74
Project Specifications: CONSTRUCTION SERVICES ARIE CROWNE THEATER STAGE SHORING Prepared For: Metropolitan Pier and Exposition Authority (MPEA) Chicago, Illinois May, 21, 2018

Project Workbook - MPEA

  • Upload
    others

  • View
    26

  • Download
    0

Embed Size (px)

Citation preview

Project Specifications:

CONSTRUCTION SERVICES

ARIE CROWNE THEATER STAGE SHORING

Prepared For:

Metropolitan Pier and

Exposition Authority (MPEA)

Chicago, Illinois

May, 21, 2018

Arie Crowne Theater Stage Shoring

May 21, 2018

TABLE OF CONTENTS

00002-1

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

DESCRIPTION Page No.

DIVISION 1 - GENERAL REQUIREMENTS

00850 List of Drawings 00850-1

01010 Summary of Work 01010-1 thru 8

01040 Coordination 01040-1 thru 3

01045 Cutting and Patching 01045-1 thru 3

01095 Reference Standards and Definitions 01095-1 thru 3

01152 Applications for Payment 01152-1 thru 2

01202 Progress Meetings 01202-1 thru 4

01310 Schedule and Reports 01310-1 thru 4

01340 Shop Drawings, Product Data and Samples 01340-1 thru 8

01370 Schedule of Values 01370-1 thru 2

01400 Quality Control Services 01400-1 thru 3

01500 Temporary Facilities 01500-1 thru 3

01600 Material and Equipment 01600-1 thru 6

01700 Project Closeout 01700-1 thru 4

01710 Cleaning 01710-1 thru 2

01720 Project Record Documents 01720-1 thru 2

DIVISION 3 - CONCRETE

03611 Non-Shrink Grout 03611-1 thru 4

DIVISION 5 - METALS

05120 Structural Steel 05120-1 thru 10

Construction Services Arie Crowne Theater Stage Support

May 21. 2018

LIST OF DRAWINGS

00850-1

SECTION 00850

LIST OF DRAWINGS

The following drawings dated 5/16/2018, accompany and form a part of these Documents.

SHEET NUMBER TITLE

S-1 Orchestra Pit Support Steel

END OF SECTION

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-1

SECTION 01010

GENERAL REQUIREMENTS AND

SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Division 1 for this project includes the following Sections:

a. Refer to all specification sections listed in the “Table of Contents”

B. Each Section of Division 1 applies to all the Work.

1.2 PROJECT DESCRIPTION

A. The name and location of the Project is:

Arie Crowne Theater Stage Support

B. The Owner of the Project is:

Metropolitan Pier & Exposition Authority

301 Cermak Rd.

Chicago, Illinois 60616

C. The contract Drawings and Specifications have been prepared by Milhouse

Engineering & Construction, Inc.

D. The project scope generally consists of but is not limited to providing all construction

services, permits, labor, material, equipment, coordination, supervision, scheduling,

coordination and related services, necessary and appropriate for the installation of

structural steel support columns on anchored grout pads in the orchestra pit of Arie

Crowne Theater. The existing stage lift machinery will be removed by others after the

shoring is complete.

E. Work will be performed within the Arie Crowne Theater. Access to the orchestra pit

is extremely limited and the Work may require bringing in and installing materials

using only manual labor and hand hosts and rigging.

F. The weight of the structural steel is estimated at 7,500 pounds.

G. Dimensions shown on the Drawings are approximate and the Contractor shall be

responsible for the accurate measurement and location of the support columns

based on actual field conditions.

H. Final payment for work items shall be made on the basis of accepted work as

approved by the Engineer.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-2

1.3 COORDINATION AND SCHEDULING

A. The Contractor shall be responsible to coordinate, expedite and schedule all the Work

which shall be done in the proper sequence and at the proper time so as not to cause

any delay in the progress of the Work and the completion of the Project.

B. The Contractor shall plan and schedule the Work to allow the use of the theater and

stage as required in support of theater operations.

1.4 CONDUCTING THE WORK

A. The Work shall be conducted so as not to interfere with any of the Authority’s

operations, shows and other contractors, nor to obstruct any thoroughfare or access to

buildings or facilities and nor to impede vehicular and pedestrian traffic. Any exception

must be specifically requested and authorized by the Authority, in writing.

B. All work shall be conducted in full accordance with the requirements of the applicable

City, County, State and Federal regulatory bodies.

1.5 COORDINATION OF DRAWINGS

A. Layouts of equipment and accessories are diagrammatic. The Contractor shall avoid

interference between trades, secure maximum head room and clear access to services

and equipment and to maximize usable areas.

1.6 CORRESPONDENCE BETWEEN CONTRACTOR AND ARCHITECT

A. Correspondence regarding shop drawings, catalog information, and the Contract

Drawings and Specifications shall be carried on directly between the Contractor and

the Engineer. Copies of all such correspondence and of all shop drawings, catalog

information, drawings, specifications and other documentation and information shall be

sent simultaneously to the Authority by the sender.

1.7 STANDARD SPECIFICATION REFERENCES

A. Any material specified by reference to the number, symbol, or title of a specific

standard such as a Federal Specification, an American Standard Specification, an

ASTM Standard, or a trade association standard, shall comply with the latest revision

thereof and any amendment or supplement thereto in effect on the date of the

Contract, except as limited by these Specifications.

1.8 INSTALLATION OF SUPPORTS

A. The Contractor shall furnish and install all structural supports in place, providing all

necessary setting materials and accessories, including concrete, structural steel

supports, hangers, bolts, anchors, and other fastening devices, securely erected in

place.

1.9 CONSTRUCTION LOADS ON BUILDING STRUCTURES

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-3

A. If the Contractor desires to place loads in excess of the design loads on any part of

building structures or facilities, he shall first submit drawings and stress calculations

prepared by a State of Illinois licensed Structural Engineer of the proposed method for

supporting materials for the review and approval by the Authority of the necessary

drawings and calculations.

B. Construction load interference with general, mechanical, electrical, and other work shall

be considered in any proposed permanent design. The cost of engineering, and all

additional labor and materials required to support loads other than design loads, shall

be the responsibility of the Contractor.

1.10 TEMPORARY CONSTRUCTION OPENINGS

A. The Contractor shall provide openings in slabs, walls, and partitions, where required for

moving in materials or equipment and shall close and/or restore all openings and

finishes after their use. The Contractor shall not make any openings requiring structural

modifications without the prior review and approval of the Authority.

1.11 ACCESS AND PARKING

A. Access to the site for delivery of construction material or equipment shall be made only

in locations designated by the Authority. It is the Contractor’s responsibility to supply

flagmen as required and approved by the Authority.

B. Pedestrian ways, roadways, loading docks and utility access shall not be obstructed.

C. Fire hydrants adjacent to the Work shall be kept accessible at all times and no

materials or obstructions shall be placed within twenty (20) feet of any such hydrant, or

at a greater distance if required by law or ordinance.

D. Staging areas for the Contractor shall be only as designated by the Authority.

E. Vehicle parking areas for the Contractor’s use will not be provided by the Authority.

F. The Contractor shall be responsible for becoming familiar with and for taking into

consideration, the Mayor's Traffic Management Task Force Bulletin, which is a

publication of projects and special events in the Chicago area that have a significant

impact on traffic. Copies of this Bulletin can be obtained through the Mayor's Traffic

Management Task Force, (312) 744-0645.

G. The Authority reserves the right to designate all entry and exit points for the

Contractor's use and by the Contractor's employees and their materials. Access and

means of access to construction areas will not be unreasonably withheld.

H. No access will be allowed to the Authority’s facilities except that required to perform

Work under this Contract.

1.12 OCCUPANCY

A. The Authority shall be permitted to occupy any completed or partially completed

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-4

portions of the Work, during the progress of the Work to the extent possible without

interference. Such occupancy shall not in any way indicate completion of the Work or

signify the Authority's acceptance of the Work or any part thereof.

B. Any interruption or shut-off of an operational service or utility line shall be done only as

scheduled with and approved by the Authority in writing.

1.13 ADVERTISING

A. No on-site advertising or signs of any type will be permitted on any part of the building,

scaffolding, fences, materials, obstructions or site except as may be specifically

approved by the Authority in writing.

1.14 SECURITY

A. Security of the Work under construction and the contents of buildings are the

responsibility of the Contractor. The Contractor shall be limited to the area of the Work

and to access routes approved by the Authority. The Contractor shall submit a

proposed phasing and security plan within fourteen (14) days after being awarded the

Contract and shall illustrate the Contractor's intended plan for accomplishing the Work

and maintaining security while not interfering with or adversely affecting the Authority's

operations.

1.15 PHASING

A. The Work shall be phased in such a manner as to minimize and limit the mixing of the

Contractor’s activities with those of Show Contractors and Users subject to the Work

Day Schedule and the requirements and approval of the Authority.

B. The Contractor shall devise its own schedule, phasing, and sequence of work. It is

recognized that certain elements of Work such as pipes, ductwork and conduits may

project into adjacent areas or existing buildings and facilities. Such projections shall be

done so as not to interfere with normal usage of those adjacent areas during certain

times of Shows and kept to minimum practicable amounts of time.

C. The Work Day Schedule has been provided for the Contractor’s information and is

subject to revision by the Authority at any time. The Contractor must permit access by

Show Contractors during show move-ins and move-outs at all times.

D. Construction areas which are without direct access to the exterior by means of doors

will require access and security approval by the Authority.

1.16 TRUCK DOCKS, TAXI TUNNELS, RAMPS, AND PERIMETER SPACE ADJACENT TO

BUILDINGS

A. Emergency access lanes shall be maintained to the satisfaction of the Authority and

applicable governmental agencies at all times.

1.17 CONTRACTOR'S OFFICES AND STORAGE AREAS

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-5

A. Subject to the Authority's approval, the Contractor may use space in and around the

Work area as a field office. The Contractor shall provide his field office with all furniture

and equipment required for use by personnel and for the storage of contract drawings,

shop drawings, documents, data, samples and the like.

B. The Contractor shall provide his field office with and pay all costs of telephone and

electric service.

C. If directed by the Authority, the Contractor shall be responsible for the costs of removal

of the field offices from within or around the existing Work.

D. The Authority will be the sole judge of determining the acceptability of the appearance

of the Contractor’s office and storage areas.

1.18 COMBUSTIBLE AND FLAMMABLE MATERIALS

A. The storage of all combustible and flammable materials shall be maintained outside

and detached from buildings.

1.19 TARPAULINS

A. Only flameproof tarpaulins shall be used.

1.20 TEMPORARY CONSTRUCTION WALLS

A. Non-combustible temporary walls and barricades shall be used to segregate

construction areas from the operating portions of the Authority’s property and they shall

be used wherever sound, dust or odors may be transmitted to occupied areas. All

joints shall be taped and made dustproof.

B. The Contractor’s design of temporary walls and barricades is subject to the Authority’s

review and approval. Portions of wall exposed to view within the areas used by the

public shall be taped and painted with colors selected by the Authority.

C, Temporary walls shall be removed and adjacent property in contact with the temporary

walls refinished when the Work within the construction area has been completed

1.21 PAINTS, SOLVENTS, OILS, GAS CYLINDERS, COMBUSTIBLES.

A. No more than a one day supply of paints, solvents, oils, gas cylinders and combustibles

shall be permitted inside buildings. The handling of these materials shall be carefully

controlled and supervised by the Contractor.

1.22 WELDING AND CUTTING

A. All welding and cutting operations shall be done by competent personnel and shall be

controlled by the Contractor only with the Authority’s permission. The Contractor shall

notify the Authority at least 48 hours prior to the start of each welding or cutting

operation.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-6

1.23 SMOKING

A. Smoking is not permitted anywhere in or on Authority property except in those areas as

may be designated by the Authority.

1.24 CONSTRUCTION WASTE AND SCRAP MATERIAL

A. All waste and scrap materials shall be removed by the Contractor from the Work on a

daily basis.

1.25 POWER ACTIVATED ANCHOR DEVICES

A. Contractor shall not use power (shot) anchors for making attachments to concrete.

Anchors shall be drilled. Any concrete damaged due to an inappropriate use of

anchorage systems shall be removed and replaced at no expense to the Authority and

to the extent determined by the Authority as sole judge of acceptability.

1.26 SHOP DRAWINGS

A. One copy of each shop drawing of fire protection piping and alarm systems and all

related items shall be submitted to the Authority at the same time drawings are

submitted to the Architect. This additional submittal must be reviewed by and be

acceptable to the Authority's insurance company.

1.27 LIFE SAFETY SYSTEMS

A. All life safety systems shall be restored to operation during the Contractor's non-

working hours unless otherwise permitted by the Authority. Contractor shall provide a

fire watch during construction or during shut down periods of time. All improvements,

shutdowns and fire watch activities shall be coordinated with and approved by the

Authority's Safety and Security Departments. Existing systems shall be maintained at

all times except for those periods where the Contractor is permitted to make

changeovers from existing to new permanent systems.

B. Only the Authority will shut down and turn on life safety systems each time the

Contractor requires a changeover.

1.28 EXISTING DRAINAGE SYSTEMS

A. Contractor shall not use existing drainage piping, floor or area drains for the disposal of

construction generated debris or hazardous materials. Existing and new drains shall

be protected throughout the construction period.

1.29 DELIVERY ACCESS

A. Contractor's deliveries shall not interfere with the loading and unloading of Show

Contractors’ vehicles. During show move-in and move-out, all deliveries shall be

scheduled through the Authority's Truck Marshalling facility.

1.30 SHOW/CONTRACTORS COORDINATION

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-7

A. On a weekly basis, the Contractor shall meet with the Authority and Show Management

to review and coordinate construction with show activities to the satisfaction of Show

Managers and the Authority.

1.31 CONDITION OF SPACE

A. The Contractor shall carefully review the Work Day Schedule. Work shall be

scheduled such that areas under construction shall be returned to the Authority in a

useable fashion for show use at those times indicated on the Work Day Schedule

which may be amended from time to time by the Authority. Contractor shall not work in

those areas reserved for show use as outlined in the Work Day Schedule. In general

this shall mean, but shall not be limited to, the following:

1. If work is begun on existing ceilings or floors in areas being used, those

areas shall be turned over for use by the Authority in a completed condition.

2. If work is begun on existing walls in areas being used, in those areas that are

not complete at the time that the area must be used by the Authority, the

Contractor shall provide drapes or temporary partitions to cover the

unfinished portion of the Work.

3. The condition in which areas are turned over from time to time for use by the

Authority shall be carefully coordinated with the Authority who will solely

determine what constitutes an acceptable condition.

1.32 TEMPORARY SIGNAGE:

The Contractor shall provide only such temporary signage as is necessary for the conduct of the

Work and such signage shall be subject to the approval of the Authority as to verbiage, size, color,

graphics and location.

1.33 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into standard Divisions and

Sections.

1. Divisions are used for broad categories of trade and work disciplines.

2. Sections are subdivisions of the broad categories.

3. Only the categories that are applicable for this project are used, therefore all

available category numbers are not necessarily present although the categories

are in sequential order and those included are listed in the Table of Contents.

4. Division 1 applies to the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use standard conventions as to style of

language and the intended meaning of certain terms, words, and phrases.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SUMMARY OF WORK

01010-8

1. Language used in the Specifications may be abbreviated. Words and meanings

shall be interpreted as may be appropriate in the context of the subject. Words

implied, but not stated, shall be inferred as the sense requires. Singular words

shall be interpreted as plural and plural words shall be interpreted as singular

where applicable as the context indicates.

2. Imperative mood and streamlined language are generally used in the

Specifications. Requirements expressed in the imperative mood are to be

performed by the Contractor. Occasionally, the indicative or subjunctive mood

may be used in the Section text for clarity to describe responsibilities that must be

fulfilled indirectly by Contractor or by others when so noted.

3. The words "shall," "shall be," or "shall comply with," depending on the context, are

implied where a colon (:) is used within a sentence or phrase.

END OF SECTION 01010

Construction Services Arie Crowne Theater Stage Support

May 21. 2018

COORDINATION

01040-1

SECTION 01040

COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes requirements for coordinating construction operations including,

but not limited to, the following:

1. General project coordination procedures.

2. Coordination Drawings.

3. Administrative and supervisory personnel.

4. Cleaning and protection.

1.2 COORDINATION

A. Coordinate all construction operations to assure efficient and orderly installation of the

Work.

1. Schedule construction operations in the sequence required to obtain the best

results.

2. Coordinate installation of all Work to assure maximum accessibility for

maintenance, service, and repairs.

B. Prepare memoranda, notices, reports, and attendance at meetings outlining

procedures required for coordination and distribute to those involved on the

construction team, the Authority and separate contractors.

C. Administrative Procedures: Coordination and scheduling of construction activities to

avoid conflicts and assure orderly progress of the Work, include, but are not limited to,

the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Delivery and processing of submittals.

4. Progress meetings.

5. Project closeout activities.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare coordination drawings where careful coordination is

required for installation of Work where limited space necessitates maximum utilization

of space. Show the relationship of components shown on Shop Drawings and indicate

required installation sequences.

B. Staff Names: Within 7 days of the award of the contract, the Contractor shall submit a

Construction Services Arie Crowne Theater Stage Support

May 21. 2018

COORDINATION

01040-2

list of its principal staff assignments for Authority review and approval, including the

project director, project manager, field superintendent and other key personnel

identifying individuals and their duties and responsibilities. Include their addresses,

telephone numbers and email addresses.

PART 2 - EXECUTION

2.1 GENERAL COORDINATION PROVISIONS

A. Inspect the substrate and conditions for Work and do not proceed until unsatisfactory

conditions have been corrected.

B. Coordinate the performance of required inspections and tests to avoid the necessity of

uncovering completed construction.

2.2 CLEANING AND PROTECTION

A. Clean and protect Work in progress and in place and apply protective covering where

required to avoid damage or deterioration.

B. Clean and provide maintenance on completed construction as frequently as necessary

and adjust and lubricate components to avoid damage.

C. Limiting Exposures: Assure that no part of the Work is subject to harmful, dangerous,

damaging, or deleterious exposure during the construction period, including but not

limited to the following:

1. Excessive static or dynamic loading.

2. Excessive internal or external pressures.

3. Excessively high or low temperatures.

4. Thermal shock.

5. Excessively high or low humidity.

6. Air contamination or pollution.

7. Water or ice.

8. Solvents.

9. Chemicals.

10. Light.

11. Radiation.

12. Puncture.

13. Abrasion.

14. Heavy traffic.

15. Soiling, staining, and corrosion.

16. Bacteria.

17. Rodent and insect infestation.

18. Combustion.

19. Electrical current.

20. High-speed operation.

21. Improper lubrication.

22. Unusual wear or other misuse.

Construction Services Arie Crowne Theater Stage Support

May 21. 2018

COORDINATION

01040-3

23. Contact between different materials leading to corrosion.

24. Destructive testing.

25. Misalignment.

26. Excessive weathering.

27. Unprotected storage.

28. Improper shipping or handling.

29. Theft.

30. Vandalism.

END OF SECTION 01040

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

CUTTING AND PATCHING

01045-1

SECTION 01045

CUTTING AND PATCHING

1.1 SUMMARY

A. This Section includes general requirements for cutting and patching. Refer to other

Sections for requirements and limitations applicable to cutting and patching for specific

parts of the Work.

1.2 SUBMITTALS

A. Cutting and Patching Plan: Submit a plan describing procedures, well in advance of

the time cutting and patching will be performed, to the Architect and Authority for

approval of the procedures before proceeding. Include the following information as

applicable:

1. Describe the extent of cutting and patching contemplated showing how it will be

performed and indicating why it is necessary.

2. Describe the changes to structural elements, operating components, building's

appearance and other significant visual elements.

3. List products to be used and firms or entities that will perform Work.

4. Indicate dates when cutting and patching will be performed.

5. List utilities that cutting and patching procedures will disturb or affect, or that will

be relocated and those that will be temporarily out-of-service, indicating how long

service will be disrupted.

6. Where cutting and patching involves adding reinforcement to structural elements,

submit details and engineering calculations showing integration of reinforcement

with the original structure.

7. Notwithstanding any approval by the Architect or the Authority, the Contractor

shall remain responsible for the removal and replacement of unsatisfactory work.

1.3 QUALITY ASSURANCE

A. Requirements for Structural Work: Do not cut and patch structural elements in a

manner that would change their load-carrying capacity or deflections.

B. Operational Limitations: Do not cut and patch operating elements or related

components in a manner that would result in reducing their capacity to perform as

intended and do not cut and patch operating elements or related components in a

manner that would result in increased maintenance or decreased operational life and

life safety.

C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in

occupied spaces in a manner that would, in the Architect's or the Authority’s opinion,

affect aesthetics. Do not cut and patch that would result in visual evidence of cutting

and patching. Remove and replace work that has been cut and patched, that is

unsatisfactory in the opinion of the Architect or the Authority.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

CUTTING AND PATCHING

01045-2

1.4 WARRANTY

A. Existing Warranties: Replace, patch, and repair material and surfaces cut or damaged

in such a manner as not to void any existing warranties.

1.5 MATERIALS, GENERAL

A. Use materials identical to existing materials that match existing adjacent surfaces. to

the fullest extent possible if identical materials are unavailable or cannot be used. Use

materials whose installed performance will equal or surpass that of existing materials.

1.6 INSPECTION

A. Examine surfaces to be cut and patched and conditions under which cutting and

patching is to be performed before cutting. If unsafe or unsatisfactory conditions are

encountered, take corrective action before proceeding.

1. Before proceeding, meet at the Site of the Work with parties involved in cutting

and patching, including mechanical and electrical trades. Review areas of

potential interference and conflict and resolve potential conflicts before

proceeding.

1.7 PREPARATION

A. Temporary Support: Provide temporary support of work to be cut.

B. Protection: Protect existing construction during cutting and patching to prevent

damage. Provide protection from adverse weather conditions for portions of the Work

that might be exposed during cutting and patching operations.

C. Avoid interference with use of adjoining areas or interruption of free passage to

adjoining areas.

D. Avoid cutting existing pipe, conduit, or ductwork serving existing facilities but scheduled

to be removed or relocated until provisions have been made to bypass them.

1.8 PERFORMANCE

A. General: Employ skilled workmen to perform cutting and patching. Proceed with

cutting and patching at the earliest feasible time and complete without delay.

1. Cut existing construction to provide for installation of other components or

performance of other construction activities and the subsequent fitting and

patching required to restore surfaces to their original condition.

B. Cutting: Cut existing construction using methods least likely to damage elements

retained or adjoining construction. Review proposed procedures so as to comply with

the original Installers’ recommendations.

1. In general, where cutting, use hand or small power tools designed for sawing or

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

CUTTING AND PATCHING

01045-3

grinding, not hammering and chopping. Cut holes and slots as small as possible,

neatly to size required, and with minimum disturbance of adjacent surfaces.

Temporarily cover openings when not in use.

2. To avoid marring existing finished surfaces, cut or drill from the exposed or

finished side into concealed surfaces.

3. Cut through concrete and masonry using cutting machines such as carborundum

or diamond-core saws and drills.

4. Comply with requirements of all applicable Sections where cutting and patching is

required including, but not limited to, excavating and backfilling.

5. Where services are required to be removed, relocated, or abandoned; by-pass

utility services, such as pipe or conduit, before cutting. Cut-off pipe or conduit in

walls or partitions to be removed. Cap, valve, or plug and seal portion of pipe or

conduit that are to remain so as to prevent entrance of moisture or other foreign

matter.

C. Patching: Patch with materials that are as invisible as possible and comply with

specified tolerances.

1. Inspect and test patched areas to assure integrity of the installation.

2. Restore exposed finishes of patched areas and extend finish restoration into

retained adjoining construction in a manner that will not show evidence of

patching and refinishing.

3. Where removing walls or partitions extends into adjacent existing spaces, patch

and repair floor and wall surfaces in such places. Provide even surfaces of

uniform color and appearance. Remove existing floor and wall coverings and

replace with new materials, if necessary, to achieve uniform color and

appearance.

4. Where patching occurs in a smooth painted surface, extend final paint coat over

entire unbroken surface containing the patch after the area has received primer

and second coat.

5. Patch, repair, or re-hang existing ceilings as necessary to provide an even-plane

surface of uniform appearance.

1.9 CLEANING

A. Clean areas and spaces where cutting and patching are performed, completely

removing paint, mortar, oils, putty, and similar items. Thoroughly clean piping, conduit,

and similar features before applying paint or other finishing materials. Restore

damaged pipe covering to its original condition.

END OF SECTION 01045

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

REFERENCE STANDARDS AND DEFINITIONS

01095-1

SECTION 01095

REFERENCE STANDARDS AND DEFINITIONS

1.1 DEFINITIONS

A. General: Basic definitions are included in the Contract. In the event of any

discrepancies with these definitions, those in the Contract shall govern.

B. Indicated: The term “indicated” refers to graphic representations, notes, or schedules

in the Drawings and Specifications. Terms such as Shown, Noted, Scheduled, and

Specified do not limit locations, extent or scope of the Work.

C. Directed: Terms such as “directed, requested, authorized, selected, approved,

required, and permitted” mean actions by the Authority or the Architect.

D. Approve: The term “approved” is used in conjunction with the Authority’s or

Architect's action on the Contractor's submittals, applications, and other requests

stated in the Contract Documents.

E. Regulations: The term “regulations” includes laws, ordinances, statutes, and lawful

orders issued by authorities and agencies having jurisdiction, as well as rules,

conventions and agreements in the construction industry relating to performance of

the Work.

F. Furnish: The term “furnish” means supply and deliver to the Project site ready for

unloading, unpacking, assembly and installation.

G. Install: The term “install” means operations at the Project site such as unloading,

unpacking, assembly, erection, placing, anchoring, applying, finishing, curing,

protecting, cleaning, and similar operations necessary to complete the Work.

H. Provide: The term “provide” means to “furnish and install” complete, ready for use

and in compliance with Contract Requirements.

I. Installer: An “installer” may be the Contractor or an entity engaged by the Contractor,

either as an employee, subcontractor, or contractor of lower tier, to perform a

particular construction activity, including installation, erection, application, and similar

operations. Installers are required to be experienced in the operations they are

engaged to perform.

1. The term “experienced”, when used with the term installer means having

previously and successfully completed a minimum of three projects of similar

size and scope and also means having familiarity with the special requirements

of governmental agencies with jurisdiction for such projects. Upon request, the

Contractor shall submit detailed credentials and references to show evidence of

the qualifications of such subcontractors and installers prior to their

employment on the Project.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

REFERENCE STANDARDS AND DEFINITIONS

01095-2

2. Trades: Trade terms such as “carpentry” are not intended to limit construction

to individuals with a corresponding generic name, such as “carpenter” nor does

it imply that requirements specified apply exclusively to tradespersons of the

corresponding generic name. Means and methods of performing the Work is

the sole responsibility of the Contractor.

3. Specialists: Certain Sections of the Specifications may require that specific

construction activities shall be performed by specialists who are recognized

experts in those activities; however, the use of such specialists does not relieve

the Contractor of full responsibility for fulfilling Contract Requirements.

This requirement shall not be interpreted to conflict with compliance with

building codes and similar regulations governing the Work or to interfere with

local trade union jurisdictional agreements and similar conventions.

J. “Project Site” is the space available for the Contractor to perform the Work but does

not mean the space is for the Contractor’s use exclusively since others may be

performing work as separate contractors on the Project.

1.2 SPECIFICATION FORMAT AND CONTENT EXPLANATION

A. Specification Format: These Specifications are organized into Divisions and Sections

based on industry standard numbering systems.

B. Specification Content: The Specifications use certain conventions regarding the style

of language and the intended meaning of certain terms, words, and phrases when

used in particular situations or circumstances. These conventions are explained as

follows:

1. Abbreviated Language: Language used in Contract Documents may be

abbreviated and shall be interpreted as commonly used in the industry. Words

that are implied, but not stated, shall be interpolated as the sense requires.

Singular words will be interpreted as plural and plural words interpreted as

singular where applicable.

2. Requirements expressed in the imperative mood are to be performed by the

Contractor. At some locations in the Specifications, subjective language is

used to describe responsibilities that must be fulfilled by the Contractor. The

words "shall be" are implied wherever a colon (:) is used within a sentence or

phrase.

1.3 INDUSTRY STANDARDS

A. Applicability of Standards: Except where the Contract Documents include more

stringent requirements, applicable construction industry standards have the same

force and effect as if bound or copied directly into the Contract Documents and are

made a part of the Contract Documents by reference.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

REFERENCE STANDARDS AND DEFINITIONS

01095-3

B. Publication Dates: Comply with the standards in effect as of the date of the Contract.

C. Conflicting Requirements: Where compliance with two or more standards is

specified and where the standards may establish different or conflicting requirements

for minimum quantities or quality levels, the most stringent requirement shall apply.

The Authority shall be the sole judge of which requirement is the most stringent.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or

specified shall be the minimum provided or performed. The actual installation

may comply exactly with or may exceed the minimum quantity or quality

specified. To comply with these requirements, indicated numeric values are

minimum or maximum, as appropriate, in the context of the requirements.

D. Copies of Standards: Each entity engaged in construction on the Project is required

to be familiar with industry standards applicable to its construction activity

whether or not bound with the Contract Documents.

E. Abbreviations and Names: Trade association names and titles of standards may be

abbreviated. Where such acronyms or abbreviations are used in the Contract

Documents, they mean the recognized name of the trade association,

standards-generating organization, and authority having jurisdiction or other

applicable entity in the context of the provision. The "Encyclopedia of Associations,"

published by Gale Research Co. may be used as a reference.

1.4 SUBMITTALS

A. Permits, Licenses, and Certificates: Submit copies of permits, licenses, certifications,

inspection reports, releases, jurisdictional settlements, notices, receipts for fee

payments, judgments, and similar documents, correspondence, and records

established in conjunction with compliance with standards and regulations bearing

upon performance of the Work.

END OF SECTION 01095

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

APPLICATIONS FOR PAYMENT

01152-1

SECTION 01152

APPLICATIONS FOR PAYMENT

1.1 GENERAL

A. Submit Applications for Payment to the Authority in accordance with the provisions

established by the Contract.

1.2 PENCIL DRAW

A. Prior to the submission of the formal Application, meet with the Authority in a so-called

“pencil draw” to informally discuss and tentatively mutually agree with the Authority on

the content and details of the current Application. The format of the pencil draw will be

established by the parties attending.

1.3 FORMAT

A. Submit the Application using the format of AIA Document G702 and G703.

1.4 SUBMITTAL PROCEDURE

A. Submit Applications for Payment in the number of copies requested and include Waivers

of Lien, Affidavits and other substantiating documents as requested or required.

1.5 PREPARATION OF APPLICATIONS

A. Application Form Content:

1. Include Change Orders to date.

2. Show summary Schedule of Values with data supported by detailed supporting

Schedules of Values for each line item. See Section 01370 for Schedules of

Value.

3. Execute certification by an authorized person.

1.6 SUBSTANTIATING DATA

A. Provide such substantiating data and documentation as may be requested by the

Authority,

1.7 WAIVERS OF LIEN

A. Submit waivers of lien and sworn statements from subcontractors, sub-subcontractors

and suppliers in the form required by the Contract or as may be requested by the

Authority.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

APPLICATIONS FOR PAYMENT

01152-2

1.8 PRECEDENT DATA FOR PAYMENT

A. Prior to the first Application for Payment submit the following:

1. List of all subcontractors, lower tier sub-subcontractors and suppliers

2.. List of Contractor's consultants and testing agencies.

3. Summary Schedule of Values and supporting detailed Schedules of Values.

4. Schedule of principal products.

5. Submittal Schedule.

6. Construction Schedule.

7. Copies of building permits.

8. Copies of authorizations and licenses from governing authorities for performance

of the Work.

9. Initial progress report.

10. Report of pre-construction meeting.

2. Certificates of insurance and insurance policies (prior to any work on site).

3. Performance and payment bonds.

4. Initial settlement survey and damage report, if required.

1.9 APPLICATION FOR PAYMENT AT SUBSTANTIAL COMPLETION

A. Administrative actions and submittals that shall precede this Application include:

1. Occupancy permits and similar approvals.

2. Warranties (guarantees) agreements.

3. Test reports.

4. Maintenance instructions.

5. Final cleaning.

6. Consent of surety.

7. Detailed and monetized list of incomplete Work (including punchlists), recognized

as exceptions to the Certificate of Substantial Completion.

1.10 PREPARATION OF APPLICATION FOR FINAL PAYMENT

A. Administrative actions and submittals that shall precede this application include:

1. Project closeout requirements.

2. Completion of all incomplete Work (including punchlists).

3. Provisions that assure that unsettled claims will be settled.

4. Transmittal of required Project construction records to Authority.

5. Proof that taxes, fees and similar obligations have been paid.

6. Removal of temporary facilities and services.

7. Removal of surplus materials, rubbish and similar elements.

END OF SECTION 01152

Construction Services Arie Crowne Stage Support

May 21, 2018

PROGRESS MEETINGS

01202-1

SECTION 01202

PROGRESS MEETINGS

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for project meetings

including:

1. Pre-Construction Meeting.

2. Pre-Installation Meeting.

3. Coordination Meetings.

4. Progress Meetings.

1.2 PRE-CONSTRUCTION MEETING

A. The Authority will schedule a pre-construction and organizational meeting at the Project

site prior to commencement of construction activities to review responsibilities and

personnel assignments.

B. Attendees: The Authority, Architect and Contractor and its superintendent, major

subcontractors, manufacturers, suppliers and other concerned parties shall each be

represented at the meeting by persons familiar with and authorized to resolve matters

relating to the Work.

C. Agenda: Discuss items of significance that could affect progress including such topics

as:

1. Project Schedule.

2. Critical Work sequencing.

3. Designation of responsible personnel.

4. Procedures for processing field decisions and Change Orders.

5. Procedures for processing Applications for Payment.

6. Review/verification of Contract Documents.

7. Summary of Critical Requirements.

8. Submittal of Shop Drawings, Product Data and Samples.

9. Preparation of record documents.

10. Use of the premises.

11. Office, Work and off-site staging, parking and storage areas.

12. Materials and equipment deliveries and priorities.

13. Safety procedures.

14. First aid.

15. Security.

16. Housekeeping.

17. Working hours.

18. Clean-up.

19. Temporary facilities.

Construction Services Arie Crowne Stage Support

May 21, 2018

PROGRESS MEETINGS

01202-2

D. Unless otherwise requested by the Authority, prepare and issue minutes of the meeting

which shall identify and list the title of the project and the title of the meeting; the date,

time and place of the meeting; attendees; the purpose of the meeting; discussions,

decisions and actions to be taken; status of required submittals; critical dates and

priorities and responsibilities. Distribute the report of the meeting to everyone in

attendance plus others involved within three (3) working days after the meeting date.

1.3 PRE-INSTALLATION MEETINGS

A. Conduct pre-installation meetings at the site. The Installers, manufacturer’s

representatives, fabricators involved in or affected by the installation, and those involved

with other installations that precede or follow, shall attend the meeting. Advise the

Authority in advance of all meeting dates.

1. Review the progress of other construction activities and preparations for the

particular activity under consideration at each pre-installation meeting, including

requirements for:

a. Contract Documents coordination.

b. Options.

c. Related Change Orders.

d. Purchases

e. Deliveries, staging.

f. Shop Drawings, Product Data and quality control Samples.

g. Possible conflicts.

h. Compatibility problems.

i. Warranty and Guarantee requirements.

j. Time schedules.

k. Weather limitations.

l. Manufacturer's recommendations.

m. Compatibility of materials.

n. Acceptability of substrates.

o. Temporary facilities.

p. Space and access limitations.

q. Governing regulations.

r. Safety.

s. Inspection and testing requirements.

t. Required performance results.

u. Record Documents.

v. Protection and cleaning.

w. Cooperation with Authority and other contractors.

x. Schedule.

2. Prepare minutes of each meeting and distribute copies to all concerned, including

the Authority and Architect, within three (3) working days after the meeting date.

3. Do not proceed with the Work if the meeting does not resolve all issues. Initiate,

expedite and resolve impediments to the Work and reconvene the meeting at the

earliest practicable date.

Construction Services Arie Crowne Stage Support

May 21, 2018

PROGRESS MEETINGS

01202-3

1.4 COORDINATION MEETINGS

A. Conduct coordination meetings at regularly scheduled times. Project coordination

meetings are in addition to regular progress meetings and pre-installation meetings.

B. Have representation at each meeting of all those involved in coordination and planning

for the related activities.

C. Prepare and issue minutes of the meeting within three (3) working days after the meeting

date and show the title of the project, title of the meeting, date, time, place, attendees,

purpose, discussions, decisions, actions to be taken, status of submittals, critical dates,

priorities and responsibilities. Distribute the minutes to all involved or affected.

1.5 PROGRESS MEETINGS

A. The Authority will schedule regular periodic meetings as it may be deem necessary to

discuss the progress of the Work.

B. Attendees should be:

1. Authority's representatives.

2. Consultants.

3. Contractor's Project Manager.

4. Project superintendent.

5. Subcontractors and suppliers as necessary.

All representatives should have authority to act regarding the Work.

C. The Contractor shall maintain daily progress records containing significant matters such

as problems, material deliveries, scheduling, manpower and weather conditions.

D. Agenda:

1. Reviews of current progress schedule.

2. Review of work progress since previous meeting.

3. Planned work progress until next meeting.

4. Problems affecting construction progress.

5. Corrective measures to be taken.

6. Sequences.

7. Deliveries.

8. Off-site fabrication.

9. Site access.

10. Site utilization.

11. Temporary facilities and services.

12. Hours of Work.

13. Safety.

14. Housekeeping.

15. Quality and Work standards.

16. Field observations, problems, conflicts, coordination.

17. Submittals.

Construction Services Arie Crowne Stage Support

May 21, 2018

PROGRESS MEETINGS

01202-4

18. Requests for Information, Architect's Supplemental Instructions.

19. Change Orders.

20. Documentation for payment requests.

21. Other Business.

22. Completion Schedule.

23. Coordination with others.

E. The Contractor shall submit a written report indicating the work completed to date and

planned work for the next work period at each meeting. As discussed and amended,

these reports shall be compiled by the Contractor and submitted to the Authority within

three (3) working days after the meeting date.

F. The Architect or Authority may issue a written commentary clarifying, correcting or

supplementing the Contractor's report of the meeting.

END OF SECTION 01202

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULES AND REPORTS

01310-1

SECTION 01310

SCHEDULES AND REPORTS

1.1 GENERAL

A. In addition to other submission requirements in the Contract, the Contractor shall submit

the schedules and reports defined in this Section.

B. The CPM schedule is required to assist the Authority and the Contractor.

C. The Project Schedule is the sole responsibility of the Contractor.

D. Float, the time duration between the early finish and late finish dates of the schedule, is

not for the exclusive use or benefit of the Contractor and may be used by the Authority.

1.2 SCHEDULES AND SCHEDULE REPORTS

The Contractor shall provide the following:

A. CONSTRUCTION SCHEDULE GRAPHIC

Provide a Construction Schedule Graphic in the form of a time scaled logic diagram showing

pre-construction and construction activities and their relationships. Bar charts without logic

clearly indicated are not acceptable.

Include: pre-construction activities; permit acquisition; submittal/review/approval process for

samples and mockups; manufacture/delivery cycles of manufactured items; actual

construction, punch lists and clean up.

Follow the Work Breakdown structure specified hereinafter. Illustrate compliance with the

Specifications, special requirements and coordination with the Work Day Schedules provided

by the Authority.

B. PROJECT SCHEDULE

Within 21 days after the date of the Contract, prepare a fully detailed computer generated

schedule using Critical Path Method precedence diagramming in a system equal to and

compatible with latest edition of Primavera Project Planner, and submit for approval by the

Authority. This schedule shall be a detailed expansion of any requirement for a Proposed

Construction Schedule in the Request for Proposal.

The CPM network shall include testing and inspection activities. It shall be fully coordinated

with the requirements of the Authority for the maintaining of its operations and, if applicable,

shall reflect the performance of work by other contractors.

Show submittal/review activities and indicate applicable Specification Sections.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULES AND REPORTS

01310-2

Show activities that are the responsibility of the Authority and others.

1. Upon approval by the Authority, the Project Schedule shall become the Baseline

for the Project. The Contractor shall provide the Authority with complete schedule

information stored in, or generated by, the Contractor’s approved computer based project

management system. Information which is not text or graphic information delivered in hard

copy shall be delivered to the Authority stored on electronic media in a form suitable for use

by the Authority’s computer systems and project management software.

Hard copy reports and graphics shall be submitted in their original printer or plotter output

form in six copies. All password protection, user lists, access lists or other electronic

protections shall be removed or adjusted so that the Authority can have complete access to

all the relevant information contained therein.

The Contractor shall:

1. Apply retained logic rather than progress override,

2. Show start-to-start lag from early start,

3. Show early start of finish-to-finish successors as contiguous duration,

4. Show total float.

5. Show progress graphics using percent complete.

6. Employ activity coding as outlined in this Section such that the Authority can undertake

sorts or filters based on the Authority’s project management software to isolate activities

and produce reports of their status independent of the balance of the schedule.

7. Assure that the Project Schedule is cost loaded, updated and maintained.

8. Submit electronic media based copies, reports and graphics as specified below.

C. CHANGES

1. If a Change in the Work is authorized prior to a mutual agreement on possible changes

to the Lump Sum Contract Price or the Project Schedule, then to avoid delay, the

Contractor shall revise the network logic and/or duration time estimates of all activities

affected by the modification on the next succeeding update report. Submit the revisions

for concurrence by the Authority prior to inclusion in the network.

2. Revise the Submittal Checklist to reflect such changes.

1.4 PERIODIC SCHEDULE PROGRESS REPORTS

The Contractor shall provide the following reports:

A. WEEKLY REPORT

1. TWO-WEEK LOOK AHEAD: At least once a week the Contractor shall meet with all

trades concerned to establish and submit a detailed Two-Week Look Ahead

schedule indicating daily activities of all of the trades and subcontractors in each

area of the Project.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULES AND REPORTS

01310-3

B. MONTHLY SCHEDULE AND PROGRESS REPORT

1. The Contractor shall incorporate into the CPM Project Schedule all current schedule

status information and perform a complete network recalculation and analysis

monthly.

The following report and copy of the schedule information stored on electronic

media shall be submitted to the Authority by the twenty-fifth of each month,

reflecting progress projected to the end of that month and shall contain the following

minimum information:

a. Narrative Description of Project Progress During the Current Month.

b. Summary Schedule Graphic in Bar Chart Format.

c. Tabular reports of the updated Project Schedule including an Activity Listing

organized by Early (earliest to latest) and an Activity Listing by Float (lowest

to highest).

d. An Updated Project Cash Flow Projection.

e. A written report showing action taken to correct any schedule slippage.

f. The schedule information shall be stored on electronic media as specified

herein.

C. SUBMITTAL CHECKLIST/PROGRESS REPORT

1. The Contractor shall provide a list or log of all submittals required by the

Specifications in either of the two forms listed below:

a) A checklist produced independently of the Project Schedule.

b) A tabular or graphic schedule report generated directly from the Contractor’s

scheduling or project management program using a sort or filter of the

database to isolate the submittal activities in the schedule and show their

status and progress.

2. The Project Schedule and Submittal Checklist shall be mutually consistent in both

content and status of submittal activities. The Submittal Checklist shall be submitted

initially with the Project Schedule and then updated and resubmitted weekly

thereafter. The basic information required and a suggested format are shown below

but alternative formats may be submitted for approval by the Authority.

1.5 OTHER REPORTS

A. DAILY REPORTS: The Contractor shall submit to the Authority a Daily Construction

Report recording and reporting the following information.

1. List of subcontractors at the site.

2. List of separate contractors at the site.

3. A count of personnel at the site.

4. Accidents of any nature.

5. Meetings and significant decisions.

6. Unusual events.

7. Stoppages, delays, shortages, losses.

8. Emergency procedures undertaken.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULES AND REPORTS

01310-4

9. Inspections, orders and requests of governing authorities.

10. Change Orders received, implemented, requested or expected to be requested.

11. Services connected or disconnected.

12. Partial completions or occupancies

13. Substantial Completion.

14. A narrative description of daily construction activities.

15. Any other required reports required by the Contract.

16. Reports of material and equipment delivery and location of storage or placement.

B. FIELD CORRECTION REPORTS

1. When the need to take corrective action that requires a departure from the Contract

Documents arises, prepare a detailed report including a statement describing the

problem and recommended changes. Indicate reasons the Contract Documents

cannot be followed and submit a copy to the Architect and Authority immediately.

1.6 WORK BREAKDOWN

Activities shall be organized and reported per the following:

General

1. Submittals

2. Permit

3. Procurement

4. Demolition

5. General

6. Architectural

7. M.E.P.

8. Punch list

Activity coding shall include at least the following:

1. Area per work breakdown above.

2. Responsibility by Contractor, Subcontractor, Manufacturer, Authority, Architect and

any other entity with responsibility for or control over any activity.

3. Submittals, Procurement, Permits, Preconstruction, Construction, Punch list.

4. Any other categories which may be appropriate to organize the work.

5. Project specifications section where applicable.

END OF SECTION 01310

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-1

SECTION 01340

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

1.1 GENERAL

A. Submit a Checklist, indicating the scheduled dates for submission and review of Shop

Drawings, Product Data, and Samples.

B. Shop Drawings are drawings, diagrams, schedules and other data specially prepared to

illustrate some portion of the Work.

C. Product Data are illustrations, standard schedules, performance charts, instruction,

brochures, diagrams and other data to illustrate materials or equipment for some portion

of the Work.

D. Samples are physical examples that illustrate materials, equipment or workmanship to

establish standards by which the Work will be judged.

E. Shop Drawings, Product Data, Samples and similar submittals are not Contract

Documents and they do not revise, alter, negate or in any way change any of the

Contract Requirements.

F. The Contractor shall review and approve all submittals before submitting them for the

review of the Architect or the Authority, with reasonable promptness so as to cause no

delay in the Work or in the activities of the Authority or of separate contractors.

The review and approval of submittals by the Contractor represents that he has

determined and verified that materials, field measurements and field construction criteria

related thereto have been checked and coordinated with the requirements of the Work

and of the Contract Documents.

G. The Contractor shall perform no portion of the Work requiring submittal and review of

Shop Drawings, Product Data, Samples or similar submittals until the relevant submittals

have been reviewed by the Architect.

H. The Contractor shall not be relieved of responsibility for strict compliance with the

Contract Requirements by the approval action of submittals by the Architect or the

Authority.

I. No deviation from Contract Requirements is permitted unless specifically requested in

writing and approved in writing by the Authority.

J. The Contractor shall not be relieved of responsibility for errors or omissions in submittals

for any reason whatsoever including, but not limited to, the approval action by the

Architect or the Authority.

K. The Contractor shall call specific attention, in writing, on resubmitted submittals to

revisions other than those requested by the Architect or the Authority on previous

submittals.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-2

L. There may be Informational submittals identified in the Contract Documents upon which

no approval action is expected.

M. When professional certification of calculations or performance criteria for materials,

systems or equipment is required by the Contract Documents, the Architect or the

Authority shall be entitled to rely upon the accuracy and completeness of such

documentation.

N. The Architect or the Authority will review and take appropriate approval action on the

Contractor's submittals, but only for the limited purpose of checking for conformity with

information given and the design concept expressed in the Contract Documents. The

approval action will be taken with reasonable promptness so as not to cause delay in the

Work.

Reviews of submittals are not for the purpose of determining the accuracy and

completeness of details such as dimensions, quantities, substantiating instructions for

installation or performance of equipment and systems, all of which remain the

responsibility of the Contractor, and such reviews do not relieve the Contractor of any of

its obligations under the Contract.

Reviews do not constitute approval of safety precautions or of any construction means,

methods, techniques, sequences, procedures or assembly of which the items are a

component.

O. The Contractor shall supervise and direct the Work, using its best skills and attention and

shall be solely responsible for and have control over construction means, methods,

techniques, sequences and procedures and for coordinating all portions of the Work

under the Contract, unless the Contract specifically instructs otherwise.

The Contractor shall be responsible for acts and omissions of its and the Subcontractors’

employees, agents and other persons performing portions of the Work under a contract

with the Contractor. The Contractor shall not be relieved of obligations to perform the

Work in accordance with the Contract Documents either by activities or duties of the

Architect in the Architect's administration of the Contract, or by inspections or approvals

required or performed by persons other than the Contractor.

The Contractor shall be responsible for inspection of portions of Work performed under

this Contract to determine that such portions are in proper condition to receive

subsequent Work.

P. The Contractor warrants to the Authority that materials and equipment furnished under

the Contract will be of good quality and new unless otherwise required or permitted by

the Contract Documents, that the Work will be free from defects not inherent in the

quality required or permitted, and that the Work will conform to the Contract

Requirements.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-3

Work not conforming to these requirements, including substitutions not properly

approved and authorized, may be considered defective. The Contractor's warranty

excludes remedy for damage or defect caused by abuse, modifications not executed by

the Contractor, improper or insufficient maintenance, improper operation, or normal wear

and tear under normal usage. If requested by the Architect or the Authority, the

Contractor shall furnish satisfactory evidence as to the kind and quality of such materials

and equipment.

1.2 SHOP DRAWINGS

A. Submit newly prepared drawings or information, drawn to accurate scale. Do not

reproduce Contract Documents or copy standard printed information as the basis of

Shop Drawings unless authorized to do so.

1. Include the following information on Shop Drawings:

a. Configurations in detail.

b. Dimensions, work points, gauges and capacities.

c. Identification of products and materials.

d. Compliance with specified standards.

e. Notation of coordination requirements.

f. Notation of dimensions established by field measurement.

g. Contractor's Structural Engineer's Certified Drawings and Calculations.

2. Submit Coordination Drawings where required for integration of different

construction elements. Show construction sequences and relationships of

separate components to avoid conflicts in utilization of the space available.

3. Highlight, encircle or otherwise indicate Authority approved deviations from the

Contract Documents on the Shop Drawings. Do not include any deviations not

properly authorized by the Authority.

4. Do not permit Shop Drawing copies to be used in construction without an

appropriate final stamp or other marking indicating the action taken by the

Architect.

B. Drawings shall be presented in a clear and thorough manner, identified by reference to

sheet, detail, schedule, location or other indications shown on Drawings.

1.3 PRODUCT DATA

A. Preparation:

1. Clearly mark each copy to identify pertinent products or models.

2. Show performance characteristics and capacities.

3. Show dimensions and clearances required.

4. Show wirings diagrams and controls.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-4

B. Manufacturer's standard schematic drawings and diagrams:

1. Modify drawings and diagrams to delete information which is not applicable to the

Work.

2. Supplement standard information to provide information specifically applicable to

the Work.

C. Include the following information in Product Data:

1. Manufacturer's printed recommendations.

2. Compliance with recognized trade association standards.

3. Compliance with recognized testing agency standards.

4. Application of testing agency labels and seals.

5. Notation of dimensions verified by field measurement.

6. Notation of coordination requirements.

D. Do not submit Product Data unless compliance with requirements of the Contract is

confirmed.

1.4 SAMPLES

A. Samples shall be of sufficient size and quantity to clearly illustrate:

1. Functional characteristics of product, with integrally related parts and attachment

devices.

2. Full range of color, texture and patterns.

B. Submit Samples that are physically identical with the material or product proposed for

use, full-size, fully fabricated and finished in the manner specified.

1. Mount, display, or package Samples in the manner specified to facilitate review of

qualities indicated. Prepare Samples to match the Architect's Sample where so

indicated. Include the following information:

a. Generic description of the Sample.

b. Size limitations.

c. Sample source.

d. Product name or name of manufacturer.

e. Compliance with recognized standards.

f. Compliance with governing regulations.

g. Availability.

h. Delivery time.

2. Submit Samples for review of kind, color, pattern, and texture, for a final check of

these characteristics with other elements, and for a comparison of these

characteristics between the final submittal and the actual component as delivered

and installed.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-5

a. Where variations in color, pattern, texture or other characteristics are

inherent in the material or product represented by a Sample, submit sets of

multiple units of the Sample (not less than 3 units), which show approximate

limits of the variations.

1.5 SUBMISSION REQUIREMENTS

A. Contractor shall make submittals promptly in accordance with the approved schedule

and in such sequence as to cause no delay in the Work or in work of others.

B. Coordinate preparation and processing of submittals with performance of the Work.

Transmit each submittal to the Authority and the Architect sufficiently in advance of

scheduled performance of related construction activities to avoid delay.

1. Coordinate each submittal with other submittals and related activities that require

sequential activity including:

a. Purchasing.

b. Fabrication.

c. Delivery.

2. Coordinate transmittal of different types of submittals for the same element of the

Work and different elements of related parts of the Work so that processing will not

be delayed by the need to review submittals concurrently for coordination.

a. The Architect or the Authority has the right to withhold action on a submittal

requiring coordination with other submittals until related submittals are

submitted.

3. Allow sufficient review time so that installation will not be delayed as a result of the

time required to process submittals, including time for resubmittals.

a. Allow at least 10 working days for the initial review of each submittal plus

additional time where processing must be delayed to permit coordination

with subsequent submittals.

b. Where necessary to provide an intermediate submittal between the initial

and final submittals, process the intermediate submittal in the same manner

as the initial submittal.

c. Allow at least10 working days for processing of each resubmittal.

d. Advise the Architect or the Authority when processing time is critical to

progress, and the Work would be expedited if processing time could be

shortened.

e. No extension of time will be authorized because of the Contractor's failure to

transmit submittals sufficiently in advance of the Work to permit processing.

f. Distribute all submittals under a transmittal which shall include the date,

project title, addressor, addressee, purpose, number of reproducibles sent

and number of reproductions sent. For each item sent, the Specification

Section Number and the Submittal Title as it appears in the Submittal

Checklist should be listed as well as any other critical information relevant to

the submittal should be noted.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-6

C. The Contractor shall review and approve Submittals to the Architect or the

Authority in such sequence as to cause no delay in the work or the activities of the

Authority or of the Authority’s separate contractors. The Contractor shall, on the

first page of each bound set, on each single document page or on the label of

each sample, affix its stamp which shall state and certify that the Contractor has

reviewed, coordinated and approved the work as proposed in such submittal, has

checked existing conditions, dimensions, actual field measurements, layouts,

connections, fit, match and hidden conditions and that the work as shown on such

submittal complies with Contract Requirements. Submittals received without

Contractors review stamp will be returned for proper resubmittal.

D. If the Contractor makes all submittals directly to the Architect in the required

number of sets, a copy of the cover transmittal shall be sent concurrently to the

Authority.

E. Number of submittals required:

1. Shop Drawings: Submit one (l) reproducible transparency along with

sufficient opaque reproductions to provide the number of prints required by

the Contractor, plus two (2) which will be retained by the Architect, plus three

(3) which will be retained by the Authority.

2. Product Data: Submit number of copies required by the Contractor, plus two

(2) which will be retained by Architect and three (3) which will be retained by

the Authority.

3. Samples: Submit number of samples required by the Contractor, plus two

(2) which will be retained by Architect and three (3) which will be retained by

the Authority.

F. Submittals shall contain the following:

1. Date of submission and dates of any previous submissions.

2. Project title and number.

3. Contract identification.

4. Names of Contractor, subcontractor, supplier, and manufacturer.

5. Identification of the product, with Specification Section number.

6. Field dimensions, clearly identified as such.

7. Relation to adjacent or critical features of the Work or materials.

8. Applicable standards, such as ASTM or Federal Specification numbers.

9. Identification of approved deviations from Contract Requirements.

10. Identification of revisions on resubmittals.

11. An 8" x 3" blank space for Contractor and Architect or Authority approval

stamps.

12. Contractor's stamp, initialed or signed, certifying to review of submittals,

verification of products, field measurements and field construction criteria,

and coordination of information within submittal with requirements of the

Work and of the Contract Documents.

1.6 RESUBMISSION REQUIREMENT

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-7

A. Contractor shall make any corrections or changes in Submittals required by the

Architect or the Authority and resubmit until approved.

B. Shop Drawings , Product Data, and Samples:

1. Revise initial drawings or data, and resubmit as specified for initial submittal.

2. Indicate any changes which have been made other than those requested by

the Architect or the Authority.

C. Samples: Submit new samples as required for initial submittal.

1.7 ARCHITECT'S OR AUTHORITY’S ACTION

A. Compliance with contract documents is the Contractor's responsibility.

B. Approval Action Stamp: The Architect will stamp each submittal with a uniform,

self-explanatory action stamp. The stamp will be appropriately marked, as follows,

to indicate the action taken:

1. Final Unrestricted Release: Where submittals are marked "Reviewed," that

part of the Work covered by the submittal may proceed, provided it complies

with Contract Requirements. Final acceptance will depend upon that

compliance.

2. Final-But-Restricted Release: When submittals are marked "Furnish As

Corrected," that part of the Work covered by the submittal may proceed

provided it complies with both the Architect's notations or corrections on the

submittal and Contract Requirements; final acceptance will depend on that

compliance.

3. Returned for Resubmittal: When submittal is marked "Revise and

Resubmit," do not proceed with that part of the Work covered by the

submittal, including purchasing, fabrication, delivery, or other activity, revise

or prepare a new submittal in accordance with the Architect's notations;

resubmit without delay. Repeat if necessary to obtain a different action

mark.

Do not permit submittals marked "Rejected" or "Revise and Resubmit as

Noted" to be used on the Project.

4. Other Action: Where a submittal is primarily for information or record

purposes, for special processing or other Contractor activity, the submittal

will be returned marked "Action Not Required".

1.8 DISTRIBUTION

A. Contractor shall distribute reproductions of Shop Drawings and copies of Product Data

which carry Architect's stamp of approval to:

1. Contractor's Job site file.

2. Contractor's Record Documents file.

3. Subcontractors.

4. Suppliers or Fabricators.

5. The Authority.

Construction Serivces Arie Crowne Theater Stage Support

May 21, 2018

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01340-8

B. The Contractor and Architect shall distribute to the Authority, in-progress samples and

actual samples which shall bear the Contractor’s stamp of approval and the Architect’s

stamp of approval in exactly the same process as for Shop Drawing and Product Data

and that, prior to Closeout, Contractor shall transmit to the Authority one indexed filed and

boxed set of actual samples, which shall each bear the Contractor’s stamp of approval

and the Architect’s stamp of approval. Such samples are in addition to any requirements

specified for Attic Stock or Extra Material.

END OF SECTION 01340

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULE OF VALUES

01370-1

SECTION 01370

SCHEDULE OF VALUES

1.1 GENERAL

A. This Section augments the Payment Application provisions of the Contract and in case of

a conflict, the requirements of the Contract shall govern.

1.2 SCHEDULE OF VALUES

A. Coordinate the Schedule of Values with the Construction Schedule.

1. Submit the Schedule of Values to the Authority for approval before submitting the

first Payment Application.

2. Sub-Schedules: Provide sub-schedules as necessary showing details and

breakdowns of line items in the primary Schedule.

B. Format and Content: Use format equivalent to AIA Documents G-702 and G-703 and

include the following project identification on the Schedule of Values:

1. Name and address of the Authority.

2. Title of Project and location.

3. Name of Architect/Engineer.

4. Name and Address of Contractor.

5. Contract identification.

6. Date of submission.

7. Generic name of item.

8. Related Specification Section.

9. Name of subcontractor.

10. Name of manufacturer, fabricator or supplier.

11. Change Orders.

C. Provide the breakdowns of the line items in sufficient detail satisfactory to the Authority.

1. Round amounts off to the nearest whole dollar.

2. Each item shall be for the actual proper cost of the work with no unbalancing.

3. Establish separate line items for general conditions, overhead and profit, insurance

and bond costs. Such items should be billed at the same percentage as gross

contract completion unless approved otherwise by the Authority.

4. For items on which progress payments will be requested for stored materials when

permitted by the Authority, break down values into:

a. Price of the materials, delivered and unloaded.

b. Total installed value.

D Schedule Updating: Update and revise the Schedule of Values to reflect Change Orders

or when requested by the Authority to reflect actual costs.

E. The Schedule of Values shall contain only items of work of tangible value to the Authority

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

SCHEDULE OF VALUES

01370-2

and intangible or indirect items such as Mobilization, Engineering, Shop Drawings will not

be periodically paid for unless at the same percentage as gross contract completion

unless approved otherwise by the Authority..

END OF SECTION 01370

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

QUALITY CONTROL SERVICES

01400-1

SECTION 01400

QUALITY CONTROL SERVICES

1.1 SUMMARY

A. Quality control services include inspections, tests and reports performed by

independent agencies, governmental authorities, and the Contractor.

B. Inspection and testing services shall verify compliance with contract requirements.

C. Requirements of this Section relate to customized fabrication and installation

procedures.

1. Additional quality control requirements are specified in other Sections and

include inspections and tests for standard products.

2. Inspections, test and related actions specified do not limit the Contractor's

own quality control procedures that may be required to ensure compliance

with Contract Requirements.

1.2 RESPONSIBILITIES

A. Contractor Responsibilities: The Contractor shall provide inspections, tests and

similar quality control services, specified in individual Specification Sections and

required by governing authorities, except where they are specifically indicated to

be the Authority’s responsibility, or are provided by other identified entities. The

costs for these services shall be included in the Contract Price.

1. The Contractor shall employ and pay an independent agency, acceptable to

the Authority, to perform specified quality control services.

2. Retesting: The Contractor is responsible for retesting where results of

required inspections, tests or similar services prove unsatisfactory and do

not indicate compliance with Contract Requirements, regardless of whether

or not the original test was the Contractor’s responsibility.

a. Cost of retesting Work revised or replaced by the Contractor is the

Contractor’s responsibility.

3. Associated Services: The Contractor shall cooperate with agencies

performing required inspections, tests and similar services and provide

reasonable auxiliary services as requested. Notify the agency sufficiently in

advance of operations to permit assignment of personnel. Auxiliary services

required, include but are not limited to:

a. Providing access to the Work and furnishing incidental labor and

facilities necessary to facilitate inspections and tests.

b. Taking adequate quantities of representative samples of materials that

require testing or assisting the agency in taking samples.

c. Providing facilities for storage and curing of test samples, and delivery

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

QUALITY CONTROL SERVICES

01400-2

of samples to testing laboratories.

d. Providing testing agencies with preliminary design mixes that require

later testing by the agencies.

e. Security and protection of samples and test equipment at the Site.

B. Duties of Independent Agencies: Independent agencies engaged to perform

inspections, sampling and testing of materials and construction specified in

individual Specification Sections shall cooperate with the Architect and Authority in

performance of its duties, and shall provide qualified personnel to perform required

inspections and tests.

1. The agency shall notify the Architect and Authority promptly of irregularities

or deficiencies observed in the Work during performance of its services.

2. The agency is not authorized to release, revoke, alter or increase Contract

Requirements, and approve or accept any portion of the Work.

3. The agency shall not perform any of the Work itself.

4. The agency shall comply with specified standards and other recognized

industry standards.

1.3 SUBMITTALS

A. The independent testing agency shall submit a certified written report of each

inspection, test or similar service, to the Architect and Authority, in duplicate.

1. Submit additional copies of each written report directly to governing

authorities when required to do so.

2. Report Data: Written reports of each inspection, test or similar service shall

include, but not limited to:

a. Date of issue.

b. Project title and number.

c. Name, address and telephone number of testing agency.

d. Dates and locations of samples and tests or inspections.

e. Names of individuals making the inspection or test.

f. Designation of the Work and test method.

g. Identification of product and related Specification Section.

h. Complete inspection or test data.

i. Test results and interpretations thereof.

j. Ambient climatic conditions at the time of sample-taking and testing.

k. Comments or professional opinions as to whether inspected or tested

Work complies with Contract Requirements.

l. Name and signature of laboratory inspector.

m. Recommendations on re-testing if required.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

QUALITY CONTROL SERVICES

01400-3

1.4 QUALITY ASSURANCE

A. Qualifications for Testing Agencies: Engage inspection and testing service

agencies, including independent testing laboratories, who are prequalified as

complying with "Recommended Requirements for Independent Laboratory

Qualification" by the American Council of Independent Laboratories, who satisfy

the requirements of ASTM E329, and who specialize in the types of inspections

and tests to be performed.

1. Each independent inspection and testing agency engaged on the Project

must be authorized to operate in the State of Illinois and the City of Chicago.

2.1 REPAIR AND PROTECTION

A. General: Upon completion of inspection, testing, sample taking and similar

services, repair damaged construction and restore substrates and finishes to

eliminate deficiencies, including deficiencies in visual qualities of exposed finishes.

B. Protect construction exposed by or for quality control service activities, and protect

repaired construction.

C. Repair and protection is Contractor's responsibility.

2.2 TESTING

A. All items requiring inspection and/or testing shall not be concealed or covered until

the test or inspection has been completed and the work accepted. Any items

which are covered prior to such inspections or tests shall be uncovered for the test

or inspection as directed by the Architect or the Authority at no additional cost to

the Authority.

END OF SECTION 01400

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

TEMPORARY FACILITIES

01500-1

SECTION 01500

TEMPORARY FACILITIES

1.1 GENERAL

A. The Work includes the minimum requirements for temporary work.

B. This Section does not limit the type or amount of temporary work required for the

successful completion of the Project and for compliance with the Contract Requirements.

The Contractor shall provide all temporary work and services required for the Work. The

Contractor shall install, operate, protect, service, maintain, and remove all temporary

work connecting to existing building services.

C. Temporary connections shall not be made to new or existing permanent service lines

without approval of the Authority. When the temporary service lines are no longer

required, they shall be removed by the Contractor.

D. Any part or parts of the permanent service lines, grounds and buildings, disturbed or

damaged by the installation or removal of temporary service lines shall be restored to

their original condition by the Contractor.

1.2 TEMPORARY ELECTRIC POWER

A. Subject to the approval of the Authority, existing electrical systems may be used to

provide temporary power for construction. The Contractor shall ascertain the electrical

characteristics and insure their compatibility with construction tools and equipment.

B. The Contractor shall reimburse the Authority for providing temporary service connections

at junction boxes in existing electrical systems. The Contractor shall provide all

supplementary wiring, outlets and lighting, required for the proper conduct of the Work.

All temporary electric services shall be properly insulated and maintained in a safe

manner, and shall be installed in accordance with the applicable requirements of all

governing codes and ordinances.

C. The Authority will pay for the cost of electrical energy from existing electrical systems

used for the work provided it is used efficiently and properly in the sole opinion of the

Authority.

1.3 TEMPORARY WATER SUPPLY

A. Subject to the approval of the Authority existing water supply systems may be used to

provide temporary water for construction.

B. The Contractor shall reimburse the Authority for providing all temporary service

connections to existing water supply systems. The Contractor shall provide all

supplementary distribution equipment required to bring an adequate supply of water to

valved outlets within the areas of construction and all supplementary hoses, valves and

outlets required for the proper conduct of the Work.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

TEMPORARY FACILITIES

01500-2

C. The Authority will pay the cost of water from existing water supply systems used for the

work provided it is used efficiently and properly in the sole opinion of the Authority.

1.4 SANITARY FACILITIES

A. The Contractor shall provide its own sanitary facilities for the use of all construction

personnel. The Contractor shall prohibit construction personnel from using the

Authority’s sanitary facilities.

B. The Contractor shall provide all supplies and cleaning services as required.

1.5 FIELD OFFICE AND TELEPHONE SERVICE

A. Subject to the approval of the Authority, the Contractor may use space on the Authority's

property as a field office. The Contractor shall provide a field office with all furniture and

equipment required for its use and for the storage of Project drawings, documents, data,

samples, etc. and shall keep the office clean and in good order. The Contractor shall

include a large table and chairs suitable for conducting job progress meetings.

B. The Contractor shall provide the field office with and pay all costs for telephone and

electric service.

C. The Contractor shall remove field offices from within or around the existing building at its

own cost when directed by the Authority.

D. The Authority will be the sole judge of determining the acceptability of the appearance of

the Contractor’s office and storage areas.

E. Exterior storage shall be enclosed with 6 ft minimum height chain link fencing equipped

with opaque slats to provide a visual barrier.

1.6 HOISTS, DERRICKS, LADDERS AND SCAFFOLDING

A. The Contractor shall provide and maintain all hoists, derricks, ladders, scaffolding, lifting

apparatus and other such equipment and required for the execution of the work,

equipped with all safety devices required by and in compliance with laws and regulations.

Such equipment shall not interfere with the work nor damage property.

1.7 PROTECTION OF PROPERTY AND TEMPORARY COVERINGS

A. Protect all areas and facilities adjacent to the areas of construction, all utility lines,

adjacent buildings, site improvements and landscaping from damage caused by

construction operations. All damage shall be repaired at the Contractor’s expense to the

satisfaction of the Authority and the Architect.

B. Provide, maintain and remove all temporary coverings as required to protect materials,

equipment, and the completed work. The Contractor shall be held responsible for all

damages until final acceptance.

C. Protect all new or existing finished surfaces, walls, stairways, floors, paving, walkways,

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

TEMPORARY FACILITIES

01500-3

traffic lanes, decks, jambs, soffits and all openings used as passageways or through

which materials are handled; against any damage resulting from construction operations

D. Provide temporary weather protection during intervals between demolition and removal

of existing construction on exterior surfaces and installation of new construction to

ensure that no water leakage or damage occurs to structures or interior areas of new or

existing facilities.

1.8 SECURITY

A. The Contractor shall provide all security that may be required for the protection of the

Work, equipment, materials and tools.

END OF SECTION 01500

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-1

SECTION 01600

MATERIAL AND EQUIPMENT

1.1 GENERAL

A. All material and equipment incorporated into the Work shall meet or exceed the following

criteria:

1. Conform to applicable specifications and standards.

2. Comply with size, make, type and quality specified, or as specifically approved in

writing by Architect or the Authority.

3. Manufactured and Fabricated Products:

a. Design, fabricate and assemble in accordance with the best engineering and

shop practices.

b. Manufacture like parts of duplicate units to standard sizes and gages, to be

interchangeable.

c. Two or more items of same kind shall be identical, by same manufacturer.

d. Products shall be suitable for service conditions.

e. Equipment capacities, sizes and dimensions shown or specified shall be

adhered to unless variations are specifically approved in writing.

4. Do not use material or equipment for any purpose other than that for which it is

designed or is specified.

B. Match Existing: Wherever existing work is to be repaired, refurbished, removed and

replaced, etc., and/or wherever new work is to be added to existing work, all materials

incorporated into such new work shall, unless specified or noted otherwise, match in

quality, size, color, texture, finish, etc., similar materials in existing work. The Architect or

the Authority shall be the sole judge as to whether or not each new material is an

acceptable match to existing material.

1.2 SUBMITTALS

A. Product List Schedule: Prepare a schedule showing products specified in an acceptable

form and include generic names, manufacturers’ names and proprietary names for each

item or product listed.

1. Coordinate the product list with the Project Schedule and the Submittal Checklist.

2. Prepare the product listing schedule with information on each item tabulated under

the following column headings:

a. Related Specification Section number.

b. Generic name used in Contract Documents.

c. Proprietary name, model number and similar designations.

d. Manufacturer's name and address.

e. Supplier's name and address.

f. Installer's name and address.

g. Projected delivery date, or time span of delivery period.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-2

3. Initial Submittal: Within 30 days after date of commencement of the Work, submit

4 copies of an initial product list schedule, 2 copies to the Authority and 2 copies to

the Architect. Provide a written explanation for omissions of data, and for

deviations from Contract Requirements.

a. The initial submittal may be limited to product selections and designations

that must be established early in the contract period.

4. Completed Schedule: Within 60 days after date of commencement of the Work,

submit 4 copies of the completed product list schedule distributed as indicated

above. Provide a written explanation for omissions of data, and for deviations from

Contract Requirements. No deviations will be permitted unless approved in writing

by the Authority.

5. Architect's Action: The Architect will respond in writing to the completed product

list schedule. All products must comply with Contract Documents.

1.3 QUALITY ASSURANCE

A. Source Limitations: To the fullest extent possible, provide products of the same kind,

from a single source.

1. When specified products are available only from sources that do not or cannot

produce a quantity adequate to complete project requirements in a timely manner,

consult with the Architect for a determination of the most important product

qualities before proceeding. Qualities may include attributes relating to visual

appearance, strength, durability, or compatibility. When a determination has been

made, select products from sources that produce products that possess these

qualities, to the fullest extent possible.

B. Compatibility of Options: When the Contractor is given the option of selecting between

two or more products for use on the Project, the product selected shall be compatible

with products previously selected, even if previously selected products were also options.

C. Nameplates: Except for required labels and operating data, do not attach or imprint

manufacturer's or producer's nameplates or trademarks on exposed surfaces of products

which will be exposed to view in occupied spaces or on the exteriors of Authority

property.

1. Labels: Locate required product labels and stamps on a concealed surface or,

where required for observation after installation, on an accessible surface that is

not conspicuous.

2. Equipment Nameplates: Provide a permanent nameplate on each item of service-

connected or power-operated equipment. Locate on an easily accessible surface

which is inconspicuous in occupied spaces. The nameplate shall contain the

following information and other essential operating data:

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-3

a. Name of product and manufacturer.

b. Model and serial number.

c. Capacity.

d. Speed.

e. Ratings.

1.4 MANUFACTURER'S INSTRUCTIONS

A. When the Contract requires that installation of work shall comply with manufacturer's

printed instructions, obtain and distribute copies of such instructions to parties involved in

installation, including two copies to Architect and two copies to Authority prior to

installation or start of work.

1. Maintain one set of complete instructions at job site during installation and until

completion in a 3-ring binder, tabbed for easy reference following the

Specifications format.

B. Handle, install, connect, clean, condition and adjust products in strict accordance with

manufacturers’ instructions and in conformity with drawings and specifications.

1. Should job conditions or specified requirements conflict with manufacturer's

instructions, consult with the Architect or the Authority for further instructions

before proceeding with the work.

C. Perform work in accordance with manufacturer's instructions without omitting any

preparatory step or installation procedure unless specifically modified or exempted by

Contract Requirements.

1.5 TRANSPORTATION AND HANDLING

A. Arrange and coordinate deliveries of Products in accordance with the Progress Schedule

to avoid conflict with Work and job conditions.

1. Deliver products in undamaged condition, in manufacturers’ original containers or

packaging and with identifying labels intact and legible.

2. Inspect shipments to assure compliance with Contract Requirements and

approved submittals, and that products are properly protected and undamaged.

B. Handle products by methods to prevent soiling or damage to products or packaging.

1.6 STORAGE AND PROTECTION

A. Store products in accordance with manufacturers’ instructions, seals and labels intact

and legible.

1. Store products subject to damage by the elements in weather tight enclosures.

2. Maintain temperature and humidity within ranges required by manufacturers’

instructions.

B. Arrange storage in a manner to provide easy access for inspection. Make periodic

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-4

inspections of stored products to assure that products are maintained under specified

conditions, and free from damage or deterioration.

C. Provide substantial coverings as necessary to protect installed products from damage by

traffic or construction operations and remove them when no longer needed.

1.7 SUBSTITUTIONS AND PRODUCT OPTIONS

A. Contractor's Options:

1. For products specified only by a referenced standard, select only products that

meet that standard.

2. For products specified by naming one or more products or manufacturers and "or

approved equal"; and products specified as "equal to" or "not limited to" a

specifically named product or manufacturer: the Contractor must submit a request

for substitutions for any product or manufacturer not specifically named.

3. For products specified by naming one or more products or manufacturers, select

any one of the products or manufacturers named or specified with no substitutions.

B. Request for Substitutions:

1. Requests for substitutions will be considered only if in accordance with the

requirements listed herein.

2. Substitutions require Authority approval in writing.

3. The Contractor shall submit the following information with any request for

substitution:

a. Submit 3 copies of each request for substitution.

b. Identify the product, fabrication or installation method to be replaced in each

request and show related Specification Section and Drawing numbers.

Provide complete documentation showing compliance with the requirements

for substitutions, and the following information, as appropriate:

1) Product data, including drawings and descriptions.

2) Samples.

3) Detailed comparison of qualities of the proposed substitution with

those of the Work specified and include such elements as size, weight,

durability, performance and visual effect.

4) Include a list of modifications needed to other parts of the Work that

will become necessary to accommodate the proposed substitution.

5) Effect on the Construction Schedule and Contract Time.

6) Cost information, including a credit proposal, if any.

7) Certification that the substitution proposed is equal-to or better in every

respect to that required by the Contract and that it will perform

adequately in the application indicated.

8) Include waiver of rights to additional payment or time that may become

necessary because of the failure of the substitution to perform

adequately.

4. For substitutions, the Contractor shall represent all of the following:

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-5

a. The proposed product is equal to or superior in all respects to that specified.

b. The same or superior warranties or bonds will be provided as for the product

specified.

c. Any changes as may be required will be made to make the work complete in

all respects at no additional cost to the Authority.

d. The Contractor understands that certain products may be specified due to

unique visual or performance requirements required and the decision of the

Architect or the Authority will be final.

d. The Contractor understands that it will bear the costs of the Architect,

Consultants or the Authority in evaluating or processing the proposed

substitution.

e. Contractor certifies that it will bear all related costs for the substitution which

later become apparent.

5. The Contractor's substitution request will be considered only when the following

conditions are satisfied.

a. Extensive revisions to Contract Documents are not required.

b. Proposed changes are in keeping with the general intent of Contract.

c. The request is timely, fully documented and properly submitted.

d. The request is directly related to an "or equal" clause or similar language in

the Contract Documents.

e. The specified product or method of construction cannot be provided within

the Contract Time except if the product or method cannot be provided as a

result of failure to pursue the Work promptly or properly.

f. The specified product or method of construction cannot receive necessary

approval by a governing authority.

g. An advantage is offered to the Authority, in terms of cost, time, energy

conservation or other considerations.

h. The specified product or method of construction cannot be made compatible

with other elements of the Work.

i. The specified product or method of construction cannot be coordinated with

other elements of the Work.

j. The specified product or method of construction cannot provide a warranty

required by the Contract.

6. The Architect's action on Shop Drawings, Product Data or Samples on items that

do not comply with the Contract, does not constitute an acceptance or approval of

any substitution.

C. EVALUATION

1. Any costs incurred by the Authority to review requests for substitutions shall be

borne by the Contractor.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

MATERIAL AND EQUIPMENT

01600-6

2.1 PRODUCT SELECTION

A. Provide products that comply with the Contract, that are undamaged, new and not used

1. Provide products complete with all accessories, trim, finish, safety guards, other

devices and details needed for a complete installation and for the intended use and

effect.

2. Standard Products: Where available, provide standard products of types that have

been produced and used successfully in similar situations on other projects.

B. Product Selection Procedures: Product selection is governed by the Contract,

governmental laws, regulations and the following:

1. Where three or more products or manufacturers are named, provide one of the

products indicated. No substitutions will be permitted.

a. Where products or manufacturers are specified by name, accompanied by

the term "or equal," or "or approved equal", comply with the provisions

concerning "substitutions".

2. Where the Specifications list products or manufacturers that do not require the

Contractor to use these products only, the Contractor may propose any product

that complies with Contract Requirements.

3. Where the Specifications describe a product or assembly, listing exact

characteristics required, with or without use of a brand or trade name, provide a

product or assembly that provides the characteristics and otherwise complies with

Contract Requirements.

4. Where Specifications require compliance with performance criteria, provide

products that comply with these requirements, and are recommended by the

manufacturer for the application indicated. General overall performance of a

product is implied where the product is specified for a given application.

Manufacturer's recommendations may be contained in published product literature,

or by the manufacturer's certification of performance.

5. Where the Specifications only require compliance with an imposed code, standard

or regulation, select a product that complies with the codes, standards or

regulations specified.

6. Where Specifications require matching an established Sample, the Architect's

decision will be final on whether a proposed product matches satisfactorily.

7. Where specified product requirements include the phrase "...as selected from

manufacturer's standard colors, patterns, textures..." or a similar phrase, select a

product and manufacturer that complies with other Contract Requirements. The

Architect will select the color, pattern and texture from the product line selected.

END OF SECTION 01600

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT CLOSEOUT

01700 - 1

SECTION 01700

PROJECT CLOSEOUT

PART 1 GENERAL

1.01 SCOPE OF WORK

Provide all labor, materials, equipment, supervision and incidentals necessary

for closeout procedures, final cleaning, project record documents, warranties and

waivers of lien. This work is incidental to the project.

1.02 CLOSEOUT PROCEDURES

A. Submit written certification to the Engineer / Owner that Contract

Documents have been reviewed, work has been inspected and that work has

been completed in accordance with Contract Documents and ready for

Engineer’s punchlist walkthrough.

B. As applicable, provide final approved submittals and certificates of inspections

to the Owner indicating evidence of compliance with requirements of the

governing authorities.

C. Submit final Application for Payment identifying total Contract Sum (with all

approved change orders), previous payments, and retainage due.

D. Provide final as-built drawings to the Engineer/Owner. Maintain as-built

drawings on the project site.

1.03 FINAL CLEANING

A. Execute final cleaning prior to Engineer’s punchlist walkthrough.

B. Clean debris from drainage systems.

C. Clean site. Sweep and powerwash floor slabs in the work areas, and adjacent

areas as required and directed by the Owner.

D. Clean interior and exterior glass surfaces exposed to view; remove temporary

labels, stains and foreign substances, and polish transparent and glossy surfaces.

E. Clean mechanical / electrical equipment and fixtures to a sanitary condition.

Reattach dislodged hangers for mechanical / electrical systems, as required.

F. Remove waste and surplus materials, rubbish, and construction facilities from

the site.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT CLOSEOUT

01700 - 2

1.04 PROJECT RECORD DOCUMENTS

A. Maintain on site, one set of the following record documents and record actual

revisions to the Work:

1. Contract Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other Modifications to the Contract.

5. Reviewed shop drawings, product data, samples, material submittals, and

approved shoring plans.

6. Material Safety Data Sheets for all materials used in the construction.

B. Store Record Documents separate from documents used for construction.

C. Record information concurrent with construction progress.

D. Specifications: Legibly mark and record at each Product section description of

actual Products installed, including the following:

1. Manufacturer’s name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and Modifications.

E. Record Documents and Shop Drawings: Legibly mark each item to record actual

construction including:

1. Field changes of dimension and detail.

2. Details not on original Contract Drawings.

3. Location and quantity of completed work.

F. Prepare and maintain as-built drawings, showing the location of all repair work

completed on the project. Contract work item designations and quantities to be

included on these drawings. Contractor to coordinate as-built information with

the Engineer during the work.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT CLOSEOUT

01700 - 3

G. Legibly mark each item as a Record Document prepared by Contractor.

H. At the end of the project, Contractor shall provide three (3) sets of final as-built

drawings in CAD Format in paper and electronic format for the

Engineer/Owner.

1.05 FINAL STRUCTURE WALKTHROUGH/PUNCHLIST

A. Upon completion of all contract work, the Contractor will notify the Engineer in

writing that all work is completed and that a final walkthrough review of the

structure is requested for the purpose of final punchlist preparation.

B. The Contractor shall review the project prior to written notification to verify

completeness of all contract work. The intent of final punchlist preparation is

not to identify contract work not performed but to review completed work for

conformance with project specifications.

C. Upon receipt of the final punchlist from the Engineer, the Contractor has one

week to complete all punchlist items, unless otherwise approved by the Owner

(work hours to be approved by the Owner). After the one week period, the

Engineer will review the project site and verify completeness of the punchlist

items. For any punchlist items not completed during this period as identified by

the Engineer during his review, the Owner has the right to complete the

remaining work outside the contract and deduct the cost of this work from the

Contractor's final payment on the project.

D. Any punchlist review time spent by the Engineer beyond the two reviews

outlined above, will be paid by the Contractor at the Engineer's current Fee and

Rate Schedule by deducting these fees from the Contractor's final payment on

the project.

1.06 WARRANTIES

A. Provide duplicate original copies to the Owner for all warranties/guarantees in

accordance with project specifications. Provide one copy of all

warranties/guarantees to the Engineer.

B. All warranties/guarantees are to be addressed to the Owner, not the

Engineer.

C. All warranties/guarantees will provide labor and material for both material

and workmanship deficiencies during the warranty period.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT CLOSEOUT

01700 - 4

D. All warranties/guarantees shall include the following:

1. Name of product installed.

2. Location of product installation.

3. Quantity of product installed.

4. Final completion date of project as start date of warranty period.

E. Execute and assemble applicable documents from Subcontractors, suppliers, and

manufacturers.

F. Provide Table of Contents and assemble all warranties/guarantees in three ring

binders with durable plastic cover.

G. Provide warranties/guarantees prior to submitting final Application for Payment

of retainage.

H. For items of Work delayed beyond the Contract Date of Completion, provide

updated submittal within ten days after acceptance, listing date of acceptance as

start of warranty period.

1.07 WAIVERS OF LIEN

A. Provide sworn statement and full unconditional waiver of lien for total project

cost.

B. Provide individual full unconditional waivers of lien from all material suppliers

and subcontractors.

END OF SECTION

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

CLEANING

01710-1

SECTION 01710

CLEANING

1.1 GENERAL

A. Execute cleaning, during progress of the work, at completion of the work, and as

required by the Contract.

B. Conduct cleaning and disposal procedures in compliance with all applicable laws, codes,

ordinances and regulations.

1.2 MATERIALS

A. Use only those cleaning materials and methods recommended by the manufacturer of

the surface material to be cleaned and the cleaning material manufacturer.

1.3 DURING CONSTRUCTION

A. Perform continuous cleaning to keep the work, the site, roadways and adjacent premises

free from accumulations of waste materials, rubbish, windblown debris, dirt and mud

resulting from construction operations.

B. Provide on-site containers for the collection of waste materials, debris and rubbish.

C. Remove waste materials, debris and rubbish from the site daily and dispose of at legal

disposal areas away from the site.

1.4 DUST CONTROL

A. Clean interior spaces prior to the start of finish painting and continue cleaning on an as-

needed basis until painting is finished.

B. Schedule operations so that dust and other contaminants resulting from cleaning

process will not fall on wet or newly-coated surfaces and does not become offensive to

occupants, neighbors or passers-by.

C. Employ properly trained workmen for all cleaning operations.

1.5 FINAL CLEANING

A. Complete the following cleaning operations before requesting inspection for Certification

of Substantial Completion for the entire Project or a portion of the Project and upon Final

Completion in areas where Work was completed during the period between Substantial

Completion and Final Completion.

1. Clean the Project site, yard and grounds, in areas disturbed by construction

activities, including landscape development areas, of rubbish, waste materials,

litter and foreign substances. Sweep paved areas broom clean. Remove petro-

chemical spills, stains and other foreign deposits. Rake grounds that are neither

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

CLEANING

01710-2

planted nor paved, to a smooth even-textured surface.

2. Remove tools, construction equipment, machinery and surplus material from the

site.

3. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition,

free of stains, films and similar foreign substances. Avoid disturbing natural

weathering of exterior surfaces. Restore reflective surfaces to their original

condition.

4. Remove debris and surface dust from limited access spaces, including plenums,

shafts, trenches, equipment vaults, manholes, and similar spaces.

5. Broom clean concrete floors in unoccupied spaces.

6. Clean transparent materials, including mirrors and glass in doors and windows.

Remove glazing compounds and other substances that are noticeable vision-

obscuring materials. Replace chipped or broken glass and other damaged

transparent materials. Polish mirrors and glass, taking care not to scratch

surfaces.

7. Remove labels that are not permanent labels.

8. Touch-up and otherwise repair and restore marred exposed finishes and surfaces.

Replace finishes and surfaces that can not be satisfactorily repaired or restored,

or that show evidence of repair to the satisfaction of the Authority. Do not paint

over "UL" and similar labels, including mechanical and electrical name plates.

9. Wipe surfaces of mechanical and electrical equipment and similar equipment.

Remove excess lubrication, paint and mortar droppings and other foreign

substances.

10. Replace air disposable filters and clean permanent air filters. Clean diffusers,

registers, grilles, ducts, blowers and coils.

11. Clean light fixtures, lamps, globes and reflectors to function with full efficiency.

Replace burned out bulbs, and defective and noisy starters in fluorescent and

mercury vapor fixtures.

12. Leave the Project clean and ready for occupancy.

B. Remove temporary protection and facilities installed during construction.

C. Comply with governing regulations and safety standards for cleaning operations.

Remove waste materials from the site and dispose of in a lawful manner. Where extra

materials of value remain after completion of associated construction have become the

Authority's property, deliver these materials as directed.

D. Prior to final completion and occupancy, the Contractor, Architect and the Authority shall

conduct an inspection of sight-exposed interior and exterior surfaces, and all work areas,

to verify that the entire Work is clean.

END OF SECTION 01710

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT RECORD DOCUMENTS

01720-1

SECTION 01720

PROJECT RECORD DOCUMENTS

1. GENERAL

1.01. WORK INCLUDES

A. The Contractor will:

1. Maintain one copy of:

a. Contract drawings, including separate volume(s) of details.

b. Project Manual

c. Interpretations and supplemental instructions

d. Addenda

e. Reviewed, approved shop drawings and product data

f. Other modifications to contract

g. Field test records

h. All schedules

i. Correspondence file

2. Store documents in temporary field office/other apart from documents used for field

construction.

3. Provide files and racks for document storage.

4. File documents in format in accord with Project Manual Table of Contents.

5. Maintain documents in clean, dry, legible condition.

6. Do not use record documents for field construction purposes.

7. Make documents available at all times for inspection by Engineer and Owner.

1.02. RELATED REQUIREMENTS

A. Specified elsewhere:

1. 01340 - Shop Drawings, Product Data & Samples

1.03. MARKING DEVICES

A. Provide colored pencils/ballpoint pens/felt tip marking pens/other for marking.

1.04. RECORDING

A. Label each document "PROJECT RECORD DOCUMENTS" in 2" high printed letters.

B. Keep record documents current.

C. Do not permanently conceal any work until required information has been recorded.

D. Contract drawings: Legibly mark to record actual construction:

1. Location of internal utilities and appurtenances concealed in construction referenced

to visible and accessible features of structure.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

PROJECT RECORD DOCUMENTS

01720-2

2. Field changes of dimension and detail.

3. Changes made by change order.

4. Details not on original contract drawings.

E. Specifications and addenda: Legibly mark up each section to record:

1. Manufacturer, trade name, catalog number, and supplier of each product and item of

equipment actually installed.

2. Changes made by change order or field order.

3. Other matters not originally specified.

F. Shop Drawings: Maintain as record documents; legibly annotate drawings

to record changes made after review.

1.05. SUBMITTALS

A. At completion of project, deliver record documents to Engineer.

B. Accompany submittal with transmittal letter, in duplicate, containing:

1. Date

2. Project title and number

3. Contractor’s name and address

4. Title and number of each record document

5. Certification that each document as submitted is complete and accurate

6. Signature of Contractor, or his authorized representative

END OF SECTION 01720

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

NON-SHRINK GROUT 03611– 1

SECTION 03611 NON-SHRINK GROUT

PART 1 – GENERAL

1.01 RELATED DOCUMENTS

A. Contract Drawings and General Provisions of the Contract, including General and Special Conditions and Division 01 Specification Sections, apply to this Section..

1.02 SUMMARY

A. This Section specifies requirements for furnishing all labor, materials, and equipment required to provide and install the grout as shown on the Contract Drawings and as required including surface preparation and all other appurtenant work and items required to complete this Work; including the following:

1. Cementitious Grout.

1.03 DEFINITION

A. For the purpose of these Specifications, “non-shrink grout” shall be defined as a high-strength mortar or grout which does not shrink in the plastic state, is dimensionally stable in the hardened state, and bonds permanently to a clean metal base plate and concrete substrate.

1.04 REFERENCES

A. American Concrete Institute (ACI):

1. ACI 503.2 Specification for Bonding Plastic Concrete to Hardened Concrete with a multi-Component Epoxy Adhesive.

B. American Society for Testing and Materials (ASTM):

1. ASTM C109 Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or 50-mm Cube Specimens.

2. ASTM C157 Test Method for Length Change of Hardened Hydraulic-Cement Mortar and Concrete.

3. ASTM C579 Test Methods for Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings and Polymer Concretes.

4. ASTM C827 Test Method for Change in Height at Early Ages of Cylindrical Specimens from Cementitious Mixtures.

5. ASTM C881 Specification for Epoxy-Resin-Base Bonding Systems for Concrete.

6. ASTM C1090 Test Method for Measuring changes in Height of Cylindrical Specimens from Hydraulic-Cement Grout.

7. ASTM C1107 Specification for Packaged Dry, Hydraulic-Cement grout (Non-shrinkable).

1.05 SUBMITTALS

A. Submit, for the grout provided, for the Authority’s review and approval, the following:

1. Manufacturer’s product data. 2. Manufacturer’s installation instructions and recommendations including mixing,

surface preparation and temperature considerations.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

NON-SHRINK GROUT 03611– 2

3. Manufacturer’s Safety Data Sheets (MSDS) for the grout. 4. Recommended storage requirements and product life. 5. Product testing methods and conformity to ASTM standards. 6. Curing requirements and recommendations.

B. Certification: Submit certificates of compliance or laboratory test reports which indicate the following:

1. Materials used in the grout are free from metallic components and corrosion-producing elements.

2. Materials meet specified shrinkage and compressive strength requirements.

1.06 DELIVERY, STORAGE AND HANDLING

A. Deliver materials to site in manufacturer’s original, unopened packaging, with labels clearly identifying product name and manufacturer.

B. Store materials in a clean, dry area in accordance with manufacturer’s instructions.

C. Protect materials during handling and application to prevent damage or contamination.

1.07 PROJECT CONDITIONS

A. Ensure that substrate ambient air and surface temperatures are 40 degrees F. within 24 hours of placement.

1.08 COORDINATION

A. Coordinate work of this Section with other subcontractors to verify required dimensions and locations including for other items to be installed with the grout.

B. Coordinate the delivery of items to be installed with the grout so as to avoid delays.

PART 2 – PRODUCTS

2.01 MATERIALS

A. Cementitious Grout: Provide non-shrink, non-metallic, non-corrosive cement-based grout conforming to the following requirements:

1. Applicable Standards: ASTM C1107 and CRD-C621. 2. Grout shall be manufactured specifically for use in supporting heavy loads (loads

in excess of 300 pounds per square foot concentrated load or 100 pounds per square foot uniform load). Grout: ASTM C1107, Grade A, B, or C, as appropriate for the condition or circumstance.

3. Shrinkage at 28 days: No shrinkage before hardening (0.00 shrinkage when tested in accordance with ASTM C827); no shrinkage after hardening (0.00 shrinkage when tested in accordance with CRD-C621).

4. Compressive strength, minimum:

a. At one day: 1000 psi b. At three days: 2500 psi c. At seven days: 3500 psi d. At 28 days: 5000 psi

5. Initial setting time, after addition of water: approximately one hour at 70 degrees F.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

NON-SHRINK GROUT 03611– 3

6. Provide nonsag trowelability or flowability as necessary for the particular application.

B. Water: Clean and potable, free of impurities detrimental to grout.

2.02 MIXING

A. Mix grout ingredients for both cementitious grout and epoxy grout in accordance with the respective manufacturer’s mixing instructions and recommendations. Mix grout materials in proper mechanical mixers.

B. Mix grout as close to work area as possible.

2.03 SOURCE QUALITY CONTROL

A. Visual Inspections: Perform visual inspection of the grout mixing and placement to determine and verify grout consistency, slump and stiffness are appropriate and proper for the location and type of installation.

B. Shrinkage Tests:

1. Cementitious Grout: Grout shall meet the following performance requirements:

a. Expansion: 0.4 percent maximum at 3, 14 and 28 days. Grout shall exhibit no displacement when tested in accordance with ASTM C157.

b. Shrinkage: None (0.00 shrinkage at 28 days when tested in accordance with ASTM C827 and ASTM C1090). There shall be no vertical volume shrinkage of grout in the plastic or hardened stage at any time.

C. Strength Tests: Compressive strength of grout shall meet the following requirements:

1. Cementitious Grout: 5,000 psi minimum at 28 days when tested in accordance with ASTM C109.

2. Epoxy Grout: 10,000 psi minimum at 7 days when tested in accordance with ASTM C579.

PART 3 – EXECUTION

3.01 SURFACE PREPARATION

A. Concrete surfaces to receive grout shall be prepared by chipping, sandblasting, waterblasting or other accepted methods to remove defective concrete, laitance, dirt, oil, grease and other foreign matter to achieve sound, clean concrete surfaces. Lightly roughen concrete for bond, but not enough to interfere with proper placement of grout.

B. Cover concrete areas with protective waterproof covering until ready to place grout.

C. Remove foreign matter from steel surfaces to be in contact with grout. Clean contact steel surfaces as necessary by wire brushing and wiping dust clean.

D. Align and level components to be grouted and maintain in final position until grout placement is complete and accepted.

E. Install forms for grout around the column base plates and other spaces to be grouted. The tops of such forms shall be one inch above surfaces to be grouted.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

NON-SHRINK GROUT 03611– 4

F. Saturate concrete surfaces with clean water and remove excess water immediately before grouting.

3.02 PLACING GROUT

A. Place grout in accordance with the manufacturer’s installation instructions and recommendations. Pour grout from one side only until grout rises at least one inch above the plate on the opposite side of said plate. Strapping and plunging or other recommended method may be used to force grout to flow under the entire area.

B. Neatly trowel edges of grout base, tapered at an angle of 60 degrees when measured from the horizontal or as indicated. Provide dry-pack cementitious grout where additional grout is required for shoulders.

C. Do not remove leveling shims for at least 48 hours after grout has been placed.

D. After shims have been removed, if used, fill voids with grout, packing the material with a suitable tool.

E. Do not use grout which has begun to set or if more than one hour has elapsed after initial mixing.

3.03 CURING

A. Cementitious grout shall be cured the same as specified for concrete.

B. Epoxy grout shall be cured as recommended by the grout manufacturer.

C. Do not remove forms until grout is sufficiently hard to avoid sagging or damaging.

D. Wet cure the grout until the forms are stripped. Cure exposed material following placement using wet burlap for 48 hours.

END OF SECTION 03611

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-1

SECTION 05120

STRUCTURAL STEEL

PART 1 GENERAL

1.01 SECTION INCLUDES:

A. Work under this Section is subject to the requirements of the Contract Documents.

B. Furnish and install all Structural Steel Work as shown on the Drawings and as specified herein, including but not limited to the following:

1. Columns with top and base plates

2. Plates, shims, clips, fasteners, etc., necessary to install structural steel.

C. Furnish all items as shown on the Drawings and as specified to be installed under other Sections, including but not limited to the following:

1. Anchor Bolts

1.02 REFERENCES:

A. "Manual of Steel Construction", American Institute of Steel Construction.

B. "Specifications for the Design, Fabrication and Erection of Structural Steel for Buildings", American Institute of Steel Construction.

C. "Code of Standard Practice for Steel Buildings and Bridges", American Institute of Steel Construction.

D. "Specification for Structural Joints using ASTM A 325 or A 490 Bolts", Research Council on Structural Connections (RCSC), American Institute of Steel Construction.

E. ANSI B18.2.2 " Square and Hex Nuts", American National Standards Institute.

F. AWS D1.1 “Structural Welding Code", American Welding Society.

G. AWS SR-1 "Special Ruling for Gas-Metal Arc Welding with Carbon Dioxide Shielding", American Welding Society.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-2

H. "Specifications for Assembly of Structural Joints Using High Strength Steel Bolts", Research Council on Riveted and Bolted Structural Joints of the Engineering Foundation.

I. "Guide to the Shop Painting of Structural Steel", The Society for Protective Coatings, and American Institute of Steel Construction.

J. SSPC-PA 1 " Paint Application Specification", The Society for Protective Coatings.

K. References to ASTM Specifications are to the designated Specifications of the American Society for Testing and Materials, latest edition.

1.03 SUBMITTALS:

A. Submit the following

1. Shop Drawings

a. Shop Drawings must show all materials, method of joining, sizes of members, and thickness of metal, and must contain full and complete information regarding joints and fastenings.

(1) Drawings must show relative layout of walls, beams, girders, and other supports, as well as openings, all correctly dimensioned.

(2) Items must be plainly marked for location on the job and referenced to the shop Drawings.

b. Use AWS symbols to indicated welding and show length, size, and spacing (if not continuous).

(1) Auxiliary view must be shown to clarify all welding.

(2) Notations such as “¼ inch weld” and "tack weld " are not acceptable.

c. Erection diagrams clearly indicate the method and sequence of erection, item mark numbers, equipment loads and calculations indicating the adequacy of the permanent construction to sustain equipment and construction loads and required tolerance for setting embedded items.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-3

B. Test Reports

1. Submit test reports necessary to show compliance with the Contract Documents.

C. Manufacturer’s Certification

1. Submit certification that products meet or exceed the specified requirements.

a. Furnish the Authority with two (2) Certified copies of mill reports covering the chemical and physical properties of all steel used in the Work.

(1) Certification of Welders; hereinafter specified in Part 2, Paragraph 2.03 of Section 05120 – Structural Steel.

1.04 QUALITY CONTROL:

A. Contractor Qualifications: Installation of structural steel must be performed only by a qualified Installer. The Contractor must submit evidence of such qualifications upon request by the Authority.

B. Perform Work in accordance with the latest edition, of the appropriate divisions, of the following:

1. Structural steel details, fabrication, and erection must conform to AISC “Manual of Steel Construction” unless otherwise shown or specified.

2. All structural steel material must be ASTM A 992 Grade 50 for wide flange. All plate material must be ASTM A572, Grade 50.

3. Field connections must be bolted or welded. High strength bolts must be installed in accordance with AISC Specifications. Bolts must be ASTM A 325, ¾" diameter unless noted otherwise. All welding to be done by certified welders. All welds to be E70 XX Electrodes.

4. Shop and field welding procedures and standards of acceptance must be in accordance with AWS D1.1 “Structural Welding Code”, American Welding Society.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-4

1.05 DELIVERY, STORAGE AND HANDLING:

A. Exercise care in storing, handling and erecting structural steel and provide necessary blocking or other supports required and in supporting it properly at all to insure that no piece must be bent, twisted, or otherwise damaged. Damaged material must be corrected to the approval of the Authority before being erected, or replace when so directed by the Authority.

B. Protection - Protect materials against damage from mechanical abuse, plaster, salts, acids, staining and other foreign matter by an approved means during transportation, storage and erection and until completion of construction work. All unsatisfactory materials must be removed from the premises, and all damaged materials replaced with new materials.

C. Access and Storage Areas

1. All access routes and storage areas must be subject to the approval of the Authority in order to reduce interference with Facility Operations.

1.06 SPECIAL REQUIREMENTS:

A. Field Measurements - Before proceeding with the fabrication of the work, the Contractor must verify all dimensions and take such measurements as are required for proper fabrication and erection of the work.

PART 2 PRODUCTS

2.01 MATERIAL AND WORKMANSHIP:

A. Except as otherwise noted or specified, all materials, unit stresses, fabrication, assembly erection and painting must be in accordance with the American Institute of Steel Construction Specification for Design, Fabrication and Erection of Structural Steel of Buildings.

B. All steel shapes and plates unless otherwise specified, must conform to ASTM A 992 for wide flange beams, ASTM 572 for all plates. All welding must be with E70 electrodes and in accordance with procedures and recommendations of the American Welding Society as referred from the AISC Specifications.

C. Shop assembled members must be welded.

1. No field riveting will be permitted.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-5

a. Field connections must be high strength bolted or welded.

D. Where welding occurs, it must be by the electric arc process in accordance with American Welding Society's Code for Arc and Gas Welding in Building Construction.

E. Execute all welding by operators who have been qualified previously by tests as prescribed by the American Welding Society's Standard Qualification Procedure" to perform the work required.

F. Provide all connections, clip angles, anchors, etc., necessary for complete erection.

G. No burning of steel will be permitted in the field.

1. Members burned in the shop must be finished to an acceptable appearance, equal to a sheared finish.

a. Holes must not be burned in either shop or field.

2. No cutting of structural shapes must be done in the field without the consent of the Authority.

H. Materials must be properly marked and match-marked where field assembly is required. The sequence of shipments must be such as to expedite erection and minimize the field handling of material..

I. Use care in handling and erection to insure that steel must not be twisted, bent or otherwise damaged, and should any difficulty be encountered, it must be immediately reported to the Authority.

J. Fasteners

1. High strength bolts, nuts, and washers: ASTM A 325 bolts, nuts, and washers must conform to ANSI B18.2.2, regarding dimensions.

K. Welding Electrodes

1. E70 In accordance with AWS standards.

L. Anchor Bolts

1. ASTM F1554 Grade 55

M. Shop Painting

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-6

1. Primer for concealed steel: rust-inhibitive metal primer standard with the steel fabricator.

2. Products from one of the following Manufacturers will be acceptable:

a. Tnemec Co., Inc., Blue Island, IL 60406,

b. Glidden Coatings & Resins

c. Sherwin-Williams Company

2.02 DESIGN:

A. Steel Contractor must provide design of all structural steel framing connections including connection details shown on the Drawings, conforming to applicable codes and standards.

B. Details indicated on the Drawings may be modified in order to simplify or expedite erection. Such modifications must be submitted prior to shop detailing.

1. Do not make changes, substitution, or modifications subsequent to approval of Shop Drawings without resubmission and acceptance of the Authority.

2. All connections designed by the Contractor must be submitted for review. Such submittals must be stamped by a structural engineer licensed in Illinois retained by the Contractor.

2.03 SHOP WELDERS QUALIFICATION:

A. Welders for shop fabrication, including tack welders, must be certified and tested by an AWS Certified Welding Inspector (CWI), and the certifications signed by the same, within six (6) months before start of Work. Submit welder certifications to the Authority. Those currently certified, and who are performing under the classification necessary for their Work for this Contract, need not be recertified. Aforementioned certification by the Contractor will be acceptable if submitted prior to welding for the Project.

2.04 MARKING:

A. Mark each member with an identifying mark. Marks must not be duplicated for different types of steel and must be legible throughout fabrication and visible during field erection.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-7

B. Identifying marks must correspond to marks shown on approved erection of diagrams.

2.05 FABRICATION:

A. Materials must be new, clean and free from excessive mill scale, flake, rust or pitting.

B. Fabricate only from approved shop Drawings. Substitutions of Sections or modifications of details must be made only when approved by the Authority, and at no additional cost to the Authority.

1. Cut or dress abutting joints true and straight to allow a close fit.

2. All members must be free from twist, kinks, buckles, or open joints and must be made accurately so that when assembled, parts must come together without distortion and shimming.

C. Parts assembled with bolts must be in close contact, except where separators are required. Separators must be close fitting.

D. Ends of columns must be milled to a true surface perpendicular to the vertical axis of the member and be free of all burrs or imperfections which may prevent full bearing.

E. Machined bearing surfaces must be coated with Type 3 metal primer immediately after machining.

F. Drill required holes in base or bearing plates.

1. Drill grout holes in column bearing plates where shown.

2. Drill holes in members for the work of other Sections where shown on the Drawings or when information is provided before final shop drawing approval for specific members.

G. Furnish anchor bolts, setting plates, and templates in ample time to prevent delay in the work shown in other Sections.

2.06 SHOP FINISHES:

A. Prepare surfaces scheduled to be painted per SSPC-SP 3.

1. Remove loose mill scale, rust, splatter, slag or flux deposits, oil, dirt, and other foreign matter.

2. Painting must be in accordance with SSPC-PA-1.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-8

PART 3 EXECUTION

3.01 INSPECTION:

A. Before commencing steel erection, examines substrate surfaces to determine that they are free of conditions which might be detrimental to proper and timely completion of the Work. Start of Work must indicate acceptance of the substrate.

3.02 FIELD WELDERS QUALIFICATIONS:

A. Field welders must be qualified according to applicable Specification for Manual shielded-arc welders and according to AWS SR-1 for gas metal-arc welders. Field welders must be certified and tested by an AWS Certified Welding Inspector (CWI) and the certifications signed by same, within 6 months before start of Work. Qualification tests and certifications must be paid for by the Contractor.

1. Those currently certified for the classifications necessary for their work will not be required to be re-certified. The aforementioned certification will be acceptable if submitted to the Authority prior to the start of any field welding.

3.03 ERECTION EQUIPMENT:

A. Furnish erection equipment, hoists, planking, and other equipment required for the proper and safe execution of all erection work.

B. Provide temporary bracing, guys or other devices required to provide safety and stability for the erection of structural steel.

1. Leave bracing in place until steel work is in final position and approved.

2. Maintain adequate lateral support throughout construction.

C. Torque wrenches for tightening high strength bolts may be either manual or power type. Method of calibrating must meet the approval of the Authority.

1. Calibration of wrenches must be checked daily by an approved method.

2. Check at other times when setups change or other conditions vary.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-9

3. Required bolt tension and torque values must meet the approval of the Authority.

3.04 ERECTION:

A. Assume responsibility for the correct fitting of all structural members and for the elevation and alignment of the finished structure and any adjustments necessary in the steel frame because of discrepancies in elevations and alignment.

B. Work must be assembled and erected in place as rapidly as the progress of other work will permit.

C. Columns must be erected, securely braced and guyed, and held plumb and in line until after bolting has been completed. Setting plates must be set on grout at least seventy-two (72) hours prior to the erection of base plates and columns.

D. Re-drilling and drifting pins must not be used to enlarge unfair holes in main material.

1. Holes that must be enlarged to admit bolts must be reamed.

2. Burning and drifting may be used to align unfair holes in secondary bracing members only upon meeting the approval of the Authority.

E. Field connections must be high strength bolts or welding as shown. Minimum bolted connections must be framed beam connections conforming to design procedure set forth in the "Manual of Steel Construction."

F. No cutting of structural shapes in the field will be allowed without meeting the approval of the Authority.

3.05 TESTS AND INSPECTIONS:

A. The Authority reserves the right to have materials and workmanship subject to inspections and tests in either mill or shop witnessed by an independent QA testing laboratory retained by the Authority.

1. Contractor must notify the Authority of mill and shop schedules so that arrangements can be made for a representative of the Authority or QA testing laboratory to be present when inspection or tests are to be made.

Construction Services Arie Crowne Theater Stage Support

May 21, 2018

STRUCTURAL STEEL

05120-10

B. Periodic inspection and tests which may be required by the Authority is in addition to the Contractors constant QC inspection and testing and must not relieve the Contractor of the responsibility to furnish satisfactory materials and workmanship.

C. Contractor QC to check all shop welds by visual means, by magnetic particle methods conforming to ASTM E 709, or by ultrasonic methods conforming to ASTM E l64. Submit three (3) copies of all test results to the Authority.

D. The Authority reserves the right to reject material at any time before final acceptance of the structure when, in the opinion of the Authority, materials or workmanship do not conform to Specification requirements.

3.06 GENERAL CLEAN-UP:

A. All rubbish and debris resulting from the Work of this Section must be collected, removed from the site and disposed of legally.

END OF SECTION 05120