Third Quarterly Project Tracking Report 2015 July 2015

Q3 2015 Quarterly Project Tracking Report

Embed Size (px)

Citation preview

Page 1: Q3 2015 Quarterly Project Tracking Report

T h i r d Q u a r t e r l y P r o j e c t T r a c k i n g R e p o r t 2 0 1 5

July 2015

Page 2: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 1

Table of Contents

Executive Summary .....................................................................................................................................2

NTC Project Summary ................................................................................................................................4

NTC Issuance ...................................................................................................................................7

NTC Withdraw.................................................................................................................................8

Completed Projects ..........................................................................................................................8

Project Status Summary .................................................................................................................13

Balanced Portfolio ........................................................................................................................................14

Priority Projects ...........................................................................................................................................16

Out-of-Bandwidth Projects .........................................................................................................................17

Responsiveness Report ................................................................................................................................19

Appendix I ....................................................................................................................................................21

Page 3: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 2

Executive Summary

SPP actively monitors and supports the progress of transmission expansion projects, emphasizing the importance of maintaining accountability for areas such as grid regional reliability standards, firm transmission commitments and tariff cost recovery. Each quarter SPP staff solicits feedback from the project owners to determine the progress of each approved transmission project. This quarterly report charts the progress of all SPP Transmission Expansion Plan (STEP) projects approved either directly by the SPP Board of Directors (Board) or through a FERC filed service agreement under the SPP Open Access Transmission Tariff (OATT). The reporting period for this report is February 1, 2015 through April 30, 2015. Table 1 provides a summary of all projects in the current Project Tracking Portfolio (PTP), which includes all Network Upgrades in which construction activities are ongoing, or construction has completed but not all the close-out requirements have been fulfilled in accordance to Section 13 of Business Practice 7060. The PTP includes all active Network Upgrades including transmission lines, transformers, substations, and devices. Table 1 below summarizes the PTP for this quarter. Figures 1 reflects the percentage cost of each upgrade type in the PTP. Figure 2 shows the percentage cost of each project status in the PTP.

Upgrade Type No. of Upgrades Estimated Cost Miles of New

Miles of Rebuild

Miles of Voltage

Conversion Balanced Portfolio 4 $258,217,874 226.5 0.0 0.0 Economic 4 $37,914,101 0.0 0.0 28.8 High Priority 102 $2,215,684,294 1753.4 11.5 0.0 Regional Reliability 334 $3,156,305,363 1529.2 642.3 588.6 Transmission Service 23 $110,490,871 12.7 31.6 0.0 Zonal Reliability 9 $109,245,734 34.7 28.5 0.0

NTC Projects Subtotal 476 $5,887,858,237 3556.5 713.9 617.4 Generation Interconnection 35 $165,430,659 39.5 0.0 0.0 Regional Reliability - Non OATT 5 $23,567,090 0.0 11.8 0.0 TO - Sponsored 16 $92,968,646 12.0 0.0 46.0

Non-NTC Projects Subtotal 56 $281,966,395 51.5 11.8 46.0 Total 532 $6,169,824,632 3608.0 725.7 663.4

Table 1: Q2 2015 Portfolio Summary

Page 4: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 3

Figure 1: Percentage of Project Type on Cost Basis

4%

0.6%

3%

37%

52%

2% 2%

Balanced Portfolio

Economic

Generation Interconnection

High Priority

Regional Reliability

Transmission Service

Zonal Reliability

Figure 2: Percentage of Project Status on Cost Basis

27%

40%

6%

23%

0.1%1%

1% 0.3%1%

Complete

On Schedule < 4

On Schedule > 4

Delay - Mitigation

NTC Suspension

NTC - Commitment Window

NTC-C Project Estimate Window

RFP Response Window

Re-evaluation

Page 5: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 4

NTC Project Summary

In adherence to the OATT and Business Practice 7060, SPP issues Notifications to Construct (NTCs) to Designated Transmission Owners (DTOs) to commence the construction of Network Upgrades that have been approved or endorsed by the Board intended to meet the construction needs of the STEP, OATT, or Regional Transmission Organization (RTO). Figure 3 reflects project status within each source study, and Table 2 provides the supporting data. Figure 4 shows the amount of estimated cost by in-service year for all Network Upgrades that have been issued an NTC or NTC-C. Figure 5 shows the cost trend of all the Board-approved studies that have resulted in NTCs. Note: Figures 3, 4, and 5, and Table 2 provide data for all projects for which SPP has issued an NTC or NTC-C, regardless of completion date, and therefore include data from Network Upgrades no longer included in PTP.

Figure 3: Project Status by NTC Source Study

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

On Schedule

Suspended

Delayed

Complete

$ M

illio

n

Page 6: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 5

Source Study Complete Delayed Suspended On Schedule Total

2006 STEP $230,534,912 $0 $0 $0 $230,534,912 2007 STEP $413,650,905 $28,719,000 $0 $0 $442,369,905 2008 STEP $416,912,051 $3,543,000 $0 $0 $420,455,051 Balanced Portfolio $803,531,390 $0 $0 $0 $803,531,390 2009 STEP $556,245,220 $15,049,555 $0 $0 $571,294,775 Priority Projects $847,352,680 $127,995,000 $0 $407,791,450 $1,383,139,130 2010 STEP $115,237,966 $22,570,306 $0 $27,149,017 $164,957,289 2012 ITPNT $142,718,959 $56,400,374 $0 $6,300,000 $205,419,334 2012 ITP10 $0 $0 $0 $770,463,719 $770,463,719 2013 ITPNT $121,849,435 $320,334,183 $0 $76,524,777 $518,708,394 2014 ITPNT $3,804,467 $390,988,996 $0 $265,090,771 $659,884,234 HPILS $53,858,906 $201,339,804 $0 $574,122,201 $829,320,911 2015 ITPNT $0 $153,245,705 $0 $142,860,151 $296,105,855 2015 ITP10 $0 $0 $0 $91,510,843 $91,510,843 Ag Studies $721,294,405 $87,979,996 $0 $68,157,416 $877,431,817 DPA Studies $109,182,972 $71,102,077 $0 $12,367,550 $192,652,599 GI Studies $359,171,590 $42,448,492 $10,588,285 $88,569,631 $500,777,998

Total $4,895,345,859 $1,521,716,488 $10,588,285 $2,530,907,525 $8,958,558,158 Table 2: Project Status by NTC Source Study

Figure 4: Estimated Cost for NTC Projects per In-Service Year

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

New Q2 2015 NTC

IS Integration Projects

Previous NTC

$ M

illio

n

Page 7: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 6

Figure 5: Cost Trend per Board-Approved Study

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

2007 2008 2009 2010 2011 2012 2013 2014 2015

2006 STEP

2007 STEP

2008 STEP

Balanced Portfolio

2009 STEP

Priority Projects

2010 STEP

2012 ITP10

2012 ITPNT

2013 ITPNT

2014 ITPNT

HPILS

$ M

illio

n

Page 8: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 7

NTC Issuance Six NTCs were issued since the last quarterly report for approved projects with a total cost estimate of the included Network Upgrades totaling $48.7 million. One NTC was issued to Southwestern Public Service Company (SPS) as a result of the completion of Aggregate Study, SPP-2012-AG3-AFS-9. The total estimated cost of the Network Upgrades listed in the NTC is $15.5 million. One NTC was issued to Oklahoma Gas & Electric Co (OGE) after SPP was notified that an additional Network Upgrade was required on the OGE system to fully address issues identified in the 2013 Integrated Transmission Planning Near-Term Assessment (ITPNT). The total estimated cost of the Network Upgrade is $12,000. Three NTCs were issued as a result of the Board in June approving the Short-Term Reliability Projects identified in the 2015 ITPNT. The total estimated cost of the Network Upgrades listed in these NTCs is $32.5 million. One NTC was issued to Mid-Kansas Electric Company (MKEC) as the incumbent TO to construct the portion of the Competitive Project identified in the 2015 Integrated Transmission Planning 10-Year Assessment determined to be ineligible for the Transmission Owner Selection Process (TOSP). The total estimated cost of the Network Upgrade described in this NTC is $689 thousand. SPP issued a Request for Proposal (RFP) for the portion of the Competitive Project eligible for the TOSP on May 5, 2015. Table 3 summarizes the NTC activity from April 1, 2015 through June 30, 2015. NTC ID values in bold font indicate NTC-Cs.

NTC ID DTO NTC Issue

Date Upgrade Type Source Study

No. of Upgrades

Estimated Cost of New

Upgrades

Estimated Cost of

Previously Approved Upgrades

200297 SPS 5/5/2015

Transmission Service/Regional

Reliability SPP-2012-AG3-AFS-9 3 $15,486,751 $0

200340 OGE 5/7/2015 Regional Reliability 2013 ITPNT 1 $12,000 $0 200342 MKEC 6/30/2015 Regional Reliability 2015 ITP10 1 $689,063 $0 200343 SPS 6/30/2015 Regional Reliability 2015 ITPNT 4 $18,609,838 $0 200344 SEPC 6/30/2015 Regional Reliability 2015 ITPNT 2 $4,331,457 $0 200345 WR 6/30/2015 Regional Reliability 2015 ITPNT 1 $9,536,211 $0

Total 12 $48,665,321 $0 Table 3: Q2 2015 NTC Issuance Summary

Page 9: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 8

NTC Withdraw One NTC previously issued to MKEC was withdrawn since the last quarterly report. The NTC included Network Upgrades that were requested to be restudied by the DTO, and were determined to be no longer needed through the Aggregate Study process. Table 4 lists the NTC Withdraw activity from April 1, 2015 through June 30, 2015. NTC ID values in bold font indicate NTC-Cs.

NTC ID DTO NTC

Withdraw Date

Upgrade Type Original Source Study No. of Upgrades

Estimated Cost of Withdrawn

Upgrades 200341 MKEC 5/12/2015 Regional Reliability SPP-2011-AG3-AFS-11 2 $18,616,980

Total 2 $18,616,980 Table 4: Q2 2015 NTC Withdraw Summary

Completed Projects Twenty-two Network Upgrades with NTCs and two Generation Interconnection Network Upgrades were completed during the reporting period, totaling an estimated $138 million. Transource Missouri (TSMO) notified SPP that the new 30-mile 345 kV line from Iatan to Nashua in northwest Missouri was completed and placed into service on April 30, 2015. The project was identified and studied as part of the Balanced Portfolio report that was approved by the Board in April 2009. The project scope also included a new 345/161 kV transformer at Nashua. The original NTCs were issued to Kansas City Power & Light (KCPL) and Kansas City Power & Light Greater Missouri Operations Company (GMO) before the project in its entirety was novated to TSMO in October 2013. The projected is projected to cost $65.3 million. Table 5 lists the Network Upgrades completed during the reporting period. Table 6 summarizes the completed projects over the previous year. Figure 6 reflects the completed projects by upgrade type on a cost basis for the current year and the following year based on current projected in-service dates. Tables 7 and 8 summarize all Network Upgrades that include construction of transmission lines, both for the current year and the following year. Note: Previous quarter’s updated results are listed as the Transmission Owners may make adjustments to final costs and status of projects completed during the year.

Page 10: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 9

UID Network Upgrade Name Owner NTC Source

Study Cost Estimate 10401 ACME - FRANKLIN SW 138KV CKT 1 WFEC 2007 STEP $2,065,000 10402 ACME - WEST NORMAN 138KV CKT 1 WFEC 2007 STEP $1,601,000 10403 OU SW - WEST NORMAN 138KV CKT 1 WFEC 2007 STEP $1,577,000 10425 Moundridge 138/115 kV Transformer Ckt 2 WR 2013 ITPNT $13,540,579 10519 LINDSAY SW - WALLVILLE 69KV CKT 1 WFEC 2007 STEP $1,347,000 10522 GRANDFIELD - INDIAHOMA 138KV CKT 1 WFEC 2007 STEP $1,125,000 10523 CACHE - INDIAHOMA 138KV CKT 1 WFEC 2007 STEP $7,306,000 10524 GRANDFIELD 138/69KV TRANSFORMER CKT 1 WFEC 2007 STEP $5,000,000 10629 Chaves County 230/115 kV Transformer Ckt 2 SPS 2013 ITPNT $2,917,118 10935 Iatan - Nashua 345 kV Ckt 1 (KCPL) TSMO Balanced Portfolio $6,675,931 10945 NASHUA 345/161KV TRANSFORMER CKT 1 TSMO Balanced Portfolio $2,617,433 11023 EAST PLANT INTERCHANGE - HASTINGS SUB 115KV CKT 1 SPS 2009 STEP $5,374,736 11067 Bowers Interchange 115/69 kV Transformer Ckt 2 SPS DPA Studies $3,100,001 11353 Lynn County Interchange 115 kV SPS 2010 STEP $5,342,685 11355 Crosby County Interchange 115/69 kV Transformer Ckt 1 SPS 2013 ITPNT $2,378,798 11507 Lubbock South 230/115/13.2 kV Transformer Ckt 2 SPS 2013 ITPNT $4,063,897 50499 Iatan - Nashua 345 kV Ckt 1 (GMO) TSMO Balanced Portfolio $56,048,696 50523 Floyd 115 kV Capacitor SPS 2013 ITPNT $1,731,323 50574 915 Tap South - Sub 915 T2 69 kV Ckt 1 OPPD 2013 ITPNT $260,590 50598 White Horse 69 kV Capacitor WFEC DPA Studies $237,000 50599 Fairview 69 kV Capacitor WFEC DPA Studies $237,000 50600 Hazelton 69 kV Capacitor WFEC DPA Studies $237,000 51064 Tap on Wolf Creek - LaCygne 345kV Ckt 1 WR GI Studies $13,197,769 51065 Tap on Wolf Creek - LaCygne 345kV Ckt 1 GEN-2010-003 Addition WR GI Studies $478,861

Total $138,460,417 Table 5: Q2 2015 Completed Network Upgrades

Page 11: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 10

Upgrade Type Q2 2014 Q3 2014 Q4 2014 Q1 2015 Total

Regional Reliability 28 5 23 19 75

$148,998,816 $18,181,820 $182,810,361 $59,441,727 $409,432,724

Transmission Service

5 0 2 0 7

$23,399,683 $0 $335,319 $0 $23,735,002

Balanced Portfolio 4 1 0 3 8

$127,550,762 $192,875,814 $0 $65,342,060 $385,768,636

High Priority 8 2 16 0 26

$351,643,677 $2,248,743 $514,748,573 $0 $868,640,993

Economic 0 0 0 0 0

$0 $0 $0 $0 $0

Zonal Reliability 0 0 0 0 0

$0 $0 $0 $0 $0

Generation Interconnection

3 5 6 2 16

$4,159,087 $34,643,128 $18,243,711 $13,676,630 $70,722,556

Table 6: Completed Project Summary through 2nd Quarter 2015

Page 12: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 11

Voltage Class

Number of Upgrades

Miles of New

Miles of Rebuild/ Reconductor

Miles of Voltage

Conversion Estimated Cost

69 12 14.0 42.8 0.0 $51,955,268 115 7 63.7 47.9 0.0 $77,683,919 138 21 62.9 22.0 108.3 $125,880,130 161 3 0.0 14.0 0.0 $12,050,087 230 3 61.0 0.0 0.0 $48,834,393 345 19 1183.7 0.0 0.0 $1,134,954,911

Total 65 1385.3 126.8 108.3 $1,451,358,708 Table 7: Line Upgrade Summary for Previous 12 Months

Figure 6: Completed Projects by Upgrade Type

$0

$100

$200

$300

$400

$500

$600

$700

$800

Q3 2014 Q4 2014 Q1 2015 Q2 2015 Q3 2015Projected

Q4 2015Projected

Q1 2016Projected

Q2 2016Projected

Generation Interconnection

Zonal Reliability

Economic

High Priority

Balanced Portfolio

Transmission Service

Regional Reliability$ M

illio

n

Page 13: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 12

Voltage Class

Number of Upgrades

Miles of New

Miles of Rebuild/ Reconductor

Miles of Voltage

Conversion Estimated Cost

69 19 44.1 106.2 0.0 $139,676,743 115 13 138.1 17.0 4.5 $127,297,724 138 7 29.0 20.0 2.0 $39,387,811 161 0 0.0 0.0 0.0 $0 230 4 42.4 0.0 122.0 $63,103,827 345 2 128.0 0.0 0.0 $182,000,000

Total 45 381.59 143.17 128.5 $551,466,105 Table 8: Line Upgrade Projections for Next 12 Months

Page 14: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 13

Project Status Summary SPP assigns a project status to all Network Upgrades based on the projected in-service dates provided by the DTOs relative to the Need Date determined for the project. Project status definitions are provided below:

• Complete: Construction complete and in-service • On Schedule < 4: On Schedule within 4-year horizon • On Schedule > 4: On Schedule beyond 4-year horizon • Delayed: Projected In-Service Date beyond Need Date; interim mitigation provided or

project may change but time permits the implementation of project • Within NTC Commitment Window: NTC/NTC-C issued, still within the 90-day written

commitment to construct window and no commitment received • Within NTC-C Project Estimate Window: Within the NTC-C Project Estimate (CPE)

window • Within RFP Response Window: RFP issued for the project • Re-evaluation: NTC/NTC-C active; pending re-evaluation • NTC Suspension: NTC/NTC-C suspended; pending re-evaluation

Figure 7 reflects a summary of project status by upgrade type on a cost basis.

Figure 7: Project Status Summary on a Cost Basis

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

RegionalReliability

TransmissionService

BalancedPortfolio

High Priority Economic GenerationInterconnection

NTC Suspension

Re-evaluation

RFP Response Window

Within NTC-C Project Estimate Window

Within NTC Commitment Window

Delayed

On Schedule > 4

On Schedule < 4

Complete

$ M

illio

n

Page 15: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 14

Balanced Portfolio

Approved in April 2009, the Balanced Portfolio was an initiative to develop a group of economic transmission upgrades that benefit the entire SPP region, and to allocate those project costs regionally. The projects that were issued NTCs as a result of the study include a diverse group of projects, estimated to add approximately 702 miles of new 345 kV transmission line to the SPP system. The total cost estimate of $822.2 million for the projects making up the Balanced Portfolio did not change from the previous quarter’s cost estimate total. The last Balanced Portfolio project still under construction was placed into service on April 30, 2015, when TSMO energized the 30-mile 345 kV line from Iatan to Nashua in northwest Missouri. Figure 8 below depicts a historical view of the total estimated cost of the Balanced Portfolio. Table 9 provides a project summary of the projects making up the Balanced Portfolio.

$ M

illio

n

Figure 8: Balanced Portfolio Cost Estimate Trend

$691.2

$832.3

$903.0

$810.5 $822.2

$650.0

$700.0

$750.0

$800.0

$850.0

$900.0

$950.0

FERC Filing $896.7

Page 16: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 15

Project ID(s)

Project Owner(s) Project Name

Est. Line

Length

BP Report Estimates (6/2009)

Q1 2015 Cost Estimates

Q2 2015 Cost Estimates

Variance %

705/709 WFEC/OGE Gracemont Substation 345 kV N/A $8,000,000 $15,091,100 $15,091,100 0.0%

707/708 ITCGP/NPPD Spearville - Post Rock - Axtell 345 kV 226.9 $236,557,015 $203,776,145 $203,776,145 0.0%

698/699 OGE/GRDA Sooner - Cleveland 345 kV 36.0 $33,530,000 $49,718,139 $49,718,139 0.0%

702 KCPL Swissvale - Stilwell Tap 345 kV N/A $2,000,000 $2,866,604 $2,866,604 0.0%

700 OGE Seminole - Muskogee 345 kV 118.0 $129,000,000 $165,000,000 $165,000,000 0.0%

701/704 SPS/OGE Tuco – Woodward 345 kV 290.1 $227,727,500 $320,426,576 $320,426,576 0.0%

703 TSMO Iatan – Nashua 345 kV 30.9 $54,444,000 $65,342,060 $65,342,060 0.0%

Total 701.9 $691,258,515 $822,220,624 $822,220,624 0.0%

Table 9: Balanced Portfolio Summary

Page 17: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 16

Priority Projects

In April 2010 the SPP Board of Directors and Members Committee approved for construction a group of "priority" high voltage electric transmission projects estimated to bring benefits of at least $3.7 billion to the SPP region over 40 years. The projects issued NTCs as a result of the study are estimated to add 291 miles of new single circuit 345 kV transmission line and 431 miles of double circuit 345 kV transmission to the SPP region. In October 2010 the SPP Board of Directors approved an overall cost increase for the Priority Projects due to line rerouting and addition costs for reactive compensation. The total cost estimate for the Priority Projects after the variances were approved was $1.42 billion. The current total cost estimate of $1.39 billion for the projects making up the Priority Projects indicates a slight decrease of 0.1% from the previous quarter’s total amount. Figure 9 below depicts a historical view of the total estimated cost of the Priority Projects. Table 10 provides a project summary of the projects making up the Priority Projects.

Figure 9: Priority Projects Cost Estimate Trend

$1,144.9

$1,449.7

$1,388.2 $1,389.2

$1,100.0

$1,150.0

$1,200.0

$1,250.0

$1,300.0

$1,350.0

$1,400.0

$1,450.0

$1,500.0

$ M

illio

n

Additional Costs Approved by Board

$1,416.3

Page 18: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 17

Table 11 lists construction status updates for the Priority Projects not yet completed.

Project ID(s)

Project Owner(s) Project

Est. Line

Length

Board Approved Estimates (10/2010)

Q1 2015 Cost Estimates

Q2 2015 Cost Estimates

Var. %

937 AEP Tulsa Power Station 138 kV Reactor N/A $842,847 $960,895 $960,895 0.0%

940/941 SPS/OGE Hitchland – Woodward District 345 kV Dbl Ckt

122.0 $221,572,283 $229,203,065 $231,203,065 0.9%

942/943 PW/OGE Thistle – Woodward District 345 kV Dbl Ckt 109.4 $201,940,759 $187,260,000 $190,471,326 1.7%

945 ITCGP Spearville – Ironwood – Clark Co. – Thistle 345 kV Dbl Ckt

122.5 $293,235,000 $309,000,001 $309,000,001 0.0%

946 PW/WR Thistle – Wichita 345 kV Dbl Ckt 77.5 $163,488,000 $127,026,938 $120,440,612 -5.2%

936 AEP Valliant – NW Texarkana 345 kV 76.3 $131,451,250 $127,995,000 $127,995,000 0.0%

938/939 OPPD/TSMO Nebraska City – Mullin Creek – Sibley 345 kV 215.0 $403,740,000 $407,791,450 $407,791,450 0.0%

Total 722.7 $1,416,270,139 $1,389,237,349 $1,387,862,349 -0.1%

Table 10: Priority Projects Summary

Proj

ect I

D

Proj

ect N

ame

Proj

ecte

d In

-Ser

vice

D

ate

Engi

neer

ing

Siti

ng a

nd R

outi

ng

Envi

ronm

enta

l Stu

dies

Perm

its

Mat

eria

l Pro

cure

men

t

Cons

truc

tion

C Complete

936 Valliant – NW Texarkana 345 kV 10/1/2016 C C C IP IP IP

IP In Progress

938 Nebraska City – Mullin Creek – Sibley 345 kV (TSMO) 12/31/2016 IP IP IP IP IP NS

NS Not Started

939 Nebraska City – Mullin Creek – Sibley 345 kV (OPPD) 12/31/2016 IP C IP IP IP NS

N/A Not Applicable

Table 11: Priority Projects Construction Status

Page 19: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 18

Out-of-Bandwidth Projects

In adherence to the Business Practice 7060, SPP reports projects that have updated cost values that exceed their established baseline values based upon a ±20% bandwidth. Variances are determined by total project cost. One project with a cost estimate greater than $5 million was identified as having exceeded the ±20% bandwidth requirement during the reporting period. Table 12 provides summary information and Table 13 lists the cost detail for the out-of-bandwidth project for Q2 2015.

PID Project Name Owner NTC Source

Study Upgrade Type In-Service Date

30369 Moundridge 138/115 kV Transformer Ckt 2 Westar 2013 ITPNT Regional Reliability 4/7/2015

Table 12: Out-of-Bandwidth Project Summary

Table 13: Out-of-Bandwidth Project Cost Detail

PID Baseline Cost Estimate

Baseline Cost Estimate Year

Baseline Cost Estimate with

Escalation

Latest Estimate or Final Cost

Variance Variance %

30369 $19,770,066 2013 $20,770,926 $13,540,579 ($7,230,347) -34.8

Page 20: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 19

Responsiveness Report

Table 14 and Figures 10 and 11 provide insight into the responsiveness of DTOs constructing Network Upgrades within SPP in the Quarterly Project Tracking Report for Q2 2015. Note: Network Upgrades with statuses of “NTC Suspension”, “Re-evaluation”, “Within NTC Commitment Window”, “Within NTC-C Project Estimate Window”, and “Within RFP Response Window” were excluded from this analysis.

Project Owner

Number of Upgrades

Number of Upgrades Reviewed

Reviewed %

Number of ISD

Changes

ISD Change %

Number of Cost

Changes

Cost Change

%

AEP 57 57 100% 4 7.0% 7 12.3% BEPC 15 15 100% 0 0.0% 0 0.0% GMO 5 5 100% 0 0.0% 1 20.0%

GRDA 7 3 43% 0 0.0% 3 42.9% ITCGP 15 5 33% 1 6.7% 5 33.3% KCPL 5 5 100% 0 0.0% 3 60.0% LES 1 1 100% 0 0.0% 0 0.0%

MIDW 11 0 0% 0 0.0% 0 0.0% MKEC 16 14 88% 14 87.5% 7 43.8% NPPD 26 9 35% 0 0.0% 8 30.8% OGE 48 27 56% 1 2.1% 19 39.6%

OPPD 15 11 73% 4 26.7% 4 26.7% PW 4 4 100% 0 0.0% 4 100.0% SPS 142 54 38% 17 12.0% 29 20.4%

TSMO 5 5 100% 5 100.0% 0 0.0% WFEC 43 1 2% 1 2.3% 0 0.0%

WR 51 8 16% 2 3.9% 6 11.8% Total 470 226 48% 49 10.4% 98 20.9%

Table 14: Responsiveness Summary by Project Owner

Page 21: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 20

Figure 10: In-Service Date Changes by Project Owner

Figure 11: Cost Changes by Project Owner

0

20

40

60

80

100

120

140

160

In-Service Date Changes

0

20

40

60

80

100

120

140

160

Cost Changes

Page 22: Q3 2015 Quarterly Project Tracking Report

Southwest Power Pool, Inc.

Q3 2015 Project Tracking Report 21

Appendix I

See accompanying list of Network Upgrades