Project Management Plan Workbook

Embed Size (px)

Citation preview

  • 7/27/2019 Project Management Plan Workbook

    1/50

    PPREPARATIONREPARATION WWORKBOOKORKBOOK

    FORFOR

    PROJECT MANAGEMENT PLANPROJECT MANAGEMENT PLAN

    (PMP)(PMP)

    REVISION: 1.1

  • 7/27/2019 Project Management Plan Workbook

    2/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN I

    REVISION HISTORY..............................................................................................I

    ABOUT THIS DOCUMENT PREPARING THE PROJECT MANAGEMENT PLAN.............II

    STARTING WITH THE TITLE PAGE........................................................................V

    1.0 PROJECT OVERVIEW .....................................................................................1

    2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE...............................5

    3.0 SCOPE .........................................................................................................7

    4.0 PROJECT DELIVERABLES AND METHODOLOGY................................................9

    5.0 PROJECT WORK...........................................................................................19

    6.0 PROJECT MANAGEMENT AND CONTROLS......................................................22

    7. 0 PROJECT CLOSE.........................................................................................37

    ATTACHMENTS.................................................................................................37

    REVISION HISTORYREVISION HISTORY

    RREVISIONEVISION NNUMBERUMBER DDATEATE CCOMMENTOMMENT

    1.0 July 27th, 2007 DoIT Project Management Office Revision

    2.0

    2.1

    2.2

    I

  • 7/27/2019 Project Management Plan Workbook

    3/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN II

    ABOUT THIS DOCUMENT PREPARING THE PROJECTABOUT THIS DOCUMENT PREPARING THE PROJECT

    MANAGEMENT PLANMANAGEMENT PLAN

    This workbook is built around helping the project manager and the project team to use the

    Project Management Plan in support of successful projects.

    Project Oversight Process Memorandum DoIT, July 2007Project Oversight Process Memorandum DoIT, July 2007

    1 Project management plan is a formal document approved by the executive sponsor and the

    Department and developed in the plan phase used to manage project execution, control, and

    project close.

    2 The primary uses of the project plan are to document planning assumptions and decisions,

    facilitate communication among stakeholders, and documents approved scope, cost and

    schedule baselines.

    3 A project plan includes at least other plans for issue escalation, change control,

    communications, deliverable review and acceptance, staff acquisition, and risk management.

    4 Project manager means a qualified person from the lead agency responsible for all aspects

    of the project over the entire project management lifecycle (initiate, plan, execute, control,

    close). The project manager must be familiar with project scope and objectives, as well as

    effectively coordinate the activities of the team. In addition, the project manager is

    responsible for developing the project plan and project schedule with the project team toensure timely completion of the project. The project manager interfaces with all areas

    affected by the project including end users, distributors, and vendors. The project manager

    ensures adherence to the best practices and standards of the Department.

    5 Project product means the final project deliverables as defined in the project plan meeting all

    agreed and approved acceptance criteria.

    6 Product development life cycle is a series of sequential, non-overlapping phases comprised

    of iterative disciplines such as requirements, analysis and design, implementation, test and

    deployment implemented to build a product or develop a service.

    CONCEPTS BEHIND PROJECT MANAGEMENT PLANNINGCONCEPTS BEHIND PROJECT MANAGEMENT PLANNING

    WWHATHATISISAAPROJECTPROJECT??

    0 A project is a temporary endeavor undertaken to create a unique product, service orresult PMBOK

    WWHATHATISIS PPROJECTROJECT MMANAGEMENTANAGEMENT??

    Is about how we create and manage a temporaryorganization to deliver the unique

    product, service or result!

    II

  • 7/27/2019 Project Management Plan Workbook

    4/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN III

    It is more about the temporary organization than the unique product, service or result. It

    is more about the interested parties, technical teams and the solution building process!

    PPROJECTROJECTMANAGEMENTMANAGEMENT QQUESTIONSUESTIONS

    1 What is the unique product, service or result?

    2 What do we need to do to accomplish the goal or goals?

    3 How do we know when we are finished?

    4 Who is doing what for whom?

    5 How do we know how we are doing?

    6 How do we handle uncertainty or conflict?

    UUNIQUENIQUE PPRODUCTRODUCT, S, SERVICEERVICEORORRRESULTESULT

    0 Product what are we trying to accomplish and how will we know when we are

    finished?

    7 Product Development

    Project Objectives-> Business Requirements -> System Requirements-> Architecture->

    Solution Design-> Build-> Pilot-> Deploy

    Quality of Product

    0 Trace-ability and Quality Assurance-> Test Cases, Test Planes, Pilot and Deployment

    Success Criteria

    8 Deployment of Product

    9 Resource Requirements and staffing for new product

    10 Deployment Plan and Transition To Operations

    11 Operations and Support for product

    12 Cost- What is the estimated cost of creating and implementing?

    WWHOHOISISDOINGDOING WWHATHATFORFORWWHOMHOM??

    7 Roles and Responsibilities

    III

  • 7/27/2019 Project Management Plan Workbook

    5/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN IV

    0 For Whom

    0 Project Sponsor

    1 Project Funding Source

    2 End User

    3 Beneficiaries of new solution

    1 W ho

    0 Project Team

    1 Subject Matter Experts

    2 Vendors

    3 Operations

    HHOWOWAREAREWEWEDOINGDOING??

    8 Time

    9 Calendar of tasks, task targets

    0 Work Breakdown Structure What needs to be done

    1 Time estimation how much time will be needed?

    10 Budget

    Do we have funding for project and product development, implementation and on-goingsupport?

    0 How much money have we spent?

    1 Are we spending the right amount of money for specific tasks?

    11 Quality and IV&V

    0 Are we doing what we have set out to do?

    12 Metrics

    0 How many changes are we making?

    HHOWOWWELLWELLORGANIZEDORGANIZEDAREAREWEWE

    13 Are we meeting with stake holders and team members?

    IV

  • 7/27/2019 Project Management Plan Workbook

    6/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN V

    14 Have we identified possible roadblocks?

    15 Do we document disagreements and work towards resolutions?

    16 Do we secure formal approval of changes and requirements from stakeholders?

    17 Do we keep stake holders informed?

    PPROJECTROJECT MMANAGEMENTANAGEMENT PPLANLAN

    0 Is about how we create and manage a temporaryorganization to deliver the unique

    product, service or result!

    1 Is not a Microsoft Project file -MS Project is a scheduling aid

    STARTING WITH THE TITLE PAGESTARTING WITH THE TITLE PAGE

    Even the title page has significant information, and assumptions. It tells us what the project callsitself, who the project benefits, who is running the project, and if the Project Charter has been

    revised during the project, which is okay and expected.

    THE TITLETHE TITLE

    Does the title convey to the reader the essence of the project? Is the title of the project required

    by any funding considerations?

    THE EXECUTIVE SPONSOR AND BUSINESS OWNERTHE EXECUTIVE SPONSOR AND BUSINESS OWNER

    Project sponsorship is about the resources required to do the project, whether they are thefinancial resources from state or federal funding/appropriation or from the agencys own

    operating funds.

    Many State of New Mexico projects list the agency Cabinet Secretary as the Executive Sponsorand a combination of the agency CIO and business process owner as the business owners of the

    project.

    The following are some key responsibilities of project sponsorship:

    Appoint an appropriately skilled project manager

    Understand the project complexity

    Champion the project and the team

    Formally manage the project scope

    Provide guidance for business strategies

    V

  • 7/27/2019 Project Management Plan Workbook

    7/50

  • 7/27/2019 Project Management Plan Workbook

    8/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 1

    1.0 PROJECT OVERVIEW1.0 PROJECT OVERVIEW

    The Project Overview sets the stage for the details of the project and begins the story of the project and plan. It

    states the vision for the project (and larger effort, if applicable) in terms of a business need not a solution. It

    answers What is the specific answer that will move the business owner from the current state to a valuable future

    state? The Project Overview describes the difference (gap) between the current state and future state in terms of the

    business need. The content structure order is the introduction, which provides background, the current state, thefuture state, and the need.

    1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT

    In this section should be enough information to portray the situation or problem that the project

    results will resolve, without getting into too much detail.

    Some suggestions:

    The Business Problem and Opportunity section of the one page business case

    Briefly explain the business problem faced by the agency and the opportunity the agencyhas to solve the problem through an IT solution. Briefly present essentials to relay the

    problem and opportunity presented including the agencys business performance,

    mission, goals, objectives, and strategic plan and, if any, cross agency collaborations and

    impacts

    The Problem Statement-Recommendation approach:

    A problem statement that outlines what the existing situation is and how the business of

    the agency is being negatively impacted

    A brief root cause analysis listing factors that if resolved by the project would eliminatethe problem, thus benefiting the agency.

    The project recommendation as the solution, stating clearly that the solution will address

    the root cause issues of the problem, resolving the problem and eliminating the negative

    impact to the agency.

    The current state-future state- need approach

    The current state with its issues is described

    The ideal future state is described as if the solution were in place

    The need provides a description of the gap and tells how the work of the project will

    resolve the gap between the current and future states

    The elevator speech approach

    PAGE 1

  • 7/27/2019 Project Management Plan Workbook

    9/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 2

    Imagine that you are in an elevator with the executive sponsor or Cabinet Secretary and

    can take advantage of the few minutes to pitch the project. You have a limited amount of

    that persons attention to sell the problem and the solution to the problem.

    1.2 FUNDING AND SOURCES1.2 FUNDING AND SOURCES

    This question is also asked in the request for certification and release of funds document. A project isnot a project unless it has actually funding. Provide the funding source(s), amount(s), any

    restrictions, and who the approvers are for the specific sources).

    SOURCESOURCE AMOUNTAMOUNT ASSOCIATEDASSOCIATED

    RESTRICTIONSRESTRICTIONSAPPROVERSAPPROVERS

    1.3 CONSTRAINTS1.3 CONSTRAINTS

    Constraints are factors that restrict the project by scope, resource, or schedule. Constraints caninclude parameters that force the project or work effort to fit a particular timeframe. They lead

    us into a certain way of doing things. Constraints limit the project management teams options.

    Contractual provisions will generally be considered constraints.

    NNUMBERUMBER DDESCRIPTIONESCRIPTION

    1.4 DEPENDENCIES1.4 DEPENDENCIES

    Literally dependencies are items required for something else to happen. My success in being able

    to drive for hundreds of miles is to have enough gas in my cars gas tank, which usually meansfinding an open gas station, having cash or a credit card with which to pay for the gas.

    The table in this section asks for a reference number, a description and whether the dependency

    is: Mandatory dependencies are dependencies that are inherent to the work being done.

    D- Discretionary dependencies are dependencies defined by the project management

    team. This may also encompass particular approaches because a specific sequence of

    activities is preferred, but not mandatory in the project life cycle.

    PAGE 2

  • 7/27/2019 Project Management Plan Workbook

    10/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 3

    E-External dependencies are dependencies that involve a relationship between project

    activities and non-project activities such as purchasing/procurement

    By way of simplification, having enough gas in my cars gas tank would be Mandatory; a

    specific gas station might be considered External, as our favorite corner gas station might not be

    open; Cash or credit card would be Discretionary.Dependencies help the reader and the project manager/team view the playing field realistically.A back-ordered part becomes a dependency for meeting a project schedule.

    NUMBERNUMBER DESCRIPTIONDESCRIPTION TYPE M,D,ETYPE M,D,E

    1.51.5 ASSUMPTIONSASSUMPTIONS

    Assumptions may contain little or significant amount of risk. We can assume that members ofour teams will always show up, and that the project manager will stay through the project, but

    people get sick, or get better offers.

    Here is an exercise. List all of the people, factors, and things we take for granted around the

    project environment that if they were not there would negatively impact the project. We assumevendors will stay in business, and that their key technical staff will remain in place.

    Assumptions are planning factors that, for planning purposes, will be considered true, real, orcertain. Assumptions generally involve a degree of risk. They may be documented here andconverted to formal risks.Assumptions define conditions not known but under which the project

    is planned, budgeted, and managed. They can include anything that supports the scope. Aim to

    tie risks to assumptions and place risks in risk documentation.

    NNUMBERUMBER DDESCRIPTIONESCRIPTION

    1.6 INITIAL PROJECT RISKS IDENTIFIED1.6 INITIAL PROJECT RISKS IDENTIFIED

    In this section identify and describe how each risk will be managed. Include the steps that willbe taken to maximize activity that will result in minimizing probability and impact of each risk.

    PAGE 3

  • 7/27/2019 Project Management Plan Workbook

    11/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 4

    Section 6.1 Risk Management calls for an understanding of how the project will be

    handling risks.

    Projects By their temporary nature and unique outcomes are risky Project management reducesthe impact of the threats by making them explicit and the working on reducing their impacts or

    by eliminating those Risks are always around. A project is not judged on how many risks are

    identified, but by its strategy and success at planning through the risks.

    See 6.1.2 Project Risk Identification for a listing of typical project risks.

    Description -Probability Impact

    Mitigation Strategy

    Contingency Plan

    Risk Name should easy reflect the challenge without detail

    Description - Describe the risks characteristics and explain why this risk is perceived to havethe potential to affect the outcome of the project .

    Probability and Impact -- Probability should be measured as the likelihood of that the risk will

    occur. Impact should be measured in terms of deviations from the schedule, effort, or costs from

    the schedule if risks occur.

    Probability Levels: Certain, Expected, Likely, Possible, Unlikely

    Impact Levels: Very High, High, Medium, Low, Very Low

    Mitigation Strategy - Identify what actions can be taken in order to reduce the probability of therisk, or to reduce its impact on the project.

    Contingency Plan Identify what actions will be taken when the risk materializes and threatensthe scope, budget, or the schedule of the project.

    [Risk 1 Name]

    Description -Probability and Impact

    Mitigation Strategy

    Contingency Plan

    PAGE 4

  • 7/27/2019 Project Management Plan Workbook

    12/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 5

    [Risk 2 Name]

    Description -Probability and Impact

    Mitigation Strategy

    Contingency Plan

    2.0 PROJECT AUTHORITY AND ORGANIZATIONAL2.0 PROJECT AUTHORITY AND ORGANIZATIONAL

    STRUCTURESTRUCTURE

    The Project Organization describes the roles and responsibilities of the project team. It also

    identifies the other organizational groups that are part of the project and graphically depicts thehierarchical configuration of those groups. It exists to clarify interaction with the project team.

    2.1 STAKEHOLDERS2.1 STAKEHOLDERSList all of the major stakeholders in this project, and state why they have a stake. Stakeholders are

    individuals and organizations that are actively involved in the project, or whose interests may be

    positively or negatively affected as a result of project execution or project completion. They may also

    exert influence over the project and its results.

    The PMBOK of the Project Management Institute defines project stakeholders:

    Project stakeholders are individuals and organizations that are actively involved in the

    project, or whose interests may be affected as a result of project execution or project

    completion. They also exert influence over the projects objectives and outcomes.

    This all encompassing definition would have us think about such stakeholders as:

    Cabinet Secretaries

    Agency Division directors

    CIO-IT Leads

    Project Manager

    IT operations staff

    Business process owners

    System user representatives

    Key project team members

    Training staff

    The Various stake holders should also have their stake in the project spelled out.

    PAGE 5

  • 7/27/2019 Project Management Plan Workbook

    13/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 6

    NAMENAME SSTAKETAKEININ PPROJECTROJECT OORGANIZATIONRGANIZATION TTITLEITLE

    2.2 PROJECT GOVERNANCE STRUCTURE2.2 PROJECT GOVERNANCE STRUCTURE

    2.2.1 D2.2.1 DESCRIBEESCRIBETHETHEORGANIZATIONALORGANIZATIONALSTRUCTURESTRUCTURE O ORGRG CCHARTHART

    A key element in the project governance is the Organization chart for the project.Describe theprocess that is going to be used to manage the scope of the project. Make sure to address

    managing stakeholder expectations. Describe at a high-level how issues will be escalated and

    resolved and how change requests will be processed.

    PAGE 6

  • 7/27/2019 Project Management Plan Workbook

    14/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 7

    2.2.2 D2.2.2 DESCRIBEESCRIBETHETHEROLEROLEANDANDMEMBERSMEMBERSOFOFTHETHEPROJECTPROJECTSTEERINGSTEERINGCOMMITTEECOMMITTEE

    In many projects the business owners sit as the members of the steering committee. The role of

    the steering committee is set the tone for the project, manage the project charter authorizing the

    role of the project manager, manage the scope of the project in terms of cost, schedule andquality of the project, deal with issues escalated to them, and also to accept or deny project team

    recommendations especially in go-no go decision matters.

    2.2.1 O2.2.1 ORGANIZATIONALRGANIZATIONAL BBOUNDARIESOUNDARIES,, INTERFACESINTERFACESANDANDRESPONSIBILITIESRESPONSIBILITIES

    Use this section to describe any special considerations regarding contact between the projectteam, the project manager, and individuals from various organizations involved in the project:

    The key interface between the organizations is between the Project Manager from the DoIT and

    the Project Managers from Contracting Vendor and between the Project Manager and the

    assigned Team Leaders.. The primary methods utilized will be the Status Report/Briefing, ad-

    hoc meetings, electronic mail, and phone conversations. Interaction may occur directly betweenthe technical components of all teams. However, overall task direction can only come from the

    Project Manager. Final decisions will be made at the Steering Committee level.

    2.3 EXECUTIVE REPORTING2.3 EXECUTIVE REPORTING

    Use this section to describe the method that will be used to effectively disseminate informationto the project s Executive Sponsor and/or the Business Owner and other governing bodies such

    as the Office of the Chief Information Officer and the Information Technology Commission.

    Indicate how, when, what type of information, to whom, and how often project related

    information will be conveyed. This section does not replace the need for the project manager todevelop a detail communication plan as part of the project plan.

    Keep In mind here the projects obligation: . For all projects that require Department oversight,

    the lead agency project manager shall submit an agency approved project status report on a

    monthly basis to the Department. PROJECT OVERSIGHT PROCESS memorandum

    3.0 SCOPE3.0 SCOPE

    3.1 PROJECT OBJECTIVES3.1 PROJECT OBJECTIVES

    As the project progresses it must be able to answer the following question as Yes!: Has the

    project established the ability to verify that business requirements can be traced through

    technical design, system building or software coding/ configuration and test phases to verify thatthe system performs as intended and contains no unnecessary elements?

    PAGE 7

  • 7/27/2019 Project Management Plan Workbook

    15/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 8

    3.1.1 B3.1.1 BUSINESSUSINESS OOBJECTIVESBJECTIVES

    Business objectives are the high level business requirements of the project. The following tablecomes from a requirement collection template. It suggests the ingredients of a well written

    business objective.

    Description

    Rationale

    Acceptance/Fi

    t Criteria

    The typical problems with business objectives include: Lumping more than one objective into a business objective

    Use of too many loose phrases such as more, better, improve, fix, solve

    3.1.2 T3.1.2 TECHNICALECHNICAL OOBJECTIVESBJECTIVES

    Technical objectives relate to the technical issues or goals the project is to accomplish. These

    maybe related to acquisition of hardware, software, consulting, training, application development

    and other hows of the project.

    The business requirement table presented in the section above is useful here as well, with one

    addition, the parent Objective/ requirement which should be one of the Business Objectivespresented.

    Parent

    Requirement

    #

    Description

    Rationale

    Source Source

    Document

    Acceptance/Fi

    t Criteria

    PAGE 8

    NNUMBERUMBER DDESCRIPTIONESCRIPTION

    Bus. Objective 1

    NNUMBERUMBER DDESCRIPTIONESCRIPTION

    Tech. Objective 1

  • 7/27/2019 Project Management Plan Workbook

    16/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 9

    Because technical objectives should be trace-able to specific Business Objective, when there is

    more than one business objective, it would be advisable to present the technical objectives in ahierarchical manner: The following is an example of such a presentation of technical objectives.

    NNUMBERUMBER DDESCRIPTIONESCRIPTION

    Bus. Objective 1 Reduce cost of government operations through IT

    Tech. Objective 1 Identity Management and Directory Services

    Tech. Objective 2 Common Business Functions and data interchange and discovery

    methodology for all agencies to access and use for report creation.

    Bus. Objective 2 Reduce cost of IT operations through an enterprise Model

    Tech. Objective 4 Common IT service architecture and operating environment,including Standards, SLA (Service Level Agreements) approach,

    governance model and improved funding mechanism

    3.2 PROJECT EXCLUSIONS3.2 PROJECT EXCLUSIONS

    The project should list items, features, would like to haves that stakeholders might associate with

    this project but that the project would not be providing.

    3.3 CRITICAL SUCCESS FACTORS3.3 CRITICAL SUCCESS FACTORSIdentify the critical success factors for achieving success in this project. Metric are key to

    understanding the ability of the project to meet the end goals of the Executive Sponsor and the

    Business Owner, as well as the ability of the project team to stay within schedule and budget.

    NUMBERNUMBER DESCRIPTIONDESCRIPTION

    QUALITY METRICS1

    4.0 PROJECT DELIVERABLES AND METHODOLOGY4.0 PROJECT DELIVERABLES AND METHODOLOGY

    A deliverable is any measurable, tangible, verifiable outcome, result, or item that is required to

    complete a project or part of a project. The term is often used more narrowly in reference to an

    external deliverable (i.e. this deliverable is subject to approval by the project sponsor orcustomer). Analyze the project scope and objectives outlined in the Project Proposal and Charter

    to develop a list of deliverables.

    PAGE 9

  • 7/27/2019 Project Management Plan Workbook

    17/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 10

    In its efforts to move from the high level business objectives to the desired end product/service

    the project team will need to deliver specific documents or work products. The State of NewMexico Project Management Methodology distinguishes between the project and the product.

    Project Deliverables relate to how we conduct the business of the project. Product Deliverablesrelate to how we define what the end result or product will be, and trace our stakeholder

    requirements through to product acceptance, and trace our end product features and attributesback to our initial requirements

    4.1 PROJECT MANAGEMENT LIFE CYCLE4.1 PROJECT MANAGEMENT LIFE CYCLE

    The project should present here a summary of its approach, and its phases:

    Phase Summary of Phase Key Deliverables

    Here is some background:

    The following is a description of a Project Management Life Cycle based on the PMI (Project

    Management Institutes PMBOK.

    Key Project Deliverables of each of these five processes are identified as including the

    following:

    PAGE 10

  • 7/27/2019 Project Management Plan Workbook

    18/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 11

    Initiating:

    Project Charter

    Project Scope

    Business Requirements Business Case

    Assumptions

    Constraints

    Authorization to proceed with planning

    Planning:

    Project Plan

    Critical success factors

    Work Break down Structures

    Project Schedule

    Controlling:

    Performance/Status Reports

    Corrective Action

    Measurement Metrics

    Plan Change Requests

    Product Change Request

    Risk ManagementIssues Management

    Execution:

    Actual efforts

    Project Deliverables completion

    Closing:

    Deliverable or Product Acceptance

    Lessons Learned

    As a companion to the five major project processes, PMI through the PMBOK has instituted

    nine management focuses that will be followed in this project:

    Integration Management

    PAGE 11

  • 7/27/2019 Project Management Plan Workbook

    19/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 12

    The purpose of integration management is to ensure coordination of the different elements of a

    project to achieve the needs and expectations of project stakeholders. It includes project plan

    development, project plan execution, and integrated overall change control.

    Scope Management

    The purpose of scope management is to ensure the work performed in a project is necessary tothe successful completion. It includes initiation, scope planning, scope definition, scope

    verification, and scope change control.

    Time Management

    The purpose of time management is to ensure a project completes in a timely manner. It includesactivity definition, activity sequencing, activity duration estimating, schedule development, and

    schedule control.

    Cost Management

    The purpose of cost management is to ensure a project completes within its approved budget. It

    includes resource planning, cost estimating, cost budgeting, and cost control.

    Quality Management

    The purpose of quality management is to ensure the products and services produced by a project

    satisfy the needs for which the project was undertaken. Quality the satisfaction of project

    needs is a measure of adherence to stated requirements combined with fitness for use. TheQuality Management Knowledge Area includes quality planning, quality assurance, and quality

    control.

    Human Resource Management

    The purpose of human resource management is to ensure effective use of the people involved in

    a project. It includes organizational planning, staff acquisition, and team development.

    Communications Management

    The purpose of communications management is to ensure timely and effective flow of

    information for a project. It includes communication planning, information distribution,

    performance reporting, and administrative closure.

    Risk Management

    The purpose of risk management is to ensure the identification, analysis, and appropriateresponse to the risks encountered by a project. It includes risk management planning, risk

    identification, qualitative risk analysis, quantitative risk analysis, risk response planning, and risk

    monitoring and control.

    Procurement Management

    The purpose of procurement management is to ensure effective acquisition of products andservices from sources external to the projects organization. It includes procurement planning,

    solicitation planning, solicitation, source selection, contract administration, and contract closeout.

    PAGE 12

  • 7/27/2019 Project Management Plan Workbook

    20/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 13

    4.1.1 P4.1.1 PROJECTROJECT MMANAGEMENTANAGEMENT DDELIVERABLESELIVERABLES

    Project Deliverables are work products or artifacts that are driven by the project management

    methodology requirements and standard project management practices regardless of the productrequirements of the project. Examples are project, phase, and iteration plans, and project

    schedules. Project Deliverables must be reviewed and approved by the projects Executive

    Sponsor prior to their implementation.

    Description - Deliverable description conveys the features and/or the functions that will beincluded in the project product. Each deliverable is a subsidiary element of the project product

    (final deliverable), each with its own separate but interdependent deliverable scope

    Deliverable Acceptance Criteria - Acceptance Criteria are quantifiable measures of the success

    of each deliverable (or set of deliverables). Its how the executive sponsor and the project team

    know when a deliverable is acceptable and can be approved. Acceptance criteria are similar tomeasures of success except they are for a specific deliverable. The criteria may include

    functional and technical testing and utility verification at defined points in the process;methodology and criteria should be published.

    Standards for Content and Format - Standards for Content and Format describe the format

    that the executive sponsor can expect to receive the deliverable. This section ensures that the

    deliverable will be usable to meet its objective upon delivery. The tools, techniques, andprocesses used to develop the deliverable must compliment the executive sponsors environment

    and enable the executive sponsor to use the deliverable

    Quality Review - Quality review provides the opportunity for peer and cross-discipline reviews

    of the deliverable. This process will improve the Quality Control metrics by reducing the testing

    cycle and the number of exceptions reported by Quality Control and eventually the executivesponsor.

    4.1.1.1 [Deliverable 1 Name]

    Description - Deliverable Acceptance Criteria - .

    Standards for Content and Format -

    Quality Review -

    4.1.1.2 [Deliverable 2 Name]

    Description - Deliverable Acceptance Criteria -

    PAGE 13

  • 7/27/2019 Project Management Plan Workbook

    21/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 14

    Standards for Content and Format -

    Quality Review -

    4.1.2 D4.1.2 DELIVERABLEELIVERABLE AAPPROVALPPROVAL AAUTHORITYUTHORITY DDESIGNATIONSESIGNATIONS

    Complete the following table to identify the deliverables this project is to produce, and to namethe person or persons who have authority to approve each deliverable. Each deliverable should

    be assigned a control number for tracking. The date approved column serves as a log of wheneach deliverable was approved.

    DDELIVERABLEELIVERABLE

    NNUMBERUMBERDDELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W(WHOHO

    CANCANAPPROVEAPPROVE))DDATEATE

    AAPPROVEDPPROVED

    PRJ-DEL-001 Project Management Plan (PMP)

    4.1.3 D4.1.3 DELIVERABLEELIVERABLE AACCEPTANCECCEPTANCE PPROCEDUREROCEDURE

    Describe the process that this project will use for the formal acceptance of all deliverables.

    Generally, a Deliverable Acceptance Form is utilized with specific timeframes allowed forreview, approval, rework, etc. Issues identified in this Deliverable Acceptance Procedure should

    follow the Issues Escalation Process that is defined in a later section.

    4.2 PRODUCT LIFE CYCLE4.2 PRODUCT LIFE CYCLE

    This section is intended to have the project present the product development life cycle. During

    the project management lifecycle, agencies shall select and implement a phase product

    development lifecycle methodology approved by the Department. PROJECT OVERSIGHTPROCESS Memorandum

    Phase Summary of Phase Key Deliverables

    PAGE 14

  • 7/27/2019 Project Management Plan Workbook

    22/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 15

    The typical approach is one of the SDLC, solution/software development life cycle. One

    example is presented here.

    What is a product life cycle?

    A collection of generally sequential project phases whose name and number aredetermined by the control needs of the organization or organizations involved in the

    project. Project Management Institutes PMBOK Guide 2000, Glossary p. 205

    .

    The Product Life Cycle includes identifiable and distinct phases, each of which encompasses the

    critical five project management processes. Each phase has its own initiation, plan, execute andcontrol aspects and each will have its own close process. The close process or gate will include

    project approval to enter the next phase of the project.

    Where the DoIT Project Management Office has not yet published product life cycle

    development templates to use, projects have used documents similar to those mentioned in thisapproach. The following is a high level description of project document-deliverables per phase

    Initiation

    Product development Rationale

    End Vision and purpose

    Project Scope

    Plan

    Work Breakdown Schedules

    Project Schedule

    Business Requirements

    Initial technical requirements

    Initial deployment and transition to operations plan

    Initial Operations and Support Plan

    Define

    PAGE 15

  • 7/27/2019 Project Management Plan Workbook

    23/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 16

    Analysis of the current state

    Technical Requirements

    Systems Specifications Requirements

    Initial Training Requirements

    System Architecture Document

    System Use Cases where appropriate

    Test Cases or system acceptance criteria

    Revised deployment and transition to operations plan

    Revised Operations and Support Plan

    Design

    Systems Design Documents

    Training Curriculum

    Revised deployment and transition to operations plan

    Revised Operations and Support Plan

    Build

    Systems Design Documents applied

    Training Materials ready

    Revised deployment and transition to operations plan

    Revised Operations and Support Plan

    Pilot Acceptance CriteriaPilot

    Systems Design Documents applied

    Training Materials ready

    Revised deployment and transition to operations plan

    Revised Operations and Support Plan

    Pilot Run, Evaluated

    Pilot Acceptance

    Deploy

    Systems Design Documents applied

    Training Materials Used

    Deployment and transition to operations plan

    Operations and Support Plan

    Close

    PAGE 16

  • 7/27/2019 Project Management Plan Workbook

    24/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 17

    Systems Acceptance by Operations

    4.2.1 T4.2.1 TECHNICALECHNICAL SSTRATEGYTRATEGY

    Discuss the key technical strategies for achieving success in this project. Among these might be:

    Build-reuse-buy approach

    Commercial Off The Shelf COTS- criteria development

    Hardware-Operating System choices

    New Mexico Enterprise IT Standards or exceptions or requests for new standards

    Hosting location with justification

    Outsourcing with justification

    Adoption of new technologies

    4.2.2 P4.2.2 PRODUCTRODUCTANDAND PPRODUCTRODUCT DDEVELOPMENTEVELOPMENT DDELIVERABLESELIVERABLES

    Product Deliverables are work products or artifacts that are driven by the product managementmethodology requirements and standard project management practices regardless of the product

    requirements of the project. Examples are project, phase, and iteration plans, and project

    schedules. Product Deliverables must be reviewed and approved by the projects ExecutiveSponsor prior to their implementation.

    Description - Deliverable description conveys the features and/or the functions that will beincluded in the project product. Each deliverable is a subsidiary element of the project product

    (final deliverable), each with its own separate but interdependent deliverable scope

    Deliverable Acceptance Criteria - Acceptance Criteria are quantifiable measures of the success

    of each deliverable (or set of deliverables). Its how the executive sponsor and the project teamknow when a deliverable is acceptable and can be approved. Acceptance criteria are similar to

    measures of success except they are for a specific deliverable. The criteria may include

    functional and technical testing and utility verification at defined points in the process;methodology and criteria should be published.

    Standards for Content and Format - Standards for Content and Format describe the formatthat the executive sponsor can expect to receive the deliverable. This section ensures that the

    deliverable will be usable to meet its objective upon delivery. The tools, techniques, and

    processes used to develop the deliverable must compliment the executive sponsors environment

    and enable the executive sponsor to use the deliverable

    Quality Review - Quality review provides the opportunity for peer and cross-discipline reviews

    of the deliverable. This process will improve the Quality Control metrics by reducing the testing

    PAGE 17

  • 7/27/2019 Project Management Plan Workbook

    25/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 18

    cycle and the number of exceptions reported by Quality Control and eventually the executive

    sponsor.

    4.2.2.1 [Deliverable 1 Name]

    Description - Deliverable Acceptance Criteria - .

    Standards for Content and Format -

    Quality Review - .

    4.2.2.2 [Deliverable 2 Name]

    Description - Deliverable Acceptance Criteria -

    Standards for Content and Format -

    Quality Review -

    4.2.3 D4.2.3 DELIVERABLEELIVERABLE AAPPROVALPPROVAL AAUTHORITYUTHORITY DDESIGNATIONSESIGNATIONS

    Complete the following table to identify the deliverables this project is to produce, and to namethe person or persons who have authority to approve each deliverable. Each deliverable should

    be assigned a control number for tracking. The date approved column serves as a log of when

    each deliverable was approved.

    DDELIVERABLEELIVERABLE

    NNUMBERUMBERDDELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W(WHOHO

    CANCANAPPROVEAPPROVE))DDATEATE

    AAPPROVEDPPROVED

    PRJ-DEL-001 Project Management Plan (PMP)

    4.2.4 D4.2.4 DELIVERABLEELIVERABLE AACCEPTANCECCEPTANCE PPROCEDUREROCEDURE

    Describe the process that this project will use for the formal acceptance of all deliverables.Generally, a Deliverable Acceptance Form is utilized with specific timeframes allowed forreview, approval, rework, etc. Issues identified in this Deliverable Acceptance Procedure should

    follow the Issues Escalation Process that is defined in a later section.

    PAGE 18

  • 7/27/2019 Project Management Plan Workbook

    26/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 19

    5.0 PROJECT WORK5.0 PROJECT WORK

    5.1 WORK BREAKDOWN STRUCTURE (WBS)5.1 WORK BREAKDOWN STRUCTURE (WBS)

    A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total

    work scope of the project. Each descending level represents an increasingly detailed definitionof the project work. Include at least the highest level grouping for the project in this section

    Describe the work activities that comprise the work breakdown structure (WBS) or the workpackages within the WBS. Identify the WBS element or other work package identifier and

    provide a general description of the tasks or activities, the definition or objectives, and the

    milestones and deliverables of each work package.

    IdentifierWork PackageDescription

    Definition/Objective Milestone/Deliverable

    5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE

    The project timeline is a high-level view of project activities with a focus on project milestones.

    The project timeline does not replace the need for a detailed project schedule and it is to

    highlight key events such as deliverable due dates and when go/no-go decisions are made.

    The table below should provide a high level view of the project time line, or a summary-levelGantt chart can be used to meet the timeline requirement.

    Please provide a more detailed project schedule as an attachment to this plan

    Identifier Task/ActivityName ResourceName Milestone(Y/N) Effort/Duration Start Finish DependentTask

    PAGE 19

  • 7/27/2019 Project Management Plan Workbook

    27/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 20

    5.3 PROJECT BUDGET5.3 PROJECT BUDGETCosts estimates are the costs applied to an activity in a project by assigning resources with

    associated rates or fees. Resources can include equipment, material, technology, processing

    cycles, or people. The total cost is critical and should be consistent with the proposal; includebreakdowns as needed. Match these cost estimates with the actual billed amounts. Use an

    appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or

    deliverable).

    Identifier Work Package or Budget Category Cost

    Or..

    Phase / Activity Associated Deliverables EstimatedBudget

    Umbrella Tasks

    Phase 1

    Project Preparation

    & Planning

    Project plan

    Project Schedule

    Phase 2

    Phase 3

    Phase 4

    Project Closing

    TOTALS

    5.4 PROJECT TEAM5.4 PROJECT TEAM

    PAGE 20

  • 7/27/2019 Project Management Plan Workbook

    28/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 21

    5.4.1 P5.4.1 PROJECTROJECT TTEAMEAM OORGANIZATIONALRGANIZATIONAL SSTRUCTURETRUCTURE

    Insert a graphical Organization Chart here. The Organizational Structure (OS) is a hierarchical

    configuration defining levels of program management and may identify all project personnel.The OS should be simple and straightforward. Include role names and peoples names.

    Consider identifying the core project team by shading their respective boxes on the chart. On

    complex projects, consider using a second OS to identify core project team. The OS can also beused for management reporting.

    5.4.2 P5.4.2 PROJECTROJECT TTEAMEAM RROLESOLESANDAND RRESPONSIBILITIESESPONSIBILITIES

    List the team members, their role, responsibility and functional manager. Make sure to include a

    comprehensive listing including those from the organization managing the project, business

    members involved to ensure business objectives are met and the vendor members that may havea specific role.

    RROLEOLE RRESPONSIBILITYESPONSIBILITY NNAMEAME FFUNCTIONALUNCTIONAL

    AAREAREA

    5.5 STAFF PLANNING AND RESOURCE ACQUISITION5.5 STAFF PLANNING AND RESOURCE ACQUISITION

    Complete the chart below identifying the project team members and details concerning theirproject commitment. Type should be State, Contract, Customer (Business Owner), or Vendor.

    5.5.1 P5.5.1 PROJECTROJECT SSTAFFTAFF

    Resource

    Cost

    Estimate

    Estimated

    Hours Availability Skill Set Work Product/Deliverable

    PAGE 21

  • 7/27/2019 Project Management Plan Workbook

    29/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 22

    5.5.2 N5.5.2 NONON-P-PERSONNELERSONNELRESOURCESRESOURCES

    Use this section to list services or product (HW/SW and such) needed for project

    ResourceCostEstimate

    Estimatedunits/hours Availability Source

    WorkProduct/Deliverable

    5.6 PROJECT LOGISTICS5.6 PROJECT LOGISTICS

    Logistics describes how the project manager, project team, the business owner/customer and any

    vendor resources will physically work together. Include anything to do with moving or starting

    resources. Identify a role to coordinate logistics with the business owner/customer and vendors.

    Logistics includes factors, issues, notes, etc. relating to operational details (space, materials,access, etc.) at the customer or vendor site. It can also be used to describe the need and use of a

    forthcoming logistics document. Cross-reference any risk, assumption or exclusion that isrelated to logistics. Training specifically related to project team members should be included

    here.

    5.6.1 P5.6.1 PROJECTROJECT TTEAMEAM TTRAININGRAINING

    Describe training if any needed by project team members. This is not to include training for endusers, system administrators or business owners; those should be handled within a training

    document or part of the transition to operations planning.

    Resource

    Cost

    Estimate

    Estimated

    Hours Availability Skill Set Work Product/Deliverable

    6.0 PROJECT MANAGEMENT AND CONTROLS6.0 PROJECT MANAGEMENT AND CONTROLS

    6.1 RISK AND ISSUE MANAGEMENT6.1 RISK AND ISSUE MANAGEMENT

    PMBOK:

    PAGE 22

  • 7/27/2019 Project Management Plan Workbook

    30/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 23

    Risk: An uncertain event or condition that, if it occurs, has a positive or negative effect on a

    projects objectives.

    Issue: A point or matter in question or dispute, or a point or matter that is not settled and isunder discussion or over which there are opposing views or disagreements.

    Both Risks and Issues can significant impact a projects success, and both should be handled insimilar ways.

    Project Management IS Risk Mitigation. Is about how we create and manage a

    temporaryorganization to deliver the unique product, service or result!

    By providing structure to the temporary organization and the solutiondevelopment/deployment process we reduce the risk of counterproductive Chaos.

    By communicating with stakeholders we keep them in the loop, and often involve them

    in risk mitigation or lessening its impact

    By acknowledging that there is risk, we can structure ways of avoiding or effectivelydealing with specific risk.

    6.1.1 R6.1.1 RISKISKMMANAGEMENTANAGEMENT SSTRATEGYTRATEGY

    Provide a detailed explanation on the strategy for how risks are identified, analyzed/ quantified,

    mitigated, reported, escalated and tracked. Include the use of tools such as project management

    software, forms, and templates. A separate risk management plan may also be developed ifneeded for the project and included as an Appendix to this document. If that is the case, a high

    level summary of this plan needs to be included here with the specific reference.

    6.1.2 P6.1.2 PROJECTROJECT RRISKISKIIDENTIFICATIONDENTIFICATION

    Organizational

    Project Organization

    Resource

    Staff, Skills, Etc

    External Risks

    Vendors, suppliers

    Planning Risks

    Uncertainty, Complexity

    Technical Risks Requirements, Reliability

    Organizational Risks

    Poor Initiation

    Sponsor Changes

    PAGE 23

  • 7/27/2019 Project Management Plan Workbook

    31/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 24

    Priorities Change

    Unrealistic Deadline

    Funding

    Lack of internal stakeholder support

    Delayed Approval/Decisions

    Lack of Technical or business direction

    Project Manager Experience or inexperience

    No organization history

    No established project templates or processes

    No organizational understanding of RISK

    Resource Risks

    Lack of Resources

    Staff Availability

    Staff Inexperience

    Holiday and Vacation

    Personal or Family Illness

    Retirement or resignations

    Overbooking

    Personalities

    Ineffective training

    Contractor or Consultant

    Team Morale

    Ineffective Communication

    External Risks

    Vendor/Supplier

    PAGE 24

  • 7/27/2019 Project Management Plan Workbook

    32/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 25

    Timing

    Quality

    Lack of incentive or penalty

    Misunderstood requirements

    Statement of Work incomplete

    Too Many External vendors or suppliers

    Weather Issues

    Key Staff issues or sickness

    Dependencies on other projects

    Purchasing or hiring

    Planning Risks

    Lack of Planning

    Lack of Anticipation

    Poor Estimation

    Lack of stakeholder involvement

    Lack of end customer involvement

    Poor Project Definition

    Unrealistic expectations

    Number of implementation sites

    Training process

    Government or Regulatory Changes

    Poor Communications

    Poorly Run or attended meetings

    No record keeping

    PAGE 25

  • 7/27/2019 Project Management Plan Workbook

    33/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 26

    Technical Risks

    Incomplete Requirements

    Scope Creep

    No or Poor Change Management Process

    Complex or Overly Complex Designs

    Technology Readiness

    Technical Dependencies

    No Test Environment

    Cutting Edge Components

    Inadequate Documentation

    Vendor Technical Support

    Code or Patch directly to Production Environment

    No Pilot

    PAGE 26

  • 7/27/2019 Project Management Plan Workbook

    34/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 27

    6.1.3 P6.1.3 PROJECTROJECT RRISKISKMMITIGATIONITIGATION AAPPROACHPPROACH

    6.1.4 R6.1.4 RISKISKRREPORTINGEPORTINGANDAND EESCALATIONSCALATION SSTRATEGYTRATEGY

    The DoIT Risk and Issue Log Template uses a calculation based on the following values:

    Probability Levels: Certain, Expected, Likely, Possible, Unlikely

    Impact Levels: Very High, High, Medium, Low, Very Low

    The following table suggests the values at which the risks should be tracked, reported and

    escalated:

    Minimum risk - Acceptable

    Some risks - Monitor at PM/Team Level

    High risks - Active monitoring with ongoing Contingency/Mitigation activity

    Show stoppers - Active participation with steering committee to mitigate

    This is an example of the calculation that indicates a serious risk that needs to be escalated to the

    Steering Committee.

    Number Risk Probability Impact R

    1 Example Certain High 0

    PAGE 27

  • 7/27/2019 Project Management Plan Workbook

    35/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 28

    6.1.5 P6.1.5 PROJECTROJECT RRISKISKTTRACKINGRACKING AAPPROACHPPROACH

    In the DoIT Risk and Issue Template the risk log provides a risk log that not only calculates the

    risk level, but also provides space for inputting the contingency and mitigation plan summary

    highlights.

    Number Risk Probability Impact Rating Contingency

    Plan

    Mitigation

    Plan

    1 Example Certain High 0.7125

    6.1.6 ISSUE MANAGEMENT6.1.6 ISSUE MANAGEMENT

    For either type of issue, projects should consider using the DoIT Risk and Issue Log template as

    is presented below:

    Issue Log:

    IssueNo. Issue

    PersonResponsible

    Date OpenMonth/Day

    1 Example ProjectManager

    03/

    Issue Form

    IssueNo.

    (FromIssue

    Log)

    ResponsibleParty (From

    Issue Log)

    Level(High,Medium,

    Low)

    Class(Impact

    Area)

    DateOpened(FromIssue

    Log)

    Date

    Closed Originator1 Project Manager 03/15/07

    Issue (From Issue Log)Example

    Consequence(s)If not resolved this issue could delay the project by 30 days, resulting in a fine for non-complian

    Resolution

    Hiring a contractor could resolve this delay at a cost less than the fine for non-complian

    PAGE 28

  • 7/27/2019 Project Management Plan Workbook

    36/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 29

    6.1.6.1 Internal Issue Escalation and Resolution Process

    This internal process is provided for issues that involve project resources, processes, procedures,

    or methodology that should be resolved within the Division that is responsible for managing the

    project without affecting the overall project schedule, cost, or quality. This process should beused for improving project processes as the project is executed and where the implementation of

    such improvements should not be postponed to Lessons Learned during Project Close.

    6.1.6.2 External Issue Escalation and Resolution Process

    The external process is provided for issues that involve project resources, processes, procedures,or methodology that cannot be resolved within the Division that is responsible for managing the

    project without affecting the overall project schedule, cost, or quality.

    6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V

    Independent Verification and Validation (IV&V) means the process of evaluating a system to

    determine compliance with specified requirements and the process of determining whether theproducts of a given development phase fulfill the requirements established during the previous

    stage, both of which are performed by an organization independent of the development

    organization. Describe the process that will be employed to meet IV&V requirements.

    See Project Charter for Certification Workbook for some details.

    6.3 SCOPE MANAGEMENT PLAN6.3 SCOPE MANAGEMENT PLAN

    Describe the process that is going to be used to manage the scope of the project. Make sure to

    address managing stakeholder expectations.

    6.3.1 CHANGE6.3.1 CHANGE CONTROLCONTROL

    6.3.1.1 Change Control Process

    Change Control establishes how change will be managed, including capturing, tracking,

    communicating, and resolving change. Due to much ambiguity regarding change, it is vital thatwe document and discuss the change process with the executive sponsor.

    PAGE 29

  • 7/27/2019 Project Management Plan Workbook

    37/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 30

    6.3.1.2 Change Control Board (CCB)

    Insert a graphic or textual description identifying the Change Control Board (or function) for this

    project. The CCB may be an individual or group of individuals authorized to approve changes tothe project plan.

    A project might want to formalize Change Management through a form such as shown below:

    PPROJECTROJECT CCHANGEHANGE RREQUESTEQUEST

    PROJECT:PROJECT:

    AGENCY: DATE:

    PROJECTMANAGER:

    PROJECT #:

    AGENCYAND PROJECT INFORMATION:

    REQUESTED BY: DATE:

    AUTHORIZED BY: DATE:

    DESCRIPTION:

    PAGE 30

  • 7/27/2019 Project Management Plan Workbook

    38/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 31

    IMPACT: Technical Schedule Cost Other

    ACTION PLAN:

    MARKONE:

    THIS CHANGE: Is Is NOT Within Scope.

    THIS CHANGEIS: Accepted Denied On Hold Delayed

    6.4 PROJECT BUDGET MANAGEMENT6.4 PROJECT BUDGET MANAGEMENT

    Costs estimates are the costs applied to an activity in a project by assigning resources with

    associated rates or fees. Resources can include equipment, material, technology, processingcycles, or people. The total cost is critical and should be consistent with the proposal; include

    breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an

    appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or

    deliverable).

    6.4.1 B6.4.1 BUDGETUDGET TTRACKINGRACKING

    6.5 COMMUNICATION PLAN6.5 COMMUNICATION PLAN

    Communication planning involves determining the information and communication needs of thestakeholders, executive sponsors, project team and others as needed. The communication plan

    needs to address who needs what information, when they will need it, how it will be given to

    them, and by whom. The complexity of the project may require a separate communication plan;however a high level summary of that plan will need to be included here and a reference made to

    the appropriate Appendix.

    PAGE 31

  • 7/27/2019 Project Management Plan Workbook

    39/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 32

    6.5.1 C6.5.1 COMMUNICATIONOMMUNICATION MMATRIXATRIX

    6.5.2 S6.5.2 STATUSTATUS MMEETINGSEETINGS

    6.5.3 P6.5.3 PROJECTROJECT SSTATUSTATUS RREPORTSEPORTS

    6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)The Project Manager and Executive Sponsor define the project metrics that will be used to

    control the project. Each project will need to have an established metrics program. Metrics are

    collected for measuring the progress of a project against its planned budget, schedule, resourceusage, and error rates, and of establishing a historical database, which will aid in planning and

    forecasting future projects. At a minimum metrics must be established for time (schedule), cost

    (budget) and quality.

    Project Area Category Measure

    Example used by another state:

    Common Project Issue Area Category Measure

    Schedule and Progress Milestone Performance Milestone Dates

    Work Unit Progress Component Status Requirement Status Test CaseStatus Critical Paths Tested Problem Report Status ReviewsCompleted Change RequestStatus

    Incremental Capability Build Content Component Build Content Function

    Resources and Cost Personnel Effort Staff Experience StaffTurnover

    Financial Performance Earned Value Cost

    Availability Resource Availability Dates Resource Utilization

    Growth and Stability Product Size and Stability Lines of Code Components Database Size

    PAGE 32

  • 7/27/2019 Project Management Plan Workbook

    40/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 33

    Functional Size and Stability Requirements Function Points Change Request Workload

    Product Quality Defects Problem Reports DefectDensity

    Complexity Cyclomatic Complexity

    Rework Rework Size Rework Effort

    Development Performance Process Maturity Capability Maturity Model Level

    Productivity Product Size/Effort Ratio Functional Size/Effort Ratio

    6.6.1 B6.6.1 BASELINESASELINES

    6.6.2 M6.6.2 METRICSETRICS LLIBRARYIBRARY

    6.7 QUALITY OBJECTIVES AND CONTROL6.7 QUALITY OBJECTIVES AND CONTROL

    Quality Management includes the processes required to ensure that the project will satisfy theneeds for which it was undertaken. It includes all activities of the overall management function

    that determine the quality policy, objectives, quality assurance, quality control, and quality

    improvement, within the quality system. If a separate Quality Plan is used, include a high level

    summary in this document and refer to the appropriate appendix.

    6.7.1 Q6.7.1 QUALITYUALITY SSTANDARDSTANDARDS

    Describe the agency, industry or regulatory project performance standards that will be followed andassessed by the project. These quality standards will be used to assess whether the quality objectiveswere achieved.

    Identify each of the project quality standards that are directly related to the project and not to theperformance of the actual product and/or service. For each quality standard, identify the tracking tool ormeasure such as number of project reviews or Project Status.

    From another states planning process

    No. Quality Standard Tracking Tool or Measure

    1 Project phase is completed by the established finish date. Project Schedule

    Project Status

    2 Project is completed within budget. Project Charter

    Project Status

    3 Quarterly project reviews show contractors deliver requirements

    specified in the contract by due dates or pay penalties.

    Vendor Contract

    Final Customer

    Acceptance

    PAGE 33

  • 7/27/2019 Project Management Plan Workbook

    41/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 34

    No. Quality Standard Tracking Tool or Measure

    4 Project issues are resolved and documented within 10 calendar days of

    identification or extensions are justified.

    Issues Tracking

    5 Project will be completed based on the original project scope and

    approved scope changes.

    Project Charter

    Project Plan

    Control ChangeRequest

    6.7.2 P6.7.2 PROJECTROJECTANDAND PPRODUCTRODUCT RREVIEWEVIEWANDAND AASSESSMENTSSSESSMENTS

    Review Type Quality Standard Tools Reviewer Reports

    Requirements

    Plans

    Milestones

    Testing

    6.7.3 A6.7.3 AGENCYGENCY/C/CUSTOMERUSTOMERSSATISFACTIONATISFACTION

    The project manager should assess the on-going sense of the customer agency about how they

    feel the project is going, and how team members are acting on the project. This feedback wouldbe helpful to the success of the project and the professional growth of the project team members.

    Examples:

    Areas of feedback When How Often

    Agency awareness

    Quality of communications

    Manages project tasks

    Productive Meetings.

    An example used by some State of New Mexico agencies:

    SSSTANDARDSSTANDARDSNot

    Applicable

    Strongly

    Disagree

    DisagreeSomewhat

    Agree

    AgreeStrongly

    Agree

    PAGE 34

  • 7/27/2019 Project Management Plan Workbook

    42/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 35

    0 1 2 3 4 5

    The level ofbusiness or agency

    knowledge of [projects name] meets yourexpectations.

    [Projects name] performs in aprofessionaland cooperative manner.

    The level ofcommunications by

    [projects name], both written and oral,

    meet your expectations.

    [Projects name] project team works well

    with you and your staff.

    [Projects name] project management

    team is accessible when you need them.

    [Projects name] provides adequate

    information and trainingresulting in

    effective knowledge transfer.

    [Projects name] completes project taskswithin the agreed upon schedule.

    The level oftechnical or businessexpertise of [projects name] meets yourexpectations.

    You are receivingfull value from the

    [projects name] project management

    team.

    The overall service provided by [projects

    name] is fully meeting your expectations.

    6.7.4 P6.7.4 PRODUCTRODUCT DDELIVERABLEELIVERABLE AACCEPTANCECCEPTANCE PPROCESSROCESS

    How the client takes procession of the product. Delivery of media; manuals; contracts; licenses;services agreements; configuration settings; status of patches to COTS products; in-house or

    vendor developed code; test cases, routines, and scripts; and other items required to operate the

    product.

    PAGE 35

  • 7/27/2019 Project Management Plan Workbook

    43/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 36

    Deliverable Final Approval Process Customer Acceptance Criteria

    6.8 CONFIGURATION MANAGEMENT6.8 CONFIGURATION MANAGEMENT

    Configuration Management determines how project information (files, reports, designs, memos,

    documents, etc.) will be managed (tracked, approved, stored, secured, accessed, version control,

    etc.) and owned by (e.g., Agency managing the project or the Customer). Standards and teamawareness are critical.

    6.8.1 V6.8.1 VERSIONERSION CCONTROLONTROL

    Documents should be tracked for version control, on the title page, and using a revision history

    table such as used for this PMP. Document file names should have project name agency revisionnumber reflected. Best practice involves change management for documents, and a numbering

    scheme such as 1.0, 2.0, 3.0 to reflect a projects phases and toll gates or approval processes per

    phase.

    6.8.2 P6.8.2 PROJECTROJECT RREPOSITORYEPOSITORY (P(PROJECTROJECT LLIBRARYIBRARY))

    Provide to the Department all project management and product deliverables. Deliverables shall includebut not limited to the project plan, project schedule, initial and periodic risk assessments, quality

    strategies and plan, periodic project reports, requirements and design documents for entire project. Thelead agency must make available all deliverables in a repository with open access for the Department to

    review PROJECT OVERSIGHT PROCESS Memorandum.

    6.9 PROCUREMENT MANAGEMENT PLAN6.9 PROCUREMENT MANAGEMENT PLAN

    Projects often have some element of procurement, i.e. the requirement to purchase goods and/or

    services from outside the organization. The procedures to be used to handle these procurements

    should be included here. Activities such as a make-or-buy analysis; writing requirements;

    solicitation planning, evaluation and selection; inspection and acceptance; contract closeoutshould all be included.

    State of New Mexico RFP, IT Contract and other procurement processes should be followed by

    all state agencies IT Projects.

    PAGE 36

  • 7/27/2019 Project Management Plan Workbook

    44/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 37

    7. 0 PROJECT CLOSE7. 0 PROJECT CLOSE

    Project Close will always consist of administrative project activities and possibly contractual

    project activities and an external vendor is employed. Completing both sets of activities is amandatory step in the project life cycle. Administrative activities complete the internal needs for

    the Agency/Unit that is responsible for managing the project, such as lessons learned, recording

    the last hours against the project, and providing transition for the staff to other assignments.Contractual activities meet the contractual needs, such as executing a procurement audit and

    formal acceptance of the project work products.

    7.1 A7.1 ADMINISTRATIVEDMINISTRATIVE CCLOSELOSE

    Administrative Close occurs at both the end of phase and end of project. This closure consists of

    verification that objectives and deliverables were met. Acceptance is formalized and phaseactivities are administratively closed out. Administrative closure occurs on a by-phase basis in

    accordance with the WBS and should not be delayed to project end. At that point, the burden of

    closing is too great and audits inaccurate. The specific project close activities for a given projectare contingent on the projects complexity and size. Project managers should work with the

    projects project management consultant to tailor Project Close procedures to compliment the

    projects objectives

    7.2 C7.2 CONTRACTONTRACT CCLOSELOSE

    Contract close is similar to administrative close in that it involves product and processverification for contract close.

    Projects that have been certified need to complete the required DoIT project closure

    certification processes.

    ATTACHMENTSATTACHMENTS

    Attachments are included for additional information, but are not formally considered part of

    the Project Plan for approvals and change management purposes. Examples

    Acronyms, abbreviations and definitions

    Technical glossary of IT terms

    Project Work breakdown schedule

    Project timeline

    ATTACHMENT A ACRONYMS, ABBREVIATIONS AND DEFINITIONSATTACHMENT A ACRONYMS, ABBREVIATIONS AND DEFINITIONS

    PMI Project Management Institute.

    PMBOK Project Management Body of Knowledge

    PMO Program Management Office

    PAGE 37

  • 7/27/2019 Project Management Plan Workbook

    45/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 38

    PMP Project Management Plan

    WBS Work Breakdown Structure

    DEFINITIONSDEFINITIONS

    Acceptance Criteria

    The criteria that a system or component must satisfy in order to be accepted by a user, customer,

    or other authorized entity. [IEEE-STD-610]

    Acceptance Testing

    Formal testing conducted to determine whether or not a system satisfies its acceptance criteriaand to enable the customer to determine whether or not to accept the system. [IEE-STD-610]

    Assumptions

    Planning factors that, for planning purposes, will be considered true, real, or certain.

    Assumptions generally involve a degree of risk. They may be documented here, or converted to

    formal risks.

    Baseline

    A specification or product that has been formally reviewed and agreed upon that thereafterserves as the basis for further development, and that can be changed only through formal

    change control procedures. [IEEE-STD-610]

    Commitment

    A pact that is freely assumed, visible, and expected to be kept by all parties.

    Configuration Management (CM)

    A discipline applying technical and administrative direction and surveillance to identify anddocument the functional and physical characteristics of a configuration item, control changes to

    those characteristics, record and report change processing and implementation status, and

    verify compliance with specified requirements. [IEEE-STD-610]

    Configuration Management Library System

    The tools and procedures to access the contents of the software baseline library.

    Constraints

    Factors that will (or do) limit the project management teams options. Contract provisions will

    generally be considered constraints.

    Contingency PlanningThe development of a management plan that identifies alternative strategies to be used to ensureproject success if specified risk events occur.

    Crashing

    Taking action to decrease the total duration after analyzing a number of alternatives to

    determine how to get the maximum duration compression for the least cost.

    PAGE 38

  • 7/27/2019 Project Management Plan Workbook

    46/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 39

    Critical Path

    The series of activities that determines the duration of the project. The critical path usually

    defined as those activities with float less than or equal to specified value often zero. It is the

    longest path through the project.

    Dependencies, DiscretionaryDependencies defined by the project management team. They should be used with care and

    usually revolve around current Best Practices in a particular application area. They are

    sometimes referred to as soft logic, preferred logic, or preferential logic. This may alsoencompass particular approaches because a specific sequence of activities is preferred, but not

    mandatory in the project life cycle.

    Dependencies, Mandatory

    Dependencies that are inherent to the work being done. In some cases, they are referred to as

    hard logic.

    Dependency Item

    A product, action, piece of information, etc., that must be provided by one individual or group to

    a second individual or group so they can perform a planned task.

    Deliverable

    Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete

    a project or part of a project that is subject to approval by the project sponsor or customer.

    Duration

    The number of work periods (not including holidays or other nonworking periods) required tocomplete an activity or other project element.

    Duration CompressionShortening the project schedule without reducing the project scope. Often increases the project

    cost.

    End User

    The individual or group who will use the system for its intended operational use when it isdeployed in its environment.

    Effort

    The number of labor units required to complete an activity or other project element. Usually

    expressed as staff hours, staff days, or staff weeks.

    Fast Tracking

    Compressing the project schedule by overlapping activities that would normally be done insequence, such as design and construction.

    Float

    The amount of time that an activity may be delayed from its early start without delaying the

    project finished date.

    PAGE 39

  • 7/27/2019 Project Management Plan Workbook

    47/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 40

    Formal Review

    A formal meeting at which a product is presented to the end user, customer, or other interested

    parties for comment and approval. It can also be a review of the management and technical

    activities and of the progress of the project.

    Integrated Project PlanA plan created by the project manager reflecting all approved projects and sub-projects.

    Lessons Learned

    The learning gained from the process of performing the project. Lessons learned may be

    identified at any point during the execution of the project.

    Method

    A reasonably complete set of rules and criteria that establish a precise and repeatable way ofperforming a task and arriving at a desired result.

    Methodology

    A collection of methods, procedures, and standards that defines an integrated synthesis of

    engineering approaches to the development of a product.

    Milestone

    A scheduled event for which some individual is accountable and that is used to measureprogress.

    Non-technical Requirements

    Agreements, conditions, and/or contractual terms that affect and determine the management

    activities of an architectural and software project.

    Performance ReportingCollecting and disseminating performance information. This includes status reportingmeasurement, and forecasting.

    Procurement Planning

    Determining what to procure and when.

    Product Scope

    The features and functions that characterize a product or service.

    Project Leader (Technical)

    The leader of a technical team for a specific task, who has technical responsibility and providestechnical direction to the staff working on the task.

    Project Management

    The application of knowledge, skills, tools, and techniques to project activities to meet the

    project requirements. Project Management is also responsible for the oversight of the

    development and delivery of the architecture and software project.

    Program

    PAGE 40

  • 7/27/2019 Project Management Plan Workbook

    48/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 41

    A group of related projects managed in a coordinated way. Programs include an element of

    ongoing work.

    Program Management Office

    An organizational entity responsible for management and oversight of the organizations

    projects. As a specific reference in this document, the Office of the Chief Information Officer.Project Manager

    The role with total business responsibility for an entire project. The individual who directs,

    controls, administers, and regulates a project. The project manager is the individual ultimately

    responsible to the customer.

    Project Charter

    A document issued by senior management that formally authorizes the existence of a project. It

    provides the project manager with the authority to apply organizational resources to project

    activities.

    Project Management PlanA formal, approved document used to guide both project execution and project control. Theprimary uses of the project plan are to document planning assumptions and decisions, facilitate

    communication among stakeholders, and documents approved scope, cost, and schedule

    baselines. The Project Management Plan (PMP) is a project plan.

    Project Schedule

    A tool used to indicate the planned dates, dependencies, and assigned resources for performingactivities and for meeting milestones. Software products such as ABTs Workbench and

    Microsoft Project are tools used to develop project schedules.

    Project Scope

    The work that must be done to deliver a product with the specified features and functions.

    Project Sponsor

    The individual that provides the primary sponsorship for an approved project. This individualwill play a key role in securing funding, negotiating for resources, facilitating resolution of

    critical organizational issues, and approving key project deliverables.

    Quality

    The degree to which a system, component, or process meets specified requirements.

    The degree to which a system, component, or process meets customer or user needs or

    expectations. [IEEE-STD-610]Quality Management

    The process of monitoring specific project results to determine id they comply with relevant

    standards and identifying ways to eliminate causes of product non-compliance.

    Risk

    Possibility of suffering loss.

    PAGE 41

  • 7/27/2019 Project Management Plan Workbook

    49/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 42

    Risk Management

    An approach to problem analysis, which weighs risk in a situation by using risk probabilities to

    give a more accurate understanding of, the risks involved. Risk Management includes risk

    identification, analysis, prioritization, and control.

    Risk Management PlanThe collection of plans that describes the Risk Management activities to be performed on a

    project.

    Risk Management

    Risk mitigation seeks to reduce the probability and/ or impact of a risk to below an acceptable

    threshold.

    Scope Change

    Any change to the project scope. A scope change almost always requires an adjustment to the

    project cost or schedule.

    Software Life Cycle

    The period of time that begins when a software product is conceived and ends when the software

    is no longer available for use. The Software Life Cycle typically includes a concept phase,requirements phase, design phase, implementation phase, test phase, installation, and checkout

    phase, operation and maintenance phase, and, sometimes, retirement phase.

    Stakeholder

    Individuals and organizations that are actively involved in the project, or whose interests may be

    positively or negatively affected as a result of project execution or project completion. They mayalso exert influence over the project and its results.

    StandardMandatory requirements employed and enforced to prescribe a disciplined uniform approach to

    software development

    Statement of Work

    A description of all the work required completing a project, which is provided by the customer.

    System Requirements

    A condition or capability that must be met or possessed by a system component to satisfy a

    condition or capability needed by a user to solve a problem. [IEEE-STD-610]

    Subproject

    A smaller portion of the overall project.

    Task

    A sequence of instructions treated as a basic unit of work. [IEEE-STD-610]

    A well-defined unit of work in the software process that provides management with a visiblecheckpoint into the status of the project. Tasks have readiness criteria (preconditions) and

    completion criteria (post conditions). (see activity for contrast.)

    PAGE 42

  • 7/27/2019 Project Management Plan Workbook

    50/50

    WORKBOOKFORPREPARATIONOFTHE PROJECT MANAGEMENT PLAN 43

    Team

    A collection of people, often drawn from diverse but related groups, assigned to perform a well-

    defined function for an organization or a project. Team members may be part-time participants

    of the team and have other primary responsibilities.

    Technical RequirementsThose requirements that describe what the software must do and its operational constraints.

    Examples of technical requirements include functional, performance, interface, and quality

    requirements.

    Traceability

    The degree to which a relationship can be established between two or more products of thedevelopment process, especially products having a predecessor-successor or master-subordinate

    relationship to one another. [IEEE-STD-610]

    Work Breakdown Structure

    A deliverable-oriented grouping of project elements that organizes and defines the total workscope of the project. Each descending level represents an increasingly detailed definition of the

    project work.