Islanding Operation

Embed Size (px)

Citation preview

  • 8/4/2019 Islanding Operation

    1/13

    PROJECT : NALCO CPP UNIT 7 AND 8

    PROBLEM : ISLANDING OPERATION

    Islanding operation of units - 1 to 6 was successfully

    demonstrated earlier. However, after addition of units - 7 & 8,

    under the grid disturbances, the total plant used to trip causing loss

    of power to the smelter plants. During islanding operation trials of

    unit 7 and 8 of NALCO CPP, wide fluctuations of load, frequency and

    voltages were noticed, which could not be stabilized even after 10

    minutes.

    WHY ISLANDING CRITICAL?

    During the grid disturbances, such as under frequency or under

    voltage smelter pot lines control gets disturbed and metal in the pot

    lines will get solidified causing production loss and down time of

    smelters for a week. Due to this, a circuit has been envisaged such

    that in NALCO CPP Generators and Smelters will get isolated from

    the grid on under frequency or under voltage to protect the pot lines

    and avoid losses.

  • 8/4/2019 Islanding Operation

    2/13

    DETAILS OF THE PLANT:

    NALCO CPP is having 8 units of 1 20 MW each, that are feeding the

    captive consumption of 600 MW at their smelter plant. Unit 1- 6steam turbines are having Electro-Hydraulic Governing system

    ( EHTC) and are of KWU design. Unit 7 and 8 steam turbines are

    supplied with Electronic High pressure Governing and are of KN series

    of Siemens Design.

    OBSERVATIONS DURING TRIALS OF ISLANDING OPERATIONS:

    TRIAL - 1 dated 28th October, 2005 (From 16:49:30 hrs to

    17:15:40 hrs)

    Islanding Operation was tried as per the scheme 1 enclosed. During

    the trial wide fluctuations of load, frequency and voltages were

    noticed which could not be stabilized and smelter feeders tripped onunder voltage (Trend- 1 enclosed). Further during the trial, it was

    observed that in unit - 7 high speed controller was interfering and

    causing valves to close & open continuously.

  • 8/4/2019 Islanding Operation

    3/13

    During trial starting and load limiting device (SLLD) of unit 7 was

    reduced such that load limiting devices action superseded the speed

    controllers action. It was observed on reduction of SLLD hunting had

    reduced and on release of SLLD hunting again started.

  • 8/4/2019 Islanding Operation

    4/13

  • 8/4/2019 Islanding Operation

    5/13

  • 8/4/2019 Islanding Operation

    6/13

    TRIAL- 2 dated 25th April, 2006 (From 11:37:30 hrs to 11:51:05 hrs)

    From the above trial , certain logics were modified for avoiding high

    speed controller interference and in such a way that a gain of 1 . 5

    will get automatically reduced to 0.3 during islanding operation to

    eliminate the fluctuations. Islanding trial operation of unit - 7

    along with units - 5 & and 6 was carried out under the conditions

    of export of 30 MW and with smelter load of 195 MW by opening

    the bus coupler (refer scheme 2). The transient performance was

    not settling even after 1 3 minutes and wide fluctuations of load,

    frequency and voltages were observed as below:

    ? Load fluctuation of 10 MW in unit 5, 30 MW in unit 6 and 60MW in unit 7

    ? Frequency fluctuations of 1 . 6 Hz in all units? Generator Voltage fluctuation of 2.5 kV in all units

  • 8/4/2019 Islanding Operation

    7/13

    During wide fluctuation of load, frequency and voltage , it was decided

    to take unit- 5 to load control mode for improvement . When Unit -

    5 was taken to load control mode , the machine got unloaded fully and

    tripped. The system frequency dropped and smelter feeder tripped on

    under frequency and units - 6 & 7 tripped on over speed protection

    after tripping of smelter feeder.

  • 8/4/2019 Islanding Operation

    8/13

  • 8/4/2019 Islanding Operation

    9/13

  • 8/4/2019 Islanding Operation

    10/13

    The wide fluctuations observed in the above two trials were attributed

    to mismatch in Governor/ Valve response time, AVR response time

    between the old units and units - 7 & 8. Hence it was decided to

    check the Governor/ Valve response time, AVR response of old units

    and new units (7 and 8).

    From 15th October 2006 to 18th October 2006, responses of valves

    were recorded with high speed recorder, for units - 5, 7 & 8. AVR

    responses were also recorded. The following were observed:

    Serial No. TEST CONDITIONS OBSERVATIONS

    1 UNIT 5: 3V 8V

    step up command to

    position controller

    For 3- 8 V step command HPCV

    and IPCV started responding

    after 0. 2 seconds and stabilized

    in 7 seconds (Refer graph 1 )

    2 UNIT 5: 8V 3V

    step down command

    to position

    controller

    For 8- 3 V step down command

    HPCV and IPCV started

    responding after 0. 1 second,

    HPCV stabilized in 2.6 secondsand IPCV stabilized in 5 seconds

    ( Refer graph 2)

    3 UNIT 7: 3V 8V

    step up command to

    position controller

    HPCV and IPCV responded

    immediately, HPCV stabilized in

    1 . 54 seconds and IPCV

    stabilized in 5.29 seconds.

    4 UNIT 7: 8V 3V

    step down commandto position

    controller

    HPCV and IPCV responded

    immediately, HPCV stabilized in2. 2 seconds and IPCV stabilized

    in 5.4 seconds.

  • 8/4/2019 Islanding Operation

    11/13

    5 AVR Step response in

    unit 5

    Found OK

    6 AVR Step response inunit 7

    Response was faster andretuned to match unit 5.

    7 Unit 8 Valve response was similar to

    unit 7 and AVR response was

    retuned to match unit 5.

    The above responses were further studied and it was decided to

    carry out the following.

    ? To slow down the valve response of units - 7 & 8, PT blocks wereprovided (First order time delay function block) in position

    reference circuit of HPCV 1 & 2, IPCV 1 & 2 and Over load

    Control Valve (OLCV). This time delay block is in operation only

    under islanding conditions and when frequency is less than 52 Hz.

    ? To Disable Power System Stabilizer (PSS) in units - 7 & 8 as wasin units 1 - 6, where no PSS is provided.

    The above modifications were carried out on 23rd April 2008. On 25th

    April 2008, islanding operation was carried out under the conditions

    of export of 30 MW and smelter load of 1 95 MW by opening bus

    coupler (Refer scheme 3). The transient performance was found to

    be satisfactory with a settling time of 1 minute of load, frequency

    and voltage. Machines were run on islanded mode for around 50

    minutes. After satisfactory Speed reference of units - 7, 8 and 5

    were varied one at a time and voltages and frequencies were matchedand re- synchronized with the grid.

  • 8/4/2019 Islanding Operation

    12/13

    During wide fluctuation of load, frequency and voltage , it was decided

    to take unit- 5 to load control mode for improvement . When Unit -

    5 was taken to load control mode ,the machine got unloaded fully and

    tripped. The system frequency dropped and smelter feeder tripped on

    under frequency and units - 6 & 7 tripped on over speed protection

    after tripping of smelter feeder.

  • 8/4/2019 Islanding Operation

    13/13

    Conclusions:

    After the above demonstration of Island operation at NALCO- CPP,it can be concluded that before carrying out islanding trials, the

    following are to be checked / carried out for a successful islanding

    operation

    1 . Valve response time of each machine is to be measured,compared and matched with other units by suitable modifications

    in position reference circuit and or in the servo timing of

    valves.2. AVR response time of each machine is to be measured andmatched precisely by retuning AVR PID.