34
1 MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN FOR ROAD METAL AND BUILDING STONE QUARRY OVER AN EXTENT OF 0.773 Ha IN Sy. NO.249/5P, OF KOTHAPALLE (V), S.R.PURAM (M), CHITTOOR DISTRICT, A.P. INTRODUCTION M/s. Vijayalakshmi Stone Crushers, Managing Partner.T.Murali, has filed an application for grant of of Quarry Lease for Road Metal and Building Stone over an extent of 0.773 Hectares in Sy. No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15 years and the same was received by the Assistant Director of Mines and Geology (ADM &G), Chittoor on 06.02.2003.. The Assistant Director of Mines and Geology (ADM &G), Chittoor has submitted proposals vide File. No.2046/Q/2003, dated.05.05.2003 to DDMG, Kadapa, duly recommending for grant of QL for Road Metal and Building stone over an extent of 0.773 Hectares in Sy. No.249/5P of Kothalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15 years in favour of M/s. Vijayalakshmi Stone Crushers, Managing Partner. T.Murali subject to the satisfaction of Andhra Pradesh Minor Mineral Conservation (APMMC) Rules, 1966 and subsequent instructions issued from time to time. Further the Deputy Director of Mines and Geology (DDM&G), Kadapa based on the recommendation of the ADMG, Chittoor vide Proceeding no.2046/Q/2003, dated12.05.2003 is here by granted the quarry lease in favour of M/s.Vijayalakshmi Stone Crushers, Managing Partner. Sri. T.Murali for Road Metal & Building Stone over an extent of 0.773 Hectares in Sy. No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15 years, as per Rule 13(1) of Andhra Pradesh Minor Mineral Rules, 1966 subject to the satisfaction of other terms and conditions specified in the appendix enclosed to these orders and also subject to the following conditions as shown in Annexure - II . Accordingly the Assistant Director of Mines & Geology, Chittoor vide proceedings no.562/Q/2003, dated 16.06.2003 is here by accorded to work for Road Metal & Building Stone quarry lease over an extent of 0.773 Hectares in Sy. No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh in favour of M/s.Vijayalakshmi Stone Crushers, Managing Partner. Sri.T.Murali for a period of 15 (Fifteen) years with effect from 16.06.2003 to 15.06.2018. as shown in Annexure - III

MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

1

MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN FOR ROAD

METAL AND BUILDING STONE QUARRY OVER AN EXTENT OF 0.773 Ha IN Sy.

NO.249/5P, OF KOTHAPALLE (V), S.R.PURAM (M), CHITTOOR DISTRICT, A.P.

INTRODUCTION

M/s. Vijayalakshmi Stone Crushers, Managing Partner.T.Murali, has filed an application for grant

of of Quarry Lease for Road Metal and Building Stone over an extent of 0.773 Hectares in Sy.

No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15

years and the same was received by the Assistant Director of Mines and Geology (ADM &G),

Chittoor on 06.02.2003..

The Assistant Director of Mines and Geology (ADM &G), Chittoor has submitted proposals vide

File. No.2046/Q/2003, dated.05.05.2003 to DDMG, Kadapa, duly recommending for grant of QL

for Road Metal and Building stone over an extent of 0.773 Hectares in Sy. No.249/5P of Kothalle

(V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15 years in favour of M/s.

Vijayalakshmi Stone Crushers, Managing Partner. T.Murali subject to the satisfaction of Andhra

Pradesh Minor Mineral Conservation (APMMC) Rules, 1966 and subsequent instructions issued

from time to time.

Further the Deputy Director of Mines and Geology (DDM&G), Kadapa based on the

recommendation of the ADMG, Chittoor vide Proceeding no.2046/Q/2003, dated12.05.2003 is

here by granted the quarry lease in favour of M/s.Vijayalakshmi Stone Crushers, Managing

Partner. Sri. T.Murali for Road Metal & Building Stone over an extent of 0.773 Hectares in Sy.

No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh for a period of 15

years, as per Rule 13(1) of Andhra Pradesh Minor Mineral Rules, 1966 subject to the satisfaction

of other terms and conditions specified in the appendix enclosed to these orders and also subject

to the following conditions as shown in Annexure - II .

Accordingly the Assistant Director of Mines & Geology, Chittoor vide proceedings

no.562/Q/2003, dated 16.06.2003 is here by accorded to work for Road Metal & Building Stone

quarry lease over an extent of 0.773 Hectares in Sy. No.249/5P of Kothapalle (V), S.R.Puram (M),

Chittoor District, Andhra Pradesh in favour of M/s.Vijayalakshmi Stone Crushers, Managing

Partner. Sri.T.Murali for a period of 15 (Fifteen) years with effect from 16.06.2003 to 15.06.2018.

as shown in Annexure - III

Page 2: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

2

The submission of Mining plan is a pre requisite for quarry lease as per Rule 7(A) of APMMC

Rules, 1966.As per the Notification of the Ministry of Environment & Forests, Climate Change

(MoEF& CC), New Delhi dated: 14 Sep 2006, it is mandatory for all the Mining Projects with lease

area of 5.000 Ha and above irrespective of the mineral (major or minor) to obtain prior

Environmental Clearance (EC) under the provisions thereof. Further, all Category A and Category

B1 projects shall under take public consultation in accordance with the above notification. Further

the Government of India, Ministry of Environment & Forest vide office memorandum No. L-

11011/47/2011-IA.II(M), Dated: 18th May, 2012 in order to ensure compliance of the Honourable

Supreme Court Dated:27.02.2012 in I.A.12-13 of 2011 in SLP( C ) No. 19628-19629 of 2009,

instruction were issued that all the mining projects of minor minerals including their renewal,

irrespective of the size of the lease would hence forth require prior environment clearance.

Decentralizing the Environmental Clearance (EC) for sustainable sand mining and mining of minor

minerals, Govt of India MoEF, has created District Environment Impact Assessment Authority

(DEIAA) vide S.O.141(E) dated 15 Jan 2016. This district level authority has the powers to

approve the ECs for the mining of minor minerals for an area less than 5.000 Ha.

As the area of mining in this case is less than 5.000 Ha (0.773 Ha) the lessee has to obtain EC

from MoEIAA, Delhi after the approval of this Mine Plan. In view of the above, the lessee intends

to prepare an Environmental Management plan for submission for grant of Environmental

Clearance for their proposed 0.773 Ha of Road Metal and Building Stone Quarry lease area,

thereby submitting this draft Mining Plan for necessary further action which is a pre-requisite for

EC.

In this connection, Sri.T.Murali, Managing Partner of M/s.Vijayalakshmi Stone Crushers, has

approached Mr. B.Damodaram, Consultant Geologist & RQP to prepare the Quarry Plan following

the prescribed guidelines. Hence, this Mining Plan is being prepared and submitted under Rule 7

(A) of APMMC’1966, following the contents of Form-T.

The proposed Mining Plan covers a scientific and systematic assessment of the deposit which

indicates the details of conservation of the deposit and protection of environment in and around

the quarrying area. The survey includes of Topographical Survey, Large Scale Mapping with

contours.

The survey enables the lessee to take up the exploration of Road Metal & Building Stone in a

systematic manner and plan for future expansion programme.

Page 3: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

3

This Mine Plan has been prepared taking into account strictly the restrictions to be adopted by the

applicant while conducting quarry operations due to the existence of any structures railway lines,

roads, water bodies such as river, lake etc., and the stipulated distances as per the various

Regulations prescribed under Metaliferous Mines Regulations, 1961.

The present Mining plan is being submitted to achieve the proposed production of

approximately 28,044 tones of road metal during the first five years plan of residual period.

i.e. 2017-18.

1.0 GENERAL

• Name and Address of Applicant / Lessee

Name M/s. Vijayalakshmi Stone Crushers,

Address Mg.Pt. T.Murali

H.no.2-418,Main Street.,

Kongareddypalle,, Chittoor,

District & State Chittoor (Dt), A.P State,

Mobile No. + 91

Status of Applicant / Lessee Private Individual

Mineral which is the Applicant

Intend to Mine Road Metal & Building Stone

Period for which the Mining Lease

Is Granted / Proposed to be Applied 15 Years

• Name of Recognized Person Preparing Mining Plan

Name: B.DAMODARAM

Consultant Geologist & RQP

Address: H.no: 19-12-87, Bairagipatteda,

Thirupati – 517 501, Chittoor (Dt)

Andhra Pradesh State

Mobile No: 9491043877 , 7780646416

Registration No(s) & validity RQP/DMG/HYD/106/13

Valid up to: 19-07-2023

Page 4: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

4

2.0 LOCATION AND ACCESSIBILITY

a. Lease Details (Existing Mine): It is an existing lease

Table 01: Details of First ‘Proposal Nos’ ,Lease Grant’

Name of lessee Location Extent

Ha

DDM&G,

Kadapa,Proc.

and date

ADM&G,Ctr,

Work

Order&date

Initial

lease

M/s.Vijayalakshmi

Stone Crusher

Sy. No. 249/5P

Kothapalle(V),

S.R.Puram(M),

Chittoor District,

A.P

0.773 2046/Q/2003,

12.05.2003

562/Q/2003,

16.06.2003

b. Details of Applied / Lease Area with Location Map (Fresh Area)

The Quarry Lease area can be approached from Chittoor – Puttur road travelled of about 25 km

via G.D.Nellore up to Kothapallemitta cross road and take diversion towards North of Kammapalle

road travelled of about 1.5 km and again take Right towards East a cart track travelled of about 1

km leads to QL area.

c. Description of the Area:

The proposed Quarry Lease area falls on the part of Survey of India Topo Sheet No. 57 O/3 & 57

O/7..The QL area is located North latitudes13° 18' 06.8ʺ to 13˚ 18ʹ 03.9ʺ and East longitudes 079˚

37ʹ 15’ 37..4ʺ to 79˚ 315ʹ 34.6ʺ(Plate 1).

Table 2: Description of the Area

State District Mandal Village Survey No.

Extent (Ha)

Status of Site

Andhra Pradesh

Chittoor S.R.Puram Kothapalli 249/5P 0.773 Govt. Revenue land (barren)

The proposed QL area is located at a distance from 1.0 km East of Ramakrishnapuram village of

S.R.Puram mandal, at a distance West of 1.5 km from Kottapalle village and at a distance of 64.5

km from the district headquarters of Chittoor.

i. Existence of public road / railway line, if any nearby and approximate distanceThe nearest

road is Kothapallimitta – Kammapalli road 1.0 km West of Quarry Lease area. Connecting Chittoor

Page 5: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

5

– Puttur road is at a distance of 1.5 km. The nearest railway station is at Chittoor at a distance of

28 km. Thirupati airport is at distance of 53 km from the QL area.

ii. Availability of Electricity, School and Medical Facility etc:

Electric line is available within 0.5 km of QL area for obtaining connection. Primary school are

available at Kothapallimitta village and high school are available at S.R.Puram mandal head

quarters,. Primary Health center is available in Kothapallemitta whereas well-equipped hospitals

are available in Chittoor.

iii. Toposheet No. with latitude and longitude of all Boundary Point / Pillars:

The quarry lease area falls on part of SOI Toposheet no. 57 O/3 & 57 O/7 and the Geo-

coordinates of corner boundary pillars is tabulated below:

Table 3: GPS Readings of Boundary Pillars

Boundary Piller no North-Longitude East-Latitude

P (Ref Point) 13° 18' 06.8ʺ 790 15ʹ 38.0 ʺ

A 13° 18' 06.8/ʺ 790 15ʹ 37.4 ʺ

B 13° 18' 04.1ʺ 790 15ʹ 37.7 ʺ

C 13° 18' 03.9ʺ 790 15ʹ 34.6 ʺ

D 13° 18' 06.6ʺ 790 15ʹ 34.4 ʺ

Map Datum: WGS - 84.

iv. Site Boundaries

The boundaries of the QL area are tabulated below:

Table 4: Site Boundaries

Direction Particulars

North Sy.no.248

East Sy.no.249/5

South Sy.no.250

West Sy.no.249/5

Page 6: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

6

3.0. DETAILS OF APPROVED MINING PLAN / SCHEME OF MINING (if any) : Nil

PART – A

1. GEOLOGY AND EXPLORATION

a. Physiography

i. Topography:

The applied quarry lease area belongs to hilly terrain and it covers part of the hill portion on

Eastern side. Due to hilly terrain, the applied area is elevated mound on Western part and sloping

towards SouthEast. The applied area is rising maximum to a height of 305 m MSL and minimum to

a height of 302 m MSL and a maximum relief of 3.0 m from normal ground level. The hilltop is

covered by soil zone of 0.5 m thickness underlain by granite sheet rock formation and the slopes

of the area is covered by the boulders.

ii. Drainage Pattern:

The drainage pattern of the Quarry Lease environs is sub dendritic in nature. No perennial

streams observed within the Quarry Lease area. One tank existing in the Eastern part of the

quarry lease area of about 1.5 km in which catchment of rain water will flow through drain on

rainy season. No streams,ponds noticed in the lease area.

iii. Vegetation

There is no vegetation within Quarry Lease area..

iv. Climate:

The climate is tropical with temperatures raging form 340 C to 420 C in summer and 150 C to 250 C

in the winter. The normal annual rainfall is about 800 mm.

b. Regional Geology

The oldest rocks of the area belonging to the late Archaean or Early Proterozoic era, which is

succeeded by rocks of younger granite rock of Archean group. and both are traversed by Dolerite

dykes. The Geological formations in the Chittoor (Dist) can broadly be divided in distinct and well

marked groups and older groups of metamorphic rocks belonging to Archean and Younger group

of Sedimentary rocks belonging to the Proterozoic age, later cover part of younger granite rock

formation of Archean group. The remaining part of district is occupied by Archean rocks which

consists of Schist, Gneisses, Quartz veins and Basic Dykes.The Archean rocks have suffered

considerable degree of tectonic disturbances as a result of which the rocks have been

Page 7: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

7

metamorphosed and recrystallized. During the late Archean Era, igneous intrusions of alkaline

rocks formed in Chittoor belt.

Table 4: Stratigraphy of the Quarry Lease Area:

Geological Age Lithology

Recent Alluvium

Pliestocene Laterite

-----------------------------Unconformity---------------------------------

Younger intrusive,epidote veins,quartz veins

and reefs

Pegmatites veins of alkali feldspar

Granite and syenite

Dolerite/Gabbro/Basalt dykes

Leuco Granite

Nebulitic to homophonous biotite granite

Peninsular gneissic complex

(Migmatite group) Nebulitic to homophonous

Hornblende Granite and Leuco Hornblend

Granite

Archeans Biotite Granite Gneiss, Hornblende Granite

Gneiss,Porphyritic Hornblende Granite

c. Local Geology:

The Quarry Lease area consists of Crystalline Basements Complexes of younger granite rock

formation of Archaean age. Granite and Granodiorite of grey and pink colour is the main litho unit

occurring in the area. Geomorphology of the area is pediment inselbergs complex with small

mound of Granitic gneisses formation.Granite in the QL area is occurring as sheet rock and

pebbles to boulders spread randomly over the sheet rock with irregular joints, Biotite Granulitic

patches. The OB portion is covered by highly weathered adjacent rock material with boulders of

about thickness 0.5 m .Granite composed of Quartz, Feldspar and Biotite mica.. Granite observed

Page 8: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

8

in the area is leucocratic, light grayish white, medium grained with an estimated hardness of about

6 on Moh’s scale and a specific gravity of 2.5.

d. Prospecting Agency:: N.A.

e. Details of Prospecting/Exploration Already Carried Out

The QL area is exposed by Granite sheet formation extended both lateral and vertical directions

depicted. The adjacent Quarrying the vicinity confirms the presence of Granite in the proposed QL

area. In addition, sufficient information gathered and careful observation of samples collected

during the site visit has aided in determination of the presence of reserves in the QL area. Hence,

specific exploration is not required. A few corners where installation of stone pillars was not

possible due to the presence of solid sheet rock were indicated with appropriate paint marks.The

subject area is demarcated on the ground with reference to Revenue stones.Later topographical

survey of the area was carried out.

The ABM (BP-D) is connected to Grid of N 130 18’ 06.8” & E 790 15 37.4” located in Northern part

of the QL area. Based on topographical survey and geological features, collected from the surface

data, the surface geological plan is prepared on 1:1000 scales with 1.0 m contour interval and

enclosed as Plate – 3.

f. The Key Plan

The key cum Location plan (Topo map) of the area is prepared on a scale of 1:50,000 with 5 km

radius from the center of the QL area showing predominant wind direction, drainage pattern, water

bodies, topo features along with extremities of the lease cum Location area(Plate – 1).

g. The Surface cum Geological Plan

The surface cum geological plan of the Quarry Lease area is prepared on 1:1000 scale with 1.0 m

contour interval and is enclosed as Plate – 3.

h. Geological Sections

Three Geological cross sections A-A’, B-B’ & C-C’ were drawn at an average interval of 1.0 m on

1:1000 scale and enclosed as Plate – 3A.

i. Future Programme Of Exploration

i. Future Programme: Since the deposit is exposed over the surface, no future programme of

exploration is required.

Page 9: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

9

ii. Previous Production Status: The quarrying operations is going on, hence there was a

previous production of total quantity 6,864 cbm from 2003 onwards. The year wise production

details is shown in the below table.

YEAR PRODUCTION-CBM

2003-04 Nil

2004-05 Nil

2005-06 Nil

2006-07 Nil

2007-08 Nil

2008-09 600

2009-10 600

2010-11 600

2011-12 576

2012-13 546

2013-14 552

2014-15 900

2015-16 900

2016-17 660

2017-upto oct-17 930

TOTAL 6,864

TABLE - 5

2. Reserves and Resources as per UNFC

i. Type of Deposit As Per UNFC Guidelines

Road metal and Building stone is not failing in any category of UNFC classification. It is a localized

mineral available, spatially utilized for construction purpose such as laying of roads, construction

of buildings etc, depending upon the characteristics of the rock. Granite, Dolerite and Dolomite

Limestone etc., which are mostly fractured and disturbed which are not useful for any other

specific purpose of their characteristics in specified area are useful for construction as road metal

and building stone locally.

ii. Parameter – Grade, Threshold Value, Sectional Area And Bulk Density: As the ROM is

intended for use in the Road Metal and Building Stone, no specific parameters considered. The

bulk density of Granite was considered at 2.5 to estimate the reserves.

iii. Status of Exploration: G1

b. GEOLOGICAL AXIS

1. Geological Survey:

i.Mapping: Detailed geological survey was carried out in the QL area on 1:1,000 scale with 1.0

meter contour intervals.

Page 10: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

10

ii.Preparation Of Detailed Topographical Cum Geological Map: The topographical cum

Geological map including all surface Geological features, extent of deposit, structures, have been

prepared on 1:1,000 scale with 1.0 contour interval duly marked with surface geological features,

ABM etc., and presented on Plate-3.

iii.Topo Grid / Triangulation Stations: The topo grid with Geological cross-sections has been

prepared on 1:1,000 scale showing litho-units. Relevant plans are enclosed as Plate- 3A.

2. Geochemical Survey: Geo-Chemical survey is not warranted as the deposit is used for Road

Metal & Building stone purpose only.

3. Geophysical Survey: Not carried out.

4. Technological Survey:

a. Detailed topographical and geological survey was carried out on 1:1,000 scale showing all the

surface features, contours at 1.0 m interval, the lease boundary, surface Geology & Structural

features.

b. The maximum thickness of Road metal & Building stone above the existing ground level is

about nearly 3.0 m, with RL in between 305 m – 302 m that is considered to be proved reserves.

c. Reserves are estimated by cross sectional method.

5. FEASIBILITY AXIS

a. Geology: The detailed Geology of the area has been presented in Part-A, which may kindly be

referred to.

i. Geology: Road Metal and Building stone will be exploited through opencast other than fully

mechanized mining methods with drilling & Blasting. The quarrying operation will be carried out in

a systematic way by forming benches of 3.0 m height and the height with proportionate width will

be maintained. Jack Hammer drilling and controlled blasting will be carried out in the QL area.

ii. Environment: The deposit will be mined adopting conventional opencast semi-mechanized

mining methods without any adverse environmental impact. The Lessee will obtain statutory

clearances as soon as this Mining Plan is approved. Mining in the leasehold does not disturb any

human settlements as they are far away from the QL area. On the other hand, the quarrying

operations will create livelihood to the villagers nearby. The Lessee will develop green belt around

the QL area as part of his commitment to environment protection.At the time of rainy season water

flows through stream channel from the up streams to down wards.This stream channel will goes

Page 11: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

11

from west to east in the quarry lease area, however precaution measures will take as per the

norms of APMMC Rules.

iii. Processing: After blasting, the ROM will be utilised own crusher. No processing is required

excepting sizing manually.

Quarrying operations will be carried out by deploying the following machinery:

Table 6: Machinery & Equipment:

S.No Type of machine No Diameter of hole

Size/ capacity

Make Motive power

1 Excavator /JCB 1 - 0.9 cu.m BC 210 Diesel

2 Tippers 2 - 12 tons Leyland Diesel

3 Drilling machines 1 58 mm - - Diesel

4 Tractormounted compressors

1 2” 3 cu.m - Diesel

5 Water Tankers 1 NA 5000 Ltr. - Diesel

6 Loaders 1 NA 3 cu.m - -

7 Pick-up/Jeep 1 - 4X4 M&M Diesel

8 Generator 1 - - - Diesel

iv. Infrastructure: The necessary infrastructure of site services such as office, rest shelter,

magazine, explosive van, water tankers, power connection etc., will be provided at the North

Eastern corner of the quarry lease, once the mining plan is approved. The QL area is connected

with well-built asphalt roads to the Mandal and District headquarters.

v. Costing: The cost of production of Road Metal & Building Stone works out to be approximately

Rs. 250/- per ton.

vi. Marketing: ROM generated from this quarry is proposed for captive purpose for the crusher

and hot mix plant intended to put for use in the highway road project from Banglore to Chennai for

this year and also intends to continue selling the Road Metal and Building stone for various civil

projects in and around villages and Chittoor and G.D.Nellore towns.

vii. Economic Viability: As the proposed quarry lease is in the near vicinity and quarrying of road

metal is definitely economic and viable.

viii. Other Factors: Relevant clearances shall be obtained for continuing the mining operations in

the QL area.

Page 12: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

12

6. ECONOMIC AXIS

i. Detailed Exploration: Detailed topographic survey and geological mapping of the applied QL

area was subject to detailed exploration by field traverses and well inventory data. The depth of

sheet rock is assessed by the litho log observed in the boreholes of agricultural lands.

ii. Mining Reports / Mining Plan: This is the first Mining Plan has been submitted.

iii. Specific End-Use Grades Of Reserves (Above Economic Cut-Off Grade): ROM is intended

for crushing to use in the aggregates for roads and building stone materials.

iv. Specific Knowledge Of Forest / Non-Forest And Other Land Use Data: The entire QL area

is Government waste land.

v. Feasibility Report Along With Financial Analysis Per Economic Viability Of The Deposit:

The cost of production of road metal and building stone is arrived at Rs. 250/- per ton inclusive of

taxes and royalty. The entire ROM is for captive purpose as such it is surely economic and

profitable.

6. Reserves

i. Mining Method, Recovery Factor, Mining Losses, Processing Loss etc: Road Metal and

Building Stone will be quarried by open cast other than fully mechanized method with drilling and

controlled blasting. The recovery factor is considered as 95% with 5% intercalated waste. There

will not be any quarrying losses except handling loss, which will be recovered during next loading.

ii. Cut-off Grade, Ultimate Pit Depth Proposed: There is no cut-off grade as the ROM will be put

to use for road metal and building stone as aggregates. The Ultimate Pit average depth Limit

(UPL) will be 12 m in the middle portion of the QL area during the end of first fifth year of this

Mining Plan of residual period.

iii. Mineral/ Ore Blocked Due to Benches, Barriers, Pillars, Road, Railway, River, Nala,

Reservoir, Electric Line and Other Statutory Barriers etc,: The mineral will be blocked in 7.50

m safety barrier zone, roads and benches which is computed separately and tabulated below in

the succeeding sections.

iv. Total Mineral Reserves: The reserves are estimated basing on field traverses and the

information gathered during the field visit of the area and cross sections drawn. The area of the

influence and the cross sections on either side of the cross sections A-A’, B-B’ & C-C’’ were taken

at 25.0 m.The occurrence of the Granite is probably more than 3.0 m above existing above ground

Page 13: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

13

level. Based on the field traverses, the estimated reserves considered as Proved Reserves.Three

cross-sections A-A’, B-B’ & C-C’’ are considered for computation of reserves. The depleted

reserves have been accounted by cross sections and reserves are computed.

Table 7: Reserves Estimation:

Section Catagory

Sectional Area (m2)

Sectional Influence

(m) volume

(m3) T.F

Geological Reserves

100%

Mineable Reserves

@95% (MT)

Waste @5% (MT)

A-A’ Proved 2,128 25 53,200 2.5 1,33,000 1,26,350 6,650

B-B’ Proved 2,089 25 52,225 2.5 1,30,563 1,24,034 6,528

C-C’ Proved 2,179 25 54,475 2.5 1,36,188 1,29,378 6,809

TOTAL 6,396 1,59,900 3,99,750 3,79,762 19,988

Table 7 a: Reserves Blocked in 7.50m Buffer Zone

Section Catagory

Sectional Area (m2)

Sectional Influence

(m) volume

(m3) T.F

Geological Reserves

100%

Mineable Reserves

@95% (MT)

Waste @5% (MT)

A-A’ Proved 415 25 10,375 2.5 25,938 24,641 1,297

B-B’ Proved 375 25 9,375 2.5 23,438 22,266 1,172

C-C’ Proved 450 25 11,250 2.5 28,125 26,719 1,406

TOTAL 1,240 31,000 77,500 73,625 3,875

Table 7.b Table showing Reserves blocked in safety Bench slopes:

Section Catagory

Sectional Area (m2)

Sectional Influence

(m) volume

(m3) T.F

Geological Reserves

100%

Mineable Reserves

@95% (MT)

Waste @5% (MT)

A-A’ Proved 552 25 13,800 2.5 34,500 32,775 1,725

B-B’ Proved 552 25 13,800 2.5 34,500 32,775 1,725

C-C’ Proved 814 25 20,350 2.5 50,875 48,331 2,544

TOTAL 1,918 47,950 1,19,875 1,13,881 5,994

(A)Total Mineable Reserves = 3,76,762 tons

(B)Reserves blocked in 7.50 m buffer zone = 73,625 tons

(C)Reserves blocked in Safety Bench Slope = 1,13,881 tons

Page 14: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

14

Net Mineable Reserves A – (B+C)

= 3,76,763 – (73,625 + 1,13,881) = 3,76,763-1,87,506 = 1,89,257 Tons

v. Mineable Reserves and life of the Quarry:

Initially the total quantity of mineable reserves is considered as (economic) marketable reserves.

* In this way a total mineable reserves available in this Quarry Lease area = 1,89,257 MT.

*The average proposed production is to obtain per annum = 28,044 MT

At this rate of production the expected life of the mine is calculated as given below.

* Life of the Quarry: Mineable Reserves / Annual production

= 1,89,257 / 28,044 = 6.74 Years = 7 Years

Vi . Mineral Reserves and Resources

Table 8: Resources

Level of Exploration Resource in tons Grade

G1 – Detailed exploration 1,89,257 -

G2 – General exploration - -

G3 – Prospecting - -

G4 – Reconnaissance -

2. MINING:

i. OPEN CAST MINING

a. Breifly describe the existing as well as proposed method for Excavation with all design

parameters indicating plate nos of plans / sections.The applied area belongs to hilly terrain

and raising to a height of more than 3.0 m from the normal ground level. Most of the area is

covered by the granite sheet formation at higher levels with less over burden. The mining activity

is proposed to be carried out by open cast bench forming method with the help of drilling, blasting

and using excavator. The granite is hard in nature the blasting is required for excavation. Hence

the lessee is advised to get the explosive licence, since it is a time taking process, the blasting will

be allocated to put sourcing blasting licensed agencies which has an explosive license in starting

of the lease period. The blasted ROM will be loaded into trippers/ dumpers of 20 tons capacity by

using excavator. The loaded ROM will be transported to the crushing plant . The ROM will crushed

in the crusher plant to different sizes of 60mm, 40mm, 20mm, 12mm, 6mm and dust and supplied

to construction, road and railway works. The quarry operations will be carried out by benches of

Page 15: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

15

3.0 m height from higher levels to lower levels. It is proposed to raise about 29,520 tons ROM

during the five years of plan of residual period.

b. Year-Wise Tentative Excavation in Cubic Meters Indicating Development, ROM, Pit Wise:

It is proposed to raise the insitu ROM of 28,044 m3 on an average per year from this quarry. The

granite sheet rock is exposed as a hillock to a height of 3.0m from the ground level, so no

separate development is required in the beginning of the mining activity to get the target

production from this quarry. The quarry working will be carried out by open cast method with the

help of drilling and blasting from the top of the hill. Since the applicant does not have blasting

license, the blasting part will be allocated to private licensed agency in the initial stage inwhich the

lessee has get an blasting license. The blasted ROM will be loaded into trippers/ dumpers of 20

tons capacity by excavator. The loaded ROM will be transported to the crushing unit which is

existing near by the lease area in the proposed own / lease land on the south western part of the

lease area. The ROM will be crushed at the crushing unit to various sizes and sorted to 60mm,

40mm, 20mm, 12mm, 6mm and sand and supplied to different construction works, road works and

railway ballast.. The Tentative excavation proposed to be carried out for the first five years plan of

residual period is estimated at 11,808 m3 from which intended ROM 28,044 of tons of Road Metal

and Building Stone will be mined out by open cast mechanised method by forming benches of

3.0m each and 7.5m buffer zone. The year-wise details are presented below:

i. In-situ Tentative Excavation

Table 9: Year wise Tentative Excavation

Year Sec Area M2

Influence

Volume (M3 )

T.F Geological Reserves

(100%)

Minerable Reserves

(95%)

ROM/ Waste (5%)

2017-18 RL295 m -292 3,936 3 11,808 2.5 29,520 28,044 1,476

TOTAL 3,936 11,808 29,520 28,044 1,476

ii. Dump Re Handling (for The Purpose of Recovery of Mineral):

5% intercalated waste is generated to the tune of 590 m3 will be generated which will be dump

over an area of 149 m2 in Northern part of the Quarry Lease area as depicted on Plate – 4. The

generated waste will be utilized to strengthen the internal roads of the quarry lease area.

c. Composite Development Plans Showing Pit Layouts, Dumps, Stacks of Mineral Rejects,

if Any, etc. and Year wise Sections:

Page 16: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

16

Year wise development plan with the details of depth of excavation, bench levels, and stockyard

area are depicted on Plates – 4, 5, 6 & 7..

d. Layout of Mine Workings, Pits, Roads etc:

The quarrying operation is going on, previous working one pit is observed in the QL area..At the

time of quarrying operation the overburden will be used for existing haulage roads and

strengthened for better navigation. Dump will be positioned at Northern portion of the QL area.

The Lessee intends to extract Road Metal and Building Stone production to the tune of 11,217 m3

or 28,044 tons of road metal and building stone @95% with an anticipated waste of 5% amounting

to 590 m3 or 1,476 tons of saleable mineral during this five years Plan period. During this five

years Plan of residual period, it is proposed to exploit the road metal from the total area of 3,936

m2 to an average depth of 3.0 m over the lease area from RL 295 in the North Western portion as

depicted on Plate – 4.

I.2017-18: Quarrying is proposed on the North Western portion extending in the East and South

direction between RL 295 to RL 292 m over an area of 3,936 m2 of influence 3 m. The whole area

will be excavated to a depth of 3.0 m from the existing level for this year. About 11,808 m3 or

29,520 tons of ROM will be excavated. Out of which a saleable ROM of 11,217 m3 or 28,044 tons

@95%and an intercalated waste of 590 m3 or 1,476 tons @5% will be produced. The waste

generated will be dumped on the proposed dump over the Northern portion of the QL Area (Plate-

4).

Table 10: Year wise Development

Year Area of

Excavation

(m2)

Bench

Height

(m)

Volume

(m3)

ROM @2.50

T/ m3

(Tons)

Recovery

@95%

(Tons)

Intercalated

Waste @5%

(Tons)

2017-18 3,936 3 11,808 29,520 28,044 1,476

TOTAL 3,936 11,808 29,520 28,044 1,476

Page 17: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

17

e. Production Schedule: The production of Road Metal and Building Stone will continue for a

minimum 300 working days per annum. An anticipated average production of 28,044 tons/annum

or 93.48 tons/day is planned from this Quarry during this five years plan of residual period.

Adequate men and machinery is planned to meet this production schedule.

f. Drilling & Blasting:i. Drilling: 54 mm diameter hammer drilling will be employed for blasting

holes in staggered pattern of 2X3m with a depth of 3.35m. Holes will be drilledvertically to a depth

of 3.35m for a bench height of 3.0 m with a spacing and burden of 3.0 m and 2.5m respectively.

Each blast hole will break an amount of

Drilling parameters are as given below

Drill hole diameter D - 0.054m

Drill hole depth L - 3.35m

Burden B - 1.5 m

Spacing S - 3.0m

Proposed Bench Height H - 3.0m

Volume of rock broken per hole V(SXBXL) - 22.5m3

Specific gravity of rock - 2.5

Mass of rock broken per hole - 56.25 tons

Total proposed rock excavation for five years plan

of residual period (i.e 2017-18) - 11,808 m3

(Average rock excavation per annum - 11,808 m3

No of holes proposed per annum - 524.8

No of working days scheduled per annum - 300

No of holes proposed per day - 1.8 (say 2)

ii. Blasting: Blasting will be carried out by using controlled blasting techniques for the purpose to

reduce the amount of over break and to control the ground vibrations. Blasting will be done with

the help of electronic merger by using electronic detonators, ordinary detonators, fuse wire and

Ammonium Nitrate. The applicant will be hiring a licensed blasting contractor for the services of

blasting. Besides this, the applicant has to obtain all necessary permits to store, handle the

explosives on site. The charge per hole will be about 1kg of explosive.

Amount of explosive required per hole - 1 Kg

No of holes planned per day - 1.8 (say 2)

Page 18: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

18

Amount of explosive required per day - 2.0 Kg

Amount of explosive required per annum - 600 Kg

Amount of explosive required for five years plan

of residualperiod(2017-18 ) - 600 Kg

After blasting working places will not be entered by any of the worker, unless sufficient time has

elapsed for dust, smoke and fumes to be cleared by a current of air and the broken ore or rock will

not be removed unless it has been thoroughly wetted with water.

g. Conceptual Mining Plan:

i. Details of the conceptual status of pits: The lease period is for 15 years ending in June 2018.

Thus, the present period of five years block ends in 2017-18. By the end of the first five years plan

period, i.e 2013-14 to 2017-18 total of 28,044 tons of ROM is planned for production. The planned

depth of the quarry would be 3.0m.

ii, The worked out pit as a whole will occupy an area of 3,936 m2 to a depth of 3.0 m from the

existing FRL 295 m of the worked out pit. The area occupied by internal roads would be 106 m2,

while plantation would be occupying an area of 540 m2 in all the four directions in buffer zones of

QL area. The conceptual plan and conceptual section on a scale of 1:1000 is presented on Plate –

6.

h. UNDERGR GROUND MINING N.A.

3. MINE DRAINAGE:

a. Minimum and Maximum Depth of Water Table: The QL area is a small mound with a

maximum height of 3.0 m above existing ground level. There are no water bodies existing in the

vicinity. GW level is observed to be ranging between 30-35m below GL

b. Maximum and Minimum Depth of Workings: Initial GL of the mine area is ranging between

305 m to 302 m MSL. After first five years of plan of production, the maximum and minimum depth

of workings reached level of 295 m and 292 m MSL

c. Quantity and Quality of Water Likely to be Encountered: No water will not be encountered in

the QL area during the excavations and subsequent operations as the quarrying is on an elevated

mound above the GL of 3.0 m and the GWL is at 30-35m below the existing GL. Hence no need

for pumping does not arise. Quality of GW tested from the surroundings is found to be potable.

Page 19: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

19

d. Regional and Local Drainage Pattern: The entire QL area has a down slope only. Sheet wash

run-off is anticipated during the monsoon area. Annual rainfall in the QL area is below the district

average rainfall i.e., 700mm.at the time of rainy season one of the stream course flow from west to

east in the quarry lease area. There is one tanks existing on eastern part of about 1.5 km away

from the quarry lease area, precautions measures takes as per the norms of APMMC Rules .Solid

wash expected during monsoon season in the QL area is negligible.

4.STACKING OF MINERAL REJECT / SUB-GRADE MATERIAL AND DISPOSAL OF WASTE

Tops soil in the QL area is negligible. The waste that would be generated is only form interstitial

voids that is estimated at 5%. This will be utilized for the formation of internal roads periodically.

Rest of the waste will be utilized to form a 2.0m high barrier all along he 7.50m buffer zone of the

QL area.

Table 11: Stacking of Mineral Reject

Year Top Soil (cu.m) Mineral Rejects (cu.m)

Reuse /

spreading Storage Backfilling Storage Blending

Laying of

Roads& Rising

of Barrier (tons)

2017-18 Nil Nil Nil Nil Nil 1,476

5. USE OF MINERAL AND MINERAL REJECT

The ROM will be fed to the crusher outside the QL area where it will be crushed to desired sizes.

Different grades of output from the crusher will be primarily used in the construction of Banglore-

Chennai Highway road for the one year and also will be sold in the market for various civil works in

and around Chittoor and C.D.Nellore towns of Chittoor district.

6. PROCESSING OF ROM AND MINERAL REJECT

ROM will be fed to the crusher to obtain different sized aggregates required for road construction

and input to hot mix plant.

7. OTHER

a. Site Services:

Site services such as office room, first aid, rest shelter, toilets for gents and ladies will be built at

the eastern part of the QL area.

b. Employment Potential:

1. Highly skilled - Second Class Mines Manager - 1

Mine Supervisor - 1

2. Skilled &Semi-skilled - Bore Compressor Operators - 2

Page 20: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

20

Bore Compressor Assistants - 2

JCB Backhoe Operator - 2

JCB Backhoe Assistants - 2

Pick-up Drivers - 2

Security Guard - 2

Total personnel in Mining Operations - 14

Personnel involved in Crusher Operations - 14

PART – B

8. PROGRESSIVE QUARRY CLOSURE PLAN (PQCP)

8.1.. Environment Base line information:

a. Existing Land Use Pattern: The QL area is a wasteland. An area of about 3,936 m2 will be

excavated to a depth of 3.0m on an average to win the mineral. An area of 540 m2 is proposed for

afforestation. The QL area is a barren land and surrounding lands are Cultivated

lands..Environmental Plan on a scale of 1:5000 is enclosed as Plate-5.

b. Human Settlements: Within a radius of 5km of QL area exists 14 villages.The main profession

of the people is agriculture, rearing sheep and cows and other small business and labour on daily

wages. More details of the villages in the surroundings are as tabulated below in Table No.12.

Table 12: Villages in the Vicinity of QL Area

S. No. Village Direction Distance

(km) Population

1 Kammapalle N 2.0 900

2 Tippanayudupalle N 3.0 600

3 Garampalle N 4.0 200

4 Tellagundupalli N 4.5 500

5 Kannikapuram E 2.5 800

6 Oddipalle E 2.0 400

7 Pilligundlapalle NE 3.0 700

8 Eguvamangunta NE 4.2 900

9 Kottapallimitta S 2.0 500

10 Pathurnatam S 4.0 600

Page 21: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

21

11 Kothapalle W 2.0 300

12 Basavareddipalle W 3.0 300

13 Lakshmireddypalle SW 2.8 200

14 Bodidevampalle SW 3.0 400

c. Public Buildings, Places of Worship and Monuments: No public buildings, places of worship

or interest and monuments are present in the vicinity of QL area.

d. Sanctuary if any in the Vicinity ofthe Lease Hold: No sanctuary, zoo or park are present in

the vicinity of the QL area.

8.2. Impact Assessment:

a. Land Area Degraded: An area of about 3,936 m2 will be degraded for the working pit. In

addition, an area of 106 m2 will be used for internal roads of the quarry. Plantation will occupy 540

Sq mts.

b. Air Quality: Various activities involved in mining of Road Metal and Building Stone generates

dust. To some extent, dust generated will be controlled by sprinkling of water on roads. Masks,

earplugs and safety goggles will be supplied to the workers on site to protect themselves from

dust.

c. Water Quality: There are no water bodies like ponds, lakes in the vicinity of QL area. One

stream course in the quarry lease area, precautions takes as per the norms of APMMC

Rules..Quarrying of Road Metal and Building Stone generates minimal dust, which is not harmful.

Hence, the quality of the water in the surrounding water bodies will not be affected by the mining

activity.

d. Noise Level: The QL area does not have any villages in the immediate neighborhood. The

nearest village are Ramakrishnapuram and Kothapalle villages which are 0.5 km and 1.0 km away

from the QL area. Noise is anticipated in the various activities involved like Drilling, blasting and

vehicle movement. As the mining activities are of the small scale in nature, the noise generated

would be well within the limits and would not affect the residents in the surrounding villages.

Lessee will take all necessary measures to minimize the sound generated particularly during

blasting activity like using of mufflers. Site workers will be supplied with ear plugs to protect

themselves from noise pollution.

e. Vibration Levels due to Blasting: As the drilling method proposed, is by using tractor mounted

compressors and controlled blasting vibration level will be within the limits and will not affect the

people working on site.

Page 22: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

22

f. Water Regime: Mining activity proposed is over the elevated mound and the maximum level of

the pit will be 12 m that is only 3 m higher than the above ground level and 9 m lowest of the

existing below ground in the QL area i.e., level 292 m MSL. As the GW is at expected to be at a

depth more than 35m in the QL area GW will no way will be affected.

g. Acid Mine Drainage: No chemicals are involved in the extraction or processing of the mineral,

hence there is no danger of acid mine drainage.

h. Surface Subsidence: The ground surface in around the QL area is covered by Granites of

Archaean Basements complex the ground is stable. Internal roads are well compacted to avoid

any skidding of vehicles. The benches and ramp ways will be well built and maintained to avoid

any kind of subsidence or skidding.

i. Socio Economics: Quarrying of Road Metal and Building Stone will generate employment to

the people of surrounding villages both skilled and unskilled. Government will get income in the

form of royalty, rent etc. Raw material for the road and civil works will be generated by the

quarrying activity that will be one of the boosting factors for the local economy.

j. Historical Monuments: No historical, archeological or Geological monuments are present in

and around the QL area.

k. Bio-Diversity: The slopes and crevices of the mound have some bushes and shrubs. No wild

animals are reported within these bushes.

8.3. Progressive Reclamation Plan:

a. Mined-Out Land: No Mined out land will be formed during the first five year plan of residual

period. The mineral reserves exist further deeper than the UPL 12m of this plan period and

quarrying will continue for the rest of the lease grant period.

b. Topsoil Management: Top soil present in the QL area is negligible and hence topsoil

management does not arise.

c. Tailings Dam Management: Tailings Dam is not required.

d. Acid Mine Drainage and Mitigation Measures: No chemicals are involved in the extraction or

processing of the mineral, hence there is no danger of acid mine drainage.

e. Surface Subsidence Mitigation Measures: The ground surface in around the QL area is

covered by Granites of Archaean Basements complex the ground is stable. Internal roads are well

Page 23: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

23

compacted to avoid any skidding of vehicles. The benches and ramp ways will be well built and

maintained to avoid any kind of subsidence or skidding.

8.4. Disaster Management and Risk Assessment:

Disasters are possible in an industry like mining. The possibilities of occurrence of some of

incidents are tabulated below in Table12.

Table 13: Probability Table for Disasters of Operations planned on 100 Point Scale.

Sl. No.

Type of Disaster Exposure Index

Severity Index

Frequency Index

Risk Numeric

1 Mining injuries 50 100 0.1 500

2 Land slides 10 100 0.01 10

3 Inundation 100 100 0.0001 1

4 Fire accidents 10 40 0.01 4

5 Floods & epidemics 100 100 0.00001 0.1

6 Animal and reptile attack

1 10 0.0001 0.001

To meet with any kind of emergency on or off site, risks are assessed in advance and Risk

assessment plan is prepared. Assessing the possible hazards and planning the procedures to be

followed in case of emergency will reduce the intensity impact. Proper bench design in mine and

observing all kind of safety measures, usage of proper PPE on site, attentiveness of the work

force on site, following pre-defined traffic rules by all the people on site some of the measures to

be followed to reduce accidents on site. Proper care in storage and handling of explosives,

hazardous materials, fuels is also necessary. Proper communication is key factor in minimizing the

accidents on site.

Safety of all working personnel will be the utmost priority of the lessee. Lessee will provide all the

site personnel with necessary PPE like, hard hats, safety goggles, earplugs, dust masks etc.

To meet any kind of emergency, readiness to shift the injured to the nearest hospital is necessary.

All mining personnel should be aware of the nearest health centers and hospitals. All managing

personnel will take the responsibility of taking the injured immediately to the hospital in case of any

accident. A few of the site personnel should be provided first aid training besides the presence of a

well-maintained first aid kit.

Chittoor is at a distance of 28 km from the lease area, which has all kind of healthcare facilities

starting from primary health care to corporate hospitals. In case of emergency state government’s

Page 24: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

24

108 service is available. Apart from this one additional pick up with driver will always be available

to meet with emergency situation.

In event of any emergency the Contact person is:

Sri Prakash, Manager

Kothapalle (V)&(PO)

S.R.Puram (M),

Chittoor District. A.P State.

Tel: +919676569700

8.5. Care and maintenance during temporary discontinuance:

An emergency plan to deal with the situation of temporary discontinuance or incomplete

programme due to court order / due to statutory requirements or any other unforeseen

circumstance will be drawn by the technical and managerial person to suit the specific situation of

this mine. This would be reviewed and modified to suit the changing conditions and needs. This

would take care of preventing of access to dangerous places, pits and prevent accidental fall in to

the water logged pit of animals and men. Security is also to be looked in to the safety measures

placed at various places like firefighting equipment, main switches etc. Security to be deployed at

Explosive storage.

The mining is yet to commence. As mining continues till then the question of discontinuance does

not arise. However, any untoward incidence happens the safety of the mining area will not be

disturbed. Security / Watchmen will be posted at the mine site for watch and ward.

8.6. Financial Assurance:

Financial assurance can be submitted in any encashable from preferably a bank guarantee from a

Scheduled Bank at the rates equivalent to rates prescribed as per the amendment Rule 27 (1) of

Mineral Conservation Development Rules, 2017 for next 5 years period expiring at the end of

validity of the document.

The proposed quarrying operations are by Open Cast other than fully mechanized method of

quarrying and by jack hammer drilling and blasting and hence the cost of reclamation &

rehabilitation is calculated as per the provisions of rule 27(1) MCDR, 2017 @ 2,00,000/- per

hectare of total 0.773 hectare to be Rs 1,54,600/-.

a. Financial Assurance:

The details of area put to use and calculations thereof for financial assurance are furnished below:

Page 25: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

25

Table14: Details of Area Considered for Computation of Financial Assurance

S.No. Head

Area put on use at the start of plan (in Ha.)

Additional requirement during the plan period (in Ha.)

Total (in Ha.)

Area considered as fully reclaimed and rehabilitated (in Ha.)

Net area considered for calculation (in Ha.)

1 2 3 4 5 6 7

1 Area under Mining 0.00 0.3936 0.3936 0.3936 0.3936

2 Storage for Top Soil

3 Overburden / Dump 0.00 0.0149 0.0149 0.0149 0.0149

4 Mineral Storage

5

Infrastructure (Workshop, Administrative Building etc.,)

0.00 0.0153 0.0153 0.0153 0.0153

6 Roads (Within the pits)

0.00 0.0106 0.0106 0.0106 0.0106

7 Railways

8 Green Belt 0.00 0.0540 0.0540 - 0.0540

9 Tailing Pond - - - - -

10 Beneficiation Plant - - - - -

11 Mineral Separation Plant

- - - - -

12 Township Area - - - - -

13 Others

Retaining Wall

- - - - -

Fencing around the pit (included quarry area)

- - - - -

GRAND TOTAL 0.4884 0.4884 0.1344 0.4884

Page 26: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

26

The proposed mining operations for the cost of reclamation and rehabilitation is calculated as per

the provisions as per the amended rule 27(1) of MCDR,2017 @INR.2,00,000/- per Hectare or part

thereof. This amount works out to be INR 97,680/- for 0.4884 hectare of area but the minimum

financial assurance is INR 5,00,000/-. Hence the financial assurance in the form of Bank

Guarantee for INR 5,00,000/- will be submitted to the Assistant Director , Department of Mines and

Geology, Chittoor.

Place:TIRUPATHI

Date: 01 -12-2017

SIGNATURE OF THE APPLICANT SIGNATURE OF THE RQP

Page 27: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

27

MINING PLAN FOR ROAD METAL & BUILDING STONE QUARRY

OVER AN EXTENT OF 0.773 HECTARE (1.910 ACRES)

IN SY.NO.249/5P OF KOTHAPALLE (V),

S.R.PURAM (M), CHITTOOR DISTRICT, AP

PLAN PERIOD – 2013-2014 TO 2017-2018

BALANCE PERIOD – 2017-2018

Submitted under Rule 7A of Andhra Pradesh Minor Mineral Concession

(APMMC) Rules 1966

Category- A Open cast other than Fully Mechanized Mine

Non- Forest, Revenue Barren lands

LESSEE

M/S. VIJAYALAKSHMI STONE CRUSHERS

Mg.Partner. T.MURALI

H.NO.2-418, MAIN STREET,

KONGAREDDYPALLE , CHITTOOR (Dt) ,

ANDHRA PRADESH STATE

PREPARED BY:

B.DAMODARAM,

RQP/DMG/HYD/106/13

D.NO.19-12-87, BAIRAGIPATTEDA,

TIRUPATHI-517 501, CHITTOOR DISTRICT, AP.

Page 28: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

28

MOBILE NO: - 9491043877, 7780646416

INDEX

Chapter Contents Page No

Introduction 1

1.0 General 3

2.0 Location & Accessibility 4

3.0 Details of Approved Mining plan/Scheme of 6

Mining if any

PART - A

1 Geology and Exploration 6

2 Reserves 12

3 Mining 14

4 Mine Drainage 18

5 Stacking of Mineral Reject / Sub-Grade

Material a

And Disposal of waste 19

6 Use of Mineral and Mineral Reject 19

7 Processing of Rom and Mineral Reject 19

8 others 19

PART - B

9 Progressive Mine Closure Plan (PMCP) 20

PLATES

Plate-1 Location cum Key Plan (Scale: 1:50000)

Plate-2 Applied QL Area Lease Sketch (Scale: 1Cm=1Chain of 20 mts)

Plate-3 Surface Cum Geological Plan (Scale 1: 1000)

Plate-3A Surface Geological Cross Section (Scale 1: 1000)

Plate-4 Yearwise Development Plan & Section (Scale 1: 1000)

Plate-5 Environment Plan (Scale 1: 5000)

Plate-6 Conceptual Plan (Scale 1: 1000)

Plate-7 Progressive Mine closure plan (Scale 1: 1000)

ANNEXURES

Page 29: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

29

Annexure-I Photographs of the area

Annexure-II Copy of DDM&G ,Kadapa , Proc.no – 2046/Q/2003, dated 12.05.2003

Annexure-II Copy of ADM&G ,Ctr , Proc.no – 562/Q/2003, dated 16.06.2003

Annexure-IV Copy of RQP Certificate

ANNEXURE – I

Photo of view of Boundary Pillers- Ref P, AStone of the Quarry Lease.

Page 30: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

30

ANNEXURE – I

Photo of view of Boundary piller-B and working pit of the Quarry Lease Area

Page 31: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

31

ANNEXURE – I

Photo of view of working pit and Granite sheet formation of the Quarry Lease Area

Page 32: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

32

MINING PLAN FOR ROAD METAL & BUILDING STONE

Over an extent of 0.773 Ha in Sy.No.249/5P of Kothapalle (V), S.R.Puram (M), Chittoor (Dt.), A.P.

Lessee : M/s Sri Vijayalakshimi Stone Crushers

1. Proved Zone Influence 25 mts,

2. Ultimate pit avg depth 12 mts, UPL MTS

3. Total Mineable Reserves = 376, 763 Tons

Reserves blocked under buffer zone = 73, 625 Tons

Reserves blocked under Safety Bench Slope = 113, 881 Tons

Total Recoverable Reserves = {Mineable Reserves – (Reserves blocked under buffer zone + Reserves

blocked under Safety Bench Slope)}

= 376, 763 – (73, 625 + 113, 881) = 192, 256 Tons

4. Total Recoverable reserves 192, 256 are available in this Quarry Lease area. The production is

proposed to obtain 28, 044Tons per annum

5. Life of the Quarry: Mineable Reserves / Annual production

= 192, 256/ 28, 044= 6.85 = 7 Years

6. First year to Fifth year working area dimensions - 28, 044Tons

7. Plantations:

Plantations number Area Total

2017-18 540

Total 540

8. Land Degradation: An extant of about 3936 Sq.mts area will be sliced down during first five

years to a depth of 3mts.

9. Minimum Contour Value 302m

Maximum Contour Value 305m

Page 33: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

33

CERTIFICATE

01. It is certified that the CCOM Circular No. 2/2010 will be implemented and complied with

when an authorized agency is approved by the State Government.

02. It is certified that the Progressive Mine Closure Plan of Road Metal and Building stone Quarry of M/s.

Vijayalakshmi Stone Crushers, Managing Partner. T.Murali, over an extent of 0.773 Hectare in

Sy.No.249/5P of Kothaplle (V), S.R.Puram (M), Chittoor District, Andhra Pradesh state complies with all

statutory rules, regulations, orders made by the Central or State Government, Statutory Organization,

Court, etc., which have been taken into consideration and wherever any specific permission is required

the Applicant will approach the concerned authorities.

The information furnished in the Progressive Mine Closure plan is true and correct to the best of my

knowledge and records.

03. The provisions of Mines Act, Rules and Regulations made there under have been observed in the Mining

Plan over an area of of 0.773 Hectares in Sy. No.249/5P of Kothapalle (V), S.R.Puram (M) Chittoor

District, Andhra Pradesh state belonging to M/s.Vijayalakshmi Stone Crushers, Managing Partner.

T.Murali, and wherever specific permissions are required, the Applicant will approach the D.G.M.S.

Further, standards prescribed by D.G.M.S. in respect of Miners Health will be strictly implemented.

Date: 01 -12-2017 SIGNATURE OF THE LESSEE

Place: TIRUPATHI

Page 34: MINING PLAN INCLUDING PROGRESSIVE MINE CLOSURE PLAN …environmentclearance.nic.in/writereaddata/Online/... · 1 mining plan including progressive mine closure plan for road metal

34

CERTIFICATE

The provisions of the MCR’1960 & APMMC’1966 have been observed in the preparation of Mining Plan for

Road Metal & Building Stone Mine over an extent of 0.773 Hectare in Sy. No.249/5P of Kothapalle (V),

S.R.Puram (M), Chittoor District, Andhra Pradesh state belonging to M/s. Vijayalakshmi Stone

Crusher,Managing Partner. T.Murali, and wherever specific permissions are required, the Applicant will

approach the concerned authorities of Indian Bureau of Mines or DGMS.

The information furnished in the Mining Plan is true and correct to the best of my knowledge.

Date: 01 -12-2017 SIGNATURE OF THE RQP

Place: THIRUPATI