28
GLOBALPLEX INTERNATIONAL DOCK PORT OF SOUTH LOUISIANA RESERVE, LOUISIANA Ayodeji Adeyemi Rhett Bouquet David Brasset Andrew Judice

Globalplex International Dock Port of South Louisiana Reserve, Louisiana

  • Upload
    belle

  • View
    41

  • Download
    0

Embed Size (px)

DESCRIPTION

Ayodeji Adeyemi Rhett Bouquet David Brasset Andrew Judice. Globalplex International Dock Port of South Louisiana Reserve, Louisiana. Introduction. Project Brief and Design Criteria Alternative Designs and Selection Permits Public Participation Health and Safety Construction Schedule - PowerPoint PPT Presentation

Citation preview

Permits

Globalplex International DockPort of South LouisianaReserve, LouisianaAyodeji AdeyemiRhett BouquetDavid BrassetAndrew JudiceIntroductionProject Brief and Design CriteriaAlternative Designs and SelectionPermitsPublic ParticipationHealth and Safety Construction ScheduleConstruction Cost EstimatePlansThe Project OutlineProject BriefGeneral Cargo Dock

Port of South Louisiana

Between River Miles 138 &139

St. John the Baptist Parish

Reserve, LouisianaDesign CriteriaPanamax Vessel with 65,000 dwt

General Cargo Design Load of 1000 psf

HS20-44 Truck Loading

Maximum Current of 4.5 Knots

Just a brief of the project, a general cargo dock was asked to be designed. The location of the dock is between river miles of 138 & 139 of the Mississippi River, located in St. John the Baptist Parish in Reserve, Louisiana. The dock is designed for a Panamax ship with 65,000 dead weight tons and a general cargo design load of 1000 psf. It is also designed for HS20-44 truck loading, which refers to handling a semi-truck and trailer with 3 to 4 axles.3Alternative Design & Selection

Two designs were considered in the design process of this project; the L-Shaped and T-Head platform docks. The main difference between these two docks is the location of the roadway on the dock. The L-Shaped docks roadway is located at the corner end of the dock, making the entrance and exits of the dock difficult. Whereas the roadway for the T-Head is located in the center of the dock, making the entrance and exits of the dock a lot easier. The L-Shaped docks primary function is for grain transportation with the use of conveyers, whereas the T-Head dock is used for general cargo. Since the project calls for a general cargo dock, the T-Head platform dock was chosen.4PermitsGovernment Agencies US Army Corps of EngineersLevee BoardUS Coast GuardRiverboat PilotsLADOTDSt. John the Baptist Parish

Before construction can begin , we need to obtain the proper permits and letters of no objection from the proper government agencies which are listed on the slide.5

This form is the ENG4345, it is found on the Army corps of engineers website. It comes with instructions that will tell you how to fill it out. If a person were to have any problems they can also call the corps and they will walk you through the process.6PermitsProcessEfficient methodThorough methodLetters of no objectionTime Six eight months

There are two processes to getting the permits. The efficient method and the thorough method. The thorough method involves finding the permit applications for each individual agency, filling it out, and submitting it with copies of the drawings. This method is time consuming and should be avoided. The efficient method is to fill out the ENG4345 form from the corps, and submit that to all government agencies, with the copies of the drawings. Once all the agencies have reviewed the plans and the applications they will issue the permits. The way it works is that once the levee board and the LADOTD approve of the project, they send letters of no objection to the corps. After the corps receives both letters of no objection, they will issue a permit to the company. This process needs to be started as soon as the plans are complete because it can take from six-eight months.7Elevated Roadway StructurePermitsLADOTD Project PermitCrossing LADOTD Right of Way

Another permit we will need is the LADOTD project permit for constructing a bridge over LA 44, or river road. The is a different permit application and it can be found on the DOTD website. It is complete with directions and if any problems do arise, you can call them and their staff will help you.8LADOTD Project Permit

This is a copy of the LADOTD project permit. 9Public input for the Preliminary Design

Informing the public of temporary changes

Informing the public of progress

Suggestions of the public

Public Participation

The public will also participate in this project. The plans will be presented at the St. John the Baptist Parish Planning commission meeting, and the public will be given a chance to comment or ask questions. Once construction begins our engineers will be present at every Planning commission meeting in order to inform the public of any changes as well as the progress of the construction.10Safety is part of the design process

OSHA Where do their regulations come from?

OSHA Structural requirements

OSHA Safety equipment and actions

The power of OSHAHealth and Safety

Since an engineers 1 job is to ensure public safety, the safety of the employees is taken into account during the design of the project. OSHA is the government agency that ensures the safety of all workers. All of their regulations come from previous accidents on a job site. Thus their laws are written form blood and are strictly enforced. Structurally you need to have a rail on all structures above the water. But if it is a cargo dock you dont need it . You also need first aid kits and trained personnel on the job site at all times. If these orders are not followed, the project will be shut down.11Construction ScheduleGeneral Cargo DockActivity IDActivity DescriptionEarly StartEarly Finish10 Permits23-Mar-091-Jun-0920 Engineering23-Mar-0927-Jun-0930 Bid & Award Contract for28-Jun-0918-Aug-0940 Procurement: Piles Etc.19-Aug-0914-Sep-0950 Yard Work Fabrication7-Sep-099-Nov-0960 Mobilize Land Work7-Sep-0918-Sep-0970 Levee Crossing and Abutment21-Sep-0923-Oct-0980 Drive Land Piles21-Sep-0923-Oct-0990 Install Roadway Bents26-Oct-096-Nov-09100 Install Roadway Spans with Deck2-Nov-094-Dec-09110 Set Walkway Spans4-Jan-1015-Jan-10120 Mobilize River Work2-Nov-0918-Nov-09130 Drive Marine Piles19-Nov-0920-Jan-10140 Install Marine Platforms4-Jan-101-Mar-10150 Pour Concrete Deck on Platform2-Mar-1015-Mar-10160 Construct Dolphins7-Dec-0930-Dec-09170 Install Fender System2-Mar-1013-Apr-10180 De-Mobilize14-Apr-1030-Apr-10

The schedule is a vital part of the construction process and is intended to provide an efficient estimate of the duration of time of each individual step of the construction process. It is critical that each step stay on task and is completed in the order that the schedule provides. Here is our construction schedule for the general cargo dock. As you can see it will take approximately 13 months to complete.12Construction Schedule

This is just a graphical representation of the construction schedule. It shows the order in which the activities are occur. It also gives a good representation of how long a specific activity will take compared to 13Cost Estimation: What is it?Educated approximation of final cost.Done at a point when:A basic idea of material quantities is knownBefore all of the final details have been worked outWhy is it important?Prevents a waste of the engineers time and the clients money.A worthwhile cost estimateTotal material costTotal labor costAdditional costsGRAND TOTAL (Sum total material and labor)

14Cost Estimation: The ComponentsRoadway BridgeAbutmentCast in Place ConcreteCompacted FillPilesLevee CrossingCast-in-Place ConcreteCompacted FillSlope PavingRoadway DeckPrecast Concrete Deck SlabsDeck Framing (Girders & Diaphragms)PaintingRoadway BentsPiles6 Bracing8 BracingStructural SteelPaintingT-Head PlatformPlatform Deck &FramingTimber CurbBollardsCast-in-Place Concrete DeckFinishing Concrete DeckStructural Steel (Beams)Piles and Pipe Bracing42 x .500 Pipe Piles12 Horizontal Bracing12 Vertical BracingFender Connection to PilePaintingFender SystemMooring DolphinsWalkway BentsWalkway Spans

Cost Estimation: Roadway BridgeDESCRIPTIONQUANTITYUNITUNIT PRICETOTAL ESTIMATED MATERIAL COSTUNIT PRICETOTAL ESTIMATED LABOR COSTTOTALAbutment:Cast-in-Place Conc.39.15C.Y.$100.00$3,915.00$600.00$23,490.00$27,405.00Compacted Fill66.67C.Y.$15.00$1,000.05$75.00$5,000.25$6,000.30Piles255LF$60.00$15,300.00$20.00$5,100.00$20,400.00SUBTOTAL$20,215.05$33,590.25$53,805.30Levee Crossing:Cast-in-Place Conc.58.3C.Y.$100.00$5,830.00$600.00$34,980.00$40,810.00Compacted Fill46.24C.Y.$15.00$693.60$75.00$3,468.00$4,161.60Slope Paving386.8S.Y.$20.00$7,736.00$80.00$30,944.00$38,680.00SUBTOTAL$14,259.60$69,392.00$83,651.60Roadway Deck:Precast Conc. Deck Slabs11760SF$50.00$588,000.00$25.00$294,000.00$882,000.00Deck Framing (Girders & Diaphrams)149Ton$2,000.00$298,000.00$1,500.00$223,500.00$521,500.00Painting149Ton$200.00$29,800.00$200.00$29,800.00$59,600.00SUBTOTAL$915,800.00$547,300.00$1,463,100.00Roadway Bents (20 Total): Piles5175.5LF$75.00$388,162.50$25.00$129,387.50$517,550.006" Bracing520LF$15.00$7,800.00$30.00$15,600.00$23,400.008" Bracing240LF$18.00$4,320.00$32.00$7,680.00$12,000.00Structural Steel9.1Ton$2,000.00$18,200.00$1,500.00$13,650.00$31,850.00Painting9.1Ton$200.00$1,820.00$200.00$1,820.00$3,640.00SUBTOTAL$420,302.50$168,137.50$588,440.00

The Process was started with the roadway bridge. The Individual components shown for the bridge were broken down into their sub-components and the unit quantities were determined. For example, for the abutment it was found that there was approximately 39.15 cubic yards of concrete, 66.67 cubic yards of compacted fill, and 225 linear feet of piles. These quantities were then multiplied by the unit price for both material as well as labor in order to attain the total estimated material and labor cost for that component. These two cost were then added to determine the total cost for the abutment.These blue values are highlighted in order to point out that only they will be plugged directly into another spreadsheet that will be seen in a min. In other words, this sheet was used in order to attain these total costs, and these total cost are then plugged into the final sheet rather than all of the other calculated values.Each of these components were calculated entirely by hand, and can be seen in the appendix portion of the appendix, with the exception of the roadway deck. Because of the repetitive but still varying nature of the spans (what I mean by that is unlike the bents which were nearly all the same, there were 6 different types of spans), we determined that a quicker way to approach this was with the use of Microsoft Excel. 16Cost Estimation: T-Head PlatformDESCRIPTIONQUANTITYUNITUNIT PRICETOTAL ESTIMATED MATERIAL COSTUNIT PRICETOTAL ESTIMATED LABOR COSTTOTALPlatform Deck & Framing:Timber Curb456LF$25.00$11,400.00$25.00$11,400.00$22,800.00Bollards4Each$2,500.00$10,000.00$500.00$2,000.00$12,000.00Cast-in-place Conc. Deck208.9C.Y.$100.00$20,890.00$400.00$83,560.00$104,450.00Finishing Conc. Deck7520S.F.$0.00$0.50$3,760.00$3,760.00Structural Steel - Beams62.5Ton$1,000.00$62,500.00$2,000.00$125,000.00$187,500.00Painting62.5Ton$200.00$12,500.00$200.00$12,500.00$25,000.00Piles & Pipe Bracing:42" x 0.500" Pipe Piles4080LF$155.00$632,400.00$125.00$510,000.00$1,142,400.0012" Vertical Bracing1321LF$38.00$50,198.00$40.00$52,840.00$103,038.0012" Horizontal Bracing1208LF$38.00$45,904.00$40.00$48,320.00$94,224.00Fender Connection to Pile20EACH$200.00$4,000.00$400.00$8,000.00$12,000.00Painting6609LF$4.50$29,740.50$4.50$29,740.50$59,481.00Fender System:188LF$1,500.00$282,000.00$1,500.00$282,000.00$564,000.00Roadway Bridge: (From Sheet 1)Abutment$20,215.05$33,590.25$53,805.30Levee Crossing$14,259.60$69,392.00$83,651.60Roadway Deck$915,800.00$547,300.00$1,463,100.00Roadway Bents$420,302.50$168,137.50$588,440.00Mooring Dolphins:2Each$300,000.00$600,000.00$300,000.00$600,000.00$1,200,000.00Walkway Bents:2Each$20,000.00$40,000.00$20,000.00$40,000.00$80,000.00Walkway Spans:4Each$10,000.00$40,000.00$10,000.00$40,000.00$80,000.00SUBTOTAL$3,212,109.65$2,667,540.25$5,879,649.90

This is the portion of the cost estimate where the rest of the unit quantities and total cost (without the additional expenses) were calculated. As you can see, the highlighted data from the roadway bridge spreadsheet has been inserted directly (already calculated) into this sheet. Most of this was done the same way as with the roadway with the exception of the dolphins, walkway bents and walkway spans. We were given a lump sum price for these items. The green highlighted values seen here at the bottom represent the project material, labor, and total cost, but this total cost is not the total price of the project.17Cost Estimation: Additional ExpensesDESCRIPTIONQUANTITYUNITTOTAL ESTIMATED MATERIAL COSTTOTAL ESTIMATED LABOR COSTTOTALSUBTOTAL$3,212,109.65$2,667,540.25$5,879,649.90Home Office Overhead (15% x Total Labor)$400,131.04Payroll Taxes, Ins, FICA, FUI, SUI, Gen Liability, Longshoreman Ins(80% x Total Labor)$2,134,032.20Indirects(15% x Total Material)$481,816.45Sales Tax(8% x Total Material)$256,968.77Mobilization $ De-Mobilization(Lump Sum = $100000)$100,000.00GRAND TOTAL =$9,252,598.36

In order to get the total project price, these values were used in the calculation of the additional expenses. For example, the home office overhead was estimated as 15% of the Total labor costext. Finally, these values on the right hand side hear can be summed up in order to arrive at the Grand Total cost. From this cost estimate procedure, we determined that the projects entire cost was around $9.25 Million.18PlansProposed General Arrangement

Shows Position of Roadway, Dock, and Dolphins

Selected Elevations Were Highlighted

Soil Borings are Indicated

PlansProposed Roadway Plan and ProfileShows Elevation of Road at Start of Ramp, Highway Crossing, Levee Crossing.Locations of the piles and the spread footings.The road way is 12ft wide.The span length is 1019 ft.

PlansSample BentA general view of the bent12ft wide, 10in thick concrete deck W36X135 steel girder . The pile used is a 24in diameter and run -50ft deep from it tip into the ground

ConclusionsT-Head Platform dock was chosen as the general cargo dock.Importance of permit acquisitionConstruction time of approximately 13 months.The total project cost was estimated to be around $9.25 Million

Questions

APPLICATION FOR DEPARTMENT OF THE ARMY PERMIT OMB APPROVAL NO. 0710-0003(33CFR325)Expires April 30, 2008

Public reporting burden for this collection of information is estimated to average 10 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Service Directorate of Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302; and to the Office of Management and Budget, Paperwork Reduction Project (0710-0003), Washington, DC 20503. Respondents should be aware that notwithstanding any other provision of law, noperson shall be subject to any penalty for filing to comply with a collection it it does not display a currently valid OMB control number Please DO NOT RETURN your form to either of those addresses. Completed applications must be submitted to the District Engineer having jurisdiction over the location of the proposed activity.

PRIVACY ACT STATEMENTAuthorities: Rivers and Harbors Act, Section 10, 33 USC 403;Clean Water Act, Section 404, 33 USC 1344; Marine Protection, Research and Sancutaries Act, 33 USC 1413. Principal Purpose: Information provided on this form will be used in evaluating the application for a permit. Routine Uses: This information may be shared with the Department of Justice and other federal, state, and local government agencies. Submission of requested information is voluntary, however, if information is not provided the permit application cannot be processed nor can a permit be issued.One set of original drawings or good reproducible copies which show the location and character of the proposed activity must be attached to this application (see sample drawings and instructions) and be submitted to the District Engineer having jurisdiction over the location of the proposed activity. An application that is not completed in full will be returned.

(ITEMS 1 THRU 4 TO BE FILLED BY THE CORPS)

1. APPLICATION NO. 2. FIELD OFFICE CODE 3. DATE RECEIVED 4. DATE APPLICATION COMPLETED

(ITEMS BELOW TO BE FILLED BY APPLICANT)

ADVANCE \D 1.405. APPLICANT'S NAME 8. AUTHORIZED AGENT'S NAME AND TITLE (an agent is not required)

6. APPLICANT'S ADDRESS 9. AGENT'S ADDRESS

7. APPLICANT'S PHONE NOs. W/AREA CODE 10. AGENT'S PHONE NOs. W/AREA CODE a. Residence a. Residence b. Business b. Business

11.STATEMENT OF AUTHORIZATION

I hereby authorize, to act in my behalf as my agent in the processing of this application and to furnish, upon request, supplemental information in support of this permit application.

APPLICANT'S SIGNATURE DATE

NAME, LOCATION, AND DESCRIPTION OR PROJECT OR ACTIVITY

12. PROJECT NAME OR TITLE (see instructions)

13. NAME OF WATERBODY, IF KNOWN (if applicable) 14. PROJECT STREET ADDRESS (if applicable)

15. LOCATION OF PROJECT

COUNTY STATE

16. OTHER LOCATION DESCRIPTIONS, IF KNOWN (see instructions) Section, Township, Range, Lat/Lon, and/or Accessors's Parcel Number, for example.

17. DIRECTIONS TO THE SITE

18.Nature of Activity (Description of project, include all features)

19.Project Purpose (Describe the reason or purpose of the project, see instructions)

USE BLOCKS 20-22 IF DREDGED AND/OR FILL MATERIAL IS TO BE DISCHARGED

20.Reason(s) for Discharge

21.Type(s) of Material Being Discharged and the Amount of Each Type in Cubic Yards

22.Surface Area in Acres of Wetlands or Other Waters Filled (see instructions)

23.Is Any Portion of the Work Already Complete? Yes No IF YES, DESCRIBE THE COMPLETED WORK

24.Addresses of Adjoining Property Owners, Lessees, Etc., Whose Property Adjoins the Waterbody (If more than can be entered here, please attach a supplemental list).

25.List of Other Certifications or Approvals/Denials Received from other Federal, State, or Local Agencies for Work Described in This Application. AGENCY TYPE APPROVAL* IDENTIFICATION NUMBER DATE APPLIED DATE APPROVED DATE DENIED

* Would include but is not restricted to zoning, building, and flood plain permits

26. To the best of my knowledge the proposed activity described in my permit application complies with and will be conducted in a manner that is consistent with the Louisiana Coastal Management Program. Application is hereby made for a permit or permits to authorize the work described in this application. I certify that the information in this application is complete and accurate. I further certify that I possess the authority to undertake the work described herein or am acting as the duly authorized agent of the applicant.

SIGNATURE OF APPLICANT DATE SIGNATURE OF AGENT DATE

The application must be signed by the person who desires to undertake the proposed activity (applicant) or it may be signed by a duly authorized agent if the statement in block 11 has been filled out and signed.

18 U.S.C. Section 1001 provides that: Whoever, in any manner within the jurisdiction of any department or agency of the United States knowingly and willfully falsifies, conceals, or covers up any trick, scheme, or disguises a material fact or makes any false, fictitious or fraudulent statements or representations or makes or uses any false writing or document knowing same to contain any false, fictitious or fraudulent statements or entry, shall be fined not more than $10,000 or imprisoned not more than five years or both.