GTRInewFormat.ppt-1Electronic Systems Laboratory
TMC Operator Requirements and Position Descriptions, Phase 2, Kickoff Meeting
Presented by Dennis J. Folds
GTRInewFormat.ppt-2Electronic Systems Laboratory
Disclaimer
• Georgia Tech is not yet under contract to UMTRI for this task
• Remaining issues are administrative – we expect them to be resolved quickly
• Some planned kickoff meeting items will be provided after the contract is in place• Draft project fact sheet
• Project management data
GTRInewFormat.ppt-3Electronic Systems Laboratory
Overall Technical Approach
• Conduct intensive review of Phase 1 material• Determine what Phase 1 material to include in
software tool
• Identify gaps in Phase 1 material, and develop material necessary for tool support
• Define functional requirements for interactive tool• Software capabilities
• User interface features
GTRInewFormat.ppt-4Electronic Systems Laboratory
Overall Technical Approach
• Determine software architecture and requirements• Platform requirements
• Software standards
• Configuration management
• Software design, development, and testing• Develop preliminary tool design and prototypes
• Finalize design
• Develop software
• Perform software testing
GTRInewFormat.ppt-5Electronic Systems Laboratory
Overall Technical Approach
• Usability testing of tool• Develop a usability test plan• Perform usability testing• Develop usability test report with recommendations
for modifications• Finalize interactive tool
• Documentation• Outreach material• Technical support
GTRInewFormat.ppt-6Electronic Systems Laboratory
Project Schedule
• Phase 1 review – Day 45
• Functional Requirements Document – Day 75
• Software Architecture and Software Requirements Documents – Day 120
• Usability Test Plan – Day 120
• Preliminary design and prototypes – Day 150
GTRInewFormat.ppt-7Electronic Systems Laboratory
Project Schedule
• Software Test Plan – Day 180
• Detailed Design Document – Day 210
• User Quick Reference Guide – Day 250
• Ready for testing software – Day 280
• Phase 1 revision material – Day 320
GTRInewFormat.ppt-8Electronic Systems Laboratory
Project Schedule
• Summary project report – Day 340
• Usability Test Report – Day 360
• Final tool – Day 400
• Detailed plan available in Microsoft Project
GTRInewFormat.ppt-9Electronic Systems Laboratory
Staffing Plan
• Dr. Dennis J. Folds – Task Order Lead
• Dana Stocks – Software Development Lead
• Jerry B. Ray, Jr. – User Interface Design Lead; will also develop prototype tool
• Tonya M. Whaley – Usability Testing Coordinator
• Above personnel were all involved in the TMC simulator project and the ErgoTMC website
GTRInewFormat.ppt-10Electronic Systems Laboratory
Plan for Tracking Comments
• Use of change tracking in Microsoft Word• Will provide electronic versions of revised
deliverables so that reviewer can see revisions
• Will provide summary documentation of responses to comments in table format in the transmittal letter for the revised deliverable
GTRInewFormat.ppt-11Electronic Systems Laboratory
Plan for Stakeholder Involvement
• Expect project advisory board to consist of• TMC managers (will also participate in usability
testing task)
• Contractor personnel experienced in TMC operations
• Individuals directly involved with development of Phase 1 material
• Other individuals named by FHWA
GTRInewFormat.ppt-12Electronic Systems Laboratory
Plan for Project Outreach
• Project presentation• Issues/challenges in current practice
• Purpose of project
• Outcome and findings
• Products developed
• Intended audiences
• Project fact sheet (draft to be provided)
GTRInewFormat.ppt-13Electronic Systems Laboratory
Mechanisms for Technical Interchange
• Teleconference Calls (monthly?)
• Net Meetings (quarterly?)
• VTC (?) if all parties have access
• One major TIM at TFHRC