Upload
dotuyen
View
215
Download
2
Embed Size (px)
Citation preview
Masahiro AOKIIntegrated Nuclear Infrastructure Group (INIG)
27 July 2011
2
3
•Sequential development through the 3 Phases for each of 19 infrastructure issues
•Ranging from government’s national position on nuclear power to procurement of items and services for the 1st NPP
There are 3 Phases and 3 Milestones
Phase Milestone1. Pre-project 1. Ready to make a knowledgeable
commitment to a nuclear programme2. Decision making 2. Ready to invite bids for the 1st NPP3. Construction 3. Ready to commission and operate
the 1st NPP
4
5
Key Infrastructure Issues
• National position• Nuclear safety• Management• Funding and financing• Legislative framework• Safeguards• Regulatory framework• Radiation protection• Electrical grid• Human resources
development
• Stakeholder involvement• Site and supporting
facilities• Environmental protection• Emergency planning• Security and physical
protection• Nuclear fuel cycle• Radioactive waste• Industrial involvement• Procurement
6
Preparing for assuming commitments & obligationsIn
fras
truc
ture
dev
elop
men
t pro
gram
1st. N
PP P
roje
ct
Commissioning
Operation / decommissioning
Nuclear power option included within the
national energy strategy
10 – 15 years
PHASE 2
PHASE 3
PHASE 1
MILESTONE 1Ready to make a knowledgeable
commitment to a nuclear programme
MILESTONE 2Ready to invite bids
for the first NPP
MILESTONE 3Ready to commission and
operate the first NPP
Feasibility study Bidding process
Pre project Project decision making Construction
Considerations before a decision to launch a nuclear power programme is taken
Preparatory work for the construction of a NPP after a policy decision has been taken
Activities to implement a first NPP
Maintenance and continuous infrastructure improvement
INFRASTRUCTURE DEVELOPMENT PROGRAMME
Never moving beyond planning stage
Focusing on specific issues but missing the big picture
Inviting bids with no appropriate response
Developing unsustainable nuclear power programme
7
Description Number in 2008
Number in 2010
Not planning to introduce nuclear power plants, but interested in considering the issues associated with a nuclear power programme
16 31
Considering a nuclear programme to meet identified energy needs with a strong indication of intention to proceed
14 14
Active preparation for a possible nuclear power programme with no final decision
7 7
Decided to introduce nuclear power and started preparing the appropriate infrastructure
4 10
Invitation to bid to supply a nuclear power plant prepared 1
New nuclear power plant ordered 2
New nuclear power plant under construction 1 1
Total 43 65
8
After Fukushima Accident, of 38 countries without nuclear power that, before the accident, had strongly indicated their intentions to proceed with nuclear power programmes, including those with active construction or reactors on order, a few have cancelled or revised their plans but most have not.
9
0
5
10
15
20
25
30
35
40
45
2007-2008 2009-2011 2012-2013concepts
NationalRegional
IAEA Technical Cooperation
10
IAEA’s role
• Standards and Guidance• Reviews and Services• Capacity Building• Knowledge Networks• Forum for communicating, increasing
transparency, sharing lessons learned
Established in July 2010 Purpose- Improved development and delivery of the
IAEA nuclear infarstructure related services
- Improved integration of the IAEA activities- Better coordination on technical aspects of
the TC projects- Optimization of the IAEA staff resources
dedicated to these services
11
12
DecommissioningOperationConstructionPrep work for construction
Considerations before decision
to launch
Phase 1 Phase 2 Phase 3
13
- Milestone approach/ Evaluation Methodology/ INIR Guideline
- Responsibilities and Capabilities of NEPIO (Nuclear Energy Programme Implementing Organization) (2009)- Initiating Nuclear Power Programmes: Responsibilities and Capabilities of Owners and Operators
2007 2008 2008
Jordan - August 2009 (Phase 1) Indonesia - November 2009 (Phase 1) Vietnam - December 2009 (Phase 1) Thailand - December 2010 (Phase 1) UAE - January 2011 (Phase 2&1)
14
15
1 National Position Phase 1Condition Status1.1 Safety, security and non-proliferation needsrecognized
Minor Actions Needed
1.2 NEPIO established and staffed No Actions Needed1.3 National strategy defined No Actions Needed
2 Nuclear Safety Phase 1Condition Status2.1 Understanding of key elements of nuclear safety
Minor Actions Needed
2.2 Need of intergovernmental instruments on safety
No Actions Needed
2.3 Support through international cooperation Significant Actions Needed
INIR
Integration of technical elements – “catalogue of services” for sub-elements of 19 items
Element Sub-element Phase 1 Phase 2WS EM RM WS EM RM
National Position
National Policy, Strategic Plan, Feasibility Study and
pre-feasibility study◘ ◘
Energy Planning, Sustainability of Nuclear
Energy System◘ ◘ ◘
Public Communication ◘
16
Example
WS: Workshop, EM: Expert Mission, RM: Review Mission
17
Thematic Areas Phase 1 Phase 2
National position
Nuclear safety
Management
Funding and Financing
Legal framework
Safeguards
Regulatory framework
Radiation protection
Electrical grid
Radioactive waste
Industrial involvement
Procurement
HR development
Stakeholder involvement
Site and supporting facilities
Environmental protection
Emergency planning
Security
Nuclear fuel cycle
Example fo ths staus of nuclear power infrastrucutre for 19 issues
18
Core Team established in the IAEA-Technical officer and PMO for TC-Experts from other technical deparatments
e.g. Safety, Security, SG, HRD, Legal affairs,Energy Plan, Waste, Emergency response etc.
Integrated Workplan
Self-EvaluationExercise
Implementation of TC projects
Information on the nuclear infrastructure in country (CNIP=Country Nuclear Infrastructure Profile) INIR
19
Phase 1
decision
Phase 2 Phase 3
call for tenders commissioning
Operation
Before contract After contract
Several bilateral assistance may be provided in parallel
Most of the assistance provided by the vendor and by the RB that have licensed a similar facility
Signature of the Contract
- Bilateral Assistance can facilitate the development of nuclear infrastructureAnd it will be further augmented with- Multi-lateral information sharing- Soft-coordination among bilateral cooperation
20
- Experts in the Mission- Acceptance of Fellowship and Scientific Visit- Sharing experience through workshops, netwoking and
the development of the IAEA document
Appreciate to co-hosting the training course with the IAEA- KHNP: Mentoring Programme - KOICA/KAERI: Nuclear Power Policy, Planning and
Project Management- Argonne National Laboratory: Leadership and Management- French Atomic Energy Commission: Leadership and Management
- Proposal from - JICC and- KAERI on Technical Aspects for NP Introduction
21
http://www.iaea.org/NuclearPower/Infrastructure/Meetings/2011-02-TM-WS-Vienna.html
89 participants from more than 45 countries discussed the developmentof a national position, their experiences with self-evaluation of infrastructure status and INIR Missions.
The Next Workshop is24-27 Jan 2012
22
- Adovisory Group to DDG-NE- The first TWG meeting in November 2011- Consist of 19 experts both from newcomer and experienced
countries (Chair; Mr R Mendez, Uruguay)
- Documents and assistance services have been developed and provided to MSs
- More integrate and phased approach for the IAEA assistance through INIG
- Support from experienced countries, including soft-coordination, to be further enhanced
- Lessons learned from Fukushima Accident to be shared
23
24
…atoms for peace.