Project Overview and Status

June 17, 2014

Loreen Bobo, P.E.I-4 Ultimate Construction Program Manager

Page 2: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Improvements

• Length: 21 miles from west of

Kirkman Road to East of SR 434• Orange and Seminole Counties

• Cost: $2.323 billion (yoe) in

design/construction costs

• What: Reconstruction of mainline

and interchanges

• What: Addition of 4(four) Express

Lanes (4Express)

• Design/Construction Duration:

~ 6.5 years

Page 3: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Improvements

• Reconstruction of 15 interchanges

• 3 system-to-system interchanges

• Over 60 new bridges

• Over 70 bridge replacements

• 2 new pedestrian crossings at • Maitland Blvd. and SR 436

• Increase design speed to 60 mph

• P3 – public-private partnership• Design-build-finance-operate-maintain• I-4 Mobility Partners chosen 4/23/14

Page 4: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

6 general use lanes + auxiliary lanes

4 Express Lanes (2 in each direction)

Interstate Typical Section

Page 5: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Interstate Typical Section

Emergency access gates will be provided between the Express Lanes and general use lanes at a minimum of every 2 miles.

General Use Lanes

Express

Lanes

Page 6: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Planned Access to Express Lanes

• FDOT will set the toll rates and collect

the tolls.

• Access to and from the tolled express

lanes will be limited

• Barrier wall separated

• Slip ramp access

• Direct ramp access

• Six to seven access points in each

direction

• Variable tolling

• All Electronic Tolling

• Everyone pays

• No heavy trucks

Page 7: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

I-4 Ultimate Aesthetics

• Enhanced treatments levels

• Decorative columns

• Special lighting

• Color coordinated

• Landscaping

Page 8: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Noise Barriers

Page 9: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Corridor Options

SunRail

Page 10: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Public Private PartnershipsValue Proposition

P3 Seeks to Achieve 5 Primary Goals • Provide capacity improvements much sooner than possible under

traditional pay-as-you go approach – 20 years sooner!

• Eliminate project phasing and advance the overall project

• Capitalize on the private sector’s innovation and access to capital markets

• Transfer of appropriate risk items to private partner

• Enhance long-term, lifecycle cost efficiency and service quality

Page 11: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Availability PaymentsType of P3

• The “owner,” meaning the government entity, “pays” to the extent the facility is open to traffic and meets contractual performance specifications for operations and maintenance.

• Typically used for projects with established traffic.

• May be used for toll deals where goal is to maximize use or reduce congestion, rather than to maximize revenue.

• Example: 595 Express, Port of Miami Tunnel, • Florida’s Turnpike Service Plazas

Page 12: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Estimated Costs

• Capital Cost (Design and Construction): $2.4 billion (Year of Expenditure – YOE)

• $54 million toward local roads

• Operations and Maintenance: $378 million over contract

• Renewal and Replacement: $493 million over contract

• Other (SPV, Insurance, Interest, Finance): Varies

Not actuals from Best Value Proposer

Page 13: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Financial Details

Strategic Corridor 7%Other State

Funds 2%

SIS Allocation - 20%

Other Federal -

4%

DS and DDR - 6%

OOCEA, Turnpike

4%

Toll Revenu

e 57%

FUND-ING

Page 14: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Timeline

March 4, 2013 Industry Forum

March 5-6, 2013 One on One’s with interested teams (8)

March 8, 2013 Request for Qualifications

June 5, 2013 Short-listed 4 teams (out of 7), RFP released

February 12, 2014 Technical Proposals due (4 received)

March 13, 2014 Financial Proposals due (4 received)

April 23, 2014 Best Value Selection – I-4 Mobility Partners

Late Summer 2014 Financial close, contract signed

After Financial Close Start design (NTP 1)

4+ months later Construction;operations & maintenance (NTP 2)

2020/2021 Construction completed

Full O&M starts, replacement & renewals

2054 Contract ends

Page 15: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Request for Proposals

Instructions to Proposers (ITP): Procurement Document

Volume I: Concession Agreement (CA)

435 pages, including 26 appendices

Volume II: Technical Requirements

495 pages

Section 1: Project Description

Section 2: Project Requirements and Provisions for Work

Section 3: Design and Construction Requirements

Attachment 1 – ITS Deployment Requirements

Attachment 2 – Tolls Infrastructure Requirements

Attachment 3 – QAM and QAF Requirements

Attachment 4 – QA/QC Requirement

Section 4: Operations & Maintenance Requirements

Section 5: Handback Requirements

Volume III: Additional Mandatory Standards

Page 16: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Alternative Technical Concepts (ATC’s)From ITP

Alternative Technical Concepts (ATC’s) Confidential

RFP was not changed if an ATC was allowed 5 meetings with each team, in person Quick turn around needed Team of 25 + people from different disciplines participated in the process. Base Line and Grade – Any deviation of more than 5 feet had to be submitted

Alternative Financial Concepts (AFC’s) Not confidential Teleconferences with each team

One on One meetings Four Meetings with each team Contract Issues rather than technical

Page 17: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Alternative Technical Concepts (ATC’s)From ITP

• Set forth the process for FDOT’s review and acceptance of technical concepts that

conflict with the requirements of the Contract Documents

• This process is intended to allow Proposers to incorporate technical innovation and

creativity into their Proposals

• To be eligible for consideration, proposed ATCs must result in performance, quality and

utility of the end product that is equal to or better than the performance, quality and

utility of the end product that would result from full compliance with the Contract

Documents

Page 18: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Alternative Technical Concepts (ATC’s)From ITP

• A proposed ATC may not be approved if, in FDOT’s sole discretion, it is premised upon

or would require (a) a reduction in quantities without achieving equal or better

performance, quality and utility; (b) a reduction in performance, quality, utility or

reliability; (c) major changes to the existing Environmental Approvals, including

changes that would trigger the need for a supplemental Environmental Impact

Statement under NEPA; (d) a Change in Law; or (e) multiple or material additional

right of way parcels.

Page 19: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Possible ATC Responses

(A) The proposed ATC is acceptable for inclusion in the Proposal (with such conditions,modifications or requirements as identified by FDOT). Approval dates are noted below.Conditional Approval requirements are provided in Attachment 1.

(B) The proposed ATC is not acceptable for inclusion in the Proposal.

(C) The proposed ATC is not acceptable in its present form, but may be acceptable upon thesatisfaction, in FDOT’s sole discretion, of certain identified conditions which must be met orclarifications or modifications that must be made prior to resubmittal (FDOT will not utilize this response after the final submission date for ATCs).

(D) The proposed ATC appears to comply with the Contract Documents and does not require an ATC as to the specific provision of the Contract Documents identified by the Proposer in itsproposed ATC (provided, however, that should it turn out that the concept as incorporated into the Proposal is not within the requirements of the Contract Documents, FDOT reserves the right to require compliance with the requirements of the Contract Documents, in which event the Proposer will not be entitled to modify its Proposal or receive additional compensation or a time extension under the Agreement).

(E) Although the submittal does not require an ATC because it appears to comply with theContract Documents, it may not be included in the Proposer’s Proposal and FDOT will modify the Contract Documents to preclude the concept.

Page 20: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

ATC Stats

Page 21: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

ATC Stats

Page 22: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

I-4 ULTIMATEProposal Scores

Technical Proposal Criteria [Up to 60 points]Technical Proposal Qualitative Assessment - 35 points

Preliminary Corridor Master Plan Submittal Evaluation Criteria Operation and Maintenance Evaluation Criteria

Baseline Construction Period - 5 pointsInclusion of Direct Connection Proposal - 5 pointsProject Technical Enhancements - 15 points

Financial Proposal Criteria [Up to 40 points]Financial Price - 35 pointsFeasibility of Financial Proposal - 5 points

Page 23: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

EEO, DBE, SB & OJT

Disadvantaged Business Enterprise (DBE) Goal

9% for Construction

9% for Design

9% for Operations and Maintenance

Small Business (SB) Goal (non DBE)

3% for Construction

3% for Design

3% for Operations & Maintenance

On-the-Job Training (OJT) Goal

250 trainees

Page 24: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

595 Express - Ft. Lauderdale

595 Express: P3, $1.2 billion design and construction, began construction in 2008, opened to traffic in March 2014.

DBE goal was 8.6% (FY actuals)

08/09 - 9.0%09/10 - 9.2% 10/11 - 8.7% 11/12 - 10.6%12/13 – 17.0%13/14—33.3% (CURRENTLY PROJECTED)4 females working in construction crafts (last year’s report)

On-the-Job Training (OJT) goal

118 trainees (goal) 164 graduated!

Employed on the job

1,728 (average) 2,160 (at peak)

Page 25: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Public InformationCommunity Outreach

• Project website

• Public information

• Lane/ramp closures

• Developing a mobile app

• Project videos

Loreen Bobo, P.E.FDOT Project ContactConstruction Program [email protected]

Page 26: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Project Video

Page 27: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Project Video

Page 28: Project Overview and Status June 17, 2014 Loreen Bobo, P.E. I-4 Ultimate Construction Program Manager

Thank You