INVITATION OF BUDGETARY OFFER FOR SUPPLY, INSTALLATION AND
COMMISSIONING OF PLAIN WATER DUST SUPPRESSION SYSTEM IN CQ1-CQ2
BERTH AND BACK UP AREA OF PPT.
SUBMISSION OF BUDGETARY OFFER ON OR BEFORE DT. 09.04.2019.
EXECUTIVE ENGINEER
WORKSHOP DIVISION-I
PARADIP PORT TRUST
CONTACT NO. 06722-222074
CONTACT PERSON:
SRI. NIHAR RANJAN BHOI (SE, WSD, PPT): 9556050300
MRS. BIJAYALAXMI MOHAPATRA (EE, WSD-I, PPT):9937565111
REQUEST FOR BUDGETARY OFFER
(A) GENERAL INFORMATIONS:
Sl. No. Item Details
1. Name of Work Supply, installation and commissioning of plain water
dust suppression system in CQ1-CQ2 berth and back
up area of PPT.
2. Department / Organization ELECTRICAL & MECHANICAL DEPARTMENT /
PARADIP PORT TRUST
3. Executive Design Workshop Division-I
4. Officer Inviting the Offer Executive Engineer
5. Immediate Next Authority Superintending Engineer
6. Sanctioning Authority Chairman, PPT
7. Executing Authority Executive Engineer
(B) OTHER INFORMATIONS:
Sl. No. Item Date Time
1. Publication Date 20.03.2019 12:00 Hrs.
2. a) Document Download Start Date 20.03.2019 12:30 Hrs.
b) Document Download End Date 09.04.2019 17:15 Hrs.
3. a) Start Date for Seeking Clarification
On-Line
_____ _____
b) Last Date for Seeking Clarification
On-Line
_____ _____
4. Date of Uploading Response to
Clarifications Sought
_____ _____
5. Offer Submission End Date 09.04.2019 17:15 Hrs
6. Offer Validity Period 120 days
7. Currency of Offer Indian Rupee
8. Language of Offer English
Scope of Work
Budgetary offer for the work: Supply, installation and commissioning of plain water dust
suppression system in CQ1-CQ2 berth and back up area of PPT.
Paradip Port Trust intends to install a dust suppression system for its CQ1-CQ2 berth and backup
area of PPT. After installation and commissioning of the system, the same will be handed over to
the contractor for operation and maintenance of system for three (03) years in consideration of
one (01) year warranty period.
In this context the following data are annexed for reference.
1. System Concept Envisaged
2. P & ID for SPDS
3. Drawing of VAT (03 sheets) – Annexure-1
4. Drawing of pump house (tentative)- Annexure-2
5. BOQ for supply of goods and execution including O&M for 03 years.
It is requested to submit budgetary offer along with all terms & conditions as per system
envisaged. It is also requested to suggest any addition / modification / deletion to the system
envisaged, drawing, BOQ in order to make the system more robust, reliable & economic and
accordingly furnish the offer in consideration with changes suggested. Both the offers i.e. (1) as
per our system concept & BOQ and (2) if changes suggested shall be inclusive of all taxes, duties
and other incidentals except GST.
Name of Work: Supply, Installation & Commissioning of Plain Water Dust Suppression
System in CQ1-CQ2& back up area of PPT
DESCRIPTION OF SYSTEM ENVISAGED
A. System Description:
The system designation and corresponding area covered is as under.
Sl.
No.
System Area Covered Pump House
Location
1 PWDSS* Dust suppression system for CQ1-CQ2 berth
&it’s back up area in one side and plots in
other side.
Within 100m radius
from the stockpile
*Plain water dust suppression system
B. Coverage:
Sl. No. Stockpile Dimension
1 Length : 700 m
Width : 70 m
Height : 15m
Qty.: 2nos i.e. CQ1-CQ2 berth &it’s back up area in one side and siding plots in
other side. Full circle sprinklers are to be positioned in center.
C. System concept envisagedand Design Consideration
1. The intended Mechanized Water Sprinkling System will be having sump (vat) and pre-
fabricatedpump house with control roomfor operation of system. Sump and pump house
will be located within 100meters from the plot.
2. Water Requirement:
There is water requirement of 2809 cum per day for the intended system considering 20
hr operation per day. It is planned to source the water by making bore well in the vicinity
of location of the system. In general water from bore-well is slightly saline in nature.
Accordingly total system shall be designed to suit this type of quality of water.
3. Selection of sprinklers:
The throw of sprinkler shall cover width of the plot considering wind velocity.Hence, for
the purpose, radius of throw is considered 75meter.
Minimum capacity of Sprinkler:159 m3/hr (approximate)
Minimum Throw Radius: 75 m
Minimum Tip Pressure: 6.0 kg/cm2
Qty : 14 Nos.
Distance between 2 sprinklers: 50 meter (Approx.)
Make :Sime / Nelson/equivalent
4. Each sprinkler is connected to main header pipeline through Globe Valve & Control
valve. The sprinklers shall be operated automatically and sequentially through PLC. The
surface of stockpiles will bewetted by operating one (1) sprinkler at a time for this
stockpile.
5. There shall be 14 sprinklers to be installed in total. Out of that one sprinkler shall be
operating at a time. Inone hr. cycle each sprinkler shall run for 3.7min approximately. So
sprinkler will run one after another.
6. Water qty. required for dust suppression system when 1 sprinkler is working at a time and
each sprinkler ishaving capacity (159 X1) m3/hr =159.0 m3/hr
i.e. Total consumption = 159.0 m3/hr
Considering @10% margin total consumption = 175.0 m3/hr
Considering Pump capacity is 175m3/hr (1W+1S)
7. Evaporation rate = 1.3 lit/hr/m2.
Selected Sprinkler’s Capacity = 159 m3/hr.
So that sprinkler to be run ≈ 53 min for wetting the stockpile
Qty. of Sprinklers = 14 Nos.
So, eachsprinkler will be run for = 3.7 min.
Therefore one sprinkler will run for 3.7min after that another will run with overlapping of
10 sec and so on sequentially. This operationwill continue for 53min in an hour which is
a cycle time.
i.e. cycle time = 1 hr. = 60 min.
Sprinklers ON time = 53 min.
Sprinkler OFF / Pause time = 7 min.
1
2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
ON Time =53min OFF
Time
=7
min
ON Time =33min OFF
Time
=
7min
Cycle Time = 60min (1hr)
Considering 20hr / day will be the operation time of dust suppression system.
i.e. total cycle time = 20 hr. / Day
Sprinklers ON time per day = 53min per hr. * 20 min = 1060 min.
Water consumption / Day = (159*1060/60) m3 = 2809 m3.
The pause time can also be controlled by adjusting the time sequence in the sequential
controller so thatwater consumption rate can be controlled as per site condition.
8. Lay out of Pipelines and valves arrangement:
Configuration of pipes and valves is considered as under.
a) There will be a continuous main header line (overhead &underground) of size
150NB.
b) Sprinklers are to be installed at an interval of 50meters (approximately). For this
purpose, risers of size 100NB pipe will be tapped from main header line.
c) The main overhead header line will be placed / laid along the retaining wall with
suitable base arrangement towards road side. Since retaining walls are not continuous
and there are 6 openings, the pipes shall be laid inside culvert existing in the openings
with suitable base arrangement. Height of retaining wall is 1.4 meter from road level.
Height of the sprinkler shall be decided considering to reach the stack height of
15meter so also width of 70meter.The riser stating from tapping point will be
positioned vertical by means of structural support. Accordingly, suitable section of
steel structural shall be selected to hold the riser firmly without any vibration of
sprinkler in operation. The support structures shall be anchored with the existing
retaining wall with grouting chemicals for proper rigidity. All the structural to be used
in system shall be galvanized and painted.
14th
no of sprinkler may be come on ground where there will be no retaining wall.
Hence, header line needs to be placed underground. For laying of pipe underground it
shall be at a depth of 1.5 meter from ground level. The bed of 300mm depth after
1.5meter from ground level comprising 225mm earth filling and 75mm sand filling
with proper compaction shall be prepared for placing &laying of pipeline. This
sprinkler and riser shall be placed in a retaining wall to be constructed new of
appropriate thickness (minimum 400mm overground) with proper supporting
structure.
9. VAT:
The location of the VAT will be located within a100m radius from the stockpile area and
to be made up of concrete structure having dimension as mentioned in Annexure-1 (3
Sheets).
10. Pump House:
Pump house has been considered within 100m radius from the stockpileadjacent to
VAT.The intended dust suppression system will be operatedfrom the control room in
Pump House. The pump house shall be connected to the VAT. The pump house shall be
constructed using pre-fab structures.Dimension of pump house as shown in drawings is a
tentative dimension for reference and dimension shall be freezed considering installation
of all equipment and its accessories.
Required no. of Pumps, MCCs, PLC panels will be installed in the pump house.
Necessary Gate valves, Globe valves, Pressure release valves, Non-return valves,
Pressure gauges, Pressure switches will be provided for each pumping unit. Strainer will
be provided at suction line in the pump inlet. Bypass arrangement with Pressure release
valve & Gate valve is considered in the discharge line to prevent the pump running at
shut-off head. A level switch is considered for Sump to avoid dry run of pump.Water will
re-circulate to the water sump from header line through by pass line when there is no
demand of water.
11. Operation of Pumps:
2 centrifugal pumps are required for smooth operation of the DSS system. Both the
pumps shall be operated in regular interval one after another.
12. Electrical System:
The connected load for total system is worked out to be 170 KW. LT MCC, PLC panel,
Lighting DBsare to be located in thepump house.The source of power supply 415V/AC,3
Ph& N, 50 Hz will be provided by PPT.LT MCC will be equipped with microprocessor
based incomer, Motor control center with earth fault protection, over current protection,
unbalanced load protection, control transformer, spare feeder etc.
All JBs to be installed at site are outdoor type and should be double door type with IP65
grade protection.
PLC with HMI will be provided for selection, control, and operationand monitoring of
the sprinkling system. All solenoid valve operated ON/OFF controller are to be operated
by 230 V AC.
Water flow in each sprinkler will be monitored throughflow switch and this signal will
appear in PLC panel with LED type fuse protector.Cables of suitable rating will be laid
along the pipeline.
13. Basic Data:
Following basic data may be considered for design of the system.
i) Site ambient condition
Maximum ambient air temperature: 55 deg. C (Outdoor equipment),
50 deg.C (Indoor equipment)
Minimum ambient air temperature: 10 deg.C.
Atmosphere: Humid and heavily dusty with dust from different
types of cargo coals / iron ores/chromes /
limestone etc.
ii) Design Specification for Electrical equipment
Auxiliary Power Supply
For Motor rated Up to 180 KW
and below
415V, 50 Hz, 3 phase, 3 wire solid earthed AC
For Motor control center (pump
starter panel)
415V, 50 Hz, 3 phase, 4 wire solid earthed AC
Control supply 240V, 1 phase, 2 wire, 50 Hz AC
Variation in power Supply
AC Supply Voltage Variation +/-10%
Frequency +/-3%
iii) Any other voltage levels required if any for instruments, Control System,
Panel/cabinets lighting shall be generated by the Contractor.
All equipments shall be suitable for working in the above conditions. As far as
possible, the water lines shall be self balanced without adjustment of valves. Water to be
used for dust suppression will be portable water. The equipment / components selected
by the Contractor shall be suitable for this water quality.
14. Operation logic:
a) All the sprinklers are to be operated round the clock in sequential manner.
b) Auto Feedback to be transmitted to PLC panel for monitoring of the system.
c) Operation of sprinklers starting from 1stsprinkler to 14
thsprinkler one after
another.
d) From HMI panel, operation will be monitored.
Basing on the above system concept & requirement, the system shall be installed and
commissioned including construction of pits in stockyard as per drawing attached.
15. Typical spray coverage diagram is attached for your reference & record.(Annexure-A)
16. Operation & Maintenance of the System for 3 years.
The Contractor is responsible for smooth O & M of the system for 3 years from the date
of commissioning of the system including fulfillment of warranty obligations for 1 year.
Supply of spares, consumables and any other requirement which is required for smooth O
& M of the system is included in the scope of the Contractor.
DR
AIN
���
����
����
Bill Of Quantity
Supply, Installation & Commissioning of Plain Water Dust Suppression System in CQ1-CQ2 & back up
area of PPT
Sl.
No.
Description Unit Qty. Rate
(in Rs.)
Amount
(in Rs.) excluding
GST
SUPPLY OF GOODS
1 RCC Tank Inlet motorized gate valve,
manual gate valve and drain Gate Valve
and tank outlet gate valve
(a) CCS Motorized gate Valve - 150NB
(interlocked with Level switch)
Nos 1
( b) CCS Gate Valve – 150NB Nos 1
( d ) CCS Gate Valve – 80NB Nos 1
(e ) Float valve - 150 NB Nos 1
2 Duplex filter at the tank inlet / make up
water line - 150 NB (MS with SS filter
element)
Sets 1
3 Pump with motor (1W+1S) and all
accessories of capacity 175m3 / hr and
head 155mWC
Nos 2
4 Water pump inlet & outlet gate,
check/globe valves, recirculation globe/pr
relief/gate valve.
(a) CCS Gate Valve – 200NB Nos 2
(b) CCS Gate Valve – 150NB Nos 2
(a) FCS Gate Valve – 25NB Nos 1
( c) CCS Check Valve – 150NB Nos 2
(d) CCS Globe Valve – 150NB Nos 1
(e ) CCS Globe Valve – 50NB Nos 1
(f) FCS / CCS Pr. Relief Valve – 25 NB Nos 1
(g) FCS / CCS Motorised gate valve - 50 NB at
water pump reciculation line
Nos 1
(h) CI Y strainer - 200NB Nos 2
5 Pr gauge at each pump inlet, outlet and Pr
switch at Common line of pump outlet
and DPS in Duplex filter
(a) Compound Gauge Nos 2
(b) Pressure Gauge Nos 2
( c) Pressure Switch Nos 1
(d) Flow Transmitter Nos 1
( e) Pressure Tranmitter Nos 1
(f) DPS for Duplex filter Nos 1
(g) Flow Switch Nos 14
6 Level Switch for RCC Tank Nos 1
7 Sprinklers Nos 14
8 CCS Globe Valve – 100 NB Nos 14
9 Solenoid Control valve (230VAC) Nos 14
10 HDPE pipes (150NB approximate) as per
working pressure 15.5 bar.
Meter 950
11 HDPE pipes (200NB approximate) as per
working pressure below 10bar.
Meter 50
12 HDPE pipes as per (100NB approximate)
as per working pressure 15.5 bar
Meter 30
13 HDPE pipes as per (50NB) as per working
pressure 18 bar.
Meter 150
14 Fittings for pipelines including bends, tee,
flanges,sockets, etc
Lot Lot
15 Metallick Expanssion below for suction
side of suitable size
No. 2
16 Metallick Expanssion below for delivery
side of suitable size
No. 2
17 Structural MT 8
18 DSS MCC ( Pump starter panel) No. 1
19 Power & Control Cables, cable glands and
lugs, cable tray, cnduit, earthing
Lot Lot
20 Sprinkler Control Panel (PLC based) with
HMI
No. 1
21 JB No. 5
22 LPBS No. 2
23 Other Electrical items, Lighting DB Lot Lot
24 Incoming Power Supply cable (415V) upto
DSS MCC at Pump House
Lot Lot
25 Other left out materials Lot Lot
A. Supply of Goods Rs.___________
EXECUATION
1 Civil
(a) RCC tank as per Annexure-1 including
painting
No. 1
(b) Pre fabricated structure for construction
Pump House as per Annexure -2
No. 1
(c ) Concrete Road (approximate 300mm RCC)
cutting for laying of pipeline through
hume pipe and repiring of damage road
by RCC
Meter 70
(d) Any other civil works if any LS LS
(e) Supply and installation of Submessible
Pump with Bore well and connection to
main pipe (7.5HP, head minimum
36meter, discharge 42cum/hr)
No. 5
(f) Any other civil works if any LS LS
2 Fabrication & Erection and installation of
system
LS LS
3 Testing and commissioning of system. LS LS
B Total of Execution Rs.___________
C TOTAL Supply & Execution Rs.___________
D Operation & Maintenance of the System
for 3 years including supply of all spares
in consideration of warranty obligations
of 1 year
Rs.___________
E GRAND TOTAL Rs.___________
NB.We hereby confirm that the above quoted price is inclusive of all taxes, duties, cess etc.
and all other incidentals like transport, insurance etc excluding GST and a firm landing price at
Paradip Port Trust.