Upload
phanimvv
View
232
Download
0
Embed Size (px)
Citation preview
8/4/2019 Islanding Operation
1/13
PROJECT : NALCO CPP UNIT 7 AND 8
PROBLEM : ISLANDING OPERATION
Islanding operation of units - 1 to 6 was successfully
demonstrated earlier. However, after addition of units - 7 & 8,
under the grid disturbances, the total plant used to trip causing loss
of power to the smelter plants. During islanding operation trials of
unit 7 and 8 of NALCO CPP, wide fluctuations of load, frequency and
voltages were noticed, which could not be stabilized even after 10
minutes.
WHY ISLANDING CRITICAL?
During the grid disturbances, such as under frequency or under
voltage smelter pot lines control gets disturbed and metal in the pot
lines will get solidified causing production loss and down time of
smelters for a week. Due to this, a circuit has been envisaged such
that in NALCO CPP Generators and Smelters will get isolated from
the grid on under frequency or under voltage to protect the pot lines
and avoid losses.
8/4/2019 Islanding Operation
2/13
DETAILS OF THE PLANT:
NALCO CPP is having 8 units of 1 20 MW each, that are feeding the
captive consumption of 600 MW at their smelter plant. Unit 1- 6steam turbines are having Electro-Hydraulic Governing system
( EHTC) and are of KWU design. Unit 7 and 8 steam turbines are
supplied with Electronic High pressure Governing and are of KN series
of Siemens Design.
OBSERVATIONS DURING TRIALS OF ISLANDING OPERATIONS:
TRIAL - 1 dated 28th October, 2005 (From 16:49:30 hrs to
17:15:40 hrs)
Islanding Operation was tried as per the scheme 1 enclosed. During
the trial wide fluctuations of load, frequency and voltages were
noticed which could not be stabilized and smelter feeders tripped onunder voltage (Trend- 1 enclosed). Further during the trial, it was
observed that in unit - 7 high speed controller was interfering and
causing valves to close & open continuously.
8/4/2019 Islanding Operation
3/13
During trial starting and load limiting device (SLLD) of unit 7 was
reduced such that load limiting devices action superseded the speed
controllers action. It was observed on reduction of SLLD hunting had
reduced and on release of SLLD hunting again started.
8/4/2019 Islanding Operation
4/13
8/4/2019 Islanding Operation
5/13
8/4/2019 Islanding Operation
6/13
TRIAL- 2 dated 25th April, 2006 (From 11:37:30 hrs to 11:51:05 hrs)
From the above trial , certain logics were modified for avoiding high
speed controller interference and in such a way that a gain of 1 . 5
will get automatically reduced to 0.3 during islanding operation to
eliminate the fluctuations. Islanding trial operation of unit - 7
along with units - 5 & and 6 was carried out under the conditions
of export of 30 MW and with smelter load of 195 MW by opening
the bus coupler (refer scheme 2). The transient performance was
not settling even after 1 3 minutes and wide fluctuations of load,
frequency and voltages were observed as below:
? Load fluctuation of 10 MW in unit 5, 30 MW in unit 6 and 60MW in unit 7
? Frequency fluctuations of 1 . 6 Hz in all units? Generator Voltage fluctuation of 2.5 kV in all units
8/4/2019 Islanding Operation
7/13
During wide fluctuation of load, frequency and voltage , it was decided
to take unit- 5 to load control mode for improvement . When Unit -
5 was taken to load control mode , the machine got unloaded fully and
tripped. The system frequency dropped and smelter feeder tripped on
under frequency and units - 6 & 7 tripped on over speed protection
after tripping of smelter feeder.
8/4/2019 Islanding Operation
8/13
8/4/2019 Islanding Operation
9/13
8/4/2019 Islanding Operation
10/13
The wide fluctuations observed in the above two trials were attributed
to mismatch in Governor/ Valve response time, AVR response time
between the old units and units - 7 & 8. Hence it was decided to
check the Governor/ Valve response time, AVR response of old units
and new units (7 and 8).
From 15th October 2006 to 18th October 2006, responses of valves
were recorded with high speed recorder, for units - 5, 7 & 8. AVR
responses were also recorded. The following were observed:
Serial No. TEST CONDITIONS OBSERVATIONS
1 UNIT 5: 3V 8V
step up command to
position controller
For 3- 8 V step command HPCV
and IPCV started responding
after 0. 2 seconds and stabilized
in 7 seconds (Refer graph 1 )
2 UNIT 5: 8V 3V
step down command
to position
controller
For 8- 3 V step down command
HPCV and IPCV started
responding after 0. 1 second,
HPCV stabilized in 2.6 secondsand IPCV stabilized in 5 seconds
( Refer graph 2)
3 UNIT 7: 3V 8V
step up command to
position controller
HPCV and IPCV responded
immediately, HPCV stabilized in
1 . 54 seconds and IPCV
stabilized in 5.29 seconds.
4 UNIT 7: 8V 3V
step down commandto position
controller
HPCV and IPCV responded
immediately, HPCV stabilized in2. 2 seconds and IPCV stabilized
in 5.4 seconds.
8/4/2019 Islanding Operation
11/13
5 AVR Step response in
unit 5
Found OK
6 AVR Step response inunit 7
Response was faster andretuned to match unit 5.
7 Unit 8 Valve response was similar to
unit 7 and AVR response was
retuned to match unit 5.
The above responses were further studied and it was decided to
carry out the following.
? To slow down the valve response of units - 7 & 8, PT blocks wereprovided (First order time delay function block) in position
reference circuit of HPCV 1 & 2, IPCV 1 & 2 and Over load
Control Valve (OLCV). This time delay block is in operation only
under islanding conditions and when frequency is less than 52 Hz.
? To Disable Power System Stabilizer (PSS) in units - 7 & 8 as wasin units 1 - 6, where no PSS is provided.
The above modifications were carried out on 23rd April 2008. On 25th
April 2008, islanding operation was carried out under the conditions
of export of 30 MW and smelter load of 1 95 MW by opening bus
coupler (Refer scheme 3). The transient performance was found to
be satisfactory with a settling time of 1 minute of load, frequency
and voltage. Machines were run on islanded mode for around 50
minutes. After satisfactory Speed reference of units - 7, 8 and 5
were varied one at a time and voltages and frequencies were matchedand re- synchronized with the grid.
8/4/2019 Islanding Operation
12/13
During wide fluctuation of load, frequency and voltage , it was decided
to take unit- 5 to load control mode for improvement . When Unit -
5 was taken to load control mode ,the machine got unloaded fully and
tripped. The system frequency dropped and smelter feeder tripped on
under frequency and units - 6 & 7 tripped on over speed protection
after tripping of smelter feeder.
8/4/2019 Islanding Operation
13/13
Conclusions:
After the above demonstration of Island operation at NALCO- CPP,it can be concluded that before carrying out islanding trials, the
following are to be checked / carried out for a successful islanding
operation
1 . Valve response time of each machine is to be measured,compared and matched with other units by suitable modifications
in position reference circuit and or in the servo timing of
valves.2. AVR response time of each machine is to be measured andmatched precisely by retuning AVR PID.