Sub: Statement of Deviation Charges including Additional Deviation Charges, RRAS & AGC Settlement Account for the period from 20.09.2021 to 26.09.2021. Sir, Statement of Deviation charges for the week has been prepared as per CERC (DSM & Related matters) regulation,2014 & all amendments (including 5 th Amendment regulation,2019 dated 28.05.2019) & Petition No. 11/SM/2020 dated 29.05.2020. RRAS Settlement Account for the weeks has been prepared as per the guidelines of Detailed Procedure for Ancillary Services Operation approved by CERC. AGC Settlement Account for the week has been prepared based on the CERC order in petition No. 79/RC/2017, dated 06.12.2017. The last installment of data for the subjected week has been received from ERLDC/NLDC on 01.10.2021. The constituents, who have to pay the Deviation Charges as indicated in the statement, are requested to make the payment to the Deviation Pool account operated by ERLDC within 10 days of the billing date. In case of delayed payments for Deviation charges against these bills beyond 12 days, the defaulting constituents shall have to pay simple interest @0.04 % for each day of delay. जिन संघ के सदय को जिचलन शुक का भुगतान करना है , उनसे अनुरोध है िजिललंग जतजि के 10 कदन के भीतर ईआरएलडीसी ारा संचाजलत जिचलन पूल खाते भुगतान कर। इन जिचलन शुक के जिल के भुगतान 12 कदन से अजधक के विलंब की थिवि , विामी घटकं विलंब के ेक विन @ 0.04% का साधारण ाज का भुगिान करना हगा In case of delay in Payments to/ Receivables from the DSM Pool by the RRAS/AGC providers beyond 12/17 days of the issuance date, the RRAS/AGC providers shall pay to/receive from the DSM Pool Account simple interest @0.04 % for each day of delay. आरआरएएस/एिीसी िािाओं ारा डीआरएम पूल से भुगिान / ाि ि री की थिवि , जारी करने की िरीख से 12 से 17 विनं के बाि, आरआरएएस/एिीसी िािा विलंब के ेक विन के वलए डीएसएम पूल खािा@ 0.04% का साधारण ाज भुगिान / ाि कर गे। Observations, if any, may be intimated to ERPC Secretariat within a fortnight. यवि कई अिलकन , पंह विनं के भीिर ईआरपीसी सवििालय सूविि वकया जा सकिा है। This is issued with the approval of Member Secretary. Encl: As above भििीय / Yours faithfully, (S. KEJRIWAL) SUPERINTENDING ENGINEER Tel No. :033-24239651, 24239650 FAX No.:033-24239652, 24239653 Web: www.erpc.gov.in : 9001-2008 : 9001-2008 NO: ERPC/COM-II/ABT-DC/928 Date: 07.10.2021 To: As per List / सलं सूची के अनुसार

NO: ERPC/COM-II/ABT-DC/928 Date: 07.10

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Sub: Statement of Deviation Charges including Additional Deviation Charges, RRAS & AGC

Settlement Account for the period from 20.09.2021 to 26.09.2021.

Sir,

Statement of Deviation charges for the week has been prepared as per CERC (DSM & Related matters)

regulation,2014 & all amendments (including 5th Amendment regulation,2019 dated 28.05.2019) &

Petition No. 11/SM/2020 dated 29.05.2020.

RRAS Settlement Account for the weeks has been prepared as per the guidelines of Detailed

Procedure for Ancillary Services Operation approved by CERC. AGC Settlement Account for the week has

been prepared based on the CERC order in petition No. 79/RC/2017, dated 06.12.2017.

The last installment of data for the subjected week has been received from ERLDC/NLDC on 01.10.2021.

The constituents, who have to pay the Deviation Charges as indicated in the statement, are requested to make

the payment to the Deviation Pool account operated by ERLDC within 10 days of the billing date. In case of

delayed payments for Deviation charges against these bills beyond 12 days, the defaulting constituents shall

have to pay simple interest @0.04 % for each day of delay.

जिन संघ के सदस्यों को जिचलन शुल्क का भुगतान करना ह,ै उनस े अनरुोध ह ै कक िे जिललंग जतजि के 10 कदनों के भीतर

ईआरएलडीसी द्वारा संचाजलत जिचलन पलू खात ेमें भुगतान करें। इन जिचलन शुल्क के जिलों के भुगतान में 12 कदनों से अजधक

के विलंब की स्थिवि में, व्यविक्रामी घटक ं क विलंब के प्रते्यक विन @ 0.04% का साधारण ब्याज का भुगिान करना

ह गा ।

In case of delay in Payments to/ Receivables from the DSM Pool by the RRAS/AGC providers beyond 12/17

days of the issuance date, the RRAS/AGC providers shall pay to/receive from the DSM Pool Account simple

interest @0.04 % for each day of delay.

आरआरएएस/एिीसी प्रिािाओ ंद्वारा डीआरएम पूल से भुगिान / प्रास्ि में िेरी की स्थिवि में, जारी करने की िारीख से 12

से 17 विन ं के बाि, आरआरएएस/एिीसी प्रिािा विलंब के प्रते्यक विन के वलए डीएसएम पूल खािा@ 0.04% का

साधारण ब्याज भुगिान / प्राि करें गे। ।

Observations, if any, may be intimated to ERPC Secretariat within a fortnight.

यवि क ई अिल कन ह , पंद्रह विन ंके भीिर ईआरपीसी सवििालय क सूविि वकया जा सकिा है।

This is issued with the approval of Member Secretary.

Encl: As above भििीय / Yours faithfully,

(S. KEJRIWAL)

SUPERINTENDING ENGINEER

Tel No. :033-24239651, 24239650 FAX No.:033-24239652, 24239653 Web: www.erpc.gov.in

: 9001-2008

: 9001-2008

NO: ERPC/COM-II/ABT-DC/928 Date: 07.10.2021

To: As per List / सलंग्न सूची के अनुसार

List of Addressee

1. CE (Trans/O&M), BSPTCL, Vidyut Bhavan, Bailey Road, Patna-21. (Fax 0612-2504557)

2. ESE (Interstate), BSPHCL, Vidyut Bhavan,3rd Floor, Bailey Road, Patna-800 021. (Fax 0612-2504557)

3. CE (Comml & Revenue), JBVNL, Engineering Building, H.E.C. Township, Dhurva, Ranchi-834004,

Jharkhand . (Fax : 0651-2490486 / 2400799)

4. GM-cum-CE (Trans), JUSNL,Kusai Colony,Duranda, Ranchi, Jharkhand (Fax:0651-2490486)

5. CE (Comml), DVC, DVC Towers, VIP Road, Kolkata-700 054. (Fax: 033-23552129)

6. CE (SLDC), DVC, P.O.: Danesh Seikh Lane, Andul Road, Howrah - 71110 9. FAX-033-2688-5094

7. Sr. GM(PP),GRIDCO,4th floor, Vidyut Bhawan, Janpath, Bhubaneswar-22. (Fax : 0674-2547180/2547261).

8. Sr. GM (PS), OPTCL, SLDC Bldg, PO Mancheswar Rly Colony, Bhubaneswar-17, (Fax: 0674-2748509)

9. Sr. General Manager(Finance), OPGC, Odisha ( Fax: 06645 222225 )

10. CE (Trans.), Energy & Power Deptt., Govt. of Sikkim, Gangtok.-737 101 (Fax: 03592-201148 / 202927)

11. CE (SLDC), WBSETCL, PO. Danesh Sheikh Lane, Howrah-109. (Fax: 033-26886232)

12. Chief (Finance), NHPC Ltd, Sector-33, Faridabad-121003 (Fax: 0129-2254668)

13. ED (Comml), NHPC Ltd, Sector-33, Faridabad-121003 (Fax No. 0129-2254668)

14. AGM (Comml), NTPC Ltd, Loknayak Jaiprakash Bhawan, 2nd floor, Dak Banglow Chowk, Fraser Road, Patna-

800 001. (Fax : 0612-2230035 / 2224287 ,2211807 )

15. GM (Comml), NTPC Ltd, 7 Institutional Area, Lodhi Road, New Delhi-3 (Fax: 011-24360318 / 24368417)

16. AGH (Comml), Maithon Power Ltd, MA-5,Gonga, PO: Maithon Dam-828207 (Fax: 06540-276606,

08860004758)

17. DGM (Electrical), APNRL, P.O. kandra, Behind 400kV PGCIL S/s, Tata-Kandra road, Dist: Saraikela,

Kharsanwa ( Jharkhand) – 832 105 ( FAX: 0657 – 6628440)

18. AGM(Comml.), ER-I, Powergrid, Patna ( Fax: 0612 2227630 )

19. AGM(Comml.), ER-II, Powergrid, Kolkata (Fax NO. 033 2357 2827)

20. AGM(E&M), GATI Infrastructure Ltd.,, Sundung, Rongli, East Sikkim, Sikkim-737131(Fax: 08066885455)

21. ED, ERLDC, 14 Golf Club Road, Tollygunge, Kolkata-33 (Fax: 033-24235809)

22. ED, NRLDC, 18A, Shaheed JSS Marg, Katwaria Sarai, New Delhi-110 016. (Fax:011-26852747)

23. GM, SRLDC, 29 Race Course Road, Bangalore-560009 (Fax : 080-22268725).

24. GM, WRLDC, MIDC Area, Marol, Andheri (E), Mumbai-490093 (Fax: 022-28235434)

25. GM, NERLDC, Dongtieh, Lower Nongrah, Laplang, Shillong-793006 (Fax:0364-2537470)

26. GM(Electrical),Ind Barath Energy Utkal Ltd.,Vill:Sahajbahal P.O: Charpali-Barpali, Dist:Jharsuguda – 768211

(Fax: 0674-2532174)

27. GM(Power Sales), GMRKEL, Plot no 29, Satya Nagar, Bhubaneshwar- 751 007(Fax: 0674- 2572794)

28. Head(Power Sales),JITPL, Local shopping centre, Sector-B1, Vasant kunj, New Delhi- 110 070

29. AGM, SO, NVVN, SCOPE Complex, Core-5, 1st & 2nd Floor, Lodhi Road, New Delhi-110003 (Fax: 011-

24367021)

30. Head(Commercial), TPTCL, Tata Power Co Ltd, B12 & 13, 2nd Floor, Shatabdi Bhawan, Sector 4, NOIDA –

201 301 (Fax: 0120-2540085/0050)

31. ED, DANS Energy Pvt Ltd, 5th Floor, Building no.8, Tower-C, DLF Cyber City, Phase-II, GURGAON – 122

002

32. GM, Teesta Urja Limited, 2nd Floor, Vijaya Building. 17, Barakhamba Road. New Delhi – 110001 (Ph.

9810519283; 011- 46529600/46529700)

33. AGM, BRBCL, Nabinagar, Aurangabad BIHAR (Fax : 06332 233002)

34. Director, Shiga Energy Pvt. Ltd., 5th Floor, DLF Building No. 8, Tower-C, DLF Cyber City, Phase-II, Gurgaon

– 122002

35. CEO, Sneha Kinetic Power Projects Pvt.Ltd. #31 -A, National Highway, Behind SNOD building,. Deorali,

Gangtok, Sikkim-737102

Receivable Payable Receivable Payable

BSPHCL 563.45740 81.53423 101.43730 746.42893

JUVNL 27.13570 12.16140 16.72455 1.75025

DVC 124.92352 3.82956 14.52089 106.57307

GRIDCO 54.61022 19.80217 1.85371 76.26610

SIKKIM 27.26200 4.26340 0.22025 31.74565

WBSETCL 361.76224 99.63611 52.45890 513.85725

HVDC SASARAM 0.02553 0.01035 0.00000 0.01518

HVDC ALIPURDUAR 2.94918 0.09533 0.00000 3.04451

FSTPP - I & II 5.68838 0.23337 0.75131 6.67306

FSTPP-III 41.93942 2.27516 7.70804 51.92262

KHSTPP-I 70.65996 1.26492 1.81898 73.74386

KHSTPP-II 23.10495 0.56631 0.14306 23.81432

TSTPP 16.06052 0.31470 0.68687 17.06209

BARH 34.15655 0.46631 0.00000 34.62286

MTPS-II 13.69698 0.15952 0.00000 13.85650

BRBCL 25.44203 0.00000 0.39753 25.04450

TEESTA 34.64534 0.20318 0.00000 34.44216

RANGIT 0.36113 0.22482 0.00000 0.13631

MPL 14.02777 1.48320 0.00000 12.54457

NPGC 2.04402 0.00000 0.13715 1.90687

DARLIPALI 2.25588 0.21337 0.11946 2.58871

APNRL 7.94209 0.04656 0.00000 7.98865

GMRKEL 35.51793 0.49464 1.79035 33.23294

JITPL 7.71517 0.05162 0.02322 7.79001

CHUZACHEN 5.30947 0.08332 0.00000 5.22615

DIKCHU 11.29314 0.06068 0.00000 11.35382

JORETHANG HEP 27.47615 0.45280 0.00000 27.92895

THEP 30.55257 0.51504 0.00000 31.06761

TUL 4.84548 0.00000 0.00000 4.84548

RONGNICHU HEP 1.98507 0.05449 0.00000 1.93058

NER 4819.81435 4819.81435

NR 3875.22704 3875.22704

SR 8711.59866 8711.59866

WR 9457.80953 9457.80953

NVVN-BD 31.33052 0.13439 0.39502 30.80111

NVVN-NEPAL 190.71565 3.40710 23.76400 163.54455

TPTCL 162.90759 2.92727 165.83486

NPGC-INFIRM 8.73400 8.73400

BARH SG1_INFIRM 1003.38763 1003.38763

BRBCL_U4_INFIRM 12.67296 12.67296

TALCHER SOLAR 1.31412 1.31412

TOTAL 14834.73336 15019.62448 236.96532 224.95059 14756.66767 15403.47470

15019.62448

14834.73336

184.89112

461.91591

Payable To The Pool (A) :

Receivable From The Pool (B) :

Differential Amount Arising

from capping of

Generating Stations(A-B) :

Additional Deviation Amount :

INFIRM GENERATORS

SOLAR GENERATORS

BENEFICIARIES OF EASTERN REGION

CERC REGULATED GENERATORS (CGS/ISGS)

OTHER GENERATORS

INTER-REGIONAL

INTER-NATIONAL

EASTERN REGIONAL POWER COMMITTEE, KOLKATAABT based Deviation Charge Account

From 20-09-2021 to 26-09-2021

AS PER 5TH AMENDMENT OF DSM, 2019 W.E.F. 03/06/2019 & 01/12/2020

UTILITIES AND DEVIATION

CHARGES PAYABLE BY THEM

DEVIATION CHARGE (in Rs. Lakhs) ADDITIONAL DEVIATION CHARGE

DUE TO BLOCKWISE VIOLATION

OF VOLUME LIMIT (in Rs. Lakhs.)

ADDITIONAL DEVIATION CHARGE

DUE TO VIOLATION OF

SIGN CHANGE (in Rs. Lakhs.)

FINAL DEVIATION CHARGE

(in Rs. Lakhs)

SUPERINTENDING ENGINEER

EASTERN REGIONAL POWER COMMITTEE

KOLKATA

i) For computing Deviation Charge for the week , Korba meter(NP2657A) has been used as master frequency meter.

ii) Deviation charges for the week has been calculated as per amendment of CERC ( Deviation Settlement Mechanism and related matters) Regulation.Notification no. No.L-1/132/2013/

CERC dated 06.01.14. Amendment as per CERC order dated 20.01.2015 on petition no RP/06/2015, 4th Amendment order dated 20.11.2018, 5th Amendment order

dated 28.05.2019 & clause 7.10(b) of DSM 5th Amendment has been incorporated we.f. 01.12.2020.

iii) ACP values for computation of deviation rate vector has been taken from NLDC website

iv) The Cap rate for all generators has been fixed at 303.04 paisa/kwh as per DSM 5th amendment'2019.

v) Additional Deviation Charge due to violation of Block wise volume limit is inclusive of Additional deviation charge due to OD/UI at f<49.85Hz & OI/UD at f>=50.10 Hz.

vi) CHPC, KHPC, THPC and Mangdechhu are not covered under ABT. Hence Deviation energy (MWh) of these stations shall be adjusted monthly after getting data from concerned agency.

vii) The payable/receivable of "Deviation Charge " in respect of Inter-Regional exchanges are settled on first charge basis without any adjustment.

viii) As informed by ERLDC OPGC (2*660 MW), new Pool Member of ER, has started drawing power from 15.01.18.

ix) As informed by ERLDC NPGC(NTPC) became a regional entity and DSM pool member wef 10.05.18 as NPGC started drawing start up power wef 10.05.18

x) As informed by ERLDC DARLIPALI(NTPC) became a regional entity and DSM pool member wef 31.05.18.

xi) Dagachhu HEP has been considered as pure Run of River without pondage as per TPTCL letter dated 06.02.2019 for computation of ADC due to sign change violation

xii) As informed by ERLDC one unit of NPGC(1x660 MW) has been scheduled w.e.f. 06.09.2019

xiii) As informed by ERLDC, NPGC Unit#2 starts drawing Start Up Power w.e.f. 27.08.2019.

xiv) As informed by ERLDC, BARH Stage-I starts drwaing Start up Power w.e.f 01.02.2020.

xv) As informed by ERLDC one unit of DARLIPALI has been scheduled w.e.f. 01.03.2020.

xvi) As informed by ERLDC, DARLIPALI U#2 start drwing start Up power w.e.f. 31.03.2020.

xvii) As informed by ERLDC, RONGNICHU HEP start drawing start Up power w.e.f 00.00 hr of 17.04.2021 & Infirm Injection w.e.f 18.15 hr of 18.04.2021.

xvii) As informed by ERLDC, RONGNICHU HEP has been schduled w.e.f 02.07.2021.

xviii) As informed by ERLDC, NPGC U#2 has been scheduled wef 23.07.2021

xix) As informed by ERLDC, BRBCL_U#4 start drwing start Up power w.e.f. 23.08.2021.

xx) As informed by ERLDC, DARLIPALI U#2 has been scheduled wef 01.09.2021

SUPERINTENDING ENGINEER

Date ConstituentsTotal Scheduled

(MWH)

Total Actual

(MWH)

Total AGC

(MWH)

Deviation

(MWH)

Deviation

Charge(Rs.)

Additional Deviation

Charge (Volume Limit)

in Rs.

Additional Deviation

Charge (Sign Change

Violation)

in Rs.

Total DSM

Charges

in Rs.

2021-09-20 APNRL 5904 5843.418 0 -60.582 -140725 -2479 0 -143204

2021-09-20 NVVN-BD -17478.487 -17406.763 0 71.723 315373 -1629 0 313744

2021-09-20 BARH 14731.831 14535.87 0 -195.961 -463950 -10415 0 -474365

2021-09-20 BARH SG1_INFIRM 0 8975.947 0 8975.947 13738692 0 0 13738692

2021-09-20 BSPHCL -111010.453 -112393.351 0 -1382.898 -7006652 -691763 -420399 -8118814

2021-09-20 BRBCL 7725 7826.686 0 101.686 266003 0 0 266003

2021-09-20 BRBCL_U4_INFIRM 0 -67.413 0 -67.413 -415480 0 0 -415480

2021-09-20 CHUZACHEN 1961.44 1982.928 0 21.488 54532 -394 0 54138

2021-09-20 DARLIPALI 30181.25 30234.191 0 52.941 198743 0 0 198743

2021-09-20 DIKCHU 2274.48 2102.545 0 -171.935 -435244 0 0 -435244

2021-09-20 DVC 41206.912 41199.193 0 -7.719 -41725 -32579 0 -74304

2021-09-20 NR -76060.26 -83509.541 0 -7449.28 -38074870 0 0 -38074870

2021-09-20 NER 6194.152 -11523.041 0 -17717.193 -86512806 0 0 -86512806

2021-09-20 SR -27860.446 -55117.492 0 -27257.046 -129815271 0 0 -129815271

2021-09-20 WR -47494.2 1291.36 0 48785.56 234482553 0 0 234482553

2021-09-20 FSTPP - I & II 22036.934 21554.066 0 -482.868 -1252179 -2927 -75131 -1330237

2021-09-20 FSTPP-III 10218.683 9779.97 0 -438.713 -1170854 -14077 -292714 -1477645

2021-09-20 GMRKEL 15750 15794.763 0 44.763 172379 0 0 172379

2021-09-20 HVDC ALIPURDUAR -15.742 -27.467 0 -11.726 -57111 -2092 0 -59203

2021-09-20 HVDC SASARAM -20.142 -20.797 0 -0.656 -3479 -279 0 -3758

2021-09-20 JUVNL -22639.522 -22854.148 0 -214.626 -1512179 -332331 -181461 -2025971

2021-09-20 JITPL 24411.375 24474.618 0 63.243 175104 -3234 0 171870

2021-09-20 JORETHANG HEP 2425.5 2251.584 0 -173.916 -431976 -4746 0 -436722

2021-09-20 KHSTPP-I 17479.993 17242.713 0 -237.28 -670801 0 0 -670801

2021-09-20 KHSTPP-II 22499.993 21789.806 -584.603 -125.584 -382367 -5284 0 -387651

2021-09-20 MPL 23625.235 22197.927 -1568.467 141.159 360226 -27074 0 333152

2021-09-20 MTPS-II 4258.871 4154.404 0 -104.467 -272320 -7015 0 -279335

2021-09-20 NVVN-NEPAL 0 705.891 0 705.891 3225541 0 -290299 2935242

2021-09-20 NPGC 20450 20460.967 0 10.967 233724 0 0 233724

2021-09-20 NPGC-INFIRM 0 -93.368 0 -93.368 -459021 0 0 -459021

2021-09-20 GRIDCO -34438.83 -34808.609 0 -369.779 -2563582 -596488 0 -3160070

2021-09-20 RANGIT 1446 1451.548 0 5.548 17335 0 0 17335

2021-09-20 RONGNICHU HEP 2100.5 2096.352 0 -4.148 15662 0 0 15662

2021-09-20 SIKKIM -1413.465 -1583.297 0 -169.832 -889970 -57940 0 -947910

2021-09-20 TALCHER SOLAR 24.745 22.635 0 -2.11 -20663 0 0 -20663

2021-09-20 TUL 30043.2 29764.072 0 -279.128 -293188 0 0 -293188

2021-09-20 TEESTA 12474 12611.382 -29.222 166.604 430555 -5841 0 424714

2021-09-20 THEP 2173 1872.672 0 -300.328 -749363 -21867 0 -771230

2021-09-20 TPTCL 2963.52 2169.535 0 -793.985 -2053037 -52754 0 -2105791

2021-09-20 TSTPP 21590.25 21471.299 0 -118.951 -310858 0 -9326 -320184

2021-09-20 VAE_ER 48.503 0 0 -48.503 -84999 -55260 0 -140259

2021-09-20 WBSETCL -42156.866 -41830.997 0 325.869 1186498 -470974 -71190 644334

2021-09-21 APNRL 5904 5744.364 0 -159.636 -134131 0 0 -134131

2021-09-21 NVVN-BD -17539.393 -17465.963 0 73.429 149763 -4318 0 145445

2021-09-21 BARH 11367.148 11141.89 0 -225.258 -122039 0 0 -122039

2021-09-21 BARH SG1_INFIRM 0 11093.128 0 11093.128 12245957 0 0 12245957

2021-09-21 BSPHCL -112063.788 -113425.664 0 -1361.877 -3369525 -39360 -303257 -3712142

2021-09-21 BRBCL 6000 6059.655 0 59.655 135902 0 0 135902

2021-09-21 BRBCL_U4_INFIRM 0 -41.618 0 -41.618 -97572 0 0 -97572

2021-09-21 CHUZACHEN 2174.68 2224.262 0 49.582 110747 -1485 0 109262

2021-09-21 DARLIPALI 35045 34953.685 0 -91.315 17482 -5824 0 11658

2021-09-21 DIKCHU 2015.4 1936.364 0 -79.036 -126937 -351 0 -127288

2021-09-21 DVC 39618.482 39438.727 0 -179.755 -1153346 -84953 -103801 -1342100

2021-09-21 NR -81751.13 -74969.649 0 6781.481 17211243 0 0 17211243

2021-09-21 NER 3926.89 -14392.455 0 -18319.345 -44457765 0 0 -44457765

2021-09-21 SR -9802.842 -45206.101 0 -35403.259 -80020147 0 0 -80020147

2021-09-21 WR -49031.966 -1640.115 0 47391.851 104816534 0 0 104816534

2021-09-21 FSTPP - I & II 15611.961 15697.059 0 85.098 244333 -13470 0 230863

2021-09-21 FSTPP-III 7083.939 7075.268 0 -8.671 131121 -3632 0 127489

2021-09-21 GMRKEL 15750 15431.345 0 -318.655 -200065 0 0 -200065

2021-09-21 HVDC ALIPURDUAR -15.742 -26.672 0 -10.931 -25964 0 0 -25964

2021-09-21 HVDC SASARAM -21.089 -21.089 0 0 289 -7 0 282

2021-09-21 JUVNL -22718.532 -22391.437 0 327.095 796969 -170421 -95636 530912

2021-09-21 JITPL 24505.875 24444.945 0 -60.93 -59378 0 0 -59378

2021-09-21 JORETHANG HEP 2328.35 2199.408 0 -128.942 -217686 0 0 -217686

2021-09-21 KHSTPP-I 16236.633 15739.421 0 -497.212 -649699 0 0 -649699

2021-09-21 KHSTPP-II 20813.578 19891.109 -715.983 -206.486 -261246 0 0 -261246

2021-09-21 MPL 21306.365 19819.891 -1587.758 101.284 227875 -3399 0 224476

2021-09-21 MTPS-II 3878.233 3783.104 0 -95.129 -166755 -5972 0 -172727

2021-09-21 NVVN-NEPAL 0 1029.891 0 1029.891 1920075 -56861 -480019 1383195

2021-09-21 NPGC 20360.638 20047.904 0 -312.734 53079 0 0 53079

2021-09-21 NPGC-INFIRM 0 -37.468 0 -37.468 -87272 0 0 -87272

2021-09-21 GRIDCO -33681.282 -34500.881 0 -819.599 -1000251 -315176 -30008 -1345435

2021-09-21 RANGIT 1446 1441.784 0 -4.216 8770 0 0 8770

2021-09-21 RONGNICHU HEP 2062.5 2047.04 0 -15.46 -55546 0 0 -55546

2021-09-21 SIKKIM -1462.597 -1534.187 0 -71.59 -135473 0 0 -135473

2021-09-21 TALCHER SOLAR 26.76 24.516 0 -2.244 -25119 0 0 -25119

2021-09-21 TUL 27504.295 26503.418 0 -1000.877 -310182 0 0 -310182

2021-09-21 TEESTA 12474 12619.564 0 145.564 259333 -4573 0 254760

2021-09-21 THEP 2097.1 1934.592 0 -162.508 -291210 -152 0 -291362

2021-09-21 TPTCL 2963.52 2082.593 0 -880.927 -1413513 0 0 -1413513

2021-09-21 TSTPP 20542.466 20112.654 0 -429.812 -650173 0 -39010 -689183

2021-09-21 VAE_ER -3255.135 0 0 3255.135 109389 0 0 109389

2021-09-21 WBSETCL -30960.363 -31836.255 0 -875.892 -2032806 -816102 -121968 -2970876

ERPC, KolkataDay-wise schedule, actual and Deviation charge statement

From 20-09-2021 to 26-09-2021

Date ConstituentsTotal Scheduled

(MWH)

Total Actual

(MWH)

Total AGC

(MWH)

Deviation

(MWH)

Deviation

Charge(Rs.)

Additional Deviation

Charge (Volume Limit)

in Rs.

Additional Deviation

Charge (Sign Change

Violation)

in Rs.

Total DSM

Charges

in Rs.

ERPC, KolkataDay-wise schedule, actual and Deviation charge statement

From 20-09-2021 to 26-09-2021

2021-09-22 APNRL 5904 5870.545 0 -33.455 -34982 0 0 -34982

2021-09-22 NVVN-BD -17502.53 -17457.891 0 44.639 189375 0 0 189375

2021-09-22 BARH 9982.66 9785.69 -50.618 -146.352 -357480 -181 0 -357661

2021-09-22 BARH SG1_INFIRM 0 10916.273 0 10916.273 16772834 0 0 16772834

2021-09-22 BSPHCL -106501.457 -107502.181 0 -1000.723 -3050633 -810058 -274557 -4135248

2021-09-22 BRBCL 6239.988 6335.852 0 95.864 264583 0 0 264583

2021-09-22 BRBCL_U4_INFIRM 0 -39.997 0 -39.997 -159060 0 0 -159060

2021-09-22 CHUZACHEN 2156.4 2192.822 0 36.422 84164 0 0 84164

2021-09-22 DARLIPALI 33683.75 33561.246 0 -122.504 -351685 0 -10551 -362236

2021-09-22 DIKCHU 1906.49 1917.455 0 10.965 36132 0 0 36132

2021-09-22 DVC 37094.136 37533.439 0 439.303 1428520 -94274 -42856 1291390

2021-09-22 NR -77257.783 -69320.563 0 7937.22 24134122 0 0 24134122

2021-09-22 NER 119.939 -16412.563 0 -16532.502 -65426101 0 0 -65426101

2021-09-22 SR -6221.303 -40645.795 0 -34424.492 -134924399 0 0 -134924399

2021-09-22 WR -50612.805 -9978.953 0 40633.852 158297386 0 0 158297386

2021-09-22 FSTPP - I & II 16160.474 16286.447 0 125.974 441259 0 0 441259

2021-09-22 FSTPP-III 7349.64 7417.952 0 68.312 219422 -2318 -6583 210521

2021-09-22 GMRKEL 14802.838 15040.218 0 237.381 872224 0 -52333 819891

2021-09-22 HVDC ALIPURDUAR -15.934 -26.558 0 -10.624 -41846 -1044 0 -42890

2021-09-22 HVDC SASARAM -21.031 -20.871 0 0.161 1103 -101 0 1002

2021-09-22 JUVNL -21772.116 -20921.873 0 850.244 3170427 -137364 -634085 2398978

2021-09-22 JITPL 24461.25 24497.891 0 36.641 127988 0 0 127988

2021-09-22 JORETHANG HEP 2279.567 2210.72 0 -68.847 -152425 0 0 -152425

2021-09-22 KHSTPP-I 14535.834 14295.1 0 -240.734 -547098 -19198 -32826 -599122

2021-09-22 KHSTPP-II 21102.295 20342.251 -533.714 -226.329 -578418 -22834 0 -601252

2021-09-22 MPL 19751.79 19062.909 -812.384 123.503 298996 -439 0 298557

2021-09-22 MTPS-II 3675.883 3625.864 0 -50.019 -118768 0 0 -118768

2021-09-22 NVVN-NEPAL 0 855.2 0 855.2 3038341 0 -273451 2764890

2021-09-22 NPGC 17904.283 17878.354 0 -25.928 103663 0 0 103663

2021-09-22 NPGC-INFIRM 0 -15.373 0 -15.373 -64445 0 0 -64445

2021-09-22 GRIDCO -31137.235 -31192.093 0 -54.857 448134 -281545 -13444 153145

2021-09-22 RANGIT 1443 1417.117 0 -25.883 -55415 -1418 0 -56833

2021-09-22 RONGNICHU HEP 2044.5 2034.432 0 -10.068 -4747 0 0 -4747

2021-09-22 SIKKIM -1381.265 -1443.28 0 -62.015 -148095 -40672 0 -188767

2021-09-22 TALCHER SOLAR 37.503 37.775 0 0.273 2464 0 0 2464

2021-09-22 TUL 27314.798 26988.218 0 -326.58 -178424 0 0 -178424

2021-09-22 TEESTA 12474 12616.836 -7.095 149.932 376003 0 0 376003

2021-09-22 THEP 2111.1 2030.368 0 -80.732 -175115 -7382 0 -182497

2021-09-22 TPTCL 2963.52 2016.296 0 -947.224 -2343446 -30356 0 -2373802

2021-09-22 TSTPP 21179.171 21112.248 0 -66.923 45784 -9432 -1374 34978

2021-09-22 VAE_ER -6158.428 0 0 6158.428 481917 -5879 0 476038

2021-09-22 WBSETCL -34558.83 -35654.147 0 -1095.317 -2925072 -522160 -263257 -3710489

2021-09-23 APNRL 5904 5802.473 0 -101.527 -129935 0 0 -129935

2021-09-23 NVVN-BD -17444.406 -17393.673 0 50.734 118943 0 0 118943

2021-09-23 BARH 12595.812 12097.405 -147.586 -350.82 -709222 0 0 -709222

2021-09-23 BARH SG1_INFIRM 0 11877.831 0 11877.831 17072874 0 0 17072874

2021-09-23 BSPHCL -101153.394 -103717.404 0 -2564.009 -8306893 -1675511 -2492068 -12474472

2021-09-23 BRBCL 6000 6175.432 0 175.432 419081 0 0 419081

2021-09-23 BRBCL_U4_INFIRM 0 -37.904 0 -37.904 -116875 0 0 -116875

2021-09-23 CHUZACHEN 1940.6 1964.89 0 24.29 55441 0 0 55441

2021-09-23 DARLIPALI 30997.5 30925.89 0 -71.61 -174504 0 0 -174504

2021-09-23 DIKCHU 1831.28 1821.727 0 -9.553 -31813 0 0 -31813

2021-09-23 DVC 36263.667 36304.889 0 41.222 -217766 -9061 -6533 -233360

2021-09-23 NR -65742.731 -56896.704 0 8846.027 19611925 0 0 19611925

2021-09-23 NER -1997.175 -19231.79 0 -17234.615 -53155304 0 0 -53155304

2021-09-23 SR 2807.728 -36863.802 0 -39671.53 -118386514 0 0 -118386514

2021-09-23 WR -57340.612 -9142.694 0 48197.918 147661145 0 0 147661145

2021-09-23 FSTPP - I & II 17759.074 17781.482 0 22.409 3517 0 0 3517

2021-09-23 FSTPP-III 8412.315 8161.572 0 -250.744 -518097 -425 -46629 -565151

2021-09-23 GMRKEL 13320.838 13585.163 0 264.326 967515 0 -29025 938490

2021-09-23 HVDC ALIPURDUAR -15.934 -27.265 0 -11.33 -34051 0 0 -34051

2021-09-23 HVDC SASARAM -20.962 -20.589 0 0.373 1280 0 0 1280

2021-09-23 JUVNL -21149.166 -20426.486 0 722.68 2046386 -2341 -613916 1430129

2021-09-23 JITPL 24020 23996 0 -24 -77396 0 -2322 -79718

2021-09-23 JORETHANG HEP 2304 2110.08 0 -193.92 -371075 0 0 -371075

2021-09-23 KHSTPP-I 17664.218 16928.209 0 -736.009 -1584761 0 -95086 -1679847

2021-09-23 KHSTPP-II 22500.084 21430.362 -815.163 -254.559 -476857 0 -14306 -491163

2021-09-23 MPL 22997.783 21543.345 -1480.068 25.631 164261 0 0 164261

2021-09-23 MTPS-II 4160.539 4055.708 0 -104.831 -214483 0 0 -214483

2021-09-23 NVVN-NEPAL 0 745.527 0 745.527 2148795 0 -257855 1890940

2021-09-23 NPGC 18000 17833.443 0 -166.557 -113106 0 0 -113106

2021-09-23 NPGC-INFIRM 0 -15.953 0 -15.953 -46760 0 0 -46760

2021-09-23 GRIDCO -32078.694 -33168.813 0 -1090.118 -2701232 -282356 -81037 -3064625

2021-09-23 RANGIT 1215 1247.828 0 32.828 87579 0 0 87579

2021-09-23 RONGNICHU HEP 1882 1915.36 0 33.36 48141 0 0 48141

2021-09-23 SIKKIM -1415.61 -1635.456 0 -219.846 -787399 0 0 -787399

2021-09-23 TALCHER SOLAR 32.125 29.618 0 -2.507 -23438 0 0 -23438

2021-09-23 TUL 25268.748 24824.8 0 -443.948 -203851 0 0 -203851

2021-09-23 TEESTA 12016.5 12205.345 -23.49 212.335 455318 0 0 455318

2021-09-23 THEP 1985 1674.176 0 -310.824 -643107 0 0 -643107

2021-09-23 TPTCL 2963.52 1971.628 0 -991.892 -2172129 0 0 -2172129

2021-09-23 TSTPP 11861.994 11708.357 0 -153.637 -310423 -22039 -9313 -341775

2021-09-23 VAE_ER -2950.405 0 0 2950.405 124610 0 0 124610

2021-09-23 WBSETCL -41194.758 -43794.136 0 -2599.378 -7258146 -1611068 -1088722 -9957936

Date ConstituentsTotal Scheduled

(MWH)

Total Actual

(MWH)

Total AGC

(MWH)

Deviation

(MWH)

Deviation

Charge(Rs.)

Additional Deviation

Charge (Volume Limit)

in Rs.

Additional Deviation

Charge (Sign Change

Violation)

in Rs.

Total DSM

Charges

in Rs.

ERPC, KolkataDay-wise schedule, actual and Deviation charge statement

From 20-09-2021 to 26-09-2021

2021-09-24 APNRL 5904 5885.6 0 -18.4 -44357 -2176 0 -46533

2021-09-24 NVVN-BD -17449.558 -17324.218 0 125.34 722456 0 0 722456

2021-09-24 BARH 12183.647 11909.062 -70.748 -203.837 -560476 -27777 0 -588253

2021-09-24 BARH SG1_INFIRM 0 6755.192 0 6755.192 10436071 0 0 10436071

2021-09-24 BSPHCL -107455.075 -109954.087 0 -2499.011 -15268786 -3473780 -2290318 -21032884

2021-09-24 BRBCL 6190.009 6457.179 0 267.17 757876 0 -22736 735140

2021-09-24 BRBCL_U4_INFIRM 0 -36.524 0 -36.524 -214282 0 0 -214282

2021-09-24 CHUZACHEN 1840.8 1868.448 0 27.648 81298 0 0 81298

2021-09-24 DARLIPALI 32370 32289.398 0 -80.602 -218329 -15513 0 -233842

2021-09-24 DIKCHU 1805.37 1717.727 0 -87.643 -258503 -5717 0 -264220

2021-09-24 DVC 37303.964 38530.506 0 1226.542 6914486 0 -829738 6084748

2021-09-24 NR -67139.26 -33313.383 0 33825.877 199570938 0 0 199570938

2021-09-24 NER -2608.58 -21455.712 0 -18847.132 -112052669 0 0 -112052669

2021-09-24 SR -14370.679 -40083.649 0 -25712.97 -147188479 0 0 -147188479

2021-09-24 WR -25047.118 -11462.156 0 13584.962 76452258 0 0 76452258

2021-09-24 FSTPP - I & II 17901.959 18023.231 0 121.272 375126 -4734 0 370392

2021-09-24 FSTPP-III 8534.082 8203.714 0 -330.368 -980341 -206957 -147051 -1334349

2021-09-24 GMRKEL 13767.625 14271.636 0 504.011 1486350 0 -89181 1397169

2021-09-24 HVDC ALIPURDUAR -15.934 -26.717 0 -10.783 -63228 -6397 0 -69625

2021-09-24 HVDC SASARAM -20.716 -20.197 0 0.519 3114 -648 0 2466

2021-09-24 JUVNL -21248.966 -21202.536 0 46.431 176332 -522710 -15870 -362248

2021-09-24 JITPL 24129.188 24123.709 0 -5.479 -8555 -1928 0 -10483

2021-09-24 JORETHANG HEP 2304 2084.672 0 -219.328 -632820 -40535 0 -673355

2021-09-24 KHSTPP-I 17889.785 17265.871 0 -623.914 -1799559 -88393 -53987 -1941939

2021-09-24 KHSTPP-II 22500.058 21822.735 -563.627 -113.695 -333779 -26644 0 -360423

2021-09-24 MPL 23615.865 22574.363 -936.19 -105.311 -335725 -114504 0 -450229

2021-09-24 MTPS-II 4258.902 4210.304 0 -48.598 -139396 -2965 0 -142361

2021-09-24 NVVN-NEPAL 0 657.164 0 657.164 3352095 -233599 -201126 2917370

2021-09-24 NPGC 19668.75 19727.149 0 58.399 249702 0 0 249702

2021-09-24 NPGC-INFIRM 0 -15.84 0 -15.84 -93187 0 0 -93187

2021-09-24 GRIDCO -34208.884 -34082.554 0 126.33 1784145 -374147 0 1409998

2021-09-24 RANGIT 1265.5 1254.373 0 -11.127 -34253 -20669 0 -54922

2021-09-24 RONGNICHU HEP 2133.5 2148.544 0 15.044 43856 -5449 0 38407

2021-09-24 SIKKIM -1363.606 -1456.633 0 -93.027 -734180 -323448 -22025 -1079653

2021-09-24 TALCHER SOLAR 42.978 43.616 0 0.638 5211 0 0 5211

2021-09-24 TUL 25054.3 25535.345 0 481.045 1571251 0 0 1571251

2021-09-24 TEESTA 11708.25 11914.109 -5.064 210.923 600295 0 0 600295

2021-09-24 THEP 1886.59 1545.28 0 -341.31 -989746 -21758 0 -1011504

2021-09-24 TPTCL 2963.52 1912.277 0 -1051.243 -3044351 -204677 0 -3249028

2021-09-24 TSTPP 10872.24 10928.839 0 56.599 164944 0 0 164944

2021-09-24 VAE_ER -6256.373 0 0 6256.373 -521540 -1031634 0 -1553174

2021-09-24 WBSETCL -52154.647 -54176.27 0 -2021.624 -11172325 -4719840 -1340679 -17232844

2021-09-25 APNRL 5904 5765.164 0 -138.836 -175888 0 0 -175888

2021-09-25 NVVN-BD -17508.843 -17408.654 0 100.189 320404 -7492 0 312912

2021-09-25 BARH 13427.405 12974.64 -224.525 -228.24 -457551 0 0 -457551

2021-09-25 BARH SG1_INFIRM 0 11989.941 0 11989.941 16403147 0 0 16403147

2021-09-25 BSPHCL -112889.629 -115359.933 0 -2470.304 -9889619 -672546 -2472405 -13034570

2021-09-25 BRBCL 6480 6488.629 0 8.629 133543 0 0 133543

2021-09-25 BRBCL_U4_INFIRM 0 -37.648 0 -37.648 -131091 0 0 -131091

2021-09-25 CHUZACHEN 2054.88 2068.589 0 13.709 72071 -6454 0 65617

2021-09-25 DARLIPALI 31787.5 31853.209 0 65.709 256189 0 0 256189

2021-09-25 DIKCHU 1852.1 1773.091 0 -79.009 -198418 0 0 -198418

2021-09-25 DVC 38352.328 38963.399 0 611.072 2203343 -160732 -66100 1976511

2021-09-25 NR -65263.617 -43472.98 0 21790.637 79584372 0 0 79584372

2021-09-25 NER -4263.184 -21621.952 0 -17358.768 -61177960 0 0 -61177960

2021-09-25 SR -5595.787 -34430.936 0 -28835.149 -103497195 0 0 -103497195

2021-09-25 WR -24517.337 -1361.895 0 23155.443 76145500 0 0 76145500

2021-09-25 FSTPP - I & II 20820.728 20685.003 0 -135.725 -253709 -2206 0 -255915

2021-09-25 FSTPP-III 9875.551 9374.088 0 -501.463 -1180833 -107 -236167 -1417107

2021-09-25 GMRKEL 14309.775 14105.818 0 -203.957 -141584 -49464 -8495 -199543

2021-09-25 HVDC ALIPURDUAR -15.934 -26.519 0 -10.585 -35591 0 0 -35591

2021-09-25 HVDC SASARAM -20.361 -20.664 0 -0.303 -1317 0 0 -1317

2021-09-25 JUVNL -23027.311 -23382.272 0 -354.962 -1510225 -49045 -90614 -1649884

2021-09-25 JITPL 13348.125 13107.709 0 -240.416 -550614 0 0 -550614

2021-09-25 JORETHANG HEP 2304 2154.048 0 -149.952 -304530 0 0 -304530

2021-09-25 KHSTPP-I 17292.366 16775.113 0 -517.253 -1165196 -18901 0 -1184097

2021-09-25 KHSTPP-II 22495.921 21512.693 -863.346 -119.882 -201901 -1869 0 -203770

2021-09-25 MPL 23462.805 21807.636 -1710.49 55.321 338266 -2904 0 335362

2021-09-25 MTPS-II 4245.201 4162.628 0 -82.573 -164918 0 0 -164918

2021-09-25 NVVN-NEPAL 0 903.709 0 903.709 2840557 -50250 -568111 2222196

2021-09-25 NPGC 20450 20115.76 0 -334.24 -457170 0 -13715 -470885

2021-09-25 NPGC-INFIRM 0 -16.96 0 -16.96 -50897 0 0 -50897

2021-09-25 GRIDCO -33162.466 -33343.865 0 -181.399 -413521 -67846 0 -481367

2021-09-25 RANGIT 1404 1402.158 0 -1.842 -756 -395 0 -1151

2021-09-25 RONGNICHU HEP 2173.5 2212.064 0 38.564 150105 0 0 150105

2021-09-25 SIKKIM -1473.726 -1505.977 0 -32.251 16736 -4280 0 12456

2021-09-25 TALCHER SOLAR 43.628 41.096 0 -2.532 -29949 0 0 -29949

2021-09-25 TUL 27527.625 27115.418 0 -412.207 48410 0 0 48410

2021-09-25 TEESTA 12486 12740.036 -21.784 275.82 610209 -9904 0 600305

2021-09-25 THEP 2511.45 2477.792 0 -33.658 -53126 -345 0 -53471

2021-09-25 TPTCL 2963.52 1863.198 0 -1100.322 -2408621 -166 0 -2408787

2021-09-25 TSTPP 16721.75 16550.389 0 -171.361 -322150 0 -9664 -331814

2021-09-25 VAE_ER -1845.603 0 0 1845.603 42613 0 0 42613

2021-09-25 WBSETCL -57767.505 -60443.61 0 -2676.105 -10021645 -1552990 -2004329 -13578964

Date ConstituentsTotal Scheduled

(MWH)

Total Actual

(MWH)

Total AGC

(MWH)

Deviation

(MWH)

Deviation

Charge(Rs.)

Additional Deviation

Charge (Volume Limit)

in Rs.

Additional Deviation

Charge (Sign Change

Violation)

in Rs.

Total DSM

Charges

in Rs.

ERPC, KolkataDay-wise schedule, actual and Deviation charge statement

From 20-09-2021 to 26-09-2021

2021-09-26 APNRL 5904 5830.4 0 -73.6 -134191 0 0 -134191

2021-09-26 NVVN-BD -17083.769 -16285.963 0 797.805 1316738 0 -39502 1277236

2021-09-26 BARH 11447.524 11055.316 -81.82 -310.387 -744938 -8257 0 -753195

2021-09-26 BARH SG1_INFIRM 0 8342.465 0 8342.465 13669188 0 0 13669188

2021-09-26 BSPHCL -116338.741 -119054.269 0 -2715.528 -9453632 -790405 -1890726 -12134763

2021-09-26 BRBCL 6759.819 6970.209 0 210.39 567215 0 -17016 550199

2021-09-26 BRBCL_U4_INFIRM 0 -36.827 0 -36.827 -132935 0 0 -132935

2021-09-26 CHUZACHEN 1782.08 1808.035 0 25.955 72696 0 0 72696

2021-09-26 DARLIPALI 31320 31312.563 0 -7.437 46515 0 -1395 45120

2021-09-26 DIKCHU 1722.28 1664.636 0 -57.644 -114530 0 0 -114530

2021-09-26 DVC 41876.033 42959.598 0 1083.565 3358839 -1357 -403061 2954421

2021-09-26 NR -69521.94 -45640.336 0 23881.604 85484974 0 0 85484974

2021-09-26 NER -1117.621 -17525.654 0 -16408.034 -59198829 0 0 -59198829

2021-09-26 SR 11039.058 -33595.186 0 -44634.244 -157327861 0 0 -157327861

2021-09-26 WR -47471.197 -4703.368 0 42767.829 147925578 0 0 147925578

2021-09-26 FSTPP - I & II 17685.616 17602.831 0 -82.785 -127186 0 0 -127186

2021-09-26 FSTPP-III 8584.423 8266.842 0 -317.581 -694360 0 -41662 -736022

2021-09-26 GMRKEL 15525.1 15663.127 0 138.027 394973 0 0 394973

2021-09-26 HVDC ALIPURDUAR -15.934 -26.308 0 -10.374 -37128 0 0 -37128

2021-09-26 HVDC SASARAM -20.593 -20.292 0 0.301 1564 0 0 1564

2021-09-26 JUVNL -22790.227 -22579.708 0 210.519 -454140 -1928 -40873 -496941

2021-09-26 JITPL 13431.375 13263.927 0 -167.448 -378665 0 0 -378665

2021-09-26 JORETHANG HEP 2306.35 2051.84 0 -254.51 -637104 0 0 -637104

2021-09-26 KHSTPP-I 15461.937 15176.783 0 -285.154 -648882 0 0 -648882

2021-09-26 KHSTPP-II 20955.428 20296.001 -615.879 -43.547 -75927 0 0 -75927

2021-09-26 MPL 20922.533 19965.818 -1095.55 138.836 348877 0 0 348877

2021-09-26 MTPS-II 3830.81 3709.912 0 -120.898 -293058 0 0 -293058

2021-09-26 NVVN-NEPAL 0 786.255 0 786.255 2546163 0 -305540 2240623

2021-09-26 NPGC 20318.688 20296.381 0 -22.307 134511 0 0 134511

2021-09-26 NPGC-INFIRM 0 -19.218 0 -19.218 -71818 0 0 -71818

2021-09-26 GRIDCO -33487.228 -33327.827 0 159.401 -1014714 -62660 -60883 -1138257

2021-09-26 RANGIT 1404 1406.344 0 2.344 12853 0 0 12853

2021-09-26 RONGNICHU HEP 1859 1846.976 0 -12.024 1037 0 0 1037

2021-09-26 SIKKIM -1205.697 -1233.027 0 -27.33 -47818 0 0 -47818

2021-09-26 TALCHER SOLAR 31.76 27.794 0 -3.966 -39918 0 0 -39918

2021-09-26 TUL 27412.8 27147.491 0 -265.309 -149467 0 0 -149467

2021-09-26 TEESTA 12486 12697.964 -69.278 281.241 732821 0 0 732821

2021-09-26 THEP 2462.5 2396.384 0 -66.116 -153592 0 0 -153592

2021-09-26 TPTCL 2963.52 1835.709 0 -1127.811 -2855663 -4774 0 -2860437

2021-09-26 TSTPP 21567.184 21465.277 0 -101.907 -223175 0 0 -223175

2021-09-26 VAE_ER -10922.543 0 0 10922.543 619494 -1521 0 617973

2021-09-26 WBSETCL -52329.731 -53602.534 0 -1272.803 -3952726 -270477 -355745 -4578948

ConstituentsTotal Scheduled

(MWH)

Total Actual

(MWH)

Total AGC

(MWH)

Deviation

(MWH)

Deviation

Charge(Rs.)

Additional Deviation

Charge (Volume Limit)

in Rs.

Additional Deviation

Charge (Sign Change

Violation)

in Rs.

Total DSM

Charges

in Rs.

Week total APNRL 41328 40741.963 0 -586.037 -794209 -4656 0 -798865

Week total NVVN-BD -122006.986 -120743.126 0 1263.86 3133052 -13439 -39502.14 3080111

Week total BARH 85736.028 83499.875 -575.297 -1660.855 -3415655 -46631 0 -3462286

Week total BARH SG1_INFIRM 0 69950.778 0 69950.778 100338763 0 0 100338763

Week total BSPHCL -767412.539 -781406.889 0 -13994.35 -56345740 -8153423 -10143730.39 -74642893

Week total BRBCL 45394.815 46313.641 0 918.826 2544203 0 -39752.73 2504450

Week total BRBCL_U4_INFIRM 0 -297.932 0 -297.932 -1267296 0 0 -1267296

Week total CHUKHA 39885.2 51431.973 0 11546.773 29444270 0 0 29444270

Week total CHUZACHEN 13910.88 14109.974 0 199.094 530947 -8332 0 522615

Week total DARLIPALI 225385 225130.182 0 -254.818 -225588 -21337 -11946 -258871

Week total DIKCHU 13407.4 12933.545 0 -473.855 -1129314 -6068 0 -1135382

Week total DVC 271715.522 274929.751 0 3214.229 12492352 -382956 -1452088.99 10657307

Week total NR -502736.722 -407123.157 0 95613.565 387522704 0 0 387522704

Week total NER 254.42 -122163.167 0 -122417.588 -481981435 0 0 -481981435

Week total SR -50004.27 -285942.96 0 -235938.69 -871159866 0 0 -871159866

Week total WR -301515.235 -36997.821 0 264517.415 945780953 0 0 945780953

Week total FSTPP - I & II 127976.745 127630.12 0 -346.625 -568838 -23337 -75130.74 -667306

Week total FSTPP-III 60058.634 58279.406 0 -1779.228 -4193942 -227516 -770804.41 -5192262

Week total GMRKEL 103226.175 103892.072 0 665.897 3551793 -49464 -179034.96 3323294

Week total HVDC ALIPURDUAR -111.154 -187.507 0 -76.353 -294918 -9533 0 -304451

Week total HVDC SASARAM -144.894 -144.499 0 0.395 2553 -1035 0 1518

Week total JUVNL -155345.84 -153758.46 0 1587.38 2713570 -1216140 -1672454.91 -175025

Week total JITPL 148307.188 147908.798 0 -398.389 -771517 -5162 -2321.89 -779001

Week total JORETHANG HEP 16251.767 15062.352 0 -1189.415 -2747615 -45280 0 -2792895

Week total KHSTPP-I 116560.766 113423.211 0 -3137.555 -7065996 -126492 -181898.3 -7374386

Week total KHSTPP-II 152867.356 147084.957 -4692.316 -1090.083 -2310495 -56631 -14305.72 -2381432

Week total KURICHU 10099.25 11814.822 0 1715.572 3637013 0 0 3637013

Week total MANGDECHU 93834.65 94611.781 0 777.131 3201780 0 0 3201780

Week total MPL 155682.375 146971.889 -9190.907 480.421 1402777 -148320 0 1254457

Week total MTPS-II 28308.44 27701.924 0 -606.516 -1369698 -15952 0 -1385650

Week total NVVN-NEPAL 0 5683.636 0 5683.636 19071565 -340710 -2376399.94 16354455

Week total NPGC 137152.358 136359.958 0 -792.4 204402 0 -13715.1 190687

Week total NPGC-INFIRM 0 -214.178 0 -214.178 -873400 0 0 -873400

Week total GRIDCO -232194.62 -234424.64 0 -2230.021 -5461022 -1980217 -185371.36 -7626610

Week total RANGIT 9623.5 9621.152 0 -2.348 36113 -22482 0 13631

Week total RONGNICHU HEP 14255.5 14300.768 0 45.268 198507 -5449 0 193058

Week total SIKKIM -9715.965 -10391.856 0 -675.891 -2726200 -426340 -22025.4 -3174565

Week total TALCHER SOLAR 239.498 227.05 0 -12.448 -131412 0 0 -131412

Week total TALA 133650.8 107726.228 0 -25924.572 -54960092 0 0 -54960092

Week total TUL 190125.765 187878.762 0 -2247.003 484548 0 0 484548

Week total TEESTA 86118.75 87405.236 -155.933 1442.419 3464534 -20318 0 3444216

Week total THEP 15226.74 13931.264 0 -1295.476 -3055257 -51504 0 -3106761

Week total TPTCL 20744.64 13851.235 0 -6893.405 -16290759 -292727 0 -16583486

Week total TSTPP 124335.056 123349.065 0 -985.991 -1606052 -31470 -68686.86 -1706209

Week total VAE_ER -31339.983 0 0 31339.983 771485 -1094294 0 -322809

Week total WBSETCL -311122.7 -321337.95 0 -10215.25 -36176224 -9963611 -5245890.13 -51385725

Energy:(+ve) means injection, (-ve) means drawal.

Deviation Charge: (+ve) means receivable, (-ve) means payable

SUMMARY OF WEEKLY DEVIATION CHARGES : 20-09-2021 to 26-09-2021

LEGEND:

Sr.

No

RRAS

Provider

Energy

Scheduled

(MWH)

Fixed Charges

(Rs) (X)

Variable Charges

(Rs) (Y)

Markup as per

CERC Order (Rs) (Z)

Total Charges

(Rs) (X+Y+Z)

1 BARH 6.8325 12572 20579 3416 36567

2 BRBCL 36.105 90263 87519 18053 195835

3 Darlipali_NTPC 0 0 0 0 0

4 FSTPP I & II 301.085 248094 942697 150543 1341334

5 FSTPP-III 40.6525 60654 124966 20326 205946

6 KHSTPP-I 176.17 184626 473721 88085 746432

7 KHSTPP-II 641.865 698991 1636756 320933 2656680

8 MPL 446.6275 635551 1200535 223314 2059400

9 MTPS-II 229.9125 628581 607659 114956 1351196

10 NPGC 46.97 111366 97979 23485 232830

11 TSTPP-I 3.2725 3138 5868 1636 10642

Total 1929.4925 2673836 5198279 964746 8836861

Sr.

No

RRAS

Provider

Energy

Scheduled

(MWH)

Variable Charges

(Rs) (X)

Variable Charges

Payable to Pool

(Rs) (0.75*X)

1 BARH 11088.945 33399902 25049927

2 BRBCL 102.1275 247557 185668

3 Darlipali_NTPC 0 0 0

4 FSTPP I & II 10403.9175 32574666 24430999

5 FSTPP-III 4161.535 12792559 9594419

6 KHSTPP-I 2090.255 5620696 4215522

7 KHSTPP-II 651.89 1662320 1246740

8 MPL 3120.6425 8388287 6291215

9 MTPS-II 430.545 1137930 853448

10 NPGC 94.045 196178 147133

11 TSTPP-I 30.9375 55471 41603

Total 32174.84 96075566 72056674

EASTERN REGIONAL POWER COMMITTEE, KOLKATARRAS Settlement Report from 20-09-2021 to 26-09-2021

A. Payments to the RRAS Provider(s) from the DSM pool for UP Regulation :

B. Payments by the RRAS Provider(s) to the DSM pool for DOWN Regulation :

SUPERINTENDING ENINEER

Sr.

No

RRAS

Provider

Energy

Scheduled

(MWH)

Fixed Charges

To Be Refunded

(Rs)

To Beneficiary

Name

995 HVDC_APD

37 JUVNL

11540 TS TRANSCO

65878 Bihar Railways

5178 HARYANA

5238 PUNJAB

6589 RAJASTHAN

7380 Karnataka Railways

964 BSPHCL

2814 Delhi

85794 Gujarat

9998 HARYANA

4123 JUVNL

17625 ODISHA Solar

25877 Tamilnadu

1891 TS TRANSCO

19552 UP

76235 WBSETCL

3221 WB Solar

26218 Gujarat

24307 GRIDCO

4505 ODISHA Solar

785 TS TRANSCO

4462 WBSETCL

377 WB Solar

7809 Delhi

65110 HARYANA

66 Nagaland

8068 ODISHA Solar

19493 RAJASTHAN

2764 Tamilnadu

13 TS TRANSCO

81304 UP

4335 Delhi

169970 HARYANA

3936 HP

2170 JUVNL

11461 GRIDCO

388 ODISHA Solar

192121 PUNJAB

72580 RAJASTHAN

189314 UP

52715 UTTARAKHAND

3

4

5

6

BARH 6.83251

BRBCL 36.1052

FSTPP I & II 301.085

FSTPP-III 40.6525

KHSTPP-I 176.17

KHSTPP-II 641.865

C. Reimbursement of Fixed Charges by RRAS Provider to the Original Beneficiaries:

SUPERINTENDING ENINEER

Sr.

No

RRAS

Provider

Energy

Scheduled

(MWH)

Fixed Charges

To Be Refunded

(Rs)

To Beneficiary

Name

624438 DVC

11114 WBSEDCL

34680 DVC

593902 GRIDCO

29128 JUVNL

82238 UP

10 TSTPP-I 3.2725 3138 DVC

Total 1929.4925 2673836

8

9

7 446.6275

MTPS-II 229.9125

NPGC 46.97

E) For the purpose of refund of Fixed Charges during Regulation Up service, the total Fixed charges received by the RRAS provider from DSM Pool

Account has been apportioned in the ratio of the quantum surrendered by the original beneficiaries.

MPL

Notes :

A) RRAS settlement account for the week 20-09-2021 to 26-09-2021 has been prepared as per the detailed procedure for Ancillary Services

Operation as approved by CERC.

B) Fixed Charges and Variable Charges for RRAS providers have been calculated as per the rates furnished by the respective RRAS providers in

Format AS-I and the same published in ERPC website as format AS-3.

C) Mark Up rate for Regulation Up service has been considered at 50paise/KWh as per CERC order on petition no This is as per Clause 13.6 of the

Detailed Procedure for Ancillary Services Operation approved by CERC.01/SM/2016 dated 29.02.2016.

D) Quantum of Energy scheduled to/from VAE (Virtual Ancillary Entity) from/to concerned RRAS provider during Regulation Up/Regulation Down

service has been considered as per the data furnished by ERLDC.

SUPERINTENDING ENINEER

Sr.

No

AGC

Provider

UP Regulation

due to AGC (MWh)

Down Regulation

due to AGC (MWh)

Net Energy

(MWh)

Variable

Charges (Rs.)

Markup Charges as

per CERC Order (Rs.)

Total Charges

(Rs.)

1 BARH 239.9144 815.2303 -575.3159 -1732852 527572 -1205280

2 KHSTPP-II 178.3055 4870.6213 -4692.3158 -11965409 2524463 -9440946

3 MPL 500.9406 9691.8462 -9190.9056 -24705154 5096393 -19608761

4 Teesta_V 0 155.9308 -155.9308 -181347 77965 -103382

Total 919.1605 15533.6286 -14614.4681 -38584762 8226393 -30358369

B) AGC settlement account for the week 20-09-2021 to 26-09-2021 has been prepared based on the CERC order inpetition No.79/RC/2017, dated 06.12.2017.

C) The markup rate has been calculated at the rate of 50 Paise/Kwh for Up & Down regulation.

D) Variable Charges for AGC provider has been calculated as per the rate furnished by the respective RRAS providers in Format AS-I and the same published in ERPC website as

format AS-3.

EASTERN REGIONAL POWER COMMITTEE, KOLKATAAGC Settlement Account by ERPC from 20-09-2021 to 26-09-2021

Payments to the AGC Provider(s) from the DSM pool

Notes :

A) (+) means payable from DSM Pool to AGC provider. (-) means payable to DSM Pool by AGC provider.

SUPERINTENDING ENGINEER