H02569_OTC11928

Embed Size (px)

Citation preview

  • 8/11/2019 H02569_OTC11928

    1/13

    Copyright 2000, Offshore Technology Conference

    This paper was prepared for presentation at the 2000 Offshore Technology Conference held inHouston, Texas, 14 May 2000.

    This paper was selected for presentation by the OTC Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect anyposition of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the writtenconsent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. Theabstract must contain conspicuous acknowledgment of where and by whom the paper was

    presented.

    AbstractTo maintain profitability in the development of marginal

    fields, many new technologies and concepts have been

    exploited. One of the most promising technologies has been

    the Intelligent Well Concept, which allows the operator to

    produce, monitor and control the production of hydrocarbons

    through remotely operated completion systems. These

    systems are developed with techniques that allow the well

    architecture to be reconfigured at will and real-time data to be

    acquired without any well intervention. This paper concerns a

    case history in the Gulf of Mexico in which an operator was

    able to justify completion of marginal wells based upon thecost savings generated from innovative technologies.

    The completion methods chosen for this development were

    successful because of careful preplanning for all phases of the

    completion scenario and proved that close interaction among

    all suppliers and parties involved in the actual equipment

    purchasing, interface issues, and all operational strategies is

    critical for project success. These topics will be discussed in

    depth. Detailed test programs were implemented during the

    design and manufacturing processes to eliminate field failures.

    In this case, testing revealed system issues that ultimately led

    to the use of an alternative design.

    Also shown is the importance of allowing the proper

    amount of time to adequately plan and test these systems for

    their specific applications in order to assure delivery of a

    design that can meet the functional requirements for that

    application. In this case, although the system design was

    changed, the original functional goals were met. Two wells in

    this field were completed in April and July 1999. An

    additional well may be completed in early 2000.

    IntroductionThis case history is the first in the Gulf of Mexico in which

    intelligent completion technology was used. The field is

    located offshore in approximately 3300 ft of water. Fig. 1

    indicates field location. The field is comprised of sand unit

    that are vertically and laterally discontinuous across the

    breadth of the field. With the need for multiple take points in

    the layered reservoir system, the operator had developed a

    depletion plan, which described the order in which the

    different zones would be accessed to maximize both reserves

    and upfront production.It had been recognized early on that there was a need for

    lower overall cost solutions to develop this field because of its

    marginal reserves. Many innovative techniques from the

    incorporation of a mini-TLP platform to unique pipeline

    systems were planned, and it was felt that the use of intelligen

    completion systems could maximize field development. Fig. 2

    shows an intelligent well configuration used in this field.

    The wells were to be completed with stacked gravel packs

    to produce two independent zones. The intelligent completion

    would allow the operator to monitor pressure and temperature

    from either zone and to produce from the lower zone, the

    upper zone, both zones, or neither. The wells were also to be

    completed in different sands to optimize current well location

    and to maximize producing and sustainable production rates.The zones were completed simultaneously with the

    intelligent completion system run as part of the production

    tubing string. This was done to minimize and/or eliminate the

    need for future well interventions to initiate changes in

    production from either of the producing intervals.

    Pre-PlanningAs stated earlier, the use of intelligent completion technology

    requires a different and more involved type of pre-planning

    than conventional completion work.1 The intelligen

    completion directly affects the subsea interface, tubing hanger

    the umbilical to the production vessel or platform, topsides

    and the permanent completion itself. Thus, it is important tostart in-depth planning early in the life of the project to

    effectively interface multiple systems.

    In this case history, project planning for the intelligent

    completion system began a year and a half prior to installation

    The intelligent completion used was an electro/hyraulic

    system. Although there are other types of intelligen

    completion systems, the electro/hyraulic systems often require

    more interface consideration than pure hydraulic or electrical

    OTC 11928

    Case Study: First Intelligent Completion System Installed in the Gulf of MexicoV. B. Jackson, SPE, Halliburton Energy Services, Inc. and T. R. Tips, SPE, Petroleum Engineering Services, Inc.

  • 8/11/2019 H02569_OTC11928

    2/13

    2 V. B. JACKSON AND T. R. TIPS OTC 11928

    systems. Following is a description of the equipment chosen

    for the completion, and why it was chosen over other

    alternatives.

    Subsea Interface and Direct UmbilicalA seamless interface for control of subsea systems can be

    created with the use of a direct umbilical with dedicated

    electric and hydraulic lines from the production platform. Adirect hydraulic system was used, as the wells are a short

    distance from the field surface facility. A direct umbilical

    from the platform was connected to each template, and the

    individual wells were then connected to the templates. The

    direct umbilical requires less interface work than does a

    subsea pod and is used in applications in which the wells are

    clustered around one or several points, or all the wells are near

    the production vessel or platform.

    To control subsea systems using direct hydraulic

    umbilicals, it is important to note the type of umbilical being

    specified. The density of the hydraulic fluid for the intelligent

    completion system will affect the burst and collapse rating

    required. The oil-based fluids, having a lower specific gravitythan the water-based fluids, require higher collapse resistant

    umbilical passages. The other factor directly affecting the

    intelligent completion system is the type of umbilical

    flexible thermoplastic hose or stainless steel/incoloy type line.

    The flexible umbilicals have non-linear expansion

    characteristics and can make valve characterization and

    precise movement more difficult, though adequate techniques

    have been developed for the short umbilical lengths used in

    the case described.

    The use of a direct umbilical over long distances can be

    both costly and inefficient as the line loss on the electric lines

    becomes inhibiting, and the response time on the hydraulic

    lines becomes unacceptable. In these instances or when the

    wells are scattered over a large area, the use of anelectro/hydraulic subsea control system may be more cost

    efficient and design effective.

    Subsea Pod/Control ModuleAn alternative method for controlling an intelligent

    completion is through the use of a subsea pod.2 An

    electro/hydraulic umbilical is run from the master control

    station (MCS) to a pod system subsea. Power (both electric

    and hydraulic) and communication are transmitted subsea via

    an electro/hydraulic umbilical before being split off to the

    individual wellheads or production manifold.

    Subsea control modules are used when the wells are

    located far from one another or when the wellheads are farfrom the production vessel or platform. The use of a subsea

    pod requires detailed interfacing with the subsea control

    system. If the intelligent completion system is to be controlled

    from the surface through the master control system on the

    platform or production vessel, an interface at the pod will be

    required to communicate with the downhole tools.

    The added complication of communication protocol from

    the MCS to the wellhead to the downhole intelligent well

    completion system requires additional time for pre-planning

    and interface development. If possible, the intelligent wel

    completion system supplier should be involved prior to the

    contract award of the subsea pod system. Detailed

    engineering work may be required to develop a contro

    interface to supply hydraulic and/or electric power and signa

    to the downhole intelligent well system components.

    If a subsea electro/hydraulic production control system hadbeen used instead of the direct umbilical, the modifications

    made late in project life might not have been possible. The

    control system integration, once complete, is fixed, and the

    method of supply of hydraulic fluid to the intelligent

    completion system cannot be altered.

    There are additional problems during installation of the

    system when its function is to be tested from the rig. The

    direct hydraulic/hardwired system allowed for the intelligen

    completion system to be completely function tested from the

    rig prior to leaving the well.

    Tubing Hanger

    The field has been completed with horizontal subsea trees thaaccommodate eight tubing-hanger penetrations. The

    intelligent completion system used is comprised of dual

    hydraulic/electric encapsulated flatpacks between the tubing

    hanger and the downhole equipment for redundant electric

    control. The hydraulic system is not redundant due to design

    modifications, which will be discussed later. Low reservoi

    temperatures and the specific oil characteristics encountered

    required the use of two chemical injection subs and a deep-set

    tubing-retrievable subsurface safety valve (TRSSV). The

    TRSSV is a hydraulically redundant system, using two

    independent control lines. Thus, the tubing hanger required

    eight penetrations six hydraulic and two electric.

    The number of possible penetrations differs according to

    tree manufacturers; therefore, this issue must be addressedearly in the process planning. This will allow the tree

    manufacturer sufficient time to design the tubing hanger with

    the necessary penetrations. Ideally, since the tubing-hanger

    interfaces with the intelligent well completion equipment, the

    interface requirements should be identified prior to obtaining

    the bid for the tubing subsea trees as was done in this project

    case.

    Topsides/ElectricalIn the case of the hydro/electric intelligent completion system

    used, the topsides interface involves electrical communication

    via a surface control unit and a stand-alone computer in a 19-

    in. rack mount system. The platform computer is linked via aModbusinterface to the MCS on the platform such that well

    temperature, pressure, and sleeve position can be monitored

    from the MCS. A PC Anywherecomputer software system

    was also installed so that an engineer in an onshore office

    could look at the platform computer and identify faults or

    install minor system upgrades.

    The electrical interface can be designed as per the specific

    project. These modifications need to be addressed and

  • 8/11/2019 H02569_OTC11928

    3/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 3

    specific requirements identified by the end user (i.e.

    production manager, production engineer, or reservoir

    engineer) early in project development as the process of

    software and integration testing can be complex and time

    consuming.

    Sufficient time must be allowed for internal system testing

    along with the MCS, subsea tree, or other systems in which

    interfacing is required. Software testing and communicationprotocol is an ongoing process. After well completion and

    platform commissioning, software upgrades and modifications

    must be capable of being handled from the surface. Therefore,

    all components of the intelligent well completion system

    gauges, position sensors, solenoid valve controls, subsea pod

    interface, MCS, etc. must be verified and checked. The

    topsides interface must be compatible with all the equipment

    in the system and be able to identify that each system is

    functional.

    HydraulicsHydraulic Fluid Selection. In addition to the effect on the

    subsea umbilicals, hydraulic fluid has a direct impact on thetopsides configuration of the platform. If the intelligent

    completion system uses the same hydraulic fluid as other

    systems in the wellbore (i.e. TRSSV), the same fluid reservoir

    can be used. However, if the hydraulic fluid to be used by the

    intelligent completion system differs due to completion fluid

    compatibility, reservoir fluid compatibility, specific gravity

    requirements, environmental concerns of venting to the sea

    floor, etc., separate fluid reservoirs, hydraulic power units

    (HPU), and separate filtering systems will be required.

    Hydraulic Power Unit (HPU). The hydraulic interface can

    be integral and operated by the MCS, a separate HPU, or

    manually operated valves in conjunction with the MCS. The

    HPU provides hydraulic power from the platform to the

    subsea tree, and eventually, to the intelligent completion

    system.

    The hydraulic system can be tied in directly to the MCS

    such that the MCS controls the HPU for all systems on the

    platform, including the intelligent completion system. With

    integral MCS functioning, the system can be automated from

    the platform. A subsea pod system will require integral HPU

    functionality, and it can be implemented in a direct umbilical

    installation as well.

    The simplest method is an HPU solely dedicated to the

    intelligent completion system. This requires manual

    intervention to turn the HPU on prior to functioning the

    equipment. This method can be implemented only with directumbilical or platform applications and eliminates the need for

    interfacing the topside systems, though umbilical interfacing

    may be required.

    Downhole CompletionCompletion hardware size, weight, and grade of smallest

    inner diameter of casing, liners, or gravel pack base pipe

    dictates what types of intelligent completion equipment can be

    used. As an example, the intelligent completion equipmen

    installed in these GOM wells was set above the 7-in. liner

    This was done to maximize flow area from both the upper and

    lower zones and to allow clearance for the hydro/electrical

    flatpacks connected at the top of the production packer.

    The intelligent completion system is run on the production

    tubing. The hydraulic and electric lines are clamped to the

    tubing using over-the-coupling clamps. Clearance around theclamps is critical as it should not be too small, which might

    crimp the lines or hinder production, or too large, which

    would result in decentralized equipment.

    The downhole completion usually requires interfacing

    between numerous service companies and equipmen

    providers. In the Gulf of Mexico completions, the projec

    involved no less than 10 companies, each of which handled

    significant portions of work. Different vendors were

    employed for spooling, TRSSV equipment, gravel packing

    intelligent well completion technology, tubing testing, the rig

    perforating, subsea tree company, well testing, etc. A pre

    spud meeting, which proved helpful in communicating

    possible concerns regarding the equipment involved, was held

    in October 1998.

    Zonal IsolationMechanical. The operator used two types of zonal isolation

    techniques to mechanically isolate the formations from the

    kill-weight fluid in the wellbore. The lower-zone gravel pack

    had isolation sleeve ports, which were to be opened by

    slickline after the tubing was landed and the well-testing

    commenced. To isolate the lower-zone production from the

    upper zone, a flow tube was run through the upper gravel-pack

    assembly and stung into the PBR of the lower-zone gravel-

    pack packer. Flow from the lower zone produces up the flow

    tube, around the slickline nipple in the intelligent completion

    system, and into the flow ports of the dual-zone intervacontrol valve (DZICV) inside the shroud (Fig. 3).

    The upper-zone gravel pack contains integral pressure-

    actuated valves3 to isolate the upper zone while running

    tubing, landing the hanger, circulating packer fluid, and setting

    the production packer. This was necessary because the flow

    tube described above isolates the upper zone from any

    slickline manipulation of sliding sleeves, etc. The upper zone

    is produced around the flow tube, between the OD of the

    shroud and the ID of the production casing, and into the flow

    ports of the DZICV. (Fig. 4)

    Hydraulic. The other viable means of zonal control and

    isolation is maintaining kill weight fluid without independenisolation between the two zones. If the zones are of similar

    pressure regimes, a kill weight fluid can be optimized to

    decrease the damage created by the fluid. However, if the

    zones are at significantly different pressures, the zone of lesser

    pressure may experience significant damage and costly fluid

    loss may result.

  • 8/11/2019 H02569_OTC11928

    4/13

    4 V. B. JACKSON AND T. R. TIPS OTC 11928

    The Intelligent Well Completion SystemSystem OverviewThe original system design contained a single DZICV to

    isolate production from either zone or to produce from both

    simultaneously or neither. The valve was to be actuated

    through a redundant system utilizing actuator electronic

    modules (AEMs). As the downhole control system, the AEM

    responds to information and command requests from thesurface control unit and reacts accordingly. The AEM also

    communicates to the solenoid valves, which are used to

    control valve movement and to set the packer.

    Hydraulic Set Retrievable PackerThe production packer is a hydraulic set (minimal lateral

    motion while setting) retrievable packer. The packer

    incorporates five feed-through ports to pass -in-OD

    hydraulic or electrical lines through the packer. It is not

    necessary to terminate the lines at the packer as they are fed

    through the top of the packer, between the slips and elements,

    and the packer body. The pass-through sections then seal the

    annulus above the packer from the annulus below the packerwith proprietary connections.

    The original design of the system had incorporated a

    solenoid valve to allow hydraulic pressure to reach the packer

    setting chamber to set the packer. This function is fully

    automated and the only method by which the packer can be set

    is with direct hydraulic communication into the packer setting

    chamber. The packer sets through realization of differential

    pressure between the packer setting chamber and the annulus.

    The packers require 4,500 psi differential to set.

    Dual Zone Interval Control Valve (Fig. 5)A four-position thermoplastic sliding sleeve, the DZICV,

    allows the following production options with production from

    the bottom-most position to the top-most position 1) lower

    zone only, 2) both zones closed, 3) upper zone only, and 4)

    both zones open. The 2ndposition both zones closed was

    designed to allow an intermediate position between zones such

    that the operator could be assured that crossflow could not

    occur. This position may also be important if the reservoir

    liquids prove to be incompatible with one another. The

    implications of these four positions and the order in which

    they exist in the valve became significant when problems

    arose with the hydro/electronics package.

    The intermediate position of both zones closed is also

    critcal if there is a large pressure difference between the two

    zones. This position allows the pressure in the tubing to be

    altered from the platform to within the acceptable operatinglimits for DZICV function of 1500 psi differential.

    Solenoid ValvesIn the system as originally designed, in order to operate the

    valves and set the packer, solenoid valves are used to direct

    hydraulic fluid to the open or closed side of the actuated

    piston. Power and command functions are sent via the

    instrumentation wire in the flatpack. The system contains five

    solenoid valves two normally open (to provide hydraulic

    communication to additional tools), two normally closed (to

    actuate the valve), and a fifth normally closed (to provide

    hydraulic power to an auxiliary mechanism such as a packer)

    Unlike the systems installed in other areas, the two normally

    open solenoid valves were not necessary as there was only one

    DZICV in the system.4

    A system containing solenoid valves, though noinherently less reliable, is more complex than one withou

    solenoid valves. It was suggested in July 1998 that an option

    be developed to actuate the DZICV by directly connecting to

    the open and closed sides of the actuated piston housing. (See

    Figs.6and 7) Due to time constraints and delivery schedules

    this option was not fully pursued at that time. However, the

    idea would eventually be adopted for these completions. The

    advantages and disadvantages to the direct hydraulic option

    are:

    Advantages:

    With the solenoid system, several single point electrical

    failures render the valves inoperable without slicklineintervention.

    The direct hydraulic system is not dependent on electricalcomponents for actuation. The direct hydraulic system

    requires at least two electrical failures to prevent

    actuation.

    The direct hydraulic system is less complex, and thus, canbe more cost effective.

    Disadvantages:

    Production from more than two indepenedent zones willrequire additional hydraulic lines, as the system is no

    longer multiplexed.

    The hydraulic supply to the intelligent completion system

    is no longer redundant. If a subsea pod is used, a direct hydraulic system becomes

    much more complex than the standard electro/hydraulics

    module as hydraulic steering would have to be designed

    to take place in the pod system. While the intelligent

    completion equipment would be simpler, the intelligent

    system would be more complex.

    System integration during which the valve section

    (DZICV) is attached to the position sensor and the electronics

    module containing the solenoid valves, gauges, and position

    sensor feedback began in January 1999. The hydro/electronic

    modules had been fully tested in late 1998 to 16,000 ps

    absolute pressure and 235F. System integration involve

    connection of the appropriate hydraulic outlets to the pistonhousing and the appropriate electrical outlets to the position

    sensor. The system is then function tested at 120% o

    reservoir pressure and temperature.

    The first integrated DZICV left Houston on January 12

    1999. The tools were shipped to Houma, Louisiana for fina

    stack-up and function testing. Stack-up involves incorporating

    the DZICV, the packer, necessary slickline nipples, pup joints

    and other miscellaneous equipment for installation offshore

    During stack-up testing, an anomaly was noted with the

  • 8/11/2019 H02569_OTC11928

    5/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 5

    solenoid valves. It was confirmed that power and

    communication were reaching the hydro/electric module, but

    it was not possible to move the sleeve into the closed position.

    It became apparent after additional testing that one of the

    normally closed solenoid valves was not functioning correctly.

    The tools were shipped back to Houston to identify

    whether the problem involved a single-point failure, or

    whether the solenoid valve problem was inherent in all of thesolenoid valves being used for the equipment. Design

    modification had been done on these solenoid valves to

    increase pressure rating and improve corrosion resistance

    through the use of CRA material. While investigative testing

    was being conducted on the first of the three sets of

    equipment, the second set of equipment began experiencing a

    similar problem.

    While integrating the second set of equipment, a similar

    but not identical problem arose with one of the normally

    closed solenoid valves. While the first experienced a problem

    in which the solenoid ball would not come fully off-seat, the

    second set experienced a problem in which the ball acted as if

    it was not fully off-seat or fully on-seat. The ball was floating

    in the chamber such that the solenoid valve could not supply

    pressure to the actuated piston housing, or would not fully

    close. When the valve was instructed to close, fluid would

    continue to bleed back through the inlet port.

    Design modifications were considered as well as whether

    sufficient time remained prior to the delivery date to design,

    qualify, and build new solenoid valves. Given the time

    constraints on delivery, it was decided that alternative

    solutions would need to be devised. The option of connecting

    directly to the piston housing with the hydraulic lines in the

    flatpacks was revisited. It was recognized at the time that the

    direct hydraulic option was feasible in this application because

    1) direct hydraulic umbilicals would be used, and 2) a single

    DZICV could still be controlled with the two availablehydraulic lines.

    A test was conducted to attempt to control the valve with

    hydraulic pressure and the information obtained from the

    position sensors. It was not known whether the valve could be

    stopped at a discrete position with direct hydraulic control.

    The test was conducted through approximately 5500 ft of

    flexible umbilical and 10,300 of -in. 0.049-in. wall thickness

    hydraulic line per side of the actuated piston housing.

    Testing concluded that the valve could be stopped at an

    intermediate position with the use of position sensors.

    Attempts were made to quantify the accuracy of volumetric

    displacement. A specific volume of fluid was bled from the

    open or closed side of the piston, and valve motion wasmeasured. The exact distance of valve travel was found to be

    inconsistent with the volume of hydraulic fluid removed. (i.e.

    50 ml may equate to 2-in. of valve motion or it can equate to

    2.25-in. of valve motion) The 4-position position sensors such

    as are used in these tools have a finite distance of travel to be

    on position. The volumetric displacement was neither exact

    nor repeatable. This is due to the flexible subsea umbilical

    and the static friction pressure of the actuated piston.

    Testing concluded that the only means to verify position in

    this application is with the use of position sensors. A position

    of full up or full down can be obtained by monitoring

    pressure response or the cessation of bleed fluid on the drain

    side of the piston. The intermediate positions both zones

    closed or the upper zone open require position sensors to

    indicate to the operator of the valve when to equalize the

    pressure and stop the motion.

    At the conclusion of the test, the decision was made to usethe direct hydraulic solution. This option required the

    development of other devices, such as the packer setting sub

    These devices were subsequently developed and tested.

    It is important to note that although the aforementioned

    solenoid valve-control issues were subsequently solved, the

    operator elected to continue using the direct hydraulic solution

    for subsequent well completions. This choice was primarily

    made to maintain compatibility throughout the field and for

    the technical advantages stated earlier.

    Packer Setting MechanismsThe intelligent completion system uses a hydraulic-set

    minimal-vertical-motion-during-setting, retrievable packerAs mentioned previously, the original design involved use of a

    solenoid valve to provide hydraulic force to the packer setting

    chamber. Due to the system modifications discussed above

    an alternative solution was required.

    A slickline setting sleeve was developed to allow the

    operator to set the packer through application of tubing

    pressure. The setting sleeve is pressure balanced while

    running in the hole to avoid premature packer setting and is

    isolated from the packer setting chamber to allow the tubing to

    be tested during the completion.

    PreparationA focused effort on project engineering for the intelligent

    completion portion of this project began in November 1997

    Detailed scheduling and requirement documentation was

    started at this time to reconcile any differences and develop a

    design basis for the equipment. The DZICV, packer, the filte

    mandrel (which eventually would not be used), the particular

    version of the electro/hydraulic module, and the contingency

    size packer, were all first-time builds that required prototype

    design and testing. Three sets of intelligent completion

    equipment were ordered one for each well and one backup

    system.

    The long lead-time (greater than a year in this instance)

    required the operating company, the service companies, and

    all other equipment suppliers to become involved early in the

    process. A representative of the intelligent well system wamade a member of the operators drilling and completions

    team and served to coordinate efforts and resolve interface

    issues for more than a year, through the time of installation

    With current installations still essentially one of a kind per

    every field design, intelligent completion projects can not be

    completed in a couple of months. The many issues and

    interface questions should also be considered as an ongoing

    effort with all concerned throughout the project planning.

  • 8/11/2019 H02569_OTC11928

    6/13

    6 V. B. JACKSON AND T. R. TIPS OTC 11928

    DesignDetailed design work began in March 1998 on the DZICV, the

    packers, and the modifications to the then current model of the

    electro/hydraulic module. Various sizes of this packer style

    had been developed, tested, and successfully installed, though

    the two sizes discussed above were new developments.

    TestingIntegration. As mentioned previously, the equipment must be

    tested several times. The first systemtest is conducted after

    make-up of the electro/hydraulic module to the DZICV. The

    system is function tested at ambient conditions, pressure tested

    to 7500 psi (internal-external differential), and then, the

    system is put into a test element and heated for 12 hours at

    120% reservoir temperature. 120% of reservoir pressure is

    applied, and a full hydraulic and electrical function test is

    conducted. At the conclusion of this environmental test, the

    equipment is pressure tested to 7500 psi to verify seal

    integrity.

    Stack-Up. The DZICV assembly is shipped for final make-upin the district office. The packer, DZICV w/shroud, and pupjoint with slickline nipple to divert flow are made up and

    tested to 7500 psi differential. A full function test is

    conducted, and the make-up of the full assembly begins. (Fig.

    8).

    After pulling the lines through the packer, the hydraulic

    lines are made up to the piston housing and the electric lines

    are made up to the inlet ports of the electro/hydraulic module.

    The connections are externally tested for 15 minutes at 10,000

    psi. The hydraulic lines are then tested to 7500 psi working

    pressure, thus testing the piston seals. An electro/hydraulic

    splice sub was used so that the lines could be fed through the

    packer in the workshop, decreasing rig make-up time. A body

    test was again performed to verify seal integrity and to test theslickline nipple and plug.

    The stack-up testing is critical to ensuring field success.

    The extensive function testing is beneficial not only in

    verifying equipment integrity, but also as a means to

    familiarize the operations personnel with the particular

    installation. The personnel who will be performing the job are

    also responsible for making sure the equipment is fully

    checked and tested prior to shipping.

    Installation. As with other phases of the project, extensive

    pre-planning was required prior to installation. Multiple pre-

    spud meetings and rig visits allowed all service companies and

    suppliers the necessary interfacing to coordinate efforts. Bestpractice documentation for the intelligent completion system

    was coordinated with other installation teams in the North Sea

    to ensure the best installation possible.

    The first intelligent completion system in the Gulf of

    Mexico was installed in April 1999 with a six-man crew

    splitting the work into roughly two shifts. The equipment was

    shipped offshore as a full assembly as described above. A

    complete function test was again completed on the deck, and

    the body test was repeated. The slickline lock and plug were

    removed, and the assembly was visually inspected prior to

    picking up in the rotary table.

    After picking up into the rotary table, the hydro/electric

    splice sub was connected to the flatpacks. The two electric

    and two hydraulic terminations were made up and tested

    followed by the make-up of the packer setting sub located

    approximately 40 ft above the packer. Cross-couplingprotectors were used to protect the control lines and to hold

    tension on the flatpacks at each tubing joint. Specia

    provisions were made by the chemical injection manufacturer

    and the TRSSV manufacturer to protect the flatpacks around

    the equipment. Function testing of the intelligent completion

    system was ongoing while running the completion.

    After picking up the tubing hanger, the intelligen

    completion system was functioned prior to terminating the

    lines. The tubing hanger was made up and run to the mudline

    There was no electric communication until after the tubing

    hanger was hard landed. This is a critical test of the

    equipment to verify that the DZICV would not move from

    position and that electric communication would be restored

    The first verification that the sleeve had remained in the

    closed position was a positive test of the seal assembly in the

    lower gravel-pack packer. Electric communication was

    reestablished with all equipment.

    The valves were moved to the upper-zone open position to

    allow for packer fluid circulation. The DZICV was closed

    and a slickline plug was set in a back-up slickline-accessible

    sliding sleeve, which had been run below the DZICV. A

    slickline trip opened the packer setting sub. The tubing wa

    pressurized, and the packer set. The final process for the

    completion was to flow test each zone independently.

    Functionality. The original design of the intelligen

    completion system used an electro/hydraulic module withintegral solenoid valves, pressure and temperature gauges, and

    position sensors. While system testing was being conducted

    the solenoid valves began experiencing erratic behavior

    System modification began in January 1999 to modify the

    design and take the solenoid valves out of the system.

    For this particular application a direct subsea umbilica

    (similar to platform completion for this discussion) with a

    single valve controlling two zones the change to a direc

    hydraulic solution was both functional and appropriate. If a

    subsea pod had been used or if the design had not allowed two

    hydraulic lines to control all valve positioning, an alternative

    solution would have been required.

    Conclusions1. Several intelligent completion systems have successfullybeen installed in the Gulf of Mexico, expanding on the

    installation experience in the North Sea and Adriatic. The

    elimination of planned well intervention has allowed the

    operator to additionally enhance field economics.

    2. The fully integrated intelligent completion system placesthe responsibility and control of each portion of the projec

  • 8/11/2019 H02569_OTC11928

    7/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 7

    under the onus of the responsible individual or company and is

    an ongoing committment. This allows for system

    modification and design review when necessary.

    3. The coordination of all parties involved with thecompletion is critical to project success. Without early and

    constant involvement, critical interface issues may be missed.

    The operator, all service companies, and other suppliers must

    work as a team to insure that project goals are met.4. In these completions, the flexibility of the team allowedthe intelligent completion system to be modified late in the life

    of the project. Without this flexibility, project delays would

    have occurred, as the equipment would not have been

    delivered on time.

    AcknowledgementsThe authors would like to thank Halliburton Energy Services,

    and PES, Inc. for support and permission to publish this paper.

    The authors would also like to thank all the people involved in

    this project for their support in bringing the project to a

    successful conclusion.

    References

    1. Robison, C.E. Overcoming the Challenges Associated with the LifeCycle Management of Multilateral Wells: Assessing MovesTowards the Intelligent Well,paper OTC 8536, presented at the

    1997 Offshore Technology Conference held in Houston, Texas, 5-

    8 May 1997.2. Botto, G., Giuliani, C., Maggioni, B., Rubbo, R. Innovativ

    Remote Controlled Completion for Aquila Deepwater Challenge,paper SPE 36948, presented at the 1996 SPE European Petroleum

    Conference held in Milan, Italy, 22-24 October 1996.

    3. Worlow, D.W., Grego, L.V., Walker, D.J., Green, G.R., SmithB.E., Harris, M.E. Pressure-Actuated Isolation Valves for FluidLoss Control in Gravel/Frac-Pack Completions, paper SPE

    58778, presented at the 2000 SPE International Symposium on

    Formation Damage held in Lafayette, Louisiana, 23-24 February2000.

    4. Lie, O.H., Wallace, W. Intelligent Recompletion Eliminates theNeed for Additional Well, IADC/SPE Paper No. 59210 presented

    at the 2000 IADC/SPE Drilling Conference held in New Orleans

    Louisiana, 2325 February 2000.

    SI Metric Conversion Factorsin x 2.54* E + 01 = mm

    psi x 6.894 757 E + 00 = kPa

    ft x 3.048* E - 01 = m

    F (F 32)1.8 = C

    Conversion factor is exact

    Modbusis a registered trademark of Modicon, Inc.

    PC Anywhereis a registered trademark of Symantec, Inc.

    Fig. 1 Field Location

    Intelligent Completion System Installation

    Gulf of Mexico

    Louisiana

  • 8/11/2019 H02569_OTC11928

    8/13

    8 V. B. JACKSON AND T. R. TIPS OTC 11928

    Fig. 2Intelligent Well Completion

    7" 38.00#

    RKB - MSL -- 99.0'

    PBTD - Cmt Retainer

    9-5/8" 53.50#

    Water Depth -- 3,226'

    CI

    CI

    SCSSV

    7" 26-38# Sump Pkr

    4" 13Cr, 0.008 ga prepack screen2-3/8" 4.70# isolation assembly

    w/1.875" ID sliding sleeves

    7" 32-38# GP Pkr

    4" 13Cr, 0.008 ga screen w/3 PAVs per jt2 - 2.813" ID sliding sleeves

    7" 32-38# GP Pkr

    DZICV w/integral DHPT

    9-5/8" HF-1 Pkr

    Chem Inj Mandrel

    Chem Inj Mandrel

    DZICV OperationPosition Lower Zone Upper Zone 1 open isolated 2 isolated isolated 3 isolated open 4 open open

    9-5/8" 53.50#, Tie-back

    Production Tubing

    3-1/2" 10.20#, 13Cr85, VAM Ace

    10K SpoolTree @ 3,311'

    SCSSV

    2-3/8" 4.70# Isolation Tubingw/ATR seals

    PSSPacker Set Sub

    11-3/4"

  • 8/11/2019 H02569_OTC11928

    9/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 9

    Fig. 3Lower-Zone Production

    SCSSV Control Line

    Chemical Injection Line

    PES FlatpackControl Umbilical

    SCSSV

    Dual Splice Sub

    Cross-Coupling Protector

    Hydraulic Set Packer

    Electro/Hydraulic Module

    Sliding Sleeve (DZICV)

    Plug

    Upper Zone Gravel Pack

    Lower Zone Gravel Pack

    PBR IsolatesUpper and Lower Zones

    Methanol Injection Valve

    Chemical Injection Valv e

    Shroud

    Position Lower Zone Upper Zone

    1 open closed

    2

    3

    4

    Sleeve Operation

    Packer Setting Sub

    closed closed

    closed open

    openopen

  • 8/11/2019 H02569_OTC11928

    10/13

    10 V. B. JACKSON AND T. R. TIPS OTC 11928

    Fig. 4Upper-Zone Production

    SCSSV Control Line

    Chemical Injection Line

    PES FlatpackControl Umbilical

    SCSSV

    Dual Splice Sub

    Cross-Coupling Protector

    Hydraulic Set Packer

    Electro/Hydraulic Module

    Sliding Sleeve (DZICV)

    Plug

    Upper Zone Gravel Pack

    Lower Zone Gravel Pack

    PBR IsolatesUpper and Lower Zones

    Methanol Injection Valve

    Chemical Injection Valve

    Shroud

    Position Lower Zone Upper Zone

    1 open

    2

    3

    4

    SleeveOperation

    Packer Setting Sub

    closed

    closed

    open

    closed

    closed

    open

    open

  • 8/11/2019 H02569_OTC11928

    11/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 11

    Fig. 5Dual-Zone Interval Control Valve (DZICV)

    Upper Actuator Seal(UA)

    Lower Actuator Seal(UA)

    Upper Isolation Seal(UI)

    Middle IsolationSeal (MI)

    Lower Isolation Seal(LI)

    mingle Position

    Upper Zone Only Position

    Closed Position

    Lower Zone Only Position

    Com

  • 8/11/2019 H02569_OTC11928

    12/13

    12 V. B. JACKSON AND T. R. TIPS OTC 11928

    Fig. 6Electro/Hydraulic Module and ICV w/Solenoid Valves

    Fig. 7Hydraulically Actuated ICV

    Hydraulically Actuated ICVTUBINGHANGER

    HF-1PACKER

    SSSV

    TUBING

    INTERVAL CONTROLVALVE

    SUBSURFACE

    SAFETY VALVE

    PACKERSETTINGPISTON

    PACKER SETTING SUB

    Hydraulic Piston Up

    Hydraulic Piston Down

    Electro/Hydraulic Module and ICV w/Solenoid ValvesTUBING

    HANGER

    HF-1

    PACKER

    Hydraulic Line #1

    ANNULUS

    SSSV

    TUBING

    SOLENOID VALVE

    SOLENOID VALVE

    INTERVAL CONTROLVALVE

    SUBSURFACESAFETY VALVE

    PACKERSETTINGPISTON

    Hydraulic Line #2

  • 8/11/2019 H02569_OTC11928

    13/13

    OTC 11928 CASE STUDY: FIRST INTELLIGENT COMPLETION SYSTEM INSTALLED IN THE GULF OF MEXICO 13

    Fig. 8Direct Hydraulic Stack-Up

    Through Tubing Hydraulic

    Set Retrievable Packer

    Direct Hydraulic Sleeve for

    Dual Zone Control

    Shroud for Dual Zone Control

    Slickline Plug

    Dual Flatpack Splice Sub w/

    two pass through slots for

    packer-set-sub lines.

    Clamps on filter mandrel at topof packer.

    Electro/Hydraulic Module

    Permits Control and

    transfer of Downhole datatelem try, Gauges, Position

    sensor and Solenoid Valve

    Activation.

    Position Sensor

    Indicates Sleeve positionvia communications with

    the electro/hydraulic

    module.

    e