1 WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman Financial Model Inputs Financial Model Inputs (I (I-405 Express Toll Lanes) 405 Express Toll Lanes)

Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

1WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Financial Model InputsFinancial Model Inputs(I(I--405 Express Toll Lanes)405 Express Toll Lanes)

Page 2: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

2WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

FY 2015 FY 2020 FY 2025 FY 2030 FY 2035 FY 2040 FY 2045 FY 2050 FY 2055 FY 2060 FY 2065 FY 2070

Revenue AssumptionsU

S$ M

illio

ns (N

omin

al)

P3 Constructionscenario allowsearly opening andcommencementof tolling in FY2020.

PSC Construction scenario allowscommencement of tolling in FY 2022

For the 405 the same “Base” caserevenue profile has been used forboth the P3 and PSC Models.

PSC Revenue Assumptions P3 Revenue Assumptions

Base Case Base Case

High Case

Low Case

Page 3: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

3WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

0

50

100

150

200

250

300

350

400

450

500

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Year

Initial Construction Costs Comparison

Total Traditional Delivery Initial Construction Costs Total P3 Delivery Initial Construction Costs

Traditional Delivery Total Initial Construction - $1,317MP3 Delivery Total Initial Construction - $1,116M

Identical Pre-construction costs forPreliminary Engineering (15% design)and Right of Way acquisition

Constructioncommences

Construction Costs

P3 Case assumes accelerated construction schedule

Page 4: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

4WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Construction Costs

$22 M $43 M $40 M$22 M $2 M $124 M

$432 M $432 M

-

50

100

150

200

250

300

350

400

450

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

P3 Delivery Initial Construction Costs

$22 M $43 M $40 M$22 M $2 M $54 M

$387 M $387 M

$265 M

$95 M

0

50

100

150

200

250

300

350

400

45020

13

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Traditional Delivery Initial Construction Costs

Initial Construction Costs Savings for the P3Delivery method are based on the ability ofthe private sector to complete constructionwithin 2.5 years instead of 5, reducing all timedependant costs such as Mobilization &Preparation and Traffic Control, and to alesser extent other costs such as Design

The private sector would have the ability tobulk purchase materials such as steel whichcould potentially provide significant savings .However, this has not been assumed for thisproject.

Right of Way and Tolling & ITScosts are assumed the same forboth forms of delivery

Total Initial Construction - $1,317M

Total Initial Construction - $1,116M

Page 5: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

5WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

RIGHT of WAYGRADING, DRAINAGE AND STOCKPILINGSTRUCTURESCEMENT CONCRETE PAVEMENTOTHER ITEMSTOLLING & ITS

DESIGNMOBILIZATION AND PREPARATIONWATERLINES, STORM AND SANITARY SEWERSASPHALT AND SURFACINGTRAFFIC CONTROLNON - BID COSTS 700 Level Items

0

50

100

150

200

250

300

350

400

450

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Year

I-405/SR 167 Express Toll LanesTraditional Delivery Initial Construction Costs

-

50

100

150

200

250

300

350

400

450

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Year

I-405/SR 167 Express Toll LanesP3 Delivery Initial Construction Costs

I-405/SR 167 Express Toll Lanes InitialConstruction Costs (Millions)

TraditionalDelivery

P3Delivery

DESIGN $57 $57RIGHT of WAY $72 $72MOBILIZATION AND PREPARATION $54 $27GRADING, DRAINAGE AND STOCKPILING $112 $108WATERLINES, STORM AND SANITARY SEWERS $14 $13STRUCTURES $239 $234ASPHALT AND SURFACING $74 $73CEMENT CONCRETE PAVEMENT $50 $49TRAFFIC CONTROL $51 $26OTHER ITEMS* $340 $257NON - BID COSTS 700 Level Items** $220 $166TOLLING & ITS $35 $35

Total Construction Cost $1,317 $1,116* Other Items include Design, QAQC (15%), Guardrail , Signage otherminor i tems, Environmental mitigation like recon of wetlands, streamrestoration etc, differing site conditions

** Non Bid Costs include sales tax, construction engineering (WSDOTsown and sub costs to inspect during construction) contingency,stipend for fai led bidders

Construction Costs

Page 6: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

6WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Lifecycle Costs

220M in savings under P3 delivery Primarily due to x, y, z

$0

$20

$40

$60

$80

$100

$120

$140

$160

$180

$20020

15

2017

2019

2021

2023

2025

2027

2029

2031

2033

2035

2037

2039

2041

2043

2045

2047

2049

2051

2053

2055

2057

2059

2061

2063

2065

2067

2069

2011

USD

in M

illio

ns

Lifecycle Cost Comparison

Full DepthReconstruction of

PavementPavement

Resurfacingon a life cycle

of 10 years

Pavement Resurfacing &Tolling Equipment

Replacement to meetHandback Requirements

Tolling EquipmentReplacement on alifecycle of 8 years

Costs include Design, Resurfacing,Traffic Control and considerable

Tolling & ITS work

Traditional Delivery: Total Lifecycle Costs - $739MP3 Delivery: Total Lifecycle Costs - $517M

Page 7: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

7WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Lifecycle Costs

I-405/SR 167 Express Toll Lanes Lifecycle Costs (Millions) TraditionalDelivery P3 Delivery

Roadway Maintenance $67.43 $4.93Pavement Maintenance $85.22 $232.10Structures $0.00 $0.83Other Misc. Items $153.83 $0.00Tolling & ITS Maintenance $336.22 $265.49Design $54.79 $25.17Mobilization and Preparation $42.14 $30.20Engineering, Construction Mgmt. and Testing Fees $0.00 $39.21General Contingencies $0.00 $55.37

Total Over Concession $739.63 $664.43

$152.65 $237.03

• Overall, P3 costs are 10% lower in nominal (2011) dollars

• P3 case actually spends significantly more on pavement repairs

• Majority of savings are on Tolling and ITS ($71M or 10% of the total savings)

Page 8: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

8WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$1,000

$2,000

$3,000

$4,000

$5,000

$6,000

Traditional Delivery O&MCost

P3 Delivery O&M Costs

US$

Mill

ions

Operation & Maintenance Forecast Comparison

O&M Costs

Total Potential Savingthrough P3 Delivery (34%)

Traditional Delivery: Total O&M Costs - $5,178MP3 Delivery: O&M - $3,409M

Structures

Tolling & ITS

Enforcement

Roadway General Maintenance

Personnel

Pavement

Tolling Uncollectables

Facility Maintenance

G&A

Uncollectible tolls and enforcement aretypically overseen by Government, butpass-through of associated costs to theConcessionaire is common

Personnel costs are not captured undera single entry for the Traditional Deliveryapproach, but incorporated in each line

Greatest savings result fromTolling and ITS approach

Page 9: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

9WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

O&M Costs

Personnel

Structures

Pavement

Tolling & ITS

Tolling Uncollectables

Enforcement

Facility Maintenance

Roadway General Maintenance

G&A

I-405/SR 167 Express Toll Lanes O&M Costs(Millions)

TraditionalDelivery

P3 Delivery Comment

Personnel $0.00 $270.72WashDot personnel costs are incorporated within eachof the line items such as structures, pavements etc.

Structures $4.41 $45.82 Includes bridges, safety barriers and retaining wallsPavement $28.53 $20.95 Includes asphalt & concrete pavement

Tolling & ITS $2,897.57 $865.86 Includes annual maintenance, fixed back office costs,transaction based cost & credit card fees

Tolling Uncollectables $1,490.64 $1,489.52 For both delivery methods assumed 4.5% of RevenueEnforcement $574.68 $604.65 Assumed the same for both delivery methodsFacility Maintenance $0.00 $1.29Roadway General Maintenance $108.22 $29.46 Includes drainage, landscaping etc.G&A $83.12 $80.25 General & Administrative costs

Total Over 55 Years $5,187 $3,409

8%

1%

1%

25%

44%

18%

1%2%1%

56%29%

11%

0% 2%2%

Page 10: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

10WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Tolling & ITS Costs

* Tolling & ITS – Transaction based costsincorporate equipment maintenance,customer service center (CSC) and FixedBack Office Costs.

Equipment O&M

WSP Enforcement

Transaction Based CSC Costs

Fixed Back Office Costs

Credit Card Fees

Uncollectible Accounts

Tolling & ITS - Transaction based costs*

$474

$575

$605

$968

$599

$858

$662

$1,491

$1,490

$204

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

$4,000

$4,500

$5,000

Traditional Delivery Cost P3 Delivery Costs

US$

Mill

ions

I-405Tolling & ITS Comparison

Traditional Delivery: Total O&M Costs - $4,963MP3 Delivery: O&M - $2,960M

Total Potential Savingthrough P3 Delivery (40%)

Page 11: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

11WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Financial Model InputsFinancial Model Inputs(SR 509 Toll Lanes)(SR 509 Toll Lanes)

Page 12: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

12WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$50

$100

$150

$200

$250

$300

$350

FY 2012 FY 2017 FY 2022 FY 2027 FY 2032 FY 2037 FY 2042 FY 2047 FY 2052 FY 2057 FY 2062 FY 2067

Revenue AssumptionsU

S$ M

illio

ns (N

omin

al)

P3 Constructionscenario allowsearly opening andcommencementof tolling in FY2018.

PSC Construction scenario allowscommencement of tolling in FY 2020

PSC Revenue Assumptions P3 Revenue Assumptions

Base Case Base Case

High Case

Low Case

Page 13: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

13WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$50

$100

$150

$200

$250

$30020

15

2016

2017

2018

2019

2020

2011

US$

Mill

ions

Year

Initial Construction Costs Comparison

Total Traditional Delivery Initial Construction Costs Total P3 Delivery Initial Construction Costs

Traditional Delivery Total Initial Construction - $743MP3 Delivery Total Initial Construction - $716M

Identical Pre-construction costs forPreliminary Engineering (15% design)and Right of Way acquisition

Constructioncommences

Construction Costs

P3 Case assumes accelerated construction schedule

Page 14: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

14WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$66 M $108 M

$193 M $210 M

$166 M

0

50

100

150

200

250

30020

15

2016

2017

2018

2019

2020

2011

US$

Milli

ons

Traditional Delivery Initial Construction Costs

Construction Costs

Initial Construction Costs Savings for the P3Delivery method are based on the ability ofthe private sector to complete constructionwithin 2.5 years instead of 3, reducing all timedependant costs such as Mobilization &Preparation and Traffic Control, and to alesser extent other costs such as Design

The private sector would have the ability tobulk purchase materials such as steel whichcould potentially provide significant savings .This has been assumed for this project.

Right of Way and Design costsare assumed the same for bothforms of delivery

Total Initial Construction - $743M

$66 M $108 M

$281 M

$181 M

$0

$50

$100

$150

$200

$250

$300

2015

2016

2017

2018

2019

2020

2011

US$

Milli

ons

P3 Delivery Initial Construction Costs

Total Initial Construction - $716M

Page 15: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

15WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

RIGHT of WAYGRADING, DRAINAGE AND STOCKPILINGSTRUCTURESCEMENT CONCRETE PAVEMENTOTHER ITEMSTOLLING & ITS

DESIGNMOBILIZATION AND PREPARATIONWATERLINES, STORM AND SANITARY SEWERSASPHALT AND SURFACINGTRAFFIC CONTROLNON - BID COSTS 700 Level Items

Construction Costs

0

50

100

150

200

250

300

2015

2016

2017

2018

2019

2020

2011

US$

Mill

ions

Year

SR 509 Express Toll LanesTraditional Delivery Initial Construction Costs

-

50

100

150

200

250

300

2015

2016

2017

2018

2019

2020

2011

US$

Mill

ions

Year

SR 509 Express Toll LanesP3 Delivery Initial Construction Costs

SR 509 Express Toll Lanes Initial ConstructionCosts (Millions)

TraditionalDelivery

P3 Delivery

DESIGN $68 $68RIGHT of WAY $105 $105MOBILIZATION AND PREPARATION $60 $50GRADING, DRAINAGE AND STOCKPILING $108 $107WATERLINES, STORM AND SANITARY SEWERS $0 $0STRUCTURES $221 $219ASPHALT AND SURFACING $13 $13CEMENT CONCRETE PAVEMENT $21 $21TRAFFIC CONTROL $37 $31OTHER ITEMS $2 $2NON - BID COSTS 700 Level Items $93 $85TOLLING & ITS $14 $14

Total Construction Cost $743 $716* Other Items include Design, QAQC (15%), Guardrail, Signage other minor items,Environmental mitigation like recon of wetlands, stream restoration etc,differing site conditions

** Non Bid Costs include sales tax, construction engineering (WSDOTs own andsub costs to inspect during construction) contingency, stipend for failed bidders

Page 16: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

16WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$5

$10

$15

$20

$25

$30

$35

$40

$45

$5020

13

2015

2017

2019

2021

2023

2025

2027

2029

2031

2033

2035

2037

2039

2041

2043

2045

2047

2049

2051

2053

2055

2057

2059

2061

2063

2065

2067

2069

2011

USD

in M

illion

s

Lifecycle Cost Comparison

Overall Lifecycle Costs for Traditional Delivery Overall Lifecycle Costs for P3 Delivery

Lifecycle Costs

Full DepthReconstruction of

Pavement

PavementResurfacing

on a life cycleof 12 years

Pavement Resurfacing &Tolling Equipment

Replacement to meetHandback Requirements

Tolling EquipmentReplacement on a

lifecycle of 10 years

Costs include Design, Resurfacing,Traffic Control and considerable

Tolling & ITS work

Traditional Delivery: Total Lifecycle Costs - $216MP3 Delivery: Total Lifecycle Costs - $163M

Page 17: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

17WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

SR 509 Express Toll Lanes LifecycleCosts (Millions)

TraditionalDelivery P3 Delivery

Roadway Maintenance $23.53 $1.90Pavement Maintenance $51.72 $80.94Structures $0.00 $1.11Tolling & ITS Maintenance $87.46 $43.91Other Misc. Items $27.03 $0.00Engineering, Construction Mgmt. and Testing Fees$14.96 $0.00Design $0.00 $0.00Mobilization and Preparation $11.50 $0.00General Contingencies $0.00 $35.34Total Over Concession $216.21 $163.19

Lifecycle Costs

• Overall, P3 costs are 25% lower in nominal (2011) dollars

• P3 case actually spends significantly more on pavement repairs

• Majority of savings are on Tolling and ITS ($43.5M or 50% of the total savings)

Page 18: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

18WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$500

$1,000

$1,500

$2,000

$2,500

Traditional DeliveryO&M Cost

P3 Delivery O&M Costs

US$

Mill

ions

Operation & Maintenance Forecast Comparison

O&M Costs

Total Potential Savingthrough P3 Delivery (45%)

Traditional Delivery: Total O&M Costs - $1,927MP3 Delivery: O&M - $1,091M

Structures

Tolling & ITS

Enforcement

Roadway General Maintenance

Personnel

Pavement

Tolling Uncollectables

Facility Maintenance

G&A

Uncollectible tolls and enforcement aretypically overseen by Government, butpass-through of associated costs to theConcessionaire is common

Personnel costs are not captured undera single entry for the Traditional Deliveryapproach, but incorporated in each line

Greatest savings result fromTolling and ITS approach

Page 19: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

19WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

O&M Costs

Personnel

Structures

Pavement

Tolling & ITS

Tolling Uncollectables

Enforcement

Facility Maintenance

Roadway General Maintenance

G&A

80%

19%

1%

SR 509 Express Toll Lanes O&M Costs(Millions)

TraditionalDelivery

P3 Delivery Comment

Personnel $0.00 $173.62WashDot personnel costs are incorporated within eachof the l ine items such as structures, pavements etc.

Structures $0.21 $29.39 Includes bridges, safety barriers and retaining wallsPavement $6.25 $13.43 Includes asphalt & concrete pavement

Tolling & ITS $1,584.54 $384.89 Includes annual maintenance, fixed back office costs,transaction based cost & credit card fees

Toll ing Uncollectables $359.97 $412.88 For both delivery methods assumed 4.5% of RevenueEnforcement $5.84 $5.81 Assumed the same for both delivery methodsFacil ity Maintenance $0.00 $0.83Roadway General Maintenance $20.05 $18.89 Includes drainage, landscaping etc.G&A $4.74 $51.46 General & Administrative costs

Total Over Concession Years $1,982 $1,091

16%

3%1%

35%

38%

2%5%

Page 20: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

20WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$144$6

$904

$320

$217

$229

$360

$413

$156

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

$2,000

Traditional DeliveryO&M Cost

P3 Delivery O&M Costs

US$

Mill

ions

SR 509 Tolling & ITS Comparison

Tolling & ITS Costs

* Tolling & ITS – Transaction based costsincorporate equipment maintenance,customer service center (CSC) and FixedBack Office Costs.

Traditional Delivery: Total O&M Costs - $1,950MP3 Delivery: O&M - $803M

Total Potential Savingthrough P3 Delivery (59%)

Equipment O&M

WSP Enforcement

Transaction Based CSC Costs

Fixed Back Office Costs

Credit Card Fees

Uncollectible Accounts

Tolling & ITS - Transaction based costs*

Page 21: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

21WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Financial Model InputsFinancial Model Inputs(SR 167 Toll Lanes)(SR 167 Toll Lanes)

Page 22: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

22WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$50

$100

$150

$200

$250

FY 2017 FY 2022 FY 2027 FY 2032 FY 2037 FY 2042 FY 2047 FY 2052 FY 2057 FY 2062 FY 2067

Revenue AssumptionsU

S$ M

illio

ns (N

omin

al)

P3 Constructionscenario allowsearly opening andcommencementof tolling in FY2019.

PSC Construction scenario allowscommencement of tolling in FY 2020

PSC Revenue Assumptions P3 Revenue Assumptions

Base Case Base Case

High Case

Low Case

Page 23: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

23WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

0

50

100

150

200

250

300

350

2013

2014

2015

2016

2017

2018

2019

2020

2021

2011

US$

Milli

ons

Year

Initial Construction Costs Comparison

Total Traditional Delivery Initial Construction Costs Total P3 Delivery Initial Construction Costs

Traditional Delivery Total Initial Construction - $1,180MP3 Delivery Total Initial Construction - $965M

Identical Pre-construction costs forPreliminary Engineering (15% design)and Right of Way acquisition

Constructioncommences

Construction Costs

P3 Case assumes accelerated construction schedule

Initial Construction Costs Comparison

Page 24: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

24WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$80 M$100 M $95 M

$270 M

$327 M

$84 M

-

50

100

150

200

250

300

350

400

2013

2014

2015

2016

2017

2018

2019

2020

2021

2011

US$ M

illion

s

P3 Delivery Initial Construction Costs

$80 M

$110 M $110 M$101 M

$253 M $255 M

$165 M$106 M

0

50

100

150

200

250

300

350

400

2013

2014

2015

2016

2017

2018

2019

2020

2021

2011

US$ M

illion

s

Traditional Delivery Initial Construction Costs

Construction Costs

Initial Construction Costs Savings for the P3Delivery method are based on the ability ofthe private sector to complete constructionwithin 2.5 years instead of 5, reducing all timedependant costs such as Mobilization &Preparation and Traffic Control, and to alesser extent other costs such as Design

The private sector would have the ability tobulk purchase materials such as steel whichcould potentially provide significant savings .However, this has not been assumed for thisproject.

Right of Way and Design costsare assumed the same for bothforms of delivery

Total Initial Construction - $1,180M

Total Initial Construction - $965M

Page 25: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

25WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

0

50

100

150

200

250

300

350

400

2013

2014

2015

2016

2017

2018

2019

2020

2011

US$

Mill

ions

Year

SR 167 Express Toll LanesTraditional Delivery Initial Construction Costs

RIGHT of WAYGRADING, DRAINAGE AND STOCKPILINGSTRUCTURESCEMENT CONCRETE PAVEMENTOTHER ITEMSTOLLING & ITS

DESIGNMOBILIZATION AND PREPARATIONWATERLINES, STORM AND SANITARY SEWERSASPHALT AND SURFACINGTRAFFIC CONTROLNON - BID COSTS 700 Level Items

Construction Costs

SR 167 Express Toll Lanes Initial ConstructionCosts (Millions)

TraditionalDelivery

P3 Delivery

DESIGN $100 $100RIGHT of WAY $175 $175MOBILIZATION AND PREPARATION $52 $26GRADING, DRAINAGE AND STOCKPILING $138 $113WATERLINES, STORM AND SANITARY SEWERS $5 $4STRUCTURES $303 $226ASPHALT AND SURFACING $31 $23CEMENT CONCRETE PAVEMENT $0 $0TRAFFIC CONTROL $9 $5OTHER ITEMS* $102 $77NON - BID COSTS 700 Level Items** $232 $181TOLLING & ITS $34 $27

Total Construction Cost $1,180 $956* Other Items include Design, QAQC (15%), Guardrail , Signage other minor items,Environmental mitigation like recon of wetlands, stream restoration etc,differing site conditions

** Non Bid Costs include sales tax, construction engineering (WSDOTs own andsub costs to inspect during construction) contingency, stipend for fai led bidders

-

50

100

150

200

250

300

350

400

2013

2014

2015

2016

2017

2018

2019

2020

2011

US$

Mill

ions

Year

SR 167 Express Toll LanesP3 Delivery Initial Construction Costs

Page 26: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

26WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$5

$10

$15

$20

$25

$3020

13

2015

2017

2019

2021

2023

2025

2027

2029

2031

2033

2035

2037

2039

2041

2043

2045

2047

2049

2051

2053

2055

2057

2059

2061

2063

2065

2067

2069

2011

USD

in M

illion

s

Year

Lifecycle Cost Comparison

Overall Lifecycle Costs for Traditional Delivery Overall Lifecycle Costs for P3 Delivery

Lifecycle Costs

PavementResurfacing

on a life cycleof 12 years

Pavement Resurfacing,Bridge Structure Repair &

Tolling EquipmentReplacement to meet

Handback Requirements

Tolling EquipmentReplacement on a

lifecycle of 12 years

Costs include Design, Resurfacing,Traffic Control and considerable

Tolling & ITS workTraditional Delivery: Total Lifecycle Costs - $123MP3 Delivery: Total Lifecycle Costs - $96M

Page 27: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

27WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

SR 167 Express Toll Lanes Lifecycle Costs(Millions)

TraditionalDelivery

P3 Delivery

Roadway Maintenance $0.28Structures $35.45Pavement Maintenance $28.34 $16.10Tolling & ITS Maintenance $47.14 $23.47Other Misc. Items $17.74 $0.00Engineering, Construction Mgmt. andTesting Fees

$9.81 $6.02

Design $0.00* $3.77Mobilization and Preparation $7.55 $4.52General Contingencies $0.00* $6.51

Total Over Concession $123.51 $96.12

$12.93

* Cost is included within Engineering, Construction Mgmt. and Testing Fees

Lifecycle Costs

$51.83 $41.28

• Overall, P3 costs are 22% lower in nominal (2011) dollars

• P3 case actually spends significantly more on pavement and structure repairs

• Majority of savings are on Tolling and ITS ($24M or 50% of the total savings)

Page 28: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

28WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

Traditional Delivery O&MCost

P3 Delivery O&M Costs

US$

Mill

ions

Operation & Maintenance Forecast ComparisonO&M Costs

Total Potential Savingthrough P3 Delivery (61%)

PSC Total O&M Costs - $1,659MP3 Total O&M - $646M

Structures

Tolling & ITS

Enforcement

Roadway General Maintenance

Personnel

Pavement

Tolling Uncollectables

Facility Maintenance

G&A

Uncollectible tolls and enforcement aretypically overseen by Government, butpass-through of associated costs to theConcessionaire is common

Personnel costs are not captured undera single entry for the Traditional Deliveryapproach, but incorporated in each line

Greatest savings result fromTolling and ITS approach

Page 29: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

29WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

1%

80%

18%

1%

5%

1%

47%

45%

1%1%

O&M Costs

Personnel

Structures

Pavement

Tolling & ITS

Tolling Uncollectables

Enforcement

Facility Maintenance

Roadway General Maintenance

G&A

SR 167 Express Toll Lanes O&MCosts (Millions)

TraditionalDelivery

P3 Delivery Comment

Personnel $0.00 $29.10WashDot personnel costs are incorporatedwithin each of the line items such asstructures, pavements etc.

Structures $0.00 $4.93 Includes bridges, safety barriers and retainingwalls

Pavement $6.46 $2.25 Includes asphalt & concrete pavement

Tolling & ITS $1,367.15 $301.09Includes annual maintenance, fixed back officecosts, transaction based cost & credit cardfees

Tolling Uncollectables $304.35 $290.36 For both delivery methods assumed 4.5% ofRevenue

Enforcement $5.84 $5.89 Assumed the same for both delivery methodsFacility Maintenance $0.00 $0.14Roadway General Maintenance $12.88 $3.17 Includes drainage, landscaping etc.G&A $2.18 $8.63 General & Administrative costs

Total Over Concession $1,699 $646

Page 30: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

30WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$78$6

$695

$410

$184

$161

$304

$290

$140

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

Traditional Delivery Cost P3 Delivery Costs

US$

Mill

ions

SR 167 Tolling & ITS Comparison

Tolling & ITS Costs

* Tolling & ITS – Transaction based costsincorporate equipment maintenance,customer service center (CSC) and FixedBack Office Costs.

Traditional Delivery: Total O&M Costs - $1,677MP3 Delivery: O&M - $597M

Total Potential Savingthrough P3 Delivery (64%)

Equipment O&M

WSP Enforcement

Transaction Based CSC Costs

Fixed Back Office Costs

Credit Card Fees

Uncollectible Accounts

Tolling & ITS - Transaction based costs*

Page 31: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

31WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Financial Model InputsFinancial Model Inputs(Columbia River Crossing)(Columbia River Crossing)

Page 32: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

32WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

0

100

200

300

400

500

600

700

800

US$ M

illion

s (No

mina

l)Revenue Assumptions

P3 Constructionscenario allowsearly opening andcommencementof tolling in FY2017.

PSC Construction scenario allowscommencement of tolling in FY 2019

PSC Revenue Assumptions P3 Revenue Assumptions

Base Case Base Case

High Case

Low Case

Page 33: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

33WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

-

200

400

600

800

1,000

1,200

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$ M

illion

s

Year

Initial Construction Comparison

Total Traditional Delivery Initial Construction Costs Total P3 Delivery Initial Construction Costs

Traditional Delivery Total Initial Construction - $3,029MP3 Delivery Total Initial Construction - $2,720M

Identical Pre-construction costs forPreliminary Engineering (15% design)and Right of Way acquisition

Construction Costs

P3 Case assumes accelerated construction schedule

Page 34: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

34WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

-

100

200

300

400

500

600

70020

12

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Year

CRC P3 Delivery Initial Construction Costs

$105

$375

$1,016

$735

$490

-

200

400

600

800

1,000

1,200

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2011

US$

Mill

ions

Year

CRC P3 Delivery Initial Construction Costs

Construction Costs

Initial Construction Costs Savings for the P3Delivery method are based on the ability ofthe private sector to complete constructionwithin 5 years instead of 9, reducing all timedependant costs such as Mobilization &Preparation and Traffic Control, and to alesser extent other costs such as Design

The private sector would have the ability tobulk purchase materials such as steel whichcould potentially provide significant savings .However, this has not been assumed for thisproject.

Right of Way and Design costsare assumed the same for bothforms of delivery

Total Initial Construction - $3,029M

Total Initial Construction - $2,720M

Page 35: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

35WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

-

200

400

600

800

1,000

1,200

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

US$ M

illion

s

Year

CRC P3 Delivery Initial Construction Costs

RIGHT of WAYGRADING, DRAINAGE AND STOCKPILINGSTRUCTURESCEMENT CONCRETE PAVEMENTOTHER ITEMSTOLLING & ITS

DESIGNMOBILIZATION AND PREPARATIONWATERLINES, STORM AND SANITARY SEWERSASPHALT AND SURFACINGTRAFFIC CONTROLNON - BID COSTS 700 Level Items

Construction Costs

-

100

200

300

400

500

600

700

80020

12

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

US$

Mill

ions

Year

CRC Traditional Delivery Initial Construction Costs

Page 36: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

36WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Initial Construction Costs

• Overall, P3 costs are10% lower in nominal(2011) dollars

• Design & Right of Waycosts are the same forboth forms of delivery

• Majority of savings areon Mobilization andPreparation

CRC Toll Lanes Initial Construction Costs(Millions)

TraditionalDelivery

P3 Delivery

DESIGN $157 $157RIGHT of WAY $220 $220MOBILIZATION AND PREPARATION $293 $162GRADING, DRAINAGE AND STOCKPILING $120 $116WATERLINES, STORM AND SANITARY SEWERS $68 $66STRUCTURES $1,553 $1,519ASPHALT AND SURFACING $101 $99CEMENT CONCRETE PAVEMENT $0 $0TRAFFIC CONTROL $122 $68OTHER ITEMS* $368 $287NON - BID COSTS 700 Level Items** $0 $0TOLLING & ITS $27 $27

Total Construction Cost $3,029 $2,720* Other Items include Design, QAQC (15%), Guardrail , Signage other minoritems, Environmental mitigation l ike recon of wetlands, stream restoration etc,differing site conditions

** Non Bid Costs include sales tax, construction engineering (WSDOTs ownand sub costs to inspect during construction) contingency, stipend for failedbidders

Page 37: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

37WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$20

$40

$60

$80

$100

$120

$14020

15

2017

2019

2021

2023

2025

2027

2029

2031

2033

2035

2037

2039

2041

2043

2045

2047

2049

2051

2053

2055

2057

2059

2061

2063

2065

2067

2069

2011

USD

in M

illion

s

Year

Lifecycle Cost Comparison

Overall Lifecycle Costs for Traditional Delivery Overall Lifecycle Costs for P3 Delivery

Lifecycle CostsMajor Rehabilitationon Bridge Structure

PavementResurfacing

on a life cycleof 10 years

Pavement Resurfacing &Tolling Equipment

Replacement to meetHandback Requirements

Tolling EquipmentReplacement on alifecycle of 8 years

Costs include Design, Resurfacing,Traffic Control and considerable

Tolling & ITS work

Traditional Delivery: Total Lifecycle Costs - $356MP3 Delivery: Total Lifecycle Costs - $305M

Page 38: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

38WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

Lifecycle Costs

• Overall, P3 costs are 15% lower in nominal (2011) dollars

• P3 case actually spends significantly more on Structure repairs

CRC Toll Lanes Lifecycle Costs (Millions) TraditionalDelivery

P3 Delivery

Roadway Maintenance $42.41 $1.62Pavement Maintenance $105.33 $21.87Structures $0.00 $150.39Tolling & ITS Maintenance $109.91 $57.20Other Misc. Items $50.58 $0.00Engineering, Construction Mgmt. andTesting Fees

$27.98 $23.11

Design $0.00 $11.55Mobilization and Preparation $21.52 $13.86General Contingencies $0.00 $25.42

Total Over Concession $357.73 $305.03

Page 39: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

39WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

$4,000

$4,500

Traditional DeliveryO&M Cost

P3 Delivery O&MCosts

US$ M

illio

nsOperation & Maintenance Forecast Comparison

O&M Costs

Total Potential Savingthrough P3 Delivery (57%)

Traditional Delivery: Total O&M Costs - $3,935MP3 Delivery: O&M - $1,672M

Structures

Tolling & ITS

Enforcement

Roadway General Maintenance

Personnel

Pavement

Tolling Uncollectables

Facility Maintenance

G&A

Uncollectible tolls and enforcement aretypically overseen by Government, butpass-through of associated costs to theConcessionaire is common

Personnel costs are not captured undera single entry for the Traditional Deliveryapproach, but incorporated in each line

Greatest savings result fromTolling and ITS approach

Page 40: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

40WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

72%

20%

3%

1% 1%

O&M Costs

Personnel

Structures

Pavement

Tolling & ITS

Tolling Uncollectables

Enforcement

Facility Maintenance

Roadway General Maintenance

G&A

CRC Toll Lanes O&M Costs (Millions) * TraditionalDelivery P3 Delivery Comment

Personnel $0.00 $106.32WashDot personnel costs are incorporated withineach of the line items such as structures,pavements etc.

Structures $9.46 $15.00 Includes bridges, safety barriers and retaining wallsPavement $0.00 $6.86 Includes asphalt & concrete pavement

Tolling & ITS $2,891.04 $685.95 Includes annual maintenance, fixed back officecosts, transaction based cost & credit card fees

Tolling Uncollectables $796.24 $771.58 For both delivery methods assumed 4.5% ofRevenue

Enforcement $130.48 $41.92 Assumed the same for both delivery methodsFacility Maintenance $8.76 $34.63 Assumed the same for both delivery methodsRoadway General Maintenance $36.22 $0.42G&A $62.88 $9.64

Total Over Concession $3,935 $1,672*Costs associated with Insurance Preimums not included within this analyses.

6%1% 0%

40%45%

2% 1%

1% 0%

2%

Page 41: Financial Model Inputs - Washingtonleg.wa.gov/.../FinancialModelInputs_120611.pdf · Financial Model Inputs (I(I--405 Express Toll Lanes) 405 Express Toll Lanes) WAJTC Policy WorkingGroup

41WA JTC Policy Working Group Meeting AECOM : KPMG : Nossaman

$351

$42

$1,285

$695

$560

$429

$796

$772

$257

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

$4,000

Traditional DeliveryCost

P3 Delivery Costs

US$

Mill

ions

Tolling & ITS Comparison

Tolling & ITS Costs

* Tolling & ITS – Transaction based costsincorporate equipment maintenance,customer service center (CSC) and FixedBack Office Costs.

Traditional Delivery: Total O&M Costs - $3,729MP3 Delivery: O&M - $1,499M

Total Potential Savingthrough P3 Delivery (59%) Equipment O&M

WSP Enforcement

Transaction Based CSC Costs

Fixed Back Office Costs

Credit Card Fees

Uncollectible Accounts

Tolling & ITS - Transaction based costs*