Inception report Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods in Northern Pakistan
Citation preview
Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods in Northern Pakistan
INCEPTION REPORT
Adaptation Fund ProjectClimate Change Section, Ministry of National Disaster Management,
Government of Pakistanand
United Nations Development Programme - Pakistan
November 15-17, 2011
TABLE OF CONTENTS
i
DFINITION OF TERMS viLIST OF ACRONYMS viiEXECUTIVE SUMMARY ix
INTRODUCTIONBackground to the Project 11Inception Phase Status 12Considerations of the Government of Pakistan’s Task Force on Climate Change 12
PROJECT DESCRIPTIONProject Design Concept 14Key Challenges 15
INCEPTION WORKSHOP PROCEEDINGSProject Launching Ceremony 16Field Visit to Bagrot Valley 17Objectives of the Inception Workshop 17Introduction to the Project Design and Strategy 17Project Implementation 18Project Results Verification Exercise 19Summary of Discussions held on Day 2 24Summary of Discussions held on Day 3 25Project Cycle Operations Management 26Project M&E for Climate Change Risk Management 26Common Risks and Challenges in Climate Change Adaptation Projects 28Standard Risk Categories each project should monitor 28UNDP Services to the Project 28Institutional Cooperation 30
PSC and PMCsThe Way Forward 31
ANNEXESAnnex 1: Agenda and List of Participants of the Inception Workshop 35Annex 2: Project Results Framework (updated) 37Annex 3: Annual Work Plan 42Annex 4: Four Year Project Plan 53Annex 5: List of Inception Workshop Participants 69Annex 6: Terms of Reference 75
Pakistan Metrological Department 75Global Change Impact Study Center 78ICIMOD 80World Wide Fund for Nature 83Deputy Commissioner 86Community-based Organizations 89
LIST OF TABLES AND FIGURESTable 1: Changes during Inception Phase viiiTable 2: Key Project Design Assumptions ixFigure 1: Project Organizational Chart 19Table 3: Revisions in Project Results Framework 20Table 4: Budgeted M&E Plan 27
ii
Table 5: UNDP Services to the Project and Adaptation Fund 29Table 6: Institutional Cooperation Framework 33
iii
DEFINITION OF TERMS
Ablation: refers to all processes by which snow, ice, or water in any form are lost from a glacier - the loss of snow or ice by evaporation and melting.
Ablation Area: is the lower region of a glacier where snow ablation exceeds snowfall. Accumulation Area: is the upper region of a glacier where snow accumulation exceeds melting. Albedo: is the percentage of the incoming radiation that is reflected off a surface. An
albedo of one indicates that 100 percent of the radiation is reflected. Fresh snow has a high albedo (0.7 to 0.9), indicating that 70 to 90 percent of the radiation received is reflected; glacier ice has a lower albedo of 0.2 to 0.4.
Braided Stream: Where more sediment is being brought to any part of a stream than it can remove, the building of bars becomes excessive, and the stream develops an intricate network of interlacing channels, the stream is said to be braided. Often more is deposited than can be removed by specific fluvial processes.
Cirque Basin: a glacially eroded basin shaped like half a bowl; a deep, steep-walled recess in a mountain, caused by glacial erosion.
Climate Change: is a significant and lasting change in the statistical distribution of weather patterns over periods ranging from decades to millions of years.
Crevasses: are open fissures in glacier ice. Crevasses form where the speed of the ice is variable, such as in icefalls and at valley bends.
Density: is the ratio of the mass of an object to its volume. Snow has a density averaging about 0.1, firn has a density of about 0.55, and glacier ice has a density of about 0.89. The density of unmineralized fresh water is 1.
Equilibrium line: usually applied to polar regions, it is the boundary Firn: is old snow that has been recrystalized into a more dense substance.
Snowflakes are compressed under the weight of the overlying snowpack. Individual crystal near the melting point have slick liquid edges allowing them to glide along other crystal planes and to readjust the space between them. Where the crystals touch they bond together, squeezing the air between them to the surface or into bubbles. During summer we might see the crystal metamorphosis occur more rapidly because of water percolation between the crystals. By summer's end the result is firn -- a compacted snow with the appearance of wet sugar, but with a hardness that makes it resistant to all but the most dedicated snow shovelers! Firn has a density greater than 0.55.
Flash Floods a rapid flooding of geomorphic low-lying areas such as dry lakes, river plains and river basins within six hours of time.
Glacial advance: is the net movement of glacier terminus downvalley. Advance occurs when the rate of glacier flow downvalley is greater than its rate of ablation. Advances are characterized by a convex-shaped terminus.
Glacial Drift: is the loose and unsorted rock debris distributed by glaciers and glacial meltwaters. Rocks may be dropped in place by the melting ice; they may be rolled to the ice margins, or they may be deposited by meltwater streams. Collectively, these deposits are called glacial drift. Till refers to the debris deposited directly by the glacier. Rock debris rolls off the glacier edges and builds piles of loose unconsolidated rocks called glacier moraines. Lateral moraines form along the side of a glacier and curl into a terminal moraine.
Glacial flour: is the fine-grained sediment carried by glacial rivers that results from the abrasion of rock at the glacier bed. Its presence turns lake water aqua blue or brown, depending on its parent rock type.
Glacial Meltdown irreversible receding of a glacier due to loss of thickness and area coverage.Glacial polish: is the leveling and smoothing of rock by fine-grained debris at the glacier
bed. Coarser rocks may gouge scratches called striations. Glacial retreat: is the net movement of the glacier terminus up valley. Retreat results when
iv
the glacier is ablating at a rate faster than its movement down valley. Retreating termini are usually concave in shape.
Glacial till: An unsorted, un-stratified mixture of fine and coarse rock debris deposited by a glacier. Also called: Till.
Glacier: is a body of ice showing evidence of movement as reported by the presence of ice flow line, crevasses, and recent geologic evidence. Glaciers exist where, over a period of years, snow remains after summer's end.
Glacier outburst flood: A sudden release of melt water from a glacier or glacier-dammed lake sometimes resulting in a catastrophic flood, formed by melting of a channel or by sub-glacial volcanic activity.
Glaciospeleology The study of caves developed within or underneath glaciers. GLOF Simulation Modeling:
Is an imitation of a GLOF event in the past and also entails representing certain key characteristics or behaviors of a selected glacial lake to show eventual real effects of alternative conditions and courses of action.
Icefalls: are somewhat analogous to waterfalls in rivers. The flow of the ice down a steep bedrock gradient often results in crevasses and seracs.
Hanging Glacier: is a glacier that is perched on the side of a mountain and is not connected to a larger accumulation or ablation zone.
Kinematic waves: refer to a wave of ice moving down glacier propagated by its increased thickness. The wave of ice may move at two to six times the velocity of surrounding thinner ice.
Lateral Moraine: A moraine formed at the side of a glacier. Piles of loose unsorted rocks along the side margins of the glacier. The rocks may be pushed there by the moving ice or dumped from the glacier's rounded surface.
Mass balance: describes the net gain or loss of snow and ice through a given year. It is usually expressed in terms of water gain or loss.
Medial Moraine: These form where two mountain glaciers bearing lateral moraines unite. They appear as dark streaks of rock along the glacier centerline. The small object near the lower center is a six person pyramid tent.
Moraine: Rock debris deposited by a glacier. Moulin: A circular depression on the surface of a glacier in the ablation zone into
which melt water funnels. Also called glacier mill. Neoglaciation: refers to the advances made by mountain glaciers since the great
Pleistocene ice age. In the Cascades the advances have occurred since 6,600 years before present.
Neve: refers to an area that is perennial snow or firn. The area lying entirely within the zone of accumulation.
Nunatak: An isolated hill or peak which projects through the surface of a glacier and is completely surrounded by ice or snow.
Ogives: are arc-shaped features occasionally found across the glacier surface below icefalls. They may be ridges and swales in the ice or bands of darker or lighter ice. One theory of their formation suggests that the ice is stretched and sometimes dirtied when exposed in the icefall during the high velocities of summer; it is compressed during the winter so that bands of different ice thickness form.
Perfectly plastic solid: is a solid that does not deform until it reaches a critical value of stress, after which it will yield infinitely. Some glaciologists say that ice is a perfectly plastic substance. (That is, brittle and capable of cracking like a solid, yet deformable and capable of flowing at other stresses).
Pleistocene: is the period of earth's history, roughly two million years ago to about ten thousand years ago, characterized by the advance and recession of continental ice sheets.
Proglacial Lake: A lake formed beyond the limits of a glacier, in front of a glacier terminus.Roche moutonnee: is a small asymetrically-shaped hill formed by glacial erosion. The upper
sides are rounded and smoothed and the lower sides are rough and broken
v
due to quarrying by the glacier.Seracs: are the pinnacles of ice formed where the glacier surface is torn by sets of
crevasses.Striations: are the scratches etched into the rock at the bed of a glacier. Their presence
indicates grinding of sand and rock particles into the bed under considerable pressure. In some places find-grained debris polishes the bedrock to a lustrous surface finish called glacial polish.
Suncups: are a small (up to 1 meter across) depression on a snow or firn surface formed by melting and evaporation, resulting from direct exposure to the sun.
Terminal moraine: A moraine formed at the down valley end of a glacier. Piles of loose unconsolidated rock at the glacier are down valley end. The rocks may be pushed there by the forward motion of the glacier or dumped from the glacier's rounded surface.
Terminus: is the down valley end of a glacier. It is sometimes referred to as the glacier snout.
Till: is the unsorted rock debris deposited directly by the glacier without the extreme reworking by melt water. Also called: Glacial till.
Tidewater Glacier: is a glacier whose terminus is in the ocean.Trim line: These are the sharp vegetative boundaries delimiting the upper margin of a
former glaciation. The age differences of the ground surface are often visible because of different ages of the vegetation.
Source: http://www.mccullyweb.com/icefield/glossary.html
vi
List of Acronyms
ACD Assistant Country Director
AF Adaptation Fund
AKRSP Aga Khan Rural Support Programme
AKPBS Aga Khan Planning and Building Service
DC Deputy Commissioner
DMC Disaster Management Committee
RMC Risk Management Committee
EIA Environmental Impact Assessment
EWS Early Warning System
ERRA Earthquake Relief and Rehabilitation Authority
FC Flood Commission
FWO Frontier Works Organization
FOCUS FOCUS Humanitarian Assistance
CERT Community Emergency Response Team
FOCUS Focus Humanitarian Assistance
GBDMA Gilgit Baltistan Disaster Management Authority
GIS Geographical Information System
GCISC Global Change Impact Studies Centre
GLOF Glacier Lake Outburst Floods
GCISC Global Change Impact Study Center
GFDRR Global Facility for Disaster Reduction and Recovery
HKH Himalayan Karakorum Hindukush
ICIMOD International Centre for Integrated Mountain Development
IEE Initial Environmental Examination
IUCN International Union for Conservation of Nature
ISDR International Strategy for Disaster Reduction
IPCC Intergovernmental Panel on Climate Change
IGIS Institute of Geographical Information Systems
IUCN International Union for Conservation of Nation
KIU Karakorum International University
KPK Khyber Pakhtunkhwa
KPDMA Khyber Pakhtunkhwa Disaster Management Authority
LDCF Least Developed Country Fund
LEAD Leadership in Environment And Development
LSO Local Support organization
vii
MoU Memorandum of Understanding
MTE Mid-Term Evaluation
NESPAK National Engineering Services of Pakistan
NDMA National Disaster Management Authority
NOC No Objection Certificate
NPD National Project Director
NPM National Project Manager
PCOM Project Communication and Operations Manual
PCRWR Pakistan Council of Research on Water Resources
PDMA Provincial Disaster Management Authority
PIMS Project Information Management Systems
PMC Project Management Committees
PMD Pakistan Metrological Department
PRCS Pakistan Red Crescent Society
PRSP Poverty Reduction Strategy Paper
PSC Project Steering Committee
PWD Public Works Department
RTA Regional Technical Advisor
SLF Snow Leopard Foundation
SLMP Sustainable Land Management Project
TFCC Task Force on Climate Change
UNISDR United Nations International Strategy for Disaster Reduction
UNDP United Nations Development Project
UoP University of Peshawar
WWF World Wide Fund for Nature
viii
EXECUTIVE SUMMARY – INCEPTION REPORT
This Inception Report describes the initial start-up activities and refinements to the design of the project, Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods in Northern Pakistan. The project was jointly approved by the government, the Adaptation Fund and UNDP in May 2011. This Inception Report is an amendment to the approved Project Document (ID # 00077650; PIMS # 4454).
The objective of the project is to reduce climate change-induced risks of Glacial Lake Outburst Floods (GLOFs) in Gilgit-Baltistan and Chitral and that national, provincial, district and communities are able to prioritize and implement climate change adaptation measures. The project seeks to achieve four outcomes:Outcome 1: Strengthened Institutional capacities to implement policies, plans and investments that prevent human and material losses from GLOF events in vulnerable areas of Northern Pakistan.
Outcome 2: Improved access of disaster management planners and policy makers to knowledge, information and research on GLOF risks.
Outcome 3: Reduced human and material losses in vulnerable communities in the Northern areas of Pakistan through GLOF early warnings and other adaptation measures
Outcome 4: Project experiences documented and replicated
The inception phase resulted in four major changes to the Project Document, as summarized below in Table 1:
PROJECT STRATEGY
REFERENCE
TYPE ORIGINAL REVISION / ADDITION
OUTPUT 1.1 Output Policy Framework and guidelines to address GLOF risks in northern Pakistan institutionalized
Policy recommendations and guidelines to address GLOF risks in northern Pakistan institutionalized
OUTPUT 2.2 Target By year 2, GLOF specific simulation models for at least 2 GLOF prone mountain valleys are developed
OUTPUT 3.2 Output A special watch group for each GLOF prone valley will be formed to establish a new or to strengthen an existing Early Warning System
OUTPUT 3.3 Target By the end of the project, concrete engineering measures are in place to reduce the impact of GLOF events on vulnerable communities in each target valley (as appropriate: check dams, mini dams, ponds, spill ways, slope stabilization, tree plantation, controlled drainage)
By the end of the project, concrete engineering measures are in place to reduce the impact of GLOF events on vulnerable communities in each target valley (as appropriate: effective drainage systems, check dams, mini dams, ponds, spill ways, slope stabilization, tree plantation, controlled drainage)
Institutionalization of policy framework and guidelines is beyond project’s scope. Rather a set of recommendations supported by a guideline prepared jointly by the Gilgit Baltistan and the project
ix
management will be developed for passage to the Federal Secretary for National Disaster Management.
Due to the complexities involved in the hazards related to GLOF, existing disaster management plans will be modified in light of valley specific simulation models. Modified or completely new disaster management plans will emerge out of the subsequent hazard zonation and vulnerability assessment which will inform both land use and disaster management planning in a particular valley.
Regardless of peoples’ lack of sensitivity to or knowledge of GLOF; traditional early warning systems exist in all valleys due to perpetual occurrences of natural hazards such as flash floods, landslides, debris flow and seismic activity. Depending upon the preparedness of the residents of a GLOF prone valley, either existing systems will be strengthened or new systems will be installed.
Improvement in the drainage of glacial lakes will be a top most priority. All other engineering solutions will be in line with the drainage channels to ensure safety of the people and protection of property and public infrastructure.
The key project design assumptions were discussed in the inception phase workshop. The stakeholders have re-categorized following assumptions as shown in Table 2 below:
ProjectDocument
Inception Workshop Key Project DesignRisks / Assumptions
High High Adverse climatic conditions may damage adaptation measures being implemented.
Medium Low The political and security situation in pilot districts may affect project implementation or weaken the interest of stakeholders to address adaptation planning issues.
Low Low Delays in recruitment of qualified project staff may affect the timeframe of different project activities.
Medium Low Project stakeholders may disagree on institutional mechanisms for project implementation and refrain from providing the necessary coordination.
Medium Medium Government co-financing contributions may only come forth in batches and may not be available in full at the beginning of the project.
Medium Low Lack of incentives for particular local communities to cooperate in activities that do not yield immediate financial value, but aim at longer-term resilience, may reduce stakeholder engagement and comprehensive participation.
Low Low Implementing partners for local level initiatives and pilot sites for project implementation may shift during project implementation, due to unforeseen (e.g. political) reasons.
The implementation strategy is summarized as follows:
The proposed project will reduce risks and vulnerabilities from GLOFs and snow-melt flash floods in Northern Pakistan. The main objectives of the project are as follows:
To develop the human and technical capacity of public institutions to understand and address immediate GLOF risks for vulnerable communities in Northern Pakistan
x
To enable vulnerable local communities in northern areas of Pakistan to better understand and respond to GLOF risks and thereby adapt to growing climate change pressures
Project implementation strategy envisions to setup two valley-based ‘Centers of Learning.’ Bagrot and Drongagh valleys will serve as GLOF Prevention Field Schools where project will demonstrate how communities and district administrations are sensitized about GLOF, simulation models are developed, hazard zonation is done, hazard and vulnerability risk assessment is undertaken on participatory basis, land use and disaster management plans are prepared with stakeholder consultation. Broader multi-stakeholder involvement and community participation will ensure presence of an early warning system in each GLOF prone valley.
Early warning systems can be categorized according to the level of preparedness of each valley. Most prepared valleys will be Bagrot and Drongagh that will serve as the centers of learning as GLOF prevention schools. A Project Management Unit within the Climate Change Section of the Ministry of National Disaster Management will oversee implementation of the project through its National Project Director. A multi-stakeholder Project Steering Committee based in Islamabad will provide the overall direction to the project team whereas Project Management Committees based in Gilgit Baltistan and Chitral will provide the necessary input and support for achieving project outputs.
Several amendments are proposed to the project’s Risk Log. Overall, the project is deemed low risk due to the uncertainties about viable adaptation measures and the weak project delivery systems within government.
xi
INTRODUCTION
Background to the Project
The project titled Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods in Northern Pakistan was jointly approved by the government, the Adaptation Fund and UNDP in May 2011. The project period is May 2011 – April 2015. The project budget is $7,600,000 with $3,600,000 and $500,000 in cash contributions from Adaptation Fund and UNDP respectively and the remainder in contributions in kind from the Government of Pakistan.
This Inception Report describes the initial start-up activities and refinements to the project design Project Document (ID # 00077650; PIMS # 4454). The changes identified in this report can be considered amendments to the final project design.
The major climate hazards to which the Northern Pakistan is exposed regularly include glacial lake outburst floods, flash floods from snow melt and heavy rains, landslides, debris flow and seismic activity. Climate change is expected to increase the frequency and intensity of existing climate hazards and lead to long-term vulnerability of the hundreds of thousands of people exposed to multiple natural hazards
The Himalayan Karakorum Hindukush (HKH) mountain ranges in northern Pakistan possess the largest glaciers in the world outside the Polar Regions. A major part of the snow and ice mass of the HKH region in Pakistan is concentrated in the watersheds of the Indus basin. As a result of rapidly changing climatic conditions, the glaciers in Pakistan are receding at a rate of almost 40 – 60 meters per decade. The melting ice from these glaciers is increasing the volume of water in the glacial lakes. According to the IPCC’S fourth assessment report, eleven of the last twelve years (1995 – 2006) rank among the 12 warmest years of in the history of global surface record since 1850. This rapid change in the world’s temperatures is related with a faster rate of glacier melt.
Various studies suggest that the warming trend in the HKH region has been greater than the global average (ICIMOD, 2007). The most severe threat of this effect is related to the rapid melting of glaciers. The ice or sediment bodies that contain the lakes can breach suddenly, leading to a discharge of huge volumes of water and debris. These are termed Glacier Lake Outburst Floods (GLOFs) and have the potential to release millions of cubic meters of water and debris, with peak flows as high as 15,000 cubic meters per second.
According to a study conducted by ICIMOD (2007), 5218 glaciers (15040 sq km) and 2420 lakes were identified and mapped in Pakistan. Among the identified lakes, 52 lakes have been classified as potentially hazardous, and likely to cause GLOFs over the next few years to decades. Records show that on average, GLOF events occur in the Himalayas every 3-10 years, with varying degrees of socio-economic impact. A total of 35 destructive outburst floods have been recorded in the Karakoram region in the past 200 years and at least 11 surges of exceptional scale have been recorded so far in the Upper Indus Basin.
At present, the country faces a critical gap in knowledge of hydrological forecasting, risk mapping and disaster prevention planning. The information currently available about the glaciers in the water shed of the Indus basin is limited and scattered, and the understanding of the snow and ice conditions associated with the mountainous headwater of the Indus is largely inadequate.
As the current status of the identified glacial lakes is changing, the number of potentially hazardous lakes and their location/origin is shifting, and new lakes are developing rapidly, a need has developed for a formal monitoring and evaluation system to validate the information on the status of potentially hazardous glacial lakes.
12
Inception Phase Status
The Inception Phase from May – December 2011 includes and will include following activities:
Appointment of a National Project Director by the Ministry of National Disaster Management.
Appointment of a National Project Manager and an Associate Finance & Administration by UNDP.
Recruitment process for the two Field Manager positions is underway. Project Results Framework was further refined in consultation with stakeholders. NPM has started a round of consultations with potential partner organizations for identifying
activities for each of the Project Outputs. Draft 2012 Annual Work Plan and Budget are being prepared. Draft Project Workplan and Institutional Cooperation Framework have been initiated. Recommendations of the Government of Pakistan’s Task Force on Climate Change were
incorporated in the project document. Inception Workshop was held on November 15th – 17th. Bagrot and Drongagh valleys have been declared as GLOF Field Schools to serve as the
Centers of Learning.
Considerations of the Government of Pakistan’s Task Force on Climate Change
A meeting of the Government’s Task Force on Climate Change was held earlier in the inception phase to consider technical, geographical, cultural, and institutional matters related to prevention of GLOF related disasters. Vulnerability analysis on the basis of GLOF hazard exposure and sensitivity mapping was considered as a critical feature for the selection of target communities to participate in and benefit from this project. The target areas have been selected on the basis of the following criteria:
1. Technical geography:The target demonstration sites are representative with respect to their geographical location, area and height of glaciers, track of glacier lakes, hydrology, direction of sloping land surface, disintegrating ice and/or sediment barriers, geological structure and build-up, size of affected communities, and their general vulnerability profile. The geographical locations and other related features of the glaciers and lakes will be captured and analyzed by means of a Geographical Information System (GIS) under Component 2 of the project.
2. Recurring GLOF events / history:Recurring GLOF events have been identified through a time series analysis, using existing maps, satellite data and other records available from different years.
3. Affected communities and accessibility of the area:Considerations have included: The size of the community under consideration, the number of persons exposed to flooding risk; population density, traditions/culture of the community, present land use, accessibility and livelihood structure, awareness level of community about the possible impacts of GLOF.
Based on verification of the above criteria with local stakeholders, two potentially hazardous glacier lakes in Gilgit-Baltistan and Chitral have been identified as target sites for the project: The Bagrot valley in Giltgit-Baltistan is considered at high risk of GLOF from the Bagrot Glacier. Bagrot valley covers an area of 452 km2. It is characterized by an extreme geomorphological relief, ranging from 1500 m up to 7788 m at the summit of Rakaposhi. The main valley glaciers are Hinarche, Burche, Gutumi, and Yune while several smaller cirque glaciers exist in the higher reaches.
13
The glaciated area is about 42.3 km2 and major part of the lower tongue is covered by supra-glacial debris, similar to the other glacier tongues in the valley. The valley has 1100 households with an estimated population of 10,000 people. Similarly, Drongagh has been selected as a demonstration site in Chitral. The village lies in the vicinity of Gohkir Glacier. has almost 500 households with a population of almost 3500 people and lies at a distance of approximately 40 kms from Chitral municipality. Both sites are highly vulnerable to flooding related to glacial lake outbursts or glacial outbursts, which occur almost every year. The floods do not only result in damages to community infrastructure, communication networks, roads and crops, but also cause human casualties.
Technical considerations for the design of an Early Warning System (EWS):
Existing flood early warning systems in the 2 target sites of Bagrot Valley and Drongagh will be established to enable the dissemination of flashflood warning signals on a 24 hour basis. EWS design is expected to involve:
i) Threat detection (sensor), relay and warning stations;ii) GLOF watch advisories issued by Pakistan metrological department (PMD) to
communities at risk via print and electronic mediaiii) Establishment of an SMS messaging system to communicate warning signals to
community based organizations, local NGOs and Government departments;iv) Establishment of a central voice response system where end users may get flood risk
information via phone/mobile call around the clock;v) Early warning awareness and training workshops for community, NGOs, government and
media representatives to ensure that EWS procedures are internalized;vi) Real-time mock drills at community level to simulate a GLOF disaster and verify
functionality of the EWS Selected community and NGO members will be trained in the calibration, operation and maintenance of sensor equipment installed by PMD at the target sites.
Technical considerations for the design of community-based GLOF risk mitigation measures:
Potential outburst flood hazards can be alleviated by various techniques. The primary objective is to reduce the risk of a flood from the lake. However, coordinated measures to protect life and property in the downstream area must also be undertaken, hence the importance to combine these techniques with EWS-based mechanisms downstream. The most common structural mitigation measures are aimed at reducing the volume of water in the lake. Reduction of the volume of water in the lake should reduce the potential peak surge discharge as well as the hydrostatic pressure exerted on the moraine dam, and is the most effective mitigation measure. There are different ways to achieve this that can be used alone or in combination:
1. Controlled breaching of the moraine dam2. Construction of an outlet control structure3. Pumping or siphoning the water from the lake4. Tunneling through the moraine barrier or under an ice dam
Mitigation measures must be brought into play in such a way that no unintentional increase in danger occurs. Since moraine dam stability is a major part of the problem, it follows that artificial disturbance of the dam itself during construction activity could actually increase the degree of danger while mitigation measures are being put into place. Thus, choice of an appropriate method for each individual lake is critical. Physical monitoring systems for the dam, lake, glacier, and surroundings are necessary at all stages of the mitigation process.
In addition to reducing the volume of lake water, there are other preventative measures around the area that can help reduce the likelihood, or impact of, a GLOF. These include removing masses of
14
unstable rocks to guard against avalanches or rock falls hitting the lake surface and causing a surge wave, and protecting infrastructure in the downstream area. Other measures include check-dams, mini dams, spill-ways, slope stabilization and -reinforcement. Check dams are helpful in reducing the flow of water coming down by gravity flow and conserving soil and thus provide downstream protective measures. Removing or restraining trigger mechanisms include stabilization of adjacent slopes. Slope stabilization may be through vegetation or engineering structures.
In all structural mitigation measures undertaken by the project, experience from other GLOF risk reduction projects (including GLOF risk reduction projects in India, China, Nepal and Bhutan) will be integrated and adopted where appropriate.
PROJECT DESCRIPTION
Project Design Concept
The project will help by reducing climate change induced risks and vulnerabilities from GLOFs in the Northern Areas of Pakistan by encouraging community based adaptation measures for climate change induced GLOFs. The components of the project are described below.
Component 1: Policy recommendations & institutional strengthening to prevent climate change induced GLOF events in northern Pakistan
This project component responds to the need for systematic integration of GLOF risk management into the processes, policies and plans of institutions that have a stake in avoiding human and material losses from GLOF events in vulnerable areas of northern Pakistan. Project inputs will be utilized to develop the capabilities of local level institutions and federal level institutions to understand the nature and extent of GLOF risks in Pakistan, and their effects on human and economic development in all sectors. Targeted, evidence-based policy recommendations on GLOF prevention and risk management will be prepared and disseminated for adoption at national and provincial levels, which will enable the integration of GLOF risk awareness in all potentially affected sectors. Contingency plans & incentive schemes to address GLOF risks at the policy level will be developed, based on collaboration between affected stakeholders.
Component 2: Strengthening Knowledge and Information about GLOF risks in northern Pakistan
This project component addresses the need for more accurate and comprehensive knowledge of glacier lakes and their associated flooding risks in northern Pakistan. Such knowledge is essential for better risk mapping, early warning and disaster prevention planning. Based on a targeted mapping exercise of flooding hazards downstream of potentially hazardous glacier lakes, a locally anchored knowledge base & analytical framework for long-term tracking & management of GLOF risks will be developed. Systematic networking and exchanges with global & regional research institutions and resource centers, as well as with other GLOF risk management projects in the region will contribute to a widening the knowledge base about GLOF risks in Pakistan, eventually leading to a critical mass of knowledge required for specific and targeted risk reduction investments. Existing indigenous knowledge, cultural beliefs and coping mechanisms to address flooding risks in Northern Pakistan will be documented and factored into the risk reduction and preparedness activities employed by this project.
Component 3: Demonstration of community-based GLOF risk management in vulnerable mountain valleys of northern Pakistan
Adaptation Fund resources will be used to demonstrate GLOF risk management at the village and district levels, with the aim to provide an evidence base for replication and up-scaling. Based on the
15
systematic capturing of hazard information and vulnerabilities in Component 2, awareness raising activities will be undertaken to educate disaster-prone communities about the nature of GLOF risks, the particular behavior of GLOF events, evacuation routes and appropriate early warning and risk reduction measures. These awareness activities will be connected with the production and dissemination of communication products, such as posters, leaflets and videos illustrating the topic. Institutional arrangements to devise, operate, test, and maintain a community-based GLOF risk monitoring & early warning system will be established in a at least 2 high-risk target communities, providing an evidence base on the strengths and weaknesses of different types of high- and low-tech early warning systems. Based on such analyses, a prototype GLOF Early Warning system will be devised for replication in other vulnerable areas. In addition to the demonstration of an Early Warning system, the project will demonstrate targeted GLOF risk mitigation measures for at least 2 communities which are located in high-risk sites.
Component 4: Documentation, analysis and continued application of lessons learnt
Building on participative processes initiated under Components 1 and 2 of the project, and drawing on the technical experiences in the establishment of early warning and risk mitigation measures under Component 3, Component 4 of the proposed project will introduce targeted activities to enable the analysis, replication and up scaling of the project approach in other communities who are vulnerable to GLOF risks. This will entail a campaign to present the findings from the project to different public entities and development partners, as well as other district entities with similar degrees of vulnerability. This campaign will integrate all vulnerable districts and aim at the replication of the project approach in at least 3 other vulnerable areas. Exchange programmes to the target sites will be facilitated to promote learning and transfer of experience (especially with regards to the design of coupled EWS that covers as many vulnerable mountain valleys as possible).
By taking a systematic approach to the codification, analysis and dissemination of knowledge about GLOF risks and how they can be addressed, the project will allow replication of effective risk reduction measures for GLOF both within Pakistan and beyond. This systematic management will assist the replication of early warning systems and targeted risk mitigation measures in other GLOF prone areas in northern Pakistan. Other countries facing GLOF risks, such as China, India, Nepal and Bhutan, will also benefit from the knowledge generated through the project. This proposed initiative will contribute to a critical mass of experience on GLOF risks in the Himalaya region and enhance systematic regional cooperation on this critical adaptation issue.
Key Challenges
Logistical remoteness of the area has increased after damages to Karakorum highway in the aftermath of the super floods in 2010. The time for road travel from Islamabad to Gilgit town has doubled, now it takes more than 20 hours of a road trip to reach Gilgit from the Capital. Then, it is another 2 hours drive to reach the glaciers from Gilgit. In Case of Chitral, it can be accessed from two roads one coming from Gilgit which takes 12 hours drive to reach Chitral town and the second that passes through a tunnel connecting Chitral with Islamabad take equally long travel time. Approach to the glaciers is Drongagh takes another 4 hours of drive from the proposed field office. Northern Pakistan is still recovering from the disaster of the 2010 super floods caused by cloud burst.
Domestic air routes are available with daily flights to both Gilgit and Chitral towns from Islamabad. However, flights are subjected to weather.
Since 2004, climatic conditions of Gilgit Baltistan and Chitral have become harsher than before because of the extreme temperatures of both summers and winters. Glacial sites of the project are only accessible from May till November. Five months of the year most of the glacial sites in the region remain snow bound.
16
Will of the communities has to be matched by the skills of the project team members and capacities of the potential partner organizations, especially line departments. Project will have to do a careful selection of the field managers and their immediate team members because human resource turnover is high in Gilgit Baltistan and Chitral because professionals from down country rarely seek opportunities in such remote and logistically difficult areas. Availability of experienced professionals in the project’s targeted area is scarce and it takes much longer to find the right candidates for the job. This explains the delay in the hiring of a full project team.
GLOF prone valleys are afflicted with multiple hazards such as flash floods caused by heavy rains and snow melt, landslides, debris flow and seismic activity. The ultimate early warning systems, land use management, and disaster management plans will have to incorporate all prevailing hazards in the area for the sake of the participating communities without losing focus on GLOF.
The most critical challenge faced by the project is its small size and limited time in comparison to the sheer size of the GLOF problem in Northern Pakistan (Gilgit Baltistan and Chitral).
PROCEEDINGS OF THR INCEPTION WORKSHOP
Day One (15 November 2011):Project Launching Ceremony
The project launching ceremony held on 15 November 2011 at Serena Hotel in Gilgit was chaired by the Gilgit Baltistan Administration Secretary for Forests, Wildlife, and Environment Haji Abdul Hameed. The National Project Manager Mr. Khalil Ahmed in his welcome remarks expressed his gratitude to the guests who had gathered to attend the ceremony in spite of a public holiday (see annex # 1 for the workshop agenda and list of participants). The National Project Director Syed Mujtaba Hussain elaborated on the inception phase of the project and highlighted the importance of the Glacial Lake Outburst Flood (GLOF) prevention for the people and the government. He used this opportunity to express Government’s sense of urgency in addressing the impact of climate change and unfolded the mandate of the newly restructured Ministry of National Disaster Management. Later Syed Mujtaba Hussain spoke about the project implementation arrangements in detail. He stressed upon the need for greater stakeholder participation in achieving project goals.
The Regional Technical Adviser to UNDP Mr. Gernot Laganda speaking on the occasion highlighted the methodical approach used to assess the risks associated with GLOF. He stressed that GLOF prevention requires scientific modeling, hazard zonation and vulnerability assessment before any land use or disaster management planning is done. He hoped for greater cooperation amongst international non-profit organizations such as WWF, IUCN, PRCS, and others that have conducted hazard mapping and vulnerability assessment in the project area for multiple natural hazards. However, he realized that GLOF related hazards and vulnerabilities have not been understood well and require much needed cooperation amongst similar projects being implemented in the Himalayas, Karalorum, HinduKush, Alps and the Andes.
The Assistant Country Director for UNDP Mr. Abdul Qadir Rafiq speaking on the occasion highlighted the fact that UNDP understands Pakistan’s need for adaptation to climate change, especially in the Northern part of the country. He highlighted the fact that since 1996, UNDP has assisted the Government of Pakistan in implementing various projects to enable the government in adaptation to the climate change. These projects are Biodiversity Conservation Project, Mountain Areas Conservancy Project, Pakistan Wetlands Programme, Promotion of Energy Efficient Cooking and Heating, and now in collaboration with the Adaptation Fund a project for Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods in Northern Pakistan in being launched with full government support.
17
The Guest of Honor, Secretary to the Gilgit Baltistan Administration Haji Abdul Hameed khan addressed participants by emphasizing on the need for unity of purpose for making our efforts for the adaptation to the climate change, especially GLOFs. He noted that in recent years GLOF related events have increased tremendously. Since 1994, over a dozen of GLOF events have occurred in Northern Pakistan. GLOFs have been reported in Drongagh area, Buni, Sanoghar, Darkut, Karamber, Bagrot, Gulkin, Gulmit, Passu, Astore, Diamer and Skardu area. Then formation of Hunza Lake is just another phenomenon altogether. He welcomed UNDP’s assistance to the Government of Pakistan and appreciated Adaptation Fund’s interest in minimizing the climate change related risks in Pakistan. He wished the project team successful implementation of the project and extended his full support.
Field Visit to Bagrot Valley
Thirty out of seventy participants were invited to the field visit to Bagrot valley, one of the two project sites. The purpose of the field visit was to familiarize representatives of the potential partners organizations and relevant line departments with the project site and more importantly with the community representatives with whom the project team will work for next four years. The field exposure was planned to enable the thirty participants to review project documents and discuss strategies in light of ground realities.
Day Two (16 November 2011):The Objectives of the Inception Workshop
The inception workshop facilitator Mr. Faisal Farooq Khan presented the objectives of the workshop to the participants. The presentation informed the partner organization representatives about the expectations from them and what is it that they can expect from the project. Facilitator informed them that he will assist them in identifying their organization’s role and responsibilities in project implementation. Following are the sessions of the inception workshop that were delivered over a period of two days:
• Informing Stakeholders about Project Design• Verification of Results Framework• Fine Tuning of Annual Work Plan (Year-1)• Understanding Project Management (PCOM) Requirements of UNDP assisted Projects• Defining M&E Methodology and Climate Change Risk Management Strategy• Institutional Cooperation Needed from Partner Organizations• Describing Governing Structure of the Project• Way Forward
Introduction to the Project Design and Strategy
National Project Manager (NPM) Khalil Ahmed presented the overall project design and implementation strategy of the project (please see pages 4 and 5 above). Elaborating on project strategy he explained that selection of two valleys is entirely for demonstration purposes and does not necessarily address the top two GLOF hotspots in the region. The participants enquired why Karamber valley, Yarkhun valley, Diamer valley and Skardu valley were not considered for demonstration purposes. Facilitator Faisal Farooq Khan explained that the idea is to develop logistically manageable sites as ‘the centers of learning’ by conducting simulation modeling, hazard zonation, vulnerability assessment for developing land use-cum disaster management plans in participation with the communities and organizations like WWF, IUCN, PRCS, FOCUS and GBDMA that have already done a lot of work to address risks emanating from flash floods, landslides and earthquakes. He further added that an early warning system for preventing safety from GLOF can only be effectively developed after above mentioned outputs have been delivered. NPM said that selection of Bagrot and Drongagh offers the opportunity to capitalize on the enhanced capacities of the potential partner organizations, which will save time and as well as make already trained staff available.
18
Realizing the increased vulnerability of the populations living in other hotspots of Northern Pakistan, facilitator stressed that the overall remote sensing mentioned earlier by NPM will enable the project team in pinpointing trouble spots while the work in the two selected sites for demonstrating GLOF safety and an early warning system will set the benchmark for other communities. Workshop participants endorsed the project strategy to treat two selected GLOF prone valleys as GLOF Field Schools where communities, government line departments, partner organizations and the project team will collaborate mutually to demonstrate GLOF safety measures and arrange for exposure visits by other vulnerable communities to learn and adapt. Selected representatives of vulnerable communities from each GLOF prone valley will visit the project sites to develop their own valley-specific early warning systems.
UNDP Assistant Country Director Mr. Abdul Qadir Rafiq explained that during the year 1, project team will focus on streamlining baseline information, strengthening partnerships, and bring every relevant government department on board. A list of prioritized valleys will be developed after involving on-ground government functionaries at the district level. The prioritization of the GLOF prone valleys will be endorsed by the Director General of GBDMA.
Regional Technical Advisor of UNDP Mr. Gernot Laganda stressed on the importance of the scientific input required to ensure GLOF safety measures. He seconded Mr. Rafiq’s statement and said that baseline information needs to be categorized as scientific, technical, social and economic. Explaining further, he said that a repository of imagery and other knowledge products have to be built in the form of a database with web-links to other participating organizations. Similarly, other partner organizations such as WWF, IUCN, PRCS, FOCUS and GBDMA will share their secondary data with the project team and make it available to the project database.
Project Implementation
In absence of the National Project Director (NPD), the facilitator made references to NPD’s presentation made on the first day of the workshop. Facilitator revisited the project organizational chart to reiterate the roles and responsibilities of both key positions and stakeholders. Please see figure 1 below for a complete picture.
The Project Steering Committee (PSC) to be Chaired by the Federal Secretary for National Disaster Management or his/her appointed representative will exercise overall executive authority and responsibility for project activities, results, performance and reporting, as well as financial
19
management and expenditures oversight. The PSC is assisted by two regional Project Management Committees (PMC)s which are an advisory and technical guidance body intended to engage an array of stakeholders in project activity planning and implementation in Gilgit Baltistan and Chitral. Membership of PMCs will be much broader to include regional representatives of partner organizations, government line departments, local academia and communities. NPD will provide routine support and direct guidance to NPM and his team and Contractors in the implementation of specific components of the project.
The facilitator described an overall implementation strategy aiming at achieving eight major objectives, which are mentioned below:
1. To ensure application of adaptive management and setting of annual milestones to monitor performance of partner organizations and overall project progress.
2. To serve as a grant manager for partner organizations. Disbursements will be strictly tied to performance, accountability and transparency in fund utilization. Moreover, each project partner will be required to contribute financially and/or in-kind depending upon the nature of deliverables.
3. To leverage existing financial, material, and social resources separate contracts will be signed with potential partners including community-based organizations to ensure value addition through resource multiplication and timely delivery of project outputs.
4. To resolve the trained human resource scarcity problem the project will access trained manpower through partnerships.
5. To bring dispersed information and data to a common platform the project will establish a web-linked database.
6. To ensure Government’s support of the overall approach, methodology and implementation strategy the project will engage both GBDMA and KPK-PDMA in the field activities.
7. To enhance technical skills of the project team and relevant staff members of partner organizations the project will seek to firm up cooperation with international organizations implementing climate change risk management projects in the HKH, the Alps and the Andes regions.
8. To disseminate and replicate best practices in other hotspots of the HKH region the project will showcase two selected valleys as GLOF Field Schools.
Project Results Verification Exercise
Facilitator conducted a comprehensive results verification exercise on the second day of the workshop. Four major changes were proposed after long deliberations that were necessary for seeking clarifications largely for conceptual understanding and identifying roles and responsibilities of each potential partner organization. In table 3 below changes are highlighted in bold for each reading.
PROJECT STRATEGY
REFERENCE
TYPE ORIGINAL REVISION / ADDITION
REMARKS
OBJECTIVE Indicator Number of people living in Gilgit-Baltistan and Chitral suffering losses from extreme weather events
Number of people living in Gilgit-Baltistan and Chitral suffering losses from GLOF
Northern Pakistan is a multi-hazard prone region and it is necessary to distinguish GLOF related events to ensure resources are used for GLOF related initiatives only.
OUTCOME 1 Indicator Number of policies introduced to
Number of policy recommendations made to address
It is beyond the scope of project to introduce policies
20
address GLOF risks or adjusted to incorporate GLOF risks
GLOF risks or adjusted to incorporate GLOF risks
rather the NPD will make policy recommendations to his Federal Secretary who will then cooperate with the Planning Commission to formulate a policy for the Cabinet Committee’s consideration.
OUTPUT 1.1 Output Policy Framework and guidelines to address GLOF risks in northern Pakistan institutionalized
Policy recommendations and guidelines to address GLOF risks in northern Pakistan institutionalized
A set of recommendations supported by a guideline prepared jointly by the line department cooperating with the project management will be developed for passage to the Federal Secretary for National Disaster Management.
Target # 2 By the end of the project, existing DRM guidelines integrate longer-term climate risk planning
By the end of the project, existing DRM guidelines integrate longer-term climate change risk planning
Climate risk planning is rephrased to climate change risk planning.
Baseline No comprehensive disaster management guidelines exist for the Gilgit-Baltistan and Chitral regions
No comprehensive disaster management guidelines addressing GLOF exist for the Gilgit-Baltistan and Chitral regions
GBDMA in collaboration with UNDP has developed a Disaster Management Plan which were further elaborated into nine valley specific plans. However, none of them refer to GLOF related risks.
OUTPUT 1.2 Risk/Assumption NOCs are obtained from relevant authorities for accessing restricted sites
Gilgit Baltistan is an internationally disputed area therefore it is anticipated that project might need NOCs from the government if necessary. Moreover, Pakistan Metrological
21
Department is a potential project partner that can obtain required NOCs.
OUTPUT 2.1 Source of Verification
MoUs / agreements
Website linkages
To firm up cooperation with global and regional research networks and centers working on GLOF issues a series of MoUs and agreements will be signed with the project and the ministry respectively.
OUTPUT 2.2 Target By year 2, GLOF specific simulation models for at least 2 GLOF prone mountain valleys are developed
Due to the complexities involved in the hazards related to GLOF a simulation model and fore/back casting will be done to inform the hazard zonation and vulnerability assessment process.
OUTCOME 3 Target By the end of the project, at least 2 targeted engineering structures (biological and/or mechanical) have been established to reduce the effects of GLOF events on livelihood assets
By the end of the project, at least 2 targeted engineering structures (spurs, protective works, check dams, slope stabilization, spill ways and water drainage etc) have been established to reduce the effects of GLOF events on livelihood assets
It was necessary to spell out the types of interventions especially drainage which is most critical of all.
OUTPUT 3.2 Output A special watch group for each GLOF prone valley will be formed to establish a new or to strengthen an existing Early Warning System
Regardless of peoples’ lack of sensitivity to or knowledge of GLOF; traditional early warning systems exist in all valleys due to perpetual occurrences of natural hazards such as flash floods, landslides, and debri
22
flow. Depending upon the preparedness of the residents of a GLOF prone valley, either existing systems will be strengthened or new systems will be installed.
Source of Verification
GLOF watch group meeting attendance and note for records
Strengthening of traditional practices on more methodical basis in the form of GLOF watch groups will be further complimented by documentation of their concerns, decisions and actions throughout project’s life time.
Risk / Assumption
Valley wide traditional communication systems are in place
The communities of Northern Pakistan have a centuries old tradition of survival on self-help basis.
OUTPUT 3.3 Target By the end of the project, concrete engineering measures are in place to reduce the impact of GLOF events on vulnerable communities in each target valley (as appropriate: check dams, mini dams, ponds, spill ways, slope stabilization, tree plantation, controlled drainage)
By the end of the project, concrete engineering measures are in place to reduce the impact of GLOF events on vulnerable communities in each target valley (as appropriate: effective drainage systems, check dams, mini dams, ponds, spill ways, slope stabilization, tree plantation, controlled drainage)
Improvement in the drainage system of the glacial water is a top most priority. If barriers or constraints in draining of a GLOF prone glacier remain unresolved than other options discussed will be considered.
Source of Verification
Structural designs
Completion designs
For every physical intervention proper technical designs or plans will be prepared and implementation will be confirmed by preparing built drawings to assess
23
compliance.Risk/Assumption EIA yields
positive result for the mitigation measures under consideration
IEE yields positive result for the mitigation measures under consideration
EIA takes longer and is by law only required for mega construction projects. Due to the expected limited scope of construction activities in the GLOF project, only initial environmental examination (IEE) will be conducted.
OUTPUT 4.1 Indicators Number of knowledge products
A number of maps exist with PMD, SOP, NDMA, Flood Commission, MoNDM, WAPDA, WWF, FOCUS, PRCS and IUCN. However, none of them adequately if at all dealt with issues related to GLOF. Over a period of four years, the GLOF project will generate new relevant maps, reports, models, integrated educational communication materials, case studies and teaching modules.
Baseline Inaccessibility to maps, reports, remote imagery and case studies
Over a dozen entities have produced multipurpose materials on natural hazards but have not been compiled and deposited in a repository or database. Information is rather dispersed and difficult to access.
Target By the end of the project, a project website is established and linked to the GLOF risk database
By year 2 of the project, a project website is established and linked to the GLOF risk database
A database developed by the project and web-linked with all partner organizations is necessary and cannot be delayed till
24
developed under Outcome 1
developed under Outcome 1
end of the project. Rather it should start functioning by the year 2 if not earlier.
OUTPUT 4.2 Typo error Output 4.2. Project experiences disseminated to policy makers ad disaster management planners in Pakistan and the wider HKH region
Output 4.2. Project experiences disseminated to policy makers and disaster management planners in Pakistan and the wider HKH region.
Summary of Discussions held on Day Two
Introducing new policies or new policy guidelines will be beyond the scope of the project. Rather project will focus on making policy recommendations to all relevant ministries and sectors to mainstream GLOF across the board. Policies identified for mainstreaming of GLOF are National Conservation Strategy, National Water Management Policy, National Disaster Management Policy, National Environmental Action Plan, Poverty Reduction Strategy Paper, etc.
Synergies between and amongst various organizations emerged. For example for policy related work IUCN and KIU can converge their energies to translate valley based disaster management plans, land use plans, HVRA reports, socio-economic survey reports, best practices in disaster risk reduction and indigenous wisdom into policy recommendations and guidelines.
For baseline studies PMD, WWF, IUCN, UNDP, and SLFP can integrate their existing knowledge to develop a comprehensive baseline data that can serve as a baseline for the project. Similarly, imagery produced by GBDMA, WWF, FOCUS, Flood Commission, Nazir Sabir Expeditions, WAPDA and PMD can provide a solid remote sensing foundation for overlaying GLOF related information. A cohort of volunteers will be provided by PRCS and KIU for undertaking surveys and field visits. Together remote sensing, ground truthing and secondary data can provide a solid baseline for project by end of the second quarter of 2012 whereas remote sensing for baseline should be completed by third quarter of 2012.
Project has the potential to develop key partnerships for which it will enter into output based contracts with each organization. Bagrot and Drongagh valleys will serve as GLOF field schools for which project will enter into MoUs with valley wise community-based organizations. A need for proper training of volunteers was noted and KIU offered its facilities for providing short courses for GLOF sensitization. However, KIU will have to hire an instructor who has the required knowledge of GLOF, probably a glaciologist. All project team members, staff members of partner organizations, relevant government officials, community activists and media representatives will be sensitized about GLOF. Moreover, capacity building of GBDMA, PDMA (KPK), district authorities and communities is absolutely necessary and requires a need assessment exercise to determine the scope and extent of trainings.
Project duration of four years is too short for a comprehensive baseline and inventorying of all glaciers in Gilgit Baltistan and Chitral. Therefore, project baseline will be updated periodically and identification/prioritization of glacial hotspots will be reviewed annually in a port-project scenario. Field surveys will be conducted in close coordination with district authorities. The project can seek verification of data accuracy from community-based organizations, district authorities, GBDMA, and PMD.
25
Cooperation with international experts for glacial lake modeling and hazard zonation will be secured before the year 1 of project implementation because simulation modeling is a must before embarking upon HVRA and hazard zonation which leads to land use and disaster management planning. A peer review group will be formed for quality control and quality assurance of maps, plans, reports and any other knowledge products. The peer review group might be led by PMD.
For prevention of GLOF, physical intervention could take any shape but the preferred choice would be to drain a glacial lake by building a spill way or a drain. All other interventions like check dams, slow action dams, gavial walls, retention walls, tree plantations, and soil stabilization will be preferably in support of the drainage channel because due to the magnitude of the GLOF these interventions cannot provide protection on their own. EIAs will only be required for large size physical interventions whereas for all smaller or associated interventions IEEs will be sufficient.
Summary of Discussions held on Day Three
Workshop facilitator Faisal Farooq Khan started the morning session with a recap of day one. The community representatives of Bagrot and Drongagh valleys set the tone and direction of the discussions for the day by stressing that indigenous early warning systems are already in place. Importance of existing communication systems was highlighted by the office bearers of community-based organizations with a caution that modern early warning systems should be closely linked to the traditional practices and existing communication lines. A need for safe havens for the vulnerable communities was strongly felt and it was hoped that after simulation modeling and hazard zonation safe havens can be easily identified. Indigenous knowledge and traditional practices have to be documented for informing modern early warning systems.
Special watch groups consisting of herders, trekkers, guides, CERTs, etc. will be formed in each GLOF prone valley to monitor glacial lakes and debris flow during and after heavy precipitation. The watch groups will also be tasked with monitoring of the newly automated early warning systems. These watch groups will also serve as the link between automated early warning systems and traditional communication system for enhanced sustainability and reliability of new arrangements for GLOF safety.
A knowledge-attitude-practices survey will be conducted in every hot spot to map the existing behavior towards natural hazards and corresponding safety measures. Then on the basis of the findings, a GLOF communication strategy will be developed for raising awareness. New tools based on integrated education and communication methods will be developed to reach out to school children, college students, household women, elderly, and working women & men that daily commute to work outside their valleys.
A need for safe havens and associated stockpiles was strongly felt not only for GLOF related risks but also for other natural hazards such as flash floods caused by snow melt and flash floods, debris flow, avalanches, landslides and earthquakes. It was discussed that early warning systems should be developed in such a way that regardless of the nature of hazard, it should enable the vulnerable population to reach a nearby safe haven well in time.
It is possible that after project is informed by survey reports, spatial analyses, simulation models and newly realized ground realities the PSC might consider modifying the project design in the aftermath of the mid-term review to be held after two years of project implementation.
Project Cycle Operations Management
26
UNDP’s Finance & Administration focal point for the project Mr. Muhammad Saleem made a detailed presentation on PCOM to familiarize project team and the potential partner organizations with the standard operational procedures for cash flow management, procurement, recruitment, human resource management, inventory management, and overall reporting. Mr. Saleem also elaborated upon authority matrix for approval of expenditures and managing project bank account. In the nut shell he established that compliance with PCOM will enhance overall efficiency and effectiveness of the project.
Monitoring & Evaluation for Climate Change Risk Management
The M&E mechanism based on UNDP’s prescribed approach as detailed out in the project document was adopted by the participants in its true spirit after UNDP RTA Mr. Gernot Laganda emphasized on the importance of the baseline verification and criticality of monitoring and evaluation function for reducing GLOF related risks in the project area. The following passage of the project document was adopted in the inception workshop.
Project monitoring and evaluation (M&E) will be in accordance with established UNDP procedures and will carried out by the Project team, verified by the Ministry of Environment, Government of Pakistan and the UNDP Country Office in Islamabad. Dedicated support by the technical adaptation teams in the UNDP Regional Center for Asia/Pacific and UNDP New York will be provided on a regular basis. A comprehensive Results Framework of the project will define execution indicators for project implementation as well as the respective means of verification. A Monitoring and Evaluation system for the project will be established based on these indicators and means of verification.
A UNDP risk log will be regularly updated in intervals of no less than every six months in which critical risks to the project have been identified. Quarterly Progress Reports will be prepared by the Project team and verified by the Project Steering Committee. Annual Project Reports will be prepared to monitor progress made since project start and in particular for the previous reporting period. These annual reports include, but are not limited to, reporting on the following:
Progress made toward project objective and project outcomes - each with indicators, baseline data and end-of-project targets (cumulative);
Project outputs delivered per project Outcome (annual); Lessons learned/good practices; Annual expenditure reports; Reporting on project risk management.
Government authorities, members of Steering Committees and UNDP staff will conduct regular field visits to project sites based on the agreed schedule in the project's Inception Report/Annual Work Plan to assess first hand project progress.
In terms of financial monitoring, the project team will provide UNDP with certified periodic financial statements, and with an annual audit of the financial statements relating to the status of funds according to the established procedures set out in the Programming and Finance manuals. The Audit will be conducted by a legally recognized auditor of the Government, or by a commercial auditor engaged by the Government.
The project will undergo an independent Mid-Term Evaluation (MTE) at the mid-point of project implementation, which will determine progress being made toward the achievement of outcomes and identify course correction if needed. It will focus on the effectiveness, efficiency and timeliness of project implementation; will highlight issues requiring decisions and actions; and will present initial lessons learned about project design, implementation and management. Findings of this review will be incorporated as recommendations for enhanced implementation during the final half of the project’s term. A summative Terminal Evaluation will be conducted 3 months before project closure.
The budgeted Monitoring & Evaluation plan adopted from the project document is shown in table 4 below:
Type of M&E activity
Responsible Parties
Time frame Remarks
27
Inception Workshop(IW)
National ProjectCoordinatorUNDP CO
Within first 6 months IW conducted from 15 to 17 November,
2011
Inception Report Project Team UNDP CO
Within 1 month of IW IW ‘draft’ report submitted on 22 November 2011
Measurement of Means of Verification for project indicators
National Project Coordinator
Start, mid and end of project
To be done by end of the year 2011
Annual and Quarterly Progress reviews
Project TeamUNDP-CO
Quarterly and Annually First Quarterly Report will be due
in the second week of January 2012
National and Provincial Steering Committee Meetings
National Project Coordinator
UNDP CO
Following Project IW and subsequently at least once a year
PSC and PMCs will be notified in
December 2011 followed by
inaugural meetings
Periodic status reports
Project team To be determined by Project team and UNDP
Monthly short status reports
mainly for programme
communication
Technical reports Project team Hired
consultants as needed
To be determined by Project Team and UNDP
On need basis
Mid-term External Evaluation
Project team UNDP- CO External
Consultants (i.e. evaluation team)
At mid-point of project implementation.
Due by end of 2013
Terminal Report Project team UNDP-CO External
Consultant
At least 1 month before the end of the project
In April 2015
Audit UNDP-CO Project team
Yearly Report due in second quarter of
each year
Visits to field sites Project staff Government
representatives
At all stages of project implementation
On-going
28
Final Evaluation Independent external Consultants
Six months prior to the terminal tripartite review meeting.
Common Risks and Challenges in Climate Change Adaptation Projects
UNDP Regional Technical Advisor Mr. Gernot Laganda iterated that a climate change adaptation project helps a community to better understand and manage new and emerging risks in a changing environment. However, he cautioned about ten factors that could actually prove counterproductive if not managed properly, these are:
1. Institutional arrangements does not necessarily enable effective project delivery2. Lack of involvement by other ministries or departments can slow down project progress3. Poor or incomplete baseline information disable projects in measuring their success or failure 4. Projects get carried away with field activities losing focus on results5. Technical aspects of the intervention gets compromised because of logistical and social
pressures6. Breakdown of project’s communication with key stakeholders creates unnecessary
information gap and perceptional issues7. Remoteness of project location and hardship of actions isolate a project from larger risk
management scenario, which neutralizes its impact8. Absence of a phasing out or exit strategy makes a project unstable failing in realizing the
impact expected from its activities9. Overrating of achievements give a false sense of success which inhibits project team from
analyzing critical factors affecting the project10. Inability to reach out to the marginalized segments of the community can politicize a project
Towards the end of his presentation Mr. Laganda gave three principles of good project management, which are always keep the larger picture in mind, involve all stakeholders and communicate effectively with them.
Standard Risk Categories Each Project Should Monitor
UNDP Regional Technical Advisor Mr. Gernot Laganda emphasized that each project must monitor seven basic risks to ensure damage control through adaptive management. These seven categories of risks are as follows:
1. Environmental 2. Operational3. Political4. Financial5. Organizational6. Regulatory7. Strategic
He explained that classification of above mentioned risks is based on the level of control over the project. However, some risks are uncontrollable such as environmental, regulatory, and political risks whereas operational, financial, organizational and strategic risks are manageable.
UNDP Services to the Project and Adaptation Fund
UNDP’s Young Professional Officer Mr. Bilal Ali Qureshi highlighted the value of UNDP’s institutional support to the project and through the project to partner organizations. The following UNDP services documented in the project document were further stressed upon in the inception workshop for better understanding of the stakeholders.
29
Stage UNDP ServicesIdentification, Sourcing and Screening of Ideas
Provide information on substantive issues in adaptation associated with the purpose of the Adaptation Fund (AF).Engage in upstream policy dialogue related to a potential application to the AF.Verify soundness and potential eligibility of identified idea for AF.
Feasibility Assessment / Due Diligence Review
Provide up-front guidance on converting general idea into a feasible project/programme.Source technical expertise in line with the scope of the project/programme.Verify technical reports and project conceptualization.Provide guidance on AF Board expectations and requirements.Provide detailed screening against technical, financial, social and risk criteria and provide statement of likely eligibility against AF requirements.Assist in identifying technical partners.Validate partner technical abilities.Obtain clearances from AF.
Development & Preparation
Provide technical support, backstopping and troubleshooting to convert the idea into a technically feasible and operationally viable project/programme.Source technical expertise in line with the scope of the project/programme needs.Verify technical reports and project conceptualization.Provide guidance on AF expectations and requirements.Verify technical soundness, quality of preparation, and match with AF expectations.Negotiate and obtain clearances by AF.Respond to information requests, arrange revisions etc.
Implementation Technical support in preparing TORs and verifying expertise for technical positions.Participate, guide and train project teams on setting up operational plan for implementation of the project during inception phases of the approved project.Verification of technical validity / match with AF expectations of inception report.Provide technical information as needed to facilitate implementation of the project activities.Provide advisory services as required.Provide technical support, participation as necessary during project activities.Provide troubleshooting support if needed.Undertake a minimum of one technical support and oversight visit per year.Provide additional support and oversight missions as necessary.Provide technical monitoring, progress monitoring, validation, and quality assurance throughout.Allocate and monitor Annual Spending Limits based on agreed workplans.Return unspent funds to AF.
30
Stage UNDP ServicesEvaluation and Reporting
Provide technical support in preparing TOR and verifying expertise for technical positions involving evaluation and reporting.Participate in briefing / debriefing.Verify technical validity / match with AF expectations of all evaluation and other reportsUndertake technical analysis, validate results, and compile lessons.Disseminate technical findings
Institutional Cooperation
GLOF prevention or ensuring safety measures against a possible GLOF event requires involvement of a much larger group of stakeholders. UNDP is playing a role of a catalyst and standard bearer of quality of assurance. The Government of Pakistan through its Ministry of National Disaster Prevention and related Departments.
ICIMOD, PMD, WWF, IUCN, and ISDR all have contributed knowledge in the development of this project, its site selection and will continue to provide technical cooperation to the project team. Government’s Task Force on Climate Change reviews these technical inputs and shares its considerations with the decision makers and policy formulators. The project team has the opportunity make policy recommendation to TFCC through its National Project Director.
At operational level, organizations represented in the inception workshop have been invited by the National Project Manager to identify project outputs that can be delivered through them. Sheer involvement of a large number of local, national, regional and international organizations in the project warrants for one-on-one sessions with each of them. To this effect the facilitator suggested to have a series of organization specific planning sessions to firm up the indicative work plan presented by the NPM. It was agreed that the project team will have a round of sessions within one month of the inception workshop to streamline the annual work plan with partner organization’s input for submission to the PSC.
Two organizational structures PSC and PMC and a peer review process are available for supporting the project. Stakeholders expressed satisfaction over the composition and terms of reference of the PSC and PMCs, which are reproduced below.
A Project Steering Committee will be established to provide policy guidance to the project and monitor progress and performance. The PSC will facilitate inter-agency co-ordination of the project at the national level, provide avenues for maintaining inter-provincial linkages, and ensure that the lessons learned from implementation of the project are integrated into Pakistan’s overall adaptation programme. The Committee will be chaired by the Secretary, Ministry of Environment. Members will include , UNDP, DG (Environment), Designated National Authority for Adaptation Fund, ICIMOD, Economic Affairs Division, Pakistan Metrological Department, Gilgit-Baltistan Disaster Management Authority, Chitral Disaster Management Authority, the Project Manager, the Inspector General of Forests General Manager of AKRSP, IUCN-Pakistan, WWF-Pakistan and community member representatives. The office of the National Project Manager’s office will serve as the Secretariat to the Committee and will take responsibility for organizing meetings, recording minutes and ensuring that decisions are implemented.
The frequency of PSC meetings will be decided by the Chair, but initially the Committee will be convened twice a year. The first PSC meeting each year will follow the preparation of a detailed Annual Project Report (APR) on implementation. The second PSC meeting will be convened during the middle of each year. PSC meetings will normally be convened in Islamabad.
31
The PSC will be responsible for the following activities: Project review, monitoring and co-ordination; Approval of annual work plan (including training and consultancies) and annual budget,
including all components; Co-ordination of government actions and provision of policy guidance; Facilitating policy and legislative reform regarding management of GLOF as part of
adaptation measures Monitoring efforts to establish financial mechanism; Ensuring adherence to UNDP guidelines for the administration of project funds; and Ensuring linkages with the national environmental policies and adaptation plans.
Whereas a PMC will be formed in both Gilgit-Baltisan and Chitral to supervise project implementation, ensure that project targets are met, and monitor on-the ground impacts.The membershipof PMCs will be chaired by chief Gilgit-Baltistan Disaster Management Authority and Chief, Disaster Management Authority in Chirtal respectively. The membership will include project field managers, one local representative each of FOCUS, PRCS, SLF, ICIMOD, IUCN, WWF, district administration and targeted communities.
The Project Manager and a UNDP representative will also be members of both PMC’s. The PMC’s will meet at least twice a year at times and locations to be decided by the Chair. The Committees will be responsible for:
Monitoring the results of efforts to establish and strengthen GLOF related activities in the project sites;
Co-ordinating institutional arrangements for management of the activities; Co-ordinating policy and legislative development regarding GLOF Overseeing awareness and education activities; Ensuring that partner agency programmes are fully integrated into the project framework; Monitoring the results of the demonstration projects and supporting their integration into
wider development programmes; Monitoring technical assistance provided by the contracting agencies, including all
institutional strengthening services provided to local communities and government bodies; Monitoring all training activities; Ensuring linkages to regional GLOF activities; and Reviewing quarterly and annual work plans
An indicative institutional cooperation framework was presented by the facilitator to the inception workshop participants, which will be finalized after NPM locks the annual work plan 2012 with the partner organizations. The framework tentatively identifies each partner organization for delivery of a particular target along with corresponding out puts. The project team has identified partners at five different levels—community, district, provincial, national and international. The matrix also reflects at the need for strong operational coordination, both horizontally and vertically to ensure effective control over project deliverables. The Way Forward
Fifteen actions were identified that have to be taken within next six months:1 Appointment of Field Managers by end of November 20112 Circulation of the draft inception report to the key stakeholders December 20113 Notification of PSC by mid-December 20114 Consultations with KPK stakeholders by end of December 20115 Finalization of the annual work plans by first week of December 20116 Firming up of partner organization roles & responsibilities by third week of December 20117 Approval of annual work plans and budget by the PSC in December 20118 Signing of MoUs with partners organizations by end of January 2012
32
9 Notification of PMCs by mid February 201210 Establishment of field offices by end of March 201211 NOCs, if required to be obtained by March 201212 Designation of Drongagh and Bagrot valleys as GLOF Field Schools to serve as center of learning
for all vulnerable communities in Northern Pakistan in the first PSC meeting13 Collaboration with GLOF experts for simulation modeling, hazard zonation, and disaster
management/land use planning to be secured by March 201214 Review existing hazard/vulnerability maps/reports by March 201215 Baseline studies will be completed by June 201216 Remote sensing of Glaciers in Northern Pakistan to be completed by June 201217 Review of disaster management plans prepared by various partners for multiple hazards by June
2012
At the conclusion of the third day of the inception workshop, the chief guest Director General of Gilgit Baltistan Disaster Management Authority Mr. Muhammad Shigri delivered the concluding remarks and endorsed the project by highlighting the risks emanating from GLOF and extended GBDMA’s full cooperation to the project team. The Chairman of PRCS Mr. Asif Hussain, the guest of honor also spoke at the occasion. He offered services of the PRCS volunteers for data collection and field surveys.
33
Institutional Cooperation Framework
# Targets Institutional Cooperation OutputsProject Community District Provincial Federal INGOs
1 All GLOF risk sites in Pakistan are identified and inventoried in a central, web-based GLOF risk database
NPD CBOsDeputy
Commissioner
GBDMA,KPDMA, UoP, KIU
NDMA, PMD, SUPARCO,
GCISC, WAPDA, NARC,
PCRWR
UNDP, FOCUS, WWF,
ICIMOD
1.2
2 All GLOF risk areas in Pakistan are covered by remote sensing information
NPD CBOsDeputy
Commissioner
GBDMA,KPDMA, UoP, KIU
NDMA,PMD,
SUPARCO, GCISC
WWF,ICIMOD, FOCUS
1.2
3 At least 80% of disaster management institutions in Gilgit-Baltistan and Chitral (national, provincial and district level) are able to access, interpret and use GLOF risk information for planning purposes
NPM CERT/DRRCDeputy
Commissioner
GBDMA,KPDMA, UoP, KIU
NDMA, PRCS
WWF,ICIMOD, FOCUS
1.1
4 At least 10 other GLOF risk reduction initiatives from other countries are analyzed to inform risk assessment and –planning under the proposed project
NPM CERT/DRRCDeputy
CommissionerGBDMA, KPDMA
NDMA
UNDP,ICIMOD, UNISDR,
WWF
2.1
34
# TargetsInstitutional Cooperation
OutputsProject Community District Provincial Federal INGOs
5 At least 2 GLOF-prone mountain valleys are analyzed by a detailed hazard zonation and vulnerability assessment
NPD CERT/DRRC EDO WorksGB PWD, KP PWD
NESPAKAKPBSP, FOCUS, ICIMOD
1.2 & 2.2
6 At least 2 GLOF-prone mountain valleys are comprehensively covered by a GLOF Early Warning system
NPM CERT/DRRCDeputy
CommissionerGBDMA, KPDMA
NDMA, PMD, PRCS
ICIMOD, FOCUS, 1.2, 3.1 &3.2
7 100% of the national and 90% of district and community authorities in the Gilgit-Baltistan and Chitral regions are able to prioritize and plan measures to minimize potential losses from GLOFs
NPD CERT/DRRCDeputy
Commissioner
GBDMA, KPDMA, P&DD,
Finance D
NDMA, PMD
WWF,IUCN
1.1, 1.2 & 2.2
8 The GLOF risk from at least 2 potentially dangerous glacier lakes in Gilgit-Baltistan and Chitral is successfully reduced
NPM CERT/DRRCDeputy
Commissioner
GBDMA, KPDMA, P&DD,
Finance D, GB PWD, KP PWD
NDMA,FWO
ICIMOD, AKPBSP,
2.1, 2.2, 3.1, 3.2, & 3.3
35
Annex # 1: Agenda of Inception Workshop
“Reducing Risks and Vulnerabilities from Glacier Lake Outburst Floods (GLOFs)” Date: 15-17 November 2011 Venue: Serena Hotel Gilgit
Day-01: 15th November 2011Time Details of Activity Resource Person
900-930 Arrival and Registration of the participants Registration/Khurshid Khan930-945 Arrival of the Chief Guest Received by Project and
UNDP Team945-950 Recitation from the Holy Quran Any Participant950-1000 Welcome Remarks National Project Manager
GLOF Project1000-1030 Briefing on the GLOF Project and Inception
Workshop Project Implementation Arrangements
National Project Director GLOF Project
1030-1045 Statement By UNDP Representative Assistant Country Director UNDP Pakistan
1045-1100 Regional Context of GLOF Project Regional Technical Advisor UNDP
1100-1110 Statement by GB-DMA Director General/ Assistant Director GBDMA
1110-1130 Inaugural Speech by Chief Guest Chief Guest1130 Vote of Thanks National Project Director
GLOF ProjectRefreshment All Participants
1200-1700:Field Visit to Bagrot Valley Project Site (Separate Agenda to be shared)
Day-02: 16th November 2011Time Details of Activity Responsibility
Working Session-1: Project Introduction0900-930 Introduction of Participants; All participants will
introduce their current roles and responsibilitiesAll Participants
0930-1000 Workshop Objectives and Outline Faisal Farooq Khan1000-1020 Presentation on Project Objectives, Outputs,
Outcomes National Project Manager GLOF Project
1020-1100 Project Implementation Arrangements National Project Director GLOF Project
1100-1120 Tea BreakWorking Session-2: Log Frame Verification Exercise
1120-1300 Log Frame Presentation & Review Faisal Farooq Khan/ Bilal Ali Qureshi UNDP
1300-1400 Lunch Break1400-1430 Log Frame Review Faisal Farooq Khan/Bilal
36
UNDP1530-1545 Tea Break1545-1700 Log Frame Review continued Faisal Farooq Khan/Bilal
UNDPDay-03: 17th November 2011
Time Details of Activity Responsibility900-930 Recap of Day-1 and Highlights of the Change Faisal Farooq Khan/Bilal
UNDPWorking Session-3: Standard Procedures of Project Implementation
930-1030 Recruitment, Procurement and Financial Management for UNDP assisted projects
UNDP/Mohammad Saleem
1030-1100 UNDP AF Monitoring & Evaluation Requirements, and Risk Management Strategy
Regional Technical Advisor UNDP
1100-1120 Tea BreakWorking Session-4: Work Planning & Workshop Conclusion
1120-1220 Presentation on Project Work Plan, and Work Plan for the first yearInstitutional Cooperation
National Project Manager GLOF Project
1220-1300 Role & Responsibilities of Implementing Partners, Role of UNDP and GLOF Project
UNDP/Bilal Ali Qureshi
1300-1340 Next Steps and Wrap Up. How can you participate in GLOF Project?
Faisal Farooq Khan
1340-1400 Concluding Remarks Director General/Assistant Director GBDMA
1400 Vote of Thanks Project StaffLunch
37
Annex # 2: Proposed Revised Project Results Framework
Project Strategy Objectively verifiable indicators
Goal To enhance adaptive capacity to prevent climate change-induced GLOF disasters in Pakistan
Indicator Baseline TargetSources of verification
Risks and Assumptions
Objective: To reduce climate change-induced risks of Glacial Lake Outburst Floods (GLOFs) in Gilgit-Baltistan and Chitral
No. of potentially dangerous glacier lakes in Gilgit-Baltistan and Chitral
No. of institutions with increased capacity to minimize human and material losses from GLOF events
Number of people living in Gilgit-Baltistan and Chitral suffering losses from GLOF
There are 52 potentially dangerous lakes in Gilgit-Baltistan and Chitral areas.
35 destructive outburst floods are recorded in Gilgit-Baltistan and Chitral areas in last two hundred years.
The GLOF risk from at least 2 potentially dangerous glacier lakes in Gilgit-Baltistan and Chitral is successfully reduced
At least 80% of disaster management institutions in Gilgit-Baltistan and Chitral (national, provincial and district level) are able to access, interpret and use GLOF risk information for planning purposes
At least 2 GLOF-prone mountain valleys are comprehensively covered by a GLOF Early Warning system
Questionnaire-based surveys (QBS)/ Interviews at the beginning, mid-term and end of the project
Impact assessment at the end of the project
Satellite imagery of glacier lakes and vulnerable sites before and after the project
The political situation stays stable throughout the project duration.
Stakeholders are able to perceive reductions in vulnerability over the time-scale determined by project duration
No flooding disasters in target communities occur throughout the project lifetime
Outcome 1: Strengthened Institutional capacities to implement policies, plans and investments that prevent human and material losses from GLOF events in vulnerable areas of Northern Pakistan
No. of targeted institutions with increased capacity tominimize exposure to GLOF risks
Number of policy recommendations made to address GLOF risks or adjusted to incorporate GLOF risks
National, provincial and local disaster management institutions and development planners are unable to design, finance and analyze GLOF risk reduction measures on the basis of reliable, comprehensive information
By the end of Year 3, 100% of the national and 90% of district and community authorities in the Gilgit-Baltistan and Chitral regions are able to prioritize and plan measures to minimize potential losses from GLOFs
By the end of the project, at least two policies have been reviewed and/or revised to address or incorporate GLOF risk reduction
QBS, training protocols and attendance lists
Review of CC, DRM and development policies and plans at the national, district, and community levels
Government remains supportive to link longer-term climate change planning with current disaster risk management initiatives
38
Output 1.1: Policy recommendations and guidelines to address GLOF risks in northern Pakistan institutionalized
Number of policy recommendations made to address GLOF risks or adjusted to incorporate GLOF risks
Climate change risks are mentioned in the current Task Force on Climate Change (TFCC) report
No comprehensive disaster management guidelines addressing GLOF exist for the Gilgit-Baltistan and Chitral regions
By the end of the project, a Disaster Management Act is formulated that incorporates GLOF and other climate risk issues
By the end of the project, existing DRM guidelines integrate longer-term climate change risk planning
Review of Disaster Management Act, DRM policies, plans, and institutional structures
Government continues to support climate-resilient DRM.
Output 1.2: Indicators and criteria for GLOF vulnerability developed and systematically applied to enable priority allocation of risk reduction efforts and investments
Number of potentially GLOF-prone communities that are integrated in a centralized, web-based GLOF risk database
Availability of a government action plan to address GLOF risks in Pakistan, starting from the highest risk zones and the most vulnerable communities
No comprehensive database and action plans exist for addressing GLOF risk in Pakistan
By year 1 of the project, all GLOF risk sites in Pakistan are identified and inventoried in a central, web-based GLOF risk database
By the end of the project, a comprehensive disaster risk reduction plan is available to address the biggest GLOF threats in the most vulnerable communities
GLOF risk database,
Satellite imagery
Action plan document
Turnover of staff does not counteract benefits of capacity building efforts
NOCs are obtained from relevant authorities for accessing restricted sites
Outcome 2: Improved access of disaster management planners and policy makers to knowledge, information and research on GLOF risks
No. and type of government-led initiatives which conduct and update risk and vulnerability assessments
Level of knowledge about GLOF exposure and sensitivity in northern Pakistan is very limited
By the end of the project, 95 percent of population in the two targeted communities has sufficient knowledge about GLOF risks and mitigation measures
QBS
Surveys on communication channels
Continued government support for the project
Output 2.1:Systematic engagement of the project with global and regional research networks and centres working on GLOF issues
Number of specialized institutions actively connected in the exchange of relevant technical information that can inform GLOF vulnerability analysis and risk reduction
Regional platform
established by the
regional GLOF
risk reduction
project, with
punctual
interaction until
the project has
By the end of year 2, at least 10 other GLOF risk reduction initiatives from other countries are analyzed to inform risk assessment and –planning under the proposed project
Regional platform established by the regional GLOF risk reduction project, with punctual interaction
Comparative analysis report
MoUs / agreements
Website linkages
International conference
Other GLOF projects have codified their lessons in an accessible format
Relevant partners remain interested in cooperation
39
planningended
Output 2.2:Risk and hazard maps for mountain valleys with the highest GLOF risk and exposure of lives, livelihoods and infrastructure
Number of GLOF hazard and vulnerability maps for GLOF-prone mountain valleys
No comprehensive
risk and
vulnerability maps
for mountain
valleys with
highest GLOF
risks available
By year 1, all GLOF risk areas in Pakistan are covered by remote sensing information
By year 2, GLOF specific simulation models for at least 2 GLOF prone mountain valleys are developed
By year 2, at least 2 GLOF-prone mountain valleys are analyzed by a detailed hazard zonation and vulnerability assessment
Hazard maps
Vulnerability maps
Risk maps
Availability of field staff to conduct vulnerability assessment
Availability of unrestricted satellite imagery
No natural disasters in project area
Outcome 3: Reduced human and material losses in vulnerable communities in the Northern areas of Pakistan through GLOF early warnings and other adaptation measures
Number of vulnerable households in Bagrot in Gilgit-Baltistan and Drongagh valley in Chitra covered by a GLOF early warning system
Number of physical assets strengthened or constructed to withstand or mitigate the effects of GLOF events
No GLOF early warning system for Bagrot and Drongagh Valley in place
Vulnerable households are not able to receive and react to GLOF early warning messages
No physical structures in place to mitigate the effect of GLOF events
By the end of the project, 90% of households in target communities are able to receive and respond to early warnings and take the appropriate actions following the warning
By the end of the project, at least 2 targeted engineering structures (spurs, protective works, check dams, slope stabilization, spill ways and water drainage etc) have been established to reduce the effects of GLOF events on livelihood assets
QBS with households
Site visits before/after the project
No tampering with early warning system installations
Community workforce available to support engineering measures
Output 3.1: Preparedness actions for vulnerable communities conducted to reduce risks from GLOF events
Percentage of targeted population aware of GLOF impacts and appropriate responses to the threat
Limited awareness by vulnerable communities in the Gilgit-Baltistan and Chitral valleys on GLOF risks and risk reduction measures
By the end of the project, at least 90% of households in the target area are aware of the functionality of the GLOF EWS and able to respond to warning signals
By the end of the project, at least 2 full-scale GLOF early warning drills have been conducted, involving all households in the target communities
QBS
Video of mock drills, simulation protocol
Debriefing notes
Messages are delivered in an appropriate way to enhance awareness, receptiveness and understanding
Messages are delivered in a concerted, coordinated and consistent manner
Output 3.2: A community based system for GLOF risk monitoring &
Number of households in Bagrot and Drongagh valley reached
No GLOF early
warning system
for Bagrot and
By the end of the project, 90% of households in each target valley are able to receive and respond
QBS with households
Mock drill protocols
No tempering with the early warning system installations,
40
early warning in priority communities
by a GLOF early warning system
Percentage of households receiving and responding to warnings in time to avoid human losses
Drongagh
valleys in place
Vulnerable
households are
not able to
receive and react
to GLOF early
warning
messages
to GLOF early warning signals and take the appropriate actions following the warning.
By the end of the project , at least 2 CBOs are trained in the operation and maintenance of the EWS and ensure its continued functionality
A special watch group for each GLOF prone valley will be formed to establish a new or to strengthen an existing Early Warning System
Field visits to EWS sensor, relay and communication sites
GLOF watch group meeting attendance and note for records
Functioning backup systems in place
Valley wide traditional communication systems are in place
Output 3.3: Targeted GLOF risk reduction measures such as check dams, spill-ways, slope stabilization or controlled drainage established in Bagrot and Drongagh valleys
No. of physical assets strengthened or constructed to withstand or mitigate the effects of GLOF events
No risk reduction measures for GLOF in place in the target sites
By the end of the project, concrete engineering measures are in place to reduce the impact of GLOF events on vulnerable communities in each target valley (as appropriate: effective drainage systems, check dams, mini dams, ponds, spill ways, slope stabilization, tree plantation, controlled drainage)
Field visits to engineering structures
Structural designs
Completion drawings
Communities are receptive to the adoption of mitigation measures and participate actively in construction efforts
IEE yields positive result for the mitigation measures under consideration
Outcome 4: Project experiences documented and replicated
Number of proposals, papers, and other documents that incorporate learning from the project
Experiences regarding climate change-induced GLOF mitigation and preparedness in Pakistan have not been systematically captured and shared
By the end of the project, at least 2 other GLOF mitigation and early warning initiatives or studies draw on learning from experiences in Pakistan
Proposals,
papers, knowledge products, and other documents referring to AF-funded GLOF project in Pakistan
Political circumstances in Pakistan are conducive for international exchange on GLOF mitigation and preparedness efforts
Output 4.1. Technical knowledge and project lessons documented for use in future initiatives
Number of technical documents capturing project knowledge
Number of knowledge products
Inadequate technical papers capturing project knowledge available
Inaccessibility to maps, reports, remote imagery and case studies
By the end of the project, all technical decisions and lessons are captured in dedicated reports
By the end of the project, a GLOF risk reduction manual is available and disseminated both nationally and internationally
Technical briefs prepared by the project
Manual
Project website
Technical knowledge is consistently codified and reflected upon over the lifetime of the project
41
By year 2 of the project, a project website is established and linked to the GLOF risk database developed under Outcome 1
Output 4.2. Project experiences disseminated to policy makers and disaster management planners in Pakistan and the wider HKH region.
Number of organizations actively involved in knowledge transfer within and across district borders
Number of policy makers and disaster management practitioners within and outside of Pakistan who are aware of the project and willing to adopt lessons learned
No systematic knowledge transfer on GLOF risks from Pakistan to other countries
By the end of the project, at least 1 international exchange visit between GLOF risk reduction projects has taken place
By the end of the project, DRM planning authorities of at least 3 GLOF-prone districts in Pakistan visit the target sites with a view on replication of the project approach in other vulnerable sites
By the end of the project, at least 2 project dissemination workshops have been conducted in Pakistan, with attendance by stakeholders from all GLOF-prone districts
Study visit report
Site visits, consultation protocols
Workshop proceedings
Other regions and countries believe experiences from the project will be valuable for future GLOF mitigation and preparedness initiatives
Project is sufficiently visible to other GLOF-prone districts
Project is able to mobilize follow-up financing for replication and up scaling.
42
Annex # 3: Annual Work Plan
1st Year Annual Work Plan
Goal To enhance adaptive capacity to prevent climate change-induced GLOF disasters in Pakistan
Objective To reduce climate change-induced risks of Glacial Lake Outburst Floods (GLOFs) in Gilgit-Baltistan and Chitral
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Outcome 1: Strengthening Institutional Capacities to implement policies, plans and investments that prevent human and material losses from GLOF events in vulnerable areas of Northern Pakistan
Output 1.1: Policy recommendations and guidelines to address GLOF risks in Northern Pakistan institutionalized
1.1.1 Introductory Meetings with line departments, potential partners and stakeholders
03
NPD / NPM
UNDP
1.1.2 Desk review of literature and secondary data
01
NPM UNDP, PMD, WAPDA, Flood Commission, PCRWR, SUPARCO, NARC, , NDMA, WWF, KIU, ICIMOD, UOP, FOCUS
1.1.3 Knowledge, Attitude and Practice (KAP) Studies (Pre Intervention Surveys)
03
NC PS, DMCs, FOCUS, PRCS, WWF, SLF, KIU, CBOs, PCRWR AKRSP, PMD, FD,
1.1.4 Developing IEC Material and Introductory Sheets on GLOF Issues
10
NC PS, FOCUS, PRCS, WWF, NDMA, GBDMA, KPDMA
43
1st Year Annual Work Plan
Goal To enhance adaptive capacity to prevent climate change-induced GLOF disasters in Pakistan
1.1.5 Capacity Need Assessment Meetings & Capacity Development Action Plan for partner organizations and communities 03
NPM DMCs, CBOs, FOCUS, WWF, AKPBSP, NDMA, KIU, PRCS,
44
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Outcome 1: Strengthening Institutional Capacities to implement policies, plans and investments that prevent human and material losses from GLOF events in vulnerable areas of Northern Pakistan
Output 1.1: Policy recommendations and guidelines to address GLOF risks in Northern Pakistan institutionalized
1.1.6 Develop GLOF Communication & Awareness Raising Strategy.
01
NC NPM & PS
1.1.7 Review of governmental policies and plans
Move to 2013
NPM MoDM, PC, relevant Depts.
1.1.8 Establish an inter-agencies working group to incorporate climate change risk management considerations into existing disaster management policy frameworks and new legislation.
01
MoNDM Prime Minister’s Secretariat
1.1.9 Media Launch
01
NC PS, UNDP, MoNDM
1.1.10 Media Campaigns for Mass Awareness
03
NC PS, GBDMA, PDMA, PRCS, FOCUS, AKRSP, WWF,NDMA,
45
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Output 1.2: Indicators and criteria for GLOF vulnerability developed and systematically applied to enable priority allocation of risk reduction efforts and investments
1.2.1 Develop criteria for GLOF specific Hazard Vulnerability Risk Assessment (HVRA) to expand the Baseline 02
ICIMOD PMD, WWF, FOCUS, Dy. Comm., NDMA, project Staff, PRCS
1.2.2 Develop an expanded inventory of potential hazardous GLOF sites (Identifying GLOF Hot Spots) on the basis of Secondary Data, Remote Sensing and Ground Verification
01
ICIMOD MoNDM, PMD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO, NARC, PCRWR, CBOs
1.2.3 Develop scientific indicators for monitoring GLOF
01
PMD MoNDM, ICIMOD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO
1.2.4 Prioritize GLOF hotspots on the basis of HVRA and inventory update
PMD ICIMOD, MoNDM
1.2.5 Identify potential safe havens on the basis of existing disaster management plans and indigenous knowledge
Dy. Comm.
PS, WWF, ICIMOD, Focus, GBDMA, PDMA
1.2.6 Development of GLOF knowledge repository
01
MoNDM MoNDM, PMD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO, NARC, PCRWR, CBOs
46
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Outcome 2: Improve Access of Disaster Management Planners and Policy Makers to knowledge, information and research on GLOF risks
Output 2.1: Systematic Engagement of the project with global and regional research networks and centres working on GLOF issues
2.1.1 Engage selected organizations for remote sensing, GIS mapping and HVRA
01
NPM MoDM, ICIMOD, UNDP, WWF, FOCUS
2.1.2 Conduct remote sensing of all identified glaciers in Northern Pakistan for identification of a plausible GLOF sites 01
PMD Project Staff, ICIMOD, NDMA, GCISC, International Expert, WWF
2.1.3 Site visits by a multidisciplinary team to Bagrot & Drongagh for ground verification and scoping
PMD Project Staff, ICIMOD, NDMA, GCISC, International Expert, WWF
2.1.4 Conduct GLOF Risk & Vulnerability Assessment of Bagrot and Drongagh valleys
02
WWF ICIMOD, SLF, DDO, PMD, PCRWR, DMCs, Project Staff
2.1.5 Identify and establish working relations with organizations and research groups working on GLOF in the Alps, HKH and Andes region
NPM ICIMOD, MoDM UNDP, UNISDR
2.1.6 Experience sharing and lesson learning exercise/visit to regional and global networks & centers working on GLOF
NPD, NPM
MoNDM
47
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Output 2.2: Risk and hazard maps for mountain valleys with the highest GLOF risk and exposure of lives, livelihoods and infrastructure
2.2.1 Develop GIS and Google maps of the valley and the two districts
02
WWF ICIMOD, WWF, if required
2.2.2 Develop new GLOF Hazard Maps for Bagrot and Drongagh
02
WWF ICIMOD, PMD, PRCS, WWF, DDO, PS, FOCUS, DMCs
48
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Outcome 3: Reduce Human and Material Losses in vulnerable communities in the Northern Areas of Pakistan through GLOF Early Warnings and other adaptation measures
Output 3.1: Preparedness actions for vulnerable communities conducted to reduce risks from GLOF events
3.1.1 Dialogues and meetings with vulnerable communities to sensitize them about GLOF related hazards, preparedness and adaptation 06
FM NPM, NPD
3.1.2 Mutually agree upon and develop standard operating procedures and command structures for establishing a Disaster Risk Reduction Committee, Early Warning System, and Emergency Response Cells
NC PS, ICIMOD, Dy. Commissioner, CBO,
3.1.3 Provisional Emergency Response Cells established/strengthened under the command of a Dy. Commissioner in two targeted Districts 02
Dy. Comm.
GBA, GKPK, GBDMA, KPDMA
Output 3.2: A community based system for GLOF risk monitoring & early warning in priority communities
3.2.1 Documentation of indigenous knowledge o n prevailing natural hazards and means to trigger an early warning 02
NC CBO, Dy. Comm. WWF, FOCUS
3.2.2 Study existing community-based Early Warning Systems in place for flash floods, debri flow, and landslides to mainstream GLOF 02
NC DMCs, Project Staff, FOCUS, PRCS, Targeted Communities
3.2.3 Ensure Early Warning Systems are built upon existing lines of communications and benefit from indigenous knowledge 02
NC ICIMOD, DMCs Project staff, FOCUS, PRCS,
3.2.4 Establish valley specific Disaster Risk Reduction Committees
02
CBOs NPM, FOCUS, PRCS, WWF
49
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
3.2.5 Community awareness raising & sensitization training workshops on GLOF Issues
02
ICIMOD DMCs FOCUS AKRSP, PRCS, WWF, SLF, DDO, LSO, PS
3.2.6 Establishment of community-based natural hazard watch groups in Bagrot and Drongagh
02
FM WWF, FOCUS
3.2.7 Notification of safe havens and safe access routes by the Deputy Commissioner on CBOs request 02
CBO FOCUS, WWF, Dy. Commissioner
3.2.8 Opening of a community account for stockpiling, inventory management and O&M of the safe havens. 02
CBO FM
Output 3.3 Targeted GLOF risk reduction measures such as check dams, spill-ways, slope stabilization or controlled drainage established in Bagrot and Drongagh valleys
3.3.1 Identification of interventions for structural adaptation in Bagrot and Drongagh Valleys
10
PS & TC DMCs, PMD, WWF, FOCUS, AKRSP, SLF, PRCS, LSO, VCC, DDO
Outcome 4: Project Experiences Documented and Replicated
Output 4.1. Technical knowledge and project lessons documented for use in future initiatives
4.1.1 Develop project website
01
Project Staff
CF, DMCs, FOCUS, WWF, KIU, ICIMOD, NDMA, PRCS
4.1.2 Develop Case Studies to document Best Practices
02
PS CF
50
4.1.3 Periodic monitoring reports on quarterly, biannual and annual basis
06
NPM NPD
4.1.4 Annual Project Digest
01
NC NPD
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION
Timeline Partner Organization(s)
No Jan Feb Mar Apr May
Jun Jul Aug Sep Oct Nov Dec
Lead Supportive
Outcome 5: Project Management Unit and Monitoring & Evaluation
5.1 Hiring of Remaining Project Staff
NB
UNDP EAD & MoDM
5.2 Establish Project Offices
03
PS MoDM & UNDP
5.3 Procurement of Equipment & Furniture
NB
PS MoDM & UNDP
5.4 Notification of Project Steering Committee (PSC)
01
MoDM
Project Staff
5.5 Project Steering Committee Meetings
02
MoDM
UNDP, DMAs, Project Staff
5.6 Notification of Project Management Committees (PMC)
02
DMAs Project Staff MoDM & UNDP
5.7 Project Management Committee Meetings
04
DMAs Project Staff MoDM & UNDPWWF, FD Focus PRCS SLF AKRSP EPA
5.8 Field Monitoring Visits
12
PS & UNDP
SLF WWF DDO LSOs WWF DMAs FDs
51
5.9 Monthly Progress Review Meetings
14
Project Staff
UNDP MoDM
5.10 Quarterly Review Meeting
04
Project Staff
DMAs UNDP DDO LSOs
5.11 Annual Progress Review & Planning Workshops
03
Project Staff
PDMAs UNDP & MoDM DDO LSOs VCC
52
Annex # 4: Four Year Project Plan
GLOF Work Plan
Goal To enhance adaptive capacity to prevent climate change-induced GLOF disasters in Pakistan
Objective To reduce climate change-induced risks of Glacial Lake Outburst Floods (GLOFs) in Gilgit-Baltistan and Chitral
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY COMPLETION
PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Outcome 1: Strengthening Institutional Capacities to implement policies, plans and investments that prevent human and material losses from GLOF events in vulnerable areas of Northern Pakistan
Output 1.1: Policy recommendations and guidelines to address GLOF risks in Northern Pakistan institutionalized
1.1.1 Introductory Meetings with line departments, potential partners and stakeholders
03
NPD/NPM UNDP
1.1.2 Desk review of the literature and secondary data to recommend mainstreaming of GLOF in governmental plans and policies 01
IUCN UNDP, PMD, FOCUS, NDMA, WWF, KIU, SLF, ICIMOD, UoP, PRCS
1.1.3 Knowledge, Attitude and Practice (KAP) Studies in Bagrot and Drongagh valleys
02
NC PS, DMAs, FOCUS, PRCS, WWF, SLF, KIU,LSO, DDO, AKRSP, PMD, FD, VCC
1.1.4 Developing IEC Material and Introductory Sheets on GLOF Issues
03
NPM DMCs, DDO, FOCUS, WWF, AKPBSP, NDMA, KIU, PRCS,
53
GLOF Work Plan
Goal To enhance adaptive capacity to prevent climate change-induced GLOF disasters in Pakistan
1.1.5 Capacity Need Assessment Meetings & Capacity Development Action Plan for each of the field based partner organizations 10
NC PS, FOCUS, PRCS, WWF, NDMA,
1.1.6 Develop GLOF Communication & Awareness Raising Strategy
01
NC NPM & PS
1.1.7 Establish an inter-agencies working group to incorporate climate change risk management considerations into existing disaster management policy frameworks and new legislation
01
MoNDM Prime Minister’s Secretariat
1.1.8 Media Launch
01
NC PS, UNDP, MoNDM
1.1.9 Media Campaigns for Mass Awareness
03
NC PS, GBDMA, PDMA, PRCS, FOCUS, AKRSP, WWF,NDMA
1.1.10 Develop GLOF Communication & Awareness Raising Strategy
01
NC NPM & PS
1.1.11 Develop institution specific action plans and standard operating procedures for prevention of GLOF related disasters 08
NC NDMA, PDMA, GBDMA, FOCUS, FWO, WWF, SLF, PRCS
1.1.12 Strengthened indigenous early warning systems to prepare vulnerable communities
02
FM FOCUS, WWF
1.1.13 Linkages between (District Management Committees) DMCs and DRRCs established and strengthened. 02
FM MoNDM, GBDMA, KPKPDMA
1.1.14 Develop and institutionalize comprehensive GLOF risk management guidelines at the district level
01
NC ICIMOD, WWF, FOCUS, PMD, Dy. Comm.
1.1.15 Strengthening of relevant line departments for supporting district administrations addressing GLOF risk 02
NC ICIMOD, WWF, FOCUS, PMD, Dy. Comm.
54
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY COMPLETION
PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Output 1.2: Indicators and criteria for GLOF vulnerability developed and systematically applied to enable priority allocation of risk reduction efforts and investments
1.2.1 Develop an expanded inventory of potential hazardous GLOF sites (Identifying GLOF Hot Spots) on the basis of Secondary Data, Remote Sensing and Ground Verification
02
PMD ICIMOD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO
1.2.2 Develop scientific indicators for forecasting and monitoring GLOF
01
PMD MoNDM, ICIMOD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO
1.2.3 Prioritize GLOF hotspots on the basis of HVRA and inventory update on periodic basis
04
Dy. Comm. MoNDM, ICIMOD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO
1.2.4 Identify potential safe havens on the basis of existing disaster management plans and indigenous knowledge 02
CBOs PS, WWF, ICIMOD, FOCUS, GBDMA, PDMA
55
1.2.5 Conduct KAP surveys in “new” hotspot areas
03
NC WWF, FOCUS
1.2.6 Notify safe havens on the basis of existing land use practices, hazard maps and new findings
03
Dy. Comm. PS, WWF, ICIMOD, FOCUS, GBDMA, PDMA
1.2.7 Mainstream GLOF prevention/protection in valley or/and district based disaster management and emergency response plans 02
Dy. Comm. PS, WWF, ICIMOD, Focus, GBDMA, PDMA
1.2.8 Ensure allocation of public sector funding in the annual development plans of vulnerable districts
01
P&D Dept. CS, Fin Secy., PC, donor budgetary support
1.2.9 Development of GLOF knowledge repository
01
MoNDM ICIMOD, PMD, WWF, SLF, NDMA, KIU, PS, FDs, EPAs, CBOs, WAPDA, SUPARCO, NARC, PCRWR, CBOs
56
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
FOLLOW UP/ PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Outcome 2: Improve Access of Disaster Management Planners and Policy Makers to knowledge, information and research on GLOF risks
Output 2.1: Systematic Engagement of the project with global and regional research networks and centers working on GLOF issues
2.1.1 Identify and establish working relations with organizations and research groups working on GLOF in the Alps, HKH and Andes region 01
NPM ICIMOD, MoNDM UNDP, UNISDR
2.1.2 Engage selected organizations for remote sensing, GIS mapping and HVRA
NPM MoNDM, ICIMOD, UNDP, WWF, FOCUS
2.1.3 Site visits by a multidisciplinary team to Bagrot & Drongagh for ground verification and scoping
NPD PMD, ICIMOD, GISC, WWF, Dy. Comm, UNDP, GBDMA, WAPDA, KPDMA, Flood Commission
2.1.4 Develop criteria for GLOF specific Hazard Vulnerability Risk Assessment (HVRA) to expand the Baseline 01
ICIMOD PMD, WWF, FOCUS, Dy. Comm., NDMA, project Staff, PRCS
2.1.5 Conduct GLOF Risk & Vulnerability Assessment of Bagrot and Drongagh valleys
WWF ICIMOD, SLF, DDO, PMD, PCRWR, DMCs, PS
57
2.1.6 Conduct simulation modeling of GLOF in Drongagh and Bagrot valleys.
IC PS, MoNDM, ICIMOD, UNDP, WWF, FOCUS
2.1.7 Develop new or modify existing disaster management plans in accordance with the valley based GLOF models
IC PS, MoNDM, ICIMOD, UNDP, WWF, FOCUS, Dy. Commissioner
2.1.8 Develop new or modify existing land use practices in accordance with the approved disaster management plans for each valley
CBOs PS, GCISC, NARC, Dy. Commissioner
2.1.9 Experience sharing and lesson learning exercise/visit to regional and global networks & centers working on GLOF
NPD, NPM MoNDM
2.1.10 International conference on GLOF risk management in collaboration with ICIMOD, WWF, IUCN, FOCUS, UNDP, UNISDR, etc.
NC NPD, MoNDM
58
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION/FOLLOW UP
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Output 2.2: Risk and hazard maps for mountain valleys with the highest GLOF risk and exposure of lives, livelihoods and infrastructure
2.2.1 Conduct remote sensing of all identified glaciers in Northern Pakistan for identification of a plausible GLOF sites 01
PMD Project Staff, ICIMOD, NDMA, GCISC, International Expert, WWF
2.2.2 Develop hazard maps of Bagrot and Drongagh valleys
02
PMD Project Staff, ICIMOD, NDMA, GCISC, International Expert, WWF
2.2.3 Mainstream GLOF risks in land use practices in Bagrot and Drongagh valleys and develop disaster management plans 02
WWF ICIMOD, PMD, PRCS, WWF, DDO, Project Staff, FOCUS, DMCs
2.2.4 Replicate valley based disaster management planning process to prepare district wide disaster management plans in Gilgit and Chitral. 02
Dy. Comm.PMD, PCRWR, WWF, FOCUS DMCs & PRCS, ICIMOD
2.2.5 Develop detailed GIS and Google maps of the valley and the two districts
02
PMD ICIMOD, WWF, if required
59
2.2.6 Develop a GLOF Atlas of Pakistan
01
GCISC PMD, ICIMOD, WWF, WAPDA, NARC, Flood Commission, SUPARCO, PCRWR
60
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
PREPARATION/FOLLOW UP
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Outcome 3: Reduce Human and Material Losses in vulnerable communities in the Northern Areas of Pakistan through GLOF Early Warnings and other adaptation measures
Output 3.1: Preparedness actions for vulnerable communities conducted to reduce risks from GLOF events
3.1.1 Dialogues and meetings with vulnerable communities to sensitize them about GLOF related hazards, preparedness and adaptation 06
FM PS, SLF, DDO, LSO, VCC, WWF, AKRSP, FOCUS, PRCS
3.1.2 Mutually agree upon and develop standard operating procedures and command structures for establishing Disaster Risk Reduction Committees, Early Warning System, and Emergency Response Cells
03
NC PS, ICIMOD, Dy. Commissioner, CBO
3.1.3 Establish valley specific Disaster Risk Reduction Committees
3.1.4 Community Awareness Raising & Sensitization Training Workshops on GLOF Issues
02
ICIMOD DMCs FOCUS AKRSP, PRCS, WWF, SLF, DDO, LSO, PS
3.1.5 Establishment of community-based natural hazard watch groups in Bagrot and Drongagh
01
FM WWF, FOCUS
61
3.1.6 Preparation and dissemination of DRR guidelines for Bagrot and Drongagh communities
02
ICIMOD MoNDM
3.1.7 Designation or re-designation of safe havens and safe access routes by CBOs on the basis of new findings
02
CBO FOCUS, WWF, Dy. Commissioner
3.1.8 Opening of a community account for Stockpiling, inventory management and O&M of the safe havens.
CBO FM, Dy. Commissioner
3.1.9 Stockpiling and refurbishing of Safe Havens in the vulnerable communities
CBO PS, Dy. Commissioner
3.1.10 Collection of periodic tariff for mobilizing funds locally for prescribed safety measures
Dy. Comm. CSoGBA, Fin Secy., P&D Secy. PC
3.1.11 Financial provision for Safe Havens and Stockpiles incorporated into the District Annual Development Plans
Dy. Comm. CSoGBA, Fin Secy., P&D Secy. PC
3.1.12 Emergency Response Cells developed / strengthened under the command of a Dy. Commissioner in every vulnerable District
Dy. Comm. GBA, GKPK, GBDMA, PDMA
3.1.13 Valley specific Disaster Risk Reduction Committees (DRRC) develop GLOF specific Early Warning Systems
PMD FOCUS, ICIMOD, SPCS, WWF, CBOs
62
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
FOLLOW UP / PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Output 3.2: A community based system for GLOF risk monitoring & early warning in priority communities
3.2.1 Documentation of indigenous knowledge on prevailing natural hazards and ways to trigger an early warning 02
NC CBO, Dy. Comm. WWF, FOCUS
3.2.2 Study existing community-based Early Warning Systems in place for flash floods, debris flow, and landslides to mainstream GLOF 02
NC DMCs, Project Staff, FOCUS, PRCS, Targeted Communities
3.2.3 Ensure Early Warning Systems are built upon existing lines of communications and benefit from indigenous knowledge 02
NC ICIMOD, DMCs Project staff, FOCUS, PRCS,
63
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
FOLLOW UP / PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Output 3.3 Targeted GLOF risk reduction measures such as check dams, spill-ways, slope stabilization or controlled drainage established in Bagrot and Drongagh valleys
3.3.1 Identification of Interventions for Structural Mitigation in Bagrot and Drongagh Valleys
10
PS & TC DMCs, PMD, WWF, FOCUS, AKRSP, SLF, PRCS, LSO, VCC, DDO
3.3.2 Tendering of works as per UNDP/Adaptation Fund procedures and award of Contracts
NPD NPM
3.3.3 Technical Surveys of the potential GLOF channels in Drongagh and Bagrot
FM AKPBSP, AKRSP, FWO, NAWPD, KPKWPD
3.3.4 Prepare technical proposals in line with simulation modeling, building codes, community priorities, and budgetary constraints
FM AKPBSP, AKRSP, FWO, NAWPD, KPKWPD
3.3.5 Conduct Initial Environmental Examination (IEE) of technical proposals to finalize them
EPAs KIU & UOP, WWF, FOCUS, Project Staff,
3.3.6 Approval of Project Proposals and Award of Contracts
PSC Technical Committee comprising of MoDM, PMD, NAPWD,
64
KPKPWD
3.3.7 Commencement of physical works and completion of approved projects
NPM Winner of the Contract
3.3.8 Plantation of indigenous flora to stabilize slopes CBO PS, WWF
65
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
FOLLOW UP / PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Outcome 4: Project Experiences Documented and Replicated
Output 4.1. Technical knowledge and project lessons documented for use in future initiatives
4.1.1 Develop project website
01
Project Staff
CF, DMCs, FOCUS, WWF, KIU, ICIMOD, NDMA, PRCS
4.1.2 Develop Project Database to serve as a Repository of knowledge accessible to all project partners
01
NC NPM
4.1.3 Develop Case Studies to document Best Practices
08
FM NPM
4.1.4 Annual Project Digest
04
NC NPM/NPD
4.1.5 resource mobilization for sustainability and replication of lessons learnt in the new areas
66
Output 4.2 Project experiences disseminated to policy makers and disaster management planners in Pakistan and the wider HKH region
4.2.1 Project website linked to all policy formulation and planning authorities in Pakistan
01
Project Staff
MoNDM
4.2.2 Access to project database made available to all relevant authorities
01
NPD Project Staff
4.2.3 GLOF risk management manual published and disseminated to all relevant public and private institutions 08
NPD Project staff
67
Outputs and Activities
Q1 GLOF BUILD UPQ2 & Q3 GLOF THREAT
Q4 GLOF SAFETY ACTIVITY
FOLLOW UP / PREPARATION
Timeline Partner Organization(s)
# of Tasks
2012 2013 2014 2015
Lead Supportive
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Outcome 5: Project Management Unit and Monitoring & Evaluation
5.1 Hiring of Remaining Project Staff
NB
UNDP EAD & MoDM
5.2 Establish Project Offices
03
PS MoDM & UNDP
5.3 Procurement of Equipment & Furniture
NB
PS MoDM & UNDP
5.4 Notification of Project Steering Committee (PSC)
01
MoNDM Project Staff
5.5 Project Steering Committee Meetings
02
MoNDM UNDP, DMAs, Project Staff
5.6 Notification of Project Management Committees (PMC)
02
DMAs Project Staff MoDM & UNDP
5.7 Project Management Committee Meetings
04
DMAs Project Staff MoDM & UNDPWWF, FD Focus PRCS SLF AKRSP EPA
68
5.8 Field Monitoring Visits
12
PS& UNDP
SLF WWF DDO LSOs WWF DMAs FDs
5.9 Quarterly Review Meeting
04
Project Staff
DMAs UNDP DDO LSOs
5.10 Annual Progress Review & Planning Workshops
03
Project Staff
PDMAs UNDP & MoDM DDO LSOs VCC
5.11 Annual Financial Audits
04
NPD Registered Audit Firm
5.11 Midterm Evaluation Report IC UNDP
5.12 End of the Project Report NPM NPD
4.13 Final Evaluation IC UNDP
69
Annex # 5: List of Inception Workshop Participants
1 Haji Abdul Hameed Khan Secretary Forests & Wildlife GB GB Forests & Wildlife Department
2 Zaheer Uddin Babar Assistant Director GBDMA [email protected]
3 Bilal Ali Qureshi Young Professional Officer UNDP [email protected]
4 Muhammad Iqbal Khan Consultant PCRWR [email protected]
5 Mohammad Aziz Manager LSO HARSO, Chitral [email protected]
6 Muhammad Azam Khan Deputy Secretary Tourism Tourism Department GB [email protected]
7 Shahid Ali General Secretary Dubani Development Org. Bagrot [email protected]
8 Sabir Hussain Mphil Student KIU [email protected]
9 Yasir Hussain Deputy Director Tourism Department GB [email protected]
10 Anna Grieser Student LUM,Munich (KIU) [email protected]
11 Kamran Hussain Provincial Focal Point REDD+ Forest Department GB [email protected]
12 Muhammad Jamil Chairman MCDP [email protected]
13 Hadi Husani CEO AKPBS [email protected]
70
14 Fatima Bano Incharge PCRWR
15 Lal Khan RPO Focus
16 Nazir Ahmed RPM FOCUS
17 Faisal Farooq Khan Consultant UNDP/GLOF Project [email protected]
18 Aftab Mahmood DFO W/L Forest Deptt
19 Muhammad Essa General Secretary Mountain Areas Conservation Society
20 Shahadat Noor Chairman LSO Bagrot
21 Walayat Noor Conservator Wildlife & Parks Wildlife & Parks Department GB
22 Ghulam Muhammad Conservator Forests Baltistan Forests and Wildlife Department
23 Shehzad Shigri Director GB-EPA
24 Haider Raza EIA-Expert GB-EPA/IUCN
25 Nawab Ali Khan GM AKPBS
26 Dr Sherdil Khan Producer Radio Pakistan Gilgit
27 Babar Khan Head WWF Gilgit-Baltistan
28 M.Zafar Khan Manager WWF
71
29 Shams Bercha Engineer Radio Pakistan Gilgit
30 Tajdar Hussain Conservation Officer PWP-WWF
31 Garee Khan GIS Analyst WWF GB
32 Ismail Project Director GB-Forest Department [email protected]
33 Dr. Nasim Javed Conservator Forests KPK Forest Department, Abbottabad [email protected]
34 Ghulam Abbas Secretary PRCS PRCS-GB
35 Shafiq Ahmed Manager Disater Management PRCS-GB
36 Amin Beg PM AKRSP
37 Syed Ikram Ali Shah Provincial Coordinator GBDMA
38 Dilshan Fatima CLO AKPBSP
39 Sabahat FO AKPBSP
40 Abbas Ali Programme Manager AKPBSP
41 Qayyum Ali Sr. Programme Manager AKPBSP
42 Nahida Khudadad Manager M&E AKPBSP [email protected]
43 Jaffar Uddin CPM SLF-P [email protected]
72
44 Qammar ul Zaman Metrologist PMD Islamabad [email protected]
45 M.Atif Wazir Metrologist PMD Islamabad [email protected]
46 Mayoor Khan Programme Manager WCS [email protected]
47 Ismail Zafar Conservator Forests Forest Department GB
48 Aman Ali Shah GS LSO Bagrot
49 Nadeem Khan Correspondant Khyber News [email protected]
50 Massi Emilia Gilgit KIU
51 Dr Haleem HOD KIU
52 Salar Ali Lecturer KIU Gilgit
53 Shahzad Hussain Journalist KPN
54 Iftikhar Ali Student KIU
55 Syed Mujtaba Hussain NPD GLOF-Project [email protected]
56 Abdul Qadir Rafiq Assistant Country Director UNDP Pakistan [email protected]
57 M.Saleeem Programme Assistant UNDP Pakistan [email protected]
58 Khurshid Khan Admn &Finance Assistant GLOF-Project, Islamabad [email protected]
73
59 Khalil Ahmed National Project Manager GLOF-Project, Islamabad [email protected]
60 Gernot Laganda RTA UNDP [email protected]
74
Annex # 5: Terms of References (Draft)Pakistan Meteorological Department (PMD) of Pakistan, Ministry of Defense
LEAD INSTITUTION: Pakistan Metrological Department
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Office of the Deputy Commissioner, Emergency Response Cells, Disaster Risk ReductionCommittees, and GB & KP DMAs along with selected university students will receive training and develop know-how with the assistance of PMD and other contributing institutions.
REQUIRED CAPACITIES: Remote Sensing, GIS mapping, Disaster Risk Reduction, Online Scientific Monitoring, Online reporting Systems, and ability to extend full services for Early Warning System installation of and post-installation back up support
IN-KIND CONTRIBUTION: The contractor will volunteer to share all GLOF related information with the project for inclusion into the repository and web linked database. The contractor will be responsible for mobilizing all equipment, machinery and tools required to deliver the contracted services. However, capital cost of the equipment permanently installed or deployed for the project will be the property of project and the supplier will deposit a performance bond for duration of three years. The contractor will also deposit an insurance bond against advance payments of equal amount.
PMD will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Islamabad, Bagrot and Drongagh
75
DELIVERABLES:
Outputs Timelines Activities Scope1.1 Q3-Q4, 2012
Q1-Q2, 2013Strengthen indigenous EWS to prepare vulnerable communities for GLOF risk management
Valleys
1.1 Q3-Q4, 2012Q1-Q2, 2013
Linkages between DMCs and DRRCs established and strengthened Districts
1.1 Q3-Q4, 2012Q1-Q4, 2013
Develop and institutionalize comprehensive GLOF risk management at district and provincial levels
Districts/Provinces
1.2 Q2-Q3, 2012 Develop an expanded inventory of potential hazardous GLOF sites (identifying GLOF hotspots) on the basis of secondary data, remote sensing and ground verification.
Northern Pakistan
1.2 Q2-Q4, 2012 Prioritize GLOF hotspots on the basis of HVRA and inventory update Northern Pakistan1.2 Q2-Q3, 2012 Develop scientific indicators for monitoring GLOF Northern Pakistan2.1 Q1-Q2, 2012
Q1-Q2, 2013Q1-Q2, 2014Q1-Q2, 2015
Conduct remote sensing of all identified glaciers in Northern Pakistan for identification of plausible GLOF sites on annual basis
Northern Pakistan
2.1 Q1-Q2, 2012 Site visits by a multidisciplinary team to Bagrot and Drongagh for ground verification and scoping
Valleys
2.2 Q1-Q2, 2012 Develop GIS and Google maps of the valley and the districts Districts2.2 Q1-Q2, 2012 Develop new GLOF hazard maps for Bagrot and Drongagh Valleys3.1 Q2-Q3, 2012 Mutually agree upon and develop standard operating procedures and
strengthen command structures for establishing a DRRC, EWS and ERCDistrict
3.2 Q2-Q3, 2012 Study existing community-based EWS in place for flash floods, debris flow, and landslides to mainstream GLOF
Valleys
3.2 Q3, 2012 Incorporate indigenous knowledge into EWS and build it upon existing lines of communications and benefit from indigenous knowledge
Valleys
DURATION: March 2012 – June 2015
PAYABLES: 25% upon signing of the services contract and receiving of an insurance bond of an equal amount.
76
Payments for purchase of EWS and associated equipment will be tied to receiving of a performance bondof an equal amount.25% upon successful delivery of activities planned for 2012 after receiving an insurance bond of an equal amount.25% upon completion of activities planned for 2013 and 2014 after receiving an insurance bond of an equal amount.25% upon completion of activities planned for 2015 after receiving an insurance bond of an equal amount.The performance bond will be released after 3 years of successful functioning of the EWS and associated equipment
FOCAL POINTS: National Project Manager and PMD in-charge of remote sensing and early warning systems
SIGNITORIES: Director General of Pakistan Metrological Department, Ministry of DefenseJoint Secretary of the Economic Affairs DivisionNational Project Director
77
Annex # 5: Terms of References (Draft)Global Change Impact Study Center (GCISC), Ministry of Science & Technology
LEAD INSTITUTION: Global Change Impact Study Center
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Office of the Deputy Commissioner, Emergency Response Cells, Disaster Risk ReductionCommittees, and GB & KP DMAs along with selected university students will receive training and develop know-how with the assistance of GCISC and other contributing institutions
REQUIRED CAPACITIES: Ability to review national policies, academic literature and secondary data for recommending mainstreaming of GLOF risks across the country’s policy framework
IN-KIND CONTRIBUTION: The contractor will volunteer to share all GLOF related information with the project for inclusion into the repository and web linked database. The contractor will be responsible for mobilizing all equipment, machinery and tools required to deliver the contracted services. If applicable, capital cost of the equipment permanently installed or deployed for the project will be the property of project and the supplier will deposit a performance bond for duration of three years. The contractor will also deposit an insurance bond against advance payments of equal amount
GCISC will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Islamabad
78
DELIVERABLES:
Outputs Timelines Activities Scope1.1 Q1, 2012 Desk review of literature and secondary data to recommend
mainstreaming of GLOF in governmental policies and plansNational
1.1 Q2, 2012 Review of governmental policies and plans National2.1 Q2-Q4, 2013
Q1-Q4, 2014Q1-Q2, 2015
Develop new or/and modify existing land use practices in accordance with the approved disaster management plans for each valley
Community / Valleys
2.2 Q1-Q4, 2015 Develop a GLOF Atlas of Pakistan National
DURATION: March 2012 – June 2015
PAYABLES: 25% upon signing of the services contract and receiving of an insurance bond of an equal amount.Payments for purchase of EWS and associated equipment will be tied to receiving of a performance bondof an equal amount.25% upon successful delivery of activities planned for 2012 after receiving an insurance bond of an equal amount.25% upon completion of activities planned for 2013 and 2014 after receiving an insurance bond of an equal amount.25% upon completion of activities planned for 2015 after receiving an insurance bond of an equal amount.The performance bond will be released after 3 years of successful functioning of the EWS and associated equipment.
FOCAL POINTS: National Project Manager and GCISC Section in-charge of Environment
SIGNITORIES: Executive Director of Global Change Impact Study CenterJoint Secretary of the Economic Affairs DivisionNational Project Director
79
Annex # 5: Terms of References (Draft)International Center for Integrated Mountain Development (ICIMOD)
LEAD INSTITUTION: International Center for Integrated Mountain Development
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Office of the Deputy Commissioner, Emergency Response Cells, Disaster Risk ReductionCommittees, and GB & KP DMAs along with selected university students will receive training and develop know-how with the assistance of ICIMOD and other contributing institutions
REQUIRED CAPACITIES: Ability to assess capacity needs of community, district, provincial and national institutions for addressing GLOF risk management
IN-KIND CONTRIBUTION: The contractor will volunteer to share all GLOF related information with the project for inclusion into the repository and web linked database. The contractor will be responsible for mobilizing all equipment, machinery and tools required to deliver the contracted services. If applicable, capital cost of the equipment permanently installed or deployed for the project will be the property of project and the supplier will deposit a performance bond for duration of three years. The contractor will also deposit an insurance bond against advance payments of equal amount
ICIMOD will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Islamabad
80
DELIVERABLES:
Outputs Timelines Activities Scope1.1 Q2-Q3, 2012 Capacity need assessment meetings and capacity development action
plans for partner organizations and communitiesAcross
1.2 Q2, 2012 Develop criteria for GLOF specific HVRA to expand existing baselines Community/District2.1 Q4, 2012 Conduct simulation modeling of GLOF in Drongagh and Bagrot valleys Valleys2.1 Q1-Q4, 2013
Q1-Q4, 2014Q1-Q2, 2015
Develop new or/and modify existing disaster management plans in accordance with the valley based GLOF models
Valleys
3.1 Q2-Q3, 2012 Sensitize communities, districts and partner organizations about GLOF related hazards, preparedness, and adaptation
Community/District
3.1 Q3, 2012 Share international and local experience on developing SOPs and command structures for DRRC, EWS, and ERCs
Community/District
3.1 Q4, 2012 Training workshops on GLOF issues Community/District3.1 Q2-Q4, 2012 Establish and train valley specific DRRCs Community3.1 Q2, 2012 onwards Establish and train community-based natural hazards watch groups in
Bagrot and DrongaghCommunity
3.1 Q2-Q3, 2012 Preparation and dissemination of DRR guidelines for Bagrot and Drongagh communities
Community
DURATION: April 2012 – June 2015
PAYABLES: 25% upon signing of the services contract and receiving of an insurance bond of an equal amount.Payments for purchase of EWS and associated equipment will be tied to receiving of a performance bondof an equal amount.25% upon successful delivery of activities planned for 2012 after receiving an insurance bond of an equal amount.25% upon completion of activities planned for 2013 and 2014 after receiving an insurance bond of an equal amount.
81
25% upon completion of activities planned for 2015 after receiving an insurance bond of an equal amount.The performance bond will be released after 3 years of successful functioning of the interventions and associated equipment
FOCAL POINTS: National Project Manager and National Programme Coordinator of ICIMOD
SIGNITORIES: National Programme Coordinator of ICIMODJoint Secretary of the Economic Affairs DivisionNational Project Director
82
Annex # 5: Terms of References (Draft)World Wide Fund for Nature (WWF – Pakistan)
LEAD INSTITUTION: World Wide Fund for Nature – Pakistan
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Office of the Deputy Commissioner, Emergency Response Cells, Disaster Risk ReductionCommittees, and GB & KP DMAs along with selected university students will receive training and develop know-how with the assistance of WWF and other contributing institutions
REQUIRED CAPACITIES: Ability to undertake extensive field activities for KAP studies, HVRA surveys, sensitizing vulnerable populations, and formation of Disaster Risk Reduction Committees. The organization must have the ability to prepare case studies for documenting best DRR practices, assist in development of a project website and a database, and publication of IEC materials and an annual project digest
IN-KIND CONTRIBUTION: The contractor will volunteer to share all GLOF related information with the project for inclusion into the repository and web linked database. The contractor will be responsible for mobilizing all equipment, machinery and tools required to deliver the contracted services. If applicable, capital cost of the equipment permanently installed or deployed for the project will be the property of project and the supplier will deposit a performance bond for duration of three years. The contractor will also deposit an insurance bond against advance payments of equal amount
WWF - Pakistan will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Gilgit and Chitral
83
DELIVERABLES:
Outputs Timelines Activities Scope1.1 Q2, 2012 Conduct KAP studies in Drongagh and Bagrot valleys Community1.1 Q2, 2012 Develop IEC materials and introductory sheets on GLOF issues Community/District1.1 Q2, 2012 Develop GLOF communication and awareness raising strategy National2.1 Q3, 2012 Conduct GLOF vulnerability risk assessment in Drongagh and Bagrot Valleys2.2 Q2-Q4, 2012 Mainstream GLOF risks in land use practices in Drongagh and Bagrot
valleys and develop disaster management plansValleys
3.1 Q3, 2012 Establish valley specific DRRCs Valleys3.1 Q2-Q3, 2012 Sensitize communities, districts and partner organizations about GLOF
related hazards, preparedness, and adaptationCommunity/District
3.2 Q1-Q3, 2012 Documentation of indigenous knowledge on prevailing natural hazards and early warning practices
Community/District
3.3 Q2-Q3, 2012Q2-Q3, 2013Q2-Q3, 2014Q2-Q3, 2015
Plantation of indigenous flora to stabilize slopes Community/Valleys
4.1 Q4, 2012 Assist in development of a project website Project4.1 Q4, 2012 Document and publish case studies on best DRR practices Community/District4.1 Q4, 2012
Q4, 2013Q4, 2014Q4, 2015
Annual Project Digest Community/District
DURATION: April 2012 – December 2015
PAYABLES: 25% upon signing of the services contract and receiving of an insurance bond of an equal amount.Payments for purchase of equipment will be tied to receiving of a performance bond of an equal amount.25% upon delivery of activities planned for 2012 after receiving an insurance bond of an equal amount.25% upon completion of activities for 2013 and 2014 after receiving an insurance bond of an equal amount.
84
25% upon completion of activities planned for 2015 after receiving an insurance bond of an equal amount.The performance bond will be released after 4 years of successful slope stabilization.
FOCAL POINTS: National Project Manager and designated WWF in-charge
SIGNITORIES: Director General or Deputy Director General WWFJoint Secretary of the Economic Affairs DivisionNational Project Director
85
Annex # 5: Terms of References (Draft)Deputy Commissioner, Chairman, Disaster Management Committee (DMC)
LEAD INSTITUTION: Disaster Management Committee (DMC), Gilgit and Chitral
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Office of the Director General GBDMA and KPDMA, Disaster Risk Reduction Committees. Selected university students will receive training and develop know-how with the assistance of District Administration and other contributing institutions
REQUIRED CAPACITIES: Ability to assist communities in hazard risk management and capacity to immediately respond to disastersThe incumbent must have authority over district functionaries and jurisdiction over the territories within district boundaries.
IN-KIND CONTRIBUTION: DMC will extend all possible cooperation with DRRCs within its jurisdictions and rules of the business. The Deputy Commissioner will monitor the Early Warning Systems in collaboration with the Community-based Organizations. He will report all GLOF related information with the GBDMA and project for inclusion into the repository and web linked database. The Deputy Commissioner will be responsible for mobilizing all equipment, machinery and tools required to provide public safety.
The Disaster Management Committee will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Gilgit and Chitral
86
DELIVERABLES:
Outputs Timelines Activities Scope1.1 On need basis Send a representative of the district administration to the community to
attend DRRC meetingsDistrict
1.2 Annually Assist in prioritizing GLOF hotspots and vulnerable areas on the basis of HVRA and inventory updates
District
1.2 Annually Identify potential safe havens on the basis of secondary data, remote sensing and ground verification
District
2.2 Q3-Q4, 2013 Disseminate GLOF hazard maps to all relevant district offices to inform their decisions and actions
District
2.2 Q1-Q4, 2014 Mainstream GLOF risks in land use practices in Bagrot and Drongagh valleys and develop disaster management plans
District
2.2 Q1-Q4, 2014 Q1-Q4, 2015
Replicate valley based disaster management planning process to prepare district wide disaster management plans in Gilgit and Chitral
District
3.1 Q1-Q2, 2015 Financial provision for safe havens and stockpiles incorporated into the District Annual Development Plans
District
3.1 Q4, 2012Q1, 2013
Establish Emergency Response Cells and strengthen them under the command of the Deputy Commissioner in Chitral and Gilgit
District
3.1 Q4, 2012Q1, 2013
Guide Disaster Risk Reduction Committees in developing/installing Early Warning Systems
Community/District
3.2 Q3, 2012 Document indigenous knowledge and recognize existing lines of communication to ensure proper natural hazards management
Community/District
3.3 On need basis Give or arrange approvals/permits for facilitation of physical works District4.1 Quarterly Share a brief narrative report on District Administration’s cooperation
with vulnerable communitiesDistrict
DURATION: January 2012 – December 2015
PAYABLES: UNDP – Pakistan may or may not consider giving honorarium to public officials as per its official policy
87
FOCAL POINTS: National Project Manager and designated District Official
SIGNITORIES: Deputy CommissionerDirector General of GBDMA or KPDMANational Project Director
88
Annex # 5: Terms of References (Draft)Community Based Organizations (CBOs)
LEAD INSTITUTION: Community Based Organization (CBO), Drongagh and Bagrot
CONTRIBUTING INSTITUTIONS: Flood Commission, FWO, SUPARCO, GSISC, ICIMOD, WWF, FOCUS, WAPDA, NARC, PCRWR, PWD, NDMA, GBDMA, KPDMA, District Administrations, Community-based Organizations
BENEFICIARY ENGAGEMENT: CBOs, Offices of the Director General GBDMA and KPDMA, Disaster Risk Reduction Committees and Disaster Management Committees. Selected university students will receive training and develop know-how with the assistance of District Administration and other contributing institutions
REQUIRED CAPACITIES: Ability to lead vulnerable communities, represent all strata of rural society, form favorable public opinion for DRR, identify natural hazards & vulnerable populations, and influence positive behavioral change.The incumbent must have authority over Disaster Risk Reduction Committees and Community Hazard Watch Groups within its valley.
IN-KIND CONTRIBUTION: CBOs will extend all possible cooperation with DMCs of the district. CBO will collaborate with the Deputy Commissioner to ensure proper functioning of Early Warning Systems and subsequent emergency response. CBO will report all GLOF related information to the Deputy Commissioner and the field manager. The CBOs will be responsible for mobilizing people, skilled/semi-skilled labor, and other local resources required to provide public safety.
The CBOs will cooperate with all contributing institutions in terms of cross-fertilization of knowledge and information sharing.
LOCATION: Bagrot and Drongagh
89
DELIVERABLES:
Outputs Timelines Activities Scope1.1 Project life Facilitate field surveys, interviews, group discussions, meetings and
awareness raising campaigns by project partnersCommunity
1.1 Project life Disseminate IEC materials to all public fora such as masajid, imambargah, schools, madressah, marketplaces, and community halls
Community
2.1 Project life Facilitate HVRA and hazard mapping exercise on the ground Community3.1 Project life Participate in dialogues and meetings for sensitization on GLOF related
hazards, preparedness actions and adaptation to climate changeCommunity
3.1 Project life Participate in discussions on standard operating procedures and command structures for establishing Disaster Risk Reduction Committees, Early Warning Systems, and Emergency Response Cells
Community
3.1 Project life Select and nominate trainees for trainings offered by contributing institutions through project.
Community
3.1 Q3, 2012 Select and nominate participants for the community awareness raising and sensitization training workshops on GLOF issues.
Community
3.2 Q2, 2012 onwards
Establish a Disaster Risk Reduction Committee at the valley level supported by newly formed Hazard Watch Groups in all settlements of the valley
Community
3.2 Q2-Q3, 2012 Actively participate in the preparation and dissemination of the DRR guidelines
Community
3.2 Q1, 2014 onwards
Cooperate with the district administration in identification and notification of the safe havens and safe access routes for GLOF and other natural hazards safety
Community
3.2 Q2, 2012 Open a community operated account for stockpiling, inventory management and O&M of the safe havens
Community
3.2 Q3-Q4, 2012onwards
Ensure proper stockpiling and maintenance of the safe havens along with proper maintenance of the safe routes
Community
3.2 Q2, 2012 onwards
Generate community funds locally by levying local tariffs in consultation with community elders/heads of the households and periodically deposit
Community
90
collected funds into the bank account3.2 Q3, 2012 Share indigenous knowledge on the history of natural hazards and
indigenous methods of natural hazards management with the project, partners and district administration
Community
3.3 Q4, 2012Q2, 2013
Assist in identification of interventions for structural adaptation in Bagrot and Drongagh valleys
Community
3.3 Q1-Q4, 2013Q1-Q4, 2014
Select and ensure training of community-based labor for construction of physical interventions
3.3 Q2-Q3, 2012Q2-Q3, 2013Q2-Q3, 2014Q2-Q3, 2015
Plantation of indigenous flora to stabilize slopes Community
4.1 Project life Ensure community based monitoring and evaluation of project results Community4.2 Project life Provide factual community beneficiary testimonials on project
performanceCommunity
DURATION: January 2012 – December 2015
PAYABLES: UNDP – Pakistan may or may not consider giving honorarium to volunteers as per its official policy
FOCAL POINTS: Field Manager and CBO representative
SIGNITORIES: CBO PresidentDesignated District OfficerNational Project Manager
91