MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Oct-2013
SL NO PACKAGE DISCIPLINE AGENCY 3-Oct-13 4-Oct-13 5-Oct-13 7-Oct-13 8-Oct-13 9-Oct-13T A T A T A T A T A T A
1 TG-1 & PH-1 Civil SPCL 100 65 100 66 100 66 100 66 100 66 100 63
2 TG-2 & PH-2 Civil SPCL 100 176 100 181 100 181 100 181 100 181 100 178
3 Control Building Civil SPCL 135 57 135 65 135 65 135 65 135 65 135 65
4 Guard Pond Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 0
5 Fire Station Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
6 ESP-1 & 2 Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
7 Boiler-1 & 2 Civil SPCL 50 48 50 52 50 52 50 52 50 52 50 56
8 TG #1 & 2 & Control Building Structural SPCL 200 200 200 123 200 134 200 171 200 171 200 163
9 TG#1 Painting Structural SPCL 35 54 35 54 35 54 35 54 35 54 35 56
10 Fabrication U#1 Fabrication SPCL 0 0 0 0 0 0 0 0 0 0 0 0
11 Fabrication U#2 Fabrication SPCL 100 74 100 74 100 74 100 74 100 74 100 72
12 ID Fan Unit #1 & 2 Civil SPCL 10 0 10 0 10 14 10 14 10 14 10 12
13 Bowl Mill # 2 Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
14 Service Building Civil SPCL 100 82 100 70 100 70 100 70 100 70 100 72
15 Canteen Building Civil SPCL 20 12 20 12 20 12 20 12 20 12 20 17
16 Storage Shed Civil/Ern SPCL 70 37 70 37 70 37 70 37 70 37 70 39
17 Civil SPCL 80 136 80 136 80 136 80 136 80 136 80 136
18 SA Fan Foundation Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
19 PA Fan Foundation Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
20 FD Fan Foundation Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0
21 Cable Rack & trench Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 0
22 Cable Rack Mech SPCL 40 58 40 58 40 58 40 51 40 51 40 53
23 Drain & Road Civil SPCL 12 0 12 0 12 0 12 0 12 0 12 0
24 Siemens SwitchYard Civil SPCL 0 0 0 8 0 0 0 0 0 0 0 0
25 Air Compressor Building Civil SPCL 10 9 10 10 10 10 10 10 10 10 10 13
SPCL 1082 1008 1082 946 1082 963 1082 993 1082 993 1082 995
Night Shift Civil SPCL 0 0 0 0 0 0
26 BOILER-1 ERECTION BHEL/PCP 540 250 540 252 540 263 540 205 540 201 540 249
Fitters BHEL/PCP 25 8 25 8 25 8 25 6 25 6 25 8
Welders BHEL/PCP 55 15 55 15 55 15 55 12 55 11 55 14
Ducting BHEL/PCP 120 69 120 70 120 69 120 58 120 58 120 73
Mill BHEL/PCP 35 0 35 0 35 0 35 0 35 0 35 8
Fans & APH BHEL/PCP 15 26 15 26 15 26 15 26 15 26 15 18
Night Shift BHEL/PCP 0 0 0 0 0 0
27 ERECTION BHEL/UBEL 540 370 540 371 540 373 540 352 540 380 540 375
Fitters-PP BHEL/UBEL 20 7 20 8 20 8 20 7 20 8 20 8
IBR Welders BHEL/UBEL 10 2 10 2 10 2 10 2 10 2 10 2
Ducting BHEL/UBEL 120 71 120 71 120 72 120 58 120 75 120 73
Mill BHEL/UBEL 40 0 40 0 40 0 40 0 40 0 40 0
Fans & APH BHEL/UBEL 15 26 15 26 15 26 15 26 15 26 15 26
28 POWER CYCLE PIPING-1 ERECTION BHEL/B&R 602 579 602 582 602 587 602 621 602 614 602 614
29 LINING & INSULATION -1 ERECTION BHEL/B&R 240 205 240 205 240 167 240 245 240 248 240 248
B & R 842 784 842 787 842 754 842 866 842 862 842 862
Night Shift B & R 0 10 10 10 10 10
30 LINING & INSULATION -2 ERECTION BHEL/PowerMech 150 75 150 75 150 75 150 75 150 68 150 68
31 POWER CYCLE PIPING-2 ERECTION BHEL/PowerMech 250 70 250 70 250 70 250 70 250 70 250 70
PowerMech 400 145 400 145 400 145 400 145 400 138 400 138
Night Shift PowerMech 0 0 0 0 0 0
32 BTG-Electrical Erection BHEL/Vasavi 180 180 180 180 180 180 180 180 180 180 180 171
33 BTG-C&I Erection U#01 BHEL/Auto Trical 75 72 75 72 75 72 75 72 75 72 75 72
Misc (Store, Batching plant,QC,survey, steel yard,etc)
BOILER-2
Page 2 of 4
MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Oct-2013
SL NO PACKAGE DISCIPLINE AGENCY 3-Oct-13 4-Oct-13 5-Oct-13 7-Oct-13 8-Oct-13 9-Oct-13T A T A T A T A T A T A
34 BTG-C&I Erection U#02 50 27 50 27 50 28 50 27 50 28 50 28
35 PHB Cladding Erection Lloyd Insulation 50 34 50 34 50 34 50 34 50 34 50 25
36 TURBINE-1 ERECTION BHEL/UBEL 200 190 200 191 200 191 200 191 200 194 200 194
37 TURBINE-2 ERECTION BHEL/EEPL 100 50 100 49 100 49 100 49 100 51 100 51
UBEL 740 560 740 562 740 564 740 543 740 574 740 569
Night Shift UBEL 0 0 0 0 0 0
38 ESP-1 & Ducting ERECTION BHEL/Golden Edge 321 304 321 291 321 282 321 318 321 304 321 323
Night Shift 70 65 59 59 65 75
39 ESP-2 & Ducting ERECTION BHEL/Rukmani 250 166 250 174 250 148 250 111 250 164 250 162
40 Mill Bunker-2Fabrication/ Erection Rukmani 20 22 20 21 20 17 20 17 20 5 20 5
Fabrication/ Erection Omega 200 179 200 191 200 191 200 181 200 191 200 191
Rukmani/Omega 470 367 470 386 470 356 470 309 470 360 470 358
Night Shift Rukmani/Omega 21 19 21 25 21 27
41 ESP Control Room & ID fan Civil Gammon 75 90 75 91 75 91 75 93 75 89 75 89
42 ChimneyCIVIL Gammon 15 4 15 4 15 4 15 4 15 4 15 4
ERECTION Gammon 20 24 20 24 20 24 20 24 20 24 20 24
43 CW Pump House & SG BldgCIVIL Gammon 15 12 15 12 15 12 15 12 15 12 15 12
Fab/Ern Gammon 0 0 0 0 0 0 0 0 0 0 0 0
44 Water treatment plant CIVIL Gammon 175 179 175 182 175 179 175 184 175 177 175 182
45 CIVIL Gammon 50 26 50 27 50 26 50 26 50 25 50 21
46 Air Washer Building CIVIL Gammon 10 5 10 5 10 7 10 7 10 7 10 10
47 Fuel Oil Pump House CIVIL Gammon 50 26 50 27 50 27 50 31 50 31 50 31
48 Pipe rackCIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0
Gammon 10 10 10 11 10 10 10 10 10 10 10 10
49 Raw Water Pump House CIVIL Gammon 45 28 45 28 45 28 45 29 45 31 45 30
50 CW PipingCIVIL Gammon 20 0 20 0 20 0 20 0 20 0 20 0
ERECTION Gammon 30 25 30 22 30 23 30 23 30 24 30 24
51 TOWNSHIP CIVIL Gammon 335 298 335 294 335 304 335 286 335 286 335 307
52 ACW Piping Fabrication/ Erection Gammon 0 0 0 0 0 0 0 0 0 0 0 0
53 Transformer yard Civil Gammon 135 102 135 97 135 97 135 97 135 91 135 91
54 Transformer yard-Drain Civil Gammon 30 10 30 0 30 0 30 0 30 0 30 0
55 Civil Gammon 90 71 90 70 90 75 90 75 90 75 90 75
56 Raw Water Pump House Fabrication Gammon 0 0 0 0 0 0 0 0 0 0 0 0
57 Misc Gammon 130 126 130 131 130 129 130 132 130 131 130 131
GAMMON 1295 1090 1295 1077 1295 1087 1295 1089 1295 1075 1295 1096
Night Shift Civil GAMMON 95 95 92 92 97 97
58 0 0 0 0 0 0 0 0 0 0 0 0
59 TRANSMISSION LINECIVIL GAMMON 100 25 100 25 100 25 100 25 100 25 100 25
ERECTION GAMMON 400 200 400 200 400 200 400 200 400 200 400 200
500 225 500 225 500 225 500 225 500 225 500 225
60CIVIL SIEMENS 50 30 50 30 50 30 50 30 50 30 50 30
ERECTION SIEMENS 0 0 0 0 0 0 0 0 0 0 0 0
61 E BOPCIVIL SIEMENS 70 20 70 20 70 21 70 21 70 21 70 5
ERECTION SIEMENS 100 131 100 132 100 132 100 132 100 132 100 121
BHEL/Powertronics
BHEL/Golden Edge
CW Side Stream Filtration Unit & Chlorination Building
Fab/Erection & Painting
River Water PH,channel & forebay & Cofferdam
Misc (Store, batching plant,QC,survey etc)
Overhead Service Tank-Township
Abhinav Construction
GAMMON-TR LINE
Bays at Angul pooling station with metering yard
Page 3 of 4
MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Oct-2013
SL NO PACKAGE DISCIPLINE AGENCY 3-Oct-13 4-Oct-13 5-Oct-13 7-Oct-13 8-Oct-13 9-Oct-13T A T A T A T A T A T A
SIEMENS 220 181 220 182 220 183 220 183 220 183 220 156
Night Shift SIEMENS
62 LP PIPING ERECTION Zeromm 100 75 100 75 100 70 100 75 100 70 100 70
63 ERECTION NEW FIRE ENGG. 100 70 100 60 100 60 100 60 100 60 100 60
64 DG Building CIVIL KSSIIPL 10 0 10 0 10 0 10 6 10 6 10 6
65 Mill Bunker-1 CIVIL KSSIIPL 15 11 15 11 15 11 15 0 15 4 15 25
Erection KSSIIPL 300 301 300 299 300 299 300 293 300 304 300 302
66 Duct Support & ID fan CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0
67 ESP control room-2 CIVIL KSSIIPL 120 110 120 113 120 113 120 113 120 116 120 105
68 PA, FD fan foundation CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0
69 Structural Erection-TG-2 ERECTION KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0
70 Structural Fabrication Fabrication KSSIIPL 175 121 175 121 175 121 175 120 175 120 175 119
71 Misc KSSIIPL 55 19 55 19 55 19 55 19 55 19 55 19
KSSIIPL 675 562 675 563 675 563 675 551 675 569 675 576
Night Shift KSSIIPL 74 72 72 68 71 69
72 COOLING TOWER-1CIVIL PCTL 20 18 20 17 20 18 20 10 20 11 20 11
ERECTION PCTL 0 0 0 0 0 0 0 0 0 0 0 0
73 COOLING TOWER-2CIVIL PCTL 200 142 200 145 200 144 200 154 200 154 200 154
ERECTION PCTL 80 30 80 31 80 31 80 31 80 31 80 31
PCTL 300 190 300 193 300 193 300 195 300 196 300 196
Night Shift PCTL 0 0 0 0 0 0
74CIVIL TECPRO 150 95 150 93 150 95 150 95 150 102 150 105
ERECTION TECPRO 200 200 200 199 200 170 200 170 200 140 200 151
75CIVIL TECPRO 40 18 40 15 40 15 40 15 40 15 40 16
ERECTION TECPRO 30 8 30 9 30 17 30 13 30 11 30 8
TECPRO 420 321 420 316 420 297 420 293 420 268 420 280
Night Shift Tecpro 8 6 5 6 5 10
76 C W PUMPs ERECTION KBL 30 22 30 22 30 20 30 21 30 21 30 22
77 River Water Piping RAUNAQ 50 5 50 20 50 22 50 21 50 21 50 23
78 Raw Water Pump house ERECTION RAUNAQ 15 9 15 11 15 12 15 12 15 12 15 12
79 River Water Pump House ERECTION RAUNAQ 15 12 15 10 15 10 15 10 15 10 15 10
80 CW makeup line ERECTION RAUNAQ 10 9 10 9 10 9 10 9 10 9 10 9
RAUNAQ 90 35 90 50 90 53 90 52 90 52 90 54
81 CIVIL SAMARPITA 0 0 0 0 0 0 0 0 0 0 0 0
82 ERECTION IEL 110 45 110 45 110 45 110 45 110 45 110 42
83 FLY ASH SYSTEMCIVIL MACAWBER 100 74 100 82 100 82 100 52 100 52 100 52
ERECTION MACAWBER 90 73 90 71 90 67 90 58 90 68 90 77
84
CIVIL BSBK 65 70 65 62 65 62 65 62 65 58 65 58
ERECTION BSBK 40 47 40 46 40 42 40 46 40 46 40 45
Refractory ERECTION BSBK 0 0 0 0 0 0 0 0 0 0 0 0
MBPL/BSBK 295 264 295 261 295 253 295 218 295 224 295 232
Night Shift MBPL/BSBK 0 0 0 0 0 0
85 ERECTION ATLAS COPCO 10 5 10 5 10 10 10 0 10 5 10 0
86 FUEL OIL SYSTEM ERECTION 20 22 20 17 20 12 20 13 20 11 20 10
87 ERECTION 40 34 40 34 40 34 40 34 40 34 40 22
88 EOT CRANE 105/15 T-2ND ERECTION WMI 0 0 0 0 0 0 0 0 0 0 0 0
FIRE PROTECTION SYSTEM
Infrastructure & Misc (Store, batching plant,QC,survey ,steel yard etc)
CHP
MINE CONVEYOR SYSTEM
CIVIL/ERECTION
Haul Road-River Water System
WATER TREATMENT PLANT
BOTTOM ASH HANDLING SYSTEM
COMPRESSED AIR SYSTEM
THERMOSYSTEMS
AIR CONDITIONING SYSTEM
STERLING & WILSON
Page 4 of 4
MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Oct-2013
SL NO PACKAGE DISCIPLINE AGENCY 3-Oct-13 4-Oct-13 5-Oct-13 7-Oct-13 8-Oct-13 9-Oct-13T A T A T A T A T A T A
89 EOT CRANE -30 T ERECTION SAFEX 15 1 15 0 15 0 15 0 15 0 15 0
90CIVIL Gammon 40 41 40 41 40 41 40 41 40 41 40 41
ERECTION Airox Nigen 0 0 0 0 0 0 0 0 0 0 0 0
91CIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0
ERECTION Ion Exchange 0 0 0 0 0 0 0 0 0 0 0 0
92 ERECTION CHEMTROL 0 0 0 0 0 0 0 0 0 0 0 0
93 COLTCS ERECTION GEA-BGR 0 0 0 0 0 0 0 0 0 0 0 0
94 WORKSHOP EQUIP.-I ERECTION HMT 0 0 0 0 0 0 0 0 0 0 0 0
95 ERECTION BATLIBOI 0 0 0 0 0 0 0 0 0 0 0 0
96 WORKSHOP EQUIP.-III ERECTION PATHAK 0 0 0 0 0 0 0 0 0 0 0 0
97 Raw Water Reservoir Civil Sinhotia 350 355 350 354 350 356 350 325 350 282 350 255
98 Roads
Civil Nanda 30 15 30 25 30 22 30 22 30 19 30 23
Civil RK Associates 25 17 25 18 25 18 25 18 25 23 25 15
Civil Pradhan 25 13 25 22 25 21 25 21 25 22 25 12
Civil Monalisha 25 0 25 0 25 0 25 0 25 0 25 0
99 Civil Monalisha 60 82 60 82 60 88 60 83 60 79 60 85
100 Peripheral Drainage-II Civil R K Associates 50 0 50 0 50 0 50 0 50 0 50 0
101 Internal DrainsCivil R K Associates 95 85 95 85 95 72 95 78 95 83 95 78
Civil Gammon 20 13 20 11 20 10 20 15 20 17 20 14
102 Ash Dyke` Civil Sinhotia 100 0 100 0 100 0 100 0 100 0 100 0
145 85 145 85 145 72 145 78 145 83 145 78
60 82 60 82 60 88 60 83 60 79 60 85
Sinhotia 450 355 450 354 450 356 450 325 450 282 450 255
Night Shift Sinhotia 0 125 95 70 50 35
103 EOT CRANE ERECTION Electromech 5 0 5 0 5 0 5 0 5 0 5 0
TOTAL 9835 7490 9835 7442 9835 7372 9835 7342 9835 7343 9835 7350
Night Shift (Total) 268 392 354 330 319 323
Note:
HYDROGEN GENERATION PLANT
SEWAGE TREATMENT PLANT
Ambient Air Quality Monitoring System
WORKSHOP EQUIP.-II (BATLIBOI)
Peripheral Drainage-I + Internal drain
R K Associates( Drain)
Monalisha(Drains)
(i) Agency wise manpower includes night shift manpower also. Total manpower in night shift as on 08.10.2013 - 323 heads.(ii) Manpower is in reducing trend due to Durga Puja & Dussehra festival ahead.