Upload
ntannage
View
212
Download
0
Embed Size (px)
DESCRIPTION
Constructing Environments Sem 2 Student Journal Week 3 University of Melbourne
Citation preview
Constructing Environments Journal | Nicole Tan Page 1
Construction Journal Submission Report
Week Three: OVAL PAVILLION
Nicole Tan 641433
Marked up plan of photo sites:
A
B
C
D
Location
Direction of photo
Constructing Environments Journal | Nicole Tan Page 2
Photos:
FIGURE_A
Steel reinforcements have been placed in an
excavated site. These structures have safety
capping features (in yellow) as an OHS measure.
These reinforcements are likely to be for a ground
beam as they begin to construct the foundation
of the structure. The concrete poured onto these
foundations represent a composite structure
where the concrete prevents the steel from
rusting whilst the steel provides the concrete with
tensile strength.
FIGURE_B
This is an image of a wall formwork
with horizontal and vertical timber
studs as reinforcements. The stage of
works here is more advanced than
Figure A where they are beginning to
construct the primary members of the
structure such as this foundation wall.
Once this formwork is complete,
concrete will be poured into it
thereby creating an in-situ concrete
foundation wall.
LINK BETWEEN FIGURE A
AND B
The line of steel
reinforcements lie
adjacent to the formwork
which suggests that the
foundation wall will be
connected to the lateral
structure on which the
steel reinforcements will
support.
Constructing Environments Journal | Nicole Tan Page 3
FIGURE_C
This is an image of the old
heritage-listed pavilion which
was severely damaged by fire in
the 1950’s. A temporary
downpipe has been installed to
the pavilion whilst the hydraulics
of the old structure is also
present. Timber diagonal
supports have also been added.
There has been no works to
restore the broken tiles on the
roof or improve the foundation of
the building.
FIGURE_D
This section of the construction site has the most progress. The plywood formwork is clearly
in place and ready to receive extra reinforcement if necessary and the subsequent
concrete block placement. Steel reinforcements have been installed in certain grids
whilst conduits appear to present in most grids. Concrete blockwork can be seen on the
wall closest to the camera and the builder has also installed temporary timber edge
protection for OHS measures.
At this stage, on-site pouring of concrete and block work is occurring to create the
concrete blocks for the basement slabs which will be lifted and placed into the area
photographed above.