Michel RAYMOND – July 1 st , 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

Embed Size (px)

DESCRIPTION

M. Raymond – July 1 st, 2013 Summary of LS1 opening Detector movements to Standard Opening Planned from Feb. 14 th to March 8 th From Feb.14 th to March 13 th,  + 3 days C side in Large Opening configuration Planned on March 28 th Completed on March 25 th,  - 3 days Pixels in SR1 Planned on April 18 th Completed on April 9 th,  - 7 days Opening process went fine even if a very intense period 2 teams of 12 persons working in 2 shifts + experts supports : Safety, RPE… + Interventions of many experts on the various systems : Beam Pipes, Calorimeters, Cryogenics, Muons, Lucid, Survey Only one major problem : 140 T crane failed during HF Truck lifting on C side (on Feb. 19 th ) Repair completed on Feb. 22 nd

Citation preview

Page 1: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

Michel RAYMOND – July 1st, 2013

Technical Support Activitiesin PH-ADO-PO

Summary of 2013 activities

Page 2: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Manpower assigned to the Technical Support (2013)

Point 1 FacilitiesDetector environment

C. Scalisi+ General support

+ Safety team

Counting roomsRacks

C. Scalisi

MagnetP. Benoit

C. Sordé (+ DSS)

Muons EEC. Leboube

F. Limia CondeA. Yandyan

Movement systemF. RossetC. Sordé

+ General support

Supervision/operations M. Raymond

AccessL. Rose-DulcinaG. AkhperjanianS. Yukhimchuk+ General support

Mechanical workshop G. Akhperjanian (20%)

C. LeboubeL. Rose-Dulcina

A. YandyanS. Yukhimchuk

+ A. Bode (PH/DT)

IBLL. Rose-DulcinaF. Limia CondeJD lifting

A. Bode C. LeboubeA. Yandyan

G. Akhperjanian

Page 3: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Summary of LS1 opening

Detector movements to Standard Opening Planned from Feb. 14th to March 8thFrom Feb.14th to March 13th, + 3 days

C side in Large Opening configuration Planned on March 28th Completed on March 25th, - 3 days

Pixels in SR1 Planned on April 18th Completed on April 9th, - 7 days

Opening process went fine even if a very intense period2 teams of 12 persons working in 2 shifts + experts supports : Safety, RPE… + Interventions of many experts on the various systems : Beam Pipes, Calorimeters, Cryogenics, Muons, Lucid, Survey

Only one major problem : 140 T crane failed during HF Truck lifting on C side (on Feb. 19th)Repair completed on Feb. 22nd

Page 4: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Planned on March 13th Completed on March 19th, + 4 days

The installation of the lifting frame on the Small Wheel has been more difficult than expected : Expected difficulties were well

anticipated Some unexpected ones appeared !!

This milestone was not on the critical path of the schedule :Work has been done quietly without taking risk

The whole opening process has been performed in reasonable agreement with the time schedule presented on previous Atlas week. It has open the door to significant activities on various detectors.

SW-C at surface

Page 5: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

EE chamber installation

Important activity regarding the schedule because of a strong impact on the activities in the experimental cavern :

Parallel to the opening process Requires specific configuration + dismounting of many access platforms on A side Space consuming on A side, Large use of crane

Preparatory workPlanned to start on Feb. 21st actual start on Feb 26th

Chamber installation (mechanics)EEL planned from Feb. 25th to March 18th performed from Feb 28th to April 2nd EES planned from March. 29th to April 26th performed from March 26th to April 18th

Chamber alignment and commissioning Planned to be completed on May 8th actual completion on May 15th

Page 6: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Objectives 2013 – Where we are

Opening process Atlas opening

Standard opening achieved after 3 weeks in 2 shifts Large opening needed 2 more weeks in standard hours

SW-C to surface Pixels extraction

Platforms and access Scaffolding to detectors

Hand rails on top of JFS (to be installed in 2014) Fabrication and installation of additional access to EEL and EES

11 platforms installed 1 missing

Replacement of provisional access with permanent platforms (S3 & S7)

Legend : Done, On going, Not yet done

Logistics Logistics for IBL Spare components on Muon system

Page 7: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Objectives 2013 – Where we areInfrastructure and safety system

Sniffers maintenance ( to be started again before end 2013) Improvement of plastic cover on top of PX16

Maintenance and upgrade of the existing movement system Improvement of air supply table

Improvement of accuracy of detector positioning Improvement of ECTs movement devices (ECT-C done) Development of a new movement machine Consolidation / repair of the system

Shielding ECT shielding : still under study TAS shielding : installed ECTs shielding : installed USA15 shielding (under study)

IBL project Machining of finalized parts and assembly Set up of the environment around the mock-up (July / August 2013)

Test and development around the mock-up

Page 8: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Muon chambers EEL & EES installed Mechanics for BOE Fabrication of BW nacelle BOE installation Preparatory work for BME

Small Wheel Support to the replacement of 2 CSC chambers (sept/oct 2013)

Objectives 2013 – Where we are

Magnet Design and manufacture of ECT Z-stops Dismounting / Mounting of BT diffusion pumps on A side Anti-seismic brackets installed Checking/Consolidation of Bus bars Upgrade of AFT, development on alignment system Warm structure check (control in 2013) Participation to DSS & Magnet control piquet

Legend : Done, On going, Not yet done

Page 9: Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities

M. Raymond – July 1st, 2013

Distribution of 2013 activities

Plot is based on affected time (78% of total time)