143
ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI BIN MARJUKI A project report submitted in partial fulfillment of the requirements for the award of the degree of Master of Science (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia JULAI 2006

ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

Embed Size (px)

Citation preview

Page 1: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

ii

COMPUTERISED BUILDING COST ESTIMATING SYSTEM

MOFTI BIN MARJUKI

A project report submitted in partial fulfillment of the

requirements for the award of the degree of

Master of Science (Construction Management)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

JULAI 2006

Page 2: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

iv

To My parents, Marjuki Hj Abd Sallam

Whom once said

“ We’ve no wealth to give except encouragement to seek for knowledge……

For knowledge is the grates treasures of all. “

To my children Raudahtul Alya and Muhammad Aiman Asyraaf

“ let this be your inspiration to seek knowledge…..”

To my loving wife, Samsiah bte Sadli

For all the sacrifices, understanding and affection.

Page 3: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

v

ACKNOWLEDGEMENTS

This master project was never an individual effort, but with combination

contribution of others who involved directly or indirectly. Among all involved in this

project , the author wishes to express the greatest appreciation to Dr. Arham Abdullah

and En. Zamri Ismail as the supervisors of this master project. With all the guidance

and advices given from both of the supervisor, this master was able to complete on

time. Their dedication and continuous assistances has led the author to strive for better

achievement in this master project.

The author wishes to express his gratitude to his family and friends for their

supports and cares. Last but not least, the author wishes to thank all those who have

contribute in one way or other in making this master project a possible one.

Page 4: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

vi

ABSTRACT

Estimating is an important process in order to prepare cost estimating for a

proposed project. Cost estimate will give client an overview towards the total cost

needed to be spent based on design. Due to the importance of the cost estimate for a

proposed project, the utilization of computer to prepare cost estimate should therefore

be practiced. The entry of computer technology in the estimating practice is a major

event in the improvement of the traditional estimating method by reducing estimate

preparation time, reducing the amount of paperwork required for the conventional data

storage, and improving the quality of documentation. However, the actual use of the

computer varies. Some companies use the computer for all projects and others do not

use at all. The software are under-utilized due to its inefficiency in terms of difficulty,

cost and because the program does not match with the company’s style of estimate This

study is intended to identify estimating techniques used by contractors for cost estimate,

to identify problem causes using that techniques and to develop a computerized cost

estimating system for contractors. The study has found out that most of the contractors

were using approximate quantity estimating technique for their cost estimations using

computers. However, some of them still prefer to use manual technique as it is easier to

apply. Microsoft Excel is the popular software used by contractors to prepare estimate.

However, there are disadvantages in using Microsoft Excel is that users have to create

suitable format for each estimating work. A computer-aided-project-cost-estimating

system has been created to fulfill the needs mentioned. The result of this research was a

cost estimating system application named as COES (Cost Estimating System) With the

fulfill utilization Microsoft Access 2003 and other Microsoft Access functions, COES

has been able to produce cost estimating automatically. This system serves as a

systematic framework comprising elements of building works in order to help

contractors to prepare a more precise and systematic cost estimate.

Page 5: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

vii

ABSTRAK

Penganggaran merupakan proses penting yang bertujuan untuk menyediakan

satu ramalan kos bagi projek yang dicadangkan. Anggaran kos yang disediakan

membolehkan pihak klien mendapat gambaran secara kasar terhadap jumlah kos yang

perlu dibelanjakan berdasarkan rekabentuk yang disediakan. Memandangkan

pentingnya anggaran kos kepada sesebuah projek yang dicadangkan, maka penggunaan

komputer untuk menyediakan anggaran kos perlu dipraktikkan. Kemasukan teknologi

komputer dalam amalan angggaran merupakan peristiwa utama bagi memperbaiki

kaedah anggaran dengan memendekkan masa penyediaan anggaran, mengurangkan

jumlah kertas yang diperlukan untuk menyimpan data, dan memperbaiki kualiti

dokumen. Walaubagaimanapun, penggunaan komputer sebenarnya berbeza-beza.

Banyak syarikat menggunakan komputer untuk kebanyakan projek dan terdapat juga

syarikat yang tidak langsung menggunakan aplikasi komputer. Perisian tidak

digunakan kerana kurang efisien dari segi kesukaran, kos dan program yang tidak sesuai

dengan kehendak syarikat. Kajian ini bertujuan untuk mengenalpasti teknik

penggangaran yang digunakan oleh kontraktor dan membangunkan sebuah system

anggaran kos projek berkomputer untuk kegunaan kontraktor. Kajian mendapati

kebanyakan kontraktor menggunakan kaedah kuantiti hampir untuk menyediakan

anggaran kos dan majoriti firma kontraktor telah menggunakan penggunaan aplikasi

komputer untuk kerja penganggaran. Namun begitu, terdapat sesetengah kontraktor

cenderung menggunakan kaedah manual walaupun kemudahan komputer telah

disediakan dengan alasan kaedah manual adalah lebih mudah dan senang dilakukan.

Perisian Microsoft Excel telah menjadi perisian popular kepada pihak kontraktor untuk

menyediakan anggaran kos. Penggunaan perisian ini mempunyai kelemahan iaitu

penggangar perlu mencipta format dan membentukkan formula yang sesuai pada setiap

kali kerja penggangaran dilakukan. Dengan ini, sebuah sistem anggaran kos projek

berbantukan komputer telah direkabentuk untuk memenuhi keperluan ini. Keputusan

Page 6: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

viii

kajian ialah satu aplikasi anggaran kos bangunan yang dinamakan sebagai COES ( Cost

Estimating System). Dengan menggunakan sepenuhnya perisian Microsoft Access 2003

dan fungsi Microsoft Access yang lain, COES telah dapat menghasilkan sistem

anggaran kos bangunan secara automatik. Sistem ini akan menjadi rangka sistematik

yang merangkumi elemen-elemen kerja bangunan untuk membantu kontraktor untuk

menghasilkan satu anggaran kos yang lebih tepat dan bersistem.

Page 7: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

ix

TABLE OF CONTENT

CHAPTER TITLE PAGE

TITLE

SUPERVISOR DECLARATION i

RESEARCHER DECLARATION ii

DEDICATION iv

ACKNOWLEDGEMENTS v

ABSTRACT vi

ABSTRAK vii

TABLE OF CONTENT ix

LIST OF TABLES xv

LIST OF FIGURES xvi

LIST OF APPENDICES xix

1 INTRODUCTION 1

1.1 Introduction 1

1.2 Background 2

1.3 Problem Statement 4

1.4 Aim and Objectives of the Study 5

1.5 Scope of Research 6

1.6 Importance of the Study 6

1.7 Research Approach 7 1.8 Research Strategy Chart 8

Page 8: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

x

2 LITERATURE REVIEW 9

2.1 Introduction 9

2.2 Definition of Estimating 10

2.3 Proposed of Cost Estimates 11

2.4 Estimating and Project Management Roles 12

2.4.1 Project Management Estimating Responsibility 12

2.4.2 Estimator Responsibility 13

2.4.3 Estimator Skill 13

2.5 Types of Estimates 14

2.6 Method of Estimates 16

2.6.1 Preliminary Estimates 17

2.6.2 Intermediate Estimates 17

2.6.3 Final Estimates 18

2.6.4 Unit Method 18

2.6.5 Superficial Method 19

2.6.6 Cube Method 20

2.6.7 Storey-Enclosure Method 21

2.6.8 Appropriate Quantities 22

2.6.9 Cost Planning 23

2.6.10 Analytical Estimating 24

2.6.11 Cost Model 24

2.7 Construction Cost 25

2.7.1 Material Cost 26

2.7.2 Labor Cost 26

2.7.2.1 Direct Labor Costs 26

2.7.2.2 Indirect Labor Cost 27

2.7.3 Equipment Cost 27

2.7.3.1 Owning Costs 28

2.7.3.4 Operating Costs 28

2.7.4 Overhead Costs 28

2.7.4.1 Office Overhead 29

Page 9: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xi

2.7.4.2 Job Overhead 30

2.7.5 Profit 30

2.8 Factors Influence Estimating 31

2.8.1 Quantity Surveying 32

2.8.2 Costing the Quantity Take Off 33

2.9 Different Type of Costs 34

2.10 Tool and Methodologies for Cost Estimating 35

2.11 Summary 35

3 COMPUTER AND COST ESTIMATING 36

3.1 Introduction 36

3.2 Use of Computers in Construction 37

3.3 Computer the Estimating Tools 38

3.4 Computer Software for Production of Cost Estimates 38

3.5 Industry Programs 41

3.5.1 Masterbill 3 (MB3) 41

3.5.2 Ripac for Microsoft Windows 42

3.5.3 Builds Soft 43

3.5.4 General Cost Estimator for Excel 4.0 45

3.5.5 Goldenseal Estimating Software 46

3.6 Review of Software 48

3.6.1 System Features 48

3.6.1.1 Built Soft 50

3.6.1.2 Ripac 51

3.6.1.3 The Proposed Application (COES) 51

3.6.2 Screen layout/Graphical User Interface (GUI) 53

3.6.2.1 The proposed Application (COES) 54

3.6.3 Cost Effectiveness for Specific Software 54

3.6.3.1 Reliability of Software 54

Page 10: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xii

3.6.3.2 User-Friendliness 55

3.6.3.3 Sufficient Features of the Software 56

3.6.3.4 Maintenance 56

3.6.3.5 Number of Computer 57

3.7 Justification for Using Microsoft Access 57

4 ANALYSIS AND RESULT 59

4.1 Introduction 59

4.2 Data Collection 59

4.3 Data Analysis 60

4.4 Frequency Analysis 60

4.5 Average Index Analysis 61

4,6 Data Analysis 61

4.7 Section A : Estimating Model 63

4.7.1 Cost Estimating Method Applied by Company 63

4.7.2 Factors of Choosing the Cost

Estimating Method 64

4.7.3 Types of Cost Estimating Method,

Applied to the Project 65

4.7.4 Frequency the Sources of Unit Rate that

the Company Referred in Preparing cost 67

4.4.7.1 Catalogues or Supplier Quotation 68

4.4.7.2 Built Up Rate 69

4.4.7.3 Past Project 69

4.4.7.4 Past Experience 69

4.4.7.5 Elemental Cost Analysis 70

4.7.4.6 JKR’s Schedule of Rate 70

4.8 Adjustment before Applying the Sources of Unit Rate 71

4.9 Section B : Application of Computer in Preparing

Cost Estimating 72

Page 11: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xiii

4.9..1 The use of Computer to Prepare Cost Estimating 72

4.9.2 Standard Software used to Prepare Cost Estimate 73

4.9.3 Special Software used for Estimating 74

4.9.4 The Software used by company 76

4.9.5 The Advantages or Efficiencies of Computer

Software used in company for Preparing Cost

Estimating. 77

4.9.5.1 Complete work in Shorter Time 77

4.95.2 User Friendly 78

4.9.5.3 Quality of Work Done 78

4.9.5.4 Efficiency 79

4.9.6 Problem Faced when using

Standard Software in Preparing Cost Estimate 80

4.10 Problem faced when using the Computer Software

to prepare the Estimating 80

4.11 Summary of Analysis and Result 81

5 MODEL DEVELOPMENT METHODOLOGY 83 5.1 Introduction 83

5.2 System Requirements 84

5.3 System Component and Architecture 86

5.4 Database Conceptual Design 86

5.5 The Conceptual Estimate Methodology 91

5.6 Conclusion 93

Page 12: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xiv

6 MODEL IMPLEMENTATION 94

6.1 Introduction 94

6.2 Database Implementation 94

6.3 Preliminary Database 95

6.4 Main Module 99

6.5 Conclusion 100

7 SYSTEM VALIDATION 102

7.1 Introduction 102

7.2 Prototype 102

7.3 Use the Prototype 103

8 CONCLUSION AND RECOMMENDATION 114

8.1 Conclusion 114

8.2 Research Contribution 114

8.3 Recommendation for Future Research 115

REFERENCES 117

APPENDICES

Page 13: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xv

LIST OF TABLES

TABLE NO TITLE PAGE

2.1 Types of Cost Estimates 16

4.1 Respondents Percentage 62

4.2 Method use for Preparing Cost Estimating 63

4.3 Factors of Choosing Cost Estimating Method 64

4.4 Cost Estimating Method used for Several Types of

Contract 66

4.5 Degree of Frequently used the Sources of Unit Rate in order

of Preparing Cost Estimate 68

4.6 Option of any Adjustment or no need any Adjustment

in Applying Resources of Unit Rate 71

4.7 Computer used in Preparing Cost Estimate 72

4.8 Standard Software used to Prepare Cost Estimating 73

4.9 Special Software used in Preparing Cost Estimating 75

4.10 Types of Special Software used in Preparing

Cost Estimating 76

4.11 Efficiencies used Special Software in Preparing

Cost Estimating 77

4.12 Problem usually faced when Using Standard Software 80

Page 14: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xvi

LIST OF FIGURES

FIGURE NO TITLE PAGE

2.1 Research Strategy Chart 8

2.1 Superficial Method 20

2.2 Cube Method 21

3.1 Sample Interface Masterbill3 (MB3) 42

3.2 Interface Ripac for Windows 43

3.3 Four Level Estimating System In Build Soft 44

3.4 Interface Trade Breakup (level 2) 44

3.5 Interface of Rate Breakup (level 3) 45

3.6 Sample Interface of General Cost Estimator 46

3.7 Interface Goldenseal Startup Guide 47

3.8 Interface Goldenseal Estimates 47

4.1 Respondent Percentage 62

4.2 Percentage of Method use for Preparing Cost Estimating 63

4.3 Percentage of factors Choosing Cost Estimating Method 65

4.4 Frequently used the Sources of Unit Rate in order of Preparing

Cost Estimate 70

4.5 Percentages of any Adjustment before Applying Resources

of Unit Rates 72

4.6 Percentage of Standard Software used by Contractor in

Preparing Cost Estimating 74

4.7 Percentage of used Special Software in Preparing Cost

Estimate 75

Page 15: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xvii

4.8 Rating Scale Efficiencies used Special Software in Preparing

Cost Estimating 79

4.9 Percentage of Problem usually faced when Using Standard

Software in Preparing Cost Estimating 81

5.1 System Development Process 84

5.2 System Component 86

5.3 System Architecture 88

5.4 Database Entity Relationship Diagram (ER Diagram) 90

5.5 Methodology Data Flow Diagram 92

6.1 Sample Table 1 of Each Division Data 96

6.2 Sample Table 2 of Each Division data 96

6.3 Sample Table 3 of Item Taking Off List 97

6.4 Snapshot of the Form from Table Database 98

6.5 Snapshot of the Database and their Relationships 98

6.6 Snapshot of the System Main Menu 100

7.1 Snapshot of the Starting Menu 103

7.2 Snapshot of the Project Brief 104

7.3 Snapshot of Project Cost Information 105

7.4 Snapshot of Activities under Building Works 106

7.5 Snapshot of Activities under Superstructure 106

7.6 Snapshot of the Form Cost Estimating 107

7.7 Snapshot of Functional Button 108

7.8 Snapshot of High-tensile and Mild-steel Conversion 108

7.9 Snapshot Functional Buttons of Estimating Form 109

Page 16: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xviii

7.10 Snapshot of Summary Cost Concrete Staircase 109

7.11 Snapshot of Summary Total Cost Staircase 110

7.12 Snapshot of Data Record 111

7.13 Snapshot of Report Construction Cost 112

7.11 Snapshot of Report Brief Specification 113

Page 17: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

xix

LIST OF APPENDICES

APPENDIX TITLE PAGE

A Questionnaire -

Page 18: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

CHAPTER 1

INTRODUCTION

1.1 Introduction

Generally, the process of awarding any construction contract is based on a

competitive bidding. Contractors will be invited to submit their bids to the owner who

normally awards the lowest bid to construct the project. Beforehand, both the owner

and contractor have to access the construction cost of the proposed project. This is

achieved through a construction cost estimate. Although, the actual total cost of

construction is not known until the completion of the project, conceptual estimates can

be a good start for the owner and contractor. The owner will be able to estimate in

advance a range of the final cost, to secure the lowest cost to construct the project, and

budget the necessary fund in advance. Considering an adequate contingency

percentage to the total estimated cost covers such risk. In order to win the contract, the

contractor bid price has to be low enough to compete with other competitors, yet high

enough to cover his risks and make some profit. Consequently the importance of cost

estimates is enormous for all project phase, moreover at the conceptual and feasibility

phase.

The preparation of any type of cost estimate depends on the experience of the

estimator, the tools used, the time spent, and the information available. Usually the

preparation of an estimate starts by breaking down the project into components, then

taking off the quantities of the elements of each package and next pricing them all.

1

Page 19: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

2

Finally, by summing up the price the direct construction cost is computed. This

process is long and complex but the most complicated part of it is the quantity take off.

Consequently, computers are considered to be effective tools in cost estimating. due to

their capability of doing complex calculation and storing huge amount of data for

future use. Any decision concerning the construction of a project that has been or to be

executed is based on one type of estimates, which are preliminary estimates, which their

moderate level of accuracy owner, quantity survey and contractor consider them as the

first choice estimates because they are inexpensive and fast to generate. Owner uses

them to decide whether constructing a project is feasible and to evaluate contractors

bids, while architect to design within owner’s budget and considering alternatives, and

the contractor to know if bidding on a project is profitable or not. Consequently, in the

proposed methodology the concentration is on preliminary construction cost estimates

with the emphasis on a computer as an avail tool for estimators.

1.2 Background Computers are expending increasingly into all aspects of daily life. The cheaper

computer hardware today has boasted the rush of using the computers. Although the

move had been slow compared to the others, the construction industry is steadily

coping itself with the advancement in the information technology system. As a result,

the professional Architects, Engineers and surveyors had computerised their works, and

the contractor had started to use computers for their daily business purposes. From a

survey by Mohd Hisham Ariffin (2002), it is concluded that the Construction Industry

Development Board (CIDB) G7-graded contractors were highly dependent on computer

for the administration work while having mediocre dependency on computer for

technical work which include scheduling, technical calculation, budgeting, estimating,

and others.

Page 20: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

3

The early uses of computers by construction companies were limited to

accounting functions. With the advances in micro-computing, increased knowledge of

computer capabilities, and the development of user-friendly software, computers have

been used everyday construction to make quick and accurate decisions.

The method of pre-tender price estimating have been developed as manual

processes. The computer can be used in conjunction with any methods of estimating for

the rapid retrieval of cost data, of for calculating an approximate estimating. The

advantage of using a computer is that an estimate, however detailed, can be updated

quickly and efficiently for changes, which may be necessary in a revised design.

The computers potential in construction estimating has progressed from its use

as an adding machine to an integrated process of computer-aided design (CAD),

estimating software, job costing software and project scheduling systems. However the

actual use of the computer for estimating is varied within the industry. Some

companies use the computer for all projects and with high degree of sophistication.

There is a variety of estimating software program available. Some simply

perform the mathematics of the estimating process, others integrate the estimating

operation with other functions of the construction process. No matter how sophisticated

the program might be, it is imperative that the estimator understands the calculation

methods and assumptions used in the program. The estimator should be properly

trained and should known all assumptions before proceeding with an estimate.

Computer estimating still involves the measurement of dimensions and

compiling materials. This information can then be fed to the computer to obtain the

labour, equipment and material costs that may be used to compile the estimate. To

perform this type of function, the computer must be programmed to proceed through the

required steps, and appropriate unit costs must be stored in it.

Page 21: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

4

An estimator must assemble a large amount of information in an organized

manner and perform numerous calculations to prepare a cost estimate. The computer

can be used by the estimator to organize, store and retrieve information and to perform

the many calculations necessary to prepare an estimate. It can be an effective tool for

decreasing the preparation time and increasing the accuracy of cost estimating.

Numerous computer database can be developed to automate and standardize the

estimating function. Historical cost database can be developed from the cost records of

projects that have been completed by the company. Information from the historical cost

database can be retrieved for the preparation of estimates for future projects. As new

information is obtained from current projects, the historical cost database can be

updated.

The advent of the relatively powerful and economical computer technology has

realistically made the computer-aided estimating become feasible. The number of

estimating products increased rapidly since the entry of an interactive computing system

into the market. Accompanied with the emergence of estimating software, advance in

the database management system has significantly influenced the development of a

computer-aided estimating software. Therefore, it can be concluded that the entry of

computer technology in the estimating practice is a major event in the improvement of

the traditional estimating method by shortening estimate preparation time, reducing the

amount of paperwork required for the conventional data storage, improving the quality

of documentation. These advantages allow the estimator to pay more attention on

decision making during the process of estimation and leave all burdens of data handling

tasks to the automated system (Charoenngam, 1996).

1.3 Problem Statement

In general, it can be stated that the current estimating programs are unable to

fully satisfy their own users. The available software are under–utilized due to its

Page 22: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

5

inefficiency in terms of difficulty, cost and because the program does not match with

the company’s style of estimate (Charoenngam, 1996). There is very long learning

curve for practicing estimators to operate the system especially for small companies

( Lowe,1994).

Most estimating products focus on program manipulation and offer to much

irrelevant optional features rather to concentrate on the core estimate preparation. The

estimating method and techniques are different from regions, countries to countries,

location to locations and companies to companies (Lowe 1994).

Therefore the research is needed because in Malaysia the use of Cost

Estimating system was very limited. The most common and widespread method for

taking-off was still the traditional method and spreadsheet method. In the mean time,

although most of the contractors have their highly capable Cost Estimating system,

there are still many of them who still use the spreadsheets program. The reason is that

spreadsheet programs actually save more time than the Cost Estimating production

system. For all this spreadsheet users, template or standard sheets were being

developed to help out Cost Estimating process. The users will only have a key in the

dimension and then, they will have quantities for multiple items in one single sheet.

1.4 Aim and Objectives Of The Study

The aim of this project is to develop a prototype computer – aided project cost

estimating system which can help the users to prepare preliminary estimate cost of

building works. In order to achieve the above aim, the following objectives of study

have to be carried out.

1. To study the various conventional methods of estimating from contractors

perspective.

Page 23: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

6

2. To identify the software used by contractor for cost estimating in practice

and the problems they faced in using the software.

3. To develop a computer – aided project cost estimating system by using

Microsoft Access 2003.

1.5 Scope of Research

This study only covers the following scopes :-

1. This study concentrates on developing an application from taking off to

automatic approximate cost estimating.

2. This study concentrates on building work only.

3. This study focused only on an assortment of contractors who has registered

with Pusat Khidmat Kontraktor (PKK) and Construction Industrial

Development Board ( CIDB) in Johor Bahru.

1.6 Importance Of The Study

Although it is a simple application, which covers only the approximate cost

estimating preparation process, it is a landmark application that cost estimate can be

prepared automatically using Microsoft Access. This application will have the same

capabilities with the expensive Cost Estimating production software in terms of

preparing Cost Estimate.

As this application only requires Microsoft Access 2003 to run, the cost of

obtaining and installing this application is thought to be much cheaper then the

available Cost Estimate Production software. As a low cost solution, this will give the

contractor much more opportunity to use the computer in preparing their cost estimate.

As a result of this widespread usage, files can be shared among all the parties involved.

Page 24: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

7

1.7 Research Approach

The idea of this research initiate from the researcher experience in using

KAPPA-PCT Application Development System version 2.2 in doing preliminary

estimate before architectural drawings can be produced. The prototype is developed in

the form it is easy to understand and use. The user has to answer the questions appear

on the screen such as type of school, location, year when the school is to be build, site

condition and piling requirement, that is before the preliminary estimate can be

calculated. They cannot accommodate detailed element for preparation cost estimate.

Therefore, the first phase in doing this research is to make study on the Microsoft

Access of whether it can be developed into a Cost Estimate Production application.

The second phase involves doing literature review on the Cost Estimate

Production software or associated software available in the market. All the software

was extensively being reviewed and it form a model for the proposed application.

The third phase is on learning to do programming in Microsoft Access. This is

important because this application will be programmed by the researchers who have

little experience in programming before hand.

Page 25: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

PHASE 1

Research Statement

Problem

Statement

Scope of Research

INSTRUMENT Questionnaire,

Literature review

RESPONDENT

Registered contractors Class A,B,BX,C

With PKK or CIDB in Johor Bahru

Review the Computerised Cost

Estimating System

DATA

ANALYSIS

OBJECTIVE 1 Identify Cost Estimating

Method

OBJECTIVE 2

Identify Software used by contractors

and problem

OBJECTIVE 3 Developed Cost

Estimating System

Summary,

Conclusion and Recommendation

PHASE 2

Issued statement and data collecting Data Analysis, Develop Computer Cost Estimating System, Conclusion and Recommendation

Figure 1.1: Research Strategy Chart

8

1.8 Research Strategy Chart

Page 26: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction Cost estimating is an essential aspect for the business operation of

construction firms. Construction is a unique industry that by nature is risky since

most projects must be priced before they are constructed, whereas in other industries

the selling price is based on known manufacturing costs. The success or failure of a

project relies on the accuracy of several estimates done throughout the course of the

project.

Estimating has been recognized as an important element of construction

project. The primary function of preliminary or approximate estimating is to

produce a forecast of the probable cost of a future project, before the building has

been designed in detail and contract particulars prepared. In this way, the building

client is made aware of his likely financial commitments before extensive design

work is undertaken (Seeley,1996).

The purpose of pre-tender price estimating is to provide an indication of the

probable costs of construction at a very early stage in the life of a construction project.

It is one of the most important factors influencing the client’s decision to build. An

approximate estimate, which is too high, may discourage a potential client, whereas

estimates, which are shown to be far below a tender sum, may result in an abortive

design.

Page 27: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

10

2.2 Definition of Estimating

Researcher and experts give cost estimating different definition, thus the

succeeding paragraph states some of them. The Project Management ( PMI ) defines

the cost estimating to involve developing an approximation (estimate) of costs of the

resources needed to complete project activities (Duncan 1996). Hendrickson

specifies that are design, bid and control. Furthermore, he defines that at the very

early stage of design, the screening estimate or order of magnitude estimate is made

before the facility is designed, therefore it relies on the cost data of similar facilities

built in the past. While preliminary or conceptual estimate is based on the

conceptual design of the facility at the state when the basic technologies for the

design are known. Moreover, the detailed or definitive estimate is made when the

scope of work is clearly defined and the completed plans and specification when

they are ready for the owner to solicit bids from construction contractors

(Hendrickson 1989)

Association for the Advancement of Cost Engineering (AACE) International

define the cost estimation to provide the basis for project management, business

planning, budget preparation and cost and schedule control. Included in these costs

are assessments and an evaluation of risks and uncertainties (Uppal 1997). On the

other hand, Carr defines it as being an accurate reflection of reality that shows the

levels of detail that is relevant to decisions (Carr 1989).

Estimating is the process of looking into the future and trying to forecast

project costs and resource requirements (Halpin 1985). An estimate is a judgement,

opinion, forecast or prediction. It is a judgement or opinion of the cost of a process,

product, project or service. It is a prediction or forecast of what a work output or

work activity will cost (Stewart 1982). Estimating is a collection and analysis of the

bill items which influences and contribute to the cost of the project (Clough, 1984 )

Page 28: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

11

According Society by Laws, march 1978 Estimating is the art of

approximating the probable worth or cost of an activity based on information

available at the time (Stewart 1982). The primary function of preliminary

estimating is to produce a forecast of the probable cost of a future project, before the

building has been designed in detail and contract particulars prepared. (Seeley,

1996). Consequently, all those definition are similar in one way or the other in

describing cost estimating as being the process of guessing and foreseeing the future

costs of a project or product before it actually exist. Despite the likeness between

cost estimating and pricing, one has to carefully distinguish the difference. Cost

estimating involves an assessment of the likely quantitative result, how much will it

cost to perform product or service involved. Pricing is a business decision, how

much will be the charge for that product or service (Duncan 1996). Wood

mentioned that in management terminology the cost refers to expenditure, not

revenue, the price and cost are not the same. Thus, the price may be less than the

cost in the case of a loss, or the price may be greater than the cost in the case of a

profit (Wood 1974).

2.3 Purposed of Cost Estimates

Peculiar to the definitions an estimate, at its most excellent, is a close

approximation of the actual costs. Hence the purpose of an estimate is to postulate

the costs required to completing a project in accordance with the contract plans and

specification. Furthermore, it is important that management has as much

information as possible when deciding on funding projects. Sutherland (1999)

explains the purposed as to provide the client and design team with as precise an

estimate of final cost as possible so that the project can be accomplished within the

client’s budget. Likewise, Weatney (1997) outlines the purposed of a cost estimate

through the following :

Page 29: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

12

Provides an assessment of capital cost for a specified piece of work.

Forms the basic for planning and control by defining the scope of work and

it’s associated estimated cost.

Provide much of the basic information (hours, resources, tasks, and

durations) which is needed for preparing a schedule. It also states general

resource requirements such as labor, material, and construction equipment.

Provides the financial input required to prepare a cash flow curve.

Is a catalyst for discussion, idea generation, team participation, clarity and

buy-in, it ties together much of the relevant project information within a

simple document.

2.4 Estimating and Project Management Roles

Both project management and estimator differently share responsibilities in

performing an estimate at the decision level.

2.4.1 Project Management Estimating Responsibility

Decision making requires a sequence of actions needed to be taken to

perform the process from an initial status to a goal status (Hegazy 1993). Therefore,

management must know what cost information is needed and how to use it in

making decisions. Estimate development must be directed and approved by

management prior to issue. The project manager is actively involved in the

development of the estimate and is reasonable for the final product. The project

team is responsible for providing the necessary project deliverables and scope

information to the estimator (Dysert 1997).

Page 30: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

13

2.4.2 Estimator Responsibility

Estimating is a fundamental part of the construction industry. Cost estimating

accuracy is the basis of a project success or failure. Accurate estimates optimize

good contracting ( Andrian 1993). Much of the credit for the fruition or dud of a

construction enterprise is attributed to the accuracy and capability of its estimating

department and personnel. An accurate, liable and realistic bid preparation demand

good judgement and estimating skills. It is the estimator responsibility to ensure

that a project team understands the information needs for the estimate, then ensure

that a project team understands the information needs for the estimate, then ensure

that the information provided is suitable to produce the quality of estimate desire

(Dysert 1997). Estimators should compile and analyze data on all factors that might

influence the cost like materials, labor, location and equipment (Cost Engineering

Journal 1998). Estimating is not an easy process, it involves complex calculations,

and when little information is available demand the estimator to imagine the

elements of the projects. It is important that the estimator views the complete

estimate in orderly steps that include quantity takeoff, costing of the work,

determination of overhead costs, and the determination of an appropriate profit

(Adrian 1993). Including all the items in the project neither more nor less

challenges estimator. Prior to the design completion, estimator has to have the

vision to see beyond the obvious components and their primary costs of construction

(Carr 1989).

2.4.3 Estimator Skill

The challenge that faces a cost estimation is to have it close the actual cost,

this inquires good skill and experience. Dyset and Elliot (1999) avows that an

effective estimating organization requires highly knowledgeable personnel,

Page 31: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

14

possessing technical skills. Furthermore they define a set of skills as estimating

core competencies as follows :

Understanding of the capital project process.

Detailed understanding of the estimate requirements for each class of

estimate.

Engineering document reading.

Code of accounts/works breakdown structure/project breakdown structure.

Basic project controls (budget, schedule, cost control, change management,

progress measurements, earned value, forecasting).

Data analysis (labor productivity, database standards and development,

historical data analysis, and benchmarking).

Strategic estimating skills (capacity factoring, equipment factoring, cost

modeling, general factor, and ratio development).

Detailed estimating skills (material takeoffs, pricing and costing ).

General software.

Estimating software.

Presentation skills.

Report writing.

Listening.

2.5 Types of Estimates

The availability of design data to the estimator does influence the types of

estimate to be chosen. Cost estimates may be divided into two different types,

depending on the purpose for which they are prepared for and the amount of

information known when estimates are prepared. Approximate and detailed

estimates are the major types of construction cost estimate. (Steward 1982) classifies

the cost estimating methods as the “top-down” or parametric approach that uses

Page 32: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

15

historical data from previous projects to develop the cost of new project based on

increased or decreased factors : or the “ground-up” or industrial engineering

approach that requires estimating and pricing the man-hours and materials of each

element. Approximate estimate are commonly known as Conceptual, Preliminary,

Order of Magnitude and Budget or feasibility estimates. Meanwhile bid and

definitive estimates are other names for detailed estimates. The most common

estimates type used in building construction are 1) Conceptual estimate. 2)

Preliminary estimate. 3) Engineer’s estimate. 4) Bid estimate. The four levels

reflect the fact that as the project proceeds from concept through preliminary, to

final and bidding phase, the level of detail increases, allowing the development of a

more accurate estimate (Halpin 1985). AACE International has identified a

progression of five types of estimates of construction costs during engineering

design, order of magnitude, conceptual, preliminary, definitive and control ( Duncan

1996). Furthermore, Westney (1997) classified the estimating types based on 1)

How the estimate will be used. 2) The type, quality and amount of information

available for preparing the estimate. 3 ) The range of accuracy desired in the

estimate. 4) The calculation technique used to prepare the estimate. 5) The time

chosen to produce the estimate. 6) The method or input and output (manual or

computer) used in preparing the estimate. 7) The phase of project (feasibility,

appropriation and construction) related to the estimate. 8) For whom the estimate is

prepared (owner, contractor or insurance company). Generally, the estimating chore

continues during the different phases of the project construction to ascertain whether

the actual costs match with the bid’s estimate. Although, numerous methods and

level of accuracy are available to estimate the cost of constructing a project, all these

estimates are approximated and are based on experience and judgement (Barrie and

Paulson 1992). Certainly the total actual costs will be known just when the project

construction is consummated. Table 2.1 lists the four commonly used estimates,

when each one of them can be used according to the design progresses. In addition

to the purpose of using each one of them.

Page 33: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

16

Table 2.1 : Types of Cost Estimates

ESTIMATE TYPE

WHEN

WHY

Conceptual

Estimate

Prior to design

Useful for decision in conceptual

and budgetary stage.

Preliminary

Estimate

After preliminary design

(40% of total design)

Offers the owner a pause to

review design before the detail.

Engineers estimate

After detail design

( 100% of total design)

Ensure design is within financial

resources and assists in

evaluating bids.

Bid Estimate

During bidding by

contractors

Establish bid price

2.6 Method of Estimates

Estimating are required at all stages of a project with varying of available

information thus several methods are evolved. Estimator has to always consider the

relationship between available information, project stage, method and estimate

accuracy. Forecasting is the procedure for simulating the future by creation of a

picture based on historical information (Wood 1974). Yet forecasting contrived from

publishing press is slightly accurate so forecast should be carried out on information

related to the industry in which it is serve. Different estimating methods are

described in the midst of the succeeding paragraphs.

Page 34: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

17

2.6.1 Preliminary Estimates.

Early in the planning stages, both building owners and designers must agree on

an anticipated cost of the project at bid award. Preliminary Estimates are employed in

the early planning phases of a proposed project to match an owner's needs, expressed as

written programmatic requirements, with budget constraints in order to establish its

overall scope (size) and quality expectations. The Work Breakdown Structure

recommended at this stage is a systems-based format, where elements of the building

(e.g. exterior closure) are the method of categorization. Estimate comparisons at this

stage are especially valuable in evaluating the feasibility of strategic alternatives being

considered to satisfy current and projected space requirements (e.g. new construction

versus renovation, or lease space). As the design is not fully developed at this stage, a

design contingency is typically included, typically between 10-15%. Issues which need

to be identified at this juncture include method of procurement being considered,

location market factors, specific site constraints or challenges, proposed phasing plans,

and start and finish dates. It is recommended that a formal risk analysis be carried out at

every stage in the design, but particularly in the planning stage when proactive steps can

be taken to mitigate identified risks.

2.6.2 Intermediate Estimates.

After proceeding with a preferred course of action, Intermediate Estimates are

employed at various stages of project design development to maintain accountability for

initial budget projections and as a means of evaluating competing alternative

construction assemblies, systems, and materials. On large projects it is common practice

for an owner to employ a construction manager or professional estimator to continually

update project estimates and provide feedback on budget impacts of decisions on major

design elements. The estimates will typically still be in a Work Breakdown Structure.

Page 35: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

18

The risk assessment should be updated and a contingency factor calculated depending

on the outcome of the risk analysis. As the design progresses and risks are mitigated,

the design contingency can typically be reduced.

2.6.3 Final Estimates.

As the design is completed a detailed pre-bid estimate can be prepared. At this

stage the design contingency would typically be reduced to zero: however, in some

instances, there will still be risk surrounding the project, which would make it prudent

to still include a small bidding contingency. The estimate should be organized in the

same Work Breakdown Structure as required of the bidders. This then allows for a

comparison of the final estimate with the bids received and can aid in negotiating with

the lowest bidder. In addition, having the final estimate and bids in the same format

facilitates developing cost databases for use in planning future projects.

2.6.4 Unit Method

Wood (1976) elaborate unit estimates as selecting a standard unit like seat

per cinema, bed per hospital, table per school to obtain the estimate cost of project.

Based on the total unit of functional proposed building, the estimate cost of a

building can be obtained from past project of the same functions.

The unit of preliminary estimating consists of choosing a standard unit of

accommodation and multiplying this an appropriate cost per unit. The standard

units may represent, for example schools (cost per pupil), hospital (cost per bed) and

car parks (cost per apace). The technique is based upon the fact that there is usually

a close relationship between the cost of construction project and the number of

functional units it accommodates. Functional units are those factors, which express

the intended use of the building better than any other. This method is extremely

Page 36: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

19

useful on those occasions where the building client requires a preliminary estimate

based upon little more information than the units of accommodation.

The method of counting the number of units is extremely simple, but

considerable experience is necessary in order to select an appropriate rate. Rate can

be obtained by the careful analysis of a number of recently completed projects of a

similar type, size and construction. Adjustments based upon professional judgment

will however need to be made to account for varying site conditions, specification

changes and market conditions. It is the simplest and quickest method to

implement, but it must be used with care. Therefore, it is advisable to express the

cost within a range of prices that can be useful for budgetary estimate.

2.6.5 Superficial Method

This perhaps the most common method in use for estimating purposes. The

estimate is easy to calculate and costs are expressed in a way fairly readily

understood by an average building. The area of each of the floors are measured and

then multiplied by a cost per square meter.

The rules of measurement for the superficial area of a building were defined

by the Royal Institution Of Chartered Surveyor, United Kingdom. In order to

provide comparability between various schemes, the floor areas are calculated from

the internal dimensions of the building. It is preferable to separate the floor areas

and apply different unit rates. It is appropriate for projects such school and housing

where storey heights are constant.

Page 37: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

20

Figure 2.1 Superficial Method

Factors such as storey height and plan shape are particularly important when

deciding upon the rate to be used. Another factor in its favour is that rates are

readily available from many sources, or alternatively, they can e very easily

calculated from existing schemes.

2.6.6 Cube Method

The Royal Institute of British Architects defined the rules of measurement

for the cubic content of a building as follows :-

The external plan area was multiplied by the height from the top of the

concrete foundation to halfway up the roof if pitched or to 610mm above the roof if

flat. If the roof space was to be occupied then the height on pitched roof building

was three-quarters way up the roof. The allowances for flat and pitched roofs and

the measurement to foundation depth are all very arbitrary. Additional allowances

need to be made for projections such as porches, chimney stacks, etc. Other

length

width

Page 38: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

21

weaknesses of this method are that it does not give any indication to a building

client of the amount of usable floor area, it takes no account of storey or plan shape

and it produces a large cubic quantity that will increase the possibility of further in-

accuracy in the estimate.

Figure 2.2 Cube Method

2.6.7 Storey Enclosure Method James (1954) as cited by Ashworth (1988) evolves a new method in an

attempt to overcome the many disadvantages of the other methods of estimating

using the following rules of calculation.

610mm

height width

length

height

equal

equal

Page 39: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

22

1. Twice t the area of the lowest floor.

2. The area of the roof measured on plan.

3. Twice the area of the upper floors, plus an addition of 15 per cent for the

first floor, 30 per cent for the second floor.

4. The area of the external walls.

The method attempts to take into account :

1. Plan shape ( by measuring the external wall area )

2. Total floor area ( by measuring each floor)

3. Vertical position of the floors (by using different multipliers for each

floor)

4. Storey height (ratio of floor and roof areas for external wall area)

5. Overall building height (ratio of roof area to external wall area)

6. Extra costs of providing usable floor area below ground (by using

multipliers)

James as cited by Ashworth (1988) claimed that it would perform better, in

terms of accuracy than the other methods. The weightings used are subjective and

are unlikely to apply equally to every building. In addition, the quantification does

not easily relate to the client’s accommodation requirements and as such fails from

the same deficiencies as the cube method.

2.6.8 Approximate Quantities

Approximate quantities provide a more detailed preliminary estimate than

any of the other methods described. They represent composite items which are

measured by combining or grouping typical bill measures items. In practice only the

major items that are of cost importance are measured. This method does provide a

Page 40: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

23

detailed and reliable method of approximate estimating, but it does involve more

time and effort than any of the methods previously described. No particular rules of

measurement exist and the composite items result from the experience of each

individual in practice. Considerably more information is required from the designed

if the method is to be applied adequately in practice.

2.6.9 Cost Planning

The first stage of cost planning can be used to determine the approximate

cost of a construction project. This method analyses the cost of the project on an

element basis often attempting to make use of the cost analyses from other similar

projects. Cost planning also seeks to do much more. It provides cost advice during

the design process, offering the client better value for money. It also keep the

designer fully informed of all the cost implications of the design in relationship to

an approved approximate estimate and likely accepted tender sum. Full cost

planning services would also incorporate the attributes of life cycle costing. Two

alternative forms of cost planning have been develop, although in practice a

combination of both is sometimes used. The first form is known as Elemental Cost

Planning where the project must be designed within an overall framework of a cost

limit. It is often referred to as ‘designing to a cost’. In practice it is more

appropriate to public sector projects which often incorporate some form cost limit.

The alternative form is Comparative Cost Planning where alternative designed can

be examined within an economic context. This method is referred to as “costing a

design”

Page 41: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

24

2.6.10 Analytical Estimating

This is the method that is traditionally adopted by contractors’ estimators to

determine their individual rates for measured items in bills of quantities. Each

individually measured item is analysed into its constituent parts of labour, material and

plants. Each part is then costed on the basis of outputs, gang sizes, material quantities

and plants hours. Particular emphasis is placed upon such project factors as type, size,

location, shape and heights as being important factors affecting the contractor’s costs.

In theory the contractor will make extensive use feedback. Alternative analytical

methods may calculate cost on the basis of operations rather than individual bill items.

Analytical estimating is not strictly a pre-tender method of price prediction,

because of the amount of time required and the type of data necessary. It will, however,

find application in those circumstances where, for example, a new material or

construction process is envisaged. In these circumstances where existing data is not

available, the design team may have no choice but to refer to analytical estimating.

2.6.11 Cost Model

Cost models are the latest technique to be used for forecasting the estimate cost

of a proposal construction project. Although they were first “discovered” during the

early 1970s there is only scant evidence of their use in practice. However, considerable

interest has been shown and research has been undertaken to convert the theory into

practice.

A mathematical model or formula is constructed that best describes the data

collected in terms of cost or price. The technique most widely used has been that of

multiple linear regression analysis, although evidence suggests that a more appropriate

technique might be that of simulation. The development of cost model is a lengthy

Page 42: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

25

process requiring the collection and analysis of large quantities of data, and then at an

appropriate stage testing the model against conventional methods before it can be put

into practice. A further disincentive towards the adoption of this method of estimating

is the radical approach to the treatment of the data. The use of a computer together with

appropriate software is essential when developing and using cost models due to the

large amounts of statistical analysis that is required.

2.7 Construction Cost

After the drawing and specification which represent the owner requirements

have been completed by the architect and engineers or the owner himself, the costs of

work have to be determined by the bidders ( contractors ) who will make offers to do

the work for the owner.

The cost of work is made up of different types of costs which constitute the total

cost. The analyze them, they may be classified as follows (Collier 1987):

1. Material costs.

2. Labors costs.

3. Equipment costs.

4. Overhead costs.

5. Profit.

Page 43: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

26

2.7.1 Material Costs

Different elements of costs are involved when estimating material cost. Storage,

freight, transportation and inspection are different parts of the cost of material (Collier

1987).

An estimator may keep current price lists of material for reference, and he

obtains as they are issued. But for basic materials or products that represent a

significant part of the total costs of a project, the estimator usually receives specific

quotation are desirable so that such important considerations as price, status freight

charges, delivery schedule and guarantees are explicitly covered. It is common

practice to enter material price as a lump-sum amount on the tendering sheet.

2.7.2 Labor Costs

A detailed contractor labor cost estimate includes two types of component :

direct labor cost and indirect labor cost.

2.7.2.1 Direct Labor Costs

This is the cost of labor directly related to the project such as engineers,

carpenters, foreman, etc. It can be calculated as follows :

A = B * C * D (Collier 1987).

Where:

A = Estimated labor cost for a quantity work.

B = Labor hours or crew hours required to accomplish a unit of a given work

type (production rate).

Page 44: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

27

C = Appropriate wage scales per hour.

D = Total number of units of work of this category. For an accurate

production rate, which is the largest area of uncertainly facing the

estimator, reliable labor productivity records from completed projects

should be available.

2.7.2.2 Indirect Labor Costs

This is the cost of labor indirectly related to the project, such as payroll, taxes,

insurance and employee fringe benefits of wide variety such as health paid vacations

and pension plans. Indirect labor cost normally constitutes a 35 to 50 percent addition

to the direct payroll costs (Collier 1987).

2.7.3 Equipment Costs

To evaluates and select one particular piece of equipment, it is essential to

determine its hourly cost very accurately. The equipment cost is divided into owning

cost and operating cost. The manufacturer’s data and past cost records constitute means

of determining the equipment costs. Some factors have to be considered at this stage

and they are (Collier 1987) :

Number of hours used per day, month and year.

Severity of job conditions.

The way the equipment has been maintained.

Demand for used equipment when it is sold.

Page 45: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

28

The above factors should be considered and studied carefully in the light of

estimator’s experience.

2.7.3.1 Owning Costs

Owning costs include the cost of depreciation, insurance and loss of interest.

This cost, divided by the average number of hours utilized in a year will give the hourly

owning rate. The straight line, sum of the year, or the declining balance method can be

used in calculation of depreciation per year.

2.7.3.2 Operating Costs.

Operating costs include the cost for fuel, lubricants, filters, grease, tires, repairs,

maintenance and any other variable costs. The manufacturer data is good reference but

most of the time, for marketing reasons, they are lower than the actual figures which put

more emphasis on previous cost records. One should also consider the job conditions.

An accurate estimate of total hourly rate for the operating costs is essential.

2.7.4 Overhead Costs

These are construction costs of any kind that cannot be attributed to any specific

item of work. Overhead cost can be classified into two types, namely, job overhead

costs and office overhead costs. If cost can be attributed to a specific job site because

the costs arise only out of that particular job, these costs are job overhead costs. If cost

Page 46: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

29

cannot be attributed to any particular job, they are office (operating) overhead cost

(Ferry 1972).

Overheads are a significant item of expense and will generally run from 5 to 15

percent of the total project cost, depending somewhat on where certain project costs are

included in the cost estimate (Carr 1989).

2.7.4.1 Office Overhead

The item of adequate overhead expense is sometimes neglected by many

contractors, but it is of such importance that every contractor should give it careful

consideration.

Every contractor has certain fixed expense that must be paid regardless of the

amount of work done or contracts received and these items should be charged to office

overheads.

These include such as office rent, fuel, lights, telephone and stationery, office

supplies, advertising, trade journals and magazines, legal and accounting expenses not

chargeable directly to any one job, fire and liability, insurance for office, club and

association dues, office employees such as bookkeepers, clerks, estimator, and services,

along with travel and entertainment expenses and depreciation of office furnishings and

equipment.

Page 47: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

30

2.7.4.2 Job Overhead

Each job will entail certain expenses that are chargeable to the job as a whole.

These are set forth in general conditions. These will include such items as

superintendent, temporary buildings, offices, utilities, protection, clean-up, permits,

survey, photographs, tools and equipment, insurance and benefits, sales taxes, surety

bonds and warranties. Sometimes, these are covered only in a general way and it is up

to the contractor to visit the site to determine what is needed.

As discussed above, job overheads and office overheads are most excellent kept

separately although, occasionally the cost of employees, insurance, tools and equipment

and other items may be divided between office expenses and job expenses.

Many contractors figure a certain percentage of the cost of the job to take care of

all overhead expenses and plant charge, but this is not the correct method to use and

does not give the contractor or estimator a reliable basis for computing the cost of this

work.

Each item entering into the cost job overhead expenses should be estimate in the

same way as any other branch of work.

2.7.5 Profit

The amount of profit to be added to the estimates cost of the work is a question

which a contractor must answer individually for each bid. There is no set amount that

can be added. It all depends on local conditions, competition, and how badly the job is

wanted.

Page 48: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

31

On small job alterations, remodeling and similar work a contractor is justified in

adding twenty five percent to the actual cost for profit. On new work where it is

possible to estimate the cost with a fair degree of accuracy, a contractor is entitled to ten

percent on the actual cost of the work but, when submitting competitive figures, it is

safe to say there are many jobs let on a five percent instead of an ten percent basis.

The amount of profit is generally computed as a percentage of the contract, or in

some cases, as a percentage of each item in the contract (Carr 1989).

2.8 Factors Influencing Estimating

Estimate costs are based on combination of historical data of previous projects

and price quotation received from suppliers or vendors. Cost estimates are influenced

by factors that arise from the operating environment. For instance, the cost varies if the

proposed project is constructed near a city or in a rural location. Effective construction

cost estimating is heavily dependent on experience (Carr 1989). Since estimating

process is a forecast of the future cost of constructing a project, it is a process

surrounded by uncertainty and risk. To produce a reliable estimate numerous factors

should be considered. Errors during the estimating process have cost construction firms

millions of dollars all over the years. Usually estimator uses cost data from past

projects or published in estimating guides. Using such data arbitrary without knowing

their similarity at hand will produce an inaccurate estimate because it is not based on

the reality of the current project (Carr 1989).

There are many items that influence and contributes to the cost of a project,

each item must be complied and analyzed. Since the estimate is prepared before the

actual construction of the project, a great deal of study must be put into the construction

documents, and this makes estimating one of the most important phases of any

construction business (Dagistino, 1973).

Page 49: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

32

The accuracy of any estimate is particularly important. Factors that influence

accuracy include the amount, type and quality of data available and the proficiency of

the estimator and the way that the data is interpreted. The estimating expertise depends

upon many factors such skill, experience, judgement, knowledge, intuition and luck

(Ashworth, 1983). Regardless of the type, preparing an accurate estimate requires

several skills. Andrian (1993) classifies three essential elements to an accurate estimate

stated as follows :

1. Determination of the quantity of work.

2. Identification of the productivity needed to perform the most difficult to

estimate, project drawings and the cost of rework.

3. Calculation of the unit cost of the resources to be used for the work.

2.8.1 Quantity Surveying

The development of the quantities of work to be placed in appropriate units is

referred to the quantity takeoff or surveying (Halpin 1985). Regardless of the type of

the estimate, items to be estimated must be listed. This is the most important look of

the contractor’s estimating and bid functions. Taking off the quantities from drawings

and specification is a time consuming step. Adrian (1983) assorts the required time and

accuracy level of quantity takeoff to be depending on :

The skills and procedures used by the estimator.

The quality of the project drawings and related documents prepared by

the designer.

The definition of the work items to be taken off the drawings.

Quantity takeoff may be done manually or by using electronic digitizers in

conjunction with estimating software. Since it is one of the most time consuming

Page 50: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

33

activities in the estimating process, contractors and owners more frequently use

computer system (Westney 1997). Traditionally, quantity takeoff is done manually

according errors are most likely produced. According to Halpin (1985) list some of the

most common errors as being :

1. Arithmetic, errors in addition, subtraction, and multiplication.

2. Transposition mistakes in copying or transferring figures, dimension, or

quantities.

3. Errors of omission, overlooking items called for or required to

accomplish the work.

4. Poor references, scaling drawings rather than using the dimensions

indicated.

5. Unrealistic waste or loss factor.

In addition to the foregoing list, Halpin (1985) has added two more common errors that

are 1)using wrong formula, and 2) using the wrong conversion factors.

2.8.2 Costing the Quantity Takeoff

Once the quantity takeoff is located to the work components, and the quantities

of each elements are tabulated, their cost must be indicated. First, estimator deals with

the direct costs that consist of the cost of materials, labor, and equipment for each work

components or elements. Doing so, typical mistakes occur. Halpin (1985) includes the

following :

Errors in simple mathematics (careless extensions of quantities times

unit prices.

Using old or unverified material unit prices.

Using wrong labor rates.

Transposing figures after extension are made.

Inadvertently leaving elements of the work off the pricing sheet.

Page 51: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

34

Basically cost estimates are prepared from three sources of cost related data.

These are 1) published cost information, 2) costs from similar projects and costs of

project equipment, and 3) historical company cost data files and in-house projects. The

sources of outside cost data are many, listed are some of the most common ones.

2.9 Different Types of Costs.

Although the determination of cost is the final in the preparing of an estimate,

estimator has to determine all types of costs to be engaged. The estimator has to have

ability to understand the concept of a cost and its components. This highlighted by the

fact that the cost estimate serves to initiate the project and to engage the contractor who

will build that project (Adrian 1993). Halpin (1985) classifies costs into four major

genera 1) Direct costs related to placing construction, 2) Subcontractor cost and

repayment, 3) Job indirect costs (for mobilizing), 4) Markup.

A direct cost of an activity is physically traceable to the activity in an economic

manner it is not counted if the activity is not performed. On the other hand, indirect

costs, known as overheads, are business costs other than direct costs of construction

activities, they are not physically traceable and are counted even the activity is not

performed (Carr 1989). Construction direct costs are those resources costs required to

place the elements of construction in a project. Meanwhile Carr (1989) classifies direct

costs as costs of material, labor, and equipment. Halpin (1985) includes the cost of

small hand tools. Traditionally, most contractors cover the project overhead costs by

adding a percentages to the direct cost. This method to be inaccurate and recommended

that project overhead costs can be estimated with some accuracy by carefully examining

contract conditions since they consider overhead cost is not part of actual construction

cost but an indirect cost. Estimating project overhead costs is the most difficult ones to

estimate with reasonable accuracy, especially for large and complex project (Collier

1984).

Page 52: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

35

2.10 Tools and Methodologies for Cost estimating

Regardless of the cost estimating type, the preparation requires specific tools

and methodology in order to achieve the most excellent out of it. According to Steward

(1982) list five basic tools for a cost estimate as follows 1) An estimator or team of

estimators, 2) A methodological approach, 3) Knowledge or data concerning the

project, process, product, or service, 4) A computation capability, 5) A publication

capability. Besides Westney (1997) pronounces that cost estimating tools include the

forms, hardware, and software used to execute the estimating methodology. Estimating

tools fall into the two broad classes of manual forms and computer software.

Additionally the Project Management Institute considers that computerised tools are

widely used to assist with cost estimating. Parametric tools bring speed, accuracy and

flexibility to estimating process that are often bogged down in unnecessary detail.

2.11 Summary

Thus chapter has reviewed previous theories and practical works related to the

process of construction cost estimating. The literature review reveals that the most

important types of construction cost estimates is the preliminary estimates. Major

decisions are based on this estimates therefore the level of accuracy is an important

issue. Many factors influence the process of producing accurate estimates. Beside the

estimator experience, method and the amount of data available, are effective tools that

will be most likely aid the estimating processes. Indeed computers are practically the

first tools to consider in this task.

Page 53: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

36

CHAPTER 3

COMPUTER AND COST ESTIMATING

3.1 Introduction

This chapter the role of computers, as an effective tool to increase the level

of accuracy and reduce the time required in preparing a construction cost estimate.

Computer have tremendous number and type of applications in construction

business, which very from accounting to scheduling, estimating and so forth. Fast

and accurate estimate is one of the key factors that can make the difference between

gaining a reasonable profit and running out of business. Therefore the use

computers is essential to fulfill this obligation.

In Malaysia, computers were used to prepare cost estimating since 1980’s

(Chong WP,2001). At that time, Quantity Surveying System (Q.S.S) was selected by

the QS Department of Jabatan Perumahan Negara to handle the taking off, cost

planning, tender procedure, interim payment, variation orders, cost estimating,

tender report, specification, preliminaries, prime cost and provisional sum.

In the mid 1990’s, when the computer are becoming more affordable and

user friendly and more contractor and consultant firm are using the computer to

facilities their work not only in the technical field but in administrative works. At

the same time, students and trainees in this field were exposed in the importance of

information technology and as a matter of fact, more construction graduates are

well-literate in computers.

Page 54: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

37

On the development of computer software and application, more and more

complete, reliable and easy to use software was produced. More and more specific

and specialized software for construction industry were being produced and being

introduced to the industry. From a blue screen of dimension sheet ( the old DOS

version of specific software ), it has develop in a 32-bit application with enhance 3D

and digital imaging for instant processing. The latest version of the software would

be able to automatically calculate quantity from CAD drawing and produced a

complete BQ and cost estimating in just a few mouse click.

3.2 Use of Computers in Construction

Most construction cost estimates in the past and newfangled are performed

manually accordingly errors are most likely to occur. Thus the use of computers in the

construction industry is growing rapidly. The early use of computers in construction

and general accounting functions. Nowadays, computers increasingly are playing a big

role in the contractor’s project management functions, including estimating.

Computers have introduced modern technology to the construction industry. The

estimator in search of any advantage that can assist in preparing an estimate (Jurkiewicz

1999). Computers play an essential role in cost estimating because estimating may

involve complex and advanced mathematical calculations and techniques. Automating

the process of construction cost estimation is desirable not only for improving the

efficiency, but also for reducing human errors as much as possible (Wu and Adeli

1998). Computers cannot do the entire estimating process, but they can ease the

estimating procedure. The use of computers in documenting cost estimating, give

estimators more times to study and analyze projects. Consequently, estimators will be

able to generate more accurate estimates (Cost Engineering Journal 1998).

Page 55: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

38

3.3 Computer the Estimating Tool

The accuracy of any estimate depends greatly on the tools used in the tools used

in its preparation. Cost estimators need tool that not only forecast and tracks cost, but is

able to reduce considerably the burden of data entry as well as provide instantly

reliable financial reports. One of the estimator’s most important tools is the computer

and associated software. Today, personal computer is most often the estimator’s

choice. ( Dyset and Elliott 1999). Once you learn to build an electronic estimate on the

screen, you will be able to turnout more estimates, faster, with less chance of making an

error, analyse and manipulate numbers before you finalised you bid.( Feldman 1996).

The use of computers with cost estimating can simply and facilitate rapid consideration

of many costing alternative (Ducan 1996). Listed are some of the activities that

computers can be used for (Duncan 1996) :

Performing quantity take-off using digitizer.

Performing extension of units of labor, material, equipment and other

expenses to develop the estimate.

Developing spreadsheet for bid preparation.

With digitizer, contractors can electronically make measurement from blueprints

and prepare detailed estimates with a day ( Cost Engineering Journal 1999). Hence

computer estimating programs can greatly reduce the time it takes to perform quantities

take-off and prepare bids, increase calculating accuracy and create a professional

looking estimate. As well as offering an easy way to evaluate job profitably.

3.4 Computer Software for production of Cost Estimates

There is a large number of estimating software available to the construction

industry. Yet computer programs encompass a significant portion of computer

Page 56: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

39

software that are prepared by the process known as programming. Andrian (1993)

defined programming as being a prepared set of computer instructions that provides

the mode of solving a specific problem. These programs are available to perform

complex pricing, estimating, and analysis functions. It is difficult to generate overall

ground rules of thumb for computer software cost estimating because of the increasing

number and types of computers and computer languages (Steward 1982). Steward

(1982) has grouped cost estimating software programs into two kinds:-

1. Industry-dependent systems based on predefined historical data and

equations with specialized reporting facilities. The equations are

usually concealed in the source code or in the data files, out of reach of

the user. Normally they are written in a high –level language like C,

C++, or Visual Basic.

2. Systems primary focusing on production of cost reports generators.

Historical data and algorithms are usually kept separate from the

estimating system. These systems are written in a spreadsheet language

or database.

The utilization of estimating software allows the contractors to breakdown

costs to the last minute. They provide wide range of capabilities-from conceptual to

final estimate, also they simplify the task of providing different cost views of an

estimate. Most estimating computer programs are either written in-house or

purchased from vendors. In both cases the result has not been entirely satisfactory in

achieving the desired results because this satisfaction requires both the engineer and

programmer to be highly trained and experienced in the field of estimating. Steward (

1982) has ranked the elements that affects the development of estimating software as

following:-

1. System size and complexity (in terms of the number of code lines or of

function. Modules or program features).

2. Personnel capabilities and experiences

Page 57: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

40

3. Hardware constraints.

4. The use of modern software tools and practices.

5. User understanding of the software.

Several software developers sell their estimating software with own quarterly

database updates or third parties database. In addition of considering most estimating

programs to be based on the use of some vendor’s database. Hicks (1992) listed the

similarity of these programs as:-

Difficult to learn and to operate in a reasonable length or time.

They have a tendency to shift the user’s attention from estimate

preparation to program manipulation.

They have many auxiliary features more or less to estimating but

unnecessary for estimate preparation.

They lack the ability to do what is necessary for estimate closure and bid.

Although, Steward (1982) has listed the advantage of these programs as the consistent

organization and format for estimating, the capabilities of estimating item by item.

He also listed the disadvantages as giving a rigid format and very few short cuts are

permitted. In the same manner, Miller (1998) provides some of the problems that

might be encountered by the use of vendors’ database 1) a database that has been

developed in another country or state and does not match how things are done in the

geographic area where the company is located 2) The database generate too much

information ( i.e. the number of nails needed for forming). 3) The database contains

formulas that use multiplication factors with no explanation of why they are there ( in

case of calculation quantities). Furthermore, as a solution for these problems Miller

suggested to create own database from scratch, starting by the determination of the

basic coding structure with respect to the industry standards. The database available

from vendors can be good guide on how to build a database with the requirement of

modifying them in order to fit individual estimating methods.

Page 58: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

41

3.5 Industry Programs

In general, the available estimating programs in the market typically require

few days of training to get familiar with and to operate. Additionally, if other

functions are to be tied into the estimating process then a modular package is required

and in this case the training time span will extended.. Software developers have

designed computer programs to meet the needs of a specific industry. Since industry

programs are developed for a specific business or industry, they are referred to as the

vertical market, because they are sold to one business type rather than many.

MASTERBILL, BUILDS SOFT, RIPAC , GENERALCOST ESTIMATOR AND

GOLDENSEAL ESTIMATES are a few of many industry programs. Some other

computer application aid in improving the efficiency and accuracy of the construction

estimating process, such as Computer Aided Design (CAD) application, math

Conversion applications, Database applications, and simulation applications ( Andrian

1993).

3.5.1 Masterbill 3 (MB3)

MB3 is being developed by Masterbill Micro System Ltd. It is one of the

leading software for QS in Malaysia. MB3 is a fully featured BQ production package

comprising pricing, tender analysis, estimation and valuations features, plus multiple

libraries and ability to transfer data between projects. However, MB3 only have a

simple format for estimate calculation.

Page 59: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

42

Figure 3.1 : Sample of Interface Masterbill 3 (MB3)

3.5.2 Ripac For Microsoft Windows

Ripac dominates the world market for QS software. Ripac is produced and

supported by CSSP, an international software house specializing in construction

solutions . Ripac is used by Quantity Surveyor for quantities measurement, tender

analysis, contract administration and management (CSSP,2002).

Every measurement with Ripac will simultaneously create a database from

which every calculation, every analysis, every report can be produced for pre and post

– contract administration without recreating data. Ripac gives QS the power to

integrate all their activities at pre and post contract stages, maximizing the

productivity of their resources and increasing the range of their services. Ripac can

do the following process comprehensively :-

Page 60: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

43

a. Bill preparation

b. Estimating

c. Tender appraisal

d. Payments

e. Cost reporting

f. Final accounts.

Figure 3.2 : Sample of the Ripac Measurement Screen

3.5.3 Builds Soft

Global Estimating is an estimating program that has been tailored for commercial use in the building and construction industry. It produces Bills of Quantities or detailed Estimates and Cost Plans. Designed primarily for use by commercial

Page 61: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

44

building contractors and professional Quantity Surveyors it includes features which allow it to be used in other industries where estimating is required.

Information that is entered into the program can be re-sorted or analysed by the use of powerful grouping columns. For example, the estimate can be summarised to produce totals by area, block, stage, cost centre, accounting group, or any user defined set of codes.

Figure 3.3 : Four Level Estimating System in Build Soft

Figure 3.4 : Interface of Trade Breakup ( Level 2 )

Page 62: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

45

Figure 3.5 : Interface of Rate Breakup ( Level 3)

3.5.4 General Cost Estimator for Excel 4.0

General Construction Cost Estimating System for Excel. Designed specifically

for contractors, builders, cost estimators, architects and construction professionals.

GeneralCOST Estimator contains industry standard cost data in the CSI format (16

division) for all cost categories covering general construction. Unit prices include

material and labor including labor hours. City indexes are automatically applied to

adjust costs for your local area. Easily modify and add cost data to suit your local

conditions and business. GeneralCOST Estimator instantly creates user-modifiable, on-

screen or printed estimate reports including price quotation. Built-in Step-By-Step

tutorial makes learning fast and easy. Use GeneralCOST Estimator as an estimating and

bidding tool to save time, improve accuracy and achieve greater success.

GeneralCOST Estimator is designed and developed in the USA by CPR International,

Inc., a leading provider of cost estimating software tools and cost data for the

construction industry since 1986.

Page 63: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

46

Figure 3.6 : Sample Interface of GeneralCOST Estimator

3.5.5 Goldenseal Estimating Software

The Goldenseal estimating program includes many cost estimation features that

help users to increase the accuracy of the project estimates, and reduce the time it takes

to prepare a bid:

• dimensions calculate quantities from a few simple measurements

• unit costs and assemblies calculate an accurate cost for the work -- and

update automatically when prices change

• competitive bid tracking handles price quotes from suppliers and

subcontractors

• project templates make it easy to estimate "standard" types of projects

Goldenseal estimate, can automatically get other useful information from it--

including a project schedule, contracts and material takeoff lists. Goldenseal has many

Page 64: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

47

features that are simply not available in other estimating programs for construction and

other fields. The Goldenseal project estimator program includes "smart dimensions"

which take simple project measurements, and convert them into actual quantities for the

items in estimates.

Figure 3.6 : Interface Goldenseal Startup Guide

Figure 3.7 : Interface Goldenseal Estimates

Page 65: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

48

3.6 Review Of Software

Review of software were done by running the software or intensively studying

on the demo disc provided by supplier. The results of the review were classified into

the following categories for easier comparisons and documentation :

a. System Feature

b. Screen Layout Features

c. Cost Estimating Features

d. Dynamic Link

3.6.1 System Features

Computer technologies has been growing at a very fast pace. All systems must

be able to be up-to date so that user can benefit more from the new enhancement in

the information technologies. At present, the operating system that were widely use

were Microsoft Windows with XP version being the entry level to new computers.

Although there are users who use other operating system such Linux, Mac OS, DOS

etc, most of the software developers are concerning on the Microsoft Windows

platform for is huge share in the market.

Watkins (2002) recommended that the software system worth considering

must be a true 32-bit Windows system. It should no be an 8/16 bit hybrid or DOS

with a Windows-like front end system. Starting from the Windows 95 version,

Microsoft and the computer world are moving into 32-bit environment. Obviously,

32-bit system provides a better computing platform than the old 16-bit system.

To understand the difference we must first go back a little while. The very

first IBM PC caused quite a stir when it was released as it used 16-code and as a result

Page 66: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

49

ran 16-bit applications. Prior to this, the most powerful computers had 8-bit

processors and could only stores only up to 255. However, these new 16-bit

processors could handle 16-bit numbers (i.e 0 to 65,535) quite efficiently, but still to

deal with larger numbers it was forced to do some extra work carrying out double the

instruction in order to get round its number handling limitations.

Modern 32-bit applications can handle 32-bit quantities as easily as a 16-bit

application handles 16-bit quantities. Basically 32-bit is superior when handling 32-

bit values (i.e. o to 4,294,967,295) and as a result will probably run faster because

fewer instructions and fewer memory accesses are required.

Beside that, 32-bit application also has a greater capacity for dealing with

larger quantities of data. A 16-bit programmed can deal with only 64K of data at a

time, but a 32-bit application can work with up to 4GB. This means a 16 bit

application must do more work to read and write large quantities of data. The

difference is insignificant when an application is dealing with arrays, data structures

and others smaller than 64K in length, but when the data size exceeds 64K the larger

segment size available to 32-bit applications pays great dividends because an

application does not have to load and reload segment registers to access all the data.

The extent to which 32-bit code speeds up an application depends on the extent

to which the application performs these kinds of tasks; moving data around in

memory; adding, subtracting, multiplying, dividing, comparing, and in other ways

manipulating 32-bit values; and handling large arrays. 32-bit applications won’t be

superior in every circumstance but given the size of a typical application carrying out

the same tasks.

Furthermore in Windows a 32-bit application is a accorded special treatment

by the operating system :

Page 67: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

50

32-bit Windows application are pre-emotively multi-tasked, while 16-

bit windows application are cooperatively multi-tasked.

32-bit Windows application can spawn additional threads of execution

to do work in the background such as printing that can dramatically

increase an application’s speed and responsiveness.

32-bit Windows application have access to the richer Win32

application programming interface (API); 16-bit application are still

stuck with the old Windows 3.1 API.

In general Windows 95/98 is a better operating system if use 32-bit

applications and the situation is likely to be even more dramatic in the fully 32-bit

environment of Windows 2000. With the trend now showing sign of moving into a

64-bit system, where AMD has managed to produce the 64-bit processor, it will be

soon that the 32-bit system becomes obsolete.

3.6.1.1 Builds Soft

Build Soft is Microsoft Windows compatible where they can be installed in all

version of Windows. They are a 32-bit application and can support up to a 64-bit

environment (for future upgrade only). It ha s a similar Microsoft product ‘look and

feel’ in order for new user to quickly adapt to their environment. Besides, Build Soft

employed Windows such as right mouse button functionality and can link to other

Windows product.

On the database part, Build Soft uses the SQL database format. SQL stand for

Structured Query Language and SQL database have been used in the IT industry for a

number of years. In its previous version, i.e Builds Soft, it adopt a third party SQL

called Sybase SQL. Anywhere in their products which involve the software being

Page 68: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

51

installed on both the server and the terminal machine in order to make the data

available across the network.

The main advantages of using a SQL are speed and stability. An SQL

database provides a ‘true client/server’ networking, which is ideal for use over either a

Local Area Network (LAN) or Wide Area Network (WAN). True client/server

networking means that the server will only supply specific data in response to client

request. An a result, the software will not be vulnerable when hardware or

networking problem occurred. A SQL database also ensures that ‘open database

architectures’ is adopted. This mean that other application can have access to the

database with little application.

3.6.1.2 Ripac

For the Ripac system, it is not known whether it is a 16-bit or 32-bit system.

However, it is developed for all version of Microsoft Windows including the earliest

version being the Windows 3.1. Ripac need a very low system resource in order to

run. Based on the technical specification, it only needs a 486 – 50 MHz PC with 8Mb

of RAM and 20Mb of hard disk space.

3.6.1.3 The proposed application (COES)

The proposed system will not have anything to concern in the regards.

Whether it is a 16-bit or 32-bit system or even the future upgrade 64-bit system, it will

have no effect on the COES application. This is because COES is will just another

application which resides inside Microsoft Office. As long as the Microsoft Office is

upgraded, the application will be upgraded too.

Page 69: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

52

The system required for the COES will be determined by the system

requirement of the Microsoft Office version. This should not give any threat to this

software as the entry level of the computer today is at Pentium IV 2.60 GHz processor

with 256Mb of RAM while the latest Microsoft Office 2003 version only needs a

Pentium III processor with 128Mb of RAM (Halbrok, 2004).

On the COES database, it does not employ an external database system. Since

COES is true Microsoft Office application, it has no problem sharing its database with

any other external program. Moreover, COES will only required a simple 2D

database for keeping its description library and as such, it does not need the

sophisticated external database system. Initially, this application proposed to use

Microsoft Excel as its database system but in the end, it was determined that

Microsoft Access itself will be more than enough for such a simple database.

3.6.2 Screen Layout / Graphical User Interfaces (GUI)

For normal and average user, this is the feature that determined whether the

software is good or not. Therefore, it is important that this feature was given high

emphasis on the development stage. Screen Layout Features / GUI does not have to

be “beautiful” in terms of it back screen, icon, dialog boxes, etc. More important

aspects are the interfaces and the navigational tools that have to be kept as simple as

possible. For example, a user shall only be require to click one or two buttons for him

to go to a required page rather than navigate here and there which is time consuming.

A GUI with mouse intensive is much preferable than the keyboard shortcuts.

However, it is still important not to discount the much faster keyboard shortcuts for

advance users and sometimes inaccessible function by mouse. Besides that,

single/double clicked menu, drop-down list, check boxes and tools button are much

more preferable than the traditional coding and keyboard system.

Page 70: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

53

As explained, Masterbill and Build Soft is developed in a Microsoft Windows

Environment and utilized the Microsoft Features. Therefore, all its Graphical user

Interface are to Microsoft standard and all of the them are accessible by mouse click.

Moreover, it has a similar text editing features and use Windows fonts. In additional

to that, Masterbill and Build Soft allow user to view on their dim sheet, selection of

item (libraries) and calculation cost estimate. Furthermore, it has a user defined

headers and footers as well as numbering and referencing.

Ripac has menus, entry routines and reporting which are totally compatible

with Microsoft Windows. Ripac leads the user through project setup and data entry in

a simple and intuitive style.

3.6.2.1 The proposed application (COES)

Starting with the Access 95 version, the interface has allowed user to create

custom forms, dialog boxes, check-boxes, user-define tools and etc as a method of

simplifying the data-entry processes. Nevertheless, there are not many of the users

who were able to utilize this tools as it needs some basic programming knowledge to

create a transfer the entered data into the relevant form.

The COES application will fully utilize this tools to match the user interface of

the specific software while making sure that the data entered will reach its true

destination. Moreover, COES is an application build with Microsoft Access.

Therefore, all Microsoft Access interfaces, shortcut keys, function, formula, tools, etc

will still be available to the user.

Page 71: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

54

3.6.3 Cost Effectiveness For Specific Software

The main purposes of using computer software are to save time an reduced

error for double-handling work while maintaining the accuracy of cost estimate. The

time saving will subsequently generated in cost saving as the companies can save on

resources (particularly salary and office overhead) spend on each project. Besides

that, it also increase the efficiency and motivation of estimator as he no longer needs

to got through long, tedious and repetitive tasks.

A research by Chong S Y (2001) found that the most important factors that

affect the cost effectiveness of the specific software are :-

a. Reliability of software

b. User-friendliness

c. Sufficient feature of the software

d. Maintenance

e. Number of computers

These factors plays a big part in determining whether a software success or

not. Therefore, these factors were seriously studied and incorporated into the

application.

3.6.3.1 Reliability Of Software

Good and reliable software must be consistently functional so that cost

effectiveness for the usage of that software can be achieved. Unreliable software will

cause havoc where the result will not be accurate. Besides, more time and resource

will be spent in order to check and rectify all those mistakes. (Chong SY, 2001)

Page 72: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

55

Unreliable software can be defined as software which always caused the

system to crash and hang. Besides, there were computer bugs all around and

sometimes cannot perform some important function that it have. Moreover, some

system will not be able to handle a large amount of data or will cause to use a huge

amount of computer resources such as a hard disk spaces and the memory.

However, nowadays, established software such as Microsoft Windows and

Microsoft Office which were running on a 32-bit Windows system shall have

eliminated much of these problems. Nevertheless, this might not always happened

with all the specific software. From some user experience, the software did hang up

and crash especially when the amount of data exceed the capabilities of the computer.

3.6.3.2 User-friendliness

Software that is user-friendly will be easy to learn and use. New user or

employee will not encounter big problem to use user-friendly software even without

through and proper training. The staff will not have to waste time in looking for the

supplier help once there are any problems if the software is user-friendly (Chong SY,

2001). A user friendly and efficient system with proper training and motivation will

bring more effective as well as economic service (Kelly 1990).

There is some specific software which is actually not user friendly. For all

novice and average users, the modern trend is to use the mouse and the click, and the

drag and drop command. Undoubtedly most software has this interface in their

system. However, what is really lacking is the shortcut command in which most

advance user are familiar with. It is a sure bet that most specific software have their

own shortcut key assignment which is totally different to Microsoft Windows standard

interface. This is extremely troublesome and can cause a lot of accidental errors.

Therefore, the system developed must be as similar to the Microsoft Window system.

Page 73: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

56

3.6.3.3 Sufficient Features Of The Software.

Software ought to have sufficient features in order to have an efficient

performance or else saving in terms of time value failed. (Scott, 1987). In actual fact,

Cost Estimating production software shall have a full feature of automatically

producing cost estimate from the measurement sheet. However, most specific

software come with other feature such as analysis of cost estimating, comparison of

bids and tender appraisal, monthly or interims valuation, variation control and

scheduling.

Of course, these additional features are very good in nature but does anyone

really need it. As a matter of fact, the more feature that the specific software has, the

more expensive it will be. Therefore, does this feature add to the cost effectiveness

of the software or reduce it?

3.6.3.4 Maintenance

Maintenance of software can be defined as service provided by the

supplier/technical staff of the software developer periodically to ensure smooth

functioning of the software. Maintenance ensures that the software is always fully

functional and the work will not be stop as an effect of corrupted software. If problem

always occur because of no proper maintenance schedule, it will cause delays in

estimator works. Therefore, cost effectiveness will not be able obtained .(Chong SY,

2001).

As a matter of fact, the maintenance service does not come cheap. For

example, the supplier for specific system charged a minimum fee of RM3,000.00 per

annum for annual support maintenance charge.

Page 74: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

57

Of course maintenance is important but what if a software that does not need

maintenance or need only simple maintenance. This can be achieved if the software is

kept in the simplest format where any staff with some computer technically could

reinstall the software if any problem occurs. Besides that, if the software is properly

developed and tested, there shall have little problem with the software.

3.6.3.5 No of computer

According to the specific software suppliers, number of computers will give

effect to the cost effectiveness of specific software. In order to get optimum cost

effectiveness, the optimum ratio of computer to user is 1:1 (Chong SY,2001)

3.7 Justification for Using Microsoft Access

The research is focusing cost estimating system with Microsoft Access 2003.

From the study majority of the respondents using Microsoft Excel in preparing cost

estimating and the user has to develop the formula before develop cost estimating. As

we all concerned, Microsoft Access has been one of the most common and easy to use

application to develop simple programmed for Windows. Initially, this research is to

use the Microsoft Access as the programming language. Another key point of

programming in Microsoft Access is that output application can be used as an Add-ins.

This Microsoft Access programming language offers a lot of advantages Among them

were :-

a. Prevent access to the programmed code.

End user cannot view the programmed codes in the workbook.

Page 75: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

58

b. Avoid confusing users.

If an end user loads the application as an add-ins, the file is not visible and is

therefore less likely to confuse novice users or get in the way

c. Easier access for users.

The steps were in a multiple path ( where clicking here and there ) and this

have made the system to be error-prone..

d. Always a read only

User cannot make accidental (or intentional) modifications to the workbook

or code.

In fact, the concept that made this application distinguished from other

specific software development is that it only Microsoft Access to create an application

that can match the ability of the specific software.

Page 76: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

59

CHAPTER 4

ANALYSIS AND RESULTS

4.1 Introduction

A through planning and scheduling had been organised on the methodology and

research sequence to ensure a smooth running of the research program from literature

review, data collection, data analysis until discussion of result and conclusion.

Literature review involved a through searching and investigating project

manager related issues through different primary and secondary sources such as

textbooks, articles, and journals. In additional, there also effort on searching and

browsing through internet web pages, internet websites, electronic database and online

articles and journals to seek for supplementary information. The purpose of literature

review is to gather important information related to the topic and deepen the

understanding of cost estimating.

4.2 Data Collection

Despite literature review, interviews were conducted with relevant parties who

have involved in preparing cost estimating, to find out hands-on issues and experiences

related preparing cost estimating. This was preceded by a pilot study in which the

interviewers were asked to consider the layout, order, complexity, intelligibility and the

Page 77: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

60

length of the questionnaires. In other hand, series of question were set for conducting a

survey to obtain feedback and response from the local construction industry. Then, the

questionnaires were distributed through mail to several contractor Class A, Class B,

Class C and Class D who have been registered with Pusat Khidmat Kontraktor (PKK)

and Construction Industrial Development Board (CIDB) in Johor Bahru. Both the

interviews and questionnaires were conducted to support the literature review.

4.3 Data Analysis

Upon the collection of questionnaires, every type of data received under

different questions will be separated and segregated to answer different research

objectives. The data will be categorized under different variables to represent the result

of the research objectives. Different statistical methods such as frequency analysis and

average index analysis were being used in the data analysis.

4.4 Frequency Analysis

Frequency analysis will be using tabular form to represent result of data analysis

of frequency of response that respondent give to the different variables in the

questionnaires. The result was tabulated in the form of frequency number and

percentages according to total respondents. For graphic result presentation, bar chart

and pie chart will be used as summary.

Page 78: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

61

4.5 Average Index Analysis

In average index analysis, the result will further summarized to obtain the level

of efficiency of methods and computer software uses by contractor to prepared cost

estimating. The respondent were requested evaluate methods and computer software

on five point scale starting with 1 for extremely inefficient, 2 for inefficiently, 3 for

moderate efficient, 4 for very efficient and 5 for extreme efficient.

The classification of the rating scales proposed by Abd. Majid, M.Z., McCaffer,

R., (1998), have been referred in this study. The classifications of the rating scales are

as follows:

Average Index Level of Importance or Evaluation

4.50 ≤ Average Index ≤ 5.00 Extreme efficient/used

3.50 ≤ Average Index < 4.50 Very efficient/used

2.50 ≤ Average Index < 3.50 Moderate efficient/ used

1.50 ≤ Average Index < 2.50 Inefficiently/less used

1.00 ≤ Average Index < 1.50 Extreme inefficiently/not used

All the collected data from the questionnaires were analysed in frequency

analysis as preliminary analysis. This method shows the frequency and the percentages.

The frequencies are then represented in the form of tables and pie charts.

4.6 Data Analysis

A detail analysis of data and result will be shown and elaborated by using

Frequency Analysis and Average Analysis. In order to complete the master dissertation

Page 79: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

62

Class A51%

Class B8%

Class BX22%

Class C19%

Class A Class B Class BX Class C

Categories Contractors

Class A Class B Class C Class D Total

No of questionnaire

returned from respondent 19 3 8 7 37

Percentage 51.35 8.11 21.62 18.92 100.00

project, 60 respondents were specifically identified as the targeted respondents of the

“Computerised Building Cost Estimating System”. The respondents included the

contractors Class A, Class B, Class C and Class D. Among 60 sets of questionnaire

forms distributed, there were 37 sets of replied with complete questionnaire from that

cover 62% of the total 60 sets of questionnaires in the study.

Table 4.1 : Response Percentage

Figure 4.1 : Response Percentage

Page 80: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

63

Class Contractors

No Method of Estimate Class A Class B Class C Class D Total Percentages

1 Unit Method 12 1 3 4 20 542 Cube Method 2 2 3 0 7 193 Superficial or floor area method 7 1 4 3 15 414 Storey enclosure method 2 0 0 0 2 55 Element cost analysis 13 2 7 4 26 706 Comparative estimates 9 1 4 0 14 387 Interpolation method 1 0 0 0 1 38 Approximate quantities 15 3 5 6 29 78

Total Respondent 19 3 8 7 37

54%

19%

41%

5%

70%

38%

3%

78%

0

10

20

30

40

50

60

70

80

Percentage

1MathodUnit Method Cube Method Superficial or floor area method

Storey enclosure method Element cost analysis Comparative estimates

Interpolation method Approx imate quantities

4.7 Section A :

Estimating Model

4.7.1 What kind of cost estimating method applied by your company?

The respondents were asked to identify, from the list given, the method that the

respondent represents in order for preparing cost estimating. The results for question

A.1 shown in table 4.2 below:

Table 4.2: Method use for Preparing Cost Estimating

Figure 4.2: Percentage of Method use for Preparing Cost Estimating

Page 81: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

64

Class of ContractorsNo Factors Class A Class B Class C Class D Total Percentage

1 Easy to apply 6 1 3 2 12 322 Time factor 10 2 4 5 21 573 Types of project 11 2 4 1 18 494 Types of contract 8 4 3 4 19 515 Size of project 7 0 4 2 13 356 Information given by client 13 1 5 4 23 627 Client requirement 6 1 2 3 12 328 Cost Estimate obtained is more accurate 3 2 5 2 12 32

Total Respondent 19 3 8 7 37

Table and figure 4.2 shows the percentage of method use for preparing cost

estimating where majority (78%) of the respondents were used approximate quantities

method for preparing their cost estimate.. From the total number of respondents, 70%

were used elemental cost analysis method while only 3% of the respondents were use

interpolation method.

4.7.2 What are the factors of choosing the cost estimating method as mentioned ?

The respondents were asked to identify, from the list given, factors of choosing

the cost estimating method as mentioned. Table and figure 4.3 shows the percentage of

factors choosing the cost estimating method.

Table 4.3 : Factors of Choosing Cost Estimating Method

Page 82: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

65

32%

57%49% 51%

35%

62%

32% 32%

0

10

20

30

40

50

60

70

Percentage

1Factors

Easy to apply Time factorTypes of project Types of contractSize of project Information given by clientClient requirement Cost Estimate obtained is more accurate

Figure 4.3 : Percentage of Factors Choosing Cost Estimating Method

From the analysis it was found that 62 percent or 23 out of the total 37

respondents were choose information given by client as a important factors for choosing

the cost estimating method in order preparing cost estimate. Time factor were contribute

57 percent or 21 out of the total 37 respondent, types of contract contribute 49 percent

or 18 out of the total 37 respondent and size of project contribute 35 percent or 13 out of

the total 37 respondent.

The others factors such as easy to apply, client requirement and cost estimate

obtained is more accurate only contribute 32 percent or 12 out of the total respondent.

The number of contractors involved in this questionnaire survey will provided a good

result in terms of their knowledge and experience which can contribute to this

investigation.

Page 83: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

66

Cost Estimating Method

A B C D E F G H

No Type of Contract No % No % No % No % No % No % No % No %

1 Work Order 12 32 2 5 3 8 0 0 10 27 5 14 5 14 3 82 Lum Sum Contract 9 24 1 3 13 35 0 0 19 51 11 30 3 8 0 03 Bill Of Quantities 15 41 1 3 2 5 0 0 17 46 13 35 5 14 0 04 Cost Plus Contract 8 22 0 0 5 14 0 0 9 24 8 22 2 5 0 05 B.O.T Contract 3 8 2 5 3 8 0 0 8 22 8 22 2 5 2 56 Turnkey Contract 7 19 1 3 2 5 3 8 7 19 6 16 1 3 2 57 Schedule of Rate Contract 9 24 0 0 3 8 2 5 10 27 5 14 0 0 0 0

Total Respondent 19 3 8 7 37

4.7.3 What types of cost estimating method, which your company applied to the

project ?

The respondents were asked to identify, from the list given, types of cost

estimating method used for several types of contract. Table 4.4 shows the percentage of

factors choosing the cost estimating method.

Table 4.4 : Cost Estimating Method used for Several Types of Contract

Legend:

A : Unit method B : Cube method

C : Superficial or floor area method D : Storey-enclosed method

E : Approximate quantities F : Elemental cost analysis

G : Comparative estimate H : Interpolation method

Table 4.4 shows the analysis of cost estimating method used in preparing cost

estimate for several types of contract. According Hashim Sikan (1999), work order

contract in general used in public sector for small project and the interim payment base

on schedule of rate. It was found that unit method is the high frequently method used in

preparing cost estimating for work order contract, where represents 32% out of total 37

respondents. Percentage for approximate quantities method using in work order contract

Page 84: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

67

only 27% out of total respondents. From the analysis shows, overall cost estimating

method has been listed above represents below 50% from the total of respondents.

For lump sum contract, approximate quantities method were the highest

frequently used in preparing cost estimate. From the total number of respondents,

approximate quantities method represent 51% in lump sum contract, 46% in bill of

quantities contract, 27% in schedule of rate contract and 24% in cost plus contract.

As a conclusion, majority of the respondents declared approximate quantities

method were the most popular technique in preparing cost estimate for any type of

contract. Elemental cost analysis is a secondary method or child in approximate

quantities in order for preparing cost estimate for several types of contract.

6.7.4 How frequently the sources of unit rate that your company referred to?

The respondents were asked to rate the degree of uses on the list of how

frequently the sources of unit rate that the contractor referred in preparing cost

estimate.. In analyzing the data, the following assumed values have been considered for

responses on the degree of frequently used by the contractors: “Not Used” (1), “Less

Used” (2), “Moderately Used” (3), “Very Used” (4), and “Extremely Used” (5). The

list provided was produced by the researcher from the case study carried out and was

arranged and classified according to the research objective. The results presented in

Table 4.5 shows a full list of frequently used the sources of unit rate listed in the

questionnaire.

Page 85: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

68

Table 4.5 : Degree of Frequently used the Sources of Unit Rate in

order of Preparing Cost Estimate

No

List of Sources

1

%

2

%

3

%

4

%

5

%

Average

Index

1

Base on catalogues or supplier quotation

0

0

0

0

0

0

11

30

26

70

4.702

2

Based on built up rate

0

0

0

0

0

0

15

41

22

59

4.594

3

Base on past project

0

0

0

0

2

5

12

32

23

63

4.567

4

Base on experience

0

0

0

0

0

0

9

24

28

76

4.757

5 Base on elemental cost analysis

0

0

0

0

5

14

24

65

8

21

4.081

6

Base JKR’s schedule of rate

6

16

14

38

17

46

0

0

0

0

2.297

The explanation and a review of the survey results received for each sources listed in

the table are presented in the section that follows.

4.7.4.1 Base on Catalogues or Supplier Quotation

This result reveals that 70 percent which 26 out of 37 respondents agreed that it

is extremely used that the catalogues or supplier quotation to be use as a resources

before prepared cost estimate. Another 30 percent (11 respondents) approved that the

resources should be referred in order to produced accuracy cost estimate.. From the

average index score which is 4.702, it can be said that the catalogues and supplier

quotation is “extremely used”.

Page 86: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

69

4.7.4.2 Based on Built Up Rate

From the table, it can be seen that more than half (59 percent) of the respondents

accepted that it is extremely used the built up rate in order to ensure that the cost

estimate accurate and profitable. 15 numbers of respondents (41 %) believed that it is

very used resources base on built up rate in order for preparing cost estimate. From the

average index score which is 4.594, it can be concluded that the feasibility study is

“extremely used” and should be taken into account in the referred resources for

preparing cost estimating.

4.7.4.3 Base on Past Project

A majority of the respondents classified this type past project resources

extremely used (63%) and 32 percent as very used resources in order for preparing cost

estimate. Only 5 percent of the respondents ranked the resources under moderately

used. It can be noted that this resources is “extremely used” based on the average index

result from the table which is 4.567. This may be due to the accuracy of preparing

building cost estimating.

4.7.4.4 Base on Past Experience

Twenty respondents (76%) indicate that it is extremely used for the contractor to

referred resources base on their experience before they produced their cost estimating.

Furthermore, 24 percent of the respondents realized that resources base on previous

experience is very used in order to prepared cost estimate. From the average index

score of 4.757, it can be seen that the past experiences resources is “extremely used”

and should be one of the contractors data information in preparing their cost estimating.

Page 87: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

70

4.703

4.595

4.568

4.757

4.081

2.297

1 1.5 2 2.5 3 3.5 4 4.5 5

Base on catalogues or supplierquotation

Base on build up rate

Based on past projects

Base on experiences

Base on elemental cost analysis

Base JKR's schedule of rates

Sour

ces

4.7.4.5 Base on Elemental Cost Analysis

Different levels of importance and frequent referred were established for

elemental cost analysis as shown in table 4.5, where the result for extremely used, is 21

percent, for very used 65 percent and 14 percent for moderate used. The average index

score for referred resources base on elemental cost analysis is 4.081 which is

categorized under “very used”.

4.7.4.6 Base JKR’s Schedule of Rates

A majority of the respondents classified this type JKR’s schedule of rates is

moderate used (46%) and 38 percent as less used resources in order for preparing cost

estimate. Only 16 percent of the respondents ranked the resources under not used . It

can be noted that this resources is “less used” based on the average index result from the

table which is 2.297.

Figure 4.4: Frequently used the Sources of Unit Rate

in order of Preparing Cost Estimate

Not Used Less Used Moderate Used Very Used Extremely Used

Page 88: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

71

Class of Contractors

No Option Class A Class B Class C Class D Total Percentage

1 Need any adjustment 19 3 8 5 35 952 No Need any adjustment 2 2 5

Total Respondent 19 3 8 7 37

4.8 Do your company do any adjustment before applying the sources of unit

rates as mentioned above?

The respondents were asked to identify, from the list given, any adjustment

before applying the resources of unit rates in order preparing cost estimate. Table 4.6

shows the option applying the resources of unit rates in order preparing cost estimate.

Table 4.6 : Option of any Adjustment or no need any Adjustment

in Applying Resources of Unit Rates

It was found that 95 percent of the respondents accepted, there are need any

adjustment before applying resources of unit rates in order preparing cost estimate,

Contractors Class A (19), Class B (3), Class C (8) and Class D (5) which contribute to

the total numbers of 37 respondents The number of contractors involved in this

questionnaire survey will provided a good result in terms of their knowledge and

experience which can contribute to this investigation. From the analysis shows only 5

percent or 2 out of total number of 37 respondents declared there are no need any

adjustment in applying resources of unit rate in order preparing cost estimate.

Page 89: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

72

Any adjustment before applying the sources of unit rates

95% ( 35 samples )

5% ( 2 samples )

Need any adjustment No Need any adjustment

Class of Contractors

Class A Class B ClassC Class D Total Percentage

Yes 19 3 8 7 37 100

No 0 0 0 0 0 0

Total 19 3 8 7 37

Figure 4.5 :Percentage of any Adjustment before

Applying Resources of Unit Rates

4.9 Section B :

Application of Computer in preparing Cost estimating.

4.9.1 Do your company use computer to prepare cost estimating?

The respondents were asked to identify, from the list given, did the contractors

company used computer in order preparing cost estimating. Table 4.7 shows

discretionary from the respondents. The ratings are as follows:

Table 4.7 : Computer used to Preparing cost estimating

Page 90: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

73

Class of Contractors

No Types of Sofware Class A % Class B % ClassC % Class D %

1 Microsoft Excel 19 100 3 100 8 100 7 1002 Lotus 123 0 0 0 0 0 0 0 03 Microsoft Word 5 26 1 33 3 38 2 29

The study found, as shown in the table 4.7, that overall of the respondents had

dealt with the computer facilities in order preparing cost estimating. From the table, it

can be noted that computer is very important to prepare cost estimating and other works

in construction industries.

4.9.2 What kind of standard software which your company used to prepare

estimating?

The respondents were asked to identify, from the list given, types of standard

software they used to prepare cost estimating. Table and figure 4.8 shows the types of

respondent against their discretionary standard software in preparing cost estimate.

Table 4.8 :Standard Software used to Prepare Cost Estimating

From table 4.8 above, most of the respondents used Microsoft Excel in order

preparing cost estimating which the respondents were Contractors Class A (19),

Contractors Class B (3), Contractors Class C (8) and Contractors Class D (7). A total of

26 percent of respondents Class A (5), 33 percent of respondents Class B (1), 38 percent

of respondent Class C (3) and 29 percent of respondent Class D (2) used Microsoft

Page 91: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

74

100

0

26

100

0

33

100

0

38

100

0

29

0

20

40

60

80

100

120

Standard Software

Perc

enta

ge

Class A 100 0 26

Class B 100 0 33

Class C 100 0 38

Class D 100 0 29

Microsoft Excel Lotus 123 Microsoft Word

Word in order preparing cost estimating. This shows that most of the respondents used

Microsoft Excel as a standard software in preparing building cost estimate.

Figure 4.6 : Percentage of Standard Software used by Contractors

in Preparing Cost Estimating.

4.9.3 Do your company use any special software that designed for estimating ?

The respondents were asked to identify, from the list given, any special software

used in their company in preparing cost estimating. Table and figure 4.9 shows the

types of respondent against their discretionary in using special software.

Page 92: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

75

Categories Contractors

No Item Class A Class B Class C Class D Total Percentage

1 Use special Software 2 0 0 0 2 5

2 Not used 17 3 8 7 35 95

5% ( 2 sample )

95% ( 35 samples )

Used special softw are Not Used

Table 4.9 : Special Software used in Preparing Cost Estimating

Table 4.9 shows that 5 percent of the respondents had used the special software

in preparing cost estimating. Only 2 out of 37 respondent ( Contractor Class A).used

special software in order preparing cost estimating. It was found that majority of the

respondents ( 95 percent ) no used any special software in preparation their cost

estimate.

Figure 4.7 : Percentage of used Special Software in Preparing Cost Estimating

Page 93: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

76

Categories Contractors

No Types of Software Class A Class B Class C Class D Total Percentage

1 MASTERBILL 2 0 0 0 2 1002 RIPAC 0 0 0 0 0 03 CATO-2000 0 0 0 0 0 04 BUILDSOFT 0 0 0 0 0 05 ICEPAC 0 0 0 0 0 0

Total Respondent 2 0 0 0 2

4.9.4 What kind of software which your company used ?

The respondents were asked to identify, from the list given, what kind of special

software they used in preparing cost estimating. Table 4.10 shows the types of

respondent against their discretionary in using special software.

Table 4.10 : Type of Special Software used in Preparing Cost Estimating

The study found, as shown in the table 4.10,. it represented 100 percent of the

total respondent (2) from Contractors Class A were use special software in preparing

their cost estimating. .From the table, it can be noted that 100 percent from the total

respondent were used special software acknowledged. Masterbill is the special software

they used in prepared cost estimating.

Page 94: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

77

4.9.5 What are the advantages or efficiencies of computer software used in your

company for preparing the estimating ?

The respondents were asked to rate the degree of advantages on the list of how

efficiencies the special software in preparing cost estimate.. In analyzing the data, the

following assumed values have been considered for responses on the degree of

efficiencies by the contractors: “not efficient” (1), “less efficient” (2), “moderate

efficient” (3), “highly efficient” (4), and “extremely efficient” (5). The list provided was

produced by the researcher from the case study carried out and was arranged and

classified according to the research objective. The results presented in Table 4.11 shows

a full list of efficiencies used special software in the questionnaire.

Table 4.11 : Efficiencies used Special Software in Preparing Cost Estimate

No

List of Sources

1

%

2

%

3

%

4

%

5

%

Average

Index

1

Complete work in short time

0

0

0

0

0

0

17

46

20

54

4.541

2

User friendly

0

0

0

0

0

0

16

43

21

57

4.568

3

Quality of work done

0

0

0

0

14

38

16

43

7

19

3.810

4

Efficiency

0

0

0

0

0

0

11

30

26

70

4.702

4.9.5.1 Complete work in shorter time

The study shows that 54 percent of the respondents ranked the complete work in

short time is extremely efficient. Another 46 percent were classified under very e

efficient. From the average index score which is 4.541, it can be concluded that the

Page 95: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

78

complete work in short time is “extremely efficient” and should be part of listed

advantages that should be in preparing cost estimating used computer software.

4.9.5.2 User friendly

A majority of the respondents classified this type of user friendly as extremely

efficient (57%) and 43 percent as very efficient in user friendly. It can be noted that this

advantages is “extremely efficient” based on the average index result from the table

which is 4.568. This may be due to the function and linkage of design computer

software that might affect the process in preparing cost estimating

4.9.5.3 Quality of work done

Seven respondents (19%) indicate that it is extremely efficient in quality of work

done in order using computer software for preparing cost estimating. Furthermore, 43

percent of the respondents realized that quality of work done is very efficient while the

contractors used computer software. 38 percent of the respondents felt that quality of

work done is moderate efficient. From the average index score of 3.810, it can be seen

that quality of work done is very efficient and should be one of the advantages using

computer software in preparing cost estimating.

Page 96: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

79

4.541

4.702

4.568

3.810

1 1.5 2 2.5 3 3.5 4 4.5 5

Complete work in short time

User friendly

Quality of work done

Efficiency

Adva

ntag

e

Rating value scale

4.9.5.4 Efficiency

This result reveals that 70 percent which 26 out of 37 respondents agreed that it

is extremely efficient that the efficiency using computer software is one of the

advantage in preparing cost estimating. Another 30 percent (11 respondents) approved

that using computer software is very efficient. From the average index score which is

4.702, it can be said that the efficiencies of using computer software is “extremely

efficient” and should be listed as one of the advantage using computer in preparing cost

estimating.

Figure 4.8 : Rating Scale Efficiencies used Special Software

in Preparing Cost Estimating

Not Efficient

Less Efficient

Moderate Efficient

Very Efficient

Extremely Efficient

Rating Scale

Page 97: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

80

Categories Contractors

No Task Class A Class B Class C Class D Total Percentage

1 Formula has be develop before key in the data 11 3 6 4 24 652 There is no standard format for costing 15 2 5 5 27 733 Lack of knowledge to use the computer software 10 1 6 5 22 594 Have to refer past document 6 2 3 4 15 415 More time to spent in checking 1 0 0 1 2 5

Total Respondent 19 3 8 7 37

4.10 Problem usually faced when using the computer software to prepare the

estimating.

The respondents were asked to identify, from the list given, what are the

problem usually faced when using the computer software in preparing cost estimating.

Table 4.12 shows the types of respondent against their problem usually faced when

using the computer software.

Table 4.12 : Problem usually faced when using Standard Software

Table 4.12 shows 73% from contractors where used computer for preparing

cost estimating certainty, there is no standard format for preparing cost estimating.

The contractors should be develop their own format before preparing estimate. From

the analysis 65% or 24 out of total 37 respondents decide formula has be develop before

preparing cost estimating. 59 percent decide, lack of knowledge to use the computer is a

weakness factor to be consider as a problem usually facing when used the standard

software for preparing cost estimating, 41 percent decide have to refer past document

and only 5% out of total 37 respondents decide more time to spent in checking as a

problem usually facing when using standard software in preparing cost estimating.

Page 98: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

81

65%73%

59%

41%

5%

01020304050607080

Percentage

1ProblemFormula has be develop before key in the data

There is no standard format for coasting

Lack of knowledge to use the computer software

Have to refer past document

More time to spent in checking

Figure 4.9 : Percentage of problem usually facing when using Standard Software in Preparing Cost Estimating.

4.11 Summary of Analysis and Results

Objective 1 : To study the various conventional methods of estimating from

contractors perspective.

From the study, it can be concluded that the approximate quantities is the

impressive method used by the contractors in preparing cost estimating. Besides that

unit method and element cost analysis as a partake of the method decide by the

contractors Class A, Class B, Class C and Class D who has registered with Pusat

Khidmat Kontraktor (PKK) and Construction Industrial Development Board (CIDB) in

Johor Bahru. Base on the analysis, researcher can be considering from that method for

develop building cost estimating database system .The data obtained from the

questionnaires with contractors involved in preparing cost estimating were analysed in

terms of frequency and average index.

Page 99: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

82

Data in section A showed that majority of the respondents used computer in

preparing cost estimating, 78 percent from total 37 respondents decide approximate

quantity as a method in preparing cost estimating. Data obtained in section B, showed

from the total 37 respondents using computer in preparing cost estimate only 2

contractors from Class A used Masterbill as a special software in order preparing cost

estimating. Microsoft Excel as a standard software used by the total 37 respondents in

preparing cost estimating and finally, no standard format costing is the highest problem

facing when using standard software in preparing cost estimating.

Objective 2 : To identify software use by contractor for cost estimating and the

problems.

The result shows 100% of the total 37 respondents used computer in preparing

cost estimating and Microsoft Excel as a standard software intentionally used by the

respondents. From the study only 2 respondents (Contractors Class A) used Masterbill

as a special software in order preparing cost estimating. Finally 73% or 27 out of total

37 respondents decide there is no standard format and 65 percent make a decision

formula has be develop before key in data as highest problem usually facing when using

standard software in preparing cost estimate..

Objective 3 : To develop an application which is capable of producing cost

estimating using Microsoft Office Access.

Cost Estimating Database has been develop used Microsoft Access 2003 and the

system is base on building work concept with approximate quantities and element cost

analysis as a basis for cost estimating. The system has been develop with the

minimum cost and accomplished to produce cost estimating easily and efficiently.

Page 100: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

83

CHAPTER 5

MODEL DEVELOPMENT METHODOLOGY

5.1 Introduction

This chapter evinces the methodology of developing a conceptual cost

estimating computer model. The system requirements are distinguished, base on the

literatures review of the chapter 2 and 3, along with the aspects to be considered in a

practical system. The process of introducing a valiable approach is considered in order

to enhance the benefits of the system under its classified requirements and development

constrain. Good information system depends on the integration between databases,

programming languages, and software engineering: its lifecycle incorporates the

interrelated technologies of conceptual modeling and database design (Loucopoulos,

1992). Figure 5.1 illustrates the system development process. The process consists of

two major phases: 1) the conceptual modeling phase , and 2) the Implementation phase.

The conceptual modeling phase will be discussed in the current chapter and

included problem investigation and user requirements, system architecture and

components. Thereafter, the database requirements, can be identified and the

conceptual design can be carried out then the conceptual scheme (Entity Relationship

diagram) can be derived. All the proposed database modules will be explained and

finally the proposed methodology will be established and shown through the current

practice (data flow).

Page 101: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

84

Figure 5.1 : System Development Process

5.2 System Requirements

The problem investigation and user requirements are rooted on the literature

review of chapter 2 and 3. The basis of an integrated methodology that fosters the

preparation of timely, dependable, and efficient conceptual cost estimate incorporates

Conceptual Modeling

Problem Investigation

Users Requirements

Database Requirements

Conceptual Design

Conceptual Schema

Logical design

Data Model Mapping

Implementation Data Model

PHYSICAL DESIGN

PHYSICAL SCHEMA

BDMS Independent

BDMS Specific

Page 102: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

85

the importance of having data available when needed and a computer tool use for

generating the estimate. To this end, a list of a specifications and basic requirements

that was followed in the developing the proposed estimate preparation system is shown

in Table 4.1. Besides such requirements, the system would be designed to have the

following characteristics:

SPECIFICATIONS

1. Designing and implementing database for preliminary estimate.

2. Utilizing cost of previously projects as handy historical data for

preliminary estimate.

3. Employing the Masterformat division for preliminary estimate as WBS

in metric units.

4. Flexibility of updating the built in costs when deeded.

5. Generating various reports that can be used for bid preparation and

summary cost.

6. Direct linkages between the generated items take off list and summary

cost.

Information-intensive; incorporate different database to store, process,

and employ available data in order to improve the practically of

preparing a cost estimate.

Efficient; user friendly and fast processing

Flexible; previously estimated projects can be added to built the

historical data, costs and items can be edited and modified easily.

Modular; allows future expansions and enhancements.

Practical; includes fast calculations process by applying available tools

( expressions and structured query language (SQL).

Page 103: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

86

5.3 System Components and Architecture

The developed system consists of components designed in preliminary estimate

module. Figure 5.2 illustrates the system components used in the model methodology

development. The function performed within each of the systems components.

Figure 5.2 : System Components

DATABASE

Page 104: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

87

The preliminary estimates module that integrates the preliminary database base

on Masterformat provides the user with the option of using metric cost data to calculate

the direct and indirect cost of chosen items. The user cal also use own cost data in

calculating the direct and indirect costs. The selection methodology evaluate four

selection criteria:

1. Work Break Down Structure (WBS)

2. Data sources ; own cost data

3. Cost adjustment

4. Unit in metric

The System Architecture is illustrated in Figure 5.3. The process stats with

entering the project information. Selecting the work breakdown, entering take off form

for generated the quantity for estimate is chosen.

Page 105: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

Figure 5.3 : System Architecture

86

System Database

Preliminary Own Cost

Item Direct Material Installation Labor rate

Total Cost Calculation Each Division Per Unit Area

Whole Project

Cost Summary Report Tabulated Detail

Data Analysis

OUTPUT

WBS Masterformat

Data Source Own Data

Unit Metric

Items Take Off List

CRETERIA

Preliminary Module Project

Information. Cost Data . Own

Unit : Metric

INPUT REQUIREMENTS

Project Cost Estimates

88

Page 106: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

5.4 Database Conceptual Design

The conceptual cost estimate database has been created by slaving computers to

minimize the required time in preparing an estimate, the ability to call up and modify

costs data when needed for preliminary estimates, and to provide a professional output

reports for bidding purposes. Utilizing computers has myriad benefits, perhaps the

foremost of them is employing their immense capacity to store huge amount of data and

the capability to retrieve it fast. The foregoing paragraphs have classified the system or

database requirements thereafter the conceptual design can be established by identifying

the components of the conceptual schema. The conceptual schema concentrates on

describing the database entities. Their attributes and relationships. The graphical

representation of the conceptual schema is accomplished by using an approach known

as Entity-Relationship diagram (ER-diagram). The ER approach uses rectangles to

specify entities, diamond-shaped to represent the available relationship between two or

more entities and oval-shaped to represent the attributes. Figure 5.4 shows the ER-

diagram used to conceptually design the model.

Entities are the primary data objects about information is to be collected, and

represent the cost estimate concepts that are stored in the database. The entity name is

written inside the rectangles and the proposed database comprises 5 entities (Project,

Division, Element, Cost estimate, Cost Source).

89

Page 107: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

Figure 5.4 : Database Entity Relationship Diagram (ER-Diagram)

Address

Area

Address

Project

Description

Unit

Number

Cost/unit area

Total Cost

Estimator

Date

Name

Element

% of Total Cost Name

Cost

Number Uses

M

N

Cost Estimate

Has

Uses

M

N

M

N

Name

Uses Cost Source

Name

M

1

Division

Cost

% of total Cost

Number

Uses

M

N

Item Unit

QuantityDescription

Total Cost Unit Cost

Uses

M

1

90

Page 108: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

9

- Relationships represent the associations among two or more entities. The

different types of connectivity between entities are One –to-One (1:1), One-

to-Many (1:M), and many-to-Many (M:N). In the proposed database one

type of connectivity has been used which is Many-to-Many (Figure 4.4)

- Attributes are the entity characteristics that provide descriptive detail about

that entity. Attributes opposite entities by having values, they are in two

types either identifiers or descriptors. An identifier (or key) uniquely

determines an instance of an entity and underline in the ER-diagram (Figure

5.4, e.g Number).

5.5 The Conceptual Estimate Methodology

Base on the previous discussion, the proposed step-by-step methodology that

effectively incorporate the cost estimate, the function fulfilled and the necessary

input/output data links is outlined by the data flow diagram as shown in Figure 5.5.

This diagram simplifies the implementation and the development of the model. From

the main module, the user will select the module and accordingly a connection with its

module will be created and its integrated database will be opened. Thus, the user will

start the process of estimating costs of the constructing a project.

91

Page 109: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

92

Start Menu

Project Brief

Project Cost Information

Main Element Building

Work

Sub Element Building

Work

Standard Form for

Estimating Form Built

Up rate

Summary Cost of Sub

Element

Total Cost of Main

Element

Report Data in Form

Estimating

Preview Report Brief

Specification

Report Cost of Project

Stop

No

Yes

Figure 5.5 :Methodology Data Flow (Current Practice)

Page 110: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

93

5.6 Conclusion

This chapter proposed a methodology for cost estimating model, using available

tools (algorithms and database management system) that can avail cost engineering and

estimator s to prepare preliminary cost estimates. A procedure for developing the

methodology is applied based on a group of identified system requirements. The

preliminary estimate based on historical data of previous executed projects and the

module utilizes built in cost data or user own cost data to produce a quickly preliminary

estimate. The proposed system, “SAVER” eases the preparation of a conceptual cost

estimate in a favorable technique, efficient and accurate. This chapter stressed the

conceptual modeling phase of the system development, founding a structured

methodology for conceptually estimating the costs of constructing building works. The

model implementation phase is presented in chapter 6

Page 111: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

94

CHAPTER 6

MODEL IMPLEMENTATION PROCESS

6.1 Introduction

Former chapter listed the phases of developing the system’s methodology, dealt

specifically with the conceptual phase and derived the conceptual schema. This chapter

described phases two of the development process that is the model implementation. It

exhibits the process practiced in developing the computer model that comprises the

system database for preliminary estimate module.

6.2 Database Implementation

The development stats by mapping the data model’s components, which are

entities, attributes and relationships within a Database management System (DBMS).

This is achieved by using Microsoft Access 2003 through design Preliminary Database.

The database development is conceptually pictured in the ER-diagram as show in

Figure 5.4 of chapter 5. The design of each database is considered separately in the

succeeding paragraphs.

Page 112: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

95

6.3 Preliminary Database

The components of this database are incorporated from the ER-diagram as

follows : Project, Cost Source, Division and Cost Estimate. Each entity is used with

partially of fully of its associated attributes. To design this database three major steps

are performed sequentially. The data source bused is based on Metric for coasting that

uses the Masterformat to breakdown the project structure with some modifications

made for design purposes as follows :

Step One

Having settled the data pertinent to this database, each division and its

associated sub-divisions and items have to be identified through a unique ID number.

The importance of identifying each line items data by a unique number so that the

database software (Microsoft Access 2003) accepts it is necessary because it speeds the

process of retrieving desired items and eliminates duplications.

Step Two

Having the numbering system identified each division and associated items are

given a unique number and then the operation of building the tables can be commences.

Normally a relation database is composed of a collection of tables that accommodate

grouped data. Every division and its interrelated items are entered into two different

tables. Entering data is the most time consuming process of the system development, as

shown in Figure 6.1 and Figure 6.2 below :

Page 113: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

96

Figure 6.1 : Sample Table 1 of Each Division Data

Figure 6.2 :Sample Table 2 of Each Division Data

Page 114: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

97

Afterward, the Item ID links these table one-to-one relationship because each

division line item is unique and cannot be duplicate. The related tables are named after

the name of each division with an abbreviation showing the unit used.

Figure 6.3 :Sample Table 3 of Item Taking Off List

Additionally, there are few minor tables for the user to make use of. For

instance, entering required data (e.g size of those element, no of element, length, width

and key in own rate data. Figure 6.4 shows the design of a form.

Page 115: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

98

Figure6.4 : Screen Snapshot of the form from Table Database

Figure 6.5 : Snapshot of the Database tables and their Relationships

Page 116: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

99

Because tables are rigid objects and do not permit any data manipulation,

queries are utilized due to their flexibility and ability to do that job. Expressions are

used in all the queries in order to carry out all the required calculations. All the

employed queries are base on at least one or two related tables, and each one of them is

specified to one division accordance to the data source.

Step Three

Once all the appropriate data of this database are precisely listed into sets of tables and

queries, the database interface is carried out. The goal of designing this database is to

deliver a tool that comprises clearness, simplicity and user friendly. Thus, this aim is

achieved through using set of series of forms. Each series represents the Masterformat

divisions in a specific unit. This form is linked to a query called “Qttl_SumAPRON,”

which provides the form with the required data, as well it stores all the calculation for

this database. Similarly, all the other division for the selected are similar forms. This

process has been repeated for all the other division.

6.4 Main Module

Following the design of the database, it is necessary to design a simple procedure to

be the gate for the user to access the database under choice. In other words, from that

form the user assign the type of division he or she wants to use. Consequently, a main

form, name “Cost Estimating System” is design in a way that links the database and by

simple clicks the desired one opens. The first form that opens in this procedure is the

introduction screen as shown in Figure 6.6. At the bottom of this form there are two

Page 117: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

100

command buttons, one to exit the model and the second to enter and mentioned forms

respectively.

Figure 6.6 :Snapshot of the System Main Menu

6.5 Conclusion

The developed computer system Cost Estimating System (COES) that

conceptually estimates the costs of construction for building works. Base on the model

operation, the system has several useful features as follows :

Page 118: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

101

The system is designed and structured in a manner that allows future expansion

and enhancements.

User friendly, easy to use, efficient, and fast calculations.

Ability to easy edit, add and modify the available data of all database.

Professional output reports that can be used for bidding purposes, and the ability

to graphically visualize.

Exporting the generated estimates to a spreadsheet and a word processing

document .and as a result, Cost estimating System (COES) was created.

Generally, COES can facilitate the user to do cost estimating, built up rate,

report of total construction cost and preview report of brief specification and

finally formatting the cost estimate to a proper format.

Page 119: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

102

CHAPTER 7

SYSTEM VALIDATION

7.1 Introduction

Validation is the part of evaluation that deals with the performance of the system

(for example, how it compares to the other software). Simply stated, validation refers to

building the “right” system, which is, substantiating that the system performs with an

acceptable level of accuracy.

7.2 Prototype

Based on the model that has been developed, a prototype has been designed and

produced to help the user to obtain cost estimate before the contractors submit their

tender bid. In this study, Microsoft Access 2003 has been selected as a tool to develop

the prototype. This system has various functions and characteristics which is suitable to

develop the prototype based on the scope of the study which has been specified.

The objective of developing the prototype is to help to speed the process of

preparing cost estimating which normally carried out manually and take a longer time.

This process of preparing cost estimate will be repeated until the contractors is satisfied

with the estimate figure.

Page 120: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

103

This study will try to develop a system to prepare cost estimating through

prototype, which has been developed. The function of the system produced is in line

with the objective and purpose of this study.

7.3 Use Of The Prototype

The prototype consists few session which need to be selected and correct button

to be chosen till end of the window. The final window will show the report of the cost

estimating. If the user does not want to continue till end of the window, the BACK

button can be used to go back and leave the window.

To use this prototype, the step is to open COES Software. The following screen

will appear that allows the user to use COES. If user do not wish to continue, click the

EXIT button. Click the CONTINUE button to start the estimating work.

Figure 7.1 : Snapshot of the Starting Menu

Page 121: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

104

The following interface will appear. In this interface, The user has to key in the

information present in the form such as project name, location, client, floor area, name

of estimator, check by and date of estimate. Click button ENTER to open form Project

Cost Information.

Figure 7.2. : Snapshot of the Project Brief

In this interface, the user can choose the main element of building work in

general for preparing cost estimating The user only has to click ENTER button to

move the next selected screen or can choose the BACK button to go back to the

previous screen.

Page 122: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

105

Click ENTER button to open interface list of

elements under building work

Click BACK button to go back previous

interface

Click ENTER button to view report of

summary Project Cost

Figure 7.3 : Snapshot of Project Cost Information

Figure 7.4 and 7.5 illustrate respectively the events when the user chooses to

preview superstructure work, the next interface opens a form listed activities under

superstructure work.

Page 123: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

106

Click ENTER button to view activities under Superstructure

Click ENTER button to view form

estimating for staircase

Figure 7.4 : Snapshot of Activities under Building Work

Figure 7.5 : Snapshot of Activities under Superstructure

Figure 7.6 display the main activity in preparing cost estimating according to the

approximate quantities method. The user has to key in all the dimension, description

Page 124: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

107

and other information according to the drawing in the form. For the example, in the

concrete staircase work, the user must key in all the information such as estimating for

formwork, reinforcement and reinforce concrete. For the other application, the user

only has to click the button provide in the form. The same process has be carried out

for all the other elements.

Figure 7.6 : Snapshot of Form for Cost Estimating

Page 125: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

108

Information about the specification

Location for building

Auto number

Works item for concrete staircase

Number base on total data was key in

Button for delete data in row

Button for save data in row

Information for high tensile and mild steel

conversion from meter length to kilogram

Figure 7.7: Snapshot of Functional Buttons

Figure 7.8: Snapshot of High-tensile and Mild-steel Conversion

Page 126: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

109

Save all record for all data

Add new record

View summary cost of concrete staircase

View total cost staircase

Open form Built Up rate

Delete all record

Open form element landing

slab

Open form element

landing beam

Open form element steps

Open form Hand railing

Close / exit the form

Figure 7.9 : Snapshot Functional Buttons of Estimating Form

Figure 7.10 : Snapshot of Summary Cost for Concreting Staircase

Page 127: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

110

Figure 7.11 : Snapshot of Summary Total Cost for Staircase

Figure 7.8 displays the summary total cost for activities staircase and cost per floor area.

If the VIEW button is entered, the screen summary cost of each element was entered

will be prompted similar to Figure 7.7. Click button BACK to go back to the cost

estimating screen.

From the estimating form (Figure 7.6), when the user hitting view summary button,

we are transferred to the “summary cost for concreting staircase” as shown in Figure

7.7 and illustrates the total cost for form work, reinforcement and reinforced

concrete. If the VIEW TOTAL COST FOR STAIRCASE button is entered, the total

cost for staircase will be prompted. Click the BACK button to return to the cost

estimating form.

Page 128: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

111

Figure 7.12 : Snapshot of Data Record In this screen, a report consisting the data of the estimating for form work

landing will be shown.

Page 129: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

112

Figure 7.13 : Sample Snapshot of Report Construction Cost In this screen, a last, a report consisting the detail of the building cost estimating

will be shown.

Page 130: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

113

Figure 7.14 : Sample Snapshot of Report Brief Specification

Page 131: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

114

CHAPTER 8

CONCLUSION AND RECOMMENDATION

8.1 Conclusion

After extensive research on the specific software for producing cost estimating

and analysed data from respondents, finally Cost Estimating System (COES) was

being develop. It is Microsoft Access 2003 application designed specifically for doing

building cost estimating. Cost Estimating System have the ability to automatically

produce cost estimating from the calculation form has be develop according to

approximate quantities and element cost analysis method. Moreover, user-friendly

interfaces features such as selecting built up rate development and producing summary

of cost estimating making this system easy to use application. Nevertheless, there are

still some features which are lacking such as formatting errors. Actually, the problem

can be solve by either reprogramming or using a patch file. As a final conclusion, this

research has achieved its objective of developing an application which is capable of

producing building cost estimating using Microsoft Office Suite.

8.2 Research Contribution

The contribution of this research reside in the following :

A unique cost estimate computer system has been developed that is

particular for the construction industry.

Page 132: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

115

An operational database system has been designed and implemented using

windows environment and utilizing Microsoft Access 2003applications.

This advances the field of MIS (Management Information System)

applications in the construction industry, which is known to lack behind

other industries in this area. This will aid practitioners in the construction

industry to perform conceptual estimates within the short time available to

study a project.

The developed system is intended to assist owners, contractors, and estimators

in preparing fast, efficient, and reliable cost estimates. It provides the user with the

option of selecting the of division to use. It reduces the time required to build costs list

for the project activities so that this reduction can be beneficial for the quantity take off

time process. It provides professional output reports that can be used for bidding

purposes. The system includes a structured database, which can be extended, enhanced

and modified depending on the user needs.

8.3 Recommendation For Future Research

The research has generated a milestone result for automatically producing

building cost estimating from Microsoft Access 2003 Despite that this research

introduces a functional system as a tool for contractors and estimators to use in

preparing cost estimates for the construction industry, it is a platform that can be

potentially enhanced by future works. These may include :

Detailed cost database models so that the user will be able to prepare all

types of estimates in accordance with the different phases of the project.

Automatic integration between the detailed estimate and scheduling tools

allowing the user to schedule the activities according to the crew

productivity after generating the estimate.

Page 133: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

116

Integration between AutoCAD and the detailed cost estimate database

model to enable the user to automate the quantity off process directly

from the drawings while preparing the estimate.

Using neural networks or regressions to forecast the cost items of the

preliminary cost estimate database model.

Page 134: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

117

REFERENCE

Abd. Majid, Muhd Zaimi (1997). “Non-Excusable Delays in Constructions.”

Loughborough University of Technology, UK: PhD Thesis.

Adrian. J. “Construction Estimating an Accounting and Productivity Approach’:, 2nd

edition, 1993 , Stipes Publishing Company.

Asworth, Allan, “Cost Studies Of Building”, Longman Group UK Limited, 1988,

p60,85.

Bryan, S.M. “Assembly Pricing in Construction Cost Estimating.” Cost Engineering

Journal, Vol.33, No. 8, August 1991.

Carr, R.I, “Cost Estimating Principle,” Construction Engineering and management

Journal, Vol. 115, No 4, December 1989.

Charoenngam, C., Yeh, C.-Y. (1999) "Model for Estimation of Time and Cost for

Tunnel Projects." Int. J. Project Management 17: 29-37

Che Wan Putra, CWF, “Object Definition and Data Exchange In An Integrated

Construction Environment”, Ph.D Thesis, Department Od Surveying, University Of

Salford, U.K, March,1996.

Chong W.P. (2001). “Mereka Bentuk Perisian Kos Rendah (M.S. Excel) Untuk

Pengukuran Kuantiti.” University Technology of Malaysia : Undergraduate Thesis.

Page 135: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

118

Chong Wan Siang (2004). “ Developing Computer Application For Quantity Surveying

Services Using Microsoft Office Application.” Research management Centre,

Universiti teknologi Malaysia.

Coolier, Keith, “ Fundamentals of Construction Estimating and Cost Accounting”,

Englewood Cliffs, N J: Practice Hall, 1974, p12.

CSSP (2002). “CSSP Company Overview.” : Trade Brochuer.

Dagistino, Frank R, “Estimating in Building Construction”, 2nd Edition, Reston, V.A.

Reston, 1978. p1.

David S.M.Hall, “Elements Of estimating,” B.T. batsford Ltd, London, 1972.

Ducan, W.R,. “ A Guide to the Project Management Body of Knowledge,” 1996,

Library of Cataloging-in-Publication Data.

Dysert, L.R. “Developing a Parametric Model for Estimating Process Control Cost,”

Transaction of the AACE 43rd Annual Meeting, Denver Colorado, U.S.A,. June

1999.

Dyset, L R, and Elliott, B.G, “The Organization of an Estimating Department,”

Transaction of the AACE 43rd Annual Meeting, Denver, Colorado, U.S.A, June

1999, pp EST.06.1-EST.06.6.

Feature article, “Estimating Software Comes of Age,” Cost Engineering Journal,

February 1999, pp.16.

Feldman, W. and Feldman, P., “Construction and Computers,” 1996, McGraw-Hill.

Page 136: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

119

Fletcher, William R. (1996) “Utility Cost estimating,” Transactions of AACE

International 1.1.

Halbrok, M (2004). “Spreadsheet Microsoft Axcel 2003” PC Plus Vol .2 N0.1. 67.

Halpin, D.W. ”Financial & Cost Concepts for Construction Management,” 1985, John

Wiley & Sons.

Halpin, Daniel W, “Construction Management” New York: John Wiley 1980,p41.

Harris, Frank, “Modern Construction Management”, 2nd Edition, Granade Publishing

Limited, 1983.

Hegazy, T and Ayed, A, “Neutral Network Model For Parametric Cost Estimation of

Highway Projects,” Journal of Construction Engineering and Management, ASCE,

vol 124, May/June 1998, pp, 210-218.

Hendrickson, C, “Project Management for Construction,” 1998, Prentice Hall, Inc.

Hicks, J, “Heavy Construction Estimates and Without Computers,” Journal of

Construction Engineering and Management, ASCE, Vol, 118, No, 3, September

1992, pp 545-560.

Jurkiewicz, W.J., “Theory and Practice With Dual Entry in Project Cost Accounting

and Control,” Transaction of the AACE 43rd Annual Meeting, Denver, Colorado,

U.S.A., June 1999, pp. CSC.05.01-CSC.05.8.

Kamaruddin Md Ali, (2000) “Pre-estimate Of School Building Using Knowledge Base

System.” Universiti Teknologi Malaysia, Thesis Master of Science in Construction

Management..

Kelly, G (1990) “Computer Update.” Chartered Quantity Surveyor.12.

Page 137: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

120

Loucopolos, P., Zicari R. “Conceptual Modeling, Database, and CASE and Integrated

View of Information Systems Development,” 1992, John Wilev and Sons, Inc.

Lowe, David, “Experiental Learning in Cost estimating, Construction management And

Economics, 1994, 12, p423-431.

MacVaffer, Ronald and Balwin, Andrew (1995). “Estimating for Construction”

dlm.Smith, Nigel, J. “Project Cost estimating,” London: Thomas Telford Ltd. p32-

50.

Miller, P.F ,. “Project Cost databanks,” Butterworths & Co.Ltd.

Mohd Hisham Ariffin (2002), “Penggunaan Komputer di Firma-Firma Pembinaan

Kelas G-7 C.I.D.B Di Malaysia.” The Malaysian Surveyor. 37.2.32-38.

Nisbet, James, “Estimating and Cost Control”, London Batsford, 1961.

Rederick Allen Robinson (2000). “A Construction Management Information System To

Assist Contractor Prequalification.” Master Of Science Building Construction

Management, Michigan Stste University.

Reston, 1978, p1 Halpin, Daniel W, “Construction Management”, 2nd Edition,

Graanada Publishing Limited, 1983.

Sanders, S,R, Maxwell R.R and Glagola, C.R “Preliminary Estimating Models for

Infrastructure Projects, “ Cost Engineering Journal, Vol.34, No.8, August 1992, pp

7-13.

Schuette, Stephen D. & Liska W. (1994). “Building Construction estimating,” United

States of America: MacGraw Hill Inc. p1-115.

Page 138: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI

121

Scott, T (1978). “Computerised Taking-Off.” Chartered Quantity Surveyor.15.

Seeley, Ivor H. (1996). “Building Economic” 4th Ed. London Macmillan Press Ltd 154-

173.

Sigurdsen, A, “CERA: An Integrated Cost Estimating Program,” Cost Engineering

Journal,Vol 34, No 6, June 1992, pp.25-30.

Steward, R.D,. “Cost Estimating,” 1982, John Wiley and Sons.

Sutherland, J, “Project Cost Estimating for major Renovation Projects,” Transaction of

the AACE 43rd Annual Meeting, June 1999, pp EST 05.1-EST.05.7

Uppal, K.B, “Estimating? Past, Present and 21st Century,” Transaction of the AACE

41st Annual Meeting, July 1997, pp.Est.01.1-EST 01.4

Van Kempen, jay R. (1983), “Construction Cost Estimating” Reston, Virgina: reston

Publishing Company, Inc p1-4.

Westney, R.E,. “The engineer’s Cost Handbook Tools for managing Project Cost,”

1997, Marcel Dekker, Inc.

Wood, E.G,. “Costing matters for Manager,” 1974, Business Books London.

Page 139: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI
Page 140: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI
Page 141: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI
Page 142: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI
Page 143: ii COMPUTERISED BUILDING COST ESTIMATING SYSTEM MOFTI