20
1 PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan

PLANNING FOR WIND AND QUEUE MANAGEMENT

  • Upload
    becky

  • View
    33

  • Download
    0

Embed Size (px)

DESCRIPTION

PLANNING FOR WIND AND QUEUE MANAGEMENT. Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan. 400 kV Network. BULGAR İSTAN. KARADENİZ. DIMODICHEV. HABİPLER. BATUM. GÜRCİSTAN. BABAESKİ. HAMİTABAT. ALİBEYKÖY. AHALTSIKHE. İKİTELLİ. A.ALANI. - PowerPoint PPT Presentation

Citation preview

Page 1: PLANNING FOR WIND AND QUEUE MANAGEMENT

1

PLANNING FOR WIND AND QUEUE MANAGEMENT

Turkish Electricity Transmission Corporation(TEIAS)

prepared by Gül Okan & Nurhan Ozan

Page 2: PLANNING FOR WIND AND QUEUE MANAGEMENT

2

400 kV Network

KARADENİZ

AKDENİZ

EREĞLİ

AMBARLI

BULGARİSTAN

FILIPPI

H.UĞURLUKAYABAŞI

ÇANKIRI

TİREBOLU

BORÇKA

GÜRCİSTANBATUM

ERMENİSTAN

GUMRI

BALIKESİR

SOMA

ALİAĞA

DENİZLİ

YATAĞAN

KEMERKÖYOYMAPINAR

SEYDİŞEHİR

KONYA

ADANAERZİN

G.ANTEP

ANDIRIN

ELBİSTAN

KANGAL

YEŞİLHİSAR

KAYSERİ

ÇAYIRHAN

GÖLBAŞI

KEBAN

KARAKAYA

ATATÜRK

DİYARBAKIR

Ş.URFA

BATMAN

KARS

ÖZLÜCE

ERZURUM

HORASAN

IĞDIR

D.BEYAZIT

DIMODICHEV

SURİYE

DERİNER

İSKENDERUN

İRAN

IRAK

HALEP

PS3

ZAKHO

KHOY

BAZARGAN

BABEK

KALKANDERE

KOCATEPE

TEİAŞ-APK 2010

220 kV EİH

154 kV EİH

HES (PLANLANAN)

HES (MEVCUT)

TS (MEVCUT)

TL (MEVCUT)

TL (PLANLANAN)

TS (PLANLANAN)

Y.TEPE

ALİBEYKÖY

TUNÇBİLEK

D.PAŞA

KARABİGA

ADA-GEBZE

PAŞAKÖY

OSMANCA

GÖKÇEKAYA

TEMELLİ

SİNCAN

BABAESKİ

HAMİTABAT

ÜMRANİYE

BURSA

AYDIN

YENİKÖY

BİRECİK

SEYİTÖMER

IŞIKLAR

ADAPAZARI

YUN

ANİS

TAN

KIZILTEPE

AĞRI

Z.KÖY

TEPEÖREN

UNIMAR

HİLVAN

ILISU

CİZRE

VAN

ERMENEK

MERSİN

HATAY

İKİTELLİ A.ALANI

KAPTAN

UZUNDERE

SİVASDEÇEKO

YUSUFELİ

KAVŞAK

İSDEMİR

BOYABATAMASRA

BEYKOZ

ÇARŞAMBA

HOPA

VARSAK

MANİSA

HABİPLER

SAMSUN DGKÇ

BORASCO

ÇAN

İÇDAŞ

İÇDAŞ

AKSA

SİLOPİ TES

K.KALE DGKÇ

İÇANADOLU DGKÇ

BAĞLUM

KAYRAKTEPE

YEDİGÖZE

İSPİR

ARKUN

AKINCI

ORDU-2

SİİRTÇETİN

MUSUL

V.ŞEHİR

AHALTSIKHE

Page 3: PLANNING FOR WIND AND QUEUE MANAGEMENT

3

Profile of System (end of 2010)

NUMBER OF SUBSTATIONS:

400 kV 184 (35020 MVA)

154 kV 1034 (58015 MVA)

66 kV 54 (637 MVA)

TOTAL 1272

INSTALLED CAPACITY (93672 MVA)

LENGTH OF TRANSMISSION LINES (km):

400 kV 14,623

154 kV 31,932

220 kV 84,5

66 kV 508,5

154 kV Cable 170,9

380 kV Cable 22,3

TOTAL 47,148

Page 4: PLANNING FOR WIND AND QUEUE MANAGEMENT

4

Generation & Demand (for the year of 2010)

Installed Capacity 48.500 MW

Hydro+Renewable 34.4 %Hydro 32.1 % & Renewables 2.7 %

Thermal 65.2 %

Annual Consumption 208 TWh

Peak Demand 33.500 MW

(13 August 2010)

BREAKDOWN OF I NSTALLED CAPACI TY

0

5.000

10.000

15.000

20.000

25.000

30.000

35.000

THERMAL WIND HYDRO

THERMAL

WIND

HYDRO

Page 5: PLANNING FOR WIND AND QUEUE MANAGEMENT

5

Topics

• Brief history of interconnection queue• Challenges while planning• Tariff Policy• Queue Management• Future Efforts

Page 6: PLANNING FOR WIND AND QUEUE MANAGEMENT

6

Brief History of Queues

• First WPP commissioned in: 1998• Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW• Current Licensed wind generation: 3483 MW• Date: 1th November 2007 Number of the wind pp’s: 722 Total capacity: 78.000 MW

• According to the system available capacity for connecting wind generation which is equal to 8474 MW a bidding code was prepared by TEIAS which includes the requirements for the applications.

• According to the bidding document the wind owner which will get the right to use the open capacity has to pay an amount to TEIAS for 20 years since connecting to the system which is equal the amount which will be calculated for per kwh generation of the wind power plant.

Page 7: PLANNING FOR WIND AND QUEUE MANAGEMENT

7

Wind power plant application areas

Page 8: PLANNING FOR WIND AND QUEUE MANAGEMENT

8

Recent Situation for Wind Generation in Turkey

• 3483 MW of wind applications has been licensed by EMRA

• 1320 MW is in Operation • 2283 MW is Underconstruction

• 8488 MW is under evaluation

• The amount of the available wind generation capacity can be connected to the system until 2013 is 12000 MW

• In the strategy document it is foreseen that the total wind generation capacity will reach to 20.000 MW until 2023.

Page 9: PLANNING FOR WIND AND QUEUE MANAGEMENT

9

The available wind generation capacity around 8488 MW is under evaluation

Page 10: PLANNING FOR WIND AND QUEUE MANAGEMENT

10

Marmara & Thrace Region available wind generation capacity ~ 2745 MW is under evaluation

Page 11: PLANNING FOR WIND AND QUEUE MANAGEMENT

11

Aegean Region available wind generation capacity around 2499 MW is under evaluation

Page 12: PLANNING FOR WIND AND QUEUE MANAGEMENT

12

Hatay Region available wind generation capacity around 190 MW is under evaluation

Page 13: PLANNING FOR WIND AND QUEUE MANAGEMENT

13

Challenges while planning

• Available system reserve

• The required reinforcements for connecting WPP’s into power system.

• The difficulty to guess their production time of wind power plants.

• Who pays the investments and how it will be recovered

• Beside load flow, voltage profile, short-circuit and contingency studies; the %5 of the short circuit power of the substation which WPP will be connected is applied as a restriction criteria in order to keep the overall system security by now.

• Detailed dynamic studies for determining the connection capacities are going on.

Page 14: PLANNING FOR WIND AND QUEUE MANAGEMENT

INCENTIVES FOR RENEWABLE POWER PLANTSINCENTIVES FOR RENEWABLE POWER PLANTS

The Turkey’s Parliament approved a new law 29 December 2010 on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of:

• Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3 US$ /MWh is guaranteed

• Geothermal PPs are paid at system marginal price, but minimum 10.5 US$ /MWh is guaranteed

• Biogas PPs and Solar PPs are paid at system marginal price, but minimum 13.3 US$ /MWh is guaranteed

• Those tariffs shall be valid for the PPs which came into service between 18 May 2005 to 31 December 2015 and will be applied for 10 years.

• After 31 December 2015, new tariff shall be given by the Government but the new tariff shall not exceed the tariff above.

Page 15: PLANNING FOR WIND AND QUEUE MANAGEMENT

15

Queue Management

• Process:

1. The available capacity for connecting wind generations are published by TEİAS.

2. WPP applications are forwarded to EMRA (Turkish Regulatory Agency) for these capacities.

3. These applications are forwarded to TEIAS for studying connection opportunities.

4. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications.

5. If there are multiple applications, bidding process is done by TEIAS to determine the owner of the capacity.

6. After taking license the investor sign a connection agreement with TEIAS.

7. Project will be approved by MENR after the realization of the project System Usage Agreement will be done with TEIAS.

Page 16: PLANNING FOR WIND AND QUEUE MANAGEMENT

16

Queue Management

• Principle of connection cost sharing in between TSO and investor:

If the investor pays for the connection line then the TSO will pay back to the investor this amount in 10 years from the investment budget.

Otherwise, TSO will put the required investment for the connection of the power plant in it’s yearly investment plan and these procedures takes

approximately 3-5 years for bidding (plus constructing period)

Page 17: PLANNING FOR WIND AND QUEUE MANAGEMENT

17

Planning Process by TEIAS

• Turkish Electricity Transmission Corporation responsible from the WPP integration studies and to define the available capacity for connecting wind generation

• According to the results of load flow, contingency analyses and short circuit power calculations, the estimation for capacity for each substation and each region which will be available for connecting wind generation are defined by TEIAS

• Concentrated small wind generations in one region are collected in one substation (example: Çeşme Region)

• We have a specific grid code which defines the connection criteria for wind generation but it will be revised for future power system conditions.

Page 18: PLANNING FOR WIND AND QUEUE MANAGEMENT

18

ÇEŞME REGION WIND PROJECTS: 460 MW

380/OG kV Karaburun SS

Karaburun RES 120 MW

380/OG125 MVA

~

380/OG150 MVA

OG

154/OG50 MVA

380/154 kV Uzundere SS

~

~

~

~

Sarpıncık RES 32 MW

Yaylaköy RES 15 MW

Mordoğan RES 30,75 MW

Mordoğan RES 13,8 MW

Zeytineli-2 RES 49,5 MW

~

~

~

Urla RES

15 MW

Seferihisar RES

14 MW

Seferihisar RES

16 MW

Korkmaz RES 24 MW

Demircili RES

40 MW

Çeşme RES

16 MW

Alaçatı RES

16 MW

Ovacık RES

18 MW

Germiyan RES

10,8 MW

OG

Karadağ RES 16,25MW

21 km 380 kV 3 Cardinal

16,2

km

380

kV

2 C

ard

inal

26 k

m

17 k

m

12

km

10 k

m

OG

7 km

14 km

10 km

4 km

9 km

11 km

~

~

~

~

~

~

55 km 380 kV 3 Cardinal

380/OG Çeşme HAVZA SS

Urla RES

13 MW

13 km ~

154/OG50 MVA

154/OG50 MVA

31 km 154 kV 2x1272 MCM

OGOG

6 km

11 km

9 km

10 km

5 km

154/OG URLA HAVZA SS

SS TOTAL CAP: 211,55 MW SS TOTAL CAP: 139,55 MW SS TOTAL CAP: 109 MW

~

~

Page 19: PLANNING FOR WIND AND QUEUE MANAGEMENT

19

Future Efforts

• The wind forecast system has been developed by Turkish State Meteorological Service which is available to provide information about the wind forecasts for different heights and for 48 hours with 4 km. solubility all

around Turkey. The trial tests are going on in order to improve the system.

• Specific monitoring system for wind generation will be installed and the

procedures are going on with consultant company

Page 20: PLANNING FOR WIND AND QUEUE MANAGEMENT

20

Thank You for Your Attention !