33
Operational decommissioning experience in Germany 9 th Edition of the International Summer School on Nuclear Decommissioning and Waste Management Dr. Przemyslaw Imielski Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) gGmbH JRC Ispra (Italy), 13 September 2017

Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Operational decommissioning experience in Germany

9th Edition of the International Summer School on Nuclear Decommissioning and Waste Management

Dr. Przemyslaw Imielski Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) gGmbH

JRC Ispra (Italy), 13 September 2017

Page 2: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Outline

2

Analysing the current nuclear situation in Germany

• German phase-out decision

• Overview on decommissioning projects in Germany

• The German regulatory system

Lessons learned from past and present decommissioning projects in Germany

• Decommissioning experiences

Phased approach

Industrial development at the site

Large component removal

Waste management

Examining the current challenges (and future opportunities)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 3: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

German Phase-out Decision

3

After the events at Fukushima Daiichi in March 211 the German government decided to

• “end the use of nuclear energy for the commercial generation of electricity at the earliest possible time – by gradually phasing out.”

This decision resulted in an Amendment of the German Atomic Energy Act of July 31st, 2011

• Withdrawing the authorisation to operate an installation for the fission of nuclear fuel for the commercial production of electricity for the seven oldest NPPs and NPP Krümmel on August 6th, 2011 and

• Setting end-dates for the authorisation for the remaining 9 NPPs on a step-by-step-basis until 2022 at the latest

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 4: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

German Phase-out Decision

4

Timetable for latest shutdown of commercial reactors in operation

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Name Abbrev. Reactor type Power MWe Date of final shut down

Gundremmingen B KRB-II-B BWR 1344 31.12.2017

Philippsburg 2 KKP 2 PWR 1468 31.12.2019

Grohnde KWG PWR 1430 31.12.2021

Gundremmingen C KRB-II-C BWR 1344 31.12.2021

Brokdorf KBR PWR 1480 31.12.2021

Isar 2 KKI 2 PWR 1485 31.12.2022

Emsland KKE PWR 1400 31.12.2022

Neckarwestheim 2 GKN 2 PWR 1400 31.12.2022

Page 5: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

5

Decommissioning of nuclear facilities in Germany experiences since 1970th

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Commercial / Prototype Reactor under decommissioning

Commercial / Prototype Reactor decommissioning completed

KWB

Page 6: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

6

Decommissioning of nuclear facilities in Germany experiences since 1970th

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Research Reactor under decommissioning

Research Reactor decommissioning completed

Page 7: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

7

Decommissioning of nuclear facilities in Germany experiences since 1970th

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Nuclear Fuel Cycle Facility under decommissioning

Nuclear Fuel Cycle Facility decommissioning completed

Page 8: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

8

Past and current decommissioning projects of prototype or commercial reactors

• Total: 24

• Removed: 3

• Under dismantling: 20

• Safe enclosure: 1

• Reactor types

PWR

BWR

Fast Breeder

High Temperature Gas Cooled

Heavy Water Gas Cooled

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© Forschungszentrum Karlsruhe

Page 9: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

9

Past and current decommissioning projects of prototype or commercial reactors

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Name Abbrev. Reactor type Power MWe Decom. started Strategy/Decom. finalised

Niederaichbach KKN DRR 106 1975 RS in 1994

Gundremmingen A KRB-A BWR 250 1983 RCA KRB-II

Heißdampfreaktor Grosswelzheim HDR HDR 25 1983 RS in 1998

Lingen KWL BWR 252 1985 SE since 1988, RS since 2015

Mehrzweckforschungsreaktor MZFR PWR/D2O 57 1987 RS

Versuchsatomkraftwerk Kahl VAK BWR 16 1988 RS in 2010

Thorium-Hochtemperaturreaktor THTR-300 HTR 308 1993 SE since 1997

Kompakte Natriumgekühlte Kernanlage KNK II SNR 21 1993 RS

Arbeitsgemeinschaft Versuchsreaktor Jülich AVR HTR 15 1994 RS

Greifswald 1-5 KGR 1-5 PWR/WWER 440 1995 RS

Rheinsberg KKR PWR/WWER 70 1995 RS

Würgassen KWW BWR 670 1997 RS

Mülheim-Kärlich KMK PWR 1302 2004 RS

Stade KKS PWR 672 2005 RS

Obrigheim KWO PWR 357 2008 RS

Isar 1 KKI 1 BWR 912 2017 RS

Neckarwestheim 1 GKN-1 PWR 840 2017 RS

Biblis A & B KWB-A/B PWR 1300 2017 RS

Philippsburg 1 KKP 1 BWR 926 2017 RS

Page 10: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

10

Past and current decommissioning projects of research reactors

• Total: 39

• Removed: 29

• Under dismantling: 6

• Safe enclosure: 2

• Permanently shut down, no decommissioning license: 4

• Variety of types of research reactors:

Argonaut type

Critical assembly

Educational reactors

Liquid homogenous reactor

Propulsion reactor

Pool reactor (incl. TRIGA type)

Heavy water reactor (incl. DIDO type)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© TUM

FRM II FRM

Page 11: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Overview on Decommissioning Projects in Germany

11

Past and current decommissioning projects of nuclear fuel cycle facilities

• Total: 11

• Removed: 9

• Under dismantling: 2

• Safe enclosure: 0

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Former storage building for vitrification waste at WAK with additional building for remote dismantling and packaging of decommissioning waste.

Page 12: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

The German Regulatory System

12

Regulation of decommissioning in Germany

• § 7 (3) of the German Atomic Energy Act The decommissioning of an installation […] as well as the safe confinement of an installation, or the dismantling of an installation or of parts thereof shall require a license […].

• View point: phase in lifetime of a facility

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Power operation Shut down operation Decommissioning operation immediate or deferred dismantling

Operational phase Post-operational phase Decommissioning phase or Safe enclosure

Operating license Decommissioning license

Granting of 1st decommissioning license

Final shut down of the facility

Page 13: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

The German Regulatory System

13

Basic Requirements

• The German Atomic Energy Act allows either

to immediate dismantle or

to dismantle after a safe enclosure

a nuclear facility

Note: no entombment (near surface disposal) is allowed

• The operator of a nuclear facility is fully responsible for the decommissioning and dismantling of a nuclear facility

He decides on the decommissioning strategy and the timeframe

He decides on the scope on a license he applies for

Note: The operator has to ensure at any time the safety of the facility and any precautionary measures are taken

• Decommissioning and dismantling are subject to one or more licenses

• Decommissioning activities are subject to intensive regulatory supervision, involving technical experts and on-site presence during the full project

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 14: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

The German Regulatory System

14

Process of licensing

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Applicant/Licensee Licensing authority of the Land (Federal State)

Other authorities of the Land (Federal State)

Experts and expert organisations (TÜV)

Federal Ministry for the Environment, Nature

Conservation, Building and Nuclear Safety

(BMUB)

Other federal authorities (BfS)

Advisory bodies (ESK, SSK, RSK)

Experts and expert organisations (GRS)

General public

Application documents

License

• Draft of the license • Application documents • Evaluation reports

• Statement of BMUB on the Draft of license Agreement on the license

Page 15: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

15

Typically large decommissioning projects

• are divided into phases

corresponding to large work packages

sometimes reflected by an individual licence

• work from “outside to inside”

Phase 1: blue

Phase 2: yellow, orange

Phase 3: red

Advantages

• allows structure large complex technical systems

• allows to gain further information needed for later work packages

• allows flexibility in adapting changes in future phases not licensed yet

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© E.ON Kernkraft GmbH

Page 16: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

16

Example: A typical & recent decommissioning project – decommissioning of Stade NPP

• Design features

Reactor type: PWR

Electrical power: 672 MW

Operation: 1972 - 2003

Operator: Preussen Elektra GmbH (formerly: E.ON Kernkraft)

• Decommissioning “features”

Decommissioning due to economic reasons

4 phases approach on immediate dismantling

End-state: release of the site for unrestricted use, proposed for 2015

Inventory: total of 1017 Bq, mobile contamination of 1013 Bq

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© E.ON Kernkraft GmbH

Page 17: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

17

Example: Decommissioning of Stade NPP – Content of phase 1

• Removal of contaminated systems and components

Materials air lock and air recirculation unit (1)

Flood tanks (2)

Control rod assembly (3)

Pressurized water tanks (4)

• Objectives

Free space for later dismantling work

Preparation of later dismantling work

Removal of systems and components

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 18: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

18

Example: Decommissioning of Stade NPP – Content of phase 2

• Removal of large components, including

Steam generator (1) (transfer to studsvik for processing)

Pipes and pumps of the primary circuit (2)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 19: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

19

Example: Decommissioning of Stade NPP – Content of phase 3

• Removal of activated systems and components

Core internals (1)

Spent fuel pond internals (2)

In-situ dismantling of RPV (3) • Cutting of large parts • Drum size cutting in spent fuel pond

Biological shielding (4)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 20: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

20

Example: Decommissioning of Stade NPP – Content of phase 4

• Removal of remaining systems and components

Reactor crane (1)

Fuel transfer platform (2)

Ventilation system (3)

Water purification plant (4)

• Preparation for clearance for unrestricted rules

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 21: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Phased Approach

21

Example: Overview of 4 Phases @ Stade NPP

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Phase 1 Phase 2 Phase 3 Phase 4 © E.ON Kernkraft GmbH

Page 22: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Industrial Development at the site

22

Example: Decommissioning of the Greifswald NPPs

• Design features

Reactor type: 6 WWER (2 more planned)

Electrical power: 440 MW per unit

Operation: 1974/75/78/79/89 – 1989

Operator: EWN GmbH

• Decommissioning “features”

Shutdown due to technical reasons after German reunification

8 phases approach on immediate dismantling

End-state: release of the site for (conventional) re-use

Inventory: 4 x 1017 Bq in total

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 23: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Industrial Development at the site

23

Example: Decommissioning of the Greifswald NPPs

Example: Re-use of the machine hall (Length > 1 km)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 24: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Large Component Removal

24

Dismantling of large components – German practice shows following options

• In-situ dismantling

• Partial in-situ dismantling

Post processing on-site or off-site

• Removal and ex-situ dismantling (typically for metal components)

On-site dismantling - immediate - deferred (after decay storage)

Off-site dismantling at external service providers (cutting, decontamination / melting, clearance – in a foreign country: still according to German requirements, return of material and radioactive waste)

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 25: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Large Component Removal

25

Examples of large component removal for off-site dismantling

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© R. Borchardt, G. Hillebrecht, EWN,

2010 Annual Meeting of German Nuclear Society

KGR reactor vessel removal and interim storage at Greifswald NPP

KWO steam generator shipment for interim storage at Greifswald NPP

© ndr.de

© nadir.org

Page 26: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Waste Management

26

Specific to decommissioning

high volume of radioactive material to be handled

With consequences for

• Internal logistics of material flow within a nuclear facility

• Capacities of treatment of radioactive material

• Conditioning of radioactive wastes

• Clearance of radioactive material and related measuring devices

• Interim storage facilities for negligible heat generating radioactive waste

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 27: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Waste Management

27

Example on the masses from a recent decommissioning project

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

© E.ON

Kernkraft GmbH

Stade NPP

Page 28: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Clearance

28

Administrative act which effects the exemption of radioactive substances and any movable goods, of buildings, soil areas, installations or parts of installations which are activated or contaminated by radioactive substances and which originate from practices from regulatory control

Clearance of radioactive substances and movable goods, buildings, soil areas, facilities or parts of facilities which are activated or contaminated material, can be granted by the regulatory body (“license”) only if relevant radiological requirements are fulfilled

Basic radiological requirement / concept: “De Minimis Principle” radioactive activation and contamination of the material, … to be cleared, shall be such, that the exposure of a member of the public is no more than about 10 µSv/a

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 29: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Current Challenges

29

Decommissioning of NPPs with fuel elements still present

*permanently shut down, no decommissioning license

(Re)Classification of systems

Demonstrating absence of impact when dismantling structures, systems and components

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Name Abbrev. Storage of fuel elements

Neckarwestheim 1 GKN 1 Cooling pond

Isar 1 KKI 1 Cooling pond

Biblis Block B KWB B Cooling pond

Unterweser KKU* Cooling pond

Brunsbüttel KKB* Cooling pond

Krümmel KKK* Cooling pond

Grafenrheinfeld KKG* Cooling pond

Page 30: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Current Challenges

30

Infrastructure for waste management

• Timeline of waste generation

• Clearance options

• Treatment and conditioning capacities

• Long-term interim storage of fuel and decommissioning waste

• Availability of approved fuel assembly casks

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Time dependent accumulation of radioactive waste with negligible heat generation as waste package volumes until 2080, © BMUB

Page 31: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Decommissioning Experiences – Current Challenges

31

Knowledge management

• Maintenance of competence at all levels

Operators

Regulatory body

Technical support organizations

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Page 32: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Summary

32

In Germany a large number of decommissioning projects was successfully performed

Recent decommissioning experiences relate among others to

• Phased approach

• Industrial development at the site

• Large component removal

• Clearance option

• Waste management

Challenges

• Fuel elements still present

• Infrastructure for waste management

• Knowledge management

Decommissioning in Germany, 9th Edition of the International Summer School 2017 on ND&WM - P. Imielski

Removed NPP Niederaichbach

© Backcock Noell GmbH

Page 33: Operational decommissioning experience in Germany2017.radioactivewastemanagement.org/images/slide/... · Mülheim-Kärlich KMK PWR 1302 2004 RS Stade KKS PWR 672 2005 RS Obrigheim

Operational decommissioning experience in Germany

9th Edition of the International Summer School on Nuclear Decommissioning and Waste Management

Dr. Przemyslaw Imielski Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) gGmbH

JRC Ispra (Italy), 13 September 2017

Thank you for your attention!