Project Management What is a project? Unique, one-time operations designed to accomplish a set of objectives in a limited time frame Examples: construction of new buildings, installing a new computer network system, launching a space shuttle, producing a movie, etc Once underway, projects must be monitored to contain cost and meet timelines This chapter is devoted to a description of graphical and computational methods that are used for planning and scheduling projects Key Decisions in Project Management Deciding which projects to implement Selecting the project manager Selecting the project team Planning and deciding the project Managing and controlling project resources Deciding if and when a project should be terminated Planning and Scheduling With Gantt Charts Gantt chart - a popular tool for planning and scheduling simple projects Used to monitor progress over time by comparing planned progress to actual progress Planning with PERT/CPM PERT (program evaluation review technique) and CPM (critical path method) are two of the most widely used techniques for planning and coordinating large-scale projects By using PERT/CPM, managers are able to obtain: (a) A graphical display of project activities

Project Management - Southern Oregon Universitywebpages.sou.edu/~ordonez/BA380Web/Lecture Notes in Word... · Web viewKey Decisions in Project Management Deciding which projects to

Embed Size (px)

Citation preview

Project Management

What is a project?

Unique, one-time operations designed to accomplish a set of objectives in a limited time frame

Examples: construction of new buildings, installing a new computer network system, launching a space shuttle, producing a movie, etc

Once underway, projects must be monitored to contain cost and meet timelines This chapter is devoted to a description of graphical and computational methods that

are used for planning and scheduling projects

Key Decisions in Project Management

Deciding which projects to implement Selecting the project manager Selecting the project team Planning and deciding the project Managing and controlling project resources Deciding if and when a project should be terminated

Planning and Scheduling With Gantt Charts

Gantt chart - a popular tool for planning and scheduling simple projects Used to monitor progress over time by comparing planned progress to actual progress

Planning with PERT/CPM

PERT (program evaluation review technique) and CPM (critical path method) are two of the most widely used techniques for planning and coordinating large-scale projects

By using PERT/CPM, managers are able to obtain:(a) A graphical display of project activities(b) An estimate of how long the project will take(c) An indication of which activities are most critical to timely project completion(d) An indication of how long an activity can be delayed without lengthening the project

Network Diagram – a.k.a. precedence diagram is a chart used in PERT that depicts major project activities and their sequential relationships

o Activity on Node (AON)o Activity on Arrow (AOA)

Path – a sequence of activities that leads from the starting node to the finishing nodes

Critical path – the path with the longest time

Critical activities – activities that are on the critical path. They have zero slack

Network conventions

Deterministic vs Probabilistic Time Estimates

Deterministic times – if time estimates can be made with a high degree of confidence that actual time will not differ significantly

Probabilistic times – must include an indication of the extent of probable variation

A Computing Algorithm

ES – earliest time activity can startEF – earliest time an activity can finishLS – latest time an activity can startLF – latest time an activity can finish

Problem 1 (see page 806)

Problem 3 (768)

The information below pertains to a project that is about to commence. As the project manager, which activities would you be concerned with in terms of timely project completion? Explain.

Immediate Estimated Estimated Activity Predecessor Time (days) Activity Precedes Time (days)

a -- 15 a B 15b A 12 b C,D 12c B 6 c E 6d B 5 d End 5e C 3 e End 3f -- 8 f G,H 8g F 8 g I 8h F 9 h J 9i G 7 i End 7j H 14 j K 14k J 6 k End 6

End D,E,I,K

Problem 7 (769)

Three recent college graduates have formed a partnership and have opened an advertising firm. The first project consists of activities in the following table.

ActivityImmediate

Predecessor to tm tpA -- 5 6 7B -- 8 8 11C A 6 8 11D -- 9 12 15E C 5 6 9F D 5 6 7G F 2 3 7H B 4 4 5I H 5 7 8

End E,G,I

(a) Draw the precedence diagram

(b) What is the probability that the project can be completed in 24 days or less? In 21 days or less?

Excel Solution

(c) Suppose it is now the end of the seventh day and that activities A and B have been completed. Time estimates for the completion of activity D are 5, 6, and 7. Activity C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.

Problem 11(770)

The following precedence diagram reflects three time estimates for each activity. Determine:

(a) The expected completion time for each path and its variance

(b) The probability that the project will require more than 49 weeks.

(c) The probability that the project can be completed in 46 weeks or less.

1

5

42

3

9

8

7

6

11

10

8 -8 -8(a)

7-1 0-12(h )

11-12-14(d )

1 3-13-13(g)

1 4-18-26(f )

5 -6 -7(c )

5 -7-1 0(k)

9-1 0-12(e)

11-12-13(b )

8-1 0-14( i)

6 -6 -6(m )

10-11-12(l)