4
4/6/2016 Final account - Designing Buildings Wiki http://www.designingbuildings.co.uk/wiki/Final_account 1/4 Register Sign in Search Designing Buildings Wiki The construction industry knowledge base Home / news Site info / tools Project plans Project activities Legislation and standards Industry context Final account Construction contracts generally provide some mechanism for the final payment to be made to the contractor on completion of the works described in the contract. Generally this payment will be made at the end of the defects liability period providing that all patent defects have been rectified. Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum (the amount originally set out in the contract to be paid to the contractor for completion of the works) so that the amount of the final payment can be determined. The amount of the final payment is then set out in the final certificate (or final statement). It is possible for the final certificate to show that money is owed to the client, rather than due to the contractor. Construction contracts may not specifically require the preparation of a final account, although they generally do require the contractor to provide all documents necessary for the adjustment of the contract sum within a specified time, and set out the time scale for and consequences of issuing the final certificate. The contract sum may need to be adjusted for a number of reasons, including: Variations. Fluctuations. Prime cost sums. Provisional sums. Payments to nominated sub-contractors or nominated suppliers. Statutory fees. Payments relating to the opening-up and testing of the works. Loss and expense. Liquidated and ascertained damages. Contra claims imposed as a result of the contractor's operations (such as a third-party claim resulting from contractor negligence or contractual breach, for example, flooding a neighbour's property). The release of any remaining retention. Agreeing the final account can be a complicated, time consuming and adversarial process, often resulting in disputes. The process can be made easier if adjustments to the contract sum are agreed as the project progresses rather than saving them up for the end. It is also beneficial if the client's quantity surveyor and the contractor's quantity surveyor work together on drafts of the final account before agreement it sought. It is preferable that a draft copy of the final account is signed off by the contractor as an 'in full and final settlement' prior to issue. Agreement of the final account will allow the contract administrator to issue the final certificate. The final certificate is conclusive that all patent defects have been remedied, all adjustments to the contract sum have been agreed and all claims settled. Latent defects may still become apparent after completion of the contract and these may give rise to action for damages, for breach of contract or negligence. Where proceedings have begun in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings. Share Follow Create an article Related articles Contract sum. Contract sum analysis. Cost consultant. Cost plans. Cost value reconciliation. Defects. Final certificate. Fluctuations. Featured articles Cycling and walking plan Department for Transport's plans to turn the UK into a 'cycling and walking nation' are "frankly embarrassing" according to experts. Unusual building design of the week Last edited 03 Feb 2016 See full history

Final Account - Designing Buildings Wiki

Embed Size (px)

DESCRIPTION

Final Account

Citation preview

Page 1: Final Account - Designing Buildings Wiki

4/6/2016 Final account - Designing Buildings Wiki

http://www.designingbuildings.co.uk/wiki/Final_account 1/4

Register Sign in

Search

Designing Buildings WikiThe construction industry knowledge base

Home / news Site info / toolsProject plans Project activities Legislation and standards Industry context

Final account

Construction contracts generally provide some mechanism for the final payment to be made to

the contractor on completion of the works described in the contract. Generally this payment will

be made at the end of the defects liability period providing that all patent defects have been

rectified.

Preparing the final account is the process of calculating and agreeing any adjustments to the

contract sum (the amount originally set out in the contract to be paid to the contractor for

completion of the works) so that the amount of the final payment can be determined. The amount

of the final payment is then set out in the final certificate (or final statement). It is possible for the

final certificate to show that money is owed to the client, rather than due to the contractor.

Construction contracts may not specifically require the preparation of a final account, although

they generally do require the contractor to provide all documents necessary for the adjustment of

the contract sum within a specified time, and set out the time scale for and consequences of

issuing the final certificate.

The contract sum may need to be adjusted for a number of reasons, including:

Variations.Fluctuations.Prime cost sums.Provisional sums.Payments to nominated sub-contractors or nominated suppliers.Statutory fees.Payments relating to the opening-up and testing of the works.Loss and expense.Liquidated and ascertained damages.Contra claims imposed as a result of the contractor's operations (such as a third-party claimresulting from contractor negligence or contractual breach, for example, flooding a neighbour'sproperty).The release of any remaining retention.

Agreeing the final account can be a complicated, time consuming and adversarial process, often

resulting in disputes. The process can be made easier if adjustments to the contract sum are

agreed as the project progresses rather than saving them up for the end. It is also beneficial if the

client's quantity surveyor and the contractor's quantity surveyor work together on drafts of the final

account before agreement it sought. It is preferable that a draft copy of the final account is signed

off by the contractor as an 'in full and final settlement' prior to issue.

Agreement of the final account will allow the contract administrator to issue the final certificate.

The final certificate is conclusive that all patent defects have been remedied, all adjustments to

the contract sum have been agreed and all claims settled. Latent defects may still become

apparent after completion of the contract and these may give rise to action for damages, for

breach of contract or negligence.

Where proceedings have begun in relation to a dispute, the conclusiveness of the final certificate

is subject to the findings of those proceedings.

Share Follow

Create an article

Related articles

Contract sum.

Contract sum analysis.

Cost consultant.

Cost plans.

Cost value reconciliation.

Defects.

Final certificate.

Fluctuations.

Featured articles

Cycling and walking plan

Department for Transport's plans to turn the

UK into a 'cycling and walking nation' are

"frankly embarrassing" according to experts.

Unusual building design of the week

Last edited 03 Feb 2016See full history

Page 2: Final Account - Designing Buildings Wiki

4/6/2016 Final account - Designing Buildings Wiki

http://www.designingbuildings.co.uk/wiki/Final_account 2/4

Share Add a comment Send us feedback

In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication,

arbitration or other dispute resolution procedures may then be necessary to resolve the dispute.

The final certificate is then only conclusive in relation to matters that are not disputed.

If the client intends to pay a different amount from that shown on the certificate, they must give

notice to the contractor of the amount they intend to pay and the basis for its calculation (a 'pay

less notice' - see Housing Grants, Construction and Regeneration Act for more information).

Find out more

Related articles on Designing Buildings Wiki

Contract sum.Contract sum analysis.Cost consultant.Cost plans.Cost value reconciliation.Defects.Final certificate.Fluctuations.Housing Grants, Construction and Regeneration Act.Liquidated damages.Loss and expense.New Rules of Measurement.Outturn cost.Pre-tender estimate.Prime cost sums.Provisional sums.Retention bond.Scott schedule.Tender pricing documentVariations.Whole-life costs.

'La Lavadora' - the Washing Machine building -

of Santa Fe, Mexico City.

World's longest floating bridge

State Route 520 Bridge over Lake Washington

is officially opened.

BIM mandate

BIM is now mandatory for all centrally-

procured public projects. Check out our

resources to help you adapt.

Virtual reality in construction

The company that is helping introduce virtual

reality technology to construction.

Building services specification

New edition of BSRIA guide BG56 published -

Model Format for Building Services

Specifications.

Zaha Hadid

Page 3: Final Account - Designing Buildings Wiki

4/6/2016 Final account - Designing Buildings Wiki

http://www.designingbuildings.co.uk/wiki/Final_account 3/4

A profile of the late Zaha Hadid.

SSE Arena

The SSE Arena celebrates 10 years since it

was refurbished. Here is the story behind one

of London's most iconic entertainment venues.

Building of the week - Chrysler Building

The classic Art Deco skyscraper that

frequently tops polls as the most popular in

the world.

New York Horizon

Page 4: Final Account - Designing Buildings Wiki

4/6/2016 Final account - Designing Buildings Wiki

http://www.designingbuildings.co.uk/wiki/Final_account 4/4

© Designing Buildings Ltd. 2016 About Help Privacy Policy T&Cs Contact Feed Report Abuse Press

The winners of first place in the eVolo

Skyscraper Competition propose the radical

futuristic transformation of Central Park.

U+I Think event with John McDonnell MP

Labour's Shadow Chancellor makes plea for

further engagement with the land development

sector and the creation of more "beautiful and

exciting" urban spaces.

For more news, go to the home page.