Upload
lecong
View
215
Download
2
Embed Size (px)
Citation preview
Endako’s History• 1927 – Deposit was discovered by two local hunters
• 1962 – August, Placer Development started diamond drill program
• 1964 – March, Clearing and construction of the site began
• 1965 – May, Construction Completed – Capital Cost $22 million
• 1965 – June 8th, Endako’s Grand Opening
• 1965 -1981, Various expansion stages from 16 ktpd to 28 ktpd
• 1982 – 1986, milling portion was shut down, only Toll Roasting done
• 1997 – Endako was sold to Thompson Creek Mining Joint Venture
• 2006 – Blue Pearl Mining purchased 75% of Endako + 2 other TCM facilities, decides to keep Thompson Creek Name
• 2008 – Thompson Creek announces $373 million, 52ktpd Endako expansion
• 2009 – March, expansion placed on hold
• 2009 – Fall, Endako expansion Re-Start
Cumulative Mining History
• Mined 360 tonnes of ore, 290 tonnes of waste
• Produced 500+ million pounds of Oxide
• Provided 34.5 million man hours of employment
• Paid in Excess of $430 million in wages
Historical Wage Rates
• 1966 Labourer $2.32/hr
• 1966 Trades Person $3.29/hr
• 2010 Labourer $21.00/hr
• 2010 Trades Person $33.00/hr
• $498 Million dollar budget• 52,000 tonne per day mill
– 36’ SAG and 2 x 22’Ball Mills– 14 x OK160 Rougher/Scavenger flotation cells– 3 x M1000 Isamills for regrinding– 5 stages of column cleaner flotation
• 15 million lbs per year of Mo Production– Target 92% Mill operating time– Lower maintenance costs and downtime– Higher 79%recovery via better control and finer grinds– 18 year mine life at $12/lb Mo
Expansion Highlights
Pebble Crusher/SAG Feed Stockpile
• 100,000 tpd live load
• 360,000 tpd total load
• Raptor 1100 pebble crusher
Rougher/Scavenger Flotation
• 2 Banks
• 14 x OK 160’s
• 24 min flotation time
• 200 micron grind
• 79% recovery
Cleaning Circuit
• 5 Stages of Column Flotation, with Mechanical scavengers
• Upgrading to 92% MoS2
• Not purchased yet
Current Contractors On site
• Sharp Construction – Earthworks
• Formula Contractors – Pre Eng Mill Building Erection
• CIF – Mill Building Foundation Concrete
• K2 Electric – Temporary Power Work
• WD McIntosh – Site Surveying
• PNG – Natural Gas line work
• Hatch Engineering – EPCM contractor
• Other local labour, catering, general support
Project Status
• Construction and Engineering is ramping up
• Price of Molybdenum is doing well at +$17/lb
• Large experienced owners team
• Project completion expected mid 2011
Endako’s Reclamation and Environmental Highlights
• Endako’s has been spending close to $500,000 / yr on Environmental Work.
• Regular monitoring
• Re-vegetation
• Education