9
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12, 2015 Raymond Won Committee Chair Office of Science, U.S. Department of Energy http://www.science.doe.gov/opa/

OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

Embed Size (px)

DESCRIPTION

OFFICE OF SCIENCE 3 Charge Questions 1.At this stage of the project, is the project scope, if successfully completed, sufficient to achieve the project’s key performance parameters? 2.Is the bid solicitation package for Phase B scope consistent with the approved Project Execution Plan? Are bids or quotes already in hand? If so, are the base bids or quotes within the cost estimates, and consistent with the approved cost and schedule performance baseline? 3.Are cost, schedule, and scope contingency adequate to address the remaining risks? Are project risks being actively managed? 4.Are environment, safety and health requirements properly addressed? Are Integrated Safety Management principles being followed? 5.Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

Citation preview

Page 1: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

1

Closeout Report on theDOE/SC CD-3b Review of the

Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory

August 11-12, 2015

Raymond WonCommittee Chair

Office of Science, U.S. Department of Energyhttp://www.science.doe.gov/opa/

Page 2: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

2

SC Organization

Page 3: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

3

Charge Questions

1. At this stage of the project, is the project scope, if successfully completed, sufficient to achieve the project’s key performance parameters?

2. Is the bid solicitation package for Phase B scope consistent with the approved Project Execution Plan? Are bids or quotes already in hand? If so, are the base bids or quotes within the cost estimates, and consistent with the approved cost and schedule performance baseline?

3. Are cost, schedule, and scope contingency adequate to address the remaining risks? Are project risks being actively managed?

4. Are environment, safety and health requirements properly addressed? Are Integrated Safety Management principles being followed?

5. Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

Page 4: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCEReview Committee Participants

4

Raymond Won, DOE/SC, ChairpersonObservers Stephanie Short, DOE/SC David Michlewicz, DOE/SC Steve Neus, DOE/FSO

Review Committee Subcommittee 1: Technical *Shane Wells, SLAC Michael Finder, ANL Subcommittee 2: ES&H *Betsy Dunn, ANL Neil Gerrish, PPPL Subcommittee 3: Cost and Schedule *Stephen Langish, PPPL Laurie Casarole, BNL Jesse Saldivar, DOE/SSO Subcommittee 4: Management *Gary Bloom, ORNL Teresa Danforth, TJNAF Carolyn Galayda, SLAC *Lead

Page 5: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

5

2. Technical S. Wells, SLAC / Subcommittee 1

• Findings• Comments• Recommendations

1. At this stage of the project, is the project scope, if successfully completed, sufficient to achieve the project’s key performance parameters?

2. Is the bid solicitation package for Phase B scope consistent with the approved Project Execution Plan? Are bids or quotes already in hand? If so, are the base bids or quotes within the cost estimates, and consistent with the approved cost and schedule performance baseline?

5. Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

Page 6: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

6

3. Environment, Safety and HealthB. Dunn, ANL / Subcommittee 2

4. Are environment, safety and health requirements properly addressed? Are Integrated Safety Management principles being followed?

5. Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

• Findings• Comments• Recommendations

Page 7: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

7

4. Cost and ScheduleS. Langish, PPPL / Subcommittee 3

1. At this stage of the project, is the project scope, if successfully completed, sufficient to achieve the project’s key performance parameters?

2. Is the bid solicitation package for Phase B scope consistent with the approved Project Execution Plan? Are bids or quotes already in hand? If so, are the base bids or quotes within the cost estimates, and consistent with the approved cost and schedule performance baseline?

3. Are cost, schedule, and scope contingency adequate to address the remaining risks? Are project risks being actively managed?

5. Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

• Findings• Comments• Recommendations

Page 8: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

8

4. Cost and ScheduleS. Langish, PPPL / Subcommittee 3

PROJECT STATUS

Project Type MIE / Line Item / Cooperative Agreement

CD-1 Planned: Actual:

CD-2 Planned: Actual:

CD-3 Planned: Actual:

CD-4 Planned: Actual:

TPC Percent Complete Planned: _____% Actual: _____%

TPC Cost to Date      

TPC Committed to Date  

TPC  

TEC  

Contingency Cost (w/Mgmt Reserve) $ _____% to go

Contingency Schedule on CD-4b ______months _____%

CPI Cumulative     SPI Cumulative  

Page 9: OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,

OFFICE OF

SCIENCE

9

5. Management G. Bloom, ORNL / Subcommittee 4

1. At this stage of the project, is the project scope, if successfully completed, sufficient to achieve the project’s key performance parameters?

2. Is the bid solicitation package for Phase B scope consistent with the approved Project Execution Plan? Are bids or quotes already in hand? If so, are the base bids or quotes within the cost estimates, and consistent with the approved cost and schedule performance baseline?

5. Has the Integrated Project Team responded appropriately to recommendations from prior reviews including those applicable to the proposed Phase B work?

• Findings• Comments• Recommendations