Upload
marx0506
View
247
Download
5
Embed Size (px)
DESCRIPTION
Final Account
Citation preview
4/6/2016 Final account - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Final_account 1/4
Register Sign in
Search
Designing Buildings WikiThe construction industry knowledge base
Home / news Site info / toolsProject plans Project activities Legislation and standards Industry context
Final account
Construction contracts generally provide some mechanism for the final payment to be made to
the contractor on completion of the works described in the contract. Generally this payment will
be made at the end of the defects liability period providing that all patent defects have been
rectified.
Preparing the final account is the process of calculating and agreeing any adjustments to the
contract sum (the amount originally set out in the contract to be paid to the contractor for
completion of the works) so that the amount of the final payment can be determined. The amount
of the final payment is then set out in the final certificate (or final statement). It is possible for the
final certificate to show that money is owed to the client, rather than due to the contractor.
Construction contracts may not specifically require the preparation of a final account, although
they generally do require the contractor to provide all documents necessary for the adjustment of
the contract sum within a specified time, and set out the time scale for and consequences of
issuing the final certificate.
The contract sum may need to be adjusted for a number of reasons, including:
Variations.Fluctuations.Prime cost sums.Provisional sums.Payments to nominated sub-contractors or nominated suppliers.Statutory fees.Payments relating to the opening-up and testing of the works.Loss and expense.Liquidated and ascertained damages.Contra claims imposed as a result of the contractor's operations (such as a third-party claimresulting from contractor negligence or contractual breach, for example, flooding a neighbour'sproperty).The release of any remaining retention.
Agreeing the final account can be a complicated, time consuming and adversarial process, often
resulting in disputes. The process can be made easier if adjustments to the contract sum are
agreed as the project progresses rather than saving them up for the end. It is also beneficial if the
client's quantity surveyor and the contractor's quantity surveyor work together on drafts of the final
account before agreement it sought. It is preferable that a draft copy of the final account is signed
off by the contractor as an 'in full and final settlement' prior to issue.
Agreement of the final account will allow the contract administrator to issue the final certificate.
The final certificate is conclusive that all patent defects have been remedied, all adjustments to
the contract sum have been agreed and all claims settled. Latent defects may still become
apparent after completion of the contract and these may give rise to action for damages, for
breach of contract or negligence.
Where proceedings have begun in relation to a dispute, the conclusiveness of the final certificate
is subject to the findings of those proceedings.
Share Follow
Create an article
Related articles
Contract sum.
Contract sum analysis.
Cost consultant.
Cost plans.
Cost value reconciliation.
Defects.
Final certificate.
Fluctuations.
Featured articles
Cycling and walking plan
Department for Transport's plans to turn the
UK into a 'cycling and walking nation' are
"frankly embarrassing" according to experts.
Unusual building design of the week
Last edited 03 Feb 2016See full history
4/6/2016 Final account - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Final_account 2/4
Share Add a comment Send us feedback
In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication,
arbitration or other dispute resolution procedures may then be necessary to resolve the dispute.
The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, they must give
notice to the contractor of the amount they intend to pay and the basis for its calculation (a 'pay
less notice' - see Housing Grants, Construction and Regeneration Act for more information).
Find out more
Related articles on Designing Buildings Wiki
Contract sum.Contract sum analysis.Cost consultant.Cost plans.Cost value reconciliation.Defects.Final certificate.Fluctuations.Housing Grants, Construction and Regeneration Act.Liquidated damages.Loss and expense.New Rules of Measurement.Outturn cost.Pre-tender estimate.Prime cost sums.Provisional sums.Retention bond.Scott schedule.Tender pricing documentVariations.Whole-life costs.
'La Lavadora' - the Washing Machine building -
of Santa Fe, Mexico City.
World's longest floating bridge
State Route 520 Bridge over Lake Washington
is officially opened.
BIM mandate
BIM is now mandatory for all centrally-
procured public projects. Check out our
resources to help you adapt.
Virtual reality in construction
The company that is helping introduce virtual
reality technology to construction.
Building services specification
New edition of BSRIA guide BG56 published -
Model Format for Building Services
Specifications.
Zaha Hadid
4/6/2016 Final account - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Final_account 3/4
A profile of the late Zaha Hadid.
SSE Arena
The SSE Arena celebrates 10 years since it
was refurbished. Here is the story behind one
of London's most iconic entertainment venues.
Building of the week - Chrysler Building
The classic Art Deco skyscraper that
frequently tops polls as the most popular in
the world.
New York Horizon
4/6/2016 Final account - Designing Buildings Wiki
http://www.designingbuildings.co.uk/wiki/Final_account 4/4
© Designing Buildings Ltd. 2016 About Help Privacy Policy T&Cs Contact Feed Report Abuse Press
The winners of first place in the eVolo
Skyscraper Competition propose the radical
futuristic transformation of Central Park.
U+I Think event with John McDonnell MP
Labour's Shadow Chancellor makes plea for
further engagement with the land development
sector and the creation of more "beautiful and
exciting" urban spaces.
For more news, go to the home page.