56

Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Embed Size (px)

Citation preview

Page 1: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression
Page 2: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Introduction Tasks achieved in GP I Earthquake load Alternative # 2 Design of compression & zero force members Design of tension members Design of end beams & columns Design of welded connection Design of bolted connection Material cost Comparison and final design Conclusion

2

Outline

Page 3: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Introduction

Currently, Al Ain International Airport is under extension work due to:

o Growth in the passenger flightso Increase in the airline traffic to Al Ain

Our graduation project was motivated by the ongoing expansion of Al Ain International Airport.

The roofing system of a typical airport’s terminal was selected, analyzed and then designed.

Page 4: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The major objective was to utilize the theory of structures

principals and the Load and Resistance Factor Design

concepts to;

o Model

o Analyze

o Design

the steel elements and connections forming the main

supporting element of the long-span roofing system.

Objective

Page 5: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

5

Comprehensive literature review was conducted on common

construction material, structural systems, and dimensions of existing or

proposed airport terminals.

Two alternative architectural designs were selected.

A general structural layout was generated using the AutoCAD software to

describe all the components of the first alternative system.

GP I Summary

Page 6: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

6

The initial computer model was developed for the first alternative

system using the structural analysis software SAP2000.

The various design loads acting on the first alternative system including

dead loads, roof live loads and wind loads were calculated based on the

latest American standards developed by the American Society of Civil

Engineers (ASCE7-05).

A detailed 3D model was developed using SAP2000 to simulate the

behavior and response of the selected structural system under the

computed loads.

GP I Summary

Page 7: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

First Alternative: Multi-Curvature Arch

Generation of the Alternatives

Page 8: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Second Alternative: Traditional Single-Curvature Arch

Generation of the Alternatives

Page 9: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

9

An earthquake is a shake of the earth's

surface usually occurred by the release of

underground stress along fault lines. This

release causes movement in masses of

rock and resulting seismic waves.

Earthquake Load

Page 10: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

10

Severe Lateral load

Very complex & uncertain

Potentially more damaging than wind loads

Earthquake Load

Earthquake Load

Page 11: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

11

Designing buildings to resist earthquakes

requires that ground motions be translated

into forces acting upon a building.

Earthquake forces are called lateral forces.

The magnitude of earthquake load depends

on the mass of the structure and on the

horizontal acceleration imparted from the

ground shaking.

Earthquake Load

Earthquake Load

Page 12: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Case # 1

Case # 2

Earthquake Load Calculations

Page 13: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The procedure of calculating the earthquake load acting on the building structure is in

accordance with ASCE7-05/IBC 2009 standards .

o Required values, factors and coefficients :

W (KN) Ss R I Fa Fv S1 Ct x H (m) T

560.574 0.675 3.25 1.25 1.13 1.53 0.27 0.0488 0.75 30 0.626

Ta

T

analysis

k SMS SM1 SD1 SDs CsCs

[min]

Cs [max] Vb (KN)

0.892 2.5 1.063 0.7628 0.4131 0.2754 0.5085 0.1956 0.01 0.1692 94.853

Earthquake Load Calculations

Page 14: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Ss Values:

Abu Dhabi = 0.6

Dubai = 0.83

Al Ain = 0.675

Seismic activity in UAE (MCE)

Abu Dhabi

Dubai

Al Ain

Page 15: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Abu Dhabi

Dubai

Al Ain

S1Values:

Abu Dhabi = 0.24

Dubai = 0.33

Al Ain = 0.27

Seismic activity in UAE (MCE)

Page 16: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Long - Period Transition Period :

TL = 8

Seismic activity in UAE

Page 17: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

17

Earthquake Load Calculations

Base Shear (Vb) ; the total lateral load caused by the earthquake at the base of the structure.

Vb = Cs W

WhereVb ; the seismic base shear.

W ; the effective seismic weight “the total dead load of the entire building”.

Cs ; the seismic response coefficient

Page 18: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

18

Earthquake Load Calculations

The lateral seismic force (Fxf) ;

Fxf = Cvfx V b

The calculated base shear is distributed among all floors with respect to:o the heights of the building o their effective weight

Vertical distribution factor (Cvxf ) ;

Cvfx=( Wxf hxf k / Σi=1 n Wi hi k )(Ct hn x)

Page 19: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

19

Joint W (KN) h (m) hk Whk Cvfx= Fxf FINAL Fxf

46 26.666 2.026 2.119 56.495 0.002 0.216 0.43347 26.762 4.978 5.507 147.389 0.006 0.565 1.12948 26.859 8.542 9.778 262.615 0.011 1.006 2.01249 26.859 12.359 14.480 388.917 0.016 1.490 2.98050 26.859 16.043 19.109 513.230 0.021 1.966 3.93351 26.859 19.223 23.158 621.994 0.025 2.383 4.76652 26.859 21.577 26.184 703.261 0.028 2.695 5.38953 26.934 22.729 27.672 745.314 0.030 2.856 5.711

Alternative # 1Results

Page 20: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

20

Results

Joint W (KN) h (m) hk Whk Cvfx Fxf FINAL Fxf (KN) 41 16.261 1.671 1.726 28.063 0.001 0.096 0.19242 26.710 4.938 5.461 145.853 0.006 0.499 0.99843 26.735 8.100 9.241 247.059 0.010 0.845 1.69144 26.735 11.139 12.965 346.628 0.014 1.186 2.37245 26.735 14.044 16.588 443.486 0.017 1.518 3.03546 26.735 16.808 20.078 536.798 0.021 1.837 3.674

Case #1

Case #

2

Alternative # 2 Results

Page 21: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Joint # a1 a2 Dead Load (Ib) Dead Load (Kips) Dead Load (KN)41 0 12.435 1827.866 1.828 8.13042 12.435 12.466 3002.458 3.002 13.35543 12.466 12.466 3005.333 3.005 13.36844 12.466 12.466 3005.333 3.005 13.368

The various design loads calculations were performed based on

[ASCE/SEI 7-05].

Dead Load Calculations

Results

Page 22: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Live load acting on a typical truss joint:

Results

Joint # x1 x2 Live Load (Ib) Live Load (Kips) Live Load (KN)

49 9.954 10.360 1649.211 1.649 7.336

50 10.360 10.733 1712.419 1.712 7.617

51 10.733 11.072 1770.246 1.770 7.874

52 11.072 11.376 1822.480 1.822 8.106

Live Load Calculations

Page 23: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Direction #1: Perpendicular to 204 m Direction #2:

Perpendicular to 118.5m

The main equation

In wind load calculations, it is important to divide the system itself to different sections.

Wind Loads Calculations

Page 24: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

24

Wind direction

Results

Joint (deg)θ (rad)θ P (KN) Px (KN) Pz (KN)

41 60 1.0470.783 0.678 0.3912.543 -0.775 -2.422

42 58.5 1.0212.421 2.064 1.2655.945 5.069 3.106

43 55.5 0.9682.884 2.377 1.6336.413 5.285 3.632

Wind Loads Calculations

Page 25: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The design of the airport roofing system using AutoCAD software

Computer Model

118.5 m

31 m

4 m

System’s MaterialSteel (A572-G50)

Roofing System TypeSpace Truss

The different joints and elements were labeled in an Excel spreadsheet to be used as an input in SAP2000 Software

Page 26: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

26

Computer Model

Horizontal Structural Elements Beams &

Columns

Supports (Hinges)

Page 27: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Assigning Structural Loads in SAP2000

• To simulate the behavior and response of the structural system under the computed loads .

• To conduct full structural analysis of the entire system.

Assignment of the dead load Assignment of the live load

Page 28: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Assignment of the wind load Assignment of the earthquake load

Assigning Structural Loads in SAP2000

Page 29: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The analysis was carried out according to 11 loads combinations

Analysis Stage

1.2D +1.6L

1.2D + 1.6W + 0.5L

1.2D + 1E + 0.5L

Truss 3Truss 24

Steel SectionCircular cross-section

Page 30: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

30

SAP 2000 Output

Table : Sample SAP2000 Output

Frame Station OutputCase Case Type P

Text in Text Text Kip

686 147.098 D+L Combination -459.261

687 147.098 D+L Combination -346.644

688 149.035 D+L Combination -239.020

689 149.035 D+L Combination -141.728

690 147.572 D+L Combination -51.544

690 147.572 D+E1+L Combination 57.957

Page 31: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

oThe major objective of this phase is to insure the safety and economy of the system by comparing the element's resistance with the applied load.

o A comparison was done between the two units based on the tension and compression forces for each of the combination.

Final Design Process

Type of load Comparison Design for

Compression only - Compression

Tension only - Max. Tension

Compression or Tension Compression > Tension Max. Compression

Compression or Tension Compression < Tension

Max. Tension & Max. Compression (Consider the biggest

section)

Page 32: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

o Based on the type of load, the structural elements were classified as: • Zero force members • Compression members• Tension members

Final Design Process

o Design of Zero-Force Members

Zero-force members are special members that are designed to satisfy stiffness criterion only (i.e.; strength is not an issue).

These members should be designed following stiffness requirement of compression members.

Page 33: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Design of Compression Members

o Steel is known to be sensitive to buckling and, therefore, special

attention should be given to buckling behavior of these elements.

Data obtained from LRFD manual

o Procedure of designing the compression members

Page 34: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Design of Compression Members

Page 35: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Design of Compression Members

Page 36: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

36

Tension members are structural elements that are subjected to axial tensile forces.

Design of Tension Members

Failure mode #1 Design of steel due to yielding in the gross section.

Failure mode #2 Design of steel due to tensile rupture in net sections

Page 37: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Design of tension members

Page 38: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Specifications and Final Design

After designing the different elements, the appropriate steel section was selected for each element.

Page 39: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The design of the first upper cord is identical to the second one and same for the diagonals.

Alternative #1

Alternative #2

Steel sections

Page 40: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

End columns and beams are secondary elements that are intended to withstand self weight of cladding sheets. They should be able to provide adequate strength for moments resulting from wind loads.

Alternative #1

Design of end beams and columns

Page 41: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Alternative #2

Page 42: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

42

Steel members are usually connected in the fabrication shop by welding.

In the construction site either welding or bolting could be used; however, bolting is more recommended for quality control, ease and safety reasons.

Connections

Page 43: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

43

There is a practical limit on the maximum length of steel members that could be carry to the construction site and that is about 12 to 14 meters

Connections

Alternative #1 Alternative #2

Page 44: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Welding process; The elements are heated and fused with molten metal added to the joint

The most commonly used welding techniques are :(1) Shielded Metal Arc Welding (SMAW), used for field welds.(2) Submerged Arc Welding (SAW), used for shop welds.

The SAW process provides more penetration into the base metal and higher strength than the SMAW process.

Type of Weld: Fillet WeldsFillet Welds (about 80% of all welds), those welds placed in a corner formed by two parts in contact (the parts to be welded)

Welded Connections

Page 45: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Type of Weld: Fillet WeldsAbout 80% of all welds, those welds placed in a corner formed by two parts in contact (the parts to be welded)

Types of length weld;•Longitudinal Welds(Welds that are perpendicular to direction of the load applied)

•Transverse Welds(Welds that are parallel to the direction of the applied load)

Welded Connections

Page 46: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The procedure for designing Welded connections

Welded Connections

∅Rn/in = 0.75(0.6 FEXX) (te) (1.5) Lw= Pu/( Rn/in)∅

Lw,min = 4Sw Lw,max = 100Sw

Page 47: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Connections for tension members, such as truss members, are classified as concentric shear connections, since the centroid of the connector group (fasteners or bolts) coincides with the centroid of the member.

Bolted Connections

Concentric connections

Page 48: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Two main load transfer mechanisms control such connections:

1. Bearing-Type Connections:• Transfer of loads depends on the Bearing at

bolt holes.• The most commonly used bolts are A325

and A490

2. Friction-Type (Slip-Critical) Connections:Load transfer depends on the friction betweenconnected parts.

Bolted Connections

Page 49: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The procedure for designing bolted connections

Bolted Connections

ØRn/bolt = 0.75 Ab Ft

Nb = Pu /(ØRn/bolt)

Smin = 0.67d

Smax = the smaller of [24t , 12]

S = π D / Nb

Page 50: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

To calculate the overall cost of the project, the weight of the overall structural elements must be calculated.

The truss is divided to; Lower cord elements

Upper cord elements

Diagonals

Upper diagonals and

Horizontal elements

Purlins

Cost Estimation

Number of elements 39Section Pipe2SH40Weight (Ib/ft) 3.66Total Length (in) 6141.732Length (ft) 511.811Weight (Ib) 1873.228Weight (ton) 0.850

Data obtained

from LRFD manual

Horizontal elements (AL#2)

Page 51: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Truss PartLower

Chord

Upper

ChordDiagonal

Upper

Diagonal

Horizontal

ElementPurlin

Total Cost

(Dhs/ton)Total weight

(ton)3.534 4.71 8.1 2.6 0.4 0.4

Order (10%) 3.9 5.2 8.9 2.9 0.4 0.4

Truss

(Dhs/ton)27211.1 36266.7 62365 20216.4 3042.4 3042.4 152,144.1

System

(Dhs/ton)707489.2 942935.2 1621489.7 525627.5 79102.3 76059.9 3,952,704

Cost Estimation Alternative #1

Page 52: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Cost Estimation

Truss PartLower

Chord

Upper

ChordDiagonal

Upper

Diagonal

Horizontal

ElementPurlin

Total Cost

(Dhs/ton)Total weight

(ton)6.6 6.4 2.2 1.2 0.9 0.9

Order (10%) 7.3 7.0 2.4 1.3 0.9 0.9

Truss

(Dhs/ton)50879.5 49261.5 16717.5 9102.3 6541.2 6541.2 139,043.3

System

(Dhs/ton)1322867.1 1280799.4 434656.2 236658.9 170071.7 163530.5 3,608,584

Alternative #2

Page 53: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The project’s objective: to utilize the theory of structures principals and

the load and resistance factor design concepts to model, analyze and

design the steel elements and connections that make up the main

supporting element of the long-span roofing system.

For two different systems :

Full analysis and design.

Cost estimation.

Conclusion

Page 54: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

The second alternative was found to be more efficient since it costs less than the first alternative.

This result meets our expectation since the second alternative is a single curvature arch which is more efficient in carrying loads as compared to the first alternative.

Some gained skills: Calculating the different types of load according to the detailed analytical

procedures presented by ASCE7-05, utilizing recent data such as the maps used in earthquake load calculations.

Using structural analysis software (SAP2000) to model and analyze the roofing system.

Employing the project advisor’s and coordinator’s feedback to improve our performance and learn from our mistakes.

Solving problems, overcome difficulties and acceptable time management. Enhancing team work.

Page 55: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

• Finally, this project was very helpful and challenging at the same time.

• One remark among many is to conduct more projects and researches in the same field and other fields in Engineering to gain more experience, to develop our performance and to apply what we learnt in our career.

Page 56: Introduction Introduction Tasks achieved in GP I Tasks achieved in GP I Earthquake load Earthquake load Alternative # 2 Alternative # 2 Design of compression

Thank You