Upload
mahina
View
39
Download
0
Tags:
Embed Size (px)
DESCRIPTION
NESSiE. Towards the Technical Proposal, to be submitted to SPS-C. Luca Stanco, on behalf of NESSiE Collaboration February, 15, 2012. Middle January: 1rst meeting/Organization End of January : Intermediate Work-Out Meeting (many meetings hold on) - PowerPoint PPT Presentation
Citation preview
1
Towards the Technical Proposal, to be submitted to SPS-C
Luca Stanco, on behalf of NESSiE CollaborationFebruary, 15, 2012
Middle January: 1rst meeting/Organization
End of January: Intermediate Work-Out Meeting (many meetings hold on)
Middle February: End of Work/Start of TP drafting
End of February: Intermediate Drafting Meeting
Middle of March: TP document ready
2
Content
- Working Areas/ Sharing of responsabilities
- Next Steps
1) Mechanics
1) Detectors/Electronics/DAQ
2) Prototypes
GOAL/Problematiche
Sviluppare un DESIGN STUDY per un Rivelatore a 2 Moduli
- economico - quasi nessun R&D - veloce nei tempi di costruzione - totalmente compatibile con la proposta ICARUS (LAr) - autosufficiente - massimizzare l’output di Fisica
3
Gli Spectrometri sono essenziali per: - Identificazione della carica - controllo degli errori sistematici - chiara separazione di neutrini e anti-neutrini
4
Issues considered/decided-upon in the last month
0) PIT definition and acknowledgement
1)Allow 100 cm for Magnet in Air and related detectors
1)Choose RPC with analog Read-Out for latter case
1)Assembling of Iron structure displaced of 500 cm from final position
4) Assembling of Air Magnet+Detectors in separate HALL
5) Construct a full prototype (MagnetS + Detectors + Electronics) similar to NEAR transverse view (1/2 height) with 5+5 iron slabs
5
The general layout for the FAR site experimental hall is given in Fig. M1. The LAr detector is shown in yellow. The neutrino beam is entering the experimental hall for the LAr direction. Downstream, the air magnet part of the NESSIE spectrometer is shown in pink. The air magnet allows to track muonsemerging with low momentum
from the LAr volume. Further downstream, the iron magnet
is shown in red. This second part is designed to track higher momentum muons.
For safety reasons the LAr and the spectrometer volumes are separated by a containment wall shown in blue in Fig. M1. Fig. M1 shows also 2 of the 4 cranes needed for detector assembly and the expected location of the LAr cryo. plant and of the spectrometer gas system.
6
FAR Hall
Fig. M2: preliminary details about the occupancy of the FAR experimental hall.
7
NEAR Hall
Fig. M4: preliminary details about the occupancy of the NEAR experimental hall.
“A slope of 1.23% has been constructed, mimicking the slope of the LEP/LHC tunnel at point 5.”
high-pressure air pads(30 bars)
8
Checked it is viablefor NESSiE Iron Magnet
9
FAR NEAR
Iron Magnet
10
11
Other details: kind of material, chemical composition and mechanical characteristics
Material: S 235 JRG2 EN10025+A1(table)
z
coil
xz
y
Campo magnetico nel ferro e in aria (sezione yz ; metà superiore) potenziale vettore
(Wb/m)
IronTop
CM (T)
z (m)
y (m)
AIR CM: 0.2 T (30 cm)Bobina sezione rettangolare : 54 mm x 19 mm170 (2 strati) avvolgimenti lungo y, densità corrente 4 A/mm2
Resistenza totale : 0.1 OhmVoltage : 700 V, Potenza 4.9 MW.
Distanza bobina – Iron Spectro : 40 cm
z (m)
B (T)Simulation shows that the Magnetic Fields are perfectly contained
14
PROTOTYPE
3 major issues to clarify:
1) interplay between magnetic fields and electronics of the detectors
2) interplay between Air and Iron magnetic fields (simulation ok but check compatibility with LAr instrumentation)
3) verify viability of mechanical structure (assembling and in-situ displacement) and cooling (Air magnet consumption about 5 MW)
To be build in Lecce (see next slide)
1) MAGNETE IN ARIA (Coils – raffreddamento – strutture – etc.)
2) PROTOTIPO
3) SPETTROMETRI (NEAR & FAR)
3.1) TOP – BOTTOM – LAMIERE – STRUTTURE SUPP. (Progettazione – gare d’appalto – supervisione realizzazione – coordinamento installazione)
3.2) BOBINE – RAFFREDDAMENTO BOBINE (Progettazione – gare d’appalto – supervisione realizzazione)
3.3) STRUTTURA ASSEMBLAGGIO SPETTROMETRI (Progettazione – gare d’appalto – supervisione alla realizzazione)
3.4) TOOLS MONTAGGIO (Progettazione – supervisione alla realizzazione)
3.5) RIVELATORI “RPC”
3.6) RIVELATORI “HPT”
FRASCATI
4) INTEGRAZIONE GENERALE “ NESSIE” – COORDINAMENTO “NESSIE – CERN”
BOLOGNA
LECCE
PADOVA
PADOVA
LECCE
?
?
3.7) INTEGRAZIONE – COORDINAMENTO INSTALLAZIONE
BOLOGNA
NESSIE: TENTATIVO ORGANIZZAZIONE CAPITOLI MECCANICA SPETTROMETRI NEAR & FAR
regime di lavoro standard:•miscela: Ar (75.4 %), R124A (freon, 20 %), ISOB (4.0 %), SF6 (0.6 %), 5refills/day•tensione di lavoro: 5700 V @ 900 mB corretti per le variazioni pressione•soglie sui discriminatori:
• - 40 mV per le strip verticali (31 Ohm)• + 26 mV per le strip orizzontali (24 Ohm)
•discriminatore sopra soglia, segnale di FAST_OR (16 strips adiacenti), controller board legge la FEB e time-stampa il segnale di FAST_OR , controller board inoltra i dati al «run manager» (software trigger) •condizione di trigger «di alto livello» del «run manager» per gli RPC: coincidenza di 3 piani / controller board su 22 usando un intervallo temporale di 200 ns, acquisizione dell’evento•monitoring delle efficienze ogni 12 ore usando i raggi cosmiciil trigger con la coincidenza di 3 piani su 22 consente di acquisire cosmici senza eccessivo dead time, cosmici utili se non indispensabili per verificare il corretto funzionamento del rivelatore in assenza di fascio•efficienza *accettanza misurata integrando sui 2 spettrometri (44 piani): 90 %
One page summary sugli RPC digitali di OPERA
18
WHICH detector for the Air Magnet ?
⇒ACCEPTANCE is critical !
On top of resolution (≲ 1 mm) …
19
3 strips contain 85% of the total chargeinduced on the cathode (X) and 91% of
the total charge induced on the anode (Y)
X
Y
RPC with analog read-out seems the best solution in term of resolution/costs
20
RPC with analog Read-Out for the Air Magnet: assembling
Two options:
1) large area (8x5 m2) sandwiched with honeycomb layers (à la OPERA)PRO: homogeneity (expecially for dE/dx)CONS: never tried
2) fully equipped alluminium-framed chambersPRO: positive past experience (e.g. CMS)CONS: inhomogeneity
21
CMS experience
22
Stima preliminare costi complessivi NESSiE-PS (in K€)(stima errore 20% su singolo valore)
2012: NESSiE, 80 K per R&D
2013: 2,500 (Apparati) + 200 (Consumi) + 150 (Missioni) = 2,850
2014: 4,300 (Apparati) + 350 (Consumi) + 300 (Missioni) = 4,950
2015: 1,500 (Apparati) + 250 (Consumi) + 350 (Missioni) = 2,100
2016: 0 (Apparati) + 300 (Consumi) + 250 (Missioni) = 550===================================================TOT: 8,300 (Apparati) + 1,100 (Consumi) + 1,050 (Missioni) = 10,450
Legenda “Apparati”: nel 2013 (Magnete-FAR), nel 2014 (rivelatori+Mag.NEAR), nel 2015 (DAQ)(vedi tab. 11 del Proposal SPSC-P-343)
Recupero “OPERA” su “Apparati” (70% valore originale):nel 2013: 1,500 (Ferro), nel 2014: 1000 (Ferro) + 1,850 (rpc+strips) = 4,350
Risultato: 6,100 – 10,450
Tempistica Futura
MARZO 2012: preparazione di un Report TECNICO congiunto NESSiE+LAr
GIUGNO 2012: approvazione dell’esperimento da parte del CERN
SETTEMBRE 2012: richieste alla Commissione II per il 2013
GENNAIO 2013: Inizio gare e inizio produzione (NEAR 6 mesi dopo)
SETTEMBRE 2013: Inizio assemblaggio FAR (= T0, vedi dopo)
SETTEMBRE 2014: Inizio assemblaggio NEAR
GIUGNO 2015: Fine istallazione
23
24
Sharing per Technical Proposal
1) Meccanica: LNF, BO, PD, LE
2) Rivelatori: PD, LNF…
3) Elettronica: BA, LE, PD
4) DAQ: PD, BO
DEFINIRE un TEMPO ZERO !
e.g. T0 = starting of 1rst Installation Item at CERN (Sep.2013 for SS)
TDT= Ready to take data: November 2015 for the Spectrometers
25
Prossime RiunioniMechanics: 22 Febbraio (Genova) 13 March (Bologna)
RPC/Elettronics/DAQ: next week
Draft Tech.Prop.
1) Mechanics: General Structure Iron Magnet Air Magnet
2) Detectors: RPC in Iron Magnet RPC in Air Magnet Electronics (Iron and Air)
3) Prototypes: Magnets+Detectors+Electronics
Work out the different items in 1 and 2 week time
26
BACKUP / OLD SLIDES
27
➱ DUE Spectrometri “à la OPERA”, ottimizzati per le accettanze (recupero di contingenze: 300+300 rivelatori RPC 3 m2
possibile recupero di FERRO/Elettronica proprietà dell’ INFN)
750
cm
900 cm 500 cm
1800 + 700 m2 RPC20,000+12,000 digital channelsPrecision Trackers
FAR
NEAR600 cm50
0 cm
28
Need to go to the lowest possible muon momentum (≈ 500 MeV) with best sensitive charge Id at low energy
➯ add coils for B in air
➯ dE/dx measure ➯ long lever-arm (add iron slabs)
Need to beat Multiple Scattering and Detector Resolutionaver a large E range:
29
As a summarySPECTROMETERS complementing the LAr capabilities in measuring the muon momentum would provide valuable information in:
– measuring νμ disappearance in the full momentum range, which is a key ingredient for rejecting existing anomalies at exceeding ’s. or measuring the whole parameter space of sterile neutrino oscillations, i.e. prove sterile neutrino existence;
– measuring the neutrino flux at the close detector in the full muon momentum range, relevant to keep the systematic errors at the lowest possible values.
ALSO the measurement of the muon charge would provide valuableinformation in:
– separating μ from anti-μ in the anti-neutrino beam (where the μ contamination is large). A critical issue is to fully exploit the experimental capability of observing any difference between νμ → νe and anti-νμ → anti-νe (CP violation signature).
30
21+21 Fe-5 cm slabs-3 cm RPC
Dario Orecchini
31
MAGNETE in FERRO
MAGNETE in ARIA
32
R. Arnaldi et al. “SpatialResolution of RPC in streamermode”, Nucl. Instr. & Meth.A 490 (2002) 51
HV
gas
The center-of-gravity method with analog readout is well justifiedby the charge profile:
- Gaussian shape with a width of ~ 5 mm- gas mixture and HV do not change these features- total charge depends strongly on gas mixture and HV
Cosmic ray test with ADC read-out and thin strips (2 mm)