Upload
becky
View
33
Download
0
Tags:
Embed Size (px)
DESCRIPTION
PLANNING FOR WIND AND QUEUE MANAGEMENT. Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan. 400 kV Network. BULGAR İSTAN. KARADENİZ. DIMODICHEV. HABİPLER. BATUM. GÜRCİSTAN. BABAESKİ. HAMİTABAT. ALİBEYKÖY. AHALTSIKHE. İKİTELLİ. A.ALANI. - PowerPoint PPT Presentation
Citation preview
1
PLANNING FOR WIND AND QUEUE MANAGEMENT
Turkish Electricity Transmission Corporation(TEIAS)
prepared by Gül Okan & Nurhan Ozan
2
400 kV Network
KARADENİZ
AKDENİZ
EREĞLİ
AMBARLI
BULGARİSTAN
FILIPPI
H.UĞURLUKAYABAŞI
ÇANKIRI
TİREBOLU
BORÇKA
GÜRCİSTANBATUM
ERMENİSTAN
GUMRI
BALIKESİR
SOMA
ALİAĞA
DENİZLİ
YATAĞAN
KEMERKÖYOYMAPINAR
SEYDİŞEHİR
KONYA
ADANAERZİN
G.ANTEP
ANDIRIN
ELBİSTAN
KANGAL
YEŞİLHİSAR
KAYSERİ
ÇAYIRHAN
GÖLBAŞI
KEBAN
KARAKAYA
ATATÜRK
DİYARBAKIR
Ş.URFA
BATMAN
KARS
ÖZLÜCE
ERZURUM
HORASAN
IĞDIR
D.BEYAZIT
DIMODICHEV
SURİYE
DERİNER
İSKENDERUN
İRAN
IRAK
HALEP
PS3
ZAKHO
KHOY
BAZARGAN
BABEK
KALKANDERE
KOCATEPE
TEİAŞ-APK 2010
220 kV EİH
154 kV EİH
HES (PLANLANAN)
HES (MEVCUT)
TS (MEVCUT)
TL (MEVCUT)
TL (PLANLANAN)
TS (PLANLANAN)
Y.TEPE
ALİBEYKÖY
TUNÇBİLEK
D.PAŞA
KARABİGA
ADA-GEBZE
PAŞAKÖY
OSMANCA
GÖKÇEKAYA
TEMELLİ
SİNCAN
BABAESKİ
HAMİTABAT
ÜMRANİYE
BURSA
AYDIN
YENİKÖY
BİRECİK
SEYİTÖMER
IŞIKLAR
ADAPAZARI
YUN
ANİS
TAN
KIZILTEPE
AĞRI
Z.KÖY
TEPEÖREN
UNIMAR
HİLVAN
ILISU
CİZRE
VAN
ERMENEK
MERSİN
HATAY
İKİTELLİ A.ALANI
KAPTAN
UZUNDERE
SİVASDEÇEKO
YUSUFELİ
KAVŞAK
İSDEMİR
BOYABATAMASRA
BEYKOZ
ÇARŞAMBA
HOPA
VARSAK
MANİSA
HABİPLER
SAMSUN DGKÇ
BORASCO
ÇAN
İÇDAŞ
İÇDAŞ
AKSA
SİLOPİ TES
K.KALE DGKÇ
İÇANADOLU DGKÇ
BAĞLUM
KAYRAKTEPE
YEDİGÖZE
İSPİR
ARKUN
AKINCI
ORDU-2
SİİRTÇETİN
MUSUL
V.ŞEHİR
AHALTSIKHE
3
Profile of System (end of 2010)
NUMBER OF SUBSTATIONS:
400 kV 184 (35020 MVA)
154 kV 1034 (58015 MVA)
66 kV 54 (637 MVA)
TOTAL 1272
INSTALLED CAPACITY (93672 MVA)
LENGTH OF TRANSMISSION LINES (km):
400 kV 14,623
154 kV 31,932
220 kV 84,5
66 kV 508,5
154 kV Cable 170,9
380 kV Cable 22,3
TOTAL 47,148
4
Generation & Demand (for the year of 2010)
Installed Capacity 48.500 MW
Hydro+Renewable 34.4 %Hydro 32.1 % & Renewables 2.7 %
Thermal 65.2 %
Annual Consumption 208 TWh
Peak Demand 33.500 MW
(13 August 2010)
BREAKDOWN OF I NSTALLED CAPACI TY
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
THERMAL WIND HYDRO
THERMAL
WIND
HYDRO
5
Topics
• Brief history of interconnection queue• Challenges while planning• Tariff Policy• Queue Management• Future Efforts
6
Brief History of Queues
• First WPP commissioned in: 1998• Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW• Current Licensed wind generation: 3483 MW• Date: 1th November 2007 Number of the wind pp’s: 722 Total capacity: 78.000 MW
• According to the system available capacity for connecting wind generation which is equal to 8474 MW a bidding code was prepared by TEIAS which includes the requirements for the applications.
• According to the bidding document the wind owner which will get the right to use the open capacity has to pay an amount to TEIAS for 20 years since connecting to the system which is equal the amount which will be calculated for per kwh generation of the wind power plant.
7
Wind power plant application areas
8
Recent Situation for Wind Generation in Turkey
• 3483 MW of wind applications has been licensed by EMRA
• 1320 MW is in Operation • 2283 MW is Underconstruction
• 8488 MW is under evaluation
• The amount of the available wind generation capacity can be connected to the system until 2013 is 12000 MW
• In the strategy document it is foreseen that the total wind generation capacity will reach to 20.000 MW until 2023.
9
The available wind generation capacity around 8488 MW is under evaluation
10
Marmara & Thrace Region available wind generation capacity ~ 2745 MW is under evaluation
11
Aegean Region available wind generation capacity around 2499 MW is under evaluation
12
Hatay Region available wind generation capacity around 190 MW is under evaluation
13
Challenges while planning
• Available system reserve
• The required reinforcements for connecting WPP’s into power system.
• The difficulty to guess their production time of wind power plants.
• Who pays the investments and how it will be recovered
• Beside load flow, voltage profile, short-circuit and contingency studies; the %5 of the short circuit power of the substation which WPP will be connected is applied as a restriction criteria in order to keep the overall system security by now.
• Detailed dynamic studies for determining the connection capacities are going on.
INCENTIVES FOR RENEWABLE POWER PLANTSINCENTIVES FOR RENEWABLE POWER PLANTS
The Turkey’s Parliament approved a new law 29 December 2010 on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of:
• Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3 US$ /MWh is guaranteed
• Geothermal PPs are paid at system marginal price, but minimum 10.5 US$ /MWh is guaranteed
• Biogas PPs and Solar PPs are paid at system marginal price, but minimum 13.3 US$ /MWh is guaranteed
• Those tariffs shall be valid for the PPs which came into service between 18 May 2005 to 31 December 2015 and will be applied for 10 years.
• After 31 December 2015, new tariff shall be given by the Government but the new tariff shall not exceed the tariff above.
15
Queue Management
• Process:
1. The available capacity for connecting wind generations are published by TEİAS.
2. WPP applications are forwarded to EMRA (Turkish Regulatory Agency) for these capacities.
3. These applications are forwarded to TEIAS for studying connection opportunities.
4. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications.
5. If there are multiple applications, bidding process is done by TEIAS to determine the owner of the capacity.
6. After taking license the investor sign a connection agreement with TEIAS.
7. Project will be approved by MENR after the realization of the project System Usage Agreement will be done with TEIAS.
16
Queue Management
• Principle of connection cost sharing in between TSO and investor:
If the investor pays for the connection line then the TSO will pay back to the investor this amount in 10 years from the investment budget.
Otherwise, TSO will put the required investment for the connection of the power plant in it’s yearly investment plan and these procedures takes
approximately 3-5 years for bidding (plus constructing period)
17
Planning Process by TEIAS
• Turkish Electricity Transmission Corporation responsible from the WPP integration studies and to define the available capacity for connecting wind generation
• According to the results of load flow, contingency analyses and short circuit power calculations, the estimation for capacity for each substation and each region which will be available for connecting wind generation are defined by TEIAS
• Concentrated small wind generations in one region are collected in one substation (example: Çeşme Region)
• We have a specific grid code which defines the connection criteria for wind generation but it will be revised for future power system conditions.
18
ÇEŞME REGION WIND PROJECTS: 460 MW
380/OG kV Karaburun SS
Karaburun RES 120 MW
380/OG125 MVA
~
380/OG150 MVA
OG
154/OG50 MVA
380/154 kV Uzundere SS
~
~
~
~
Sarpıncık RES 32 MW
Yaylaköy RES 15 MW
Mordoğan RES 30,75 MW
Mordoğan RES 13,8 MW
Zeytineli-2 RES 49,5 MW
~
~
~
Urla RES
15 MW
Seferihisar RES
14 MW
Seferihisar RES
16 MW
Korkmaz RES 24 MW
Demircili RES
40 MW
Çeşme RES
16 MW
Alaçatı RES
16 MW
Ovacık RES
18 MW
Germiyan RES
10,8 MW
OG
Karadağ RES 16,25MW
21 km 380 kV 3 Cardinal
16,2
km
380
kV
2 C
ard
inal
26 k
m
17 k
m
12
km
10 k
m
OG
7 km
14 km
10 km
4 km
9 km
11 km
~
~
~
~
~
~
55 km 380 kV 3 Cardinal
380/OG Çeşme HAVZA SS
Urla RES
13 MW
13 km ~
154/OG50 MVA
154/OG50 MVA
31 km 154 kV 2x1272 MCM
OGOG
6 km
11 km
9 km
10 km
5 km
154/OG URLA HAVZA SS
SS TOTAL CAP: 211,55 MW SS TOTAL CAP: 139,55 MW SS TOTAL CAP: 109 MW
~
~
19
Future Efforts
• The wind forecast system has been developed by Turkish State Meteorological Service which is available to provide information about the wind forecasts for different heights and for 48 hours with 4 km. solubility all
around Turkey. The trial tests are going on in order to improve the system.
• Specific monitoring system for wind generation will be installed and the
procedures are going on with consultant company
20
Thank You for Your Attention !