24
Nate Babyak Alex Ho Brian Sampson Alex Schreffler Mission Statement: To deliver innovative designs, with an integrated, streamlined approach to building systems and construction management

Nate BabyakAlex HoBrian SampsonAlex Schreffler

Embed Size (px)

DESCRIPTION

Mission Statement: To deliver innovative designs, with an integrated, streamlined approach to building systems and construction management. Nate BabyakAlex HoBrian SampsonAlex Schreffler. Agenda. Roof Analysis/Redesign New Mechanical Loft Addition Lobby Analysis/Redesign - PowerPoint PPT Presentation

Citation preview

Page 1: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Mission Statement:To deliver innovative designs, with an integrated, streamlined approach to building systems and construction management

Page 2: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Roof Analysis/Redesign

New Mechanical Loft Addition

Lobby Analysis/Redesign

Moving Forward

AGENDA

Page 3: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

CABLE STAY ROOF DESIGNDESIGN CONSIDERATIONS

• Dead loads• Roof Deck• Roof Members

• Snow Loads• Unbalanced Drift

• Wind Uplift• Cable Load Combinations • ASCE 7 Load Combinations• Erection Sequencing

Page 4: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

CABLE STAY ROOF DESIGNDESIGN ATTEMPTS

First Attempt:• Deck: 3N18 spanning 14’• Beams:

• W30x90 • CB 36x55 (CMC Steel Products)

• Girder:• W40x372

• Cables: Diameters 4.25” to 5.5”• Mast:

• Composite Column Design• 36” steel pipe 1.5” thick 8 ksi concrete

Page 5: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

CABLE STAY ROOF DESIGNDESIGN ATTEMPTS

Second Attempt:• Deck: 3C18 spanning 11’• Beams:

• W33x130• CB 36x94 (CMC Steel Products)

• Girder:• W40x593

• Cables: Diameters 4” to 5.5”• Mast:

• Composite Column Design• 42” steel pipe 2” thick 10 ksi concrete

Page 6: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

3D CoordinationMechanical Space and Loft RedesignBaseline Mechanical Space

Page 7: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Event Level Ductwork ReductionBaseline Event Level Ductwork Layout Event Level Ductwork Layout Redesign

Page 8: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Redesign North Concourse SectionBaseline Event Level Ductwork Layout Baseline North Concourse Section

Page 9: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Redesign South Concourse SectionBaseline Event Level Ductwork Layout Baseline South Concourse Section

Page 10: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Redesign Shaft 1Baseline Event Level Ductwork Layout Baseline Shaft 1

Page 11: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Redesign Shaft 2Baseline Event Level Ductwork Layout Baseline Shaft 2

Page 12: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Shaft Locations and Redesign

Page 13: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Weight of Steel: 67,777 lbs Weight of Steel: 65,476 lbs Weight of Steel: 66,671 lbs

LOFT FRAMING

Page 14: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

• Bay Size Change

• Maintain Floor Deck

• Coordinating Shaft Locations

• Coordinating with Architecture

STRUCTURAL FRAMING

Page 15: Nate BabyakAlex HoBrian SampsonAlex Schreffler

• East Façade Glass Type

• Balance between thermal gain and daylight levels

• Insulated/Low-E

Page 16: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Shading: Un-shaded

Average Illuminance Level: 400 fc

East Façade Yearly Energy Costs: $27,529.00

Page 17: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Page 18: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Page 19: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Shading: Horizontal Shades

Average Illuminance Level: 225 fc

Blocks views from club level

East Façade Yearly Energy Costs: $26,443.00

Page 20: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Shading: Overhang

Due to orientation not feasible

Requires 30’ overhang to shade morning sun

Page 21: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Shading: Vertical Fins

Average Illuminance Level: 200 fc

East Façade Yearly Energy Costs: $25,911.00

Page 22: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

Page 23: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

• IESNA Lighting Recommendations:

• Vestibule: 30 lux

• Lobby: 100 lux

• Concourse/Circulation: 50 lux

• Club Lounge: 40 lux

• Stairs: 50 lux

• ASHRAE 90.1-2010 Power Densities:

• Zone 3• Allowable Power Density By Area: 0.78W/ft2

• By Space:• Entry Canopy: 0.4W/ft2

• Vestibule:30W/linear feet (door width)• Lobby: 0.9W/ft2

• Club: 1.31W/ft2

• Concourse: 1.10W/ft2

Page 24: Nate BabyakAlex HoBrian SampsonAlex Schreffler

Nate Babyak Alex Ho Brian Sampson Alex Schreffler

MOVING FORWARD:

CLASH DETECTIONBUILDING FAÇADE

COORDINATE ARCHITECTUREFINALIZE SITE LAYOUT