Project Management Environment Chapter 2 PMP Preparation Training

Project Management Environment Chapter 2 PMP Preparation Training

Embed Size (px)

Citation preview

Page 1: Project Management Environment Chapter 2 PMP Preparation Training

Project Management EnvironmentProject Management Environment

Chapter 2

PMP Preparation Training

Page 2: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-2

Objectives

• To be able to describe:– Project life cycle– Characteristics of the project phases– Key project stakeholders – Organizational and socioeconomic influences

on the project– Key management skills used in managing a

project

Page 3: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-3

Project Life Cycle

• Defines the beginning and end of the project

• Divides the project into phases that provide better management control and the appropriate links to the ongoing operations of the organization

• Defines the beginning and end of the project

• Divides the project into phases that provide better management control and the appropriate links to the ongoing operations of the organization

Page 4: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-4

Phase Characteristics

• Deliverables Tangible, verifiable work products• Reviews Evaluation of deliverables and project

performance• Phase Exit Criteria Measurements used to determine if

project should go into next phase

Page 5: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-5

Characteristics of Life Cycle

• Defines the beginning and end of the project• Deliverables usually approved before work

starts on the next phase

• Sometimes a subsequent phase is begun prior to approval of the previous phase. This is called fast tracking.

• Defines technical work and implementers

Page 6: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-6

Characteristics of Life Cycle (cont.)

• Cost and staffing levels are low at the start, higher towards the end, and drop as project closes

• Probability of project success is low at the start of the project and gets progressively higher as the project continues

• Cost of changes and of error correction generally increases as the project continues

Page 7: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-7

Phases and Resources Usage

• Concept 5%• Development 20%• Implement 60%• Close Out 15%

Page 8: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-8

Project Stakeholders

Individuals and organizations who are actively involved in the project and whose interests may be positively or negatively affected by the project success or failure

Individuals and organizations who are actively involved in the project and whose interests may be positively or negatively affected by the project success or failure

Key Stakeholders• Project manager Manages the project• Customer Uses the product or service• Performing organization Enterprise that does the project work• Sponsor Provides financial resources

Page 9: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-9

Organizational Influences

• Organizational systems – Project-based

• Derive income by performing projects for others

• Treat on-going operations as projects (management by projects)

– Non-Project-based• No project-oriented systems in place to support

project needs efficiently and effectively

Page 10: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-10

Organizational Cultures & Styles

• Shared values, norms, beliefs, and expectations

• Reflected in policies and procedures, view of authority relationships, etc.

• Directly influences the project

Page 11: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-11

Organizational Structure

• Functional organization – Hierarchy where each employee has one clear superior

• Projectized organization – Most of organization’s resources are involved in project work and report to the project manager

• Matrix organization – Blend of both

Page 12: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-12

Organizational Structure

• Project Office

– Provides services ranging from support functions to project managers, such as training, software, templates, etc. to actually being responsible for the results of the project

Page 13: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-13

Functional Organization

• Specialists grouped by function

• Difficult to cross functional lines

• Barriers exist on horizontal information flow

• Functional emphasis – loyalties may impede completion

Organizational Planning

Page 14: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-14

Matrix Organization

• Multiple-command system

• Individuals from functional areas assigned on temporary basis to PM

• Individuals return to functional organization

• Careful plans and procedures needed to minimize effects of dual reporting

Organizational Planning

Page 15: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-15

Matrix Organization• Advantages

– Visible objectives– Efficient utilization of resources– Better co-ordination– Better information flow– Retention of home after project

• Disadvantages– More than one boss– Complex structure to control– Differing priorities of PM and FM– Duplication of effort– Conflict

Organizational Planning

Page 16: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-16

Projectized Organization

• Emerges from functional when latter impedes progress

• Line of authority is the PM

• Uncertainty where to go on completion of project

• Tendency to retain assigned personnel too long

• FMs feel threatened as people are removed from their areas

Organizational Planning

Page 17: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-17

Organizational StructuresType PM Authority

Functional None

Project Expediter Low

Project Coordinator Low

Weak Matrix Low –> Medium

Strong Matrix Medium –> High

Projectized High

Organizational Planning

Page 18: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-18

General Management Skills• Leading

– Establishing direction, aligning people, motivating, and inspiring

• Communicating– Reporting project performance; deciding how, when, in what form,

and to whom

• Negotiating– Conferring with others in order to come to terms or reach an

agreement

Page 19: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-19

Management Skills (cont.)

• Problem solving– Defining the causes of problems, analyzing the

problems to identify viable solutions, and selecting the best one

• Influencing the organization– Understanding the formal and informal

structures and the mechanics of power and politics and using this knowledge to get things done

Page 20: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-20

Social-Economic-Environmental Influences

• Projects have positive or negative impacts on people, economics, and the environment

• Organizations are accountable for these impacts

Page 21: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-21

• Standards and regulations– Project plan should reflect how standards

and regulations affect the project

• Internationalization– Consider the effect of time-zone differences,

national holidays, travel requirements, teleconferencing, and political differences

Social-Economic-Environmental Influences

Page 22: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-22

• Cultural influences– Projects operate within a context of cultural norms

that affect the way people and organizations interact

• Social-Economic-Environmental Sustainability– Projects have unintended positive and negative impacts

on people, the economy and the environment– Organizations are increasingly accountable for project

impacts

Social-Economic-EnvironmentalInfluences

Page 23: Project Management Environment Chapter 2 PMP Preparation Training

Source: pmbok guide 2000 © 2002 Robbins-Gioia, Inc. 2-23

Summary

• Review Questions