Upload
hizbi7
View
217
Download
4
Embed Size (px)
DESCRIPTION
cired sabah
Citation preview
A review of the Planning methodologies for the
development of the Sabah Transmission Grid Under the 11th
Malaysian Plan
Alexsteir Moris
Engineer (Transmission Planning)
Planning Division, Sabah Electricity Sdn Bhd
Tel: 6088-282471
Email: [email protected]
AORC-CIGRE TECHNICAL MEETING 16th to 21st August 2015
The Magellan Sutera Resort, Kota Kinabalu, Sabah, MALAYSIA
Planning cycle
Deterministic Criteria
Value management
Creativity Index
Value based reliability planning
New Planning Methodology
1
2
3
4
5
6
Table of Contents
2
PLANNING CYCLE
Report from previous
report
20-Year Generation
Development Plan 2015
Load survey
Electricity Demand Forecast
2015
3
DETERMINISTIC
CRITERIA Thermal limits Voltage limits Stability limits Frequency excursion Short circuit limits
4
Frequency limit
Transient study Category A Category B
Stability limit
Short circuit limit
Thermal limit
Voltage limit
Compliance to the Sabah Labuan Grid
Code
As per SESB practice, all the deterministic criteria is a mandatory requirement for SESB to comply.
5
Criteria – Thermal Limits
Equipment (All
Transmission
Voltages)
System Condition (Planning Timescales)
Normal Operation Following Secured (N-1)
Contingency Events
Minimum Minimum
Overhead Lines No thermal overloading allowed No thermal overloading allowed
Underground/
Submarine
Cables
No thermal overloading allowed No thermal overloading allowed
Transformers No thermal overloading allowed No thermal overloading allowed
Loss of load is NOT allowed under both system conditions stated above
6
Criteria – Voltage Limits
7
Nominal
Voltage
System Condition (Planning Timescales)
Normal Operation Following Secured (N-1)
Contingency Events
Minimum Maximum Minimum Maximum
275kV 1.0 p.u. 1.05 p.u. 0.95 p.u. 1.05 p.u.
132kV 1.0 p.u. 1.05 p.u. 0.95 p.u. 1.05 p.u.
Generation
Bus 1.0 p.u. 1.05 p.u. 0.95 p.u. 1.05 p.u.
8
Criteria – Stability Limits
Rotor angle Relative rotor angle of any two generating units must not
exceed 180 degrees at any time
Damping Ratio Following a disturbance, the damping ratio of power, angle
or voltage oscillation must not less than 5 %
Voltage
Excursion
Immediately following a fault clearance,
Low Limit : 0.7 p.u. for not more than 400 ms
High Limit : 1.2 p.u. for not more than 30 s
9
Criteria – Fault clearing Times
System Voltage
(kV) Fault location
Fault clearance time
ms cycles
275 Substation 100 5
Overhead line/cable 100 5
132 Substation 150 7.5
Overhead line/cable 150 7.5
66 Substation 150 7.5
Overhead line/cable 150 7.5
10
Under Normal operating conditions • 49.5 Hz to 50.5 Hz- allow to operate continuously
Under Abnormal system conditions
• 49.0 to 49.5 Hz or 50.5 to 51.0Hz allow to operate for less
than 30 min
• 47.5 to 49.0Hz or 51.0 to 52.0 Hz allow to operate for less
than 1 min
• 47.0 Hz to 47.5 Hz – allow to operate for less than 10
seconds
Under extreme System fault conditions all
generating sets should have disconnected by
this frequency unless agreed otherwise in
writing with the Single Buyer.
• Above 52.0 Hz or below 47.0 Hz below generating set will
be allowed to disconnect without time delay. CCGT may
have a lower high frequency limit, if design limit is lower
than 52.0 Hz but should be lower than 51.5 Hz
Criteria – Frequency exursion
11
Criteria – Short Circuit Limits
System Voltage (kV) Equipment Short Circuit Rating Break Capacity
275
40kA, 3s for bulk substation
50kA, 1s for 275kV substation
equipment within Power
Station
132
31.5kA, 3s for bulk substation
40kA, 3s for 132kV and 275kV substation within Power
Station
33
31.5kA, 3s
31.5kA, 3s for Power Station equipment and 33kV equipment
within 275kV and 132kV substations
12
Transient study criteria
Category Requirements
A (N-0) No Contingencies (system intact)
• System must remain stable • No loss of demand • No cascading outages
B (N-1) Event resulting in the loss of a single element
• System must remain stable • No loss of demand • No cascading outages
C (N-2),(N-1-1) Event(s) resulting in the loss of two or more (multiple) elements
• System must remain stable • Loss of demand is allowed (controlled/planned) • No cascading outages
D Extreme event resulting in two or more (multiple) elements removed or Cascading out of service
• May involve substantial loss of customer Demand and generation in a widespread area or areas
• Portions or all of the Interconnection systems may or may not achieve a new, stable operating point.
• Evaluation of these events may require joint studies with neighbouring systems
VALUE MANAGEMENT
13
14
• For the state of Sabah, most of the electricity project funded by the Federal Government from various Malaysian Plan.
• Under the Malaysian Plan, it is Federal Government Policy that all project funded through Malaysian Plan must conduct a Value Management.
-:Value Management:- Systematic approaches to various disciplines and innovative in order to achieve more Good
value with optimum costs Without prejudice to the level of program and project performance
To determine unnecessary expenses
To simplified method and procedure
To save time, cost and energy
Innovative
To update standard, criteria and objective
To eliminate redundancy items
To challenge assumption and Generate new idea
Value Management
CREATIVITY INDEX
15
16
Based on the latest guidelines from Federal Government required Creativity Index analysis for all federal Government funded project.
•Outcomes of creativity :- Economic outputs stand for the growth of creative economy, but other inventive outcomes present the vitality and vibrancy of creativity in a place. •Structural/institutional capital •Human capital :-High mobility of human capital will facilitate cultural exchange, transfer of skills and knowledge as well as generation of new ideas in society •Social capital :-Social capital, in terms of trust, reciprocity, cooperation and rich social networks are conducive to the enrichment of collective well-being and social expression. •Cultural capital :- Cultural capital refers to the more specific activities and qualities relating to culture, the arts and creativity in everyday life.
•ICT infrastructure •Social and cultural infrastructure •Community facilities •Financial infrastructure
We measure eight types of societal conditions that are contributors to the growth of creativity in a community: •Legal system •Corruption •Freedom of expression
•Entrepreneurship
VALUE BASED RELIABILITY PLANNING
17
18
The value-based reliability transmission planning is a transmission development planning (TDP) methodology in which the cost of TDP is measured against the benefits from reliability improvement.
• The basic concept of value based reliability transmission planning is;
Total Cost = Utility Costs + Customer Outage Costs
• A new conceptual transmission planning method is proposed which considers both the
reliability and economic criteria simultaneously.
• By incorporating the two planning criteria, the proposed planning model can find the
trade-off between satisfying reliability needs and maximizing the economic value of
candidate options.
• Capital cost, • operation and
maintenance (O&M),
• losses, etc.
• The costs due to unreliability supply.
19
A new conceptual methodology to be adopted by SESB
Qualitative analysis
Deterministic Probabilistic assessment
Economic analysis
• Space • Way leave • Social impact • Risk of project
implementation
• Using software PSS/E
• Conduct study for all criteria as per mandatory requirement by SLGC
• Reliability analysis of connection scheme.
• Introduction of reliability software
The information will help in identifying
• Scenarios that have high probability or high impact or both Equipment (line, transformer, generator) that causes critical situations
• Facilities (buses and branches) that are most violated.
• The relationship between reliability index and stress level to provide a measurement of system robustness.
• Cost Benefit Analysis
• Creativity Index • Value
management
NEW PLANNING METHODOLOGY
20
21
QUALITATIVE ANALYSIS
DETERMINISTIC CRITERIA
Combining the traditional, new guideline by Federal Government and valued based reliability planning, a comprehensive project proposal established.
CREATIVITY INDEX
PROBABILISTIC ASSESSMENT
ECONOMIC ASPECT
VALUE MANAGEMENT
PROJECT PROPOSAL
22
THANK YOU