Upload
info-esha
View
213
Download
0
Tags:
Embed Size (px)
DESCRIPTION
http://www.esha.be/fileadmin/esha_files/documents/workshops/hidroenergia/EP_1_Fitzgerald.pdf
Citation preview
Hidroenergia 2006 – Crieff, Scotland
Gerard Brendan Fitzgerald
Dr. J. Prendergast & Mr. C. O’Donoghue
(School of Engineering)
Project Title:
“The Analysis of Fresh Water Rivers
as an Alternative source of Energy
in Remote Areas of Ireland”
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Presentation Contents
• Introduction
• Overview of Small-Scale Hydropower (SHP)
• Environmental aspects of SHP
• Developing SHP in Ireland
• Case Studies
• Conclusions
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Introduction
• Why do we need Small Scale Hydropower?– Ireland imported 87% of its energy requirements in 2002
– Need to diversify fuel mix to ensure security of supply
– Electricity demand is constantly increasing (193MW/year)
– Gross electricity consumption from hydropower only 2.35% in 2004
– Increased need for flexible plant according to the Transmission System Operator of Ireland
“On target to achieve 13.2% of power from RE sources by 2010”
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Hidroenergia ‘06 Gerard Brendan Fitzgerald
SHP Resource Distribution
• Installed capacity 29MW (schemes <10MW)
• Ireland has potential for further 38MW (1997 ESBI report)
• Over 50% of this is located in South West
• Locating power supply close to consumers
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Overview of Hydropower
• Focus on “Run-of-River” hydro generation
• Requires little or no damming of river
• Ensures flow regime is protected• Small civil works• Highly efficient, predictable
resource (90% Efficiency)• Long lasting, reliable technology
(50 years on average)
10kW – 100kWMicro
100kW – 1MWMini
1MW – 10MWSmall
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Potential Impacts of SHP
• Impacts During Construction– Temporary diversion of Rivers– Use of Excavators for earth moving
• Impacts During Operation– Biological Impacts (local flora and fauna)– Landscape Impacts– Visual & Sonic Impacts – Recreational Impacts
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Environmental Integration of SHP
• Scheme Aesthetics– Landscaping and vegetation– Interred Penstock– Underground Powerhouse
• Noise Reduction– Acoustic Insulation of Powerhouse & Turbine– Internal noise levels can be reduced to 70dBA
• Material Management– Trash racks remove waste material from waterways
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Environmental Integration of SHP
• Biological Protection– Reserved/Compensation Flow
• Central Fisheries Board river categorisation – Fish passes
• Behavioural Guidance System (Downstream fish)• Fish ladders (Upstream migrants)
– Fish friendly turbines• Reduce fish injury and mortality
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Developing SHP in Ireland
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Case Studies
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Case Study 1: Old Mill Site
• Derrymore, Co. Kerry
• Derelict Grain Mill
• Existing Weir
• On a Category 1 River
• No fish movements
• Natural Lake (Storage)
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Case Study 1: Old Mill Site (contd.)
• Technical Data– Mean Flow = 0.2 m3/s– Gross Head ≈ 96 m
• Potential Install Capacity 121kW
• Annual Energy Output 659MWh (RETScreen Software Package)
• Potential to supply 143 homes
• Low Environmental Impact
N
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Case Study 2: Multipurpose SHP
• Blennerville, Co. Kerry
• Water Supply Scheme
• Existing Infrastructure:
Intake and Weir
• No known fish movements
• Potential to include SHP
on water network
Intake
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Case Study 2: Multipurpose Scheme (contd.)
• Technical Data– Mean Flow ≈ 0.1 m3/s– Gross Head ≈ 60 m
• Potential Install Capacity 24kW
• Annual Energy Output 141MWh
• Potential to Supply 30 homes with water & electricity
• Low Environmental Impact
N
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Financial Evaluation – Old Mill Site
€ 90,188Contingencies
€ 40,000Connection costs
€ 128,850Turbine & Generator
€ 89,000Penstock
€ 599,770Civil Works
€ 51,700Initial Design Costs
Total Estimated Cost of Development = € 999,508
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Financial Evaluation – Old Mill Site (contd.)
25Years to Positive Cash Flow
8.6 %Internal Rate of Return
€ 134, 189Net Present Value (Discount Rate 7.5%)
7.2 cents/kWhGovernment supported tariff (ReFIT)
• Old Mill redevelopment financially feasible
• Large revenue following ‘break even’ period
• Level of risk is high for a long term investment
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Financial Evaluation – Multipurpose Scheme
€ 22,851Contingencies
€ 28,000Connection costs
€ 44,908Turbine & Generator
€ 58,500Penstock
€ 81,285Civil Works
€ 17,700Initial Design Costs
Total Estimated Cost of Development = € 253,244
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Financial Evaluation – Multipurpose Scheme
24Years to Positive Cash Flow
9.3 %Internal Rate of Return
€ 99, 815Net Present Value (Discount Rate 7.5%)
7.2 cents/kWhGovernment supported tariff (ReFIT)
• Multipurpose scheme development financially feasible
• Good potential as a long term investment
Hidroenergia ‘06 Gerard Brendan Fitzgerald
Conclusions
• Both schemes are technically & financially feasible
• Further incentives needed for development of grid connected SHP schemes in Ireland
• Need to streamline planning to reduce delays
• Transparency with regard to grid connection costs is required
• For hydro to grow, public acceptance is one of the most important issues
Thank you