Upload
shailendra-barshikar
View
222
Download
0
Embed Size (px)
Citation preview
7/31/2019 MS Project Guide Basics Only
1/45
Microsoft Project 101:
How to Build a Project Plan
7/31/2019 MS Project Guide Basics Only
2/45
Overview
After this course you will understand and be ableto:
Set up a project document using best practices
Enter task details Enter durations against tasks
Link tasks
Assign resources
Baseline the plan
Manage the project plan and track progress
7/31/2019 MS Project Guide Basics Only
3/45
Project Setup Best Practices
Iterative Saves and Versions
Project information dialog box
Project defaults (check them before starting a
new project)
Project calendar adjustments (holidays, etc..)
Task Sheet View for initial task entry
Add columns
7/31/2019 MS Project Guide Basics Only
4/45
7/31/2019 MS Project Guide Basics Only
5/45
Project Defaults
7/31/2019 MS Project Guide Basics Only
6/45
7/31/2019 MS Project Guide Basics Only
7/45
Project Calendars
7/31/2019 MS Project Guide Basics Only
8/45
Views and Columns
Task Sheet view
Add or hide a columns as necessary
Suggested columns:
Task Name % Complete
Duration
Work
Start Finish
Resources
7/31/2019 MS Project Guide Basics Only
9/45
Exercise 1
Setting project defaults
7/31/2019 MS Project Guide Basics Only
10/45
Tasks
Project Summary Task
Summary Tasks
Sub-tasks Task Types
Fixed Units
Fixed Work Fixed Duration (recommended)
Effort driven
7/31/2019 MS Project Guide Basics Only
11/45
Project Summary Task
The project summary task has uniquecharacteristics:
ID = 0
Unique ID = 0
Outline Level = 0
Summary Yes
Only project summary tasks can becreated at Outline Level 0.
7/31/2019 MS Project Guide Basics Only
12/45
Summary Tasks
7/31/2019 MS Project Guide Basics Only
13/45
Subtasks
7/31/2019 MS Project Guide Basics Only
14/45
Task Types
Fixed units tasks where the resources are a fixedvalue & changes to the amount of work or the durationdo not affect the resources
Fixed work tasks where the amount of work is a fixed
value & changes to the duration or the number ofresources do not affect the work.
Fixed duration (recommended) tasks where theduration is a fixed value & changes to the work or theresources don't affect the duration.
Effort Driven the duration of a task shortens orlengthens as resources are added or removed from atask while the effort (work) remains the same.
7/31/2019 MS Project Guide Basics Only
15/45
Task Types
7/31/2019 MS Project Guide Basics Only
16/45
Exercise 2
Entering tasks
7/31/2019 MS Project Guide Basics Only
17/45
Task Information
Task Information Form
Milestone tasks
Durations Constraints
Dependencies (predecessors)
7/31/2019 MS Project Guide Basics Only
18/45
Task Information Form
7/31/2019 MS Project Guide Basics Only
19/45
Task Information Form
7/31/2019 MS Project Guide Basics Only
20/45
Task Information Form
7/31/2019 MS Project Guide Basics Only
21/45
Task Information Form
7/31/2019 MS Project Guide Basics Only
22/45
Task Information
7/31/2019 MS Project Guide Basics Only
23/45
Milestones
7/31/2019 MS Project Guide Basics Only
24/45
Task Duration
When entering task durations, enter theamount of time expected to complete thetask
Duration abbreviations M = Minutes
H = Hours
D = Days W = Weeks
M = Months
7/31/2019 MS Project Guide Basics Only
25/45
Task Constraints
Field dependencies
Constraint types As late as possible
As soon as possible Finish no earlier than
Finish no later than
Must finish on
Must start on Start no earlier than
Start no later than
7/31/2019 MS Project Guide Basics Only
26/45
Task Dependencies
Predecessors
Finish to Start (FS default)
Start to Finish (SF)
Start to Start (SS)
Finish to Finish (FF rarely used)
7/31/2019 MS Project Guide Basics Only
27/45
Exercise 3
Setting constraints, durations andpredecessors
7/31/2019 MS Project Guide Basics Only
28/45
Resources
Resource types
Entering resources
Assigning resources to a task Understanding work
7/31/2019 MS Project Guide Basics Only
29/45
Resource Types
Work (people)
Material (expenditures)
Rates (hourly rate or cost of hardware)
7/31/2019 MS Project Guide Basics Only
30/45
Entering Resources
Best done after tasks are entered andlinked
Assign names and work effort for eachindividual
Duration is the length of time the task willtake to complete, entered in days
Work is the amount of effort needed tocomplete the task, entered in hours
7/31/2019 MS Project Guide Basics Only
31/45
Exercise 4
Entering Resources
7/31/2019 MS Project Guide Basics Only
32/45
Tracking
Base lining the project
Entering actual information
7/31/2019 MS Project Guide Basics Only
33/45
Base lining the Project
Purpose of base lining
How to do it
Tools, Tracking, Save Baseline
Remember to baseline the ENTIRE project!
7/31/2019 MS Project Guide Basics Only
34/45
Entering Actuals
Task sheet view
Enter actual start date
Break links as needed
Enter actual duration
Enter actual time commitments
Set task completion at 100% Sequence is VERY important
7/31/2019 MS Project Guide Basics Only
35/45
7/31/2019 MS Project Guide Basics Only
36/45
Views, Tables & Filters
Views
Task Views
Gantt Chart
Tracking Gantt Chart
Custom Views
Tables
Filters and Groups
7/31/2019 MS Project Guide Basics Only
37/45
Task Sheet
Task Sheet
Used for reporting
Basis for most custom forms
7/31/2019 MS Project Guide Basics Only
38/45
Gantt Chart View
7/31/2019 MS Project Guide Basics Only
39/45
Tracking Gantt
7/31/2019 MS Project Guide Basics Only
40/45
7/31/2019 MS Project Guide Basics Only
41/45
Tables
A table is the actual spreadsheetpresentation of the rows and columns
It stores which fields you see and how thecolumns are ordered
7/31/2019 MS Project Guide Basics Only
42/45
Filters & Groups
Filters - a way to select a subset of tasksto be shown in a view.
Groups - a way to organize rows based on
field content. Filters and groups can be used together to
order the data or they can be used
independently. Filters and groups can be created usingone or more conditions
7/31/2019 MS Project Guide Basics Only
43/45
Exercise 6
Views
7/31/2019 MS Project Guide Basics Only
44/45
Summary
Tip of the iceberg (much more capability).
MS Project is a tool that aids planning, itwont plan for you.
Need to invest in mastering the tool.
MS Project training guides located athttp://www.k-state.edu/InfoTech/epm/training/index.html
Iterative saves
http://www.k-state.edu/InfoTech/epm/training/index.htmlhttp://www.k-state.edu/InfoTech/epm/training/index.htmlhttp://www.k-state.edu/InfoTech/epm/training/index.htmlhttp://www.k-state.edu/InfoTech/epm/training/index.html7/31/2019 MS Project Guide Basics Only
45/45
Contact Information
Peer support call if you need help
Chuck Gould532- 4923
Lloyd Walker532- 2616
Ashley Wondra532-4761
mailto:[email protected]:[email protected]:[email protected]?subject=MS%20Project%20101mailto:[email protected]?subject=MS%20Project%20101mailto:[email protected]:[email protected]