Upload
albert-potter
View
223
Download
0
Tags:
Embed Size (px)
Citation preview
NASA GRC ISS On-Orbit Facilities
• Combustion Integrated Rack SE & Operations• Fluids Integrated Rack SE & Operations• Mission Integration & Planning
• Space Acceleration Measurement System• Microgravity Acceleration Measurement System• Principal Investigator
Microgravity Services
• Multi-user Droplet Combustion Apparatus SE & Ops• Light Microscopy Module SE & Ops • Telescience Support Center Ops & Maintenance
CIR FIR
MDCA LMM
SAMS MAMS
1
2
Fluids and Combustion Facility (FCF)GRC Project Manager: MSI/Robert Corban
Chief Engineer: Dennis Rohn
Safety Mission Assurance Lead:
NASA Customer: SLPS/OBKey Contractor(s): ZIN Technologies Inc.
Project Mission Statement:• Operate and Sustain the Combustion Integrated Rack (CIR) and the Fluids Integrated Rack (FIR) on the International Space Station (ISS) thru GRC’s Telescience Support Center.
GRC Scope:•Planning, Operation and Coordination of FCF and associated payloads•Mission Integration and Planning•Telescience Support Center operations and maintenance•Sustaining engineering on FCF Flight racks, spares, and GIU
Project Life Cycle Schedule (Operations)Milestones CIR Launch CIR Ops FIR Launch FIR Ops FIR CVB CIR FLEX FIR ARIS FIR PACE FIR ACE-1 CIR FLEX2 Final Report
Actual/ Baseline 11/2008 2/2009 8/2009 1/2010 7/2010 11/2011 9/2011 10/2010 8/2012 2012 N/A
FIR Flight Rack on ISS CIR Flight Rack on ISS
3
Fluids and Combustion FacilityProject Manager: Robert Corban
WBS 825080.04.02.20.01
Status
Variances• SCHEDULE: FIR has no samples and is currently inactive. CIR has not been given limited
operations time for last month.
Key Issue/Concern Potential Impact Action PlanResolution Date
FLEX - motor position error associated with the fuel reservoir dispenser #2
Operational ImpactScience Delay
1. Perform on-orbit Trouble-shoot (encoder or blockage)√2. Replace Fuel Reservoir #1 to continue current Ops (6/19) √3. Hold ERB to determine best plan forward √4. Install new needle set and/or fuel reservoir√
9/2012 CLOSENeedle replacement tested successful.
Data Management operational time will be excessive for future planned payloads (i.e, ACME)
Limited Science Return
1. Perform options Assessment for future planning√2. Develop proposal for additional funding to support upgrades
to enhance science return. √3. Implement some of the “low hanging fruit” options in FY12 –
put in new SOW for CY12.
10/2012CR in for funding IPSU-G Option w LMM Camera
CIR Illumination Control Module Communications
Loss of primary FLEX2 science instrument
1. Additional testing is planned on resolution of CIR loss of MRDL/LRDL, maybe thermal issue. √
2. Accelerate spare for earliest manifest opportunity TBD (ATV4) – No On-orbit Spare. √
3. Manifest spare ICM even if issue resolved
11/2012ICM Completed. No issues w/ last operations.
Cost Schedule Technical Mgmt.Current Month G Y G GPrior Month G G R G
Key Issues
Technical/Cost/Schedule Review Monthly Status Review
Glenn Research Center at Lewis Field
10 Oct 2012
1) Significant Activities • OB activities (weekly telecons, FIR/CIR awareness, L&M Data, metrics, PPBE14)
– Worked with JSC OB L&M on ORU listing for FIR and CIR (Facility vs Payload agreement w OZ)– Provided updates to the FIR and CIR “occupancy” metric– ITAs provided to OB (FCF SE & Ops, AMP) and OZ (MIP/TSC)– CRs provided to the ISS Program (OB) for ACME development and LMM Camera/IPSU upgrade
• CIR Operations − On-going FLEX-2 experiment (31 burns completed)− R&R on CIR’s main hard drive; fixed boot-up issue w/ CIR− R&R on CIR’s Igniter’s and Needle; fixed blockage in needle & burned out igniter− Proceeding, when necessary, in locked down configuration when crew time not available
• FIR Operations with Light Microscopy Module (LMM) - ACE-1A (colloids) operations successfully completed on two samples
• SpaceX-1 Manifest successfully shipped (and launched)− MDCA Fuel Reservoirs (5), CIR Manifold Bottles (4), FO Cable Spare, DCM-LCTF Spare
• Participated in OB SORRs (30S return/ATV-3 disposal, SpX-1/32S)• Completed off-gas testing of the Gas Chromatograph Instrument Package (GCIP); manifested on ATV-4• Performed crew increment training at JSC• Supported the POIWG meeting at Huntsville, AL.• ISS video capability upgrade installed at the GRC/Telescience Support Center• Tours/briefings of FCF GIUs/TSC provided to OB/OZ Management, CASIS, Northrup-Grumman
Combustion Integrated Rack / Fluids Integrated Rack / TSC / MIP
ITA Title: GRC On Orbit Facilities O&M– FY12ITA #: N/A for FY12PMII: 769347.05.08 (FY13)
Division: MSI
Name: Robert Corban 216-433-6642
4
Technical/Cost/Schedule Review Monthly Status Review
Glenn Research Center at Lewis Field
10 Oct 2012
2) Technical Issues/Schedule Issues • Lack of Crew Time (schedule impact): Agreement by Science team to proceed without PaRIS
configuration for CIR
3) Planned Activities for next quarter • Complete vibration testing for spares of ATCU Fan (Oct), ATCU Electronics Enclosure Unit (Oct),
Illumination Control Module (Oct), Smoke Detector (Oct), IPSU (Nov) and HiBMS (Nov)• Complete assembly on LMM Control Box spare• Life Extension study (2028) for CIR, FIR, SAMS, MAMS
– CIR & FIR ATCU HX Life Extension– Spares evaluation (completed)– Structural Impact assessment– Avionics upgrades (completed)
• Complete the CIR & FIR filter characterization testing on the GIUs• Kickoff of new IPSU development and LMM Camera Upgrade to define requirements• SpaceX-2 Manifest (Fuel Reservoirs, ACE samples, Return: IOP HD, Needle, Bottles) and
associated documentation• ATV-4 Manifest (Bottles, Needles, Fuel Reservoirs, FOMA Cal Unit, ICM, GCIP, CVB-2) and
associated documentation• Begin operating under OB ITAs and OZ ITA
– 13996 FCF SE & Ops (OB)– 13997 AMP Program (OB)– 14000 TSC & MIP (OZ)
Combustion Integrated Rack / Fluids Integrated Rack / TSC / MIP
ITA Title: GRC On Orbit Facilities O&M– FY12ITA #: N/A for FY12PMII: 769347.05.08 (FY13)
Division: MSI
Name: Robert Corban 216-433-6642
5
Fluids and Combustion Facility Sustaining Eng. Milestone Summary
Next Milestone Risk• SpaceX-2 Manifest SAR ERB (Nov 2012)
Milestones (CY12) Baseline Projected Actual Schedule Variance
HTV-3 Manifest SAR Mar 12 Mar 12 Apr 12 HW shipped
ATCU Fan/EEU Spares Apr 12 Jun 12 Jun 12 Assembly complete (March); Vibe (June); Thermal (June)
MDCA Avionics Package spare May 12 Sept 12 Sept 12 Assembly complete (April); Vibe complete (May); EMI complete (June); Thermal complete (June)
TSC Video Upgrade Jun 12 Aug 12 TV Install & Operating; cables being installed
CIR’s Gas Chromatograph (GCIP) Jun 12 Sept 12 Sept 12 Assembly complete (March); Vibe complete (June); EMI complete (May); Thermal complete (June); Off
Gas Complete ( Aug)
LMM GIU “fixes” Aug 12 Aug 12 Technicians working to resolve issues
Common IAM spares Nov 12 Nov 12 Assemble complete
MDCA Color Camera replacement Nov 12 Nov 12 Assemble complete
DCM (2) & ICM spares Dec 12 Dec 12 ICM made higher priority; ICM Assemble complete
LMM Control Box Spare Dec 12 Dec 12 Parts Delivered; Board level vibe completed
Project is less than 1 month behind plan Project is less than 2 months behind plan Project is greater than 2 months behind plan
Schedule Color Key
6
Project Milestone ScheduleCY 2012
J F M A M J J A S O N D
ATCU Fan/ EEU
Spares
DCMs & ICM
GCIP TSC Video
Upgrade
LMM GIU Upgrade
HTV-3 SAR
IAM Spare
MDCA Avionics
Pckg Spare
LMM Control
Box
MDCA Color
Camera
FCF Operations (over last two months)
7
Increment Week CIR FIR
31/32 14 (8-2) No Ops ACE 1st Sample Pics & Installed; Ops began
31/32 15 (8-9) Needle #2 R&R; Igniter R&R; FLEX-2 Data Points (4)
ACE 1st Sample Ops
31/32 16 (8-16) IOP HD R&R ACE 1st Sample Ops
31/32 17 (8-23) CIR Activated; Checked out; SW updates to HD
ACE 2nd Sample Pics & Ops; White Light Cable switched
31/32 18 (8-30) FLEX-2 Data Points (3) No Ops
31/32 19 (9-6) No Ops No Ops
31/32 20 (9-13) FLEX-2 Data Points (4) No Ops
33/34 A (9-20) No Ops No Ops
33/34 1 (9-27) FLEX-2 Data Points (5) No Ops
33/34 2 (10-4) No Ops No Ops
33/34 3 (10-11) FLEX-2 Data Points (4) No Ops
7
ISS OCCUPANCY -- CIR RACK1 October 2012 (Data through 30 September 2012) [POC: Robert Corban/GRC]
Rack Moves, Maintenance, Annual Cert
Trouble-shooting or Crew-time/ sched conflict
Rack not Occupied
Avg. Historical Usage
Greater than 1-sigma below the mean occupancy
8%3%
CIR As-Run Data CIR Utilization Plan
CIR Occupancy & Powered Ops(Powered Operational Time/Monthly Available Time)
% O
ccup
ancy
(Pow
ered
and
Unp
ower
ed)
Inc37
Inc38
FLEX-2
FLEX
-2
20142011 2012 2013
Inc27
Inc28
Inc29
Inc30
Inc31
Inc32
Inc33
Inc34
Inc35
Inc36
FLEX
-2
FLEX FLEX-2 FLEX ICE-GA
FLEX
NASA PayloadPowered Ops
IP PayloadPowered Ops
NASA PayloadDwell Time
IP PayloadDwell Time
CIR Main Computer Hard Drive Failure resolved with quick-turn around R&R by
the Crew
ICE-GA
8
ISS OCCUPANCY -- FIR RACK1 October 2012 (Data through 30 September 2012) [POC: Robert Corban/GRC]
Rack Moves, Maintenance, Annual Cert
Trouble-shooting or Crew-time/ sched conflict
Rack not Occupied
FIR As-Run Data FIR Utilization Plan
FIR Occupancy & Powered Ops(Powered Operational Time/Monthly Available Time)
% O
ccup
ancy
(Pow
ered
and
Unp
ower
ed)
Inc37
Inc38
20142011 2012 2013
Inc27
Inc28
Inc29
Inc30
Inc31
Inc32
Inc33
Inc34
Inc35
Inc36
NASA PayloadPowered Ops
IP PayloadPowered Ops
NASA PayloadDwell Time
IP PayloadDwell Time
Avg. Historical Usage
Greater than 1-sigma below the mean occupancy
7%0%
PACE-2BIO
ACE-
1
CVB-2BIO
ACE-
M
ACE-M2
ARIS ACE-H
First two ACE-1A Samples provided necessary data for PI. Other three samples will
not be imaged.
9
Technical/Cost/Schedule Review Monthly Status Review
Glenn Research Center at Lewis Field
10 Oct 2012ITA Title: GRC On Orbit Facilities O&M– FY12ITA #: N/A for FY12PMII: 769347.05.08 (FY13)
Division: MSI
Name: Robert Corban 216-433-6642
ITA N/A (FY12)
4a. Current FY Budget Status (Cumulative) · Procurement - Performance to Plan
Month Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepObl ($K) 47 80 152 2,288 2,364 2,430 2,998 4,095 4,643 4,721 4,601 4,677 Plan Cost Labor ($K)* 58 113 169 228 284 343 399 460 516 575 637 690Plan Cost Materials ($K)* 246 765 1174 1602 2167 2533 2898 3265 3631 4195 4562 4927Actual Cost Labor ($K) 68 102 173 228 273 339 398 473 513 573 649 709Actual Cost Materials ($K) 246 632 1185 1463 1838 2297 2617 3056 3537 3975 4537 4883
· CS FTE - Performance to Plan Month Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Avg Plan (FTE) 4.6 4.6 4.7 4.8 4.9 4.9 4.9 4.9 4.9 4.9 4.9 4.9 4.8Actual (FTE) 3.2 3.8 3.5 3.4 3.8 4.4 4.4 4.3 4.1 4.1 3.9 3.8 3.9
4b. Cost variance explanation:
4c. Civil Service FTE variance explanation:
5. Travel Budget Status (Cumulative):
Month Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepAdjusted Cost Plan ($K) 0.0 0.0 1.0 1.0 1.0 1.0 1.0 2.0 3.0 3.0 4.0 4.0Actual Cost ($K) 0.0 0.0 0.0 0.0 0.0 1.1 0.0 0.0 2.3 4.9 5.0 5.0
Travel obligations are $1.1K
WBS Numbers:904211.04.02.20.01 FCF (O&M)904211.04.02.20.02 MIP904211.04.02.20.03 GRC TSC
10
AMP – SAMS/MAMS/PIMS
11
GRC Project Manager: MSI/Kevin McPherson
Chief Engineer: Alan Linne
Safety Mission Assurance Lead:
NASA Customer: SOMD/Brad Carpenter, JSC ISS Structures and Mechanisms
Key Contractor(s): ZIN Technologies Inc.
ZIN Task Lead: Jennifer Keller
Project Mission Statement:• Acceleration Measurement Program will measure,
process, analyze, and interpret the ISS acceleration environment as measured by SAMS and MAMS for research payloads and vehicle customers
GRC Scope:• Planning and operation functions for the SAMS and
MAMS acceleration measurement payloads• Acceleration data analysis and dissemination for
microgravity Principal Investigators• Sustaining engineering functions for the SAMS and
MAMS acceleration measurement flight systems and associated ground equipment
Project Life Cycle ScheduleMilestones SCR HCR PDR CDR VRR Safety FHA Launch Ops Return Final Report
Actual/ Baseline N/A N/A 12/1995 9/1997 1/2000 9/2000 12/2000 4/2001 Inc. 1 -> N/A N/A
SAMS Interim Control Unit
MAMS Front Panel
SAMS acceleration data
12
Acceleration Management ProgramProject Manager: Kevin McPherson
WBS 904211.04.02.30.01
WBS 401769.06.03.02.02.18
Status
Variances• COST: Delays in repair and re-certification of TSH-ES SN08 (some fasteners sent out for a
locking mechanism) for ATV-4
Key Issue/Concern Potential Impact Action PlanResolution Date
SAMS ICU Replacement No SAMS Operations if fails
1. Requested by ISS Program to find solution for use of unsupported station laptops√
2. Investigate integration of SAMS and IWIS √3. Obtain CR approval√4. Implement new ICU
October
CR Approved; Directive in-work
Lack of SAMS Spares No SAMS Operations if lack spares
1. Request by ISS Program for additional spare builds2. Refurbish TSH-ES SN03 as a spare3. Determine # spares to meet 2020 goals4. Obtain CR approval5. Implement spare builds
January 2013
Cost Schedule Technical Mgmt.Current Month Y G G GPrior Month Y G G G
Key Issues
Technical/Cost/Schedule Review Monthly Status Review
Glenn Research Center at Lewis Field
10 Oct 2012
1) Significant Activities • 100% measurement availability when ISS resources allow SAMS and MAMS equipment to be powered• On-orbit SAMS File Repair procedure performed by the crew to recover after an extended power
outage. • On-going support of ISS Loads and Dynamics team for daily monitoring of structural mode regime. • Statistical analysis of acceleration data toward peer-reviewed publication of SAMS/MAMS analysis
results for first year of ISS assembly complete.• SAMS TSH-ES sensor SN 08 is completed, EMI testing completed, scheduled for vibe testing.• SAMS TSH-ES sensor SN 03 updated; EMI testing completed.• SAMS cable lost in Progress 44P failure completed (longer than original).• SAMS ICU Upgrade to the ISS Laptop approved by VCB and the SSPCB (out-of-board approval)
• “The SAMS Upgrade CR 13240 has received all evaluations and they were all concur or concur with comments. The upgrade will use the current laptop (T61p) instead of the obsolete 760XD and be aisle mounted instead of in an ISIS drawer in an Express Rack. The SSPCB selected this implementation option and the cost is $260K for the SAMS Team to perform the work in approximately 9 months.” Kathy Koerner
2) Technical Issues/Schedule Issues • None
3) Planned Activities for next quarter • Complete all hardware testing and verifications for turn-over to MSG for manifest on ATV-4• CR for SAMS TSH-ES spares (w/ wireless capability)• Begin the SAMS ICU Upgrade software
SAMS/MAMS/PIMS
ITA Title: GRC On Orbit Facilities O&M– FY12ITA #: N/A for FY12PMII: 769347.05.08 (FY13)
Division: MSI
Name: Kevin McPherson 216-433-6182
13
FCF Project Review Action Items
Action Number
Date Initiated
Date Due
Person(s) Responsible Project Actions - Notes/Status Date
Completed
MSI-Rev- 18 08/26/11 02/27/12 Corban FCFEvaluate the cost/schedule impact of replacing/upgrading the IPSUs.
08/15/12
MS-Rev- 25 01/19/12 02/29/12 Corban FCF Add State of Health Chart for FCF (Jalopy) 02/29/12
14
15
Project Manager’s Top Concerns
o Increasing CIR (and FIR) data management efficiency (ACME needed for sure)
o Maintaining trained and certified CIR and FIR Operations Team
o Keep TSC operational and properly maintained with minimal staffing (CoNNeCT operations may impact need for more staffing)
o Delays and gaps in FIR operations
o Completing the Long-Term Life study (2028) for CIR and FIR
o MDCA and LMM lack of sparing for long-term operations (FCF Sustaining Engineering inheriting the risk)
o Failures of DCM and similar designed, ICM. No Spare ICM on-orbit.
o Long-term upgrades to the CIR and FIR (Cameras, IPSUs, LMM, Software, etc)
o ISS Program requests for data and various information with multiple processes.
16
Backup Charts
Back-up charts will not be briefed unless specifically requested.
National Aeronautics and Space Administration
www.nasa.gov
CIR State of Health – Sustaining EngineeringMDCA Subsystems
Radiometer
Avionics Box
Color CameraColor Camera
Flex Consumables
Flex 2 Consumables
HiBMS Spare
Focus Prism Spare
ATCU SpareEPC U
EPCUSpare
SpareIOP Spare
Diagnostics Environmental Avionics Facility
Ground Systems(Nominal status only)
Diagnostics
Data Subsystems
Environmental
PRCU
Avionics
MDCA CIA GIU
Facility
Grey Shadow – Resolution in WorkGrey Shadow – Resolution in Work
Red Shadow – Resolution Not in WorkRed Shadow – Resolution Not in Work
LLL-UV
CIA
FOMA Cal
WFCA IPSU
FDSS
IPSU-A
FOMA Control
PaRIS
SAMS TSH-ES
Windows
Seals
Spare
SpareSpare
Spare
Spare
Spare
Spare
Spare
SpareSpare
Spare
Spare
Spare
SpareSpareSpare
Spare
Spare
Spare
Spare
RECIR Pumps SpareSpare
SpareSpare
GCIPGCIP Spare
Fuel Stowed: 6 mo.
Bottles Stowed: 9 mo.Spare
SpareSpare
SpareSpare
Operations Spares YELLOW – Spare On Ground
RED – No Spare
GREEN – Spare On Orbit
YELLOW – Off-Nominal
RED – Not Operational
GREEN – Nominal
IlluminationIllumination Spare
17
National Aeronautics and Space Administration
www.nasa.gov
YELLOW – Spare On Ground
RED – No Spare
FIR State of Health – Sustaining Engineering
GREEN – Spare On Orbit
W hite L ight
White LightSpare
Spare ATCU SpareEPC U
EPCUSpare
SpareIOP Spare
Diagnostics Environmental Avionics Facility
Ground Systems(Nominal status only)
Diagnostics
Data Subsystems
Environmental
PRCU
Avionics
Facility
YELLOW – Off-Nominal
RED – Not Operational
GREEN – Nominal
Operations SparesGrey Shadow – Resolution in WorkGrey Shadow – Resolution in Work
Red Shadow – Resolution Not in WorkRed Shadow – Resolution Not in Work
PACE
ACE
WFCA IPSU
FSAP
ARIS
SAMS TSH-ES
Seals
Spare
SpareSpare
SpareSpare
Spare
SpareSpare
Spare
SpareSpareSpare
Spare
Spare
SpareSpare
Spare
MicroscopeLMM Subsystems
Control Box
Camera
X-Y Stage
Objectives
Samples Stowed: 0 mSamples Stowed: 0 m
FDSS
SpareSpare
Spare
Spare
Spare
Spare
Spare SpareSpare
18
Facility Risks Top 10 Risks
LIKELIHOOD
5
4 F1
3 F2, F3
2 F4, F5
1
1 2 3 4 5
CONSEQUENCES
Risk ID Risk Title Risk Statement L C Approach
F1
TechnicalCorban10/04/2011
FCFSE:DCM LCTF failure
Given the DCM LCTF fails on the CIR flight rack; then there is an inability to accomplish full FLEX2 science.
4 3 Mitigate: Manifest DCM LCTF S/N2001 on the next DO period of performance. Add procurement and assembly of a second spare LCTF DCM to the DO period of performance. Status: Plans to add procurement and assembly of a second spare to the DOClose Date: 07/31/2012
F2
Technical Corban 10/18/2010
FCFSE: Unknown cause DCM failure
Given that the LCTF DCM had a communication failure on the CIR aboard ISS without a known cause; there is a risk of subsequent DCM failures on remaining DCMs will occur.
3 3 Mitigate: The flight spare on the ground is in the process of being certified for flight.This unit will need to be manifested as a flight spare to mitigate this risk. Status: There is currently additional troubleshooting going on as additional issues have arisen and need to be better understood to resolve. . Close Date : 02/29/2012
F3
Technical Corban10/04/2011
FCFSE:LMM GIU does not fully emulate the flight unit
Given that the LMM GIU does not fully emulate the flight unit;; the possibility exists that future LMM flight experiments will not operate correctly.
3 3 Mitigate: Plan is to review LMM GIU non-flight design issues and add task to update LMM GIU to the next DO period of performance. Status: Task has been added t the DO to upgrade to LMM GIU. Close Date: 07/02/2012
F4
Technical Corban 02/10/2010
FCFSE:Lack of critical spares aboard ISS
Given that there is a lack of critical spares aboard the ISS; then there is the possibility that a lack of meeting all science requirements will occur.
2 3 Mitigate: A priority list for flight critical spares has been established. ZIN has shipped and manifested flight White Light EPCU IOP FSAP. Additional flight h/w for ULF5 include: IPSU-A FCU Q-Imaging camera and IPSU (Remora). ZIN is in the process of verifying additional spare hardware(FIR &CIR velocity probe White Light lamps IPSU-A FCU and an IAM. Status: Working to add next set of spares to DO; will include spare fiber-optic cable to backfill for suspect cable on-orbitClose Date: 04/06/2012
F5
Technical Corban02/10/2010
FCFSE:IOP removable hard drive shelf life
Given that the IOP removable hard drives have a limited shelf life; then there is the possibility that these hard drives won't work over time and the FIR and CIR racks will not be able to provide support for their payloads to perform science operations will occur.
2 3 Watch: Awaiting to see if funding issues will be resolved. Status: Funding for new design functional model IOP hard drives in the current DO. Close Date: 12/31/2012
Criticality L x C Trend
High Decreasing (Improving)
Increasing (Worsening)
Unchanged
* New since last month
Med
Low
Approaches: Mitigate, Watch, Accept, Research
19