Upload
others
View
8
Download
1
Embed Size (px)
Citation preview
1
Junaid Mahoon
March 18th , 2015
2
Safety Moment
Opening
Factors Impacting Project Success
Development Stages
Role of Project Controls – Owners View!
Questions?
Agenda
3
OSSA’s industry partners have developed a common set of Regional Safety Rules enforced in 2015 across all approved OSSA member work sites. The common rules will ensure consistency and avoid confusion between companies. The rules will be applied within the Regional Municipality of Wood Buffalo in Northern Alberta.
The new Life Saving Rules are linked to those activities within the industry that have the highest historic potential for life threatening incidents. Suncor believes this is key to preventing Serious Injuries and Fatalities.
The rules align with OGP – Oil and Gas Producers standards, an internationally recognized set of rules that is the same all over the world.
There are 12 Supporting Safety Rules that can be selected and used for site specific purposes
OSSA – New Regional 7 Life Saving Rules
4
OSSA – New Regional 7 Life Saving Rules
4
Mining specific rule (non‐OGP)
Obtain authorization
before entering a
confined space
Protect yourself against a fall when
working from heights
Work with a valid permit when required
Verify isolation before work
begins and use the specific life protecting equipment
No alcohol or drugs while working or driving
Do not put yourself in an unsafe position with
relation to Mine mobile heavy equipment
Obtain authorization
before overriding or disabling safety
critical equipment
5
OSSA – 12 Extended Life Saving Rules12 Supporting Safety Rules (to be used to support Life Saving Rules above where applicable)
Working or walking immediately under a suspended load is
unsafe as the load can fall on you.
A seat belt protects you from injury in the event of an incident while
driving and keeps you safe.
Speeding or using your phone while
driving increases the risk of losing control
of your vehicle.
A journey management plan is a plan for you as a driver that will help you to travel and arrive
safely.
There is a significant risk of dropped objects when using tools and portable equipment at height. Preventing objects from falling keeps you and people working below you
safe.
Working “in the line of fire” of moving equipment and energized equipment is unsafe as this can impact
you.
Obtain authorization before starting excavation activities. Excavation activities may contain hazards such as electrical cables, confined space, collapse of walls or
excavated material.
Air is tested to stop explosions and/or make sure you can breathe the air safely
Personal flotation devices should always be worn when there is a danger of falling into
water.
Working with equipment immediately under or near overhead lines is unsafe as an electrical current or
flashover can kill you. Maintain adequate distance to keep you
safe.
Smoking or use of matches or cigarette lighters could set on fire flammable materials. Designated smoking areas will keep you safe from
causing fire and explosion.
A lift plan describes how to lift and hoist safely. For
routine lifts, there needs to be a general lift plan. For non‐
routine lifts, including complex and heavy lifts, the
plan is specific.
6
7
Gaps in scope definition Cost estimates inaccuracy Over zealous plans, Push to move projects faster Lack of good Front-End Planning Design / Engineering Quality Constructability factor Material sourcing and overlooked logistics Lack of skilled labour and Productivity hits Re-work in Engineering, Fabrication and Field In-effective Project Management High supply costs, low return projects Low corporate returns compared to competitors, The list goes on……
Factors Impacting Project Success
8
Project Stage Gates
Options Evaluation
Selection
Design Basis
FEED and Detailed Engineering
ConstructionStart-up
Execution and Start-upBasic DesignIdea and Concept Selection
Start CompletionProject Time Line
Hig
h C
ost O
ptim
izat
ion
Low
Cos
t Opt
imiz
atio
n
Project Expenditure
Options Scoping
Options Selection
Design Basis
Detailed Engineering & Procurement
ConstructionStart-up &
Investment Review
FEED
9
Scope
10
This is the 1st step, understand The Scope being developed
What plan has been defined
Are business objectives and strategy understood
Is the team integrated and aligned
As we progress through stages Are we consistently meeting business objectives
Understand Risks
Scope Finalization
Understanding Scope and Execution
11
Preliminary to Final key plan development Project Execution Plan
Contracts and Procurement Plans
Construction Execution Plan
The Project Organization
Consistent, high quality, well documented evaluations are fundamental to achieving high quality business decisions, especially with respect to capital investments
Which leads to selecting high return, low risk options
Further leads to selecting low cost structure with high resiliency to declining economic environment
Understanding Scope and Execution
12
Estimates
13
EstimatingStarting with understanding items from Scope and Execution, based on stage we can develop an effective estimate preparation plan and contribute more An Estimate is a representation of final cost of project at any given
Stage of project development i.e. say Gate-2 Development and Option Selection
Do comparative Estimates for options
Use Cost / Capacity or Equipment Factored approach and / or Similar Projects data from in-house
Utilize tools like ACCE and other such tools if appropriate
Check to see if any value improvement can be considered
Use estimate range vs. a number
14
Estimating Continued… For Design, FEED or Execution
Start utilizing engineering material take-off’s, focus on key quantities
Market data and detailed benchmark modeling
Detail out all known items in project scope i.e. labour, equipment, bulk material, freight, etc. using median cost
Develop bottoms-up detailed estimate for construction Indirects
Involve Project Management / Construction and if possible Contractors in development of the sanction estimates
Establish duration based staffing plan estimates
Risk analysis of estimates for appropriate contingency
Peer and Leadership reviews
15
Required vs. Current Accuracy+90%
+ 80%+ 70%+ 60%+ 50%+ 40%+ 30%+ 20%+10%
0%- 10%- 20%- 30%- 40%- 50%-60%
- 70%- 80%
Project DefinitionVariance from
Previou
s Gate
16
Schedule
17
Alongside estimate, planning is a key step to develop completion schedules for each stage of project
Development / Selection Identify Key Milestones schedule based on job size, start and end
dates for the options
As schedule matures add more detailed information for key engineering deliverables, long lead materials, stage-phase dates
Design, FEED, EPC Stages Integrated Level 2 plus schedule at Stage / Gate-II
Progressively develop the construction schedule per execution and have an Integrated EPC Schedule at sanction i.e. our project schedule baseline
Schedule Baseline (Plan)
18
Field Execution On Award of Construction Contracts, contractor’s Level-4 schedules to
be checked against the Gate-III baseline.
If the schedules are aligned, they are to be used to establish execution baseline for measurement of Progress & Performance
Bulk to Systems schedule conversion leading to Mechanical Completion / Transfer of Care, Custody and Control for Start-up are key to success of project completion
Schedule Baseline (Plan)
19
Integrated Schedule – Construction, Systems & C&SU
Contractor 1
Contractor 2
Contractor 3
Contractor 4
BULK CONSTRUCTION
Schedule Integration
Phase
Contractor 1
Contractor 2
Contractor 3
Contractor 4
SYSTEM COMPLETION
BY SYSTEM
BY SYSTEM
BY SYSTEM
BY SYSTEM
TURNOVER
C &SU
SYSTEM TURNOVER
Integrated Schedule
Contractor’s
Project Team
Ops
20
Cost Control & Change Management
21
Cost Control system is breaking down the estimate into Code of Accounts to manage project cost. Key considerations in setting Control Base:
Cost Planning and Management is for life-cycle of project
Break down and package details to a level suitable for control of project e.g.; Recast by Site locations, Work Fronts, aligned with Contracting,
Procurement, Logistics strategies
Linked to Man-hours and Progress Measurement for Earned Value
Establish Budgets, Commitments, Actual Cost and Trends
Cost Control
22
Time phase cost i.e. setup Cost Flow plan
In Execution phase onboard contractors and integrate their cost systems with project
In Change Management Focus on major variances, maintain change logs to document project changes
Focus on early warning to identify significant risks and potential for changes to the project Scope, Cost and Schedule.
Facilitate timely decision making by drawing on Risk based decision process
Up to date project forecast as our target
Cost Control
23
Cost Control & Management Structure
ControlBudget & Change Control
Cost Accounts
EstimateBreakdownEWP/CWP
EBS-1.1.1EBS-1.1.2EBS-1.1.3EBS-x.x.x
ContractorCost Reports
Report 1Report 2Report 3
ContractorCost
System
Detailed CostAccounts
& Forecast
Integrated Cost Management System
24
Progress and Performance Indicators Progress and Performance is critical for effective Project Controls Information required to keep project predictability up. Proactive approach vs. reactive Performance Indicator Types:
Engineering and Construction performance histogram and s-curve (Hours / Quantities)
Design completion time and quality of construction packages Receipt verification of material at site i.e. support contraction sequence Construction progress and performance report (Quantity & Hours) Key commodity curves (Quantities & Hours) Critical path Analysis and Schedule Look-ahead Cost Flow analysis Earned Value Analysis with recommendation for corrective action
25
Progress and Performance Indicators
26
Cross Functional Collaboration
27
Forecast & Results
=
28