Document title: Lorne_109_110_HP Version No.: 1 Page 1 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
Hardwood Forests Division
Harvest and Haul Plan
State Forest Lorne Compartments 109, 110
Management Area Kendall IFOA Region Lower North East
Harvest Plan No. 60835 Supply Zone /
Price Zone
3 /
Kendall
Legal Conditions Native Forest Harvesting in accordance with IFOA conditions.
To implement this plan you must hold a current Contractors Licence.
Standard Harvest Plan Conditions and Operating Procedures apply.
Survey expiry date for this plan is 12/10/2027
Unmapped drainage lines are managed under EPL and are not to be logged. FT/HC to assess whether UMDL encountered are drainage lines or drainage depressions. Refer to SOP 1 for further information.
Certification Timber products removed from the plan area are within the Defined Forest Area covered by the Responsible Wood Certification Scheme and ISO14001 Certificate 13761
Prepared by Planner
Date: 12/09/2018
Dirk van Dijk
Approved by Planning Supervisor
Date: 12/09/2018
Brent Bailey
Abbreviations FT = Forest Technician, HC = Harvesting Coordinator, PtS= Protection Supervisor, HS = Harvesting Supervisor, RC = Roading Coordinator, Crew = Harvest Contractor/Forest Operators, IFOA = Integrated Forestry Operations Approval, TSL = Threatened Species Licence, EPL = Environment Protection Licence, FL = Fisheries Licence, CH = Cultural Heritage, SOP = Standard Operating Procedure.
1. Harvest Area Details
Cpt 109 Cpt 110 Total
Event ID 130308 130309
Gross Area (ha) 133 158 291
Total Net Harvest Area 96 135 231
Document title: Lorne_109_110_HP Version No.: 1 Page 2 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
Tac Plan Harvest Area 21 36 57
Estimated Net Harvest Area *
21 36 57
Estimated Yield * 231 333 564
Yield/ha * 21 36
Slope (% >0 - 15o) 46 61 54
Slope (% >15 - 20 o) 32 29 31
Slope (% >20 - 25 o) 16 9 12
Slope (% >25 - 30 o) 6 1 3
* Based on actual area expected to be harvested, ie. ha. Slopes > 30o have been removed from NHA
Contractor must ensure timber removed is allocated to the correct compartment when entered into Electronic Delivery Docket.
2. Management Conditions on Boundaries Boundary Conditions
Private Property The eastern edge of the NHA of compartment 110 adjoins PP. Fences are generally non-existent. Marking as required on private property boundaries. FT responsibility.
National Park Bago Bluff NP to the north
Neighbourhood Noise
There are EPA regulations that relate to noise control when operating machinery within 100m from residential establishments.
When working in areas adjacent to private property, there is potential for noise associated with timber harvest and haulage to affect residential areas that occur within 100m of the active operation.
Restrictions on forest operations will apply according to the EPA regulations on neighbourhood noise.
• If working within 100m of a residential establishment, machinery
(including chainsaws) operating hours will be limited to between 7am
and 8pm Monday to Saturday, and 8am to 8pm on Sundays and Public
Holidays.
• Timber haulage trucks may enter or exit the site between 7am and
8pm Monday to Friday, and 8am to 8pm on Weekends and Public
Holidays.
The HC will monitor noise and dust resulting from the operation and take the appropriate action to minimise the effect on surrounding property owners.
SMZ / FMZ FMZ3A occurs in these compartments and are generally associated with rainforest. Crew responsibility.
Document title: Lorne_109_110_HP Version No.: 1 Page 3 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
Research No research plots nor plus trees were detected during planning. If any sites are identified, notify the planner immediately.
Modified Harvest Area
Apply 10m total exclusion on 4 sites as indicated on HPOM. No falling into or out of buffer – to be marked in the field by APLO. HC is to check markings before harvesting. Existing roads and trails through the modified harvest area may be used for snigging, however, disturbance should be minimised. Only those roads indicated to be used for haulage on the HPOM may be used for haulage.
Cultural Heritage Surveys have been conducted and no new sites were detected.
If any potential heritage sites are identified, place an interim 20m buffer around the site and notify the planner and APL immediately.
3. Expected Yields
Product Estimates Volume (m3)
Species Species Mix (Sawlog)
HQ Large Sawlog (Quota) 150 BBT 77%
HQ Small Sawlog 135 SPG 0%
Poles, Piles and Girders 114 TWD 10%
LQ Sawlog (Salvage) 408 NEH 0%
Residue 0 BBX 0%
Total 807 OTHER 13%
4. Haulage
Haul Route West along Cooks Hut Rd to Upsalls Creek Road and through Kendall on to Pacific Highway.
School Bus Routes All road users must be aware of school bus usage and private traffic.
Haulage contractor must apply SSP Appendix 1. Communication procedure.
Traffic Control Plan Traffic control is not required for this event.
Dust and Mud HC must ensure mud is not dragged onto Upsalls Creek Road during haulage.
5. Community
Issue Conditions
Neighbours
PP owners
All relevant notifications have been conducted. A notification list for FCNSW staff is available from the planner.
Document title: Lorne_109_110_HP Version No.: 1 Page 4 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
6. Infrastructure
Infrastructure Conditions
Gravel Pits Separate management plan. Do not disturb.
Fire Trails All mapped trails servicing dump locations must remain in a trafficable condition post-harvest in order to assist HR burning and other post logging management activities.
7. Harvesting Conditions
Silviculture Type Harvesting Objectives and Condition for each stand condition
STS Heavy
The estimated net harvest area will be treated with STS heavy.
The objective is to harvest the merchantable component of the mature aged crop and retain the vigorous younger age class trees. FTs to mark growers for retention where operationally appropriate.
Crew to remove all merchantable stems not marked for retention and ensure mechanical disturbance creates a suitable seed bed for regeneration.
The crew must avoid damage to areas of advanced regeneration/pre-merchantable stems where possible to minimise damage to retained trees.
Future Treatment Area
Approximately 175ha in both compartments has been set aside for future treatment.
Monitoring Planning assumptions have been made as below, and therefore the HC must conduct Basal Area Monitoring in areas treated with Heavy STS.
HC is to monitor BA retention during harvesting using 15-20 BA post-harvest sweeps, randomly located across different stand types to ensure average BA is maintained.
Evidence of BA monitoring and the plot location must be documented by HC. Ideally monitoring of BA should occur prior to leaving each dump to ensure any variance to planned outcomes can be rectified.
Retained BA can be lower in high-quality BBT stands if suitable offset is used in other areas.
Any changes to treatment and non-harvest areas need to be endorsed by the Planning Supervisor.
Document title: Lorne_109_110_HP Version No.: 1 Page 5 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
IFOA Limits STS Heavy Future treatment and non-harvest areas
Total
Mixed-age dry & moist Blackbutt & mixed spp
forest types
Total NHA Excluding plantation
57ha 174ha 231ha
% of NHA
25% 75%
Pre-harvest BA
25
7
Post-harvest BA
8 7
Standing BA Pre-harv
1425 1218 2643
Standing BA Post-harv
456 1218 1674
BA removed
969 0 969
BA removed %
68% 0 37%
8. Tree Retention - refer to TSL booklet for full conditions
Prescription Condition/Responsibility
Mark-Up – the FT is responsible for marking up the forest ahead of harvesting operations consistent with SOP 2 - Exclusion Zone Boundary Mark Up, and SOP 3 - Forest Mark Up and Tree Retention.
Compartment Mark-Up Survey
(5.1h, 5.2 & 5.13)
Compartment mark-up surveys must be conducted at least 300m in advance of operations. The survey must search for threatened and protected species features listed in conditions 5.1h, 5.2 and 5.13 of the TSL.
Impenetrable Understory may be identified and indicatively mapped by the FT. FT must map these areas during mark-up and handover unmarked areas to the HC.
Hollow-bearing and Recruitment tree retention (H and R)
Regrowth Zone - 5.6 d, e & f, conditions apply.
Additional H trees for Greater Glider condition does not apply.
FT must select and mark 5 H trees/ha where available and one R for each H retained.
Document title: Lorne_109_110_HP Version No.: 1 Page 6 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
Harvesting - crew and HC responsibilities
Protection of Retained Trees (5.6g)
Trees marked or selected for retention must not be felled.
The crew must minimise damage to H, R and E trees must by using directional felling.
Harvesting debris should not accumulate within 5 m of retained trees. Where debris does accumulate the crew must remove or flatten to < 1m high.
The HC must be notified of any badly damaged retained trees and they must assess and record if a replacement retained tree is required.
Stag Retention (Dead standing trees 5.6e)
The crew should retain stags where safe to do so.
The crew must record the date, DBH, risk and location of unsafe stags removed
Significant food resources The crew should avoid damaging flowering or fruiting banksias or grass trees.
Impenetrable Understory In areas mapped by the FT as Impenetrable Understory procedures for harvesting in un-marked forest must be implemented by the HC and Crew.
9. Site-Specific Flora and Fauna
Condition Boundary Type
Prescription
Riparian Habitat Protection (5.07)
(The HPOM indicates LIC drainage order corrected by LiDAR/Geonet)
2 bars Implement filter strip (hard) and protection zone (soft) around drainage features as shown on the HPOM. Refer to SOP1.
UMDL: An assessment must be made by FT/HC to determine whether features are drainage lines or drainage depressions. In these licenced compartments UMDL receive the same protection as mapped 1st order drainage lines. FT must mark the location of UMDL protection zone boundary with 2 bars.
Refer to SOP1.
The crew will locate and protect all 2nd order and above streams with GPS.
Ground Habitat (5.17 d)
N/A Commercial firewood collection is permitted in these compartments.
Fish Purple-spotted Gudgeon potential habitat conditions apply. Class 1.
No UMDL harvesting is permitted.
Document title: Lorne_109_110_HP Version No.: 1 Page 7 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
10. Soil & Water – Refer to EPL Booklet for full conditions
Issue Assessment Conditions
EPL Scheduled Activity No Not scheduled
Licenced/ Unlicenced Licenced
Unmapped drainage Line harvesting
Not Permitted Revert to 10m 1st order protection. All conditions of the EPL apply.
Inherent hazard level 2 See SOP 1
Dispersible Soils No Dispersible soils have not been identified.
The HC must monitor installed armoring at crossings during the event.
If armoring becomes ineffective the HC must coordinate required maintenance prior to ongoing use.
Mass Movement / Instability Minor risk Nil
Acid Sulphate Soils No Nil
Seasonality Conditions No None
Historical or existing erosion Yes, minor Road & drainage structures must remain effective at all times. Drainage works should be implemented immediately following the completion of harvesting.
Ground cover >70% Nil
Burning conditions No Nil
Log Dumps SOP 5 HC is responsible for authorising moving the location of a log dump.
Roading management during harvesting
SOP 6 Refer to SOP 6.
HC is responsible for monitoring road and crossing drainage during haulage.
Wet Weather and Rutting SOP 6 Crew is responsible for implementing automatic closures and following notified closures.
HC is responsible for ensuring crew notified when notified closure is lifted.
Snigging SOP 8 Crew is responsible for progressive drainage of snig tracks
Snig Track Crossings SOP 8 HC is responsible to ensure snig track crossings are approved prior to use and rehabilitated upon completion.
Document title: Lorne_109_110_HP Version No.: 1 Page 8 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
11. Crossing Approvals All crossing approvals are shown on the operational map – any other feature crossings must be assessed, recorded below and approved by the Planning Supervisor before use.
Crossing EPA
Approval
Conditions
Document title: Lorne_109_110_HP Version No.: 1 Page 9 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
12. Operational Plan Briefing: A briefing of this operational plan was conducted by
Person Role Nature of Briefing Date
13. Acknowledgement of Briefing: I acknowledge that I have received a copy of the plan documents
and that I have been briefed on the conditions of the Plan. I understand the operational control requirements as outlined in the plan and take responsibility for the implementation of plan conditions relevant to my responsibilities
Name Role Signature Date
Document title: Lorne_109_110_HP Version No.: 1 Page 10 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
14. Standard Operating Procedures: The following SOP’s apply to this plan. FCNSW staff and the crew
must hold a copy on site whilst operating and comply with the conditions set out in each SOP.
Procedure Number
Title
1 Drainage Feature Protection
2 Exclusion Zone Boundary Management
3 Forest Mark-Up
4 Operating in Inherent Hazard Level 3 Areas
5 Log Dump Operation and Use
6 Road and Crossing Management and Wet Weather Controls
7 Safety Requirements
8 Snigging and Snig Track Crossings
9 Tree Felling & Servicing of Logs & Products
10 Fire Precautions & Other Miscellaneous Requirements for Harvesting Contractors
15 Road Crossings of Drainage Features
Document title: Lorne_109_110_HP Version No.: 1 Page 11 of 11
Harvest Plan no.: 60835 Approval Date: 12/09/2018 Expiry Date: 12/10/2027
Warning: a printed copy of this document may be uncontrolled. Please verify this is the latest version prior to use.
Operational Diary:
Date Issue Action Required
Action Completed
Initials
Record: Daily activities (eg tree marking, dump 2); Condition 5.2 of TSL items - EEC locations, rocky outcrops, koala scats, feed tree identification etc), discussions with stakeholders/neighbours/ site visitors; areas of impenetrable understorey; unviable areas not marked, non-conformances; harvesting issues identified, twice weekly road and crossing drainage checks
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 1 of 8
FORESTS NEW SOUTH WALES CENTRAL REGION
HARVESTING PLAN - AUTHORISED NATIVE PLANTATION
Lorne State Forest – Compartment 109
Certification
This plan has been prepared in accordance with the Plantations and Reafforestation Act 1999.
Prepared by: Dirk van Dijk
Senior Planner
Reviewed by: Brent Bailey
Planning Supervisor
Signature: Signature:
Date: 12/09/2018 Date: 12/09/2018
To implement this plan, you must hold a current contractor’s licence issued by Forestry Corporation of NSW, or be authorised by the holder of this licence to operate on State Forest.
Note: Approval encompasses the Harvest Plan Operational Map (HPOM) with the corresponding approval date displayed on the map, verifying final approved version.
Description of Proposal
Clearfall remainder of eucalypt plantations in these compartments. Attachment 1: Site Safety Plan describes the safety requirements and Emergency Meeting Points for this harvesting operation. Attachment 2: Plantations and Reafforestation (Code) Regulation 2001 (as at 8 July 2011).
Area Identification
State Forest Cpt Mgt
Area
Supply Zone
Job
No#
HP
No#
Gross Area Ha
Net Area Ha
Lorne 109 Kendall 3 JN9016948 HP2018-0001 9 9
Authorisation number CH0905P dated 21/04/2010
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 2 of 8
Silviculture and Harvesting Prescriptions
Silvicultural Planning
Plantation clearfall harvesting. The planted species are a mixture of Flooded Gum and Blackbutt established during plantings from around 1962 to 1967. The stand condition is generally poorly stocked with medium to good size and good quality commercial trees (up to about 55cm dbh) with a stocking of around 100 to 160 dominant/co-dominant stems per hectare. Plantation establishment of the cleared area will be conducted under a separate operational plan, which will include site preparation, weed control and plantation establishment according to the Plantations and Reafforestation (Code) Regulation 2001, clauses 26, 27 and 28. Harvesting Prescriptions Harvesting areas are as shown on the Harvest Plan Operational Map.
• Hollow bearing trees that provide fauna habitat should be retained where they exist and where safe to do so (refer to PRA Code clauses 23 and 55).
• Pull/stack debris away from the road prism (and 3m beyond where possible to facilitate machine movement off roads) of any named roads and boundary trails, especially near intersections, passing bays and turnarounds.
Harvesting to assist where practicable
• Where adjacent harvesting and/or extraction works, badly suppressed trees with no commercial or obvious habitat value - outside buffers and modified harvest areas - may be opportunistically culled by harvester and/or skidder at the discretion of the operator. However these trees must not be placed/pushed/stacked within 5m of retained seed trees.
• Consider arrangement of tree heads during harvesting and extraction, particularly in areas where seed-tree silviculture is conducted. Preference for opportunistic alignment of larger piece size residues in rough stacks across the slope.
Special Conditions
Conditions of Authorisation
The harvesting areas are clearly defined on the HPOM.
• There are no exclusions within the authorised plantation area.
• Harvesting of drainage feature protection areas should be applied as per the PRA Code.
Road works
Internal compartment road works and feeder road maintenance via Cooks Hut Rd from Upsalls Creek Rd will be done prior to harvesting commencing under a separate road maintenance plan.
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 3 of 8
Forest Management Zoning
This Plantation area has the following FMZ zones and associated harvest conditions:
FMZ 5 - Native Plantation – Authorised Plantation – CH0905P – Harvest using Plantations and Reafforestation (Code) Regulation 2001 (referred to as the PRA Code).
Cultural heritage
Cultural heritage surveys have been completed and no new site was detected.
Condition 13.2 (FPC) and Condition 19 (PRA Code) applies; contractors and their staff must notify the Harvesting Coordinator if a site is identified so conditions can be developed. An interim minimum 50 m buffer zone must be placed around sites until a condition is developed.
Protection of Biodiversity and Unique or Special Wildlife Values
If the Harvesting Coordinator or contractor becomes aware of unique or special wildlife values (any endangered species, endangered ecological community or species presumed extinct) in the plantation area the Senior Field Ecologist must be immediately notified (Condition 13.1 FPC). Logging should cease in the immediate vicinity until such time that suitable prescriptions can be implemented. Hollow bearing trees that provide fauna habitat should be retained where they exist and where safe to do so (refer to PRA Code, clause 23). Soils and Water Protection – Refer Plantation FPC
Soil Regolith Class = R1 Rainfall Erosivity = max of 5050 within NHA. Drainage Feature Protection Areas (DFPA) - as per Table 11.1 of FPC for Soil Regolith 1
Feature Drainage Feature Protection Area
Measure From
Buffer Zone condition
5 m Zone Buffer Zone (m)
Depression N 5 Centre of depression
Harvesting allowed, subject to conditions
Drainage Line Y 10 Top edge of banks
Harvesting allowed, subject to conditions
River (3rd order or higher, permanent)
Y 20 Top edge of banks
Harvesting excluded
Wetland - > 0.1 ha Y 20 Edge of wetland
Harvesting excluded
The 0 - 5 m Zone – No processing or extraction machinery in 5m zone other than exceptions allowed under condition 11.1.2 of FPC. Take all practical precautions to avoid falling into the 5 m zone. Wetland and River Buffer Zones - No harvesting.
Drainage lines and drainage depressions - see FPC Condition 11
Trees planted in the buffer zone of drainage lines and drainage depressions may be harvested if the top 200 mm of soil in the area is dry enough to avoid the risk of soil erosion to the edge of the
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 4 of 8
drainage feature, and the tracks or wheels of harvesting and extraction machinery must not enter the area within 5 metre zone of a drainage line.
Trees in and between the bed and banks of drainage lines must not be felled.
Machinery operating in the buffer zone must:
• Not create water channels • Minimise soil exposure by using slash, litter or other ground cover • Use walkover extraction techniques where possible • Prevent skewing of machinery tracks • Elevate the leading edge of the log when skidding • No snigging along drainage depressions, or earthworks allowed in 5 m buffer zone of a drainage
depression
Falling into Drainage Features
• Where necessary, trees can be felled into rivers and drainage lines. Crowns, logs and debris (greater than 10cm in diameter and/or three metres long) must be removed with minimal disturbance to the beds and banks.
• Tree matter can only be left with Harvesting Coordinator approval.
Drainage Feature Crossings – See Clauses 37-41 of PRA Code, and 11.4 of FPC for full description of conditions
• The location and type of all drainage feature crossings must be approved by the Harvesting Coordinator and must be marked in the field prior to crossing construction.
• Crossing construction must minimise depositing loose material into the drainage feature or any disturbance to its bed and banks.
• 5 and 30 metre drainage must be constructed on approaches to extraction track crossings. • Temporary slash crossings may be constructed on drainage lines or depressions where the
crossing point is shallow and dry, the surrounding soil is dry, water is prevented from entering the crossing from the approaches and no earthworks are required to enable machinery to cross the drainage line or depression.
• Temporary crossings over a drainage feature must be removed with 5 days of the completion of harvesting.
• Road crossings, permanent crossings and crossings of rivers must be designed as per the requirements of the PRA code.
Operational Conditions
Slope limits within the plantation area - Clause 59 of PRA Code
• Slope limits for snigging within the plantation area is 30 degrees (for a given soil regolith of R1 and rainfall erosivity of 5050).
Windrow and debris management within the plantation area (Clause 52 of PRA Code) Windrows and debris heaps:
• Must be located outside buffer zones of drainage features or places or relics of cultural heritage.
• Must be heaped with minimum disturbance to topsoil.
• Must be located across the slope of the land where practical.
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 5 of 8
Wet Weather Controls
Condition 14 of the FPC describes a comprehensive list of wet weather controls that apply to this operation. • Hauling is prohibited over any road during wet weather if resulting rutting is likely to be more
than 150 millimetres deep for any distance exceeding 20 metres (FPC 14.5).
Tracks, Dumps and Roads
Extraction Tracks
All extraction tracks must be drained, maintained and managed in accordance with Part 5, Division 2 & Part 6 Division 4 of the PRA Code, and Conditions 5, 6 and 9 of the FPC:
• Wherever practicable, walkover extraction techniques are to be used in preference to snig track construction.
• Snig track drainage must be located and constructed to ensure that water flow or potential water flow does not occur on snig track or extraction track surfaces for distances exceeding those given in 9.2 of the FPC.
• Constructed snig track cross-banks must have a minimum effective unconsolidated height of 35 cm or consolidated height of 25 cm.
• If downhill snig tracks connect to a dump, tracks must enter the dump from the side, or a drainage cross-bank above where the track enters the dump must be constructed at the end of each day.
Log Dumps
All logs dumps must be managed as per Condition 14, 17 of the FPC and 60-61, 64 of the PRA Code.
• Field location of log dumps must utilise the most level site available, consistent with the location indicated on the Operational Map. It is permissible for the Harvesting Coordinator to move the location up to 200m from the indicated position to achieve this provided the new location is within the plantation area.
• Dumps must not be located in any buffer zone.
• Runoff from log dumps must not be discharged into drainage features or extraction tracks and must be dispersed onto stable surfaces.
• Dumps must be re-shaped, drained and, where it is considered that slash/debris cover and natural revegetation will not stabilise the surface, the dump must be enrichment planted or grass seeded.
• Excavators and truck mounted loaders may be used as stationery loaders when there is runoff from log dump surface. All other machinery must remain stationary when there is run-off from the dump surface. This condition does not apply to gravelled dumps (FPC 14.2.4 and PRA 64C)
• Bark and logging debris must not be stacked against retained trees. Following completion of logging on a log dump, bark and logging debris must be stacked 5 metres away from the surrounding forest and separated from other flammable material by mineral soil for a distance of 5 metres.
• Pushing bark around the dump with a blade is to be discouraged. Where bark has been pushed with the blade, the excavator must shake the soil out of the bark prior to the bark being added to the bark heap.
• Large amounts of bark should not be accumulated around the dump. Upon completion of each log dump, bark must be re-distributed throughout the surrounding harvest area. Bark piles
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 6 of 8
must not exceed one grapple load or push of the blade (approx. 2 cubic metres) and be deposited no closer than two metres apart.
• Off cuts must be stacked separately, away from the bark heaps.
Roads Roads must be managed as per conditions 18-20 of the FPC. • The Harvesting Coordinator must ensure that roads in use are inspected routinely to ensure
pavement and drainage is maintained.
• Blading off may only occur if it will cause no, or only minimal, damage to the road surface and soil material must be re-spread as soon as practicable.
• A section of road with a non-functioning culvert must be repaired as soon as practicable only.
Tree Marking Code
Contractor selection is permitted. If tree marking occurs manually then the following table should be referenced.
Compartment boundary (where not defined by clear features, such as a road or drainage line)
“O” or Yellow tape
Native Forest Exclusion “NF” with horizontal ring
Buffer Zone Two horizontal lines / rings
Extraction System, OR Road/Track line “I” or white tape
Dump site (with optional dump number reference) “D” or red tape
Approved crossing site “”
TREE MARKING
Individual tree marked for removal “•” or dots
Directional felling mark “” over “•”
Retained trees not to be removed or damaged (e.g. grower) One horizontal line or ring
Cancellation Mark (Mark to formally cancel previous marks) “X”
Legal Conditions
The plantation areas in compartment 109 was authorised as a Timber Plantation on 21 April, 2010 – Registered Number CH0905P, under the Plantations and Reafforestation Act 1999.
This operation must comply with:
• Licence Conditions issued by Forestry Corporation of NSW under the Forestry Act 2012.
• Forests NSW, Forest Practices Code - Part 1 Timber Harvesting in Forests NSW Plantations November 2005. (Referred to as FPC).
• Forests NSW, Forest Practices Code Part 4 Forest Roads and Fire Trails (1999).
• Plantations and Reafforestation (Code) Regulation 2001 (referred to as the PRA Code).
• Part 7 (Div 3) Fisheries Management Act (1994) as amended May 2003.
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 7 of 8
Pre-Operational Briefing I acknowledge that I have received a copy of the Harvesting Plan for Compartment 109 in Lorne State Forest and that I have been briefed on the conditions of the Plan and understand the supervision and operational control requirements as explained to me by the Forest Planner or his/her delegate.
Position Name Signature Date
Handover Briefing At the completion of harvesting, control will be handed over from Production to Stewardship who will prepare a specific plan for re-establishment operations. I acknowledge that I have received a copy of the Harvesting Plan for Compartments 109 in Lorne State Forest. I understand that harvesting operations have been completed and that control has been handed over to Stewardship to prepare for re-establishment operations.
Position Name Signature Date
HARVEST PLAN – Lorne State Forest, Cpt 109 Plantation Clearfall
P:\RegionalMapComponents\Central\Projects\Harvest_Planning\Kendall_MA\Lorne\Lorne_109_110_2017\HP\Lorne_109_110_Plt_CF_HP.docx
Page 8 of 8
HC NOTES
LOCATION SF: CPT NO: • This diary should record general daily events, HC movements, Operations visited which are not
otherwise recorded in detail elsewhere.
Date Event Initial
G
!.
!.
"/
!(
!(
!(
!(
"""
"
"
"
" "
"
"
""
"
""
" "
"
"
"""
""
"
""
""
"
"
"
""
"""
"""
"""
""
"
"""
"
"
"
"
"
""
"
"
"
"
"
"
""
"
"
"
Coo ks Hut Roa d
Upsa lls Creek Ro a d
Cold N ob Ro ad
N o rth Bra nc h Ro a d
1
2
3
Ko a la
Ko a la
Ko a la
Ko a la
Ko a la
Ko a la
Ma sked Owl
Po werful OwlPo werful Owl
Po werful Owl
So uthern Myo tis
W o m po o Fruit-Do ve
Little Bentwing-b a tCo m m o n Bent-wing Ba t
Spo tted -ta iled Quo ll
Ba go Bluff N P
90
110
91
109
108
111
92
93
8975
LORNE 58
NORTH BRANCH 180
COLD N OB ROAD
UPSALLS CREEK ROAD
COOKS HUT ROAD
THE RIDGE W AY
MY RTLE CREE
K ROAD
CPT 90/1 TRAIL
CPT 108/1 TRAIL
CPT 90/4 TRAIL
BLACKBUTT ROAD
CPT 108/2 TRAIL
CPT 108/4
TRAIL
CPT 90/2 TRAIL
CPT 90/3 TRAIL
CPT 108/3 TRAIL
CPT 90/3 TRAIL
465000
465000
466000
466000
467000
467000
6501000
6501000
6502000
6502000
6503000
6503000
6504000
6504000
6505000
6505000
FORESTRY CORPORATION OF NSW, HARDWOOD FORESTS DIVISIONHARVEST PLAN OPERATIONAL MAP
1:15,000Co nto ur Interva l 10m
Pla n N a m e: KEN DALL_LORN E_109_110_2017
Prepa red By Dirk va n Dijk Da te: 17/01/2019 CHECKED BY.................................................................DATE........................
Da te Printed : 17/01/2019
Pla n N o :60835
© Cro wn Co pyright 2013. The info rm a tio n a nd d a ta c o nta ined in this m a p is to the b est o f Fo restry Co rpo ra tio n’s b elief, true a nd c o rrec t a t the tim e o f pub lic a tio n. Ho wever, c ha nges in c ircum sta nc es a fter the pub lic a tio n m a y im pa c t upo n the a c c ura c y o f the m a teria l. N o wa rra nty o r gua ra ntee is pro vid ed b y the Sta te o f N ew So uth W a les, Fo restry Co rpo ra tio n a nd its em plo yees a nd a gents a nd no lia b ility is a c c epted fo r a ny lo ss o r d a m a ge, c o sts o r expense resulting fro m the use o r relia nc e upo n the info rm a tio n a nd d a ta c o nta ined in this m a p
0 0.5 1 1.5Kilo m etres
GDA_1994_MGA_Zo ne_56Ma psheet 1:25,000 Bya b a rra 9434-4N 1:100,000 Ca m d en Ha ven 9434
LORN E: Sta te Fo restN O. 58
Ma na gem ent Area :KEN DALLCpt N o :109, 110
APPROVALApproval Date: 12/09/2018Controlled Map: Lorne_109_110_HPOMAmendment Approved:
DRAINAGE FEATURES
Strea m PZ 1st Ord er (10m )Strea m PZ 2nd Ord er (20m )
Strea m PZ 4th Ord er (50m )
Threatened Species Records
#* Ko a la
ROADS, DUMPS & CROSSINGS
All W ea ther, Unsea ledDry W ea ther, Unsea ledFo ur W heel DriveN o n Ha ula ge Ro a d sRo a d s no t to b e usedRo a d s o utsid e ha rvest a rea
ú Appro ved Cro ssing![ Tem po ra ry W et W ea ther Dum p!Y Tem po ra ry Dry W ea ther Dum p Spatially corrected LIC drainage (LiDAR/Geonet)
Unm a pped Dra ina ge Fea tures (LiDAR/Geo net)Dra ina ge line 5m Opera tio na l Zo ne (1st o rd er & a b o ve)
Records requiring prescription
Records with no conditions
HARVEST AREA & EXCLUSION ZONESHarvest Area
Genera l Ma na gem ent (FMZ 4 a nd 8)Sta te Fo rest
MAP FEATURES
10m c o nto ur (LiDAR d erived )MGA 100m grid
Co m pa rtm ent Bo und a ry
h
h h
h
hh
N a tio na l Pa rk Esta te
4 Bar Exclusions
Ma pped IHL4 Exc lusio n Zo ne
Exclusions
!( Mo d ified Ha rvest Area - 10m b uffer
Area exc lud ed fro m ha rvestingMa pped b o und a ry ind ic a tive o nly
 Da m - 10m b uffer
Ra info rest
Sa fety Meeting Po intG
Pla nta tio n CF with seed tree retentio n
Other Pla nta tio n Strea m PZ 3rd Ord er (30m )
Unmapped Drainage LineHarvesting NOT PermittedHa rvesting o pera tio ns in thesec o m pa rtm ents W ILL BE lic ensed
und er the EPL. All c o nd itio ns o f the EPL will a pply.
Regrowth Zone
Qua rry`
`
(Ind ic a te Rea so n fo r N o n-Ha rvest)eg: N E
Available Area NOT Logged
HARVESTED CODESHS_H - STS hea vyHS_M - STS m ed iumHS_L - STS lightHS_R - Regen STSHA - AGSHM - Mixed silvic ultureHT - Thinning
NON-HARVEST CODESN G - Ba sa l Area Retentio nN T - To po gra phic a lly Ina c c essib leN P - Pre-m erc ha nta b leN S - SteepN L - Lo gistic s (i.e. una b le to fa ll trees o nto ro a d )N E - N o t ec o no m ic (i.e. ha rvesta b le but po o r qua lity)N U - UnfinishedN M - MissedN N - N o n-c o m m erc ia l fo rest typesN H - Ha rvested in la st five yea rsN O - N o t fo rest (c lea red )N Q - Resea rc hN K - Ro c kN W - W ild lifeN C - Ca tc hm ent, unm a pped c reeks
(Ind ic a te Mo nth &Ha rvest Type) eg: 08/12 H-STS
Logged Area
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
Ѯv
Blackbutt Road
Comboyne Road
Elkhorn Rock Road
Pacifi
c High
way
Cold Nob Road
North Branch Road
Hannam Vale Road
Lorne Road
Zinc Road
Hynd
mans
Cree
k Roa
d
Butch
ers Ya
rd Ro
ad
Upsalls Creek Road
Lorne Access RoadNorth Branch Road
102
104
101
100
103
110109
110109
110
Crowdy Bay NP
Bago Bluff NP
Dooragan NP
Middle Brother NP
Queens Lake NR
Coorabakh NP
Queens Lake SCA
LORNE
KEREWONG
LANSDOWNE
KEW
BROKEN BAGO
BULLS GROUND
BURRAWAN
MIDDLE BROTHER
JOHNS RIVER
COMBOYNE
KENDALL
COWARRA
NORTH BRANCH
QUEENS LAKE
132k
V
66kV
33kV
460000
460000
465000
465000
470000
470000
475000
475000
480000
4800006485
000
6485
000
6490
000
6490
000
6495
000
6495
000
6500
000
6500
000
6505
000
6505
000
6510
000
6510
000
6515
000
6515
000
³Central Region - Kendall MA
Locality/Safety MapCompartments 109 & 110
Lorne State Forest
Helicopter Landing PlaceCold Nob Quarry Intersection of Upsalls Creek Rdand Cold Nob Rd464 700 E / 6 501 870 N31° 37.07 S / 152° 37.67 E
Emergency Telephone 000 / 112 Forestry Corporation of NSW (02) 6585 3744
Please note this map is produced in GDA94
Emergency Meeting PointIntersection of Upsalls Creek Roadand Cold Nob Road464 700 E / 6 501 870 N31° 37.07 S / 152° 37.67 E
Datum: GDA94Map Sheets1:25,000 Byabarra 9434-4N1:100,000 Camden Haven 9434
1:125,000Scale
0 1 2 3 4 50.5Kilometers
Legend
All Weather, Unsealed
Railways
State Forest (Legal)National Park Estate
G Emergency Meeting Point
Town!
®v Helicopter Landing Place
Sealed
Dry Weather, Unsealed4WD Track
Harvesting compartments
Haulage Route
Prepared by: Dirk van Dijk 12 April 2018