Suzlon Energy Australia: Design and delivery of wind energy projects www.suzlon.com wind energy projects Mike Bagot Coolah 27/8/2010

Mike Bagot Suzlon

Embed Size (px)

Citation preview

Page 1: Mike Bagot Suzlon

Suzlon Energy

Australia:

Design and delivery of

wind energy projects

www.suzlon.com

wind energy projects

Mike Bagot Coolah 27/8/2010

Page 2: Mike Bagot Suzlon

Introducing Suzlon

www.suzlon.com

Page 3: Mike Bagot Suzlon

Operating 640 MW

Under construction 110 MW

Australian Projects

Suzlon’s Projects:

www.suzlon.com

Under construction 110 MW

Operating 1,800 MW

Under construction 200 MW

Approved > 5,000 MW

Proposed > 10,000 MW

Australian Market:

Page 4: Mike Bagot Suzlon

Suzlon’s Capabilities

• We have experience with all aspects of wind

energy project delivery

o Wind engineering

Civil Engineering design

www.suzlon.com

o Civil Engineering design

o Electrical Engineering design

o Grid Connection design

o Construction

o Service & Maintenance

o Supply chain and Logistics management

Page 5: Mike Bagot Suzlon

Why do we need the Renewable

Energy Target?

www.suzlon.com

Energy Target?

A few quick words about policy

5

Page 6: Mike Bagot Suzlon

History of the MRET

Howard’s original policy was very

successful- the 2% Target was reached in

2006. Growth in the industry greatly

reduced as REC price dropped as target

reached

www.suzlon.com6

In 2007 Kevin Rudd announced policy

plans for a second MRET- 20% of

electricity consumption by 2020 to

come from renewable energy

Page 7: Mike Bagot Suzlon

Why do we need the RET?

REC Price

www.suzlon.com7

Price ($)

Year

Page 8: Mike Bagot Suzlon

Why do we need the RET?

www.suzlon.com8

Page 9: Mike Bagot Suzlon

Without long term certainty and a

functioning incentive scheme, wind

farms will not be built.

www.suzlon.com

farms will not be built.

This is why the RET is important to our

industry.

9

Page 10: Mike Bagot Suzlon

Three defined stages in the life of a wind farm:

• Development (3-5 years)

Typical life of a wind farm

www.suzlon.com

• Development (3-5 years)

• Construction (1½-3 years)

• Operation (+25 years )

Focus of the presentation is on construction and

operation

10

Page 11: Mike Bagot Suzlon

How does is a wind farm built?

www.suzlon.com

Page 12: Mike Bagot Suzlon

What can landowners expect during the

www.suzlon.com

What can landowners expect during the

construction phase of a project?

12

Page 13: Mike Bagot Suzlon

Building access roads

www.suzlon.com

Page 14: Mike Bagot Suzlon

Foundations

www.suzlon.com14

Page 15: Mike Bagot Suzlon

Foundations

www.suzlon.com15

Page 16: Mike Bagot Suzlon

• Wind turbines require stable foundations at their base to hold them in

place to stop high winds from toppling them over.

• Suzlon S88 turbines weigh over 270 tonnes and stand 124 metres high to

the tip of the blade.

Foundations

www.suzlon.com

Page 17: Mike Bagot Suzlon

Foundations and reticulation

www.suzlon.com17

Page 18: Mike Bagot Suzlon

Tower manufacture and delivery

www.suzlon.com

Page 19: Mike Bagot Suzlon

www.suzlon.com

Page 20: Mike Bagot Suzlon

Tower assembly

www.suzlon.com20

Page 21: Mike Bagot Suzlon

Tower assembly

www.suzlon.com

Page 22: Mike Bagot Suzlon

Nacelle

www.suzlon.com

•The nacelle houses the generation

unit and the gearbox

•The structure has a steel reinforced

fiberglass shell and weighs 70

tonnes.

Page 23: Mike Bagot Suzlon

Construction is challenging

www.suzlon.com23

Page 24: Mike Bagot Suzlon

Generator main shaft

www.suzlon.com24

Page 25: Mike Bagot Suzlon

Generator cooling system

www.suzlon.com25

Page 26: Mike Bagot Suzlon

Blade shipping

www.suzlon.com26

Page 27: Mike Bagot Suzlon

Transport from port

www.suzlon.com27

Page 28: Mike Bagot Suzlon

Arrival at site

www.suzlon.com28

Page 29: Mike Bagot Suzlon

Help where required….

www.suzlon.com

Page 30: Mike Bagot Suzlon

www.suzlon.com30

Page 31: Mike Bagot Suzlon

Transport around the site

www.suzlon.com31

Page 32: Mike Bagot Suzlon

Prepare for Rotor Assembly

www.suzlon.com32

Page 33: Mike Bagot Suzlon

Rotor Assembly

www.suzlon.com

Page 34: Mike Bagot Suzlon

Hub & Nosecone

www.suzlon.com

Page 35: Mike Bagot Suzlon

Rotor Installation

www.suzlon.com

Page 36: Mike Bagot Suzlon

Rotor Installation

www.suzlon.com36

Page 37: Mike Bagot Suzlon

Snowtown

www.suzlon.com37

Page 38: Mike Bagot Suzlon

www.suzlon.com

Page 39: Mike Bagot Suzlon

Thirsty?

www.suzlon.com39

Page 40: Mike Bagot Suzlon

Site Substation

www.suzlon.com

Page 41: Mike Bagot Suzlon

Site Substation

www.suzlon.com41

Page 42: Mike Bagot Suzlon

Site Substation

www.suzlon.com42

Page 43: Mike Bagot Suzlon

Substation at Capital WF

www.suzlon.com43

Page 44: Mike Bagot Suzlon

Open days

www.suzlon.com44

Page 45: Mike Bagot Suzlon

On-going operation and maintenance

• On going service and maintenance throughout the life of the farm

www.suzlon.com

• 24/7 monitoring centre in Melbourne

• Economic stimulus for the region continues for the operational life of the infrastructure

Page 46: Mike Bagot Suzlon

Around the clock monitoring

www.suzlon.com46

Page 47: Mike Bagot Suzlon

Operation

• 25 year project lifespan typical for projects

• Wind turbine Power Performance Testing

• Post construction sound pressure level

testing

www.suzlon.com

testing

• Usually a tech for each 7 turbines

• Community fund for the life of the project

• On-going environmental management of site

• Potential for turbine upgrades

47

Page 48: Mike Bagot Suzlon

Local benefits

Local benefits to wind farm projects exist and they are considerable.

JOBS:

-Specialist technicians

-Electricians

- Freight operators

- Machine operators

- General labourers

Other benefits:

-Community funds

-Landowner payments

- Stimulus of local industries

-Hospitality

-Accommodation

www.suzlon.com

Wind farms deliver much substantial than the

community benefits from coal/gas generation projects.

48

- General labourers

-Concrete businesses

-Engineering & Geotech

-Accommodation

-Equipment hire

Page 49: Mike Bagot Suzlon

- 4 wind farms 209 turbines ~440 MW

- Wind farming provided an annual increase of between

more than 1% each year to the region’s Gross Regional

Product over the approx 10 year project span

AGL’s Hallett Wind Farms

www.suzlon.com

Hallett Project expenditure

49

As of 10 July 2010* Mid North Rest SA Rest Aust Total Aust Overseas Total % of total

Development ($k) 1560 8,086 8,902 18,548 0 18,548 2.28%

Construction ($k) 83,047 254,578 122,624 460,249 321,088 781,336 96.05%

Operation ($k) 3,186 4,108 6,302 13,595 0 13,595 1.67%

Overall 87,793 266,771 137,827 492,392 321,088 813,479

% of total 10.79% 32.79% 16.94% 60.53% 39.47%

* Source: Economic Assessment of the Hallett Wind Farms, SKM, 2010