ramron

Embed Size (px)

Citation preview

  • 7/29/2019 ramron

    1/6

    1 INTRODUCTION

    National Road No. 7 starts in the city of BuenosAires and developes from east to west- crossing the

    provinces of Buenos Aires, Santa Fe, Crdoba, SanLuis and Mendoza.The section under study starts in the Santa Fe Prov-

    ince at Km 380.0 and continues around the floodingarea of the Laguna La Picasa, ending at km 390.5.This lake is located in the southwest of the provinceof Santa Fe and North of the Province of BuenosAires and has basin of approximately 500,000 hec-tares contribution, including SE of Cordoba, NW ofBuenos Aires and SW of Santa Fe areas, on a stretchof 100 km long and 50 meters wide along NationalRoute No. 7.

    Figure 1. Level at the time of the work of the lagoon: IGN

    104.00 (approximate).

    The work, contracted by the Direccin Nacional de

    Vialidad of Argentine, was officially started

    01/02/2006 and ended on 15/06/2007. It gave conti-

    nuity to the NR No. 7 interrupted from 1999 due to

    the overflowing of the water. The track crosses the

    La Picasa lagoon by the South West end. The gen-

    eral morphology of the area has a typical landscape

    of gently undulating plains, with alternation of very

    flat hills and depressed sectors, where ponds and

    temporary lows locate, incorporating a surface stor-

    age capacity. Surface slopes are low, less than the

    0004 m / m. The aim of the project was to rehabili-

    tate the road through an embankment along the ex-

    isting track and avoid disruption in the future.

    Figure 2. View of the trace of the roadway when starting the

    work

    To achieve this, the following hydraulic and project

    parameters have been considered:

    Cement- treated soil: Experience in the work Rehabilitation of NationalRoute No 7 Section: crossing La Picasa Lagoon through existing road

    F. Gerbaudo & J.E. Ramoneda & J. ViozziDireccin Nacional de Vialidad, 7 Distrito- Divisin Obras. Santa Fe, Argentina

    ABSTRACT: The paper presents the experience of using cement treated soil to construct an embankment in

    the Rehabilitation of National Route 7 Section: crossing La Picasa Lagoon through existing road work,

    located between Km 380.0 and Km 390.5 in the Santa Fe Province, Argentine. The overflowing of La Picasa

    Lagoon in 1999 interrupted the existing road. This work rehabilitated the flood section. The project itself in-

    cluded the construction of an embankment protected by stones on the existing road. The chemical aggressive-

    ness of water, caused by high content of salts, especially sulfates, required the embankment to be neutralized

    both physically and chemically. Consequently, a treatment with low quantities of ARS Portland cement was

    proposed. While in Argentina this technique is widely used in soil stabilization, seeking to improve both phys-

    ical characteristics and bearing capacity, it has never been used to modify only the physical conditions.

  • 7/29/2019 ramron

    2/6

    Level at the time of the work of the lagoon: IGN

    104.00 (approximate). Maximum level of the lagoon at the conclusion ofthe drainage works currently in progress: 102.50IGN. Federal Plan of Flood Control administered bythe Secretary of Water Resources of the Nation. Minimal height of grade project: 104.80 IGN.The typical profile of basic work also takes into ac-

    count the following requirements, according to thelevel of service to be provided along the way: Guideline Speed: 110 km / h Roadway width: 7.44 m Crown width: 15.30 m Shoulder width: 3.00 mIt was also built a bridge located in the progressive 6+759.13, with a length of 60 m in three tranches of20m light each, a level beam background of104.50m and a roadway width of 8.30m. The basicwork of raising the embankment has its axis coinci-dent with the axis of the existing pavement. It con-sists of a shoulder and core of rockfill. The last oneis formed by a causeway to advance beyond the levelof water hair with a rematch of 0.20 m. From thisbase causeway lies layers of cement treated soil andafter that the main pavement structure is found. It isthe result of the application of 1993 AASHTO De-sign Method for annual average daily traffic designof 1960 vehicles per day in 2007. The structure wasdesigned as a semirigid pavement, trying to makerigid support layers decreasing in depth. The finalstructure was formed as follows:

    Subgrade soil treated with cement sub base of20cm thick. See Figure 2 reference 6. Sub base granular treated with cement of 20cmthick. See Figure 2 reference 5. Base granular treated with cement of 15cm thick.See Figure 2 reference 4. Asphalt concrete layer of 7cm thick. See Figure 2reference 1.A geotextile membrane resistance to puncture andtear was placed between the causeway and the layersof soil cement.

    Figure 3. Cross Section

    This paper will focus on the core layer of soil fill,the subgrade and shoulders coating, all executed insoil treated with cement.

    2 TECHNICAL SOLUTION

    The system of elements and materials that make up

    the existing basic work respond to the demands re-quired by the environment.The pier contains the nucleus and acts as protection,containment and filter side together with geotextilemembrane. The embankment forms a floor that isnot affected in its stability by the presence of waterand eliminates the phenomenon of capillary rise forthe high void ratio.The change in the physical properties aims to pro-vide the fill water insensitivity to the phenomena ofvolume changes (swelling, shrinkage and consolida-tion) and embedding capillary absorption. This em-bedding is a latent possibility in the work because ofits proximity to high laggon level and exposure torain.Moreover, the slight stiffening of cement brings anumber of advantages, among others, constructiontechnology and also influences the attenuation of thephysical phenomenon of consolidation.This series of technological advantages are: Reduces lead times and costs for using the equip-ment. A similar structural capacity as the bank exe-cuted without cement requires significant mechani-

    cal densification, which implies a considerableruntime and greater use of compaction equipment (aswill be seen in the development of constructionmethodology and equipment used for distributionand preparation of material to be compacted is simi-lar to that required for untreated soil with cement). At the same time constitutes a less deformableseat base for the pavement structure to improve itsperformance and durability. It also helps to mitigate potential differential set-tlement between the sectors of basic work that are

    above the existing pavement structure and outside it,that is, on shoulders verges and existing embank-ment slope.As a disadvantage, the soil layers agglomerated withcement have a significant potential for dryingshrinkage cracking, a problem that can be solved byattending carefully curing task.Nevertheless the useof low cement tenors in this case, presented no suchproblems.In order to use cement as a treatment of soil we hadto pay special attention to water of the lagoon. Thechemical analysis verified the presence of important

    contents of sulfate, 2.4g / l, a substance that is com-bined with tricalcium aluminate hydrates (AC3) ex-pansive cement to form compounds that cause crack-ing. We therefore had to use Portland Cement ARS,highly resistant to sulfates. It is provided to give an

    C.Rasante Min.

    C.RasanteMin. Exist.

    ANCHO TOTAL DE CORONAMIENTO 14.65 m

    Pavimento

    Existente

    4.0%2.0%4.0%2.0%

    4321 85 79

    12

    11

    10 6

    2.60 2.60ANCHO DE CALZADA=7.44m

    EJE

    RAS

  • 7/29/2019 ramron

    3/6

    order of magnitude that according to PETG Ref. [1]the maximum sulfate content for mixing water forsoil cement is 1g / l.

    3 SPECIFICATIONS

    In this paper we mention some concepts of the speci-

    fications related to soils treated with cement, whichcome from the Special Technical Specifications(PETG) of the work. Ref [1].Related to the materials, the most important re-quirement is Cement, which must be of type ARSaccording to the IRAM Norms 1669-1:1984 PortlandCement highly sulphate-resistant, with no additionsand/or IRAM Norms 1669-2:1987 Portland Cementhighly sulphate-resistant, with additions. There wereno parameters to control soil established exceptthose related to the presence of organic matter, leav-ing the feasibility of using soil from different sites

    subject to the study of economic and technical feasi-bility for mixture proportions.As for the soil-cement mixture did not set any pa-rameter that has to do with the physical properties ofthe material, grain size distribution and Atterberglimits, common practice for the specification oflime-treated mixtures. Such properties allow to di-rectly assess the effectiveness of treatment. The lackof quantifiers of these properties in the specificationsof soil treated with cement applied to this project re-sponds to the tests required to obtain the mixture

    should offer the possibility to break into particles.Because of the cement, once the mixture was com-pacted or left aside for some time uncompacted, thislast process is not easy to do. One could try to makesome kind of characterization when uncompactedmixture is young, hours or days after homogeniza-tion, but in this period the reactions and chemicalchanges are substantial minute by minute and thusthe time variable would introduce a large scatter inresults. It should be further study in this regard.It was established as an indirect control parameterfor evaluating the effectiveness of treatment in an

    indirect way the compressive strength according toStandard Test VN - E33 - 67 Ref [2], except youhave to do with curing and molding of the speci-mens. The test was due to perform after a curingprocess of 48 hours at 50 degrees Celsius or 21 daysat room temperature. The molding process took be-tween two and two and a half hours after the mixingwas made.According to the current standard specifications asoil stabilized with cement has a curing period of 7days at 20 degrees Celsius; which serves to mitigate

    the structural requirement for the mixture treated, incomparison to the stabilized one, maintaining thevalues of compressive strength environments com-monly demanded. This measure substantially reduc-es the amount of cement into the soil.

    Whenever the construction methodology adopted forthe execution is the indicated in this paper, the delaybetween mixing and compaction of the specimens iscommon practice in laboratories in order to adjustsample conditions to the real compaction in thework.It was also introduced the alternative to cure thespecimens at a higher temperature than standard 50

    degrees Celsius during 48 hours to control the mix-ture in order to verify the correct execution of layersin a reasonable time according to work deadlines.The temperature acts as a catalyst accelerating thehydration of cement in a direct analogy with thesteam-cured concrete, a technology that is used whentrying to obtain mechanical strength at early ages.The compression strength both for the bank, the sub-base coating and the coating should be betweenshoulders 18 and 25 kg/cm2.Another condition of approval of the layers is com-paction which has been one of the most discussed. In

    accordance with the Particular Specification of theWork the finished layer must be inspected compar-ing the result of compaction control test by the sandmethod according to standard VN - E8 - 66 Ref [2]with the obtained using the technique of compactiontest of soil-cement mixtures and soil-lime VN - E19- 66 Ref [2]. The last one was performed on a mixedspecimen obtained in the road prior to compaction,but using the compaction energy corresponding toeach layer as set out in the PETG Ref. [1]. Thiscombination of standards specifications for the com-

    paction test required taking an approach during thework.According to the test VN- E19 66, specific com-paction energy of 6.05 kg cm/cm3 should be appliedto the specimen, which coincides with the lowest testspecified in VN E5 - 93, Type I Ref [2]. That ener-gy depends on soil classification to be used in theformation of the embankment or coatings, in accord-ance with the PETG. The identification of soil test-ing is done according to the grain size distributionVN - E1 - 65, Liquid limit VN - E2 - 65, Plastic lim-it, Plasticity index VN - E3 - 65, Soil classification

    VN- E4 - 84 Ref. [2]. As stated above, these physicalcharacterizations are not applied to soil with cement.Beyond that if we take as a starting point that A4type soils treated with cement to improve them areused, we can speculate about obtaining a higher orequal quality, A4, A3, A2 or A1. For these types ofsoil compaction test correspond the VN E5 - 93Type II or V, both specific energy of 27.3 kgcm/cm3 compaction, the maxims contained therein.Given this uncertainty and following the technicaland economic criteria to reduce the compaction en-

    ergy applied, that supported the use of cement treat-ed soil, energy compaction test adopted was VN E5 - 93 of 6.05 kg cm/cm3 .In order to improve the slenderness of the specimenfor the simple compression test, the using of speci-

  • 7/29/2019 ramron

    4/6

    mens of greater height and larger diameter was pro-posed in the particular specifications of the work. Toachieve this, larger molds to setting the standard andalternative methods of compaction of the specimenswere indicated to keep the specific energy of com-paction. On one hand the increased number of layersand another ram using a drop of greater height andweight.

    TEST MOLD

    Noflayers

    RamWeight(kg)

    LayerHeight

    (cm)

    Nofhits

    Compaction

    Energy

    (kgcm/cm

    3)

    VN-E5-93

    AASTHO

    (cm)

    H

    (cm)

    I T 99 10.2 11.7 3 2.5 3.89 25 6.05

    V T 180 15.2 11.7 5 4.5 2.33 56 27.25

    Alternative proposal

    I T 99 15.2 17.8 5 2.5 3.56 52 6.11

    V T 180 15.2 17.8 5 4.5 3.56 86 27.45

    Table 1. Alternative proposal modified compaction test.

    Both proposed techniques were tested and discardedbecause we found no consistent results regarding thedensity achieved compared with specimens testedaccording to National Highway standards. In general,the density at optimum moisture content was higherin the range 3% - 7%. Without further analysis, tointroduce variations of this type should take into ac-

    count not only energy but also compaction specificbulbs caused by ram pressure and the thickness ofthe layers, but this was not the case.For coatings and the 0.30m at the top of the em-bankment was required to reach 100% of the densityobtained in this test, and for the 0.30m below theembankment above 95%.As regards the implementation, it was establishedthat the mixing of the materials should not exceed2.5 hours from the time the water either for irrigationor contained in the soil, contact with cement. In turn,the distribution and compaction process should not

    exceed a period of 6 hours.For soil stabilization with cement is generally re-quired that the latter term is less than 3 hours. Thereason of this is both to maximize the binding powerof the first products generated by cement hydrationand to avoid the negative consequences of fragmen-tation phenomenon beginning in the compactionprocess.In the present work this matter was not neglected butwas given a minor importance allowing longerterms, as not intended to substantially increase the

    bearing capacity of the layer.

    4 DOSAGE

    For the different layers the dosage used were thesame as those obtained as a result of a series of de-posits of soil and laboratory tests.Field studies showed that two sites had adequate andsimilar technical characteristics, operating powerand convenient transport distance to the section.

    Both showed a mantle composed of soil exploitableA4, composed mainly of silt, moderate or smallamount of coarse material and only small amount ofclay. The prevalence of silt makes it require lessamount of cement due to the smaller surface areacompared to the clays, and the presence of the latter,although to a lesser extent, gives you extra cementlong term because of their long-term reactions to hy-droxides binder.Once the type of soil to use was set, we began withthe laboratory research stage to determine theamount of cement that meets the requirements of the

    Technical Specifications of the Contract.To this end, the compaction test was performed withdifferent contents of cement, 2.5%, 3%, 3.5% and4%. Based on this, series of 6 specimen each weremolded, with such content of cement and compac-tion optimum moisture. From each set of samples, 3samples were cured for 21 days at 20 degrees Celsi-us and the remaining 3 for 48 hours at 50 degreesCelsius.The results obtained using both types of curingshowed little dispersion, although in all cases

    showed that the average compressive strength result-ing from accelerated curing was lower for all the dif-ferent cement contents.It was also found that the compressive strength re-quired, among 18 to 25 kg/cm2, is achieved withless than 3% cement, which is why the expected costin the item has not been changed.As an extra information, we also performed test onsoil-cement mixtures of durability by wetting (VN -E21 66) and durability by freezing and thawing(VN - E22 66).As expected, results were above the specified limits

    of 10% loss for soils A-4 treated with cement set bythe General Specifications Technical Specifications(1998) of Vialidad Nacional (VN).The levels needed to achieve favorable results in thistest, according to the experience of VN and the lit-erature, are in a range from 7% to 12%. The percent-age of cement used is significantly below that range.

    5 CONSTRUCTION METHODOLOGY

    Although the methodology employed is very tradi-tional, today is being replaced by mixing plants thatensure quality and reduced lead times.Nevertheless, the technology adopted for this workwas adapted properly to the generous period of 6

  • 7/29/2019 ramron

    5/6

  • 7/29/2019 ramron

    6/6

    difficult to repeat every day. This directly affects thequality of the mix and it is reflected in the results.After the work was finished, which happened onJune 2007, auscultation was performed at open skyor pit in shoulder during the month of December ofthat year in order to verify the presence of water inthe core landfill due to the phenomenon of capillaryrise. By that time the lake level remained similar to

    that which led to the interruption of National RoadNo. 7. Moisture percentages were found rangingfrom 23.5% to a depth of 0.60m at 26% to 1.3m. Inaddition to these values indicating that no saturationof pores occurred, there were no visual symptomsthat demonstrated embedding.We also performed a new visit to the site in January2010 to make an expeditious visual assessment inwhich we have not detected longitudinal corruga-tions, rutting significant -less than 3mm-, pavementcracks or defects in the shoulders, that suggested abad response of the layers studied in this work.

    7 CONCLUSION

    The experience developed with cement treated soil issuccessful and valuable. On the one hand by the re-sults obtained, which had their difficulties during thework but were within the expected and reasonable,supported it by the current performance of the work.On the other hand it represented a complete successfrom the technological innovation point of view.

    While we should not ignore that this is a techniquewhich derives from other soil stabilization with ce-ment, which has significant experience and devel-opment not only scientifically but also technological-ly, it has served as direct input for sustaining thework performed.The future also will have a bench-scale testing thathas already borne fruit and will continue throughoutlife. This is of particular importance in overall de-velopment of new research.

    Figure 6. View of the completed road. Vialidad Nacional of

    Argentine. National Route No 7.

    8 REFERENCES

    [1] Direccin Nacional de Vialidad, 1998. Pliegode Especificaciones Tcnicas Generales. Publicacin101/102.[2] Direccin Nacional de Vialidad. Normas de En-sayo.