LECTURE 1

MALAYSIAN STANDARD METHODS OF MEASUREMENT

FOR CIVIL ENGINEERING WORKS

(CESMM)

-FUNDAMENTAL PRINCIPLES-

Page 2: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Scope of civil engineering works � Civil engineering is a professional engineering

discipline that deals with the construction and design of public and private sector works such as bridges, roads, dams and buildings.

� General civil engineers work closely with surveyors and specialized civil engineers to fit and serve fixed projects within their given site, community and terrain by designing grading, drainage, pavement, water supply, sewer service, electric and communications supply and land (real property) divisions.

Page 3: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Scope of civil engineering works (continued)

� Construction engineers engage in the design of

structures temporary, cost estimating, planning and

scheduling, materials procurement, selection of

equipment, and cost control.

Page 4: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Measurement for Civil Engineering Measurement for Civil Engineering Measurement for Civil Engineering Measurement for Civil Engineering WorksWorksWorksWorks

� The civil works measurement referred to a document called 'Civil Engineering Standard Method of Measurement '(CESMM).

� Before this document is produced, the party who responsible for the

working measurement refers to the method adopted in the United Kingdom named ‘CESMM 2nd Edition or 3rd Edition’.

� There are a large part of the measurement refer to methods used in

building works or more unfortunate, they use their own measurement system. This led to inconsistencies in measurement procedures. As a result, contractors have difficulty to appreciate the tender.

� The actual measurement work must take into account the level of

complexity of work undertaken. Work measurement for any one item of work is also closely related to the methodology and construction activities

Page 5: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Malaysian Standard Method of

Measurement for Civil Engineering Works

� MALAYSIAN STANDARD METHODS OF MEASUREMENT FOR CIVIL ENGINEERING WORKS is to be used in conjunction with the Conditions Of Contract for Civil Engineering Works.

� Does not deal with the preparation of BQ

for mechanical & electrical engineering work, building work or work which is seldom encountered in civil engineering contracts.

� If any such work to be included in the

contract, such work shall be measured in accordance with their respective SMM and shall be stated in the Preambles to the BQ.

Page 6: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Development Of Civil Engineering

Codes Of Measurement

1933 – ICE provide the 1st time a standard procedure for drafting BQ for

civil engineering works – no uniformity of practice & engineers

worked up their own systems.

1953 - Revised documents named Standard Method of Measurement of Civil Engineering Quantities

1963 – reissued with slight amendments

1968 – reissued with metric addendum

1976 – reappraisal of the civil engineering code of measurement by

consultation of the construction industry, relevant bodies &

person produced Civil Engineering Standard Method of Measurement

Page 7: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Contract Documentation for Civil

Engineering

1. Conditions of contract –a written agreement intended to be enforceable by law to bind the appointed contractor with the employer based on an agreed conditions.

2. Contract Drawings – technical / detailed construction drawings for measurement / costing by QS / engineers – prepared by architect / engineers.

3. Specification / Preambles - A concise description of materials and workmanship, standard or quality of workmanship. It must convey the architect and engineer’s requirements.

4. Bill of Quantities – prepared by Quantity Surveyor based on measurement from the construction drawings / building plans This document were itemized all the quantities for each categories of works applied in constructing the buildings. E.g. building works, mechanical, electrical works, civil, structural works, infrastructure works, etc. The contractor will priced /estimate all the works associated in completing the buildings during pre-construction stage.

Page 8: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Reasons for Bills of Quantities

� All tendering contractors base their prices on the same information & therefore tenders are strictly comparable (even if an error exists in the Bill)

� Contractors are saved the costly exercise of each having to take off quantities for themselves.

� Bills provide a fair basis for valuing variations and adjustments for the final account.

� Bills may provide a convenient basis for valuation of certificated stage payments during the contract, before the accurate re-measurement figures are available.

� Bills provide an approximate checklist for the contractor to order materials and other resources.

� Bills can provide data for cost analysis for use in cost planning of future projects.

Page 9: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Comparison of Civil Engineering and

Building Methods of Measurement

CESMM SMM

� provides a standard format, either in the form of items components and

how they should be measured.

� various stages of introducing CESMM classification or space for description

of the work that can be developed.

� CESMM measurement method using the concept of method-related charges

to present the cost of construction at

the site in more obvious, such as covering the cost of site

preparation and building machinery operating costs, labor force and so on.

� The details of building works are more in precise stage at the time

preparing BQ.

� Building work covers more work sections in consequence subject

to more detailed measurement.

Page 10: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Scope of measurement based on Scope of measurement based on Scope of measurement based on Scope of measurement based on CESMMCESMMCESMMCESMM

� Various civil engineering works including roads, railway, bridges, artificial channels, canals and drainage, shipyard, ports, bases, embankments, structure-breaking waves and drainage work.

� Apart from that it also includes projects such as structural engineering among others, metal work, reinforced concrete work, stone work, wood work and brick work

Page 11: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Procedures and Practices of

CESMM � Include the scope of most project management such as:

� selection types of contracts, � documentation, � preparation of drawings, � specifications, � project information, � contract terms and list of quantities, � preparation of list of material requirements / quantities, � Method statement - detailed list of detailed construction

work with short explanation with quantity measured by CESMM

� Explanation on the scope of work that will be implemented by the contractor and then be the basis for pricing the tender.

Page 12: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Purpose of CESMM

� The main purpose of the measurement based on CESMM is for coordinating and planning of the quantity list, to list the details of work to ensure consistency and systematic and to state the new techniques of construction clearly.

Page 13: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 1

Definitions

� A number of definitions are contained.

� Referring to words / expression that will be defined in the CESMM and preparation of bill of Quantities.

� Words and expression defined in the CESMM shall have the same meaning when defining the words / expression in the Conditions of Contract and the Specifications

� Please refer to CESMM-Section 1: definitions.

Page 14: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 2

General Principles

� In this section , it clarify the following: � The application and extent of CESMM � Objective of CESMM � Objectives of the Bill of Quantities

� Malaysian Standard Method of Measurement for Civil Engineering Works (CESMM) to be used in conjunction with the conditions of contract for Civil Engineering works.

� Refer to CESMM-SECTION 2

Page 15: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 3

Application of the Work Classification

� Work classification divides work into 18 main classes; Class A- Class R

� Each class comprises up to 3 division which classify work at successive level of detail. � First division

� Second division

� Third division

� Each division comprises a list of up to 8 descriptive features of work.

� Each item description shall identify the component of work covered with respect to one feature from each division of the relevant class.

Page 16: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 4

Coding & Numbering of Items

� Each item in the work classification has been placed with the code and numbering system that alphabetically and not more than three digits.

� The letter corresponds to the class in the work classification in which the items occurs and the digits give the position of the item in the first, second and third divisions of the class.

� E.g. Code F.3.1.0 identifies an item as

Class F concrete works

1st Division 3 precast concrete

2nd Division 1 beams

3rd Divison 0

� Description: F.3.1.0 - Precast concrete, in beams

Page 17: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 4

Coding & Numbering of Items

� Reasons: � It gives an advantage to the tendered contractors due

to bills that have code. � Quantity surveyor feels that they are assisted by the

code and numbering system and can be used as a brief reference to the file system and data costs.

� Each class work contains a set of measurements,

definitions, coverage, additional rules of measurement that expands and clarify all information and evidence.

� Every classification of work explains every units for each

item of work, within the total allocation and numbering system for each item, the items in units of meters long, in units of square meters of area (hectares for cleaning site), unit volume and weight and metric units.

Page 18: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

CESMM; SECTION 4

(Code & Numbering of Items)

Applications for Bridge Work

Page 19: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

CESMM; SECTION 4

(Code & Numbering of Items)

Applications for Road works

Page 20: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 5

Preparations of the Bill of Quantities

� The preparation of BQ shall be started prior to the completion of measurement works.

� Section of the bill of Quantities:

� Preamble

� Work items – division of the BQ into parts.

� Day work schedule

� Grand summary / tender summary

Page 21: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

Form & Setting of BQ

Page 22: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 6

Completion, Pricing and Use of the BQ

� Rates and prices shall be inserted in the rate column in Ringgit Malaysia with Sen inserted as decimal fractions of one Ringgit.

� Each part of the BQ shall be totaled and the total carried to the Grand Summary

Page 23: LECTURE 1 MALAYSIAN STANDARD METHODS OF MEASUREMENT …libvolume3.xyz/civil/btech/semester7/estimationvaluation/objective... · Malaysian Standard Method of Measurement for Civil

FUNDAMENTAL PRINCIPLES OF CESMM

CESMM; Section 7

Method-Related Charges

� Meaning: the sum for an item inserted in the BQ by a tenderer.

� Two types:

� Time-related charges – a method-related charge for work, the cost of which is to be considered as proportional to the length of time taken to execute the work

� Fixed charge- a method-related charge which is not a time related charge.

� A tenderer may insert in the BQ the method related charges as he may decide to cover items of works relating to his intended method of executing the works, the cost of which are not to be considered as proportional to the quantities of the other items and for which he has not allowed in the rates and prices for the other items.