand pump, flexible hoses and interconnecting hydraulictube fittings.
47 VTA EA Bottles of Loctite Threadlockers (Model: S-13779)
8/17/2019 ELDS-DR-S-02005_01e (020812)
17/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 15 of 57Date: 24
th July 2012
BRIDGE SUPPORT JACKET UCS SCOPE OF WORK
48 2 EASling Retainer / Release Hydraulic Mechanism for UpperTrunnion supplied in accordance to Appendix 11.
49 4 EA
100mm (4") x 150# ROV operated full-bore ball valves (c/w all
flange gaskets, nuts and bolts) supplied in accordance with Appendix 4.
The Supplier shall perform all work associated with the design, manufacture and testing of theUCS in accordance with this Specification.
The Supplier shall state in their quotation where the manufacture of each component of theUCS will take place. If it is intended to sub-contract all or part of the work, the name, locationand scope of the Sub-supplier shall be stated.
The Supplier shall provide all test material, equipment and facilities unless otherwise noted.
The Supplier shall include details of their proposed test facilities and equipment in theirquotation. Should the Supplier use a Sub-supplier for testing then the name and location ofthe Sub-supplier shall be supplied. Information under this heading shall be specific for thetests required and not of a general nature.
The Jacket Fabricator shall carry out the installation of the UCS equipment as detailed in thisSpecification. The work shall be carried out at the Jacket fabrication site, which is located atCadiz, Spain.
The final testing and commissioning of the installed UCS equipment shall be carried out by theSupplier with assistance from the Jacket Fabricator.
3.2 Nominated Sub-suppl iers
The Supplier will be required to use appropriate items from Sub-suppliers when nominated byPurchaser. Where this requirement has significant technical and/or delivery impacts, theSupplier may offer alternative Sub-suppliers provided the commercial and technicalimplications are fully identified in the Supplier’s bid.
8/17/2019 ELDS-DR-S-02005_01e (020812)
18/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 16 of 57Date: 24
th July 2012
4.0 BASIC DESIGN INFORMATION
4.1 Design Life
The Supplier shall design the UCS to meet the Project requirements. The UCS supplied to therequirements of this Specification shall be used to assist in the installation of the Jacketstructure detailed in section 2.1 of this Specification.
The DCC, UIP, HPU, PMC, Hydraulic Jacks, Umbilicals and Winches shall be designed andmanufactured for a minimum design life of 5 years and shall be removed from the InstallationVessel or Jacket after Jacket installation on the seabed.
The remaining components of the UCS may or may not remain in situ. The Jacket legcompartment Flood and Vent Valves shall not be removed and must therefore be designed tohave a minimum 40 year, in situ, service life. The Flood and Vent Valves shall remain in the‘closed’ position to prevent long term egress of biocide from the leg compartments.
4.2 Environmental/Installation Data
At the Jacket fabrication site prior to loadout the Upend Control System will be exposed to asevere sea/air environment for a period of up to 12 months.
During installation several components of the UCS (i.e. flood & vent valves, tube bundles,electrical cables, pressure sensors, hydraulic jacks and umbilical interface panels) shall beimmersed in seawater and may remain in this situation for a number of days before use.These components shall therefore be capable of withstanding a hydrostatic pressure of 0.98MN/m2 (this value has been derived to account for the field water depth plus 100 year stormwave crest elevation).
Climatic conditions at the fabrication site and offshore installation site are given below:
ConditionLocation
Offshore Installation Site Fabrication Site
Air Temperature -7.9ºC to +28ºC +5ºC to +35ºC
Sea Temperature +2.6ºC to +20.0ºC -
Relative Humidity 25% to 100% 25% to 100%
Atmosphere Salt LadenSalt laden and corrosive.
Wind driven dust.
It should also be noted that equipment located on the outside of the Jacket structures mightalso be subject to direct radiant heat from the sun, which could generate temperatures as highas +80°C (maximum). The Supplier should take particular note of this high temperaturerequirement particularly when selecting materials and designing the UCS.
8/17/2019 ELDS-DR-S-02005_01e (020812)
19/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 17 of 57Date: 24
th July 2012
5.0 2/7S JACKET TECHNICAL REQUIREMENTS
5.1 General
After completion of the Jacket at the Jacket Fabrication site, the Jacket with Flotation Tanks
installed (each one located at opposite sides of the Jacket structure) shall be loaded out onto atransportation / launch barge in preparation for transportation and offshore installation.
Prior to load-out the UCS shall be functionally tested and commissioned by the UCS Supplierwith the assistance of the Jacket Fabricator. After completion of the testing andcommissioning, each Jacket leg and Flotation Tank compartment shall be filled withcompressed air to a pressure of 0.05 MN/m2 by the Jacket Fabricator. The compartmentpressures shall be monitored by the UCS to confirm the integrity of each compartment. Anongoing daily check* on the compartment pressures versus ambient temperatures shall becarried out after jacket load-out, during transportation to the offshore site and prior to jacketlaunch. Monitoring cables accessible from the deck of the barge shall be provided for thispurpose (cable specification shall be in accordance to Appendix 7 of this Specification).
Monitoring of the Jacket leg compartments shall also be carried out during jacket installationonto the seabed. Note: the Supplier shall also provide an option for monitoring the FlotationTank compartment pressures during installation of the jacket onto the seabed i.e. prior toremoval of the Flotation Tanks from the Jacket structure when the tanks shall be underwater.
During any storage period on the transportation / launch barge and during transit to theoffshore site the hydraulic system maybe subject to thermal effects. The Supplier shall designthe UCS system such that these thermal effects cannot cause premature opening of theJacket and Flotation Tank flood valves.
* Any variations in the pressure measurements prior to offshore installation shall be discussedwith the site team / designer / installation contractor and remedial action agreed.
The UCS shall be designed to control a series of flood and vent valves on the Jacket legs andnominated Flotation Tank compartments, allowing the flooding of buoyancy compartments in apre-planned sequence, such that the Jacket maintains integrity and stability throughout thecomplete upending and setting down operation.
The Jacket is designed to be barge launched and the top of the Jacket (launch frame) willsubmerge to approximately 55m water depth. After completion of the launch the Jacket willfloat at approximately 11.7º to the horizontal and will then be towed to the Installation Vessel(IV) to commence the upending and set down operation.
Once the main lifting slings are connected to the IV crane, the primary electro-hydraulicUmbilical, which shall be located on the deck of the IV shall be reeled off its Storage Winchand manoeuvred over to the Jacket structure where itwill be manually connected to theUmbilical Interface Panels (UIP). The IV crane shall assist with handling the Umbilical onto theJacket structure. Buoyancy (floats) aids shall be supplied to assist with handling the Umbilical.The floats shall be capable of being attached / detached as necessary during deployment andrecovery of the Umbilical.
The primary electro-hydraulic Umbilical shall also be connected to the DCC located adjacentto the Umbilical Storage Winches on the deck of the IV. The purpose of the Umbilical / DCC /HPU is to provide means of opening and closing the valves and to monitor Jacket andFlotation Tank compartment pressures and valve position data.
The Jacket shall be installed using a combination of the IV crane and controlled flooding andventing of Jacket leg and nominated Flotation Tank compartment valves from the DCC locatedon the deck of the IV.
8/17/2019 ELDS-DR-S-02005_01e (020812)
20/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 18 of 57Date: 24
th July 2012
The UCS is required to achieve the final Jacket vertical position prior to installation on theseabed. The set-down operation will be carried out using the IV crane. Limited ballasting maybe required during this operation for trimming the Jacket.
Any lights and cameras to be used during the set-down operation shall be provided by ROV’s.
After the Jacket is on the seabed the UCS shall be used to complete the flooding of the Jacket
leg and nominated Flotation Tank compartments to assist with on-bottom stability prior topiling. The primary electro-hydraulic Umbilical shall be disconnected and recovered to thedeck of the IV after the Jacket leg-flooding operation is completed and prior to removal of theFlotation Tanks.
The flotation tanks shall be removed from the jacket one at a time using the IV crane after the jacket has been set down on the seabed (before the piling operation). To assist with theremoval operation each tank shall be equipped with one hydraulic wedge release jack, whichshall be operated from top platform of the jacket (El +22.00m) using the UCS HPU orInstallation Contractor provided HPU. Once the flotation tanks are removed from the jacket,they will have to be fully drained and back-loaded onto a transportation barge.
Any equipment that is left permanently installed on the Jacket after its installation shall berated for 100m water depth to allow for the 100 year wave condition.
5.2 Jacket Configuration
The Jacket structure is designed to be barge launched and installed in 75m water depth in theNorwegian sector of the North Sea.
The general configuration of the Jacket and the UCS are shown on Project drawings. Specificreferences to Jacket leg numbers and buoyancy compartment numbers quoted below can be
found on schematic drawing:
ELDS-DR-S-00099-001 Jacket Flooding Schematic
The estimated upper bound dry weight of the Jacket structure is 13,200 tonnes. Actual weightwill be confirmed on detailed weight reports issued for the Jacket structure.
Each Jacket corner leg (A1, A2, D1 & D2) has 3 buoyant floodable compartments. The innerand outer launch truss legs (B1, B2, C1 & C2) have 1 buoyant floodable compartment each. All Jacket pile sleeves shall be free flooding. Each Flotation Tank has 15 buoyant floodablecompartments. Three compartments on each tank (C5, C10 & C15) shall require controlledflooding using flood and vent valves. The remaining tank compartments shall be flooded using
rip-out diaphragms, supplied by others.
The UCS shall incorporate a status monitoring system to ensure that the upending operationteam is aware of the integrity of the Jacket / Flotation Tank floodable compartments and theopen and closed positions of the flood and vent valves.
The data shall be transmitted from the pressure sensors and valve position indicators to theUIP via pre-installed electrical cables and from the UIP to the DCC via the primary electro-hydraulic Umbilicals.
From EL+0.00m (LAT) to the top of the Jacket is 24.50m (24.50m above MSL) afterinstallation, prior to cutting.
8/17/2019 ELDS-DR-S-02005_01e (020812)
21/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 19 of 57Date: 24
th July 2012
5.3 Flooding System
5.3.1 Operating Requirements
The flooding system for the Jacket legs and the nominated Flotation Tank compartments shallbe designed for operation from the DCC. The DCC shall be located on the deck of the IV nearthe HPU and Umbilical Storage Winches. The DCC shall be operated manually via HMI after
the Jacket has been launched and positioned alongside the IV.
Primary hydraulic and electrical energy to the systems located on the Jacket shall be providedby the primary electro-hydraulic Umbilical via the UIP located on top of the Jacket. After the launch the Jacket will float horizontally in the range of 5.5º to 13.6º (intact condition),
After launch the Jacket will be towed and then connected to the IV crane prior to operation ofthe DCC. The final setting down of the Jacket onto the seabed shall be achieved using the IVcrane in conjunction with the DCC by operating specified flood valves in Jacket legs (A1, A2,B2, C2, D1 & D2) and Flotation Tank compartments (C5, C10 & C15). The primary electro-hydraulic Umbilical shall be connected to the Jacket by the IV crane prior to commencement ofthe upending operation. A back-up Umbilical, stored on a wooden reel shall also be provided
in the event of a primary Umbilical failure.
The Umbilicals, winches and HPU requirements are detailed in Appendix 5 of thisSpecification.
5.3.2 Jacket Legs and Flotation Tanks
All actuated flood valves shall be located outside all Jacket leg and nominated Flotation Tankfloodable compartments and shall be operated from the DCC. All flood valves shall be highintegrity, leak proof, full-bore ball valves. The method of actuation shall be hydraulic. All valvesfitted with a spring return to the closed position shall be single acting hydraulic to open thevalve. Hydraulically actuated ball valves are detailed in Appendix 3 of this Specification.
ROV operated valves are located on the outside of all Jacket leg and the nominated FlotationTank floodable compartments. The ROV valves shall be secured in the closed position andshall only be used in the event of malfunction of the hydraulically actuated flood valves (excepton the inner truss legs). All ROV valves that are opened during the Jacket installation shall beclosed and secured after completion of the Jacket installation. The ROV claw, attached to themanipulator arm, shall operate the valves, no special ROV tooling is envisaged for operation ofthese valves. ROV operated ball valves are detailed in Appendix 4 of this Specification.
The types of valves and their sizes are also identified on the Project drawings.
5.4 Venting System
5.4.1 Jacket Legs and Flotation Tanks
As each Jacket leg and nominated Flotation Tank compartment is flooded with water it willbecome necessary to vent off the air being compressed in the top of the buoyancycompartments. This is to ensure dissipation of the energy (compressed air), which wouldotherwise be stored under each watertight diaphragm. It also reduces the risk of back-pressure across the open flood valve, and in the Jacket legs reduces oxygen levels that wouldprevent biocide working efficiently. There is no biocide in any of the Flotation Tankcompartments.
The vent lines for the corner Jacket legs (A1, A2, D1 & D2) shall run inside the legs for added
protection up to the top of the legs and shall be fitted with spring return to the closed position,single acting hydraulic to open the valve.
8/17/2019 ELDS-DR-S-02005_01e (020812)
22/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 20 of 57Date: 24
th July 2012
The vent valve assemblies for inner legs (B1 & C1) shall be located at the top of the legs onthe outside and shall be fitted with manually operated ball valves. The vent valve assembliesfor outer legs (B2 & C2) shall be located at the top of the legs on the outside and shall be fittedwith double acting hydraulically actuated ball valves with spring return to the closed position,single acting hydraulic to open the valve.
The vent lines for the Flotation Tank compartments (C5, C10 & C15) shall be located at the
top of each compartment on the outside and shall be fitted with double acting hydraulicallyactuated ball valves with NO spring return to the ‘closed’ position.
In the event of a hydraulic failure on any of the vent valves on Flotation Tank compartments(C5, C10 & C15), a back-up system for remotely opening a failed vent valve shall be provided.
The types of valves and their sizes are identified on the Project drawings.
5.5 Flotation Tank Recovery
5.5.1 Release from Jacket
Each flotation tank is secured to the jacket structure by one mechanical wedge. Each wedge inturn is mechanically connected to a double acting hydraulic jack, which shall be used to pullout the wedge to release the tank from the jacket structure. The wedge connection and the pullout jack shall be mounted onto the flotation tank and are theoretically under no load during thepull out operation. A method of hydraulically locking the jacks in position during jackettransportation, launch and installation shall be provided. During the releasing operation thetank will be connected to the IV crane which will lift it clear of the jacket structure after thewedges have been removed. The requirements for the pull-out jacks are specified in Appendix10.
The release jack on each flotation tank shall be operated independently via a jacket wedge
release interface panel located on the top platform (El+22.00m). The hydraulic power will beprovided by the UCS HPU (or Installation Contractor provided HPU) which will be transferredto the top platform after the upending operation is complete. Details of the flotation tankhydraulic service requirements are depicted on the following drawing:
ELDS-DR-S-00099-001 Jacket Flooding Schematic
In the event of a hydraulic failure a mechanical back-up system shall also be providedcomprising a pull wire and sheaves suitable for pulling via the IV crane or a winch in a verticaldirection. The wire from each jack shall terminate on the sea ladder access ladder restplatform (El+6.00m) and will be connected manually to a surface deployed crane / winch wireby one of the Installation Contractor personnel in order to complete the pulling operation. A
double piston rod type jack shall be provided for this application. The transfer of hydraulic fluidacross the jack cylinder shall be required to allow the mechanical back-up system to operate;the flotation tank wedge release cross-flow facility shall be suitable for operation by ROV.
5.5.2 Draining and Securing
After a flotation tank has been removed from the jacket it will be lifted to the surface using theIV crane. All 15 compartments will be allowed to gravity drain. Once the draining is completethe tanks will be back-loaded onto a transportation barge.
5.6 Jacket Legs and Flotation Tanks – Status Monitoring System
To ensure the integrity of the Jacket structure, Flotation Tanks and associated systems duringall phases of the load-out, transportation, launch and upend, the following status-monitoringsystems shall be incorporated:
8/17/2019 ELDS-DR-S-02005_01e (020812)
23/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 21 of 57Date: 24
th July 2012
5.6.1 Status Monitoring Display
After Jacket load-out, prior to Jacket launch and during Jacket installation, Jacket leg andFlotation Tank compartment pressures and flood/vent valve status monitoring shall beachieved by the following methods:
1. Primary system - electrical status monitoring. Output shall be displayed on the PMC(System Monitoring Laptop). PMC shall be connected to the UIP via a monitoringcable(s),
2. Back-up system - Back-up PMC (laptop). PMC shall be connected to the UIP via amonitoring cable(s).
The PMC shall be supplied with a portable external supply (if required for energising sensors). A minimum continuous duration of 24 hours full service operation is required for the PMC.
During installation, Jacket leg and Flotation Tank compartment pressures and flood/vent valvestatus monitoring shall be achieved by the following methods:
1. Primary system - electrical status monitoring. Output shall be displayed on a HMI
contained within the DCC,2. Back-up system - Back-up Laptop connected to the DCC.
The Laptop and software shall be provided by the Supplier and must be suitable for operationin a marine environment. Consideration shall be given to battery life. A minimum continuousduration of 12 hours full service operation per battery is required for the Laptop
The compartment monitoring equipment shall be purchased in accordance with Appendix 6.
5.6.2 Jacket Legs & Flotation Tanks Flood / Vent Valve Status
All hydraulically actuated flood/vent ball valves located on the Jacket structure and valves on
compartments C5, C10 & C15 on each Flotation Tank shall incorporate an open/close remotestatus monitoring facility. This is to establish the status of any flood/vent valve during theJacket upending and set down operations. Monitoring of each valve stem shall be done at thefully open, intermediate and fully closed positions.
5.6.3 Jacket Leg Ballast Compartment Content
Knowledge of the ballast tank contents of ALL the Jacket floodable legs is required. Toachieve this, an electronic pressure transmitter shall be installed near the bottom of each ofthe Jacket leg and Flotation Tanks compartments. The pressure transmitters shall also beused to monitor each compartment’s internal air pressure prior to sail-away from the Jacketfabrication site and launch at the offshore installation site. Refer to Section 5.1 of thisSpecification for a general description of this requirement.
During offshore installation of the Jacket the transmitters shall measure the head of seawaterin each respective compartment during the flooding operation. The data shall be relayed fromthe transmitter via interconnecting cables to the UIP and to the DCC via the primary electricalUmbilical. Compartment pressures shall be indicated on the DCC HMI or in the Laptop in theevent of failure of the HMI.
The Flotation Tanks compartment monitoring equipment shall be purchased in accordancewith Appendix 6.
5.6.4 Flotation Tank Compartment Pressure Monitoring
Pressure transducers shall also be installed in each Flotation Tank compartment to monitorthe internal air pressure prior to sail-away from the Jacket fabrication site and after Jacketlaunch at the offshore installation site. Refer to Section 5.1 of this Specification for a generaldescription of this requirement.
8/17/2019 ELDS-DR-S-02005_01e (020812)
24/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 22 of 57Date: 24
th July 2012
The Flotation Tanks compartment monitoring equipment shall be purchased in accordancewith Appendix 6.
5.6.5 Jacket Depth Measurement
Jacket depth measurement shall be achieved using draught marks painted on the Jacket legsto give a visual indication of the amount that the Jacket is submerged. No depth-measuring
instrumentation shall be provided.5.6.6 Seabed Clearance
Seabed clearance shall be monitored by the ROV’s. No seabed clearance instrumentationshall be provided.
5.7 Deck Control Centre (DCC)
The DCC shall be a free standing control console incorporating a weather protectionenclosure. The DCC shall include an HMI, PLC Controller and power supplies (including back-up) associated with installing the Jacket structure. The DCC shall be self contained andtransportable, and shall allow easy manual operation and monitoring via HMI of the valves and
E&I systems. During Jacket installation, the DCC shall be located on the deck of the IV. TheDCC shall be skid mounted for sea fastening on to the deck of the IV.
The DCC shall incorporate all the systems for operating and monitoring the Jacket legflood/vent valve control and position indicators, and Jacket leg and Flotation Tank pressuresensors.
Further details of the requirements of the DCC are given in Appendix 1 of this Specification.
5.8 Umbilical Interface Panels (UIP)
One UIP shall be provided. The UIP shall include all hydraulic and E&I connection fittings toallow transfer of the hydraulic fluid and data to/from the Jacket flood & vent valves and theJacket and Flotation Tanks monitoring systems associated with installing the Jacket structureonto the seabed. The UIP shall be self contained and shall allow easy manual connection ofthe primary electro-hydraulic Umbilicals pigtails prior to commencing with the flooding and set-down operation. The UIPs shall be located on top of the Jacket in an accessible location afterthe launched Jacket is positioned adjacent to the IV.
When the Jacket is launched the UIPs will submerge to a maximum water depth of 55m.When the Jacket surfaces the UIPs will be above the waterline and must therefore be fully selfdraining.
After the launched Jacket is stable the primary electro-hydraulic Umbilicals shall be transferredacross from the IV. The Umbilical will be connected with the assistance of the IV crane;Umbilical floats shall be supplied to assist with the transfer . After connecting the primaryelectro-hydraulic Umbilical the UIP personnel shall return to the IV in order to commence theupending operation.
The UIP shall be capable of withstanding wave slam and the loads imposed during thelaunching operations (ref. Appendix 8 of this Specification).
Further details of the requirements of the UIP are given in Appendix 2 of this Specification.
The UIP shall be removed from the Jacket after completion of the flooding operation along with
all externally routed tube bundles and cables (where applicable). The Supplier shall provide allfastenings and fixings to secure the UIP to the Jacket structure.
8/17/2019 ELDS-DR-S-02005_01e (020812)
25/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 23 of 57Date: 24
th July 2012
5.9 Umbilical
There is one primary Umbilical and one back-up Umbilical required which are described below(further details of the requirements of the Umbilicals, Storage Winches and HPU are given in Appendix 5 of this Specification):
5.9.1 Primary Electro-Hydraulic Umbilical
One primary electro-hydraulic Umbilical and Storage Winch shall be provided. The primaryelectro-hydraulic Umbilical shall be suitable for interconnecting between the DCC (via jumperhoses) and the UIP. The Umbilical shall operate the Jacket and Flotation tank flood and ventvalves, namely
Jacket flood and vent valves on legs A1, A2 & B2.Row A Flotation Tank flood and vent valves on compartments C5, C10 & C15.
Jacket flood and vent valves on legs C2, D1 & D2.Row D Flotation Tank flood and vent valves on compartments C5, C10 & C15.
The primary electro-hydraulic Umbilical shall be 170m long including 10m long pigtails onJacket end and 5m on winch end and shall contain sufficient hydraulic hoses and electricalcables to provide a means of opening / closing / monitoring all the hydraulically actuatedvalves located on the Jacket and Flotation Tanks. The Umbilicals will also transmit data toconfirm Valve position and the Jacket and Flotation Tank compartment pressures.
The Umbilical Storage Winches for the primary electro-hydraulic Umbilicals shall be airpowered.
5.9.2 Back-up Hydraulic Umbilical
A back-up electro-hydraulic Umbilical shall be provided, which shall be identical to the primaryelectro-hydraulic Umbilical. The back-up electro-hydraulic Umbilical shall be supplied on awooden reel/storage drum.
5.9.3 Primary Electrical Umbilical
DELETED.
5.9.4 Back-up Electrical Umbilical
DELETED.
5.10 Tubing/Tube Fittings and Tube Bundle
All tubing and interconnecting tube fittings shall be manufactured from 316 grade stainlesssteel. Stainless steel tube bundles shall be supplied as 2 cores x 1/2” (12.7mm) OD x 0.064”tubing and shall be fully over sheathed and pressure tested before leaving their place ofmanufacture.
Tubing, tube bundles and fittings shall be rated for a maximum working pressure of 20.7MN/m2.
5.11 Testing and Commissioning
The UCS and its associated equipment shall be tested and commissioned in several stagesduring manufacture, namely:
a) Testing of components at the manufacturers in accordance with this Specification andSupplier’s own specifications and test procedures.
8/17/2019 ELDS-DR-S-02005_01e (020812)
26/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 24 of 57Date: 24
th July 2012
b) Testing and commissioning of components at the Supplier’s works in accordance with thisSpecification and Supplier’s own specifications and test procedures, this shall include asa minimum:
Assembled DCC (ref. Appendix 1 of this Specification),
Assembled UIP (ref. Appendix 2 of this Specification),
Assembled Flotation Tank Wedge Release Cross-flow panel (ref Appendix 10 of thisSpecification),
Assembled Jacket Wedge Release Interface Panel (ref Appendix 10 of thisSpecification),
Assembled DCC, HPU, Umbilicals, UIP, flood/vent valves & associated tubing bundles,
Assembled DCC, instrumentation & cable systems.
c) Full integrate test and commissioning of the Jacket installed systems at the Jacketfabrication site. Note! As a minimum a fully integrated systems hydraulic pressure test shallbe carried out to 31.05 MN/m2 (1.5 x the maximum system operating pressure) for aminimum of 30 minutes. The test pressure and temperature shall be chart recorded.
Pressure charts shall show the release of pressure at completion of pressure tests, andthe ambient temperature.
5.12 Flushing and Cleaning
All hydraulic components shall be flushed and cleaned to BS ISO 4406:1999, SolidContaminant Code No. 18/12, or equivalent, prior to leaving the Supplier’s works. Additionalflushing and cleaning of the assembled systems shall also be carried out at the fabrication siteto maintain the specified level of cleanliness.
8/17/2019 ELDS-DR-S-02005_01e (020812)
27/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 25 of 57Date: 24
th July 2012
6.0 DATA REQUIREMENTS
6.1 General
All drawings and documents shall be in presented in the English language and in the SI units
of measurement, except for pipe nominal diameters and any associated valves and flangesizes, which shall be in inches.
6.2 SDRL
The Supplier shall supply drawings and documents in accordance with the requirements of theSDRL.
The schedule indicated on the SDRL shall be subject to review and agreement with thePurchaser during the Supplier kick-off meeting.
6.3 Reports and Acceptance Certi ficates
Supplier shall prepare a report on the tests and the results of the tests, which shall be includedin the ‘Manufacturing Record Books’.
8/17/2019 ELDS-DR-S-02005_01e (020812)
28/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 26 of 57Date: 24
th July 2012
7.0 PACKING AND PRESERVATION FOR TRANSPORT
7.1 General
Generally the preservation, preparation for shipment and transportation supports shall be inaccordance with Project specification, ELDS-DR-G-00038.
The Supplier shall submit for Purchaser’s approval a detailed packing and preservationprocedure that addresses the protection, preservation, packaging and shipment marking foreach item in the scope of supply.
Any Item which is subject or liable to distortion during transportation shall be suitably bracedto protect against damage during land and sea voyage, namely it shall be designed towithstand maximum vertical force of 1.75g and horizontal force of 1.0g. Temporary bracingrequired for sea transportation shall be avoided but if necessary details shall be provided ona ‘Foundation Loading Diagram’. Such temporary bracing shall be provided by the Supplier.
Fitted equipment shall only be removed from the system for shipment when specialprotection is required, or where equipment would be vulnerable to damage in transit. Anysuch removal shall require the prior agreement of the Purchaser.
7.2 Preservation
All preservation and packaging shall be suitable for outdoor storage in winter marineconditions for 12 months from shipment date.
All external unpainted surfaces of equipment shall be coated with a Purchaser approvedsolvent-removable preservation wax/paint on completion of testing.
Any machined surfaces and fasteners shall be coated with a suitable corrosion protection
compound.
7.3 Packaging for Transport
All equipment must be preserved and packaged with sufficient protection to prevent damageduring handling, shipping, and storage for a minimum period of 12 months outdoors at theJacket fabrication site. All equipment and materials shall be properly protected from damagefor sea freight.
The Supplier shall propose the methods and submit detailed procedures for approval thataddress the protection, preservation, packaging and shipment marking for each item in thescope of supply.
All external unpainted surfaces of equipment shall be coated with a Project approved solventremovable preservation wax/paint on completion of testing.
Load test certificates shall be shipped with all lifting equipment, spreader bars, slings andshackles.
Due attention shall be given to the identification, tagging and packaging of all loosecomponents and separate systems. Where necessary, silica gel bags, with tags, shall beincluded in the packing to prevent corrosion whilst in storage.
Supplier shall prepare a location plan, identifying the separate shipped components and
systems and their box numbers. This plan shall be mutually agreed upon between Supplierand Purchaser. The packing shall be clearly marked to identify the Destination, PurchaseOrder Number, Supplier and list of contents.
8/17/2019 ELDS-DR-S-02005_01e (020812)
29/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 27 of 57Date: 24
th July 2012
8.0 QUALITY MANAGEMENT
8.1 General
In addition to the following requirements, Supplier shall refer to Company Specification forQuality management documentation for this package, ELDS-DR-Q-00007, ELDS-DR-Q-00008and ELDS-DR-Q-00013.
8.2 Quality Management
The Supplier shall operate a Quality management system commensurate with the equipmentand services provided. The system should generally satisfy the requirements of IS0 9000 orother appropriate internationally recognised standard. The Supplier’s system shall specificallyinclude provision for the management of Sub-suppliers.
The Supplier shall nominate a representative to be the focal point of all quality issues for thePurchaser’s quality representative.
At the bid clarification stage, the Purchaser will discuss and agree with the Supplier the extentand levels of traceability and certification.
8.3 Suppliers Inspection and Test Plan
The Purchaser intends to ensure, where possible, that all necessary testing of equipment iscarried out at the Supplier’s works in order to minimise construction site testing. Purchasershall witness testing in accordance with an agreed test schedule. To facilitate the identificationof Purchaser involvement, the Supplier shall submit a comprehensive Inspection and TestPlan (ITP), upon which the Purchaser will identify their review and witness requirements.
The plan shall also include for the requirements of the Independent Certifying Unit (ICU) or
Third Party Inspection Authority for verification of Supplier design, fabrication and test. TheICU or the Third Part Authority requirements shall be indicated by ‘HOLD’ to be advised laterwhere deemed necessary by the ICU or Authority.
The ITP shall include all inspection and testing activities carried out at both the Supplier’s andSub-suppliers works and shall make reference to all relevant testing procedures, controldocuments and resulting records and reports.
8.4 Certi fication Documents
The Supplier shall supply manufacturing record books containing all material certificates, fullycatalogued and indexed NDT test records, mechanical test certificates, welding qualification
certificates, heat treatment certificates, hydrostatic test certificates and other certification inaccordance with the requirements of the SDRL.
Further to the above, the Supplier shall adhere to Company Specifications for MaterialCertification ELDS-DR-G-00006 and ELDS-DR-G-00037 and Instruction for Concessionrequests ELDS-DR-G-00042.
8.5 Weight Data
The Supplier shall comply with the Purchaser’s weight control requirements and shall supplyweight data sheets for all equipment.
8/17/2019 ELDS-DR-S-02005_01e (020812)
30/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 28 of 57Date: 24
th July 2012
9.0 EXPORT CONTROLS REQUIREMENTS
This document/software contains technical information that may be subject to U.S. and/or U.K.and EU export control regulations. It may not be exported except as authorised underapplicable U.S., U.K. and EU export control requirements.
8/17/2019 ELDS-DR-S-02005_01e (020812)
31/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 29 of 57Date: 24
th July 2012
APPENDIX 1 – DECK CONTROL CENTRE (DCC)
1.0 INTRODUCTION
This Appendix specifies the detailed requirements for the supply of the DCC, which shallinclude the following as a minimum:
Support frame and protection structure,
Controls and instrumentation to fulfil the requirements for upending and set down ofthe Jacket,
Primary hydraulic & electrical Umbilical Interfaces,
E&I interfaces,
Lifting lugs/padeyes, including all shackles, chains, slings and equipment required tosafely lift and transport the DCC.
2.0 DESIGN
The following condition shall apply for the design of the DCC:
2.1 Lifting
The Supplier shall design and furnish all lifting padeyes and slings for lifting and transportationto/around the fabrication site and to/from the installation vessel. One sets of slings shall besupplied.
3.0 FABRICATION
The DCC shall be fabricated in accordance with Project specification number ELDS-DR-K-00005.
4.0 CONTROL PANEL
4.1 DCC Main Control Panel
The DCC shall be a PLC based control system and contain an HMI which offers a manualoperating and monitoring facility. The layout of the display shall be arranged to mimic thedisposition of the flood and vent valves on the Jacket.
A steel-mounting panel shall be provided, of adequate strength. The panel shall be designedto be readily accessible for general maintenance and emergency repair.
The DCC shall be 316 stainless steel and supplied unpainted.
The panel facia must be protected at all times while not in use by covers to avoid damage tothe HMI.
5.0 HYDRAULIC SYSTEM
The primary hydraulic Umbilical and HPU shall provide the hydraulic power to the UIP foroperating the flood and vent valves in all the Jacket leg floodable compartments.
Hydraulic fluid shall be MacDermid Canning Oceanic HW 540E or Company approvedequivalent.
8/17/2019 ELDS-DR-S-02005_01e (020812)
32/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 30 of 57Date: 24
th July 2012
The Supplier shall select the size of hydraulic tube within the DCC; however, the minimuminternal diameter of delivery supply lines shall be 8mm.Tube fittings shall also bemanufactured from 316 stainless steel.
Note: Test pressures are 1.5 x the maximum working pressures.
6.0 ELECTRICAL SYSTEMElectrical power shall be required for the following:
DCC,
PMCLaptop (Energising Sensors).
UIP (I/O Modules + SOV’s)
The requirements shall be met by a power supply unit driven from the fabrication site mainsduring the onshore phase and by the IV during the offshore installation phase (via the powersupply jumper cable(s)).
6.1 DCC Power Supply Unit
A fully enclosed, rugged, modular regulated power supply unit shall be provided, complete withinput/output switches, indicating lamps and fuses, to the following requirements:
Input voltage - 110Vac / 240 Vac +/- 10%
Input frequency - 50Hz +/- 4%
Output current - 15A
6.2 Fabrication Site Power Supply
The power supply to the DCC shall be run from the fabrication power supply (via jumpercable(s)). The power supplies available on site are:
Single phase, 3 wire, 220 volts, 50 Hz and,
380V, 3 phase, 50 Hz.
A fused mains isolator switch, located in the DCC, shall be provided to accommodate thepower supply jumper hoses and primary electrical Umbilical connections jumper hoses.
All earth connections shall be taken to a common point and secured to the DCC by approved
methods.6.3 Installation Vessel Power Supply
The power supply to the DCC shall be run from the IV power supply (via jumper cable(s)). Thepower supplies available on the IV are:
48V AC, 32A single phase 60H
220V AC, 15A single phase 60 H
440 V AC, 250A three phase 60 H
A fused mains isolator switch, located in the DCC, shall be provided to accommodate thepower supply jumper hoses and primary electrical Umbilical connections jumper hoses.
All earth connections shall be taken to a common point and secured to the DCC by approvedmethods.
8/17/2019 ELDS-DR-S-02005_01e (020812)
33/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 31 of 57Date: 24
th July 2012
7.0 PROTECTIVE COATING
The DCC shall be protected and coated in accordance with specification number ELDS-DR-K-00007, General Coating Specification for Fabrication Sites.
8.0 TESTING
The DCC shall be fully tested and commissioned as a stand-alone unit prior to hook-up to thesystem equipment. This shall include the following as a minimum:
8.1 Flushing
All hydraulic equipment shall be flushed and cleaned in accordance with the requirements ofsection 5.11 of this Specification.
After cleaning, the systems shall be sealed off to prevent any further ingress of particulates.
8.2 Pressure Testing
All hydraulic systems shall be pressure tested to 31.05 MN/m2 (1.5 x their maximum operatingpressure) for a minimum of 20 minutes. The test pressure and ambient temperature shall be
chart recorded.
Relief valves may be set higher or removed for these tests. All vulnerable instruments mayalso be removed or isolated.
8.3 Electrical Testing
The test procedure for the DCC E&I systems shall cover as a minimum the items below:
Complete systems installation check including wiring insulation and continuity,
Verification of correct operation of the mains power supply unit when energising allelectrical systems,
Complete functional check of all electrical equipment.
9.0 DATA SHEETS
The following equipment data sheets shall be provided as a minimum:
DCC Components
HPU Components
UIP Components
Hydraulic Actuators
Flood & Vent Valves Umbilicals
Pressure Transmitters
Valve Position Transmitters
Solenoid Valves
Quick Connects
Electrical Connectors
8/17/2019 ELDS-DR-S-02005_01e (020812)
34/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 01 Page 32 of 57Date: 25
th October 2011
APPENDIX 2 – UMBILICAL INTERFACE PANELS (UIP)
1.0 INTRODUCTION
This Appendix defines the requirements for the supply of the UIP. The UIP shall be located atthe top of the Jacket structure to allow connection of the Jacket hydraulic tube bundles and
electrical cables with the primary electro-hydraulic Umbilicals transferred from the IV and shallinclude the following, as a minimum:
Support frame and protection structure,
Support interface to Jacket structure,
Primary hydraulic & electrical Umbilical interfaces; quick connects/disconnects,
Flood/vent valve interface penetration plate/connections,
Umbilical strain member connection(s),
Panel facia,
Thermal expansion facility for flood and vent valves, Hydraulic 316 stainless steel pipe work and fittings,
Lifting lugs/padeyes, including all shackles, chains, slings and equipment required tosafely lift and transport the UIP.
The Umbilical interface panel fascias shall be 316 stainless steel and supplied unpainted.
The panels are depicted schematically on Project drawing number:
ELDS-DR-S-00099-001
2.0 DESIGN
2.1 Location
The Jacket UIPs shall be located at the top of the Jacket (El +21.000) and will require manualintervention for connecting the primary electro-hydraulic Umbilicals transferred from the IV.The UIPs shall include the following:
The hydraulic connections shall be made using Holmbury Ltd PTS Series self sealingquick connect/disconnect couplings, which shall be labelled/colour coded to ensureconnection compatibility.
The electrical connections shall be made using Subsea rated plug in type electricalconnectors, which shall be labelled/colour coded to ensure connection compatibility.
2.2 Launch Forces
During the Jacket launch the velocities shall be as shown in Appendix 8 of this Specification.These velocities shall be applied in the most critical direction for the design of the Jacket andFlotation Tanks. A slam coefficient of 3 shall be used to compute the resultant forces.
2.3 Transportation Criteria
The maximum accelerations at the Jacket and Flotation Tanks shall be as shown in Appendix8 of this Specification.
8/17/2019 ELDS-DR-S-02005_01e (020812)
35/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 33 of 57Date: 24
th July 2012
2.4 Monitoring Cables
Two monitoring cables shall be supplied in order to monitor the Jacket & Flotation Tankcompartments pressures and flood/vent valve positions after Jacket load-out and prior toJacket launch.
The cables shall remain connected to the UIPs after Jacket load-out and during transportation
of the Jacket to the offshore site. The cables shall provide the monitoring data whenconnected to either the DCC or the PMC.
3.0 TESTING
The UIP shall be fully tested and commissioned as a stand-alone unit prior to hook-up to thesystem equipment. This shall include the following as a minimum:
3.1 Pressure Testing
All hydraulic systems in the UIP shall be pressure tested to 31.05 MN/m2 (1.5 x their maximumoperating pressure) for a minimum of 60 minutes. The test pressure and ambient temperatureshall be chart recorded.
Relief valves may be set higher or removed for these tests. All vulnerable instruments mayalso be removed or isolated.
A test is not required on accumulators provided the original manufacturers test certificates isvalid.
3.2 Electrical Testing
The test procedure for the UIP E&I connections shall cover as a minimum the items below:
Complete systems installation check including wiring insulation and continuity,
Complete functional check of all electrical equipment.
8/17/2019 ELDS-DR-S-02005_01e (020812)
36/59
ELDS-DR-S-02005 ELDFISK II 2/7S JACKET UPEND CONTROLSYSTEM SPECIFICATION
Rev: 05 Page 34 of 57Date: 24
th July 2012
APPENDIX 3 – HYDRAULICALLY ACTUATED BALL VALVES
1.0 INTRODUCTION
This Appendix specifies the detailed requirements for the supply of hydraulically actuated floodand vent valves.
The actuated valves shall consist of either: 6” double acting hydraulic full bore ball valves with no spring assist.
4” and 6” single acting hydraulic full bore ball valves with spring assist to ‘closed’position.
All the actuated valves shall be suitable for operation in 75m depth of seawater and shall beoperable in any orientation whilst the Jacket is being rotated through 90º. All the valves shallbe bubble tight in the shut-off condition.
2.0 DETAILED SPECIFICATION
2.1 Manufacturer
Valves supplier to confirm
Actuators supplier to confirm
2.2 Valve Body
Body and Port Sizes - 100mm (4”) and 150mm (6”) –Both sizes full bore.
Type - Trunnion mounted ball valve.
Body and Fastening Materials - Suitable for immersion in seawater.
End Connections - Flanged to ANSI B16.5, Class150, Raised Face, on both ends.
Dimensions - Flange face to face dimensions toconform to API 6D.
2.3 Valve TrimBall and Stem - Suitable for use in seawater.
Stem Packing Suitable for immersion in 75mof seawater outside the valve with0.05 MN/m2 inside the valve.
Seat - Suitable for seawater and Biocide(Refer to specification No: ELDS-DR-K-00008)
2.