Please comply with the Lean Construction Institute’s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf

when using this file. Thank you.

Page 2: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

M d l B d E ti ti t t Model Based Estimating to support Target Value Design Process

Saurabh TiwariDPR Construction, Inc.DPR Construction, Inc.

Page 3: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

COST TRACKING FOR TARGET VALUE DESIGN

Project Cost Type

70%

80%

90%

100%

Co

st

Project Cost Type

20%

30%

40%

50%

60%

% o

f To

tal C

Conceptual Estimate

Manual/Model Based Estimate

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

0%

10%

Project Time Line

Page 4: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

Cost Types Model

T di i l  Traditional  Conceptual

As design becomes more certain, cost is driven from ,project specific design elements rather than conceptual costs (unit costs)

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 5: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

Why Model based Estimating ?

Data Assumed

Manual Mappingwith cost assemblies

2D dwgsHand Takeoff

Manual Estimate(4 weeks)

Data Lost

Manual Estimating Process

Data Used

BIM Automated Mappingwith cost assemblies

Auto Takeoff Model Based Estimate(<1 week)

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

with cost assemblies ( )

Model Based Estimating Process

Page 6: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

DESIGN CHANGE MANAGEMENTWhy Model based Estimating ?

MAN

MANUALGreater Chances of Error: 

•Missing Clouds•Missing detail sheetsU

AL

Missing detail sheets•Missing Section cuts•RETAKEOFF WHOLE SET OF DRAWINGS

MODEL

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 7: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

MODEL BASED ESTIMATING PROCESS

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 8: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

MAIN VALUE ADDING ADDING FEATURE: 

MAPPING  Cost MAPPING  Cost Assemblies with 3D Model Components

Mapping Mapping remembered  (done only once)

Auto‐takeoff  Auto‐takeoff  (automated cost feedback on updated model )

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 9: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

COST TRACKING CHART FORTARGET VALUE DESIGN

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 10: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

INDIVIDUAL CLUSTER REPORT

Link with cost

1 week

approved

1 week

Estimate updatesModel updates Target Cost

Chart Updates1 week

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 11: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

Different Modeling software call for different Estimating Platforms

Revit/AutoCAD

Innovaya/Timberline COST ESTIMATE

CADDuct/CADMech CADEST COST ESTIMATECADMech/CADPipe

CADEST COST ESTIMATE

TeklaTOCOMAN/Innovaya(in progress)

COST ESTIMATE

ArchiCAD TOCOMAN/VICO E ti t

COST ESTIMATE

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Estimator

Page 12: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

CHECK THE BEHAVIOR OF MODEL OVER TIME

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 13: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

OTHER BENEFITS OF MODEL BASED ESTIMATINGQuick Cost Comparison between DESIGN alternativesQuick Cost Comparison between DESIGN alternatives

CEILING HT FULL HT

Quick Cost Comparison between CONSTRUCTION alternatives

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 14: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

CHALLENGES/LESSONS LEARNED

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 15: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

Cost Breakdown: By SourceLESSONS LEARNED

Cost Breakdown: By Source

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY

Page 16: Please comply with the Lean Construction Institute’s Usage … · 2015-01-03 · Different Modeling software call for different Estimating Platforms Revit/ AutoCAD Innovaya/ Timberline

Challenges/Lessons Learned: Aligning Traditional Estimate with Model Based Estimate

TARGET VALUE DESIGN @ SUTTER MEDICAL CENTER, CASTRO VALLEY