Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune APPENDIX II (See paragraph 6) FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity) 1.1. Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. The proposed land use is in conformity with the Development Plan (DP) of the area. REFER ANNEXURE I: AERIAL VIEW REFER ANNEXURE II: SITE LOCATION PLAN & DP PLAN REFER ANNEXURE III: CONTOUR LEVELS PLAN REFER ANNEXURE IV: MASTER LAYOUT PLAN REFER ANNEXURE VI: PARKING & TRAFFIC MANAGEMENT PLAN 1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc. Details are as follows: Total Plot Area: 42850.00 m 2 Total Built up Area (FSI): 28790.63 m 2 Total Built up Area (NON FSI): 13235.10 m 2 Total Construction Area: 42025.73 m 2

Form 1 and 1A Vastushodh - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/...Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh

  • Upload
    danganh

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

APPENDIX II

(See paragraph 6)

FORM-1 A (only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

1. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1. Will the existing land use get significantly altered from the project that is not consistent

with the surroundings? (Proposed land use must conform to the approved Master Plan /

Development Plan of the area. Change of land use if any and the statutory approval

from the competent authority be submitted). Attach Maps of (i) site location, (ii)

surrounding features of the proposed site (within 500 meters) and (iii) the site

(indicating levels & contours) to appropriate scales. If not available attach only

conceptual plans.

The proposed land use is in conformity with the Development Plan (DP) of the area.

REFER ANNEXURE I: AERIAL VIEW

REFER ANNEXURE II: SITE LOCATION PLAN & DP PLAN

REFER ANNEXURE III: CONTOUR LEVELS PLAN

REFER ANNEXURE IV: MASTER LAYOUT PLAN

REFER ANNEXURE VI: PARKING & TRAFFIC MANAGEMENT PLAN

1.2. List out all the major project requirements in terms of the land area, built up area,

water consumption, power requirement, connectivity, community facilities, parking

needs etc.

Details are as follows:

Total Plot Area: 42850.00 m2

Total Built up Area (FSI): 28790.63 m2

Total Built up Area (NON FSI): 13235.10 m2

Total Construction Area: 42025.73 m2

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

Area Statement

Item

No. Description

Area In

m2

1. AREA OF PLOT 42,850.00

2. DEDUCTIONS FOR

a) AREA UNDER 60.0 M . WIDE ROAD WIDENING 2,116.25

TOTAL 2,116.25

3. NET GROSS AREA OF PLOT (1-2) 40,733.75

4. DEDUCTIONS FOR

a) Amenity space-15% 6,110.06

a) Open space -10% (NOT DEDUCTED ) 4,073.38

a) 12.00 M WIDE INTERNAL ROAD (NOT

DEDUCTED )

4,358.34

TOTAL (a + b + c ) 6,110.06

5. NET AREA OF PLOT (3-4 × 0.90 ) 31,161.32

6. ADDITION FSI PERM. ON NET PLOT AREA 37,393.58

7. PERMISSIBLE FLOOR AREA 37,393.58

8. PROPOSED FLOOR AREA 28,790.63

TENEMENT STATEMENT

Sr.

No.

Building

Name Floors

No. & Type of Flat Total

Tenements Population 1

RK

1

BHK

2

BHK

1 A P + 9 - - 71 71 355

2 B P + 9 - - 71 71 355

3 C P + 9 - - 71 71 355

4 H P + 9 133 - - 133 665

5 I P + 9 133 - - 133 665

6 J P + 9 - 71 - 71 355

7 K P + 9 - 71 - 71 355

8 L P + 9 - 71 - 71 355

Total 692 3460

Total Population Residential = 3460

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

WATER CONSUMPTION:

During Construction Phase: 35 m3/day.

Source: Tanker/Bore well

During Operation Phase:

Water Source: Paud Grampanchayat.

Total Water demand is -538.56 m3/day

Domestic for residence is –311.40 m3/day

Flushing for residence is - 155.70 m3/day

Landscaping is - 71.46 m3/day

No. of Tenements –692 Nos. Population - For Residential – 3460 Nos.

Sr.

No.

Description Water

requirement Loss

Sewage

generation

Water use

Fresh Recycled

1

Domestic for

residential

building (@ 90

LPCD) no. of.

Persons 3460

311.40 1.14

280.26 311.40 -

2

Flushing for

residential

building (@ 45

LPCD) no. of.

Persons 3460

155.70 5.57

140.13 - 155.70

3

Landscape

irrigation 71.46 - - 71.46

4 TOTAL 538.56 6.71 420.39 311.4 227.16

STP Capacity 425m3/day

(ANNEXURE VIII – WATER BALANCE STATEMENT)

POWER REQUIREMENT:

SOURCE – Maharashtra State Electricity Distribution Company Limited (MSEDCL)

During Construction Phase:

• Total Load 30KW,

• Source- MSEDCL

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

During Operation Phase:

• Total Connected Load – 1774.7 KW

• Maximum Demand – 1252.4 KW

• Transformer – 630 KVA - 2 No.

• DG Set for residential – 200 KVA – 1 No.

• Total Fuel Consumption- 45.9 Lit/Hr for 200 KVA

(ANNEXURE XIII ELETRICAL CALCULATION, D.G. CHART & LOCATION)

PARKING STATEMENT:

Approximately 108 Nos. of four wheeler, 1218 Nos. of two wheelers & 1218 Nos. cycles are

proposed in the residential complex.

Internal circulation pattern will be so as to avoid any congestion within the complex. Parking

space will be allotted within the campus.

(REFER ANNEXURE VI – PARKING AND TRAFFIC MANAGEMENT PLAN)

1.3.What are the likely impacts of the proposed activity on the existing facilities adjacent

to the proposed site? (Such as open spaces, community facilities, details of the existing

land use and disturbance to the local ecology).

Although it is a construction activity, its impact on air quality, water quality, noise and soil will not be notable. As a matter of fact this activity will have positive impact, on socio-

economic culture of people residing in the vicinity of the proposed area. There will not be any disturbance to the local ecology as the selected site for the construction is a barren land.

The project site and the surrounding area are not developed. The plantations, which would be grown in the residential area, will be helpful in increasing green cover of the area. This would

also increase avifauna in the area.

1.4.Will there be any significant land disturbance resulting in erosion, subsidence &

instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity,

etc may be given).

Generally, soil types found in Pune district are black, copper, red, & paddy soil. Soil blends of

variable properties are modified by sand, gravel, lime salts, & other ingredients.

(REFER ANNEXURE III - CONTOUR PLAN)

1.5.Will the proposal involve alteration of natural drainage systems? (Give details on a

contour map showing the natural drainage near the proposed project site)

Not Applicable

(REFER ANNEXURE III - CONTOUR PLAN)

1.6. What are the quantities of earthwork involved in the construction activity cutting,

filling, reclamation etc. (Give details of the quantities of earthwork involved, transport

of fill materials from outside the site etc.)?

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

The debris will not be generated at the project site as the excavated material will be utilized

on site for filling.

1.7. Give details regarding water supply, waste handling etc. during the construction

period.

Total water requirement during construction phase will be approximately 35m3/day for

domestic use for the workers working/dwelling on the site. The construction water

requirement will be in addition to this. The source will be Tankers. The non biodegradable solid waste will be segregated and will send to kabadi. The wet waste will be treated by

“Organic Waste Convertor”. A septic tank and soak pit will be constructed for temporary shelters of construction workers.

The construction debris and cut and fill waste will be recycled for road construction

1.8. Will the low-lying areas & wetlands get altered? (Provide details of how low lying

and Wetland are getting modified from the proposed activity)

Not Applicable

1.9. Whether construction debris & waste during construction cause health hazard?

(Give quantities of various types of wastes generated during construction including the

construction labor and the means of disposal)

Construction debris and waste during construction will not cause health hazard. The natural

depression on site will be lined and converted into water bodies which would add to passive

cooling and will act as Rainwater Harvesting devices.

Construction debris generated will be used for development of landscape.

2. WATER ENVIRONMENT

2.1. Give the total quantity of water requirement for the proposed project with the

breakup of requirements for various uses. How will the water requirement be met?

State the sources & quantities and furnish a water balance statement.

During Construction Phase: 35 m3/day.

Source: Tanker/Bore well

During Operation Phase:

Water Source: Paud Grampanchayat

Water Demand: Dry Season

Total Water demand is -538.56 m3/day

Domestic for residence is –311.40 m3/day

Flushing for residence is - 155.70 m3/day

Landscaping is - 71.46 m3/day

STP Capacity 425 m3/day

(ANNEXURE VIII – WATER BALANCE STATEMENT)

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

2.2 What is the capacity (dependable flow or yield) of the proposed Source of water?

The source of water during operation is Paud Grampanchayat.

2.3. What is the quality of water required, in case, the supply is not from a municipal

source? (Provide physical, chemical, biological characteristics with class of water

quality)

The water will be available from Paud Grampanchayat which will accomplish the water requirement for this residential complex.

2.4. How much of the water requirement can be met from the recycling of treated

wastewater? (Give the details of quantities, sources and usage)

About 155.70 m3/day of water will be recycled for flushing at residential building &

landscaping.

2.5. Will there be diversion of water from other users? (Please assess the impacts of the

project on other existing uses and quantities of consumption)

Not Applicable

2.6. What is the incremental pollution load from wastewater generated from the

proposed activity? (Give details of the quantities and composition of wastewater

generated from the proposed activity)

There will not be any incremental pollution load from the proposed activity. The Quantity of

sewage is about 84.35 % of domestic water consumption. The wastewater-generated from the proposed activity shall be domestic. Total water will be treated and recycled within the site to

the extent possible.

2.7. Give details of the water requirements met from water harvesting? Furnish details

of the facilities created.

Run-off Calculation

Sr. No Type of Area Area in m2

Run of

Coefficient

Flow on

m3

/min

Flow on

m3

/min

I Before Implementation

A Area of Plot 42850.00 0.60 23.57 23.57

TOTAL(I) 23.57

II After Implementation

a For Terrace (Roof) Area 3978.59 0.95 3.46 3.46

b For Hardscape Area 15999.74 0.90 13.20 13.20

c For open Area 13373.50 0.60 7.36 7.36

d For Green (lawn) Area 7156.72 0.30 1.97 1.97

TOTAL(II) 25.99

Incremental in Discharge of Storm water [II - I] [25.99 – 23.57] 2.42

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

DETAILS OF STORM WATER DRAINAGE SYSTEM

INTENSITY OF PRECIPITATION

Maximum Intensity of rainfall in Pune is – 55 mm/hr.

Total No. harvesting pits: 04 Nos.

(ANNEXURE XV: RAIN WATER HARVESTING & STORM WATER

MANAGEMENT PLAN)

2.8. What would be the impact of the land use changes occurring due to the proposed

project on the runoff characteristics (quantitative as well as qualitative) of the area in

the post construction phase on a long term basis? Would it aggravate the problems of

flooding or water logging in any way?

The proposed land use is in conformity with the DP so there will not be any land use change.

The runoff from the project site will be used for the aquifers.

The storm water drains of the area are proposed to be connected to the future drain line which

is future development along the project.

2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of

ground water; give the details of ground water table, recharging capacity, and approvals

obtained from competent authority, if any)

A comprehensive Rainwater Harvesting System will be implemented in the form of aquifer

recharge. The water table in the area is likely to increase due to the proposed system with no

adverse effects envisage.

2.10. What precautions/measures are taken to prevent the run-off from construction

activities polluting land & aquifers? (Give details of quantities and the measures taken

to avoid the adverse impacts)

The runoff from the site will be filtered mechanically and present rate of discharge will be

retained without any incremental pollution load from the site.

2.11. How is the storm water from within the site managed?(State the provisions made

to avoid flooding of the area, details of the drainage facilities provided along with a site

layout indication contour levels)

Run-off Calculation:

Sr. No Type of Area Area in M2

Run of

Coefficient

Flow on

M3

/min

Flow on

M3

/min

I Before Implementation

A Area of Plot 42850.00 0.60 23.57 23.57

TOTAL(I) 23.57

II After Implementation

a For Terrace (Roof) Area 3978.59 0.95 3.46 3.46

b For Hardscape Area 15999.74 0.90 13.20 13.20

c For open Area 13373.50 0.60 7.36 7.36

d For Green (lawn) Area 7156.72 0.30 1.97 1.97

TOTAL(II) 25.99

Incremental in Discharge of Storm

water [II - I]

[25.99 –

23.57] 2.42

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

DETAILS OF STORM WATER DRAINAGE SYSTEM

INTENSITY OF PRECIPITATION

Maximum Intensity of rainfall in Pune is – 55 mm/hr.

Total no. harvesting pits: 04 Nos.

(REFER ANNEXURE XV: RAIN WATER HARVESTING & STORM WATER

MANAGEMENT PLAN)

2.12. Will the deployment of construction laborers particularly in the peak period lead

to unsanitary conditions around the project site (Justify with proper explanation)

During construction phase numbers of workers will be 60. Municipal solid waste generated

during construction will be composted at site. Temporary Toilets, Septic tank and soak pits

are provided during construction phase. This will not lead unsanitary conditions at the site.

2.13. What on-site facilities are provided for the collection, treatment & safe disposal of

sewage? (Give details of the quantities of wastewater generation, treatment capacities

with technology & facilities for recycling and disposal)

The sewage will be collected from 692 Nos. tenements. The quantity of sewage is about 78.05

% of domestic water consumption. The waste water generated from the proposed activity

shall be domestic. Sewage will be treated in the sewage treatment plants of 425 m3/day. The

treated sewage will be recycled for flushing and gardening and surplus will be connected to pond.

(REFER ANNEXURE IX – SEWAGE TREATMENT PLANT- SCHEMATIC PLAN &

PLAN)

DESIGN BASIS This Sewage treatment plant has been designed to treat the domestic wastewater generated in

the project of “AnandGram Paud”at- Paud,Pune having following characteristics:

Design Basis:

a) Plant Capacity: 425 m3/day

b) Technology: MBBR

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

DESIGN PARAMETERS:

The sewage treatment plant will be designed for a capacity of 240 KLD with a peak factor of

3. The scheme of treatment plant will be based on MBBR (Anoxic-Aerobic) Process. It will

be smell free& energy efficient (Using Samruddhi Biotechnology). Raw sewage will then be

passed through fine manual bar screens Oil & Grease to remove solids, floatables, oil &

grease from raw sewage stream before passing to equalization tank. The sewage then will be

collected in receiving /collection /Equalization Tank. The receiving /collection /Equalization

Tank will be provided with Air Blowers for mixing and aseptic conditions. Raw sewage from

equalization tank will be lifted by using Submersible Raw Sewage Lifting Pumps. Aeration

tank is provided with diffused Aeration Systems for biological aeration purpose.

In the aeration tank oxidation biological matter occurs. Nitrification occurs in aerobic tank, while nitrified effluent is denitrified in anoxic tank. Aerobically digested sewage water is

then passed to secondary clarifier where it biological Flocs formed will be removed and

separated by means of gravity. Very good quality of Bioculture is developed by using

Samruddhi Biotechnology on MBBR media. The excess biosludge is sent sludge holding tank where it is aerated. Clarified water is then passed through multimedia and activated

carbon filters for removing turbidity by means of Submersible Filter Feed Pumps.

Multimedia filtration removes fine particulate and suspended solids while activated carbon

filter removes odour and organic traces. Ozonation System is used for disinfection of treated

water

(REFER ANNEXURE IX – SEWAGE TREATMENT PLANT- SCHEMATIC PLAN)

2.14 Give details of dual plumbing system if treated waste is used for flushing of toilets

or any other use.

The sewage will be collected from 692 tenements. The quantity of sewage is about 78.05% of domestic water consumption. The waste water generated from the proposed activity shall be

domestics. Sewage will be treated in the sewage treatment plant of 425m3/day. The treated

sewage partly recycled for flushing & partly connected to Municipal Sewer line.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

3. VEGETATION

3.1. Is there any threat of the project to the biodiversity? (Give a description of the local

ecosystem with its unique features, if any)

There will not be any threat of the project to the biodiversity. The selected site for project is a

barren land. The project proponents have proposed a landscape development plan, which includes planting of flowering and shady trees, shrubs and lawn within the plot.

3.2. Will the construction involve extensive clearing or modification of vegetation?

(Provide a detailed account of the trees & vegetation affected by the project)

No. Selected site is a barren land. However, the project site will cover the flowering plants, lawns. The open spaces inside the plot will be suitably landscaped and covered with

vegetation.

3.3. What are the measures proposed to be taken to minimize the likely impacts on

important site features (Give details of proposal for tree plantation, landscaping,

creation of water bodies etc along with a layout plan to an appropriate scale)

The site presently is a barren land with no important site features. All the existing drain lines

and trees will be retained and conserved.

Landscaping and Tree Plantation

Landscape area – 10629.01 m2

Total no. of trees to be planted – 111 Nos.

(REFER ANNEXURE XII - LANDSCAPE PLAN & LIST OF TREES)

4. FAUNA

4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or

creation of barriers for their movement? Provide the details.

No

4.2. Any direct or indirect impacts on the avifauna of the area? Provide details.

No

4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts

on fauna

The proposed project will not have any adverse impact on the flora or fauna.

5. AIR ENVIRONMENT

5.1. Will the project increase atmospheric concentration of gases & result in heat

islands? (Give details of background air quality levels with predicted values based on

dispersion models taking into account the increased traffic generation as a result of the

proposed constructions)

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

As this will be a Residential & Commercial complex, air pollution is not expected to be a

major concern.

5.2. What are the impacts on generation of dust, smoke, odorous fumes or other

hazardous gases? Give details in relation to all the meteorological parameters.

During construction phase, suspended particulate matter, dust, will be the main pollutant,

which could be generated from site development activities and movement of vehicles. Odorous fumes or hazardous gases generation is not expected. Concentration of SO2, NO2 and

CO may rise a little due to traffic. Proper upkeep and maintenance of vehicles, sprinkling of water on roads and construction site and providing sufficient vegetation all around the plant

site are some of the measures that would reduce the impact during construction phase.

5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of

the present level of transport infrastructure and measures proposed for improvement

including the traffic management at the entry & exit to the project site.

Approximately 108 Nos. of four wheeler, 1218 Nos. of two wheelers & 1218 Nos. cycles

proposed within the complex will ensure no traffic congestion outside the campus. Measures

proposed for traffic management at the entry and exit to the project site are: Maintaining flow of traffic for approach roads Entry and Exit points carefully placed so as not to disturb this

flow. Easy movement of fire tender in and around the complex ensuring accessibility to every building.

(REFER ANNEXURE VI– PARKING AND TRAFFIC MANAGEMENT PLAN)

5.4. Provide details of the movement patterns with internal roads, bicycle tracks,

pedestrian pathways, footpaths etc., with areas under each category.

Area of drive way will be 6 m wide.

5.5. Will there be significant increase in traffic noise & vibrations? Give details of the

sources and the measures proposed for mitigation of the above.

The proposed activity being of residential type will not cause a notable increase in the noise

and vibration during operation.

Sources of noise Pollution during construction phase are machinery like compressor,

Compactors, Concrete Plant, Cranes and transportation materials.

Mitigation measures:

The project proponents have agreed to take precautions to control noise pollution as

mentioned under: • Use of equipment generating noise of not greater than 90 dB (A).

• High noise generating construction activities would be carried out only during daytime. Also, adequate parking space will be provided to avoid crowding and noise pollution

• Installation, use and maintenance of mufflers on equipment. • Workers working near high noise construction machinery would be supplied with ear

muffs/ear plugs.

5.6.What will be the impact of DG sets & other equipment on noise levels & vibration in

& ambient air quality around the project site? Provide details.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

Source – Maharashtra State Electricity Distribution Company Limited (MSEDCL)

During Construction Phase:

Sources of noise pollution during construction phase are machinery like Earthmoving

Machinery, Mini Hoist Crane, Mixer, Lift lade, JCB, Dumpers, Compressors and

transportation materials

These machineries will be used only day time. Canopies will be provided to these mechanical devices to reduce noise & vibration. Maximum mitigation measures such as regular

maintenance or overhauling etc.

During Operation Phase: There will not be any considerable impact on the ambient air quality around the project site as

CPCB approved DG sets along with acoustic room will be developed and plantation will be provided.

6. AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a view,

scenic amenity or landscapes? Are these considerations taken into account by the

proponents?

No. Proposed construction will not result in obstruction of a view, scenic amenity or

landscapes.

6.2. Will there be any adverse impacts from new constructions on the existing

structures? What are the considerations taken into account?

Not Applicable.

6.3. Whether there are any local considerations of urban form & urban design

influencing the design criteria? They may be explicitly spelt out.

No

6.4. Are there any anthropological or archaeological sites or artifacts nearby? State if

any other significant features in the vicinity of the proposed site have been considered

No

7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of local

population? Provide the details.

Critically analyzing the socio-economic baseline in the context of the proposed project, the

impacts of the project could be variable in nature. The proposed project does not involve any

displacement of inhabitants.

During construction 60 workers will be provided temporary shelters at the site. After completion of the project, there will be influx of 1860 Residential population 100 people in

the area. The population of the area is likely to increase.

7.2. Give details of the existing social infrastructure around the proposed project.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

This project has proposes of Residential and Commercial Complex by M/S Vastushodh

Realty coming up at -Paud, Pune. This area is rapidly developing.

7.3. Will the project cause adverse effects on local communities, disturbance to sacred

sites or other cultural values? What are the safeguards proposed?

It could be seen that the overall impact on Socio-Economic Environment is positive and

permanent in nature. The impacts on socio-economic environment due to the proposed

Projects are as follows,

• Possible source of income for this community are direct like Construction and various job

works in complex

• Improvement in transport, communication facilities.

• Improvement in lifestyle & social status etc.

• Increase in revenue generation

• Due to the proposed project, facilities are likely to grow in line with the development.

8. BUILDING MATERIALS

8.1. May involve the use of building materials with high-embodied energy. Are the

construction materials produced with energy efficient processes? (Give details of energy

conservation measures in the selection of building materials and their energy efficiency)

Conventional construction materials used from nearest source to minimize energy

consumption for transportation.

8.2. Transport and handling of materials during construction may result in pollution,

noise & public nuisance. What measures are taken to minimize the impacts?

During construction phase, sources of noise pollution will be due to operation of machinery

like compressors, compactors, concrete plant, cranes etc. as well as transportation vehicles.

This will cause nuisance to the occupants of the nearby area. The project proponents have

agreed to take precautions to control noise pollution as mentioned under:

i) Use of equipment generating noise of not greater than 90 dB (A).

ii) High noise generating construction activities would be carried out only during day time. iii) Installation, use and maintenance of mufflers on equipment.

iv)Workers working near high noise construction machinery would be supplied with ear muffs/ear plugs.

8.3. Are recycled materials used in roads and structures? State the extent of savings

achieved?

Solid waste that would be generated due to excavation will be in the form of rubble and soil.

This soil and rubble would be used for development of landscaping. Construction debris will

be reused for backfilling of roads and other construction.

8.4. Give details of the methods of collection, segregation & disposal of the garbage

generated during the operation phases of the project.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

Solid waste generated in the campus is domestic type having source separated dry and wet

components. As far as possible the dry waste like paper, cardboard boxes, thermocol packing,

plastics etc. shall be sent for recycling purpose.

However, wet waste, which is biodegradable, shall be converted to bio-compost adopting

following aerobic composting method. The quantity of biodegradable waste generated is

about 986.1 Kg/Day. The ‘Organic Waste Composter’ will be used for composting of solid

waste.

A) For Residential + Commercial 1) Quantity of Total Solid Waste = 1591.65 Kg/day.

2) Quantity of Total Wet Waste = 986.1 Kg/day.

3) Quantity of Total Dry Waste = 605.55 Kg/day.

Biodegradable and non biodegradable waste will be generated. Dry waste will be sent for

recycling and wet waste will be treated by “Organic Waste Converter”.

Process:-

1. Large volumes of food waste from pre-cooking, leftover after meal are dumped in

community bins, which is responsible for foul odor & health hazards.

2. Organic Waste Converter homogenizes organic waste with appropriate additive & bio

culture.

3. The output from device is uniform colored coarse powder in appearance and is

without any bad smell.

4. Thus treated material over-come major cause of nuisance to resident community

related to eye & nose sense.

5. It can be composted into good quality organic manure in 2 weeks.

Benefits of OWC

� The total MSW arriving on the site is cleared on the same day. � Provides a scientific method for the production of organic compost.

� Elimination of foul odor. � Elimination of Pathogens and weed seeds.

� Problem of rodents and insect pests is avoided. � Aesthetically acceptable.

� Treatment time is substantially reduced. � Eco-friendly & Economical

� Requires less space for the treatment.

� Load on the landfill is reduced, thus requires less land for disposal.

(ANNEXURE X: SOLID WASTE MANAGEMENT: ORGANIC WASTE

CONVERTOR PROCESS)

9. ENERGY CONSERVATION

9.1. Give details of the power requirements, source of supply, backup source etc. What

is the energy consumption assumed per square foot of built-up area?

POWER REQUIREMENT:

SOURCE – Maharashtra State Electricity Distribution Company Limited (MSEDCL)

During Construction Phase:

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

• Total Load – 30 KVA

• Source-MSEDCL

During Operation Phase:

• Total Connected Load – 1774.7 KW

• Maximum Demand – 1252.4 KW

• Transformer – 630 KVA - 2 No.

• DG Set for residential – 200 KVA – 1 No.

• Total Fuel Consumption- 45.9 Lit/Hr for 200 KVA

(ANNEXURE XIII ELETRICAL CALCULATION, D.G. CHART & LOCATION)

9.2. What type of, and capacity of, power back-up do you plan to provide?

During Operation Phase:

• Total Connected Load – 1774.7 KW

• Maximum Demand – 1252.4 KW

• Transformer – 630 KVA - 2 No.

• DG Set for residential – 200 KVA – 1 No.

• Total Fuel Consumption- 45.9 Lit/Hr for 200 KVA

9.3. What are the characteristics of the glass you plan to use? Provide specifications of

its characteristics related to both short wave and long wave radiation?

Normal 5 mm clear float glass is used. The glass will allow short as well as long wave

radiations to pass through. However, use of shading devices on window panes will reduce

heating inside the buildings.

9.4. What passive solar architectural features are being used in the building? Illustrate

the applications made in the proposed project.

Solar architectural features have been planned in order to reduce cooling loads of the

structure. They are:

1. Longer side facing dominant wind direction

2. Water bodies ample adding to passive cooling

3. Proper shading devices for windows. (Not Applicable)

9.5. Does the layout of streets & buildings maximize the potential for solar energy

devices? Have you considered the use of street lighting, emergency lighting and solar hot

water systems for use in the building complex? Substantiate with details.

Solar System is being used for Hot water/ Streetlights

9.6. Is shading effectively used to reduce cooling/heating loads? What principles have

been used to maximize the shading of Walls on the East and the West and the Roof?

How much energy saving has been effected?

The construction is designed in order to assure maximum of the natural light and ventilation

in the structure. Light shades will be used to color the walls so that heat gain is reduced.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical

systems? Provide technical details. Provide details of the transformers and motor

efficiencies, lighting intensity and air-conditioning load assumptions? Are you using

CFC and HCFC free chillers? Provide specifications.

As it is a residential complex with no built provision for space cooling. Energy efficiency in

lighting and mechanical systems will be achieved by:

• CFL & LED based lighting will be done in the common areas, landscape areas, Solar

lights will be provided for common amenities like Street lighting, & Garden lighting.

• Use of Solar Panel for Hot water.

9.8. What are the likely effects of the building activity in altering the micro-climates?

Provide a self-assessment on the likely impacts of the proposed construction on creation

of heat island & inversion effects?

The proposed project is of residential type and will not have space conditioners or glass wall.

Alteration of microclimate is not notable in this case. Systematic design of buildings in order

to assure maximum natural ventilation and light will be considered to reduce the effect of

creation of heat island.

9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external

walls; and (c) fenestration? Give details of the material used and the U-values or the R

values of the individual components.

Fenestration area is most vulnerable to heat gain or loss. Thermal characteristics of the

envelope are as follows: The U and R values of the construction parameters shall comply with ECBC.

9.10. What precautions & safety measures are proposed against fire hazards? Furnish

details of emergency plans.

The project proponents shall follow all the safety rules and regulations as prescribed by

regulatory authority.

9.11. If you are using glass as wall material provides details and specifications including

emissivity and thermal characteristics.

The entire building is designed with appropriate opening to reduce heat energy inside the building. No use of glass as well material.

9.12. What is the rate of air infiltration into the building? Provide details of how you are

mitigating the effects of infiltration.

Not applicable. As the ground surfaces are covered with green patches to have dust control. These openings too habitable spaces are adequate just to be functional. The openings are

covered with dust proof, air and water light aluminum glazing.

9.13. To what extent the non-conventional energy technologies are utilized in the overall

energy consumption? Provide details of the renewable energy technologies used.

Use of Solar Energy.

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune

10. Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item

wise activity to be undertaken during the construction, operation and the entire life cycle to

minimize adverse environmental impacts as a result of the activities of the project. It would

also delineate the environmental monitoring plan for compliance of various environmental

regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

(ANNEXURE XVI- ENVIRONMENT MANAGEMENT PLAN)

Form 1 & 1A for Proposed Project “AnandGram Paud” by M/S Vastushodh Realty

at Gat No.. 263 (P), 273(P), 275, 276 (P), 283 At Paud, Taluka Mulshi, District – Pune