November 9, 2017
Lower 8.3 Miles of the Lower Passaic River Operable Unit 2
Presentation to The Passaic River Community Advisory Group
Agenda
•Sediment sampling schedule and objectives
•Sample collection metrics
•Sediment sampling locations and progress
•Sampling vessels in use
Sediment Sampling Timeline
Activity
• Pre-mobilization activities
• Mobilization and Site Set-up
• Sediment Sampling
• Laboratory Analyses
Timeframe
• Early August to Early October
• Early to mid-October
• Mid-October to early January 2018
• Late October to late January
Sediment Core Collection and Data Analysis
Sediment cores collected to provide input to dredging and engineered capping design, dredged material handling, dewatering, transportation & disposal planning
•Chemical analysis
•Geotechnical characterization
•Waste characterization
Sediment core locations planned: 958
Sediment core locations completed: 341 or 36%
Sediment cores collected: 341 for sediment chemistry98 for waste characterization26 for geotechnical data5 DRET/CST
Samples sent to the laboratory: 3,385
Sediment sample analysis types: 3,056 for chemistry235 for waste characterization94 for geotechnical data
Sediment cores collected with Sonic Rig: 30 locations
Sediment cores collected with Vibracore: 146 locations
Sediment cores collected manually: 165 locations
Sonic Drill Rig Courtesy of Ann Arbor Technical Services (ATS)Access ramp at the Clean Earth property