127
II~l ELECTRIC POWER RESEARCH INSTITUTE 2011-149 BWR Vessel & Internals Project (BWRVIP) August 22, 2011 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 Attention: Andy Hon Subject: Project No. 704 - BWR Vessel and Internals Inspection Summaries for Fall 2010 Outages Enclosed are five (5) copies of the document entitled "BWR Vessel and Internals Project, Vessel Internals Inspection Summaries for Fall 2010 Outages, August 2011." The information provided in the enclosed document identifies the BWR internal components inspected and generally includes the date or frequency of inspection, the inspection method used and a summary of results including repair or replacement activities. The enclosed document is being provided to the NRC for information only. The information contained in the enclosed document was developed by the individual utilities and has been compiled into the enclosed document by the BWRVIP. The BWRVIP plans to continue to gather such information and to provide periodic updates such as in the enclosed document. Representatives of the BWRVIP would be pleased to meet with the NRC staff to discuss any comments or questions related to the enclosed document. If you have any questions on the enclosed document or the general subject of inspection results, please call Chuck Wirtz, BWRVIP Integration Committee Technical Chairman, FirstEnergy, at 440.280.7665. Sincerely, Dave Czufin Exelon Chairman, BWR Vessel and Internals Project Together... Shaping the Future of Electricity •------•4Li PALO ALTO OFFICE 3420 Hillview Avenue, Palo Alto, CA 94304-1395 USA 650.855.2000 e Customer Service 800.313.3774 A www.epri.com

II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

II~l ELECTRIC POWERRESEARCH INSTITUTE

2011-149 BWR Vessel & Internals Project (BWRVIP)

August 22, 2011

Document Control DeskU. S. Nuclear Regulatory Commission11555 Rockville PikeRockville, MD 20852

Attention: Andy Hon

Subject: Project No. 704 - BWR Vessel and Internals Inspection Summaries for Fall 2010Outages

Enclosed are five (5) copies of the document entitled "BWR Vessel and Internals Project, VesselInternals Inspection Summaries for Fall 2010 Outages, August 2011."

The information provided in the enclosed document identifies the BWR internal componentsinspected and generally includes the date or frequency of inspection, the inspection method usedand a summary of results including repair or replacement activities. The enclosed document isbeing provided to the NRC for information only.

The information contained in the enclosed document was developed by the individual utilitiesand has been compiled into the enclosed document by the BWRVIP. The BWRVIP plans tocontinue to gather such information and to provide periodic updates such as in the encloseddocument.

Representatives of the BWRVIP would be pleased to meet with the NRC staff to discuss anycomments or questions related to the enclosed document. If you have any questions on theenclosed document or the general subject of inspection results, please call Chuck Wirtz,BWRVIP Integration Committee Technical Chairman, FirstEnergy, at 440.280.7665.

Sincerely,

Dave CzufinExelonChairman, BWR Vessel and Internals Project

Together... Shaping the Future of Electricity •------•4Li

PALO ALTO OFFICE

3420 Hillview Avenue, Palo Alto, CA 94304-1395 USA • 650.855.2000 e Customer Service 800.313.3774 A www.epri.com

Page 2: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

I I

BWR Vessel and Internals Project

Vessel Internals Inspection Summariesfor Fall 2010 Outages

August 2011

Page 3: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Table of Contents

Plant Page

1. Browns Ferry Nuclear Plant: Unit 1 32. Dresden 3 143. Duane Arnold Energy Center 304. Fenni 2 415. James A. FitzPatrick Nuclear Power Plant 666. Hope Creek 887. Oyster Creek Generating Station 988. Peach Bottom Atomic Power Station, Unit 2 113

Page 4: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Browns Ferry Nuclear Plant: Unit 1

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 2005 UT Baseline: UT (two-sided) examination ofHI, H2, H3, H4, H5, H6, H7 performedper BWRVIP-76. Results as follows:

Weld #/Scan Side/% Coverage/% Flawed

HI / Upper / 83.0% /0.0%HI /Lower/82.1%/2.1%H2 / Upper 81.8% / 0.4%H2 / Lower / 88.7% / 0.0%H3 / Upper / 88.7% / 0.0%H3 /Lower/ 79.2% / 5.1%H4 / Upper/ 90.0% / 20.1%H4 / Lower / 89.6% / 2.6%H5/Upper/91.3%/ 1.2%H5 /Lower/91.3%/0.0%H6 / Upper 91.9% / 0.0%H6 / Lower 91.9% / 11.2%H7 /Upper /91.4%/ 12.0%H7 / Lower / 78.0% / 0.0%

Barring license renewal impacts, allseven horizontal welds will not bereinspected for ten (10) years.

Shroud Support 2005 VT-1, Access Hole Cover Welds at 00 andVT-3 180': Replacement required prior to Unit

1 Restart - Both access hole coversreplaced with bolted repair design perDCN 51193. VT-I visual baseline examperformed to inspect nut to retainer tackwelds only. VT-3 visual baseline examperformed to document the as-leftcondition of the AHCs. No relevantindications on either cover.

2005 EVT-1 Baseline inspection per BWRVIP-104 ofthe H8 weld from the upper side withgreater than 10% coverage between JetPumps I to 20 and 10 to 11. The lowerside was performed during the removal

3

Page 5: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2005

2005

2008

EVT- 1, UT

VT-3

VT-3

of the Access Hole Cover modificationwith approximately 10% total coveragearound the AHC areas at 0 & 180degrees. No relevant indications.

Baseline inspection per BWRVIP- 104 ofthe H9 weld from the upper side withgreater than 10% coverage between JetPumps I to 20 and 10 to 11. The lowerside was performed during the removalof the Access Hole Cover modificationwith approximately 10% total coveragearound the AHC areas at 0 & 180degrees. Also performed UT from theoutside surface of the RPV obtained fromaccess of the N I A and N IB(Recirculation outlet nozzles) windows.Achieved coverage was calculated to be19%. No relevant indications.

Baseline inspection per BWRVIP- 104 ofthe H 10 and H 12 welds at 0 and 180degrees. These inspections wereperformed through the access hole coveropenings during the repair. No relevantindications.

VT-3 visual inspection of replacementaccess hole covers at 0 and 180 degreesto confirm that the AHC is in place andthe hardware has not changedappreciably from the installed condition.No relevant indications were observed.

Core Spray Piping 2005

2001

EVT- 1

UT

Baseline inspection per BWRVIP- 18:EVT-1 visual examinations (T-Boxwelds @ 120 (P1, AP3, BP3) and 240degrees (P1, DP3), Piping Bracket (PB)welds @ 15, 110, 130, 165, 195, 230,250, and 345 degrees). EVT-1 visualexaminations of elbow and sleeve weldsfor Downcomers A through D (P4d, P8a,P8b). No relevant indications.

Baseline inspection per BWRVIP- 18:UT of T-Box welds @ 120 (P2) and 240degrees (P2, CP3). UT of elbow and

4

Page 6: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2008

2010

EVT-1,VT-3

UT, EVT- I

sleeve welds for Downcomers A throughD (P4a, P4b, P4c, P5, P6, and P7). Norelevant indications.

Reinspection per BWRVIP- 18-A:EVT- 1 visual inspections of T-BoxWelds (P 1 (1200 & 240'), AP3, BP3,DP3) and Downcomer Welds (AP4d, A-D8a, A-D8b); no relevant indicationswere observed. VT-3 visual inspectionof Core Spray Sparger S-1/S-2 RepairClamp; no evidence of clamp assemblylooseness or degradation detected.

Reinspection per BWRVIP- 18, Rev. 1:EVT- 1 visual inspections (T-Box welds@120 (P1, P2, AP3, BP3) and 240 (P1,P2, CP3, DP3); no relevant indicationswere observed. UT of elbow and sleevewelds (P4a, P4b, P4c, P4d, P5, P6, P7,P8a, & P8b) performed for DowncomersA through D. Two indications (1.04"and 2.20") observed on weld P4a on ADowncomer on the pipe side of the weld.Indications evaluated in accordance withthe Core Spray Flaw EvaluationHandbook. Evaluation showed piping isacceptable as-is for one cycle. Pipingwill be reinspected during U 1 R9 (2012).Supplemental EVT-1 visual inspectionperfomled for P4a, P4b, P4c, P4d, P8a,and P8b; no relevant indications noted.

-I- I I

Core Spray Sparger 2005

2005

EVT-1

VT-1

Baseline inspection per BWRVIP- 18:EVT- 1 visual examinations of spargerwelds (S1, S2, S4). BS2-R weld @ 9degrees (Sparger to T-Box Weld, R side(Lower Sparger) recorded a crackadjacent to the weld and was structurallyreplaced by weld repair clamp per DCN51193. AS2-R weld @ 354 degrees(Sparger to T-Box Weld, R side (UpperSparger) recorded a pin hole adjacent tothe weld and evaluated as "accept as is".Otherwise, no relevant indications.

Baseline inspection per BWRVIP- 18:

5

Page 7: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2010 EVT- 1,VT-i

VT- I visual examinations of spargerwelds (S3a, S3b, S3c, Sparger Bracket(SB) welds @ 7, 45, 88, 93, 135, 172,187, 225, 267, 273, 315, and 352degrees). No relevant indications.

Reinspection per BWRVIP- 18, Rev. 1:EVT- 1 visual examinations of Spargerwelds (S 1, S2, and S4) and VT-1 visualexaminations of Sparger welds (S3a,S3b, and S3c) and Sparger Bracket (SB)welds @ 7, 45, 88, 93, 135, 172, 187,225, 267, 273, 315, and 352 degrees); norelevant indications observed.

Top Guide (Rim, etc.) 12005

2005

2005

2010

VT-3

EVT-1

EVT- 1,VT-I

EVT- 1,VT-I

Baseline inspection (NON-BWRVIP):VT-3 visual examinations of Locations 4(Grid Beam to Rim Top / Bottom CoverPlate Pins), 6 (Fuel Guard Weld andBolting), 12 (Rim & Cover PlateFabrication Weld), and 13 (Eye BoltBoss). 1 area recorded as a condition onthe plate (Location 12), evaluated as"accept as is". Otherwise, no relevantindications.

Baseline inspection (NON-BWRVIP):EVT-1 visual examinations of Locations1 (Grid Beam & Beam to Beam CreviceSlot) and 10 (Rim Pins). 3 areasrecorded as not acceptable (Location 1),evaluated as "accept as is". Otherwise,no relevant indications.

Baseline inspection per BWRVIP-26:Inspected Rim Welds (Location 11)(EVT-1) and Aligner Pins (Locations2/3) (VT-1) at all locations. No relevantindications.

Reinspection per BWRVIP-26-A:Locations 2 and 3 (VT-1) and LocationII (EVT-1) inspected with no relevantindications.

Core Plate (Rim, etc.) 2005 EVT-1, Baseline inspection per BWRVIP-25:VT-3 All thirty-four (34) holddown bolts

6

Page 8: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

(Location 10) were EVT- 1 inspectedfrom the top side, and seventeen (17)holddown bolts (50%) were inspectedfrom the bottom side with no reportableindications. All one hundred twenty-nine(129) plugs (Location 13) were VT-3inspected; three plugs were replaced.

2008 VT-3 Reinspection per BWRVIP-25: All thirtyfour (34) holddown bolts (Location 10)were VT-3 inspected from above with noreportable indications. Three (3) coreplate plugs replaced during Unit 1Recovery were VT-3 examined toconfirm that the replacement plug was inplace. No evidence of movement, wear,or misalignment was visible.

2010 VT-3 Reinspection per BWRVIP-25: All thirtyfour (34) holddown bolts (Location 10)were VT-3 inspected from above with norelevant indications.

SLC 2007 EVT-2 Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Noreportable indications found.

2008 EVT-2 Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Norelevant indications were observed.

2010 UT Stainless steel safe end-to-pipe weldexamined for Nozzle N 10. No relevantindications reported.

EVT-2 Bare metal examination (EVT-2)performed per BWRVIP-03, -27. Norelevant indications were observed.

Jet Pump Assembly 2005 UT, Baseline (2006) per BWRVIP-41, -138:VT- I UT of holddown beam locations BB- 1,

BB-2, and BB-3 (Jet Pumps I thru 20) -no reportable indications.

Baseline (2005) per BWRVIP-41 of allHigh and Medium Priority Weldlocations. Circumferential crack

7

Page 9: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

indication in backing ring for DF-3 weld(Jet Pump 19) will be inspected forchange during UiC7 RFO in Nov. 2008.

Baseline (2005) per BWRVIP-41: VT-Iof Medium Priority Location WD- 1 (JetPumps 1 thru 20); No wedge wearobserved. VT-l of Set Screw LocationsAS-I and AS-2 performed for Jet Pumps1 thru 20. Backlighting identified nine(9) set screw gaps ranging from 12 to 35mils in width. Two reportable linearindications identified on one of two setscrew tack welds for Jet Pump Nos. 15(shroud-side) and 16 (vessel-side). Nine(9) auxiliary wedges installed on JetPumps 2, 3, 4, 6, 7, 8, 10, 12, and 14.

2008 EVT- 1, VT-3 visual examination of theVT-3 holddown beam for Jet Pump #8 was

performed in response to misalignmentconcerns raised during Unit 1 Recoveryand an RFI identified during the October2007 INPO BWRVIP Review Visit.There was a minor misalignment with thebeam but no relevant indications wereobserved.

VT-3 visual examination of sensing lineclamps installed during Unit 1 Recoveryon Jet Pumps 1-5 and 11-15 performed toconfirm that all of the repair hardware isin place and that the hardware has notshifted or changed from the as-installedcondition. No relevant indications wereobserved.

EVT- I visual inspection performed of acircumferential crack indication in thebacking ring for High Priority LocationDF-3 (Jet Pump # 19) to determine if theindication had increased in length. Thisindication was previously recordedduring Unit I Recovery and does notappear to have changed.

8

Page 10: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2008 VT- I Reinspection per BWRVIP-41 R 1: VT- Iof Medium Priority Location WD- I (JetPumps 1 thru 20) - No vibration-inducedwear noted. Indication of vertical wedgemovement at ten (10) locations wasobserved, but the movement markingsdid not appear to be recent and correlatedwith findings during the Unit 1 Recoveryexaminations. VT-I of Set ScrewLocations AS-I and AS-2 performed forJet Pumps 1 thru 20. Backlightingidentified no new set screw gaps.Inspection results identified eightapparently new set screw tack weldindications in addition to the two setscrew tack weld indications that werepreviously observed during Unit 1Recovery. Justification for ContinuedOperation (JCO) was prepared andconcluded that the jet pumps areacceptable as-is for one fuel cycle. Nine(9) auxiliary spring wedges installedduring Unit 1 Recovery were inspected toverify contact; no relevant indications

were observed.

2010 EVT-1 Reinspection per BWRVIP-41, Rev. 3:

EVT-1 of Medium Priority LocationsRS-8 and RS-9 (Jet Pumps 1 thru 20)performed in accordance with BWRVIPLetter No. 2009-202 ("Interim Guidancefor Accelerated Inspections of Jet PumpRiser to Riser Brace Welds andWedges"); no relevant indications.

EVT- 1 visual inspection performed of acircumferential crack indication in thebacking ring for High Priority LocationDF-3 (Jet Pump #19) to determine if theindication had increased in length. Thisindication was unchanged from UIR7.

2010 VT- I Reinspection per BWRVIP-41 R3: VT- Iof Medium Priority Location WD- 1 (JetPumps I thru 20) - No vibration-induced

9

Page 11: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

wear noted; three new instances of minorwedge wear since UIR7 noted at JetPumps 1, 6, and 10 determined to be theresult of routing service during operation.VT-I of Set Screw Locations AS-I andAS-2 performed for Jet Pumps 1 thru 20.Backlighting identified one new setscrew gap (Jet Pump 20: Shroud-SideSet Screw - 17 mils). Evaluationperformed to provide one fuel cycle(U I C9) of continued operation.

Inspection results identified twoapparently new set screw tack weldindications on Jet Pump 17 in addition tothe nine set screw tack weld indicationsthat were previously observed duringU I R7 (NOTE: An indication that wasidentified during U1R7 for Jet Pump 14was accidentally counted twice).Justification for Continued Operation(JCO) was prepared and concluded thatthe jet pumps are acceptable as-is for onefuel cycle (UIC9).

Jet Pump Diffuser N/A N/A N/A

CRD Guide Tube 2005 EVT-1, Baseline per BWRVIP-47: 19 controlVT-3 rod guide tubes (10% of total) examined.

VT-3 visual examination of Locations

CRGT-1 and FS/GT-ARPIN-1, EVT-Ivisual examination of Locations CRGT-2and CRGT-3; no reportable indications.

CRD Stub Tube 2005 VT-3 VT-3 examinations performed foraccessible areas for 145 stub tubes atvarious core locations. No damage ordistortion was noted.

In-Core Housing N/A N/A N/A

Dry Tube 2006 VT All twelve (12) SRV/IRM dry tubesreplaced with modified design which isresistant to cracking. Inspections will bescheduled after dry tubes have reachedthe expected 20-year life (2027).

Instrument 2007 VT-2 Visual leak check is performed duringPenetrations Unit Startup. No reportable indications

10

Page 12: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

reported.

2008

2010

VT-2

UT

VT-2

Visual leak check performed during UnitStartup. Leak observed in safe-end topipe weld for N 11B instrumentationnozzle was repaired with weld overlay.

Stainless steel safe end-to-pipe weldexamined for Nozzles N 11A, N12A,N12B, N16A, and NI6B. No relevantindications reported.

Visual leak check performed during UnitStartup. No relevant indicationsreported.

+ +

Vessel ID Brackets 2005

2008

2010

EVT-1,VT-1,VT-3

VT-3

VT-3

The dryer support brackets, guide rodbrackets, feedwater sparger brackets,core spray piping brackets, jet pump risersupport bracket, and shroud support werevisually inspected in accordance withBFN Surveillance Instruction 1-SI-4.6.G.No indications recorded.

VT-3 visual examination performed ofall twelve (12) Feedwater Sparger EndBrackets and Retaining Pins. Norelevant indications were observed.

VT-3 visual examination performed ofall twelve (12) Feedwater Sparger EndBrackets and Retaining Pins. Minorimpact damage observed on 1750 Bracket(acceptable as-is), but otherwise norelevant indications were observed (nopin wear).

LPCI Coupling N/A N/A Not applicable to this plant

Steam Dryer 2005 VT-1, Full baseline inspection performed inVT-3 accordance with BWRVIP-139 and GE

SIL 644 RI. Three Drain ChannelVertical Welds were found to haveindications, and were repaired with weldoverlays.

2008 VT-1, Four previously recorded relevant

11

Page 13: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3

VT-1,VT-3

indications noted during Unit I Recoverywere VT-1 visually examined andconfirmed. No change in condition wasnoted from what was previously reported.General visual inspection (pre-EPUbaseline) performed in accordance withBWRVIP-139 and GE SIL No. 644 R1;no relevant indications were observed.

In preparation for ascension to EPU andoperation at EPU conditions, varioussteam dryer modifications wereperformed. All thirteen (13) Steam DryerTie-Bars were replaced with a newdesign and three (3) additional steam damgussets on each steam dam were added tothe Steam Dryer. A visual (VT-1)inspection was performed to documentthe as-left condition.

Four previously recorded relevantindications noted during Unit I Recoverywere visually examined and confirmed.No change in condition was noted fromwhat was previously reported in U IR7.

2010

Steam Separator 2010 VT-3 Steam Separator tie bars (cross bracing)examined for signs of cracking(Reference: INPO OE 30657). Norelevant indications were observed on thecross bracing, but a minor dent wasrecorded at the top of a standpipe locatedin the southeast corner of the separatorthat was acceptable as-is.

Dissimilar Metal 2008 UT 3 welds inspected (RCRD-1-33, CS-I-Welds - 002-008, CS-1-002-033A): PDI-

BWRVIP-75-A qualified, automated exams. No flawsidentified, no repairs.

Cat. C2010 N/A No Cat. C DM Welds were inspected

during Unit I Refueling Outage 8(U1R8).

Dissimilar Metal 2008 UT 2 welds inspected (DRHR-1-2, DRHR-l-Welds - 11): PDI-qualified, automated exams.

BWRVIP-75-A No flaws identified, no repairs.

12

Page 14: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Cat. D 2010 N/A No Cat. D DM Welds were inspected

during Unit 1 Refuieling Outage 8(U1R8).

13

Page 15: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Dresden 3

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Spray Piping 1980'sThrough1994

VT-1

4/97-R14

2/99-R 15

9/00-R 16

10/02-R17

UT/EVT-1

EVT-1

UT/EVT-1

VT-I

IEB 80-13 (1 MIL) VT-I of piping andwelds in annulus. Indications observed attwo lower elbow to pipe welds 2P4c and4P4c. These welds were repaired usingGE designed clamps.

UT Baseline inspections per BWRVIP- 18of all piping circ welds in annulus.Repairs removed and not reinstalled.EVT- I of any piping welds in annulusinaccessible to scanner. Additional flawsidentified on 1, 2 and 3P8a welds.

EVT- I examined undemonstrated weldsP8a and P4d on all four downcomers.Installed a "bumper" repair on 1P8a at the800 downcomer.

UT of "Target" welds and EVT-1 of allundemonstrated welds. Also EVT-1 ofwelds made inaccessible from repairinstalled on the 80' downcomer including1P7, lP4c, 1P4d, lP8a and b. Welds 2P4cand 4P4c exhibited flaw growth aspredicted by Flaw Evaluation.

Six P4 welds for presence of "excessivegrinding". NRI. All undemonstratedwelds P8a and P4d and long seams onthermal collars, NRI

Examined piping welds IP1, 2P1, 1P2,2P2, 1P3, 2P3, 3P3, 4P3, 2P4a, 2P4b.Eight Core Spray Piping brackets,attachment weld, pad surface and HAZ ofcladding. NRI.

Performed Core Spray Lower Sectional

10/04 - R 18 1 EVT- I

NA

14

Page 16: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

11/06-R19 IVT-1/VT-3

EVT-1

11/08-R20 IEVT-1

Replacement (all four downcomers)eliminating welds 1-4P4c, 1-4P4d, 1-4P8a, 1-4P8b, 1-4P5, 1-4P6, and 1-4P7.

Core Spray Lower Sectional Replacement- VT-I of all accessible bolting, keepers,ratchets and latch springs. NRI- VT-3 of all repair hardware. NRI

Examined piping welds: IP1, 2P1, 1P2,2P2, 1P3, 2P3, 3P3, 4P3, 3P4a, 3P4b andtwo piping brackets, attachment weld,pad surface and HAZ of cladding. NRI.

Examined piping welds: IPI, 2P1, 1P2,2P2, 1P3, 2P3, 3P3, 4P3, 4P4a, 4P4b andtwo piping brackets, attachment weld,pad surface and HAZ of cladding. NRI.

Examined bolting and tack welds for onepiping bracket. NRI

Examined piping welds: IP1, 2P1, 1P2,2P2, 1P3, 2P3, 3P3, 4P3, 1P4a, lP4b andtwo piping brackets, attaclunent welds,pad surfaces and HAZ of cladding. NRI.

Examined bolting and tack welds for onepiping bracket. NRI.

Core Spray Lower Sectional Replacement- VT-i of 4 bolting, keepers, ratchetsprings, latch springs, lateral pins, andkeepers. NRI- VT-3 of repair hardware. NRI

ll/10-R21

VT-1

EVT-1

VT-1

VT-I /VT-3

Core Spray Sparger 1980'sThrough1994

4/97-R14

VT-I

EVT-1,VT-3

IEB 80-13 (1 MIL) VT-1 of spargers andtee-boxes. NRI.

Examined tee-box cover plate welds (S I),tee-box to sparger arms (S2), and spargerend caps (S4) to EVT-1. NRI.Examined spargers nozzles (S3) and thesparger piping to VT-3. NRI.

Per BWRVIP-18: EVT-1 of all S1. S210/00 - R 16 EVT- 1.

15

Page 17: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

10/04 - R 18

11/08 - R20

VT-3

EVT-1

VT-I

EVT-1

and S4. VT-I of 50% of S3. NRI.

Sparger to End Cap Welds: 1 S4 (70), 1 S4(1830), 2S4 (70), 2S4 (1830), 3S4 (30), 3S4(1870), 4S4 (3), 4S4 (1870). NR.

Nozzle Tack Welds: 3S3 (187-260'), 3S3(260-003°), 4S3 (187-290'), 4S3 (290-0030). NRI.

-All 12 sparger brackets and bracket toshroud welds. NR.-Core Spray Lower SectionalReplacement (all four downcomers)eliminating inspection of the followingwelds: 1-4S1, 1-4S2a-b.

Sparger to End Cap Welds: 1S 4 (70), 1 S4(1830), 2S4 (70), 2S4 (1830), 3S4 (3), 3S4(1870), 4S4 (3), 4S4 (1870). NRI.

Nozzle Tack Welds: 1S 3 (007-080'), 1 S3(080-183°), 2S3 (007-110°), 2S3 (110-1830). NRI.

All 12 sparger brackets and bracket toshroud welds. One relevant indicationidentified. Indication acceptable for onecycle of operation.

One sparger bracket to shroud weldwhich had a previous indication identifiedin R20. No identified change. Indicationacceptable for one cycle of operation.

VT-1

11/10-R21 IVT-1

Attachment Welds 4/94-R 13

10/00-R16

10/02 - R17

VT-1

VT-I

EVT-1

Section XI inspections of jet pump riserbrace, dryer, feedwater sparger, corespray, and surveillance capsule holderbrackets, performed once per interval.NRI.

ASME Section XI B-N-2, surveillancecapsule holder attachments in beltline.All six sets examined. NRI.

BWRVIP-48 attachments: four dryerlugs, eight feedwater sparger end-

16

Page 18: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

10/04 - R 18 1 EVT- 1

11/06 - R19

11/08 - R20

11/10 - R21

VT-i

VT-3

EVT-1

brackets, eight Core Spray Pipingbrackets, attachment weld, pad surfaceand HAZ of cladding. NRI

Four steam dryer wall support lugs, lug topad, and pad to vessel attachment welds.Eight feedwater sparger lug to vesselattachment welds. NRI.

Eight feedwater sparger end-bracket lugassemblies. NRI

Examined attachment welds for two CoreSpray piping brackets and all four steamdryer wall support lugs in accordancewith ASME Section XI. NRI

Inspected piping bracket to piping weldand bracket to vessel attachment weld on2 core spray piping brackets. NRI

- Examined attachment welds for twoCore Spray piping brackets. NRI- Examined surveillance capsule holderbracket attachment welds. NRI

- Examined steam dryer and steamseparator guide rod attachment welds.NRI

- Examined attachment welds for twoCore Spray piping brackets and twosteam dryer wall support lugs. NRI

EVT- 1 andVT-3

VT-3

EVT- 1

Core Shroud 4/94-R 13

4/97-R14

EVT-1 andUT

EVT- 1 andUT

Inspections per SIL 572, extensiveindications in circumferential welds.

Inspected all shroud repair design reliantstructure prior to installation ofcomprehensive repair (4 GE designed tie-rod assemblies). Inspections consisted ofEVT-1 of all ring segment welds(accessible surfaces), UT for minimumligament of all vertical welds accessibleto scanner and EVT- 1 for minimumligament on all accessible surfaces of allvertical welds not accessible to the

17

Page 19: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

scamier.

2/99-R15

10/00-R16

10/04 - R18

NA

VT-1

UT

EVT-1

11/06-R19 UT

Installed four tie-rod shroud repairassemblies and four core plate wedges.

Examined all four tie-rod assemblies andcore plate wedges at locations specifiedby the manufacturer (GE).

Examined a 40' segment of H4 to assistin shroud qualification of Core SprayRepair. NRI.

Examined Ring Segment Welds VI-V4(Shroud Head RSWs), V8-V 13 (TopGuide RSWs), and V20-V25 (Core PlateSupport RSWs). Historical indications atV23 and V25 revealed no apparentchange since last inspection in R14(indications are not in HAZ. All otherRSWs NRI.

GE utilized the Telescoping ShroudScamier to perform UT on Shroudvertical welds V5-V6, V14-V19, V26-V28. Coverage obtained as follows:V5 - 80.4%V6 - 34.8%V14 - 66.8%V15 - 75.6%V16 - 80.4%V17 - 77.9%V18 - 95.5%V19 - 69.8%V26- 13.7%V27 - 69.4%V28 - 57.6%One indication identified on V27 (1.8" inlength). Indication acceptable forcontinued operation in accordance withBWRVIP-76.

Perfornmed one-sided EVT- 1examinations on vertical welds. NRI.Coverage as follows:V7 - 40%

EVT-1

18

Page 20: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3,EVT-1

EVT-1

EVT-1

V29 - 40% (between H7 and H8 welds)V30 - 0% (between H7 and H8 welds)V31 - 30% (between H7 and H8 welds)V32 - 0% (between H7 and H8 welds)

Performed GE recommended inspectionsof shroud repair hardware. Scopeincluded inspections to addresssusceptible areas based on indicationsfound at Hatch. One RI identified due toretainer clip not engage. This retainerclip is redundant and did not requirerepair.

Examined historical indications at V23and V25. No apparent change fromprevious inspection.

Performed one-sided EVT-1examinations on vertical welds VI, V2,V3, V4, V8, V9, VIO, VIl, V12, V13,V20, V21, V22, and V24. Horizontalindications were identified in the topguide ring below H2, near V12 and V13.Indications acceptable for one cycle ofoperation.

11/08 - R20

11/10 - R21

Shroud Support 4/94-Ri3

4/97-R14

2/99-R 15

10/02- R17

10/04 - R 18

11/06 - R19

UT/VT-1

EVT- 1

EVT-1

EVT-1

EVT-1

EVT-1,

Access hole cover VT/UT for circ andradial flaws. NRI.

Examined H8 and H9 for about 12" at 4locations of shroud repair hardwareattaclunent areas. NRI.

Per BWRVIP-38: Examined H8 and H9between Jet Pumps 20 and 1 (312'-357').NRI. Requirements for this inspectioncycle are satisfied. NRI.

Welds on Access Hole Covers at 1550and 335'. The D3 AHC's have not beenrepaired. NRI.

Examined H8 and H9 between Jet Pumps10 and 11 (312'-357'). NRI

VT-3 of accessible areas of H9 and EVT-

19

Page 21: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3 I of 10% of H9 (between Jet Pumps 10and 11). NRI.

11/08 - R20 EVT-1 Examined H8 and H9 between Jet Pumps20 and 1 (132- 1770). NRI.

11/10 - R21 UT Welds on Access Hole Covers at 1550

and 335'. The D3 AHC's have not beenrepaired. NRL.

SLC 10/02 - R17 PT PT of surface of Safe-end extension andsafe-end to nozzle weld. NR.

11/06 - R19 PT PT of surface of Safe-end extension andsafe-end to nozzle weld. NRI.

11/10 - R21 PT PT of surface of Safe-end extension andsafe-end to nozzle weld. NRI.

Jet Pump Assembly 4/94-R13

4/94-R13

4/97-R14

2/99-R15

VT-I

VT-I

EVT-I

EVT-1

Hold down beams, beam bolt keepers,lockplates and retainers; restrainerwedges, stops, and adjusting screws,clamp bolts and keepers; riser braceassemblies, adapters and baffle platewelds, sensing lines and sensing linebrackets per various SILS.Prior to R13, visually inspect 100% ofupper areas of each Jet Pump includingbeam retainers every other outage.

Riser brace ani to yoke welds on threeupper (secondary) riser braces foundcracked. Repairs are not required. Noother reportable indications.

Diffuser to baffle plate welds on all

twenty jet pumps. NRA.

All ten RS-1, 2, 3, 4 and RS-5. NRL.

Initiate BWRVIP-41:Medium Priority: 50% of DF-i, MX-1,MX-3 and IN-5 welds. All twenty RB-1,2, RS-8 and RS-9. NRI.

High Priority: 50% of DF-2, AD-i, 2 and3. NRI.

20

Page 22: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-I Examined all twenty WD-1 locations.NRI.

10/02-R 17 EVT- I Repeat examination of four DF-2 weldsto improve coverage. NRI.

Five RS-9 and 10 riser to secondary braceyoke welds, NRI. Eleven secondary braceRB-3 welds per ASME XI and BWRVIP-48. NRI.

03/03- VT- I Verified acceptable restrainer set-screwD3M09 gaps when replaced beams (reference Jet

Pump Beams section of this report). Auxwedges installed two set-screw locations.The other locations were NRI.

10/04 - R18 VT-I Examined jet pump sensing line clampson jet pumps 1, 2, 3, 10, 11, 12, 13, & 20.

EVT-1 Examined all twenty WD- 1 locations.Noted normal movement of wedges 11 &20 with no abnormal wear. All otherwedges NRI.

Examined AS-I (set-screw gaps) on fivejet pumps: 8 (Vessel Side, Shroud Side),9 (VS, SS), 1 (SS), 12 (VS, SS), 20 (VS,SS). No unacceptable gaps wereidentified (all less than 0.010").

Examined AS-2 (set-screw tack welds) onfive jet pumps: 8 (VS, SS), 9 (VS,SS), 11(SS), 12 (VS, SS), 20 (VS,SS). Lack offusion of tack welds was identified on jetpumps and set screws: 9 (VS), I1 (SS), &13 (VS). Indications noted on the tackwelds for 9 and 13 were accepted as-is forone-cycle. Jet pump 11 had a set screwmissing from its housing. The set-screwwas retrieved and an auxiliary wedge wasinstalled. Also discovered during theinspection of jet pump 11 was a poorquality tack weld on the swing-gatekeeper. The condition of the bolt keeper

21

Page 23: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

was accepted for one cycle.

The auxiliary wedge installed duringD3M09 on jet pump 13 was examinedand historical cracking was re-identifiedon the set-screw mounting block. Thisindication is historical and was caused bythe ejection of the inlet-mixer followingthe failure of a beam-bolt. The indicationhas been accepted as-is. Also discoveredon jet pump 13 was a gap between thevessel side restrainer bracket and theswing gate. The condition of the bracketand swing gate was accepted for onecycle.

Examined RS-10 & -11 on jet pumps: 2,3,4, 12, & 13. NRI.Examined RS-1, 2, & 3 on five jet pumppairs: 1/2, 3/4, 9/10, 11/12, 13/14. NRI.

UT Examined MX-3a&b, DF- 1, -2 & -3 andAD-1, -2 on jet pumps: 2, 3, 4, 5, 8, 9, 12,13, 18, & 19. NRI.

11/06 - R19 EVT-1 Examined RB-I & 2 on jet pumps: 1, 2,3, 4, & 20. NRIExamined RS-4 & 5 on jet pump pairs:9/10, 11/12, 13/14. NRIExamined RS-8 & 9 on jet pump pairs:1/2, 3/4, 5/6. NRIExamined MX-1 and IN-5 on jet pumps:1,2, 3,4,5, 11, 12, 13, 14, and 15. NRI

VT-I Examined aux wedge on JP 11. RI forslight wear on JP 11 aux wedge. Justifiedcontinued operation for one cycle.Examined main wedge WD-1 on JPs 1, 2,3, 4, and 11 for wedge wear. NR.

NA - Installed new ratchet style swing gate onJP 11 to address degraded keeper tackweld identified in R18.- Staked threads due to cracked tackwelds (found in D3R18) and installed auxwedges on JP 9 vessel side and JP 13

22

Page 24: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

vessel side set screws.

11/08-R20 IEVT-1

VT-I

Examined RB-3 on JPs 1, 2, 3, 4 and 5.NRI

- Examined aux wedges on JPs 9, 11 and13. RI for slight wear on JPs 9 and 11 auxwedges. Justified continued operation forone cycle.- Examined AS-1 on JP 9 SS and JP 11VS. NRI- Examined main wedge WD- 1 on JPs 1,2, 7, 8, 9, 11, 12, 13, 14, 17, 18, 19 and 20for wedge wear. One RI for a bent mainwedge handle. Condition acceptable as-is.- Examined swing gate keeper tack weldson JPs 7, 8, 9, 10 and 20. NRI- Examined JPs 1 and 2 transition piecesand sensing lines to address operatingtrends. NRI- Examined JP 11 swing gate bolting andratchets. Swing gate installed in D3R1 9.NRI

-Examined AD-1, AD-2, AD-3a, AD-3bon jet pumps 1, 6, 7, 10, 11, 14, 15, 16,17 and 20. NRI-Examined MX-3a and DF-1 on jetpumps 1, 10, 11, 14 and 15. NR.-Examined MX-3b and DF-2 on jetpumps 1, 6, 7, 10, 11, 14, 15, 16, 17 and20. NRI.-Examined RS-1, RS-2, and RS-3 on jetpumps risers 5-6, 7-8, 15-16, 17-18 and19-20. NRI.-Examined RS-8, -9, -10, and -11 on allof the jet pumps. NR.-Examined RB-I on jet pumps 5, 6, 7, 8,9, 10, 11, 12, 13, 14, 15, 16, 17, 18 and19. NR.

-Replaced an aux wedge on JP 11.-Examined aux wedge on JP 9. Nochange to wear identified in R20.- Examined (secondary) riser brace arm to

11/10-R21 IEVT-1

VT-I

23

Page 25: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

yoke welds on jet pump 19. RI with thecondition acceptable as-is.-Examined swing gate latches and weldedkeepers on jet pumps 4, 5, 6, 15 and 16.NRI.-Examined sensing line clamps on jetpumps 1 and 20. NR.-Examined main wedge WD-1 on JPs: 3,4, 5, 6, 10, 15 and 16 for wedge wear.NR.

+ *

Jet Pump Beams 4/94-Ri 3

4/97-Ri4

2/99-Ri 5

10/00-R 16

03/03-D3M09

10/04 - R 18

11/06 - R19

11/08 - R20

UT

UT

UT

UT

NA

VT-3

EVT-1

NA

VT- 1

Jet pump beams are UT examined eachoutage using technique capable ofdetecting cracking at throat and ears.Original group 1 beams.

Examined all beams. Two beams withindications replaced. Balance NR.

Examined all beams. NRI.

Two beams with indications replacedwith group 2 style beams. Balance NR.

Replaced all 17 original beams withweld-less keeper group 3 beams.

Examined 17 group 3 beam bolt retainermechanisms (weld-less keeper) to ensureall keepers were engaged. NR.

Examined 3 group 3 welded keeper stylebeams. BB-1 and BB-2 on Jet Pumps 5,8, and 13. NR.

Pre-emptive replacement of ageing beamson JPs 5, 8 and 13 rather than UTexamine.

- Examined beam ratchet engagement onJPs 5, 8 and 13 after 1 cycle of operation.NRI

- Examined beam and ratchet engagementon JPs I and 2 to address operatingtrends. NRI

+ +

LPCI Couplings NA

24

Page 26: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Lower Plenum 4/97-R14 MVT-1 CRD Stub Tube, CR1) H7. NRI.Lower Plenum 4/97-R14 MVT-1 CRD Stub Tube, CRD H7. NRI.

4/97-R14

10/00-R16

10/02-Ri7

10/04 - R18

11/08 - R20

11/10- R2 1

MVT-1

EVT-1

EVT-1 andVT-3

VT-3

VT-3

EVT-1

VT -3

ICH/RPV- 1 and ICHGT/ICH- 1, twoinspected from cell H7. NRI.

Per BWRVIP-47: examined CRGT-1, 2and 3 on D 10. NRI.

Examined 9 CRGT-1, 2 and 3 andFS/GT-ARP[N. NRI. Thifs completes first5% in 6 years.

Bottom Head Drain cleaning projectcreated access for the followingexaminations:- Examined eight Stub Tube to VesselWelds (ST/RPV-1) and eight Stub Tubeto CRD Housing Welds (CRDH/ST-1) incells: F7, G6, G7, G8, H7, H8, H9, andJ8. NRI.- Inspected two locations for Core Plateto Stiffener Plate Stitch welds: G7 & G8beam welds. NRI.- Examined two locations for StiffenerPlate to Stiffener Rods welds: G7 and H8beam tie rods. NRI.

Examined 9 CRGT-1 and FS/GT-ARP1N.NRI. This completes 10%.

Examined 9 CRGT-2 and 3. NRI. Thiscompletes 10%.

Installation of a plug in the bottom headdrain to support drain line valvemaintenance created access for thefollowing examinations from cells G7and H8:- Examined accessible portions of eightStub Tube to Vessel (ST/RPV-1) welds,eight Stub Tube to CRD Housing(CRDH/ST-1) welds and eight CRDHousing to Cap (CRDH-1) welds. NRI.- Examined accessible portions of four In-Core Monitor Housing to Vessel(ICH/RPV- 1) welds, four In-Core

25

Page 27: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Monitor Housing to In-Core HousingGuide Tube (ICHGT/ICH-1) welds, twoIn-Core Housing Support Hardware to In-Core Housing Guide Tube (ICHS/ICGT-1) tack welds and four In-Core HousingSupport (ICHS-1) hardware tack welds.NRI.

+ 4-

Feedwater Spargers(Not in BWRVIPScope)

11/06-R19 I VT-1

11/08-R20 VT-1

Inspected all of the end bracket pins fortack weld and pin wear. RI - Wearidentified between head of pin andbracket on four brackets. Justifiedoperation for one cycle.Inspected sparger repair hardware fromD2R18 isokinetic probe retrieval. NRI

Inspected all of the end bracket pins fortack weld and pin wear. RI - Wearidentified between head of pin andbracket on five brackets. Justifiedoperation for one cycle.

Inspected all of the end bracket pins fortack weld and pin wear. No apparentchange in wear from R20.

11/10 - R21 VT-I

4- + -

Steam Dryer 10/04 - R18 "Besteffort" VT-I

- Examined exterior surfaces includingouter hoods, historical repair areas, tiebars and attachment welds, four liftingassemblies, four hold down assemblies,two man way covers, cover plates,fourteen gussets, upper ring welds,vertical guide welds, outlet plenum lowerhorizontal welds, outlet plenum verticalwelds, and perforated plates. Multipleindications identified, including structuralfatigue flaws in the outer hood areas.Outer hoods modified to repair cracking.- Examined interior surfaces including:drain channel welds, supports, verticaland horizontal plates, support ring,horizontal cross beams, and horizontalcross beam gussets. Initial start-up steamsample probe discovered missing. Probelocated and retrieved from steamseparator. Multiple non-structuralindications also noted.

26

Page 28: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

11/06 - R19

11/08 - R20

11/10-R21

VT-3

"BestEffort" VT-1

NA

"BestEffort" VT-I

"BestEffort" VT-1 and VT-3

Examined interior and exterior skirt.Indications noted.

Performed VT- I inspection of outer hoodwelds on old dryer where previousindications had been identified andrepaired. NRI.

Installed new dryer.

Examined critical components on steamdryer after one cycle of operation per GErecommendations. One RI where dryercontacted steam separator guide rod (RIon guide rod also). Dryer and guide rodindications acceptable for one cycle ofoperation.

Examined critical components on steamdryer. The RI from R20 where the dryercontacted the steam separator guide rod(RI on guide rod also) showed no changeon both the SS guide rod and the SD.

Top Guide 4/94-R 13

4/97-R14

10/00-R16

10/04 - R 18

11/06 - R19

VT-I

VT-I

EVT-1

VT-I

EVT- I

VT-I

EVT-1

EVT-1

Examined beam intersections in five cellsin response to industry experience. NRI.

Per BWRVIP-26, baseline examined allfour top guide alignment assemblies.NRI.

Examined rim to bottom plate weld at thefour aligner assembly locations. NRI.

Examined 0' and 270' top guide

alignment assemblies. NRI.

Examined rim weld 11. NRI.

Examined 900 and 1800 top guidealignment assemblies. NRI.

Examined rim to bottom plate weld at 900and 1800. NRI.

Examined rim weld from cell 03-34. NRI

27

Page 29: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

11/08 - R20 VT-i Examined 0' and 2700 top guidealignment assemblies. NRI.

EVT-1 Examined top guide rim weld. NRI

Vessel 10/02 - R17 UT Examined vertical welds SCIA, SCIC,SC2B, SC3A, SC3B, SC3C, SC3D,SC4A, SC4B, SC4C, and SC4D. NRI.

10/04 - R18 UT - Examined vertical welds SC I B, SC2A,SC2C, SC3A, and SC3B. NRI. Satisfiesthird interval Section XI inspectionrequirements.- Examined two original vesselconstruction base metal repair areas inbeltline as required by Section XI. NRI.

VT-3 Inspected cladding in accordance withASME Section XI. NRI.

11/06 - R19 VT-3 Inspected the reactor vessel claddingfrom the shroud flange to the reactorflange in accordance with ASME SectionXI. NRI

Nuclear Instrument 4/94 - R13 VT-I Identified one cracked dry tube (24-37).Dry-tubes Replaced. Examined every other outage(Not in BWRVIP to date. Per Reutter-StokesScope) recommendations, have not reached

manufacturer's service life.

11/06 - R19 VT-I Examined two SRM and four IRM drytubes from 3 sides to meet SIL 409. NRI

11/08 - R20 VT-1 Examined two SRM and four IRM drytubes from 3 sides to meet SIL 409. NRI

11/10 - R21 VT-I Examined two SRM and four IRM drytubes from 3 sides to meet SIL 409. RIidentified movement on one IRMbetween the plunger and the Top Guide.Rub marks were also noted on theplunger. Acceptable as-is.

Steam Separator 10/04 - R18 VT-I Examined shroud head bolt pin and(Not in BWRVIP window condition. RI identified minorScope) wear that was evaluated as-is for

28

Page 30: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

continued operation. Examined eightstandpipe to shroud head welds and eightgusset to ring welds, NRI.

11/10 -R21 VT-I Examined shroud head bolt pin andwindow condition. RI identified minorwear on multiple bolts that was evaluatedas-is for continued operation. Replacedtwo SHBs. One of the two was missingthe pin and the other had excessive pin towindow wear.

Piping Welds 11/08 - R20 UT Performed manual UT on four (4) IGSCC(BWRVIP-75-A) Category C welds and two (2) IGSCC

Category A welds. None of these weldswere dissimilar metal (DM) welds. Norelevant indications identified.

11/10 - R21 UT Performed manual UT on six (6) IGSCCCategory D welds. Five of these weldswere dissimilar metal (DM) welds. Norelevant indications were identified.

29

Page 31: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Duane Arnold Ener2v Center

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 95 UT Performed ultrasonic examination of theaccessible areas. Baseline per BWRVIP-01, no indication were detected.

01 UT Performed ultrasonic examination of theH 1-H7 welds, no indications found

10 UT Unable to complete the ultrasonicexamination of the accessible areas dueto equipment issues. Performed ODEVT- 1 inspections to supplement andsubmitted Deviation Disposition to dothe UT exams in 2012. No indicationsfound.

Shroud Support 88/93 UT Performed ultrasonic examination of theAccess Hole Covers, no indications werereported.

98 VT-3 VT-3 of shroud support

99 VT-3 Shroud Support including H-8/H-9 (360degrees)

01 UT Performed ultrasonic examination of theAccess Hole Covers, no indications werereported.

03 VT-3 Shroud Support including H-8/H-9 (180to 360 degrees)

05 VT-3 Shroud Support including H-8/H-9 (0 to180 degrees)

07 EVT-1 Performed EVT-1 of 10% of the H-8 andVT-3 H-9 weld. Completed VT-3 of 1800 of

the shroud plate including both accesshole covers - no indications

09 VT-3 Shroud Support including the H-8/H-9 (0to 180 degrees) - no indications

Core Spray Piping 96 (portion VT Performed Visual Examination (EVT,

30

Page 32: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

every RFO)

98

99

01

03

05

07

09

10

EVT-1

EVT-1

EVT- 1

EVT-1

EVT-1

EVT-1

EVT- 1

EVT-1

CSVT, VT-3), baseline per BWRVIP-18,no indications were detected.

Reinspection per BWRVIP- 18 - noindications.

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Reinspection per BWRVIP- 18 - noindications

Core Spray Sparger 96 (portionevery RFO)

99

01

05

09

VT

EVT-1

EVT-1

EVT-1

EVT-1VT-I

Performed Visual Examination (CSVT,VT-3), baseline per BWRVIP- 18, noindications were detected. One spargernozzle is inspected every other RFO dueto a missing tack weld.

Examined S-1, S-2, and S-4 welds, VT-3on S-3A/B welds. No indications noted

Examined S-1, S-2, and S-4 welds, VT-3on S-3A/B welds. No indications noted

Examined S-1, S-2, and S-4 welds, VT-3on S-3A/B welds. No indications noted

Examined S-i, S-2, and S-4 welds withEVT-1. Examined S-3A/B with VT-I -no indications

+ 4 I

Top Guide (Rim, etc.) 95 VT-i (1/2mil wire)

Inspection of the 1/4" fillet weld on thecontour wedge and verified thatalignment blocks in place. 100%inspection of the grid locations has been

31

Page 33: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

completed over the past three RFOs.

98 VT-3 VT-3 0' location

99 VT-3 Examined nine cells (top general andbottom of grid areas)

01 VT- I Inspection of the 1/4" fillet weld on thecontour wedge and verified thatalignment blocks in place. Also inspectthe two hold down assemblies

03 VT-3 Examined five cells (top general andbottom of grid areas)

05 VT-I Inspection of the 1/4" fillet weld on thecontour wedge and verified thatalignment blocks in place. Also inspecttwo hold down assemblies.

05 VT-3 Examined four cells (top general andbottom of grid areas).

07 VT-I Performed VT-I examination of thebottom side of eight grid locations - noindications

09 VT-1 Performed VT-I of the Latches at 460VT-3 and 2260 location. VT-I of the fillet

welds on the contour wedges at 900 and2700. Was not able to obtain 100%coverage of the fillet welds on thecontour wedges due to the fuel being inthe way. Will re-schedule in 2010.Performed VT-3 of the top guide. - noindications

10 VT- I Performed VT- I of the Latches at 136'VT-3 and 3 160 location. VT-I of the fillet

welds on all contour wedges. PerformedVT-3 of the top guide. - no relevantindications

32

Page 34: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Core Plate (Rim, etc.) 95

98

99

01

03

05

07

09

VT-3

VT-3

VT-3

VT-3

VT-3

VT-3

VT-3

VT-3

Verified 25% core plate bolts were inplace

Verified 20% core plate bolts

Examined Fuel support castings in ninecells, no indications

Verified rim hold down bolts 1-54Examined Fuel support castings in tencells, no indications

Examined Fuel support castings in fivecells, no indications

Examined Fuel support castings intwenty cells, no indications

Performed a general VT-3 of FuelSupport Casting in eight locations - noindications

Performed a VT-3 examination of FuelSupport Castings in 12 locations - noindications

1 1

SLC

Jet Pump Assembly

93

01

03

05

07

PT

EVT-2

EVT-2

EVT-2

UT

Liquid Penetrant examination of thenozzle-safeend weld.

Enhanced visual using Remote VisualEquipment on nozzle-safeend weld., noindication.

Enhanced visual using Remote VisualEquipment on nozzle-safeend weld, noindication.

Enhanced visual using Remote VisualEquipment on nozzle-safeend weld.

Performed Appendix VIII UT of theNozzle-Safeend Weld - no indications

96 (sampleevery RFO)

VT-3 Inspection of the riser spt pads(SIL551),holddown beams(SIL330), sensinglines(SIL420), three pointcontact(RICSIL078). Will inspect RiserElbow in 1998. Repair to the set screwshave been completed.

33

Page 35: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

98 MVT-1 50% of total number of jet pumps, 100%of each inspected - no indications Allhold down beams - no indications

99 UT DF-l on JPs 1,2,3,4,13,14,15,16 IN-4,EVT-l MX-2 and WD-1 on JPs 3,4,13 and 14

RB- I and RB-2 on JPs 3,4,13 and 14.This completes all exams on 8 of 16 JPs

01 EVT-l RB-I, RB-2, RS-1, RS-2, RS-3, RS-6,RS-7, RS-8, RS-9, IN-4, MX-2, WD-1,on JPs 7 and 8. No indications.

03 EVT-1 RB-1, RB-2, RS-6, RS-7, RS-8, RS-9,IN-4, MX-2, WD-1, DF-2, AD-1, andAD-2 on JPs 5,6,9, and 10.RS-1, RS-2, RS-3, DF-2, AD-1, and AD-2 on JPs 5,6,9,10, 11,12.DF-i on JPs 5,6,7,8,9, and 10.No indicationsAll hold down beams - no indications.

07 UT Perforned UT of all 16 Jet PumpHolddown beams using GE technique -no indications

EVT-1 AD- I on JPs 15,16AD-2 on JPs 15, 16DF-i on JPs 11, 12, 15, 16DF-2 on JPs 15, 16IN-4 on JPs 11, 12, 15, 16MX-2 on JPs 11, 12, 15, 16RB-I on JPs 1, 2, 11, 12, 15, 16RB-2 on JPs 1,2, 11, 12, 15, 16Riser Brace Pad on JPs 1, 2, 5, 6, 7, 8, 9,10, 11, 12, 15, 16RS-1, RS-2, RS-3 @ 3240 locationRS-6 on JPs 11, 15RS-7 on JPs 12, 16RS-8, RS-9 @ 252-, 324' locations

VT-I WD-1 on all 16 JPsNo indications noted from any of the

34

Page 36: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

visual examinations

09 EVT-1 DF-2 on JPs 1, 2, 3, 4, 13, 14AD-I on JPs 1, 2, 3, 4, 13, 14AD-2 on JPs 1, 2, 3, 4, 13, 14RS-1, RS-2, RS-3, TS-1A @ 36-, 72°,2880

VT-3 Sensing Line Clamp on JPs 1, 2, 3, 14,Sensing Line Support on JPs 4, 5, 12, 13Sensing Line Exits at 900 and 2700No indications noted from any of thevisual examinations

10 EVT-1 RB-1, RB-2 on JPs 5, 6, 7, 8RS-6, RS-7 on JPs 5, 6, 7, 8RS-8, RS-9 on all JPsIN-4, MX-2 on JPs 5, 6, 7, 8DF-1, DF-2 on JPs 5, 6, 7, 8AD-1, AD-2 on JPs 5, 6, 7, 8RS-1, RS-2, RS-3, TS-CIa A @ 108s , 1448

VT-3 Sensing Line Clamp on JPs 6, 7, 8Sensing Line Support on JPs 6, 7, 8

No relevant indications, indications onsensing line clamps were determined tobe the result of initial installation.

Jet Pump Diffuser 96 (sample General Part of doing a 100% general visualevery RFO) Visual examination

CRD Guide Tube 95 (every 10 VT-3 Inspected accessible portions of threeyears) guide tubes, no indication were detected.

35

Page 37: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

03 VT-3 Inspect CRGT-1, CRGT-2, CRGT-3, andalignment pin on five guide tubes, noindications detected.

05 VT-3 Inspect CRGT-1, CRGT-2, CRGT-3, andalignment pin on five guide tubes, noindications detected.

07 VT-3 Performed general VT-3 examination ofeight locations - no indications

CRD Stub Tube 95 (every 10 VT-3 Inspected accessible portions of three

years) stub tubes, no indication were detected.

In-Core Housing

Dry Tube 88 (6 cycles VT-1 (1 Inspected in 1988 with indicationsand then mil wire) reported, replaced with the new designevery threecycles)

99 VT-3 Inspected accessible portions of 11 drytubes, no indications noted

07 VT- 1 Performed VT- 1 of upper 24" of five drytubes. Note the exam was performed onthe accessible areas - no indications

09 VT- 1 Performed examination on four dryVT-3 tubes. Note the exam was performed on

the accessible areas - no indications

10 VT-1 Performed examination on six dry tubes.Note the exam was performed on theaccessible areas - no indications

InstrumentPenetrations

Vessel ID Brackets Every 10 VTl(active Per ASME Section XIyears fuel) VT-3

all others

LPCI Coupling N/A N/A Not applicable to DAEC

Top Head 98 VT-3 No indications

99 VT-3 No indications

03 VT-3 No indications

05 VT-3 No indications

36

Page 38: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

07 VT-3 Perfomled VT-3 of interior portion of theRPV Head - no indications

Guide Rods

Sample HolderIntegral Attachment

98 VT-3 No indications

99

01

03

07

09

VT-3

VT-3

VT-3

VT-3

VT-3

Both examined (found cracked tack weldon 0 degree rod which was evaluated asacceptable)

Inspected 0 degree guide rod, noadditional indications

Inspected 180 degree guide rod, noindications

Inspected 180 degree guide rod, bracket,and bracket welds - no indications

Inspected the 00 guide rod bracket andbracket welds - noted the previouslyidentified cracked tack weld, no otherindications noted.

98

99

01

03

05

07

09

VT-IVT-3

VT-IVT-3

VT-IVT-3

VT-IVT-3

VT-IVT-3

VT-3

VT-3

No indications

108 and 288 degree examined with noindications

108 degree examined with no indications

36 and 108 degree examined with noindications

288 degree examined with no indications

1080 location - no indications

288' location - no indications

Core Spray Bracket 98 VT-3 No indications

01 VT-3 No indications

05 VT-3 No indications

09 EVT-1 Performed EVT-1 on the Piping Bracketsat 300, 1500, 2100, and 330' - noindications

37

Page 39: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-I Performed VT-I on the Sparger Bracketsat 110, 500, 890, 910, 1290, 1690, 1910,230°, 2690, 2710, 3090, and 3490locations - no locations

Jet Pump Riser 98 VT-I No indicationsSupport Pads 03 VT-i 216 degree pad - no indications

05 VT-I 144 and 252 degree pads - no indications

Feedwater Spargers 98

01

05

07

VT-IVT-3

VT-IVT-3

VT-IVT-3

VT-I

Indications around flow holes

No additional indications

No additional indications

Detailed inspection of all four spargers atthe following locations due to brokenkeeper:Vessel AttachmentKeeper to pin Handle interfaceKeeper to Sparger Bracket weldPin to sparger bracketPin to wall bracketSparger Bracket & BoltsSparger Bracket to Vessel MeasurementSparger to End PlateJacking Bolts (two spargers only)T-Box to Sparger WeldsWear was noted in several locations(details can be provided if requested).Pefre VTio h nnrRdia

09 VT-1

EVT-1/

Performed VT-1I of the Inner Radii at450, 1350, 2250, and 315' - no

indicationsPerformed EVT- 1/VT-3 of Bracket

38

Page 40: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3 Welds at 60, 840, 960, 1740, 1860, 2640,276', and 3540 - no indicationsImplemented a FW Sparger Modificationto repair the indications noted in 2007.This modification was to re-install thepreload on the spargers @ 225' and3150.

VT-I Performed VT-I on FW Brackets @ 60,840, 96', 1740, 1860, 2640, 2760, and3540 - wear was identified on the 26402760, and 3540

VT-I Performed VT-I on the T-Box to Spargerwelds @ 45', 135'. 2250, and 315'- noindications

VT-1/89 Performed visual examination of theflow holes on the T-Box and Spargers

Steam Dryer 03 VT-1/3 Inspect per GE SIL644. Indications inUpper Support Ring, Drain Channels,and Access Openings- all indicationsevaluated "use as is".

05 VT- 1/3 Inspect per GE SIL644 Rev 1.Indications in Drain Channels and UpperSupport Ring - all indications evaluated"use-as-is". No change in previousindications

07 VT- I Inspected per BWRVIP- 139 (all exteriorlocations) Indications in Drain Channels,Access Openings and Upper SupportRing. All indications evaluated "use-as-is" for one cycle. Some of the previousindications could not be located andsome new indication were identified.(Details can be provided if requested.)

09 VT-1/89 Performed examinations per BWRVIP-139 (all exterior locations). Allpreviously identified indications werenoted as "No change". Three newindications were identified. 1) UpperGuide Bracket was observed to have arolled piece of metal extending out andbelow the face/comer of the guidechannel. 2) Middle weld on Tie Bar #4was found cracked, and 3) Lower guidebracket, 1800 side was found bent. All

39

Page 41: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

indications were determined to beacceptable.

10 VT1/89 Performed examinations per BWRVIP-139 (all exterior locations). Twopreviously identified indications werenoted as NRI, all others were "Nochange". Three new indications wereidentified on access hole cover. Allindications were determined to beacceptable.Repairs made to Tie bars 3, 4, and 7 andto the rolled metal on the upper guidefound during previous outage.

Dissimilar Metal 09 UT ASME Section XI, Appendix VIII,weld (per BWRVIP- Supplement 10 manual exams performed75-A) on four (4) Category C, seven (7)

Category D and two (2) Category Edissimilar metal welds.

10 UT ASME Section XI, Appendix VIII,Supplement 10 manual exams performedon ten (10) Category C, fifteen (15)Category D and two (2) Category Edissimilar metal welds. One category Cweld had relevant indications. This wasrepaired by a weld overlay during theoutage.

40

Page 42: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Fermi 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud RF04 VT-I Inspected: 100% ID welds H2, H3, and,(BWRVIP-07/76) (I mil H4; 100% OD welds H 1-H7; accessible

wire) areas H8 & H9

VT-1/NT- The only indications identified were3 two <1" vertical in orientation above

the H2 weld at azimuth 125 degrees.These were evaluated againstestablished flaw screening criteria andfound acceptable.

RF05 EVT-1 Inspected approximately 60-70 degrees(1/2mil arc on the core shroud in area ofwire) previous indications. H2-H4 inspected

on shroud ID, H l-H7 inspected onshroud OD. No new indications, nochange observed in previousindications above H2 weld.

RF06 UT Performed focused phased array UTexamination of the H3, H4, H5 and H7welds utilizing GE's universal carousel.No indication of cracking wasidentified.

EVT-l A cursory exam was performed on H-3weld to confirm UT results for

information only. No new indicationsand no change was observed in theprevious indication above H2 weld.

RF07 EVT-1 Reinspected the indication above theH2 weld on the inside of the shroud.

No change in appearance. The controlrod blade was withdrawn to performthe examination.

RF08 N/A No inspections performed on the Core

41

Page 43: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Shroud. Inspections were performedon the Shroud Support

RF09 N/A No inspections performed on the CoreShroud. Inspections were performedon the Shroud Support

RF 10 N/A No inspections performed on the CoreShroud. Inspections were performedon the Shroud Support

RF1 1 N/A No inspections performed on the CoreShroud. Inspections were performedon the Shroud Support

RF 12 UT Performed phased array UTexamination of the H3, H4, H5 and H7welds from both sides utilizingAREVA's demonstrated technique. Noindication of cracking was identified.Inspection coverage exceeded 60% forall welds with coverage spaced aroundthe entire circumference.

RF13 UT No inspections performed on the CoreShroud. Inspections were performedon the Shroud Support.

RF14 UT No inspections performed on the Core(10/10) Shroud. Inspections were performed

on the Shroud Support.

Shroud Support RF03 VT-3 Inspected shroud support gusset welds(BWRVIP-38/*104) and HS/H9 in conjunction with jetAccess Hole Cover pump inspections. No indications(BWRVIP- 180)

RF04 VT-iNT- Inspected areas in conjunction with jet3 pumps, included were gusset welds H8

and H9. H8 and H9 welds inspected at0 and 180 degrees with 1 mil wire. Noindications.

RF05 EVT-l Inspected sample area 60-70 degree arc(1/2 mil) plus 180 degrees location on H8, H9,

and gussets. No indications.

RF06 VT-3* *Inspection performed in conjunction

42

Page 44: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

with jet pump inspections.Approximately 50% of the gussets andH8 and H9 welds were inspected. Thiswas a best effort exam which rangedfrom MVT- 1 to VT-3 depending oncamera angle and lighting. No cleaningwas performed. No indicationsidentified.

RF07 EVT-1 *Inspection performed in conjunctionwith jet pump inspections. Remaining50% of the gusset welds wereinspected. This was a best effort examwhich ranged from EVT- 1 to VT-3depending on camera angle andlighting. (Credited as a n EVT-1 exam)No cleaning was performed or needed.No indications identified. The H8 andH9 welds were inspected in detail at 0and 180 Deg. Azimuth to EVT- Istandards where there were noobstructions.

RF08 EVT-1 The H8 and H9 welds were reinspectedto achieve required coverage. 22% ofboth welds were inspected and includedthe areas at 0 and 180 degrees as wellas adjacent to Jet Pumps 2 and 3.Accessible areas on Gussets 1, 3, 11,12, and 22 were inspected. Noindications of cracking identified.

RF09 EVT-1 The H8 and H9 welds were inspectedVT-1 adjacent to Jet Pumps 3 and

4(Coverage obtained 1% and 8.3%).Accessible areas on Gussets 2 and 15inspected (90% coverage on eachobtained). Both access hole coverswere inspected (VT-1). No indicationsidentified.

RFIO EVT-1/ The H8 and H9 welds were inspectedVT-1 adjacent to Jet Pump 5(Coverage

obtained 1% and 8.3%). Accessibleareas on Gussets 7 and 8 inspected(70/90% coverage obtained PVT-1

43

Page 45: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

quality, EVT-l not credited, CARD 05-20378). No indications identified.

RFI 1 EVT-1 The H8 and H9 welds were inspected at0 and 180 degrees as well as severalother locations. Coverage obtained was24% for H8 and 30% for H9.Accessible areas on Gussets 5, 6, 7, 8,9, 10, 18, and 21 were inspected with50% to 80% coverage obtained @EVT-1. No indications identified.

UT A portion of the H9 weld was examinedfrom the vessel outside diameter usinga manual technique as required byBWRVIP-104. Approximately 19.6%of weld was examined with noindications.

RF12 EVT-1 Accessible areas on Gussets 4 and 13were inspected with 55% to 80%coverage obtained using EVT-1. Noindications identified. Both AccessHole covers were inspected per draftBWRVIP -180 requirements. Crackingidentified on 0 degree cover. ReferenceOE 25794.

RF13 EVT-1 Accessible areas on Gussets 5 and 6were inspected with 75% coverageobtained using EVT- 1. No indicationsidentified. The 0 Degree Access Holecover was reinspected and no additionalcracking was identified. No repairinstalled.

RF14 EVT-1 Accessible areas on Gussets 1, 21, and(10/10) 22 were inspected with 50% - 60%

coverage obtained using EVT- 1. Noindications identified. All 3 welds onthe 0 Degree Access Hole Cover werereinspected and no additional crackingwas identified. No repair installed.

Core Spray Piping each outage VT-I During RF-01 two small arc strikes(BWRVIP-18/18-A) RFO1 thru (Ilmil) were identified on loop piping. These

RF04 have been reinspected each outage. No

44

Page 46: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

change in condition. Inspectionsperformed per IEB 80-013 and SIL289. No indication of cracking.

RF05 EVT-1 All welds brushed prior to inspection(1/2mil) using 1/2 mil wire. Remainder of loopVT-I piping inspected without brushing. No

indication of cracking.

RF06 EVT-1 Inspected all welds on both loops ofcore spray to EVT-1 standards asopposed to BWRVIP-i18 requirementsof MVT- 1. Cleaning assessment wasperformed - cleaning was notnecessary. No indication of cracking.

RF07 EVT-1 Inspected all welds on both loops ofcore spray to EVT-1 standards.Cleaning assessment was performed -cleaning was not necessary. Noindication of cracking.

RF08 EVT-1 Inspected all welds on both loops ofcore spray to EVT-1 standards.Cleaning assessment was performed,cleaning was not necessary. Noindication of cracking.

RF09 EVT-1 Inspected all target welds on both loopsof core spray and sample welds on Div2 to EVT-1 stnds. Cleaning assessmentwas performed, cleaning was notnecessary. No indications of cracking.

RF1O EVT-1 Inspected all target welds on both loopsof core spray and rotating sample weldson Div 2 to EVT-1. Cleaningassessment was performed, cleaningwas necessary for selected locationsand welds were brushed. Noindications of cracking. Inspectioncoverage reported separately butgenerally >80%.

RF 1I EVT-1 Inspected all target welds on both loopsof core spray and rotatinR sample welds

45

Page 47: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

on Div Ito EVT-1. Cleaningassessment was performed, cleaningwas necessary for selected locationsand welds were brushed. Noindications of cracking. Inspectioncoverage reported separately butgenerally >80%.

RF12 EVT-1 Inspected all target welds on both loopsof core spray and rotating sample weldson Div 1 to EVT- 1. Cleaningassessment was performed, cleaningwas necessary for selected locationsand welds were brushed. Noindications of cracking. Inspectioncoverage reported separately butgenerally >55%.

RF 13 EVT-I Inspected all target welds on both loopsof core spray and rotating sample weldson Div 2 to EVT-1. Cleaningassessment was performed, cleaningwas necessary for selected locationsand welds were brushed. Noindications of cracking. Inspectioncoverage reported separately butgenerally >55%.

RF 14 EVT-1 Inspected all target welds on both loops(10/10) of core spray and rotating sample welds

on Div 2 to EVT-1. Cleaning wasperformed for all locations and weldswere hydrolazed or brushed. Noindications of cracking. Inspectioncoverage reported separately butgenerallv >60%.

Core Spray Sparger each outage VT- 1 (1 During RFO1 one arc strike identified(BWRVIP-18/18-A) RF01-RF04 inl) on upper CS sparger. Reinspections

have not identified any changes. Noindication of cracking

RF05 VT- 1/2 mil wire used for junction boxl/EVT-1 remainder utilized imil wire. No(1/2mil) indication of cracking.

RF06 EVT- 1, Inspected per BWRVIP- 18 using EVT-

46

Page 48: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF07

RF08

RF09

RF10

RF1 1

MVT-1

EVT-1/VT-I

EVT-1/VT-i

EVT-1/VT-1

EVT-1/NT-1

EVT-1/VT-1

I for sparger T-box and end caps andMVT-1 for remaining locations. Noindications of cracking.

Inspected per BWRVIP- 18 using EVT-I for sparger T-box welds, end capwelds, drain plug welds, and supportbrackets and welds, and VT-I for flownozzles and tack welds. No indicationsof cracking identified.

Inspected per BWRVIP- 18 using EVT-1 for S1, S2 and S4 welds. SelectedS3a, S3b welds inspected using VT-1.Selected $3c welds as well as selectedSB bracket welds were inspected usingEVT- 1 technique. A best effort examwas performed on all accessible areas.No indications of cracking identified.

Inspected per BWRVIP- 18 using EVT-1 for 50% of the S1, S2 and S4 weldsand VT-i for 50% of the S3a, S3b and$3c welds on the same spargers. 9 SBbracket welds were inspected usingEVT-1 technique. Coverage forspecific welds will be reportedseparately. No indications of crackingwere identified.

Inspected per BWRVIP- 18 using EVT-1 for 50% of the S1, S2 and S4 weldsand VT-1 for 50% of the S3a, S3b and$3c welds on the same spargers. 6 SBbracket welds were inspected usingEVT-1 technique. Coverage forspecific welds will be reportedseparately but was > 60% for welds and>85% for brackets. No indications ofcracking were identified.

Inspected per BWRVIP-18-A usingEVT-1 for 50% of the S1, S2 and S4welds on the same spargers. 6 SBbracket welds were inspected usingVT-I technique. Coverage for specific

47

Page 49: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

welds will be reported separately butwas > 50% for welds and >75% forbrackets. No indications of crackingwere identified

RF12 EVT- Inspected per BWRVIP- 18-A using1/VT-1 EVT-l for 50% of the S 1, S2 and S4

welds on the same spargers. 6 SBbracket welds were inspected usingEVT-1 technique. Coverage forspecific welds will be reportedseparately but was > 40% for welds and>75% for brackets. No indications ofcracking were identified.

RF13 EVT- Inspected per BWRVIP- 18-A using1/VT-i EVT-1 for 50% of the S1, S2 and S4

welds on the same spargers. 6 SBbracket welds were inspected usingEVT-1 teclinique. Coverage forspecific welds will be reportedseparately but was > 50% for welds and>70% for brackets. No indications ofcracking were identified.

RF14 EVT- Inspected per BWRVIP-I 8-A using(10/10) 1/VT-1 EVT-I for 50% of the S1, S2 and S4

welds on the C and D spargers. 6 SBbracket welds and S3 nozzle weldswere inspected using VT-I technique.Coverage for specific welds will bereported separately but was > 40% forwelds and >60% for brackets. Noindications of cracking were identified.

Top Guide (Rim, Each outage VT-3 Inspected rim each outage. Noetc.) indications.Beams (BWRVIP-26) RF03 VT-I Inspected 6 locations (RICSIL 059). No(BWRVIP-183) indications.

RF04 VT-I Inspected 6 locations (SIL 554). Noindications.

RF05 VT-I Inspected 15 locations (SIL 554). Noindications.

48

Page 50: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF06 VT-I Inspected bottom edge of beams at 11core locations per SIL 554. Noindication of cracking.

RF07 VT-I Inspected bottom edge of beams at 8core locations per SIL 554. Noindication of cracking.

RF08 VT-I Inspected bottom edge of beams at 5core locations per SIL 554. Noindication of cracking.

RF09 VT-I Inspected bottom edge of beams at 6core locations per SIL 554. Noindication of cracking.

RF 10 VT- I Inspected bottom edge of beams at 2core locations per SIL 554. Noindication of cracking.

RFl 1 VT-I Inspected bottom edge of beams at 2core locations per SIL 554. Noindication of cracking. Inspected 90degree segment of top guide rim and noindications were identified.

RF12 VT-i/VT- Inspected intersection and bottom edge3 of beams at 5 core locations per SIL

554. No indication of cracking.

RF 13 EVT- 1 Inspected intersection and bottom edgeof beams at 5 core locations perBWRVIP- 183 utilizing a new visualinspection tool. No indication ofcracking.

RF14 EVT-1 No inspections performed RF14.(10/10)

Core Plate Rim RF05 VT-I Inspected 6 core plate bolts locatedBolts, etc. (imil between 100 and 160 degrees and(BWRVIP-25) wire) adjacent area. No indications.

RF06 VT-3 Inspected tops of approximately 20bolts per SIL 588. No indicationsidentified.

49

Page 51: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF07 VT-3 Inspected tops of approximately 20bolts per SIL 588. No indicationsidentified.

RF08 VT-3 Inspected tops of approximately 20core plate bolts (VT-3) per SIL 588.Did not meet BWRVIP requirements.No indications identified.

RF09 N/A No inspections performed. BWRVIPanalysis concluded that inspections arenot required. (Reference BWRVIP2003-117 and TJ-2003-01)

RF1O N/A No inspections performed. BWRVIPanalysis concluded that inspections arenot required. (Reference BWRVIP2003-117 and TJ-2003-01)

RF1 1 N/A No inspections performed. BWRVIPanalysis concluded that inspections arenot required. (Reference BWRVIP2006-041 and DD-2006-0 1)

RF12 N/A No inspections performed. BWRVIPanalysis concluded that inspections arenot required. (Reference BWRVIP2006-04 1)

RF 13 N/A No inspections performed. BWRVIPanalysis concluded that inspections arenot required. (Reference BWRVIP2006-041)

RF- 14 N/A No inspections performed. BWRVIP(10/10) analysis concluded that inspections are

not required. (Reference BWRVIP2006-041) BWRVIP 2010- 243 nowrequires preparation of a DeviationDisposition by 3/31/2011.

SLC RF04 VT-3 Performed a visual inspection from(BWRVIP-27) Reactor penetration to shroud support

when access was provided during jetpump beam replacement. Noindications.

50

Page 52: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF05 - RF07 N/A No inspections performed as accesswas not provided.

RF08 VT-2* Performed enhanced inspection onnozzle area from inside skirt area, butdid not remove mirror insulation boxfrom safe-end. No leakage observed.

RF09 VT-2* Performed enhanced inspection onnozzle area from inside skirt area, andremoved cover on the mirror insulationbox for the safe-end for directinspection. No leakage observed.

RFHO VT-2* Performed enhanced inspection onnozzle area from inside skirt area, andremoved cover on the mirror insulationbox for the safe-end for directinspection. No leakage observed.

RF 1I VT-2* Performed enhanced inspection onnozzle area from inside skirt area, andremoved cover on the mirror insulationbox for the safe-end for directinspection. No leakage observed.

RF12 VT-2* Performed enhanced inspection onnozzle area from inside skirt area, andremoved cover on the mirror insulationbox for the safe-end for directinspection. No leakage observed.

RF13 VT-2*/UT Performed enhanced inspection onnozzle area from inside skirt area, andremoved cover on the mirror insulationbox for the safe-end for directinspection. No leakage observed.Performed a manual PDI qualifiedultrasonic inspection of the nozzle tosafe end weld as well as additional basematerial of bored material. Noindications identified.

RF-14 VT-2* Performed enhanced inspection on(10/10) nozzle area from inside skirt area, and

removed cover on the mirror insulation

51

Page 53: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

box for the safe-end for directinspection. No leakage observed.

Jet Pump Assembly(BWRVIP-41)

Each outageexamine atleast 50%thru RF05

RF06

RF07

RF08

VT-I VT-3

MVT-1,VT-3

EVT-l

EVT- 1

Jet pump assemblies are inspected eachoutage from top to bottom. During RF-04 all (20) hold down beams werereplaced as a preventative measure andto avoid performing UT's on the oldstyle/original beams. Inspections areperformed to the recommendations ofSIL 551, 574, 465 S-i, and RICSIL078. During RF05 one of the 80restrainer screw tack welds was foundto be cracked. This was evaluated andwas not repaired during RF05.

Performed inspections to the intent ofBWRVIP-41 as well as augmented VT-3 of selected areas on jet pumps 1-10.Inspections included all High, Mediumand Low Priority locations. InspectedRS-1 and RS-2 welds on jet pumps 11-20. One indication identified on RS-1weld, 1.75" long. JCO performed priorto start-up. No other new indicationsidentified.

Performed inspections to the intent ofBWRVIP-41 including EVT-1 's aswell as augmented VT-1 and VT-3's ofselected areas on jet pumps 11-20.Inspections included all High, Mediumand Low Priority locations.Reinspected previously identifiedindication on RS-1 weld, 1.75" longthat was identified in RF06. No changein indication length or appearance.Existing Flaw Evaluation on handprepared by GE referenced asacceptance limit. No other indicationsor changes in previous indicationsidentified.

Performed reinspections to the intent ofBWRVIP-41 including EVT-I's aswell as augmented VT-1 and VT-3's ofselected areas on jet pumps 1& 2.

52

Page 54: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Inspections included all High, Mediumand Low Priority locations.Reinspected previously identified 1.75"long indication on RS- I weld for JetPumps 7&8 that was identified inRF06. No change in indication lengthor appearance. Existing FlawEvaluation on hand prepared by GEreferenced as acceptance limit.Inspected all 20 jet pumps perrecommendations of SIL 629 andverified no wedge damage (WD-1) aswell as full contact with restrainerscrews. No damage identified on anylocation. Reinspected all restrainerscrew tack welds with no changesobserved.

RF09 EVT-1 Performed reinspections to BWRVIP-41 including EVT-l's as well asaugmented VT-1 and VT-3's ofselected areas on Jet Pumps 3 & 4.Inspections included all High, Mediumand Low Priority locations.Reinspected previously identified 1.75"long indication on RS-1 weld for JetPumps 7&8 that was identified inRF06. No change in indication lengthor appearance. Existing FlawEvaluation on hand prepared by GEreferenced as acceptance limit.Inspected all 20 Jet Pump Hold DownBeams by UT for BB 1, BB2, and thetransition area BB3 using the latestavailable teclmique from GeneralElectric. No indications identified onthe beams. Reinspected all restrainerscrew tack welds, contact area, andwedges after both tack welds on JetPump 15 were found cracked. No otherdamage or indications identified on anylocation. Jet Pump 15 permanentlyrepaired by the installation of anauxiliary spring wedge. (ReferenceCARD 03-16929)

53

Page 55: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF 10 EVT- 1 Performed reinspections to BWRVIP-41 including EVT-I's as well asaugmented VT-I and VT-3's ofselected welds on Jet Pumps 4, 5, 6, 7,& 8. Reinspected previously identified1.75" long indication on RS-1 weld forJet Pumps 7 & 8 that was identified inRF06. No change in indication length /appearance. Existing Flaw Evaluationon hand prepared by GE referenced asacceptance limit. Reinspected auxiliaryspring wedge on Jet Pump 15. Noother damage or indications identifiedon any location.

RF 11 EVT-1 Performed reinspections to BWRVIP-41 including EVT-I's as well asaugmented VT-I and VT-3's ofselected welds on Jet Pumps 7, 8, 9, &10. Reinspected previously identified1.75" long indication on RS-l weld forJet Pumps 7 & 8 that was identified inRF06. No change in indication length /appearance. Existing Flaw Evaluationon hand prepared by GE referenced asacceptance limit. Inspected all JetPump wedges after wear was identifiedon JP2 restrainer bracket. Performedinspection of other welds on Jet Pump2 as required by BWRVIP-41.Auxiliary spring wedges installed onJet Pumps I and 2 and a slip jointclamp was installed on Jet Pump 2 torestore integrity. No other damage orindications identified.

RF 12 EVT- 1 Perforned reinspections to BWR VIP-41 including EVT-1 's as well asaugmented VT-I and VT-3's ofselected welds on Jet Pumps 7, 8, 9, 10,11, & 12. Reinspected previouslyidentified 1.75" long indication on RS-1 weld for Jet Pumps 7 & 8 that wasidentified in RF06. No change inindication length / appearance.

54

Page 56: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Existing Flaw Evaluation on handprepared by GE referenced asacceptance limit. Inspected all 20 JetPump Hold Down Beams. Inspected12 Jet Pump wedges including thewedges and hardware (auxiliary springwedges and slip joint clamp) installedin RF 11. No other damage orindications identified.

RF 13 EVT- 1 Performed reinspections to BWRVIP-41 including EVT-I's as well asaugmented VT-I and VT-3's ofselected welds on Jet Pumps 7, 8, 9, 10,13, 14, 15, and 16. Reinspectedpreviously identified indication on RS-1 weld for Jet Pumps 7/8 identified inRF06. No change in indication lengthor appearance. Existing FlawEvaluation on hand prepared by GEreferenced as acceptance limit.Inspected 9 Jet Pump wedges. Noother damage or indications identified.

RF14 EVT-1 Performed reinspections to BWRVIP-(10/10) 41 including EVT-1 's as well as

augmented VT-1 and VT-3Ys ofselected welds on most Jet Pumpsincluding RS-8/9 welds on all pumps.Reinspected previously identifiedindication on RS- 1 weld for Jet Pumps7/8. No change in indication length orappearance. Existing Flaw Evaluationon hand prepared by GE referenced asacceptance limit.Inspected all 20 Jet Pump wedges.Minor movement noted but no otherdamage or indications identified.

Jet Pump Diffuser Each outage VT-3 Diffusers will be sample inspected(BWRVIP-41) during refueling outages.

RF06 MVT-1 BWRVIP-41 on Jet Pumps 1-10 exceptinaccessible areas. No cracking.

RF07 EVT-1 BWRVIP-41 on Jet Pumps 11-20except inaccessible areas. No cracking

55

Page 57: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

identified. Welds DF-3, AD-1, and AD-2 are inaccessible for inspection.

RF08 EVT-1 BWRVIP-41 reinspection on Jet Pumps1 and 2 except inaccessible areas. Nocracking identified. Welds DF-3, AD-1,and AD-2 are inaccessible forinspection.

RF09 EVT-1 BWRVIP-41 reinspection on Jet Pumps3 and 4 except inaccessible areas. Nocracking identified. Welds DF-3, AD-1,and AD-2 are inaccessible for EVT- 1visual inspection, VT-3 performed.(TJ-2003 -02 prepared as justification)

RF10 EVT-1 BWRVIP-41 reinspection of selectedDF-1 and DF-2 welds on Jet Pumps 5,6, 7, & 8. Performed access study forfuture performance of UT examinationsof welds DF-3, AD-1, and AD-2.These welds are inaccessible for visualinspection. VT-3 performed. Noindications identified (Reference TJ-2003-02)

RF 1I EVT-1 BWRVIP-41 reinspection of selectedDF-2 welds on Jet Pumps 9 & 10.

UT Performed of UT examinations on aportion of a total of 17 DF-3, AD-1,and AD-2 welds using specializedtooling. These welds are inaccessiblefor visual inspection. No indicationsidentified (Reference DD-2006-02)

RF 12 EVT-1 BWRVIP-41 reinspection of selectedDF-1 and 2 welds on Jet Pumps 6, 11,& 12.

UT No UT examinations performed duringRF12 due to tooling failures. Thesewelds are inaccessible for visualinspection. (Reference DD-2006-02)

RF13 EVT-1 BWRVIP-41 reinspection of selected

56

Page 58: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

UT

EVT-1

UT

RF14(10/10)

DF-1 and 2 welds on Jet Pumps 7, 13,& 14.

No UT examinations performed duringRF13 due to tooling failures. Thesewelds are inaccessible for visualinspection. (Reference DD-2006-02)

BWRVIP-41 reinspection of selectedDF-1 and 2 welds on Jet Pumps 7, 8, 9,and 13-18. No indications identified.

Completed baseline UT examinationson all 20 Jet Pumps Diffuser/AdapterDF-3, AD-1 and AD-2 welds, (60welds) since these welds areinaccessible for visual inspection.Deviation Disposition is no longerneeded.

1- 4

CRD Guide Tube(BWRVIP-47)

RF04

RF07

RF08

RF09

RF10

VT-3

EVT-1 andVT-3

EVT-1 andVT-3

EVT- I andVT-3

EVT- I andVT-3

Inspected lower portion of peripheralguide tubes and stub tubes when accesswas provided during jet pump holddown beam replacement. Noindications identified.

Perfomred best effort exam on CRGT-3as weld was not visible on inside oftube. CRGT-2 not accessible due toflow and ARPIN was not felt to beaccessible. No indications identified.

Performed best effort exam on CRGT-3as weld was not visible on inside oftube. CRGT-2 not accessible due toflow and FS/GT-ARPIN was not felt tobe accessible. No indicationsidentified.

Perforied exams on CRGT-l, CRGT-2, CRGT-3, and FS/GT-ARPIN at 10Control Rod Guide Tubes/locations.No indications identified.

No inspection performed in RF 10.

57

Page 59: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RFll

RF12

RF13

EVT-1VT-3

VT-3

EVT-1VT-3

and i No inspection performed in Ri11.

Performed exams on CRGT-1 andFS/GT-ARPIN at 5 Control Rod GuideTubes/locations. CRGT-2 and CRGT-3not performed or credited due to highflow conditions. No indicationsidentified.

and No inspections performed in RF 13.

RF14(10/10)

EVT-1 andVT-3

Completed all remaining baselineinspections on the Control Rod GuideTubes. Inspections performed on (4)CRGT-1, and FS/GT-ARPIN locationsand on (9) CRGT-2 and CRGT-3locations. One manufacturing flawidentified that did not impact thefunctionality of the component.

CRD Stub Tube * RF04 VT-3 Inspected lower portion of peripheral(BWRVIP-47) guide tubes and stub tubes when access

was provided during jet pump hold

down beam replacement. Noindications identified.

In-Core Housing * RF04 VT-3 Small portion visible during jet pump(BWRVIP-47) beam replacement. No indication of

degradation.

Dry Tube * Each outage VT-1 9 of 12 tubes found not completely(BWRVIP-47) seated. Perforned all inspections per

SIL 409 and RICSIL 073. Noindications of cracking.

RF06 VT-I Reinspected 12 dry tubes. No changefrom previous condition. No cracking.

RF07 VT-I Inspected all 12 original design DryTubes. No change from previousconditions identified. No crackingidentified.

RF08 VT-I Inspected all 12 original design DryTubes from two sides. No change from

58

Page 60: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

previous conditions identified. Nocracking identified.

RF09 N/A-I No inspections performed in RF09.

RFIO VT- I Inspected all 12 original design DryTubes from two sides. Linearindications identified on 7 tubes in thecollar region above the pressureboundary weld. Evaluated asacceptable for one cycle of operation.Plan to replace in RF 11. (ReferenceCARD 04-25703)

RF1I VT-I Replaced all 12 Dry Tubes in RF11.Performed baseline VT-1 and verifiedproper engagement in Top Guide.

RF12 VT- I No inspections performed in RF 12.

RF13 VT- I No inspections performed in RF 13.

RF14 VT-I No inspections performed in RF14.(10/10)

Instrument Penet.* Each outage VT-3 Inspected jet pump sensing lines and(BWRVIP-49 & 41) brackets each outage.

RF04 VT-3 SLC and peripheral bottom headpenetrations inspected. No indications.

RF06 VT-3 Inspected JP sensing lines for pumps 1-10. No indications.

RF07 VT-3 Inspected JP sensing lines for pumps IIthru 20 only. No indications.

RF08 VT-3 Inspected JP sensing lines for Pumps 1& 2 only. No indications.

RF09 VT-3 Inspected JP sensing lines for Pumps 3& 4 only. No indications.

RFIO VT-I Inspected JP sensing lines for Pumps 5,6, 7, 16, & 17. No indications

59

Page 61: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF1 1 VT-I Inspected JP sensing lines for Pumps 6,7, 16, & 17. No indications.

RF12 VT-I Inspected JP sensing lines for Pumps 6,7, 11, 12, 16, & 17. No indications.

RF13 VT-I Inspected JP sensing lines for Pumps 6,7, 13, 14, 16, & 17. No indications.

RF14 VT-I Inspected JP sensing lines for Pumps 6,(10/10) 7, 15, 16, 17, & 18. No indications.

Vessel ID Brackets(BWRVIP-48)

Each outage

RF06

RF07

RF08

RF09

VT-1/3

MVT-1

EVT-1

EVT-1

EVT-l

Inspect sample population each outage.We have inspected most brackets eachoutage (core spray, feedwater). Jetpump riser brace, steam dryer supportlugs, guide rod brackets and specimenholder brackets are sample inspected.No indications of cracking identified.

6 feedwater brackets.All core spray piping brackets.4 steam dryer brackets1 guide rod bracket1 specimen bracket.No indication of cracking.

6 feedwater brackets.All core spray piping brackets.4 steam dryer brackets1 guide rod bracketNo indication of cracking identified.

6 feedwater brackets.All core spray piping brackets.4 steam dryer brackets1 guide rod bracketSurveillance holder and Brackets @ 30az.No indication of cracking identified.

6 Feedwater brackets.4 Core Spray piping brackets.1 Jet Pump riser brace (Jet Pump 3 and4)No indication of cracking identified.

60

Page 62: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RFIO EVT-1 6 Feedwater brackets.3 Core Spray piping brackets.1 Surveillance Holder bracket4 Steam Dryer Support brackets4 Steam Dryer Hold Down1 Guide Rod BracketI Jet Pump riser brace (Jet Pump 5 and6)No indication of cracking identified.

RF 11 EVT- No inspections performed in RF- 11.1/VT-1

RF12 EVT- 6 Feedwater Sparger bracket sets.1/VT-1 1 Surveillance Holder bracket

4 Steam Dryer Support brackets1 Guide Rod Bracket2 Jet Pump riser braces (Jet Pumps 7, 8,9, & 10)No indication of cracking identified.

RF13 EVT- No inspections performed in RF-13.1/VT-I

RF14 EVT- 3 Feedwater Sparger bracket sets.(10/10) 1/VT-1 2 Core Spray Piping Brackets

1 Surveillance Holder bracket4 Steam Dryer Support brackets1 Guide Rod Bracket2 Jet Pump riser braces (Jet Pumps 1/ 2,and 11/12)No indication of cracking identified.

LPCI Coupling N/A N/A Fermi does not have a LPCI Coupling

Shroud Head RF04 UT/VT 16 had indications, 17 replaced duringBolts/Shroud Head RF04.

RF05 Remaining bolts replaced (3 1) duringRF05 as a preventative measure. All48 are now new style.

RF06 VT-3 Bolts 1-24 (of 48). No indication ofcracking.

RF07 VT-3 Bolts 25-48 (of 48). No indication of

61

Page 63: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

cracking or damage. Springs were leftcompressed on 20 of the 24 inspected.

RF08 VT-3 Bolts 1-24 (of 48). No indication ofcracking or damage

RF09 VT-3 Bolts 23 and 25-48 (of 48). Noindication of cracking or damage. Allretainer springs verified to befunctioning properly.

RF1O VT-3 Bolts 1-24 (of 48). Inspected North1/3 rd of Shroud Head/Separator and 2

lifting lugs. No indication of crackingor damage

RF1I1 VT-3 Inspected Bolts 25-48 (of 48) andinspected Center 1/ 3rd of ShroudHead/Separators. No indication ofcracking or damage.

RF12 VT-3 Bolts 1-24 (of 48). Inspected South

1 /3 rd of Shroud Head/Separator and 2lifting lugs. All mid support ringgussets were inspected and small shortcracks were identified on 3 of the 24gussets. No repairs were required.Ref. OE 25795.

RF13 VT-3 Bolts 25-48 (of 48). Inspected North

1 /3 rd of Shroud Head/Separator and 2

lifting lugs. No changes identified inprevious indications identified in RF12.No other indications identified.

RF14 VT-3 Bolts 1-24, 27, 30, & 33 (of 48).(10/10) Inspected Center 1/3"d of Shroud

Head/Separator. No changes identifiedin previous indications and no newindications identified.

Steam Dryer RF09 VT-3 Inspected approximately 1/3 of dryer(RFO1-RF-08 not including hood welds and cover platepreviously reported) welds. (Ref. SIL 644) No indications

of additional cracking identified.

RFIO VT-1/VT- Inspected approximately 50% of dryer

62

Page 64: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

3 including all inner hood vertical weldsas recommended in SIL 644,Supplement 1, and Revision 1).Several new indications were identifiednear welds due to new locations beinginspected and the change in technique.Indications were noted at base of innerhood vertical welds. Reference CARD04-25416 and also OE #17600. Nochanges were identified on previouslyrecorded indications.

RF 1I VT-1/VT- Inspected approximately 50% of dryer3 including all inner hood vertical welds

as reconmmended in SIL 644, Revision1 and BWRVIP-139. Several newindications were identified near weldsdue to new locations being inspectedand the change in technique.Indications previously noted on hoodwelds in RF10 were reinspected and nochanges were noticed.

RF12 VT-i/VT- Inspected approximately 50% of dryer3 including inner hood vertical welds as

recommended in BWRVIP- 139.Several new small indications wereidentified near welds due to newlocations being inspected and thechange in technique and camera anglesused. Indications previously noted onhood welds were reinspected and nochanges were noticed.

RF 13 VT-I/VT- Inspected approximately 20% of dryer3 including "F" Bank welds and a

sampling of other locations followingreinspection guidelines contained inNRC SE to BWRVIP-139. One newindication identified in support ring.

RF14 VT-i/VT- Inspected approximately 20% of dryer(10/10) 3 including "E" Bank welds and a

sampling of other locations followingreinspection guidelines contained inBWRVIP-139-A. No new indications

63

Page 65: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

identified.4-

Dissimilar MetalWelds BWRVIP-75-A (Not previouslyreported, referenceBWRVIP letter2008-089)

RF-12

RF-13

RF-14(10/10)

UT

UT

UT

Performed ultrasonic examinations on4 Category B DM welds that containalloy 82/182 using automated PDIqualified techniques and procedures.Since >90% coverage was not obtainedon two welds, 2 additional welds wereselected and >90% volume coveragewas obtained. No indications ofcracking identified.

Performed ultrasonic examinations on5 Category B DM welds that containalloy 82/182 using automated andmanual PDI qualified techniques andprocedures. No indications of crackingidentified.

Performed ultrasonic examination of 1Category B DM weld that containedalloy 82/182 using manual PDIqualified technique and procedure. Noindications of cracking identified.

*VT-2 leakage inspections have been and are performed on all RPV InstrumentationNozzles and Piping Nozzles each refuel outage. An enhanced leakage inspection isperformed on all locations to ensure no pressure boundary leakage. Inspections areperformed in the annulus area adjacent to the vessel skirt, and are perforned under vesselto ensure that any leakage identified is not from welded connections. Flange leakagefrom CRDM's is recorded, evaluated, and repaired if necessary. Mirror insulation isopened for SLC safe end inspection and for bottom head inspections but is not removedfrom other locations unless the leakage source can't be determined.

Fermi 2 Refueling Outages

RFO 1:RF02:RF03:RF04:RF05:RF06:RF07:RF08:RF09:RF 10:

Fall of 1989Spring of 199109-21-92 10-31-9205-10-94 09-21-9409-30-96 11-04-9609-08-98 10-08-9804-03-00 05-04-0010-15-01 11-20-0103-28-03 04-28-0311-06-04 11-26-04

Inspection sign on/off datesInspection sign on/off datesInspection sign on/off datesInspection sign on/off datesInspection sign on/off datesInspection sign on/off datesInspection sign on/off datesInspection sign on/off dates

64

Page 66: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF 11: 03-24-06 04-29-06 Inspection sign on/off datesRF12: 09-28-07 11- 01-07 Inspection sign on/off datesRF13: 03-28-09 04-16-09 Inspection sign on/off datesRF14: 10-25-10 11-22-11 Inspection sign on/off dates

65

Page 67: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Insnection History

Plant: James A. FitzPatrick Nuclear Power Plant

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Re-inspections

Core Shroud 1994 topresent

UT, EVT-1VT-3 ForShroud TieRods

EVT-1

94/95 Outage: Planar flaws on H2, 35"length intermittent (ID/OD) less than0.75" depth by UT; two small planarflaws on H3, 1.42" length (ID/OD) byUT. A calculated 136" of vertical weldwere inspected by EVT- 1 or UT with norelevant indications.96 Outage: Crack like indications on H2,55" length intermittent (OD) by EVT-1.This cracking is being mitigated by theshroud repair from 94/95 outage with 10tie-rods; vertical crack like indications onSV5A intermittent (OD) totaling 6-3/4"in length out of total 92", and twohorizontal ½/" each (one OD and one ID).Crack like indications were less than10% of weld length and are withinallowable per BWRVIP-07. Shroudinspections included 25% vertical weldswith 50% at beltline areas, and 3 tie-rods.A calculated 286" of vertical welds wereinspected. No relevant indications onother welds. Tie-rod assemblies werefound acceptable.

Baseline completed per BWRVIP-07Guidelines (by EVT-1) for all verticalwelds. 100% of beltline shroud weldsinspected in RO- 13. Relevant indicationsfound in 5 welds as follows:*SV5A OD-There are 6 indications witha combined length of 9.3 inches.*SV5B OD-There are 18 indications witha combined indication length of 45.8inches.*SV6A OD-There is 1 indication that ismeasured to be 1" long.*SV6B ID-There is 1 indication in the

Fall 1998(RO13)

66

Page 68: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2000 (RO14) 1EVT-1

weld which is measured to be 0.8 incheslong.*SH4 Indication-Indication is 3 inchesfrom SV5A ID and is 6 inches long andgoes across the SH4 horizontal weld.

No relevant indications noted on othervertical welds.

Re-inspected per BWRVIP-76Guidelines: Vertical Welds SV5A,SV5B, SV6A and SV6B. Relevantindications found in these welds are asfollows:*SV5A OD-There are 7 indications totalwith a combined indication length of11.7" vertical and 3.3" circ.*SV5B OD-There are 19 indications totalwith a combined indication length of50.7" vertical.*SV6A OD-There is one verticalindication that is measured to be 1" long.*SV6B ID-There is one verticalindication in the weld measured to be1.25" long.*SH4 ID-There is 2 vertical indicationsacross SH4 with total combined length of6.4". The closest indication is 3" fromSV5B. This indication is branching outnear the bottom portion.

Re-inspected by BWRVIP-76Guidelines: Vertical Welds SV2B,SV5B, and SV8A; and Radial RingWelds SV3A and SV3D. Relevantindications were only noted on the SV5Bweld, as follows:* SV5B ID and OD. There appears to

be no discernable changes this outageaffecting the cracks length fromRO 14; though one additionalindication is noted on the ID CCWside of the weld approximately '½"

long. This indication may beassociated with indications on theopposite side (OD) at the same

2002 (RO15) EVT-1

67

Page 69: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

location.

2004 (RO16)

2006 (RO17)

EVT-1

UT

EVT-1

EVT-1

Inspected Vertical Welds SV2A, SV8C,SV9A, SV9B and SV9C. No relevantindications noted.

Inspected Vertical Welds SV4A, SV4B,SV5A and SV5B. No relevant indicationsnoted for welds SV4A and SV4B. ForWelds SV5A and SV5B, there is closecorrelation of flaws from previously seenby EVT-1 in R14, with limited crackgrowth and no through wall indications.Identified some additional (shortintermittent) flaws at Weld SV5A. Allindications were satisfactorily disposition

Inspected Vertical and/or Radial WeldsSV3B, SV3E, SV6A, SV6B and SV8B.Previous indications were observed inWelds SV6A and SV6B with no apparentchange since R14.

Linear indications (<1/2" length) wereobserved in the upper section of theshroud where the slot was EDM'd for thetie-rod bracket support. The indicationsare located at 8 out of 10 tie-rodlocations. The indications weresatisfactorily disposition as having noeffect on the structural integrity of theload path between the shroud and the tie-rods for applied vertical or radial loads.

Inspected Vertical/Radial welds SV2B,SC3A, SV3C, SV3F, SV7B, SV7C andSV7E. Inspection included 100% ofaccessible area of the ID/OD. Norelevant indications were noted.

Re-inspected indications identified inRO- 17 on the shroud ring segment inlocations EDM'd for Tie Rod uppersupports. No change was noted fromRO 17 results.Inspected previously recorded flaw on

2008 (RO18) EVT-1

EVT-1

EVT-1

68

Page 70: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

the shroud ID @ SH4 near SV5B. Theinspection revealed no changes in sizeand configuration from the previousinspection in 2002. This inspection wasperformed per an INPO recommendationfrom the 2008 BWRVIP review visit toassist the industry in understanding theflaw mechanism-potentially irradiation -assisted corrosion cracking (IASCC).

Inspected Vertical/Radial welds SV2A,SV7A, SV7D, SV8A, SV8C, SV-9A,SV-9B and SV-9C. Inspection included100% of accessible area of the ID/OD.No relevant indications were noted.

2010 (RO19) EVT-1

I 4 4

Shroud Support 1992 to

present

1998 (RO13)

UT orEVT-1

EVT- 1VT-3

92 Outage: Inspected 0 and 180 degaccess covers by UT. One planarindication detected at 180 deg, which isbelieved to be inherent to the fabricationprocess and is not ID connected.94/95 Outage: Inspected 40" of H9 weldand accessible areas of 10 gusset platesused for tie-rod repair.96 Outage: Inspected access hole coverat 0 deg, and inspected 36" of H9 weldand gusset plate welds at 3 tie-rodlocations. No relevant indications noted.

Baseline completed per BWRVIP-07and BWRVIP-38 guidelines for allshroud repaired tie rods and loadtransfer gusset plate welds.*7 out of 10 tie rod assemblies inspected(by EVT-l/VT-3) in Fall 1998. Norelevant indications noted.*AHl load transfer gusset plate welds and12 inches of H9 weld each side of thegussets were examined by EVT-1. 7 outof 10 gussets inspected in RO13. Norelevant indications noted.

Examined by EVT-1 the access holecover at 180 degrees. No relevantindications noted.

69

Page 71: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2000/2002

2004 (RO 16)

2006 (RO17)

2008 (RO18)

2010 (RO19)

N/A

EVT-1

EVT-1

VT-I

N/A

VT-3EVT-1

EVT-1

No inspections during RO 14 and RO 15

Inspected two shroud support gussetplate welds and 12 inches of H9 top weldeach side of the gussets. No relevantindications noted.

Inspected all ten shroud repair tie-rodsystems and corresponding shroudsupport gusset welds at same locations.No relevant indications were noted.

Inspected top portion of horizontal weldH9 at each side of tie-rod locations andbetween gussets at 1800. No relevantindications were noted.

Inspected the access hole cover at 1800,

with no relevant indications noted.

No inspection performed in RO 18

Inspected (6) non-tie rod gussetslocations plate welds and H9 weld oneach side of the gusset at the samelocation. No relevant indications werenoted.

Inspected the access hole cover at 0 and1800. with no relevant indications noted

+ + + -

Core Spray Piping 1987 topresent

1998 (RO13)

VT-3,MVT- 1 orEVT-1

EVT-1,MVT-1

IEB 80-13 of piping and welds inannulus. One clamp repair in 1988 atcracked weld in "B" loop at 190 degbelow upper elbow piping. Welds werebrushed and inspected by EVT- I perBWRVIP-18 in Fall, 1996. No relevantindications found.

Re-inspected 100% of loop "A" and "B"welds per BWRVIP-i18 Guidelines (byEVT-1). No relevant indications noted,except for a rub-mark near CSA-10 weld.

Support brackets were examined byMVT-1. No relevant indications noted.

70

Page 72: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2000 (RO14) I EVT-l

2002(RO 15) EVT-1

2004 (RO16) 1 EVT-1

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds,including repair clamp welds perBWRVIP-18 Guidelines (by EVT-1).A relevant indication was noted on weldCSB-12. No other relevant indicationswere noted.

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds; repairclamp at Loop "B" downcomer pipe; androtating sample of pipe elbowupper/lower welds in Loop "A" at 10degrees. No relevant indications noted.

Re-inspected the indication noted inRO14 on weld CSB-12. Level Illsassessment is that the indication is nowbelieved to be a scratch.

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds; repairclamp welds at Loop "B" downcomerpipe; and rotating sample of pipe elbowupper/lower welds in Loop "A" at 170degrees. No relevant indications noted.

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds; repairclamp welds at Loop "B" downcomerpipe, and rotating sample of pipe elbowupper/lower welds in Loop "B" at 190degrees. Also, inspected all bracketsupport welds, including RPV side forLoop "A" and "B". No relevantindications noted.

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds; repairclamp welds at Loop "B" downcomerpipe; and rotating sample of pipe elbowupper/lower welds in Loop "B" at 350degrees. No relevant indications noted

Re-inspected all Loop "A" and "B"creviced and T-box-to-pipe welds; repair

2006(RO17) I EVT-1

2008 (RO18) 1EVT-1

2010 (RO19) IEVT-1

71

Page 73: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

clamp welds at Loop "B" downcomerpipe; and rotating sample of pipe elbowupper/lower welds in Loop "B" at 010degrees. No relevant indications noted

Core Spray Sparger 1987 topresent

1998 (RO13)

2000 (RO14)

VT-3,MVT-1 orEVT-1

EVT-1,MVT-1

2002 (RO15) EVT-1

IEB 80-13 of sparger and welds. MVT-1and EVT- 1 inspections per BWRVIP- 18in the Fall, 1996. An indicationcharacterized as weld profile deficiencywas recorded on spray nozzle D-28.Historical IVVI data was reviewed andthe indication was previously noted anddisposition as acceptable.

Re-inspected 100% of sparger piping"A" and "B" welds per BWRVIP- 18Guidelines (EVT- 1/MVT-1) includingtee boxes, end caps, drain welds, andsupport brackets. No relevant indicationsnoted.

No inspections performed

Re-inspected all T-box and end caps tosparger pipe welds at Loops "A", "B","C", and "D". No relevant indicationsnoted.

Re-inspected Sparger "C" and "D"nozzle welds, and supporting brackets at"A" and "B". No relevant indicationsnoted.

Re-inspected all sparger bracket supportwelds at "C" and "D". No relevantindications noted.

Re-inspected by EVT-1 all T-box andend caps to pipe welds, and by VT-1 allbracket welds at spargers "A", "B", "C"& "D". Re-inspected by VT-1 all nozzleand drain to sparger welds at spargers"A" & "B". No relevant indicationsnoted.

No inspections performed in RO 18

2004 (RO16)

2006 (RO17)

VT- 1

VT-I

EVT-1, andVT- 1

2008 (RO18) 1 N/A

72

Page 74: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2010 (RO19) EVT-1 Re-inspected by EVT-1 on all S1,S2 andS4, T-box and end caps to pipe welds,and by VT-1 all (SB) bracket welds atspargers "A", "B", "C" & "D". Re-inspected by VT-I all nozzle and drain tosparger welds at spargers "C" & "D". Norelevant indications noted.

Top Guide (Rim,etc.)

1988, 92 and VT-3, and94/95 EVT-1

1998 (RO13)

2000 (RO14)

2002 and2004

2006 (RO 17)

2008 (RO18)

N/A

VT- 1, andVT-3

N/A

VT- I andVT-3

VT-I

2 cells inspected in 1988 and in 1992; 4cells in 1994. Additional inspectionsincluded, alignment wedges, hold downbolts, and rim welds at several locations(EVT-1 at rim welds in 94/95). Norelevant indications noted.

No inspections performed

A total of 4 hold down assemblies wereexamined by VT-1 and 3 alignment pinassemblies by VT-3 per BWRVIP-26Guidelines. No relevant indications werenoted.No inspections in RO 15 and RO 16.

Inspected by VT-I hold-down assembliesat 0 and 180 degrees (top only as belowtop guide is inaccessible). Inspectedsampling of top guide surfaces by VT-1/VT-3. Also, inspected aligner pins at 0and 180 degrees by VT-1. No relevantindications noted.

Inspected by VT- 1 hold-down assembliesat 90 and 270 degrees (top only as belowtop guide is inaccessible). Also,inspected aligner pins at 90 and 270degrees by VT- 1. No relevant indicationsnoted.

Inspected by EVT-1 (8) grid beam celllocations, including plates andintersection locations as specified perBWRVIP-183. No relevant indicationsnoted.

2010 (RO19) I EVT-1

Core Plate (Rim, etc.) 1 1992 and 94 1 VT-3 I Inspection at one core plate in 1992.

73

Page 75: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

1998 (RO13)

2000 (RO14)

2002 (RO 15)

2004 (RO16)

VT-3

VT-3

VT-3

2006 (RO17) VT-3

Inspected approximately 25% of holddown bolting in 1994/95. No relevantindications noted.

Inspected 100% of hold down bolting.No relevant indications noted.

Inspected core plate plugs at 5 corelocations. No relevant indications noted.

No inspections performed

Inspected a total of 6 core plate plugs (attwo locations). No relevant indicationsnoted.Inspected core plate plugs and thesurrounding core plate surface at fourLPRM locations. No relevant indicationsnoted.

Inspected 33 core plate hold down boltassemblies from 0-180 degrees with noindications noted.

Inspected 10 core plate plugs @ celllocation 12-37, 28-29 and 36-37 to meet10% sampling requirements. Noindication noted, all plugs inspected wereproperly seated, with no evidence ofmovement.

Inspected a total of 8 core plate plugs @cell locations 28-21 and 28-37. Norelevant indications noted.

2008 (RO18) VT-1

VT-1

VT-I2010 (RO19)

SLC 2000 (RO13)

2002/2004

EVT-2

EVT-2

Performed Enhanced VT-2 on SLCnozzle-to-safe end weld during RPVSystem Leakage Test per BWRVIP-27Guidelines. Test was "Accepted".

Performed Enhanced VT-2 on SLCnozzle-to-safe end weld during RPVSystem Leakage Test per BWRVIP-27Guidelines. Test was "Accepted".

Performed liquid penetrant examinationon SLC nozzle-to-safe end weld per

2006 (RO17) PT

74

Page 76: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

BWRVIP-27 Guidelines with norecordable indications noted.

2008 (RO18) N/A No Examination required based on 2006inspection.

2010 (RO19) PT Performed liquid penetrant examinationon SLC nozzle-to-safe end weld perBWRVIP-27 Guidelines with norecordable indications noted.

Jet Pump Assembly 1987 to1994

1998 (RO13)

2000 (RO14)

2002 (RO15)

VT-i,VT-3and UT

MVT-1,and VT-3

N/A

EVT-1,VT- 1, andVT-3

Inspected all riser brace attachmentwelds by VT-1. No relevant indicationsbut found debris at some weld locations.Have replaced all jet pump beams in1992 because one exhibited indicationsof cracking by UT exam. Also inspectedpump assembly, sensing lines, supportsand diffuser to shelf welds, all by visual.No relevant indications but found debrisat some weld locations.Cracking at a Japanese BWR of a JetPump riser weld prompted FitzPatrick toreview IVVI tapes from previousrefueling outages, including 1996 outage.Viewed accessible areas at two welds byVT-1, and at three welds by VT-3examination. No cracking was found inthe reviewed welds.

Inspected by MVT-1 50% of all JetPumps (#7 to # 16) for component safetypriority H (high) and M (medium), perBWRVIP-41 Guidelines. No relevantindications noted. Interferences in thearnulus region restricted inspection ofAD-1 and AD-3b welds.

Inspected by VT-3 sensing lines/bracketsat same jet pumps (#7 to #16). Norelevant indications noted.

No inspections during RO 14

Completed inspection of Jet Pumps 5 and6, and portions of Jet Pumps 19 and 20,with no relevant indications noted. Used

75

Page 77: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

inspections guidelines of BWRVIP-41and 48. There are no MX-1 welds on theinlet-mixer, but there are IN-4 and MX-2welds. Interferences in the annulus region(gussets) prevented inspection of the AD-3b welds.

VT-I Inspected Jet Pump Beams at #5, 6, 19and 20, at locations recommended byBWRVIP-41, and by latestOperating Experience. No relevantindications noted.

2004 (RO 16) EVT- 1 Performed "High - priority" riser weldinspections at Jet Pumps #1, 2, 3, 4, 17and 18. No relevant indications noted.

Performed diffuser/adapter assemblyweld inspections (Also "High"- priority)at Jet Pumps # 17 and 18. No relevantindications noted.

VT-I Performed wedge bearing surface (WD-1) inspections at Jet Pumps # 17 and 18.No relevant indications noted.

2006 (RO 17) UT Inspected all twenty jet pump beams withno relevant indications recorded.

Inspected "High"- priority welds AD-1,AD-2, AD-3a, AD-3b, DF-2 and DF-3 atall 20 jet pumps (JP) with recordableindications at welds DF-2 (#JP I & 3)and AD-3b/DF-3 (#JP12 & 17). Allindications were satisfactorily dispositionfor one operating cycle.

EVT-1 Inspected "High"- priority welds DF-2 atJP #1 &3 and DF-3 at JP #17 based onUT results. No recordable indicationnoted.

EVT- 1 Inspected riser welds RS- 1, RS-2 andRS-3 at JP #19/20 & RS-3 at JP #03/04.Also inspected RS-6, RS-7, RS-8, RS-9and RB welds at JP #01/02, ¾, 17/18 &

76

Page 78: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

19/20 with no recordable indicationsnoted.

EVT-1 Inspected weld DF- l at JP #01/02, ¾,17/18 & 19/20 with no recordableindications noted.

VT-I Inspected wedge bearing surfaces (WD-1) at JP #1, 2, 3, 4, 19 & 20 with norelevant indications noted.

2008 (RO18) EVT-l Inspected "Medium - priority welds IN-4and MX-2 at JP # 1-4 & 17- 20 with norelevant indications noted.

EVT-1 Inspected wedge bearing surfaces (WD-1) at JP # 7-12 & 20 with no relevantindications noted.

VT-1/3 Inspected JP sensing line @ 1-4, 7-12and 17-20, including bracket andattachment welds to diffuser with norelevant indications noted.

EVT-1 Inspected the ID of JP 12 & 17 DF-3welds to aid in evaluating previousindications identified by UT in RO17. Noindications were noted visually from theID and surface geometry appears normalwith no undercut or root concavity noted.

2010 (RO19) EVT-1 Inspected RS-6, RS-7, RB welds at JP-7thru 16 with no recordable indicationsnoted.

EVT-1 Inspected RB-land 2, RB leaf to pad andPad to vessel welds @ JP-7 thru 16 withno relevant indications noted.

EVT-1 Inspected "Medium - priority welds IN-4, MX-2 and DF-1 at JP # 7-16 with norelevant indications noted.

EVT-1 Inspected RS-8 and 9 welds on all JetPump as required per VIP mandate. Norelevant indications were noted.

77

Page 79: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

EVT-1

UT

Inspected WD-1 on Jet Pumps 1-6, 13-20as required by VIP mandate with norelevant indications noted.

Inspected RS 1, 2, and 3 welds @ JPlocations 7-16 with no relevantindications noted.

Re-Inspected "High"- priority welds AD-1, AD-2, AD-3a, AD-3b, DF-2 and DF-3at all 20 jet pumps (JP) withWestinghouse JAMIS tool. Previousrecordable indications at welds AD-3b/DF-3 (#JP 12 & 17) were inspectedand found to have no change in size fromRI17. Previous indications at DF-2 (#JP 1& 3) were determined to be non-relevant.A new relevant indication was identifiedon JP # 8. All indications weresatisfactorily disposition and bounded byprevious evaluations.

CRD Guide Tube 1992

1998 (RO13)

2000 (RO14)

2002 (RO 15)

2004 (RO16)

2006 (RO17)

2008 (RO18)

VT-3

N/A

EVT-1 and,VT-3

EVT-1 andVT-3

N/A

EVT-1 andVT-3

N/A

Inspected stub tube to vessel and stubtube to housing welds for 9 tubes. Norelevant indications.

No inspections performed.

Inspected accessible surfaces at 3 GuideTubes per BWRVIP-47 Guidelines.Inspected accessible surfaces at 8 GuideTubes (VT-3). No relevant indicationsnoted.

Inspected accessible surfaces at 4 GuideTubes per BWRVIP-47 Guidelines. Norelevant indications noted.

No inspections performed.

Inspected accessible surfaces at threeGuide Tubes. No relevant indicationsnoted.

No Inspections performed

78

Page 80: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2010 (RO19) EVT-1 and Inspected CRGT-1, 2 and 3 accessibleVT-3 surfaces at 4 Guide Tubes per BWRVIP-

47A Guidelines. No relevant indicationsnoted.

CRD Stub Tube 1992 VT-3 See above.

1998 N/A No inspections during RO- 13.

2000/2002/ N/A No inspection requirements per/2004/2006/ BWRVIP-47 Guidelines.2008/2010

In-Core Housing 1992 VT-I No relevant indications.

1998 N/A No inspections during RO- 13.

2000 thru N/A No inspection requirements per2010 BWRVIP-47 Guidelines.

Dry Tube 1994

1998 (RO13)

2000 (RO14)

2002 (RO15)

2004 (RO 16)

2006 (RO17)

2008 (RO18)

VT-I

N/A

VT-I

VT-1

N/A

VT-I

VT-I

No indications. Replaced all dry tubes in1987/88.

No inspections performed.

Inspected 4 IRM/SRM In Core DryTubes per GE SIL-409 and GE RICSIL-073 Guidelines. No relevant indicationsnoted.Re-inspected SRM Core Dry Tube 20-17per GE SIL 409 and GE RICSIL-073Guidelines. No relevant indications noted

No inspections performed.

Inspected dry tubes at three locationswith no relevant indications noted.

Inspected dry tubes at SRM locations 20-17, 28-41 and IRM location 20-25 perGE-SIL-409 Rev.2 with no relevantindications noted.

Inspected dry tubes at SRM locations 36-25 and IRM location 12-33, 28-33, 36-09and 12-09 per GE-SIL-409 Rev.2 with norelevant indications noted

2010(RO19) VT-1

79

Page 81: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

InstrumentPenetrations

1992

1998(RO13)

2000(RO14)

2002/2004/2006/2008/2010(RO15-19)

VT-I

N/A

VT-2

VT-2

Two inspected in 1992. No relevantindications noted.

No inspections performed.

Performed VT-2 ISI System LeakageExam Test at 6 instrument nozzles(during RPV System Test) per BWRVIP-49 Guidelines. Test was conducted to theextent possible with insulation installedand shield doors closed. Test was"Accepted".

Performed a VT-2 leakage test at 6instrument nozzles (same as in R014-Fall 2000). Test was "Accepted" with noleakage noted.

______________ - + +

Vessel ID Brackets 1987 topresent

VT-1,VT-3,EVT-l forcore spray

1998 (RO13) MVT-1

2000 (RO14)

2002 (RO 15)

N/A

EVT-l

Section XI inspections of jet pump riserbrace, dryer, feedwater sparger, corespray, and surveillance capsule holderbrackets, performed once per interval.Last inspection was Fall, 96 VT-3, orVT-I if in beltline region. EVT-1 forcore spray. No relevant indications noted.

Inspected Core Spray Brackets and JetPump Riser Brace Attachments perBWRVIP-48 requirements. No relevantindications noted.

No inspections in R014

Inspected Jet Pump Riser Brace (at JP#5/6 and # 19/20); and Feedwater SpargerBracket Attachments (at all 8-locations),per BWRVIP-48 requirements. Norelevant indications noted.

Inspected shroud support gusset platewelds to RPV wall at two locations, withno relevant indications.

Inspected all four steam dryer supportbrackets and attachment welds to RPVwall, with no relevant indications.

2004 (RO16) EVT-I

EVT-1,VT-3

80

Page 82: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3 Inspected all four steam dryer hold-downbrackets and attachment welds to RPVtop head, with no relevant indicationsnoted.

Inspected guide rod and bracket to RPVweld at 1800, with no relevant indicationsnoted.

2006 (RO17) EVT-1 Inspected all core spray piping supportbracket welds to RPV wall, with norecordable indications noted.

Inspected shroud support gusset platewelds to RPV wall at ten locations, withno relevant indications noted.

Inspected riser brace leaf welds to RPVwall at JP #01/02, ¾, 17/18 & 19/20,with no recordable indications noted.

VT-I Inspected surveillance sample holderbrackets upper and lower) at 0300 and1200 to RPV wall, with no relevantindications noted.

VT-3 Inspected guide rod and bracket to RPVweld at 0000, with no recordableindications noted.

2008 (RO 18) N/A No inspections performed

2010 (RO 19) EVT- 1 Inspected shroud support gusset platewelds to RPV wall at six locations, withno relevant indications noted

Inspected riser brace leaf welds to RPVwall at JP #7-16, with no recordableindications noted

Inspected all feedwater support bracketsand attachment welds to RPV wall, withno relevant indications

LPCI Coupling I N/A I N/A I Not applicable to this plant.

81

Page 83: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Fuel SupportCastings

1998 (RO13)

2000 (RO14)

r T

VT-3

VT-3

2002 (RO15) 1 VT-3

Inspected accessible areas at fuel supportcastings during in-process control rodblade change-out. No relevantindications noted.

Inspected accessible areas at fuel supportcastings during in-process control rodblade change-out. No relevant indicationsnoted.

Inspected accessible areas at four fuelsupport castings during in-processcontrol rod blade change-out. No relevantindications noted.

No inspections performed

Inspected accessible areas at fuel supportcastings at four locations. No relevantindications noted.

No Inspections perfonred

No Inspections performed

2004 (RO16)

2006 (RO 17)

2008 (RO18)

2010 (RO19)

VT-3

VT-3

N/A

N/A

CRD Nozzle NIR 1998 (RO13)

2000 (RO14)

2002-2008

2010 (RO19)

VT-I

EVT-1

N/A

EVT-1

The Control Rod Drive Nozzle InnerRadius was examined. No relevantindications noted.

Examined the CRD Nozzle Inner Radius,including adjacent vessel wall area. Norelevant indications noted.

No inspections in RO15 - RO18.

Examined the CRD Nozzle Inner Radius,including adjacent vessel wall area. Norelevant indications noted.

82

Page 84: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Steam DryerMoisture Separator

1998 (R0O3)

2000 (R014)

2002 (ROI15)

2004 (R0 16)

2006 (R0 17)

VT-3

VT-3 andEVT-1

N/A

VT- I andVT-3

VT-3

VT- I

Inspected 25% of shroud head bolts atstorage pit. No relevant indicationsnoted.

Re-inspected by VT-3 all areas of thesteam dryer support ring and by EVT-1previously found cracks (1992/1994). Atotal of 10 indications were noted in 2000(RO14), with no discernable changesfrom previous inspection.

No Inspections performed

Inspected steam dryer integrity per SIL644 Supplement 1 (steam dryer integrity)and INPO OE 18796 (steam dryer hoodcrack and tie bar recordable visualindications) guidelines. Two relevantindications areas were noted. Theseindications resulted in expanded scopewith additional brushing and evaluations.These indications are in the HAZ ofvibration block welds and at a drainchannel. All indications weresatisfactorily dispositions by calculations.Plans are to re-inspect the indications inR017.

Inspected steam dryer hold-downs andsupport brackets and attachment weldswith no relevant indications noted.

Inspected steam separator lifting rod eyeassemblies, and 25% of shroud headbolts with no relevant indications noted.

Inspected selected welds on the steamdryer (per requirements of BWRVIP- 139over those recommended by SIL 644). Arelevant indication was noted at theintersection of H-2 and V-7 welds (SWquadrant), and the weld was grind outand repaired in R17.

Inspected previous relevant indicationsnoted in R16 (i.e., at eight vibration

83

Page 85: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

block welds and at weld adjacent to drainchannel weld #8) with no observedchange noted since R16. The linearindication length at one vibration blockwas re-configured from the previous R 16reporting.

2008 (RO18) VT-I Inspected previous relevant indications(i.e., at eight vibration block welds and atweld adjacent to drain channel weld #8)with no changed to indication size noted.

Inspected R17 weld repair @ weld H2 &V7 intersection in SW quadrant with norelevant indications noted.

Inspected upper support ring includingprevious indications noted in R14. 9 ofthe 10 previous indications have beendetermined to be scratches and areconsider non relevant. No otherindications were noted.

VT-3 Inspected Shroud head bolts #10 thnm 19based on with no relevant indicationsnoted.

VT-I Inspected 25% of upper and mid-supportring gussets on the moisture separatorbased on recent OE25795. A linearindication was noted on the # 5 uppergusset. Scope was expanded to includeall upper and mid support ring gussetsand linear indication were also identifiedon gusset # 6 upper and mid gussets. Theindication were evaluated and foundacceptable.

Additionally during the gussetexamination a broker tie strap was notedon the separator @ 0 degrees. The brokenstrap was removed per EC- 10523 andevaluated for acceptance. Note: OE27679was issued to inform the industry of thecondition.

2010 (RO19) VT- 1 Inspected previous relevant indications

84

Page 86: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

(i.e., at eight vibration block welds and atweld adjacent to drain channel weld #8)with no changed to indication size noted.

Inspected R17 weld repair @ weld H2 &V7 intersection in SW quadrant with norelevant indications noted.

Re-examined previous identified uppermid support gusset @ locations 5 and 6with no change noted in size noted.

Re-examined previously identifiedbroken tie strap renmant @ 0 with norelevant condition noted

Inspected Shroud head bolts #29 thru 36based on OE 31414 with no relevantindications noted.

VT-I andI. 4 4

Surveillance CapsuleSpecimen Holder

Lower Plenum

Feedwater Sparger

2000 (RO 14)

2006 (RO 17)

2008 (RO18)2010 (RO19)

2000 (RO14)

2002-2008

VT-1 andVT-3

VT-1

N/A

VT- 1/3

Inspected at one location, the upper andlower mounting bracket (VT-1) and thecondition of the specimen holder (VT-3)No relevant indications noted.

Inspected upper and lower mountingbracket welds at 0300 and 120'. Norecordable indications noted.

No inspections performed

Inspected by VT-3 accessible areas oflower plenum per BWRVIP-47Guidelines. No relevant indicationsnoted. Inspected by VT-1 accessibleareas of bottom head drain. Afterremoval of debris the area was re-examined and found acceptable.

No access

Inspected Sparger pipe assembly at 45,135, 225 and 315 degrees azimuth,sparger welds and end brackets. Norelevant indications noted.

Inspected Junction T-box welds andNozzle hIner Radius (NIR) at 45, 135,

2002 (RO15) 1 VT-3

VT-I

85

Page 87: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2004 & 2006

2008 (RO18)

UT

N/A

VT 1/3

225 and 315 degrees azimuth. Norelevant indications noted.

Inspected the NIR at all 4-locations. Norelevant indications noted.

No inspections performed

Inspected sparger brackets @ 45,135,225and 315 degrees based on recentOE24382 for wear being identified.Brackets @ 45 and 135 were noted tohave some wear noted around the pin.The condition was evaluated and foundacceptable.

Inspected Sparger pipe assembly at 45,135, 225 and 315 degrees azimuth,sparger welds and end brackets. Norelevant indications noted.

Inspected Junction T-box welds andNozzle Inner Radius (NIR) Inspected theNIR at all 4-locations. No relevantindications noted.

Re-examined sparger brackets @ 45 and135 deg. for wear noted in R18. Nochange was noted.

2010(RO19) 1VT-3

VT-3

VT- 1

Dissimilar Metalwelds

2004 (RO16) UT

2006 (RO17) 1 UT

Perforned UT on DM welds 24-10-131and 24-10-132 and nozzle N-9-C1overlay with no relevant indicationsnoted.

Performed UT on Nozzle to Safe End onthe following welds with no relevantindications noted.N-lB-SEN-2H-SEN-2K-SE

Performed UT on the Nozzle to Safe Endon the following welds with no relevantindications.N-lA-SEN-2A-SEN-2B-SE

2008 (RO18) UT

86

Page 88: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

N-2D-SEN-2E-SEN-2F-SEN-2G-SEN-2J-SEN-5A-SEN-8A-SEN-8B-SE

Performed UT on Nozzle N-2C-SE andidentified one axial indication approx ½/"depth by 34 wide. The indication waslocated on the butter to butter and was IDconnected. Assumed the flaw to beIGSCC. The weld was overlaid andfound acceptable.

Performed UT on CRD return Cut andcap overlay with no relevant indicationnoted

Re-examined N-2C-SE overlay from RI 8with no relevant indication noted.

Scheduled 12 ru windows for cleaningand FOSAR MsDection in annulus.

2010 (RO19)

2008/2010

UT

UT

N/AFOSAR Examination

FOSAR Examination

87

Page 89: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Hope Creek

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud Winter 1996 VT-I Examined H-4, H-5 at 4 cell locations.RF06 1 mil No indications found IAW SIL 572 RI

Fall 1997 UT Examined 100% accessible regions ofRF07 H-3,4,5,7. No indications found

Fall 2007 UT Examined 100% accessible regions ofRF14 H-3,4,5,7. Achieved 60.1 to 62.8%

coverage. Found 5 indications in H4, allless than 2 inches length, less than 15%

thru wall, 2.1% of examined length.Found 1 indication in upper side H5, 4.3inches in length, depth 1I%, 1.1% ofexamined length. Use as is for 10 yearsIAW VIP-76.

Shroud Support Spring 1994 VT-3 Examined 6 shroud support pillar IAWRF06 Sec. XI. No indications found

Fall 1997 VT3 Examined accessible portions of H-8RF07 and H-9. No indications

EVT-1 Examined access hole covers. Noindications.

Spring 2003 UT >10% of H-8/H-9 from the Vessel OD.RF1 I No indications

EVT-1 Examined access hole covers. Noindications.

Spring 2006 EVT-1 Examined access hole covers. NoRF13 indications.

Spring 2009 EVT-1 Examined access hole covers. NoRF15 indications.

Fall 2010 VT-3 Examined annulus surface. No issuesR16 or FME found.

Core Spray Piping Winter 1996 VT-I Piping and welds in annulus examined

88

Page 90: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF06

Fall 1997RF07

Spring 1999RF08

Spring 2000RF09

Fall 2001RF10

Spring 2003RFll

Fall 2004RF12

Spring 2006RF13

Fall 2007RF14

Spring 2009RF15

EVT-1

VT-I

EVT-1

VT-l &3

EVT-1

VT-1 &3

EVT-1

VT-l &3

EVT-1

EVT-1 &VT-3

EVT-1

EVT-1 &VT-3

EVT-1

EVT-1 &VT-3

UT &EVT-1EVT-1 &VT-3

EVT-l

IAW IEB 80-13. One indication foundon a bracket bolt tack weld.

Examined all creviced and non-crevicedweld locations, no indicationsExamined all (8) header brackets, nonew indications.

Examined all creviced and 25% non-creviced locations, no indications.Examined 25% header brackets, no newindications.

Examined all creviced weld locations,no indications.Examined 25% header brackets, noindications.

Examined all creviced and 25% non-creviced locations, no indications.Examined 25% header brackets, noindications.

Examined all creviced weld locations,no indications.Examined 25% header brackets, noindications.

Examined all creviced and 25% non-creviced locations, no indications.Examined 25% header brackets, no newindications.

Examined all creviced weld locations,no indicationsExamined 25% header brackets, noindications.

Examined all creviced and 100% non-creviced locations, no indications.Examined 25% header brackets, no newindications.

Examined all locations that could not beUT examined in the previous outage, noindications.

89

Page 91: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

EVT-I & Examined 25% header brackets. NoVT-3 indications.

Fall 2010 EVT-I Examined all creviced weld locations,R16 no indications

EVT-1 & Examined 25% header brackets, noVT-3 indications.

Core Spray Sparger Winter 1996 VT-I Piping and spargers in shroud examinedRF06 IAW IEB 80-13. No indications.

Spring 1999 EVT-1 All sparger welds, no indications.RF08 VT-1 50% nozzle welds and all bracket

welds, no indications.

Fall 2001 EVT-1 All sparger welds, no indications.RF1O VT-1 50% nozzle welds and all bracket

welds, no indications.

Fall 2004 EVT-1 All sparger welds, no indications.RF12 VT-1 50% nozzle welds and all bracket

welds, no indications.

Fall 2007 EVT-1 All sparger welds, no indications.RF14 VT-1 50% nozzle welds and all bracket

welds, no indications.

Fall 2010 EVT-l All sparger welds, no indications.R16 VT-1 50% nozzle welds and all bracket

welds, no indications.

Top Guide (Rim, Fall 1992/ VT-1 Examined lAW SIL 554. Examined 4etc.) Spring 1994/ cell locations made available during

Winter 1996 normal refuel. No indications.

Winter 1996 VT-3 Examined Top Guide wedges IAW SILRF06 588 RI. No indications.

Fall 1997 VT-I Examined lAW SIL 554. Examined 4RF07 cell locations made available during

normal refuel. No indications.

Spring 1999 VT-3 Examined 4 C-clamps, no indications.RF08

Spring 2009 EVT-1 Examined 4 top guide grid beamRF 15 locations. No indications.

90

Page 92: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

VT-3 Examined 4 C-clamps, no indications

Fall 2010 EVT-1 Examined 4 top guide grid beamR16 locations. No indications.

Core Plate (Rim, etc.) Fall 1997 VT-3 Examined all hold down bolts, noRF07 indications.

Spring 1999 VT-3 Examined 26 hold down bolts, noRF08 indications.

Jet Pump Assembly Spring 1994RF05

Winter 1996RF06

Fall 1997RF07

Spring 1999RF08

Spring 2000RF09

Fall 2001RF10

VT- 1

VT-3

VT-1

VT-3

VT-1

VT-I

VT-3VT-3

EVT-1

EVT-1VT- 1VT-3

EVT-1

VT-1VT-3

VT-1VT-3

50% riser braces, RB-1/2 & RS-8/9, noindications100% wedges and setscrews JAW SIL574. 3 screws with I tack cracked

50% riser braces, RB-1/2 & RS-8/9, noindications100% wedges and setscrews. 4 screwswith 1 tack cracked, 2 screws with 2tacks cracked

50% riser braces (RB-1/2 & RS-8/9),100% RS-1, no indications100% sensing lines. Three pumps havecracked standoffs, installed clamps.100% beams, no indications100% wedges and setscrews. 1 screwwith 1 tack cracked

50% riser brace(RB-1/2 & RS-8/9), noindications100% RS-1, no indications100% sensing lines, no indications100% beams, 100% wedges andsetscrews, no indications

50% riser brace (RB-1/2 & RS-8/9), noindications100% sensing lines, no indications100% wedges and setscrews, noindications

100% sensing lines, no indications100% wedges

91

Page 93: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Spring 2003RFlI

Fall 2004RF12

Spring 2006RF13

Fall 2007RF 14

Spring 2009RF15

Fall 2010R16

VT-iEVT-I

VT-i

UTVT-iEVT-1

VT-1VT-i

EVT-1

VT-1

VT-1VT-1

UT

VT-1VT-3

VT-1VT-3

EVT-1

EVT-1

VT-1VT-3

100% wedges, no movement noted100% RS-3, 50% RS-2, 50% RS6/750% IN-4, 50% MX-2, 50% DF-1/2,50% AD 1/2, 50%, no indications50% sensing lines, no indications

100% beams, BB 1/2, no indications50% sensing lines, no indications25% RS-1, 50% RS-2, 50% IN-4, 50%MX-2, 50% DF-1/2, 50% AD 1/2, 50%RS-6/7, no indications

50% sensing lines, no indications100% wedges, one had minor wedgewear, installed slip joint clamp25% RB-1/2, 25% RS-8/9, noindications

100% wedges, one had minor wedgewear and SS setscrew gap of 35 mil,installed auxiliary wedge1 slip joint clamp, no issues7 setscrew tack welds previouslyidentified with cracks. One setscrewfound with all tacks cracked. Stakedsetscrew, use as is one cycle withoutauxiliary wedge.100% beams, BB1/2, no indications

100% wedges, no wear found.Slip joint clamp and aux wedge. Noissue found.11 sensing lines. No indications.Installed aux wedge for an issue foundprevious outage.50% RS3, no indications.

100% RS-8/9 and 25% RS-6/7. Noindications50% wedges. No new wear found.3 sensing line clamps and 1 aux wedge.No issue found.

CRD Guide Tube Winter 1996 VT-3 Examined 6 guide tubes JAW Sec. XI.

RF06 No indications

Spring 1999 VT-3/1 Examined 4 guide tubes, no indications

92

Page 94: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

RF08

Spring 2003 VT-3/1 Examined 6 guide tubes no indicationsRF1l

Fall 2004 VT-3/1 Examined 10 guide tubes, noRF 12 indications

Fall 2007 VT-I Examined 5 guide tubes, no indicationsRF 14

CRD Stub Tube Spring 94 VT-3 Examined IAW Sec XI. Examined CRDRF05 Housing through removed jet pump

diffuser. No indications.

In-Core Housing Notexamined

Dry Tube Fall 1992 VT-I Examined IAW SIL 409. No indicationsRF04 found.

Spring 1999 EVT-1 All 12 dry tubes had circumferentialRF08 cracking approx 1 inch below the upper

collar

Spring 2000 Replaced all 12 dry tubesRF09

Instrument Fall 1997 VT-1 and Examine IAW Sec. XI, no indicationsPenetrations RF07 VT-3

Vessel ID Brackets Winter 1996 VT-1 50% jet pump riser bracket, noRF06 indications

Fall 1997 VT- I 100% core spray header bracket, 50%RF07 jet pump riser bracket, 100%

surveillance sample bracket, noindications.

VT-3 100% guide rod bracket, 100%feedwater bracket, 100% steam dryerholddown bracket, no indications

Spring 1999 VT- 1 25% core spray header bracket, 100%RF08 feedwater sparger bracket, 100% steam

dryer support bracket, no indications.EVT-1 50% jet pump riser bracket, no

indicationsVT-3 100% guide rod bracket, no indications

93

Page 95: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Spring 2000RF09

Fall 2001RF10

Spring 2003RFII

Fall 2004RF12

Spring 2006RF13

Fall 2007RF14

Spring 2009RF15

Fall 2010R16

VT-1

EVT-1

VT-I

VT-3

EVT-1

EVT-1

VT-3

EVT-1

VT-I

VT-3

EVT- 1

EVT-1EVT-1 &VT-I

EVT- 1VT-I

25% core spray header bracket, noindications50% jet pump riser bracket, noindications

25% core spray header bracket, noindications100% guide rods, no indications

25% core spray header bracket, noindications

25% core spray header bracket, 100%steam dryer support bracket, 100%feedwater sparger bracket, noindications found.100% guide rod bracket, no indicationsfound.

25% core spray header bracket, 25% jetpump riser bracket, no indications100% surveillance sample bracket, noindications100% steam dryer holddown bracket, noindications

25% core spray header brackets

25% core spray header brackets.100% feedwater brackets. Found minorpin wear on 2 pins. Evaluation justifiedoperation for one cycle.

25% core spray header brackets.2 Feedwater bracket pins where wearpreviously found. No discernablechange.

LPCI Coupling Fall 2001 EVT-1 Examined 50% couplings, noRFIO VT- I indications

VT-3

Spring 2003 EVT-l Examined 50% couplings, noRF 1I VT- I indications

VT-3

94

Page 96: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Spring 2006 EVT-1 Examined 50% couplings, noRF13 VT- I indications

VT-3

Steam Dryer Fall 1997RF07

Spring 1999RF08

Spring 2000RF09

Fall 2001RF10

Spring 2003RF 1I

Fall 2004RF 12

Spring 2006RF13

VT-I

VT-IVT-I

VT-I

VT-I

VT-I

VT-I

EVT-iEVT-1VT-IVT-3VT-I

VT-I

VT-I

VT-I

VT-i

100% support ring, one indicationidentified on face, 2.25"

100% drain channels, no indicationsRe-look at previous support ringindication, no growth

100% support ring, no new indications,no growth on previous indication

100% drain channels, one indicationidentified on skirt below a seismic lugaccess plate weld, 0.75"100% support ring, no new indications,no growth on previous indication

100% support ring, no new indications,no growth on previous indicationRe-look at skirt indication, no growthManway coverplate100% coverplates100% tie bars100% lifting lug braces, one foundsevered.

100% support ring, no growth onprevious indication, new indicationidentified; 0.625" across top, and 0.75"down face.Outlet plenum plate welds-betweenbanks B&C and D&E, outer hood weldsat hood stiffener, outer hood welds attop, 100% drain channels, inner hoodwelds at hood stiffener, no indications.

Previously identified indications onsupport ring, no growth found.100% hood assembly welds (exteriorsurfaces only), 100% tie bars, 100%lifting assembly welds, 100% coverplate welds. 4 locations had IGSCCtype indications. Two indications wereabove a construction (original) repair

95

Page 97: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Fall 2007RF14

Spring 2009RF15

Fall 2010R16

VT-I

VT-I

VT-i

patch on hood C with a combinedlength of 4". Another was on the outletplenum plate between banks A&B nearbottom, 1.25". Adjacent to the coverplate on the support ring a 5" indicationwas identified. On a lifting rod twoindications were found on the threadsnear a tack weld. No repairs weremade.

5 locations with previously foundindications. No crack growth found.

Re-baseline IAW BWRVIP-139 and allprevious indications inspectedfollowing EPU implementation. Onenew IGSCC flaw found on the supportring. Previous flaws on a lifting lugtack weld were found joined. Onecreator crack found on a lifting rodbracket weld. All indications wereevaluated for use as is. No repairsrequired.

2 nd re-baseline IAW BWRVIP-139following EPU implementation. Onenew ISGCC flaw found on lifting rodthreads near the tack weld. Indicationwas evaluated for use-as-is. No repairwas made.

4 4 4

RPV DM nozzlewelds

Fall 2007RF14

Spring 2009RF15

UT

UT

Examined N2A, category C, automatedUT. Found an 89.8% thru wallcircumferential flaw and performed aweld-overlay repair. Expanded scope toexamine N9, category C, manual UTand N2D, category C, automated UT.No indications found. Weld crownsground flush for all three examinations.All three nozzles contain Alloy 82/182weld material.

Examined 8 category C welds withautomated UT after weld crownreduction. Found embedded flaws on 3welds, not ID surface connected.Evaluated IAW ASME section XI. No

96

Page 98: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

repair required.

Fall 2010 UT Examined 5 category C welds afterR 16 weld crown reduction; 2 by auto, 3 by

manual. No indications found.

97

Page 99: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Oyster Creek Generating Station

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Steam Dryer Fall 2010 Visual Re-inspected Steam Dryer indicationsand repair areas identified duringprevious outages and evaluated due to nochange to use-as-is for one cycle.

Fall 2008 Visual Completed BWRVIP-139 requiredinspections of the ID of the dryer usingGEH FireFly ROV. Identified 2 areas offatigue cracking in drain channels and 1area of fatigue cracking in support beamto mid-support ring weld. Evaluated asuse-as-is for one cycle in accordancewith BWRVIP-139 generic flaw

evaluation.

Re-inspected Steam Dryer indicationsand repair areas identified duringprevious outages. Tie bar N-I lowerrepair area was found degraded and GEHissued JCO for one cycle of operation.

Fall 2006 Visual Re-inspect Steam Dryer Indications

identified during previous outages.

EVT-1 cracks in hold-down area from1R19.

VT-I all 4 lifting lugs and EVT-1

indications on 135 deg. lug.

BWRVIP-139 required inspections (topside) completed. New fatigue indicationswere identified that required repair.Dryer repair project completed with 2areas stop drilled and one crack in centerbaffle plate was cut out.

Core Shroud Fall 2010 VT-3 VT-3 of 2 Tie-Rods at 10 and 70 deg.

98

Page 100: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Locations (#2 and #8). No findings.

Fall 2008 UT / EVT- 1 UT / EVT- 1 inspection completed for all10 shroud vertical welds. One indicationfound with UT in V10 weld - 1.76 incheslong with depth of 0.47 inches. Atechnical evaluation was completed touse-as-is.

VT-3 Tie-Rods at 100 deg, 130 deg, 160deg, 280 deg, and 350 deg. No findings.

Fall 2006 EVT-1 V-9 inspection of ID and OD. Twohorizontal indications (transverse to theweld) were found adjacent to verticalweld on the ID surface. The indicationswere 2.75 and 1 inch in length and 30and 35 inches above horizontal weld H5.A technical evaluation was completed touse-as-is.

VT-3 Tie-Rods at 170 deg, 220 deg and310 deg. No findings.VT-I of Upper Bracket to Shroud Ledgeinterface on all 10 Tie Rods. No findings.

Fall 2004 None No Examinations Required.

Fall 2002 None No Examinations Required.

Fall 2000 EVT-1 V-3, V-4, V-15 and V-16. This was aone sided exam from the OD. Nofindings.

Fall 1998 UT V-7, V-8, V-10 and V-12.EVT-1 V-1I I.D. Seven tie-rod assemblies

baseline inspected.

V-10 exhibited minor OD cracking awayfrom the heat-affected zone. Thiscracking is believed to be associated withhandling lugs that were welded duringconstruction and removed afterinstallation. All other inspected verticalwelds were found free of indications.With the inspections performed in 16R

99

Page 101: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

and 17R, all accessible vertical welds inthe shroud core region are complete.

The following vertical welds could not belocated. V-3, V-4, V-15 and V-16.

Fall 1996 Visual Inspected per BWRVIP-07. Three of tentie rods inspected, no change frominstallation. EVT-1, OD of V-9 and V-11, (120" total). V-9 exhibited 3 smallaxial cracks in HAZ on the OD totaling1.75". The ID of V-9 was free of axialcracks. A number of small transversecracks were found on the OD and ID ofV-9. V-II was free of any indications.Analysis showed structural marginmaintained.

Fall 1994 Ultrasonic Inspected per BWRVIP-0 1 and 03.and visual Cracks were detected in the Shroud

welds H2, H4, H6A, and H6B. Lack offuision was detected in H3 weld andvisual cracks on the ID surface.The Tie Rod modification was installed.Base line visual performed of the tierods.

Shroud Support Fall 2010 Visual EVT-1 of 6 of the 36 Lug / Clevis pinassemblies - # 1, #2, #7, #8, #20 and #21.No findings.

Fall 2008 Visual EVT-l of 8 Lug / Clevis pin assemblies -#10, #11, #14, #15, #17, #29, #30, and#36. No findings.

Fall 2006 Visual EVT-1 of 7 Lug / Clevis pin assemblies -#1, #18, #19, #23, #24, #32 and #33.

Fall 2004 None No examinations required.

Fall 2002 UT 30% UT of H-9 from the OD (Drywell).UT inspected H-9 weld in Nozzle N I A,N 1C and N 1E bioshield openings.Found one 4" long indication in the NIEnozzle area. This "service induced"indication is in the bottom side of the H9weld and does not penetrate into the base

100

Page 102: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

metal of the RPV.

Fall 2000 Visual 25% of H-9, cleaning performed andEVT- 1 inspection completed. Thiscompletes 100% inspection of the H-9weld. No findings.

Fall 1998 Visual 25% of H-9, cleaning performed andenhanced VT- 1, no findings

Fall 1996 Visual 25% of H-9, (different area then the 1994inspection), cleaning performed andenhanced VT-i, no findings.

Fall 1994 Visual 25% of H-9 cleaning performed andenchanted VT- 1, no findings.

Core Spray Piping Fall 2010 Visual EVT-1 of annulus piping fillet welds (all10). No findings.

EVT-1 of 25% shroud attachment welds -Pipe Bracket PB 285 deg. No findings.

EVT-1 of 25% sample butt welds: P4aA,P4g/aA, P3aC, P3bC, P4dC, P4eC, P4fC,P4aB, P3aD, and P3bD. No findings.

Fall 2008 Visual EVT-1 of annulus piping fillet welds (all10). No findings.

EVT-1 of 25% shroud attachment welds -Pipe Bracket PB 195 deg. No findings.

EVT-1 of 25% sample butt welds: P3aA,

P3bA, P2B, P4dD, P4eD, P4fD, P4gD,P4hD, P3aB, P3bB, and P4dB. Nofindings.

Fall 2006 Visual EVT-1 of anmulus piping fillet welds (all10). No findings.

EVT- 1 of 25% shroud attachment welds -Pipe Bracket PB 103.5 deg. No findings.

EVT-1 of 25% sample butt welds: P4bA,P4cA, P2A, P4g/aA, P4g/bA, P4hA,P4iC, P4g/aC, P4g/bC, P4hC, P4bB,

101

Page 103: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

P4eB, P4fB, P4gB and P4hB. Nofindings.

Fall 2004 Visual Accessible portions of the annulus pipingwelds were cleaned using a nylon brushand visual inspections performedutilizing the EVT-1 technique. Allaccessible portions of the followingpiping welds were visually inspected:

* L-3, L-3A, L-4, L-20A, L-13A,L-5, L-7, L-8, L-10, L-1 1, and L-12

• U-3, U-3A, U-4, U-15A, U-24A,U-7, U-8, U-9, U-10, U-11, U-12,U-16 and U-17

100% of annulus pipe brackets at 150,105', 195' and 2850. No findings.EVT-1 of all creviced welds in theannulus piping = U3, U3A, U4, UI5A +U24A; L3, L3A, L4, L13A + L20A.

Fall 2002 Visual EVT-1 of a 25% sample (11 welds) ofthe butt welds (non-creviced) notinspected in 17R or 18R:

* UI,U15,U17,U18,U19,U20* L1,L9,L13,L16,L20

Inspect 100% of anmulus pipe brackets(15', 105', 195' and 2850)No Findings.

Fall 2000 Visual Accessible portions of the annulus pipingwelds were cleaned using a nylon brushand visual inspections performedutilizing the EVT-1 technique. Allaccessible portions of the followingpiping welds were visually inspected:

* L3,L3A,L4,L6,Ll3A,L14,L15and L20A

• U3, U3A, U4, U7, U8 and Ul5A100% of annulus pipe brackets 15', 10501950 and 285'. No findings.

Fall 1998 Visual All creviced welds in the annulus piping;

sample (25%) of the non-creviced weldsin the annulus piping:

102

Page 104: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

" L2,L9,LlO,L11,L12,L13,L17,L18, L19 and L20

" U2,U5,U6,U13,U14,U15,U21, U22, U23 and U24

Sample (25%) of pipe brackets 2850,1950

Fall 1996 Visual Inspected per BWRVIP- 03. Cleaning ofall accessible weld/HAZ surface andperformed enhanced VT-1. No findings.

Fall 1994 Visual and Inspected VT-1, (1 mil wire). No changeair test to pinhole weld defect detected in slip

joint in 1992. Note: Pinhole weld defectdetected in 1992 in System I. Analysisshowed structural margin maintained.

Core Spray Sparger Fall 2010 Visual EVT- 1 Sparger Pipe End Cap welds $4C- 62 deg., $4C - 238 deg., S4D - 62 deg.,and S4D - 238 deg. No findings.

EVT- 1 "T" box cover plate welds - S I C,$2C (LH), $2C (RH), SID, S2D (LH)and S2D (RH). No findings.

VT-i spray nozzles - S3a, S3b, $3c - C

and D (CASS). No findings.

VT- I of 50% of the sparger bracketwelds - SB-026 deg., SB-091 deg., SB-120 deg., SB-179 deg., SB-245 deg., SB-300 deg., and SB-359 deg. No findings.

Fall 2008 Visual EVT-1 Sparger Pipe End Cap welds:S4A - 60 deg., S4A - 240 deg., S4B - 60deg., S4B - 240 deg. No findings.

EVT-1 "T" box welds - S1A, S2A (LH),S2A (RH), S1B, S2B (LH) and S2B(RH). No findings.

VT-I spray nozzles - S3a, S3b, S3c-C.No findings.

VT- 1 of 50% of the sparger bracketwelds - SB - 055, 065, 150, 208, 235,271 and 330 deg. No findings.

103

Page 105: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Fall 2006 Visual EVT-1 Sparger Pipe End Cap welds S4C- 60 deg., S4C - 240 deg., S4D - 60 deg.,and S4D - 240 deg. No findings.

EVT-1 "T" box welds - SIC, S2C (LH),S2C (RH), SID, S2D (LH) and S2D(RH). No findings.

VT-I spray nozzles - S3a, S3b, S3c-B.No findings.

VT-I of 50% of the sparger bracketwelds - SB- 026, 091, 120, 179, 240,300, and 359 deg. No findings.

Fall 2004 Visual Inspected all sparger repair clamps. Nofindings.Inspected end cap welds $4A-60, $4A-240, S4B-60, and S4B-240. No findings.Inspected sparger brackets SB-055, 065,150, 208, 235, 271 and 330. No findings

Fall 2002 Visual and VT-I all spargers, nozzles, end cap weldsAir Test and repair clamps. No findings.

No new leaks were identified during theAir Test.

Fall 2000 Visual and All sparger end cap welds were cleanedAir Test and EVT-1 inspected. No findings.

VT- I of spargers, repair clamps, andnozzles. No findings.

No new leaks were identified during theAir Test.

Fall 1998 Visual and All sparger repair clamps, both spargers.Air Test

Fall 1996 Visual and Inspected per BWRVIP-03. Cleaned endair test cap welds and performed enhanced VT-

1. No findings. Tee box welds areclamped and not accessible to clean orvisual. Performed VT-i, (1 mil wire), of

sparger piping and nozzles. No findings.

Fall 1994 Visual and Performed VT-i, (1 mil wire) of sparger

104

Page 106: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Air Test piping and nozzles. No findings.

1978 - 1980 Visual (2) Cracks in sparger piping. Repairclamps installed.Note: Cracking found in sparger in1978; repaired with clamps. Sparger hasbeen inspected and air tested everyoutage since then; report submitted toNRC for approval for restart everyoutage.

Top Guide Fall 2010 Visual EVT- 1 Inspection and Measurement of 3Cracks in Grid Beams (#4, VT-3 & VT-6). Some crack growth was observed.Flaw evaluation completed to support useas is.

BWRVIP-183: Inspect 5% = 7 cells. Nofindings.

Fall 2008 None Not required for this outage by analysis.

Fall 2006 Visual EVT-l of selected known flaws in gridbeams: #4, VT-3 and VT-6. One areashowed no growth, while the other twohad grown between 0.25" and 0.75" fromthe 2002 outage to the 2006 outage. Aflaw evaluation was performed to use-as-is.

Fall 2004 Visual VT-I of top guide hold down bolts at 303and 123 degrees. No findings.EVT-1 of VT-6 crack showed nomeasurable growth. Could not visuallylocate two other existing UT indications.

Fall 2002 Visual EVT-1 of two existing cracks measuredin 18R outage (#3 and #5). No change tocrack length identified.

Fall 2000 Visual Top guide hold down bolt assemblyVT-3 at 330 and 2130.Top guide beam to rim fillet welds VT-Iat 330 and 2130. No findings.

VT- I of two existing cracks (#3 and #5)

105

Page 107: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

with cleaning. Both cracks measured onboth sides. Crack #5 showed approx. 1"growth. Crack #3 showed no measurablegrowth.

Fall 1998 None. Not required for this outage by analysis.

Fall 1996 Ultrasonic 12 indications emanating from notches100% grid detected at intersections of crossbeams members. 5 of the 6 cracks on bottom

side of member at mid span detected.Removed sample from beam with crackto investigate root case.

Fall 1994 Visual [Under side of Top Guide] Threeadditional vertical cracks were detectedat mid span locations. Disposition use asis.

Fall 1992 Visual [Under side of Top Guide] Twoadditional vertical cracks were detectedat mid span location. Disposition use asis.

Fall 1991 Visual [Under side of Top Guide] A verticalcrack was detected at mid span location.Disposition use as is.

Core Plate Fall 2010 Visual VT-1 inspected 3 In-core guide tubeplugs 28-45, 44-13 and 44-21. Nofindings.

Fall 2008 Visual Visually inspected core plate wedges at96' and 2760 azimuths. No findings.

Fall 2006 None No exams were required.

Fall 2004 Visual No wedge inspections required.Inspected in-core guide tube plugs 04-29,20-37, and 12-21. No findings.

Fall 2002 Visual No inspections needed. Wedges replace

hold down bolt inspections.

Fall 2000 Visual Visually inspected all 8 wedges to verifyintegrity after first cycle of operation.All wedges found as installed.

106

Page 108: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Fall 1998

Fall 1996

Fall 1994

Visual

Visual

Visual

Wedges installed. No further exams ofcore plate were performed.

Inspected top portion only of 18 holddown bolt that were not inspected in fall1994 and top periphery section at boltlocations. No findings.

Inspected 18 hold down bolt tops onlyand top periphery at bolt locationsinspected. No findings.

Jet Pump Assembly NA NA NA

Jet Pump Diffuser NA NA NA

SLC Fall 2010

Fall 2008

Fall 2006

Fall 2004

Fall 2002

Fall 2000

Fall 1998

Fall 1996

Fall 1994

VT-2pressure test

VT-2pressure test

UT

VT-2pressure test

Visual / PT

VT-2pressure test

VT-2 durinngCodepressure test.

NoInspectionPerformed.

NoInsmection

Inspected insulated nozzle from drywell.No leakage observed.

Inspected insulated nozzle from drywell.No leakage observed.

PDI - UT the Liquid Poison Nozzle N12 /SE. No findings.

Inspected insulated nozzle from drywell.No leakage observed.

PT of Liquid Poison Nozzle - NoIndications. Inspect insulated nozzlefrom drywell during RPV pressure test.No leakage observed.

Inspected insulated nozzle from drywell.No leakage observed.

Not made accessible for direct exam.

Not made accessible.

Not made accessible.

107

Page 109: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Performed

CRD Guide Tube Fall 2010

Fall 2008

Fall 2006

Fall 2004

Fall 2002

Fall 2000

Fall 1998

Fall 1996

Fall 1994

EVT- 1, VT-3

None

EVT- 1,VT-3

EVT-1, VT-3

EVT-1, VT-3

VT- 1, VT-3

VT-3

NoinspectionPerformed.

NoInspectionPerformed

Inspected 2 guide tubes. Inspected 2guide tube bases for CASS (VT-1).No findings.

Not required and not made accessible.

Inspected 4 guide tubes. No findings.

Inspected 4 guide tubes. No Findings.

Inspect 1 guide tube (46-43) removed tosupport stub tube inspection. Nofindings.

2 guide tubes. No findings.

15, no findings.

Not made accessible.

Not made accessible.

CRD Stub Tube Fall 2010

Fall 2008

Fall 2006

Fall 2004

None.

None.

None.

None

VT-IFall 2002

Fall 2000

No inspections required.

No inspections required.

No inspections required.

No inspections required.

Visual Inspection of 2 stub tubes foundleaking at bottom head in Fall 2000(42-43 and 46-39). No indications noted.

None made accessible.2 stub tubes found leaking at bottomhead (42-43 and 46-39). Performed UTof CRD housing to stub tube welds (Jweld) and area of housing to be rolled.

VT-1VT-2pressure test

108

Page 110: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

No indications. Roll repaired bothleaking housings.

Fall 1998 No Not made accessible.Fall 1996 inspection

Performed.

Fall 1994 No Not made accessible.InspectionPerformed

In-Core Housing Fall 2010 No Not made accessible.InspectionPerformed

Fall 2008 No Not made accessible.inspectionperformed.

Fall 2006 No Not made accessible.inspectionperformed.

Fall 2004 No Not made accessible.inspectionperformed.

Fall 2002 No Not made accessible.inspectionperformed.

Fall 2000 No Not made accessible.Fall 1998 inspectionFall 1996 performed.Fall 1994

Dry Tube Fall 2010 Replacement Replaced final 4 Dry tubes due to servicelife: IRM-15 and 16; SRM 22 and 23.

Fall 2008 Replacement Replaced 4 Dry tubes due to service life:IRM-12, 13, 14 and SRM-21.

Fall 2006 Replacement Replaced 4 Dry tubes due to service life:IRM- 11, 17, 18 and SRM-24.

Fall 2004 Visual VT- 1 of SRM 24 found tube not fullyengaged in top guide. VT- I of IRM 17

109

Page 111: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Fall 2002

Fall 2000

Fall 1998

Fall 1996

Fall 1994

Visual

Visual

Visual

Visual

Visual

and IRM 18 found both tubes bowed.

No inspections required.

VT-I five dry tubes. One found slightlybent - use as is. No findings on others.

VT-I one dry tube, no findings

VT-I one dry tube, no findings.

VT-I four dry tubes, no findings.

Instrument Fall 2010 Visual VT-2 exam from vessel exterior.Penetrations Fall 2008 No findings.

Fall 2006Fall 2004Fall 2002Fall 2000Fall 1998Fall 1996Fall 1994

Vessel ID Brackets Fall 2010 EVT-l EVT-l all feedwater sparger attachmentwall bracket welds. No findings.

Fall 2008 None No inspection required.

Fall 2006 EVT-1 EVT-1 both Guide Rod Brackets.EVT-1 all 3 Surv. Spec. Brackets.

No findings.

Fall 2004 EVT- 1 Inspected all 4 dryer support brackets.No findings.

Fall 2002 EVT-l All feedwater sparger attachmentbrackets.Both guide rod attachment brackets.All surveillance sample brackets (30, 210and 300 degree locations)No indications on attachment welds.

Fall 2000 EVT-1 All 4 dryer support brackets. Observedwear indications on brackets. No

indications on attachment welds.All feedwater attachment bracketsinspected. No indications on attachment

110

Page 112: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

welds.Cracks observed on feedwater sparger toend bracket welds (non-safety-relatedcomponent) on 2 ends.

Fall 1998 VT-I VT-I of accessible portions of weld onFall 1996 guide rod brackets, steam dryer brackets,Fall 1994 surveillance sample brackets. All

attachment welds; no findings.

LPCI Coupling NA NA NA

Fuel Support Casting Fall 2010 Visual VT-I inspection of 2 CRGT Bases(support castings) for CASS program.No findings.

Fall 2008 None No inspection required.

Fall 2006 Visual None inspected.

Fall 2004 Visual None inspected.

Fall 2002 Visual None inspected.

Fall 2000 Visual VT-3 (2) support casting. No findings.

Fall 1998 Visual VT-3 (24) support castings. No findings.

Fall 1996 Visual VT-3 (25) support castings. No findings.

Fall 1994 Visual VT-3 (17) support castings. No findings.

Reactor DM Welds Fall 2010 UT - Auto UT examined four (4) Category C nozzle

(BWRVIP-75-A) to safe end dissimilar metal (DM) weldscontaining alloy 82/182. No findings.

Fall 2008 UT - Auto UT examined five (5) Category C nozzleto safe end dissimilar metal (DM) welds.One indication identified in NIArecirculation suction nozzle to safe endweld dispositioned as acceptable for 2cycles in accordance with IWB-3600flaw evaluation. The 0.21 inch IDconnected indication was in the RPVnozzle to clad interface on the Reactorside of the Alloy 182 DM weld. Theflaw evaluation was submitted to theNRC.

III

Page 113: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Note: All indications left "as is" were analyzed and structural margins were acceptablefor continued service.

112

Page 114: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Reactor Internals Inspection History

Plant: Peach Bottom Atomic Power Station. Unit 2

Components in Date or Inspection Summarize the Following Information:BWRVIP Scope Frequency of Method Inspection Results, Repairs,

Inspection Used Replacements, Reinspections

Core Shroud 1994

1996

2002

UT & VT

UT

UT

Comprehensive UT Baseline of someCategory "C" circumferential welds(H-2, H-3, H-4, and H-5) per BWRVIP-01, Rev. 0.Partial UT baseline of welds H-1, H-6,and H-7, w/ partial EnhancedVT-1 of H-6 OD.Exams per BWR-VIP Core Shroud NDEUncertainty and Procedure Standard,dated November 21, 1994.Indications identified on ID of H-1, H-3,H-4, and H-6, and OD of H-4 and H-5.Full structural margins calculated usingtwo cycles of crack growth forcomprehensively examined welds, onecycle for welds with limited exams.No indications identified on H-2 and H-7.

Comprehensive UT of welds H-1, H-6and H-7 per BWRVIP-01, Rev. 1.Exams per BWRVIP-03.Indications identified on ID of welds H-I,H-6 and H-7, on OD of weldH-1.Full structural margins calculated usingtwo cycles of crack growth.

Reexaminations planned per BWRVIP-76

Comprehensive UT of welds H-1 throughH-7 per BWRVIP-76.Indications identified on each weld.UT of Vertical welds V-I through V-4.No indications identified.Reexaminations scheduled per BWRVIP-76.

Shroud Support 1992 VT-3 VT-3 examination of support leg stubwelds.

113

Page 115: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

No indications identified.VT-3 examination of welds H-7, H-8, andshroud support cylinder.No indications identified.

1994 VT-3 VT-3 of accessible portions of H-8 weldbetween Jet Pump #1 and #10.No indications identified.

VT- I VT- I examination around perimeter of 0deg. access hole cover.No indications identified.

UT UT examination of both access holecovers. No indications identified.

1998 EVT-1 EVT-I examination of both AHCs. Noindications identified.EVT-1 of 10% of shroud support weld H-8, top side, no indications identified.EVT-1 of 10% of shroud support weld H-9, top side, no indications identified.

2000 EVT-1 EVT- I examination of both AHCs. Noindications identified.

VT-3 VT-3 of accessible portions of H-9 weldbetween 00 and 1800 Azimuth. Noindications identified.

2002 UT UT of 10% of H-9 weld length from ODof vessel. No indications identified.

2004 EVT-1 EVT- I of > 10% of shroud support weldH-8, top side, between jet pumps 10 - 11and 1 - 20. No indications identified.

VT-3 VT-3 of accessible portions of H-9 weld

between 180' and 360'. No indicationsidentified

2008 EVT-1 EVT- 1 examination of both AHCs. Noindications identified.

2010 EVT-l EVT-1 was performed on both AHCs, noindications indentified.

114

Page 116: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

EVT-1 of> 10% of shroud support weldH-8, top side, between jet pumps 10 - 11and I - 20. No indications identified.

UT BWRVIP-I180 baseline UT exams werecompleted on both AHCs. No indicationsidentified.

Core Spray Piping 1980 to 1996 VT-I Enhanced VT-I (1 mil resolution)(1 mil) performed on piping and welds each

refueling outage per IEB 80-13,No indications identified.

1996 VT-I EVT-1 (1/2 mil resolution) performed on(1/2 mil) annulus piping welds per BWRVIP-18.

Cracking identified in "B" Header tee-boxcover plate weld (P2B).UT perforned to characterize indication.Evaluation demonstrated structuralmargin for one operating cycle

1998 EVT-1 & Reinspection per BWRVIP- 18, using UTUT technique. EVT- 1 used to supplement UT.

No new indications identified. P2B weldreexamination yielded additional margin.

2000 EVT-1 EVT-1 of nine (9) piping welds notpreviously UT'd, and of six (6) pipebrackets and attachnment welds. Noindications identified.

2002 EVT-1 & Reinspection per BWRVIP- 18, using UTUT technique (28 welds). EVT-1 used to

supplement UT (6 welds). EVT-1 on two(2) support brackets.No new indications identified.P2B weld indication reexaminationrevealed minimal growth.

2004 EVT-1 EVT- 1 of twelve (12) piping welds notaccessible for UT inspection. Noindications identified

2006 EVT-1 & Reinspection per BWRVIP- 18, using UTUT technique (24 welds). EVT-1 used to

supplement all one-sided UT (12 welds).

115

Page 117: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

r r -r

EVT-1 only on eight (8) pipe welds andsix (6) support brackets.P2B weld indication reexaminationrevealed no growth. New 9/16" indicationidentified visually at intersection of P3B1and P2B welds. Structural and leakageevaluations found flaw acceptable forcontinued service.

2008 EVT-l Re-inspection per BWRVIP- 18, EVT- 1used on (21) pipe welds.P2B weld indication re-examinationrevealed no growth. The P3B 1 9/16"indication revealed no growth. Newindication (0.49") identified visually onthe upper side of P3B1 and P2B welds.Structural and leakage evaluations foundflaw acceptable for continued service.

2010 EVT-1 & Reinspection per BWRVIP-18, using UTUT technique (24 welds). Two sided UT

performed on selected P4 elbow welds.EVT-l used to supplement all one-sidedUT on T-box welds (8 welds). P2B weldindication reexamination revealed nogrowth. P3B1 indications identified somechange in measured size due to bettercleaning and exam video resolution..Structural and leakage evaluations foundflaw acceptable for continued service.

Core Spray Sparger 1980 to 1994 VT-i Enhanced VT-I (1 mil resolution)(1 mil) perforned on piping and welds each

refueling outage per IEB 80-13,Cracking discovered at tee-box to spargerpipe weld ("B" Sparger, 1982), boltedrepair clamp installed.No other indications identified.

1998 VT-3 & Reinspections per BWRVIP- 18, noMVT-l indications identified.

2000 EVT- 1 EVT- 1 of selected sparger welds perBWRVIP-18. No indications identified.

VT- 1 VT- I of sWarger tee-box repair clamp, and

116

Page 118: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

approx. 50% of sparger "C" and "D"nozzles and drains.VT- I of eleven (11) sparger brackets andwelds. No indications identified.

2002 VT- 1, VT- I of six (6) sparger support brackets,EVT-1 one (1) tee box repair clamp, and 50% of

sparger "A" and "B" nozzles and drains.EVT-l of seven (7) sparger pipe welds.No indications identified.

2004 VT- 1, VT-I of six (6) Sparger support bracketEVT-l welds, one (1) sparger drain, and 50% of

nozzles on spargers "C" and "D".EVT- 1 of fifteen (15) Sparger pipe welds.No indications identified.

2006 VT-1, VT-I of six (6) sparger support brackets,EVT-1 one (1) tee box repair clamp, and 50% of

sparger "A" and "B" nozzles and drains.EVT-1 of eight (8) sparger pipe welds.No indications identified.

2008 EVT- 1, VT- I of six (6) sparger support bracketsVT-1 and 50% of sparger "C" and "D" nozzles

and drains.EVT-1 often (10) sparger pipe welds.No indications identified.

2010 VT- 1, VT- 1 of six (6) sparger support brackets,EVT-l one (1) tee box repair clamp, and 50% of

sparger "A" and "B" nozzles and drains.EVT-1 of eight (8) sparger pipe welds.No indications identified.

Top Guide (Rim, etc.) 1976 to 1994 VT-3 VT-3 exam every other refuieling outageper Section XI. No indications identified.

1987 UT UT examination performed of specificcells.No indications identified.

1994 VT-3 Visual (VT-3) examination of 4 cells (48-41, 08-25, 24-17, and 24-25), per SIL554.No indications identified.

117

Page 119: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

1996 VT-3 Visual (VT-3) of 2 aligner pins (0 deg.And 270 deg.), per SIL 588.No indications identified.

Core Plate (Rim, etc.) 1996 VT-3 VT-3 examination of all accessible holddown bolts (cell 16-57, and area at 0 and270 deg. Azimuth.No indications identified.

2010 VT-3 VT-3 examination of 16 core plate plugs.No Indications identified.

SLC 1992 PT Surface (PT) examination of nozzle tosafe end weld per Section XI.No indications identified.

1998 PT & UT PT and UT of N10 nozzle to safe-end, noindications identified.

2002 PT Extended dwell time Liquid Penetrantexamination of entire safe end.No indications identified.

2006 PT Extended dwell time Liquid Penetrantexamination of entire safe end.No indications identified

2010 UT-E SLC Nozzle to safe end weld. Noindications identified.

Jet Pump Assembly 1976-1996 VT-3 Visual VT-3 of all jet pump componentsperformed every other refueling outage.

1981 VT & UT VT and UT examination performed on all20 hold down beams. No indicationsidentified.

1994 VT Restrainer bracket wedge misalignmentand wear identified on several wedges.Evaluations found condition acceptablewithout repair.One restrainer bracket set screw tack weldfound cracked. Evaluations foundcondition acceptable without repair.

1996 VT Restrainer bracket wedge conditions and

118

Page 120: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

set screw tack welds remain unchanged,condition acceptable without repair.

1998 MVT-1 MVT-1 of: RS-l weld on all 10 risers,RS-2 & RS-3 welds on 6 of 10 risers. Noindications identified.

UT UT of all 20 hold down beams. Noindications identified.

2000 EVT-1 EVT-l of adjusting screw tack weld (jetpump 7) and RS-2 & RS-3 on 5 of 10risers. No indications identified.

2002 EVT-1 EVT-1 of fifty (50) Medium priority weldlocations.EVT-l of transition region of two (2) holddown beams.No indications identified

2004 EVT-1 EVT-1 of forty one (41) medium prioritywelds, to complete 50% baselineinspections. No indications identified.

UT UT performed on all twenty (20) holddown beams(3 zones, BB-1, BB-2, and BB-3). Noindications identified.

VT-I VT-I on all twenty (20) Inlet Mixer mainwedges. Thirteen (13) jet pumps exhibitedadditional wear at main wedge-to-restrainer bracket interface. Performedexpanded scope of inspections on thesejet pumps. Set screw gaps identified atfive (5) jet pumps. No additionalproblems identified. Installed eight (8)slip joint clamps and three (3) set screwauxiliary spring wedges, to mitigate wearbelieved to be caused by vibration.

2006 VT-1, VT-1 of twenty (20) WD-1 locations.EVT-1, EVT-1 of five (5) IN-4 welds, and two (2)VT-3 riser braces-to-vessel attachment welds.

VT-3 of eight (8) Slip Joint Clamps andthree (3) Auxiliary Spring Wedges.

119

Page 121: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

Expanded EVT-1 scope on three (3) jetpumps due to WD-1 findings.

2008 UT UT exams performed on all 20 jet pumphold down beams. No indicationsidentified.

VT-3 Visual inspections performed on 5auxiliary spring wedges installed. Noindications identified.

EVT- 1 EVT- 1 of 50 medium and high prioritywelds including; riser brace leaf to yokewelds, riser pipe to riser brace welds, riserelbow to thermal sleeve, and riser elbowto riser pipe welds. No indicationsidentified.

Expanded EVT-l scope on one jet pumpdue to WD-1 findings.

VT- I VT- I of twenty (20) WD- 1 locations. Re-examined previously identified wedgewear with no apparent changes noted on19 of 20 inspections. One main wedgehad additional wear into the restrainerbracket. BWRVIP 41 expanded scopeinspections were performed with noadditional indications identified. OneSlip joint clamp was installed on theaffected Jet Pump.

2010 VT-3 VT-3 of two slip joint clamps. Noindications identified

VT-I VT-1 of all twenty (2) JP main wedges.No new/additional wear identified.VT-1 of all JP set screws for gaps. Minorgaps identified on seven JPs. Five (5)accepted for continued service byengineering analysis. Two (2) werecorrected by tapping down on the mainwedge.

EVT-1 EVT-1 of 37 medium and high prioritywelds including; riser brace leaf to yoke

120

Page 122: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

welds, riser pipe to riser brace welds, riserelbow to thermal sleeve, and riser elbowto riser pipe welds. No indicationsidentified.

Completed BWRVIP Letter 2009-202required inspections.

t * I.

Jet Pump Diffuser 1998

2000

2002

2004

2006

2010

MVT-1

EVT-l

EVT-l

EVT-l

UT

EVT-l

MVT-I of: AD-1 & AD-2 welds on 12 of20 pumps, AD-3A & B welds on 11 of 20pumps, and DF-2 weld on 10 of 20pumps. No indications identified.

EVT-1 of AD-1, -2, -3a, -3b, and DF-2 onjet pumps 1 through 10. No indicationsidentified.

EVT-1 often (10) High priority weldlocations.No indications identified.

EVT- 1 of eleven (11) medium priorityweld locations, to complete 50% baselineinspections.No indications identified

UT of ninety eight (98) Diffuser / Adapterwelds and six (6) Inlet Mixer welds. One2" indication found on DF-2 weld, JP 17.Structural and leakage evaluations foundindication acceptable for continuedservice.

EVT-1 of JP 17 DF-2 weld from the ID tolook for any visual indication of the flawidentified by UT in 2006. 100% coverageof the ID was achieved, no indication wasidentified.

CRD Guide Tube 1992 VT-3 VT-3 examination of housings accessiblefrom fuel cells 26-31 and 30-27. Noindications identified

2002 EVT-1, EVT-1 of three (3) welds on each oftenVT-3 (10) Guide Tubes (locations 50-31, 42-11,

42-23, 42-51, 38-27, 38-35, 38-51, 34-23,34-39, and 30-31). Some flow

121

Page 123: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2006

2008

2010

EVT-1,VT-3

EVT-1

EVT- 1

interference with examinations.VT-3 equivalent of anti-rotation pin onten (10) Guide Tube locations.No indications identified

EVT- I of fifteen (15) CRGT welds, VT-3of five (5) CRGT welds, verification ofseventeen (17) CRGT alignment pins.One slightly bent pin identified. Pinremains functional. Condition foundacceptable. No other indicationsidentified.

EVT-l of nine (9) CRGT welds. Noindication identified. Also, verification ofeight (8) CRGT welds and (8) CRGTalignment pins.

EVT-I of four (4) CRGT welds. Noindications identified.

All BWRVIP-47 baseline examinationshave been completed.

CRD Stub Tube 1992 VT-3 VT-3 examination of stub tube weldsaccessible from fuel cells 26-31 and 30-27.No indications identified.

In-Core Housing 1992 VT-3 VT-3 examination of housings accessiblefrom fuel cells 26-31 and 30-27.No indications identified.

Dry Tube 1984 All Dry Tubes replaced in 1984

1994 VT-1 VT-1 examination of IRM Dry Tube2D, at core location 37-32.

1997 N/A All IRM and SRM tubes replaced w/Wide Range Monitoring tubes in1997. No inspections required.

Instrument 1976 to PT PT examination performed on allPenetrations present instrument nozzle to safe end

welds once per interval, perSection XI.

No indications identified.

122

Page 124: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

LPCI CouvlinR N/A for this DlantLPC Cupin N/ o hspan

Vessel ID Brackets 1976 to VT-I or VT-I and VT-3 of all ID bracket weldspresent VT-3 performed once per interval per ASME

Section XI. No indications identified.

2000 EVT-1 EVT-1 of six (6) Core Spray pipingbrackets. No indications identified.

2002 EVT-1 EVT- 1 of two (2) Core Spray pipingbrackets, two (2) Steam Dryer supportbrackets, and five (5) Jet Pump Riserbrackets attachment welds.No indications identified.

2004 EVT-1 EVT-1 of two (2) Steam Dryer supportbrackets and three (3) Jet Pump riserbrace attachment welds.

VT-3 VT-3 of four (4) Steam Dryer hold downbrackets and three (3) lower surveillancebrackets. No indications identified.

2006 EVT-1, EVT-1 / VT-3 of twelve (12) FeedwaterVT-3, VT- Sparger attachment bracket welds.1 EVT-1 / VT-I of two (2) Jet Pump riser

brace-to-vessel welds.No indications identified.Minor anomalies incidentally identifiedon several FW Sparger bracket pins.

2008 VT-3 VT-3 of 5 Feedwater Sparger endbrackets and attachment pins

EVT-1 EVT- 1 of 2 Core Spray bracketattachment welds

Steam Dryer 2002 VT-1, VT-I of all drain channel welds. VT-I ofVT-3 upper and lower dryer bank tie bar welds

and baffle plate welds. VT-3 of dryerbank end and top covers, and instrumenttubing and supports.

One (1) central bank upper tie barsevered, and one (1) instrument tube

123

Page 125: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

support-to-baffle plate broken. Broken tiebar and instrument tube removed fromdryer. New, stiffer tie bars welded tocentral dryer banks.

2004 VT-I VT-I of five (5) replaced central bankupper tie bars, ten (10) original bankupper tie bars, and outer bank hoods @internal reinforcing plates and end platewelds, per SIL 644, Supp. 1.No indications identified.

2006 VT-I Completed all remaining BWRVIP-139recommended inspections on seventy four(74) locations. One small indication(7/16") identified at base of drain channelvertical weld. No other indicationsidentified.

2008 VT- 1 Re-examined small indication (7/16")identified at base of drain channel verticalweld. No change noted. No otherindications identified.

2010 VT- I Re-examination of small (7/16")indication at base of drain channelvertical weld. No change noted.BWRVIP- 139-A re-examination of (six)key high stress (red) locations and five (5)tie bars. No indications identified.Examination of all four (4) lifting lugs.Indications identified on anti-rotation tackwelds. Accepted continued service byengineering evaluation.

Steam Separator 2006 VT- 1 VT-1 examinations performed on asample of upper and lower shroud headbolt support ring gussets. 12 of 24 lowerring gussets revealed degradation. Noindications on upper support ring gussets.Indications acceptable for continuedservice.

2008 VT-I VT- I examinations performed on asample of upper and re-examination of alllower shroud head bolt support ring

124

Page 126: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

2010 VT-I

gussets. 5 of 12 lower ring gussets withpreviously identified degradation hadfurther crack growth and 4 lower gussetshad new indications not previouslyidentified. No indications were observedon the upper support ring gussets. AllIndications are acceptable for continuedservice.

VT-I examinations performed on asample of upper and re-examination of alllower shroud head bolt support ringgussets. Slight growth at one previouslyidentified indication. New indicationidentified on six (6) gussets. All newindications were minor and acceptable forcontinued service. Wear identified onone (1) shroud head bolt pin/window.SHB was removed.

+ *1

Dissimilar MetalWelds(BWRVIP-75-A)

2008

2010

UT-E

UT-E

Performed Manual UT on three (3)IGSCC Category D, dissimilar metalwelds, all containing alloy 82/182material. One indication identified onweld 2-AS-1 (Recirc Suction, NIA,Nozzle to Safe-end). Indication was notID connected and determined to be afabrication flaw after comparison toconstruction radiographs. Indication wasfound acceptable, no further analysis orrepairs required.

Performed Manual UT of three (3)IGSCC Category D, dissimilar metalwelds, all containing alloy 82/182material. No indications were identified.

125

Page 127: II~l ELECTRIC POWER · Plant Page 1. Browns Ferry Nuclear Plant: Unit 1 3 2. Dresden 3 14 3. Duane Arnold Energy Center 30 4. Fenni 2 41 5. James A. FitzPatrick Nuclear Power Plant

126