Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
GEOTECHNICAL INVESTIGATION
PROPOSED FOOTBRIDGE OVER EXISTING
TRACK
Motoring South West
Date:
Report Name:
10 January 2019
8318-G-R-001.docx Page i
Date: 10 January 2019
WML Name: Collie Motorplex Footbridge Additional GI
WML Project No: 8318
Distribution Record:
Revision Reviewed By Date Issued Purpose of Issue Issued To
A SM 10/01/2019 Draft for comments Steve Brake
Prepared by: Greg Tomasini
Signed:
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
About your geotechnical investigation and report………….
A geotechnical investigation is planned and conducted solely for the intended recipient of
the report and for the purposes stated in the report. The report should not be reproduced
in whole or part without agreement of WML Consultants.
A geotechnical investigation is planned and conducted based upon the information about
the site and proposed works that is made available to WML Consultants, as stated in the
report.
A geotechnical investigation typically includes investigation and testing at a few isolated
locations. The choice of the locations is usually made by the author having consideration
for the nature of the site and proposed works. Conditions for the remainder of the site are
necessarily extrapolated from the conditions observed at the locations investigated. Thus
the report will contain a mixture of facts, interpretation and professional judgement. Facts
will usually be confined to a description of the fieldwork carried out, the observations made
and any results of laboratory testing. However, field notes and logs contain estimates of
conditions observed at the time, and may differ from the results obtained from subsequent
laboratory testing of samples. Other comments and conclusions should be considered as
interpretation and professional judgement, unless specifically stated otherwise.
As the nature of geotechnical conditions is so variable WML Consultants accepts no liability
or responsibility for the conditions encountered beyond the limits of our investigation. Such
conditions may exist between test locations or in deeper strata than observed than can
reasonably be interpreted from the limited extent of this investigation.
For various reasons (e.g. seasonal effects), the site conditions encountered during
construction may differ from those observed or extrapolated from the initial investigation.
In this instance the recommendations in the geotechnical report may not be appropriate
and it is strongly recommended WML Consultants be requested to inspect the different
conditions, review the initial report and provide follow-up advice. Unless specifically
allowed for in the brief, the follow-up review will attract an additional fee.
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
CONTENTS
1 INTRODUCTION ........................................................................................................................................................... 3
2 SITE SETTING ................................................................................................................................................................ 3
2.1 SITE LOCATION AND DESCRIPTION ................................................................................................................... 3
2.2 GEOLOGY .......................................................................................................................................................... 4
3 GROUND INVESTIGATION ...................................................................................................................................... 4
3.1 SERVICE LOCATION ........................................................................................................................................... 4 3.2 FIELDWORK ....................................................................................................................................................... 4
4 CPT ANALYSIS .............................................................................................................................................................. 4
5 FINDINGS AND RECOMMENDATIONS............................................................................................................... 5
5.1 SUB-SURFACE PROFILE ..................................................................................................................................... 5 5.2 DESIGN PARAMETERS ....................................................................................................................................... 6 5.3 SITE PREPARATION ........................................................................................................................................... 6
5.4 SAFETY IN DESIGN ............................................................................................................................................. 7
6 REFERENCES ................................................................................................................................................................. 7
APPENDIX A
SITE INVESTIGATION MAP
APPENDIX B
SOIL LOGS
APPENDIX C
PREVIOUS REPORT
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
1 INTRODUCTION
Previously Calibre Consulting on behalf of their client, Motoring Southwest, requested a
geotechnical investigation for a proposed footbridge over the existing track. The purpose of
the investigation was to ascertain the subsurface profile, soil strength, bearing capacity and
possible settlement at the site. WML undertook the following scope of work as part of that
appointment:
• 4 machine excavated test pits to approximately 2m depth • 4 CPTs to 6m or refusal • Logging of boreholes and collecting of samples • Sampling of representative subgrade materials for laboratory testing.
• Taking notes and photographs of the site.
A report (7524-G-R-001) presenting the findings of the previous investigation is attached.
Since the previous report was issued the footbridge has been moved approximately 25 meters
from the original position and as such WML was appointed to undertake a follow-up
geotechnical investigation with the same purpose at the new location. The scope of works for
the new locations included the following:
• 2 machine excavated test pits to approximately 2m depth • 2 CPTs to 6m or refusal • Logging of boreholes • Taking notes and photographs of the site
This report presents the findings of the investigation.
2 SITE SETTING
2.1 Site Location and Description
The Motorplex is located approximately 15 km southeast of Collie.
The Motorplex will undergo development including the construction of a pedestrian
footbridge over the race track, located near to the existing control tower. Investigation is
required at the two foundation locations. It is assumed the bridge will be founded on spread
footings. An image of the proposed bridge is shown below:
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
2.2 Geology
The near surface ground conditions are relevant to the bridge foundations and an appropriate
investigation technique (discussed further in Section 3). The general sub-surface geology at
the site consists of:
• 0-3m depth: superficial sand, gravel and cap rock.
• 3-30m depth: Nakina Formation (weakly cemented sandstone and claystone with a laterite hard cap).
The 1:50,000 scale geological map places the site upon ‘Sand’ and states that the area has been affected by mining activities.
3 GROUND INVESTIGATION
3.1 Service Location
A “Dial before You Dig” search for services was carried out before any excavation occurred.
Power and telecommunications services were found to be servicing the Motorplex however
they were not located in the vicinity of the work area. Electrical services were present for the
start line timing equipment however these were also not in the immediate work area.
3.2 Fieldwork
The fieldwork was carried out on 7th January 2019 by an engineer from WML. The fieldwork
consisted of the following works.
• 2 machine excavated test pits to approximately 2m depth.
• 2 CPTs
GPS location and photographs were also taken of the site. The locations of the test pits are
shown on Drawing 8318-G-001 with the test pit logs presented in the Appendices.
4 CPT ANALYSIS
CPT analysis was undertaken at 2 locations on site. CPT 1 and 2 were progressed to the target
depth of 6m. The analysis of CPT1 and CPT 2 are shown below.
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
Figure 1: CPT 1 Figure 2: CPT 2
5 FINDINGS AND RECOMMENDATIONS
5.1 Sub-Surface Profile
TP1 located at Abutment 1:
• GRAVELLY, SILTY SAND 0 - 0.65m – Some cementation was present in the material.
• ASPHALT SEAL - 0.65 – 0.7m – Old haul road seal
• SANDY GRAVEL – 0.7 - 1.25m – Haul road basecourse material
• SILTY SAND – 1.25 – 1.9m – Very dense material
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
TP2 located at Abutment 2:
• SILTY SAND TOPSOIL - 0 - 0.15m – Grass and roots present.
• SANDY GRAVEL – 0.15 - 0.35m – Old gravel basecourse material
• SILTY SAND – 0.35 – 0.45m
• GRAVELLY SAND – 0.45 – 0.9m
• SILTY SAND – 0.9+m – Very dense material
5.2 Design Parameters
5.3 Site Preparation
The existing in-situ material is well compacted. If existing material is over excavated and
needs to be replaced then compaction of placed material will be required.
Abutment 1: 0 to1.3m Abutment 2: 0 to 2.0m
Medium Dense Clayey / Silty Sand and Sandy Silt Fill
Parameter Design Value
E (Young’s modulus) 25 MPa
Φ (angle of internal friction) 32°
Cu (cohesion) 0 kPa
g (unit weight) 18 kN/m3
Abutment 1: 1.3 to 6.0m Abutment 2: 2.0 to 6.0m
Very Stiff/Dense Soils
Parameter Design Value
E (Young’s modulus) 50 MPa
Φ (angle of internal friction) 36°
Cu (cohesion) 0 kPa
g (unit weight) 18 kN/m3
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
5.4 Safety in Design
This project has design elements, however these elements are considered rudimentary with
the associated risks and hazards being widely known and understood. Any competent person
carrying out this type of work should be aware of these hazards and apply standard industry
practices to mitigate the risks.
Yours faithfully,
Greg Tomasini Simon Maris
Civil Engineer Senior Geotechnical Engineer
Author Reviewer
For and on behalf of WML Consultants Pty Ltd
6 REFERENCES
1. Geological Series Map 1:50,000 Scale ‘Collie’
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
APPENDIX A
SITE INVESTIGATION MAP
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
APPENDIX B
SOIL LOGS
Not
Enc
ount
ered
SM
SM
GW
SP
Dry, pale brown, dense, fine to coarse grained, gravelly silty SAND.
Dry, cream mottled red, dense, fine to medium grained, silty SAND. Slightly cemented.
STONE SEAL
Dry, orange brown, dense, fine to coarse, sandy GRAVEL. Old haul road basecourse.
Dry, cream, dense, fine to medium grained, silty SAND.
Hole Terminated at 1.90 mTarget depth
DE
PT
H (
m)
0.5
1.0
1.5
2.0
WA
TE
R
GR
AP
HIC
LOGSAMPLES OR
FIELD TEST
CLA
SS
IFIC
AT
ION
SY
MB
OL
SOIL/ROCK MATERIAL DESCRIPTION
LOGGED: GT
LOGGED DATE: 07/01/2019
SURFACE RL:
CHAINAGE:
CONTRACTOR: WML Consultants
MACHINE: Excavator
CO-ORD SYSTEM: MGA94 Zone 50
POSITION:
TRIAL PIT: TP 1
CLIENT: Calibre
PROJECT: Collie Motorplex Geotech Investigation
LOCATION: Collie Motorplex
JOB NO.: 8318
SHEET: 1 OF 1
WM
L LI
B 1
.08.
GLB
Lo
g W
ML
SO
IL
8318
SO
IL L
OG
S.G
PJ
<<
Dra
win
gFile
>>
08
/01/
2019
14:
15
10.0
.000
D
evel
oped
by
Dat
gel
Not
Enc
ount
ered
SM
GW
SM
SW
Dry, dark brown black, loose, fine to coarse grained, silty SAND.
Dry, orange brown, dense, fine to coarse, sandy GRAVEL with a trace of clay. Possible old gravelhardstand.
Dry, pale white mottled black, dense, fine to medium grained, silty SAND.
Dry, pale orange, medium dense, fine to coarse grained, gravelly SAND.
Hole Terminated at 0.90 mTarget depth
DE
PT
H (
m)
0.5
1.0
1.5
2.0
WA
TE
R
GR
AP
HIC
LOGSAMPLES OR
FIELD TEST
CLA
SS
IFIC
AT
ION
SY
MB
OL
SOIL/ROCK MATERIAL DESCRIPTION
LOGGED: GT
LOGGED DATE: 07/01/2019
SURFACE RL:
CHAINAGE:
CONTRACTOR: WML Consultants
MACHINE: Excavator
CO-ORD SYSTEM: MGA94 Zone 50
POSITION:
TRIAL PIT: TP 2
CLIENT: Calibre
PROJECT: Collie Motorplex Geotech Investigation
LOCATION: Collie Motorplex
JOB NO.: 8318
SHEET: 1 OF 1
WM
L LI
B 1
.08.
GLB
Lo
g W
ML
SO
IL
8318
SO
IL L
OG
S.G
PJ
<<
Dra
win
gFile
>>
08
/01/
2019
14:
15
10.0
.000
D
evel
oped
by
Dat
gel
Date:
Report Name:
10 January 2019
8318-G-R-001.docx
APPENDIX C
PREVIOUS REPORT
GEOTECHNICAL INVESTIGATION
PROPOSED FOOTBRIDGE OVER EXISTING
TRACK
Motoring South West
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx Page i
Date: 5 May 2017
WML Name: Collie Motorplex Footbridge GI
WML Project No: 7524
Distribution Record:
Revision Reviewed By Date Issued Purpose of Issue Issued To
A PAF 5/5/2017 Draft for comments Steve Brake
Prepared by: Greg Tomasini
Signed:
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
About your geotechnical investigation and report………….
A geotechnical investigation is planned and conducted solely for the intended recipient of
the report and for the purposes stated in the report. The report should not be reproduced
in whole or part without agreement of WML Consultants.
A geotechnical investigation is planned and conducted based upon the information about
the site and proposed works that is made available to WML Consultants, as stated in the
report.
A geotechnical investigation typically includes investigation and testing at a few isolated
locations. The choice of the locations is usually made by the author having consideration
for the nature of the site and proposed works. Conditions for the remainder of the site are
necessarily extrapolated from the conditions observed at the locations investigated. Thus
the report will contain a mixture of facts, interpretation and professional judgement. Facts
will usually be confined to a description of the fieldwork carried out, the observations made
and any results of laboratory testing. However, field notes and logs contain estimates of
conditions observed at the time, and may differ from the results obtained from subsequent
laboratory testing of samples. Other comments and conclusions should be considered as
interpretation and professional judgement, unless specifically stated otherwise.
As the nature of geotechnical conditions is so variable WML Consultants accepts no liability
or responsibility for the conditions encountered beyond the limits of our investigation. Such
conditions may exist between test locations or in deeper strata than observed than can
reasonably be interpreted from the limited extent of this investigation.
For various reasons (e.g. seasonal effects), the site conditions encountered during
construction may differ from those observed or extrapolated from the initial investigation.
In this instance the recommendations in the geotechnical report may not be appropriate
and it is strongly recommended WML Consultants be requested to inspect the different
conditions, review the initial report and provide follow-up advice. Unless specifically
allowed for in the brief, the follow-up review will attract an additional fee.
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
CONTENTS
1 INTRODUCTION ........................................................................................................................................................... 3
2 SITE SETTING ................................................................................................................................................................ 3
2.1 SITE LOCATION AND DESCRIPTION ................................................................................................................... 3
2.2 GEOLOGY .......................................................................................................................................................... 3
3 GROUND INVESTIGATION ...................................................................................................................................... 3
3.1 SERVICE LOCATION ........................................................................................................................................... 3 3.2 FIELDWORK ....................................................................................................................................................... 3
4 LABORATORY TESTING ........................................................................................................................................... 4
4.1 ASS FIELD TESTING ................................................................................... ERROR! BOOKMARK NOT DEFINED. 4.2 SPOCAS TESTING .................................................................................... ERROR! BOOKMARK NOT DEFINED.
5 FINDINGS OF INVESTIGATION .............................................................................................................................. 5
5.1 SUB-SURFACE PROFILE ..................................................................................................................................... 5
6 RECOMMENDATIONS .......................................................................... ERROR! BOOKMARK NOT DEFINED.
6.1 PAVEMENT DESIGN ................................................................................... ERROR! BOOKMARK NOT DEFINED.
6.2 ACID SULFATE SOILS ......................................................................................................................................... 6 6.3 SITE PREPARATION ................................................................................... ERROR! BOOKMARK NOT DEFINED.
7 SAFETY IN DESIGN ................................................................................ ERROR! BOOKMARK NOT DEFINED.
8 REFERENCES ................................................................................................................................................................. 7
APPENDIX A
SITE INVESTIGATION MAP
APPENDIX B
SOIL LOGS
APPENDIX C
GEOTECHNICAL LABORATORY TEST RESULTS + CPT RESULTS
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
1 INTRODUCTION
Calibre Consulting on behalf of their client, Motoring Southwest, requested a geotechnical
investigation for a proposed footbridge over the existing track. The purpose of the
investigation was to ascertain the subsurface profile, soil strength, bearing capacity and
possible settlement at the site.
The proposed scope of work consisted of:
• 4 machine excavated test pits to approximately 2m depth • 4 CPTs to 6m or refusal • Logging of boreholes and collecting of samples • Sampling of representative subgrade materials for laboratory testing.
• Taking notes and photographs of the site.
This report presents the findings of the investigation.
2 SITE SETTING
2.1 Site Location and Description
The Motorplex is located approximately 15km southeast of Collie.
The Motorplex will undergo development including the construction of a pedestrian
footbridge over the race track, located near to the existing control tower. Investigation is
required at four locations. It is assumed the bridge will be founded on spread footings.
2.2 Geology
The near surface ground conditions are relevant to the bridge foundations and an appropriate
investigation technique (discussed further in Section 3). The general sub-surface geology at
the site consists of:
• 0-3m depth: superficial sand, gravel and cap rock.
• 3-30m depth: Nakina Formation (weakly cemented sandstone and claystone with a laterite hard cap).
The 1:50,000 scale geological map places the site upon ‘Sand’ and states that the area has been affected by mining activities.
3 GROUND INVESTIGATION
3.1 Service Location
A “Dial before You Dig” search for services was carried out before any excavation occurred.
Power and telecommunications services were found to be servicing the Motorplex however
they were not located in the vicinity of the work area. Electrical services were present for the
start line timing equipment however these were also not in the immediate work area.
3.2 Fieldwork
The fieldwork was carried out on 24th March 2017 by an engineer from WML. The fieldwork
consisted of the following works. One CPT and test pit was unable to be undertaken due to
unknown services on the inside of the track area.
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
• 3 machine excavated test pits to approximately 2m depth.
• 3 CPTs
The sampling of representative materials, GPS location and photographs were also taken of
the site. The locations of the test pits are shown on Drawing 7485-G-001 with the test pit logs
presented in Appendix A.
4 LABORATORY TESTING AND ANALYSIS
4.1 PSD Testing
Samples of representative material were submitted to Civitest Australia, a NATA accredited
laboratory for Particle Size Distribution (PSD) Testing. The test results are summarised below
with the certificates attached at the end of this report in Appendix C:
Table 1: Laboratory Testing Summary
Location Depth
(m) Test
PSD Atterberg’s
Fines
(%)
Sand
(%)
Gravel
(%)
PI
(%)
LS
(%)
TP1 1.5 PSD 29 60 11 15 6.5
TP3 0.8 PSD 17 68 15 12 4.5
Note: PSD – Particle Size Distribution; PI – Plasticity Index; LS – Linear Shrinkage;
4.2 CPT Analysis
CPT analysis was undertaken at 3 locations on site. CPT 1 and 3 were progressed to full target
depth while CPT 2 refused after pushing a dummy probe down to 1m. The analysis of CPT1
and CPT 3 are shown below.
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
Figure 1: CPT 1 Figure 2: CPT 3
5 FINDINGS AND RECOMMENDATIONS
5.1 Sub-Surface Profile
The site was consistent in soil profile
1. SANDY CLAY – Dry to moist, orange, very stiff, fine to coarse grained, low plasticity
clay. Some cementation was present in the material.
A 400mm gravel layer was found in TP 2 which may have been a part of an old haul road. A
CPT attempt refused in this area immediately.
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
5.2 Design Parameters
5.3 Site Preparation
The existing in-situ material is well compacted. If existing material is over excavated and
needs to be replaced then compaction of placed material will be required.
5.4 Safety in Design
This project has design elements, however these elements are considered rudimentary with
the associated risks and hazards being widely known and understood. Any competent person
carrying out this type of work should be aware of these hazards and apply standard industry
practices to mitigate the risks.
Yours faithfully,
Greg Tomasini Paul Foley
Civil Engineer Group Manager Geotechnical & Pavements
Author Reviewer
For and on behalf of WML Consultants Pty Ltd
Soils From 0 to 2.2m (Firm Clayey Sand/Sandy Clay)
Parameter Design Value
E (Young’s modulus) 25 MPa
Φ (angle of internal friction) 34°
Cu (cohesion) 0 kPa
g (unit weight) 18 kN/m3
Very Stiff Soils from 2.3m to 6m
Parameter Design Value
E (Young’s modulus) 50 MPa
Φ (angle of internal friction) 36°
Cu (cohesion) 5 kPa
g (unit weight) 18 kN/m3
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
6 REFERENCES
1. Geological Series Map 1:50,000 Scale ‘Collie’
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
APPENDIX A
SITE INVESTIGATION MAP
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
APPENDIX B
SOIL LOGS
Not
Enc
ount
ered
GW
SC
SC
SC
Moist, brown, very dense, fine to coarse, sandy GRAVEL. FILL.
Moist, orange, very dense, fine to coarse grained, clayey SAND. Some laterite boulders present.
Moist, orange, very dense, fine to coarse grained, clayey SAND.
Moist, mottled grey, very dense, fine to coarse grained, clayey SAND.
Hole Terminated at 2.20 mTarget depth
DE
PT
H (
m)
0.5
1.0
1.5
2.0
2.5
WA
TE
R
GR
AP
HIC
LOGSAMPLES OR
FIELD TEST
CLA
SS
IFIC
AT
ION
SY
MB
OL
SOIL/ROCK MATERIAL DESCRIPTION
LOGGED: GT
LOGGED DATE: 24/04/2017
SURFACE RL:
CHAINAGE:
CONTRACTOR: WML Consultants
MACHINE: Excavator
CO-ORD SYSTEM: MGA94 Zone 50
POSITION:
: TP 1
CLIENT: Motoring South West
PROJECT: Collie Motorplex GI
LOCATION: Collie Motorplex
JOB NO.: 7524
SHEET: 1 OF 1
CO
PY
OF
WM
L LI
B 1
.06.
GLB
Log
WM
L S
OIL
752
4 S
OIL
LO
GS
.GP
J <
<D
raw
ingF
ile>
> 2
8/03
/201
7 15
:29
10.
0.00
0 D
evel
oped
by
Dat
gel
Not
Enc
ount
ered
SC
GC
SC
Dry, orange, very dense, fine to coarse grained, clayey SAND.
Dry, brown red, very dense, fine to coarse, clayey GRAVEL. Possible old haul road material.
Dry, orange, very dense, fine to coarse grained, clayey SAND.
Hole Terminated at 1.80 mTarget depth
DE
PT
H (
m)
0.5
1.0
1.5
2.0
2.5
WA
TE
R
GR
AP
HIC
LOGSAMPLES OR
FIELD TEST
CLA
SS
IFIC
AT
ION
SY
MB
OL
SOIL/ROCK MATERIAL DESCRIPTION
LOGGED: GT
LOGGED DATE: 24/04/2017
SURFACE RL:
CHAINAGE:
CONTRACTOR: WML Consultants
MACHINE: Excavator
CO-ORD SYSTEM: MGA94 Zone 50
POSITION:
: TP 2
CLIENT: Motoring South West
PROJECT: Collie Motorplex GI
LOCATION: Collie Motorplex
JOB NO.: 7524
SHEET: 1 OF 1
CO
PY
OF
WM
L LI
B 1
.06.
GLB
Log
WM
L S
OIL
752
4 S
OIL
LO
GS
.GP
J <
<D
raw
ingF
ile>
> 2
8/03
/201
7 15
:29
10.
0.00
0 D
evel
oped
by
Dat
gel
Not
Enc
ount
ered
SC
Dry, orange, very dense, fine to coarse grained, clayey SAND.
Hole Terminated at 1.80 mTarget depth
DE
PT
H (
m)
0.5
1.0
1.5
2.0
2.5
WA
TE
R
GR
AP
HIC
LOGSAMPLES OR
FIELD TEST
CLA
SS
IFIC
AT
ION
SY
MB
OL
SOIL/ROCK MATERIAL DESCRIPTION
LOGGED: GT
LOGGED DATE: 24/04/2017
SURFACE RL:
CHAINAGE:
CONTRACTOR: WML Consultants
MACHINE: Excavator
CO-ORD SYSTEM: MGA94 Zone 50
POSITION:
: TP 3
CLIENT: Motoring South West
PROJECT: Collie Motorplex GI
LOCATION: Collie Motorplex
JOB NO.: 7524
SHEET: 1 OF 1
CO
PY
OF
WM
L LI
B 1
.06.
GLB
Log
WM
L S
OIL
752
4 S
OIL
LO
GS
.GP
J <
<D
raw
ingF
ile>
> 2
8/03
/201
7 15
:29
10.
0.00
0 D
evel
oped
by
Dat
gel
Date:
Report Name:
5 May 2017
7524-G-R-001-A.docx
APPENDIX C
LABORATORY TEST RESULTS
Page 1 of 1
CLIENT: SAMPLE NO:
PROJECT: JOB NO:
LOCATION: FIELD DESCRIPTION:
DATE TESTED:
PROPOSED USE: DEPTH TESTED mm:
CLIENT REF:
Liquid Limit % AS 1289.3.1.2
Plastic Limit % AS 1289.3.2.1
Plasticity Index % AS 1289.3.3.1
Linear Shrinkage % AS 1289.3.4.1
Length of Mould mm
Sample history
Sample Preparation Method
Nature of Shrink
Notes:
Approved Signatory:
Date:
Report Number: / 1
TEST REPORT
PARTICLE SIZE DISTRIBUTION
Collie Motorplex
Collie
24-1-454
Clay
10-Apr-17
W.M.L Consultants CT 61484
Stockpile
TP1 1.5m
-
PO7524
Sampled by Client
AS 1289.3.6.1
6.5
250
2.36 mm
75.0 mm
37.5 mm
16
15
100
100
82
31
1.18 mm
PARTICLE SIZE DISTRIBUTION AS 1289 .3.6.1
Sieve Size Sieve Size % Passing
70
100
95 0.300 mm
0.600 mm
0.150 mm
% Passing
PLASICITY INDEX & LINEAR SHRINKAGE
0.075 mm
19.0 mm
9.5 mm
0.425 mm 60
53
NATA Accredited Laboratory
No. 20040
Accredited for compliance
with ISO/IEC 17025
This document shall not be
reproduced,
except in full
36
29
H.Yama
CT 61484
22-Apr-17
Sample site selected by Client
4.75 mm Oven Dried
89 Dry Sieved
Flat
92
0
10
20
30
40
50
60
70
80
90
100
0.01 0.1 1 10 100
% P
assin
g
Sieve Size (mm)
CT-REP-011
Jul 2016
Bunbury Base Laboratory
Ph: 08 9726 2204
PO Box 5068, Bunbury WA 6231
29 Halifax Drive, Bunbury WA 6230 civitest.com.au
Page 1 of 1
CLIENT: SAMPLE NO:
PROJECT: JOB NO:
LOCATION: FIELD DESCRIPTION:
DATE TESTED:
PROPOSED USE: DEPTH TESTED mm:
CLIENT REF:
Liquid Limit % AS 1289.3.1.2
Plastic Limit % AS 1289.3.2.1
Plasticity Index % AS 1289.3.3.1
Linear Shrinkage % AS 1289.3.4.1
Length of Mould mm
Sample history
Sample Preparation Method
Nature of Shrink
Notes:
Approved Signatory:
Date:
Report Number: / 1
TEST REPORT
PARTICLE SIZE DISTRIBUTION
Collie Motorplex
Collie
24-1-454
Clay
10-Apr-17
W.M.L Consultants CT 61485
Stockpile
TP3 0.8m
-
PO7524
Sampled by Client
AS 1289.3.6.1
4.5
250
2.36 mm
75.0 mm
37.5 mm
15
12
100
100
70
27
1.18 mm
PARTICLE SIZE DISTRIBUTION AS 1289 .3.6.1
Sieve Size Sieve Size % Passing
52
100
96 0.300 mm
0.600 mm
0.150 mm
% Passing
PLASICITY INDEX & LINEAR SHRINKAGE
0.075 mm
19.0 mm
9.5 mm
0.425 mm 42
34
NATA Accredited Laboratory
No. 20040
Accredited for compliance
with ISO/IEC 17025
This document shall not be
reproduced,
except in full
22
17
H.Yama
CT 61485
22-Apr-17
Sample site selected by Client
4.75 mm Oven Dried
85 Dry Sieved
Flat
90
0
10
20
30
40
50
60
70
80
90
100
0.01 0.1 1 10 100
% P
assin
g
Sieve Size (mm)
CT-REP-011
Jul 2016
Bunbury Base Laboratory
Ph: 08 9726 2204
PO Box 5068, Bunbury WA 6231
29 Halifax Drive, Bunbury WA 6230 civitest.com.au
LOCATION:
PROJECT:
CLIENT:
ELECTRIC FRICTION-CONE PEN
Tested in accordance with AS 1289.6.5.1-1999 and IRTP 2001 for friction reducer
Collie
Collie Motorplex Geotechnical Investigation
Motoring South West
Refusal: Inclination
Approx. Water (m): Dry to 0.2
Dummy probe to (m):
0 1 2 3
01
23
45
67
89
Tip Res
Dep
th (m
)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 10 20 30 40 50 60 70 80 90 100
01
23
45
67
89
Friction Sleeve fs (kPa)
Tip Resistance qc (MPa)
Dep
th (m
)
Tip
Res
ista
nce
Fric
tion
Sle
eve
Co-ords:
RL (m):
Job No.:
24-Mar-17
Probe I.DNETROMETER
CPT 1
Rig Type: 22 tonne truck (Merc)
7524
File: WM0163G
Cone I.D.: EC21
0 1 2 3 4 5 6 7 8 9 10
01
23
45
67
89
Friction Ratio Rf (%)
Dep
th (m
)
4 5 6 7 8 9 10
istance qc (MPa)
LOCATION:
PROJECT:
CLIENT:
ELECTRIC FRICTION-CONE PEN
Tested in accordance with AS 1289.6.5.1-1999 and IRTP 2001 for friction reducer
Collie
Collie Motorplex Geotechnical Investigation
Motoring South West
Refusal:
Approx. Water (m): Dry to 6.0
Dummy probe to (m): 0.4
0 1 2 3
01
23
45
67
89
Tip Res
Dep
th (m
)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 10 20 30 40 50 60 70 80 90 100
01
23
45
67
89
Friction Sleeve fs (kPa)
Tip Resistance qc (MPa)
Dep
th (m
)
Tip
Res
ista
nce
Fric
tion
Sle
eve
Co-ords:
RL (m):
Job No.:
24-Mar-17
Probe I.DNETROMETER
CPT 1A
Rig Type: 22 tonne truck (Merc)
7524
File: WM0164G
Cone I.D.: EC21
0 1 2 3 4 5 6 7 8 9 10
01
23
45
67
89
Friction Ratio Rf (%)
Dep
th (m
)
4 5 6 7 8 9 10
istance qc (MPa)
LOCATION:
PROJECT:
CLIENT:
ELECTRIC FRICTION-CONE PEN
Tested in accordance with AS 1289.6.5.1-1999 and IRTP 2001 for friction reducer
Collie
Collie Motorplex Geotechnical Investigation
Motoring South West
Refusal: 75MPa / Rod Friction
Approx. Water (m): Dry to 1.0
Dummy probe to (m): 0.9
0 1 2 3
01
23
45
67
89
Tip Res
Dep
th (m
)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 10 20 30 40 50 60 70 80 90 100
01
23
45
67
89
Friction Sleeve fs (kPa)
Tip Resistance qc (MPa)
Dep
th (m
)
Tip
Res
ista
nce
Fric
tion
Sle
eve
Co-ords:
RL (m):
Job No.:
24-Mar-17
Probe I.DNETROMETER
CPT 2
Rig Type: 22 tonne truck (Merc)
7524
File: WM0165G
Cone I.D.: EC21
0 1 2 3 4 5 6 7 8 9 10
01
23
45
67
89
Friction Ratio Rf (%)
Dep
th (m
)
4 5 6 7 8 9 10
istance qc (MPa)
LOCATION:
PROJECT:
CLIENT:
ELECTRIC FRICTION-CONE PEN
Tested in accordance with AS 1289.6.5.1-1999 and IRTP 2001 for friction reducer
Collie
Collie Motorplex Geotechnical Investigation
Motoring South West
Refusal:
Approx. Water (m): Dry to 8.2
Dummy probe to (m): 0.4
0 1 2 3
01
23
45
67
89
Tip Res
Dep
th (m
)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 10 20 30 40 50 60 70 80 90 100
01
23
45
67
89
Friction Sleeve fs (kPa)
Tip Resistance qc (MPa)
Dep
th (m
)
Tip
Res
ista
nce
Fric
tion
Sle
eve
Co-ords:
RL (m):
Job No.:
24-Mar-17
Probe I.DNETROMETER
CPT 3
Rig Type: 22 tonne truck (Merc)
7524
File: WM0166G
Cone I.D.: EC21
0 1 2 3 4 5 6 7 8 9 10
01
23
45
67
89
Friction Ratio Rf (%)
Dep
th (m
)
4 5 6 7 8 9 10
istance qc (MPa)