Reducing Maintenance with Water Lubricated Turbine Guide Bearings
Design Principles & Case Studies
Greg Auger, P. EngDr.-Ing Guojun Ren, P. Eng
Thordon Bearings Inc.• Designer and manufacturer of water lubricated turbine
guide bearings, self lubricated bearings, and shaft seals • State-of-the-art polymer production & machining facilities
in Canada, with global presence in over 100 countries• In-house research, design, and testing of water
lubricated hydrodynamic fluid film bearings (thrust and radial designs)
Visit us at Booth #137
A Brief History of Water Lubrication• 1840’s - Wood bearings with water lubrication originally
used for ship propeller shafts • 1900’s – Many early vertical & horizontal turbines built in
used wood block or “stave” style guide bearings• 1920’s - The use of natural rubber in water lubricated
bearings becomes more common • 1930’s – Rubber bearings widely used in Russian turbines • Advancements in materials have significantly extended
life and durability of modern water lubricated bearings • Growing interest in the use of water lubrication for turbine
guide bearings for the many benefits, including compliance with increasing environmental regulation
3
Implementing a Water Lubricated Bearing – Design Considerations
1. Load capacity, stiffness & damping characteristics2. Bearing running clearance3. Water quality (abrasive content, filtration level)4. Bearing material selection5. Bearing load and Length/Diameter (L/D) ratio6. Water flow & pressure, heat removal7. Vacuum below bearing, restrictor rings8. Bearing construction & fitting methods9. Shaft sealing considerations
4
Case Study #1 – Francis TurbineCentral Hidroelectrica de Prada
• End User: Spain• Manufacturer: Neyrpic, 1958• Type: Vertical, Francis• Head: 300m (984 ft)• Speed: 600rpm • Maximum output: 36 MW • Shaft diameter: 500mm (19.7”)• Oil bearing replaced with water
lubricated bearing in 20155
Case Study #1 – Francis Turbine
6
Design Review- 2 design configurations considered for water flow - Measurements taken of pressure below existing shaft seal- Oil bearing to be removed entirely
Case Study #1 – Francis Turbine
7
Implemented Solution- New shaft seal installed on top of
bearing (easier access)- New water supply system provides
lubrication & cooling - Zero risk of oil/water contamination
Shaft protected against corrosion with stainless steel weld overlay
- Thordon SXL elastomer bearing in new split stainless steel housing
Case Study #1 – Francis Turbine
8
Case Study #2 – KaplanCentrale di Fabbriche
• End User: Italy• Manufacturer: RIVA, 1955• Type: Vertical, Kaplan• Head: 30m (98 ft)• Speed: 430rpm • Maximum output: 15 MW • Shaft diameter: 400mm (15.7”)• Oil bearing replaced with water
lubricated bearing in 20169
10
Design Review- On-going problems with seal
leakage- Small space means seal is
difficult to access for repairs- Seal water leakage can over-top
oil basin, contaminates oil- Contaminated oil can lead to
wiped bearing- Oil bearing will be removed
completely
Case Study #2 – Kaplan Turbine
11
Case Study #2 – Kaplan Turbine
Implemented Solution- New shaft seal installed on top of
bearing (easier access)- Seal leakage is reduced- Zero risk of oil/water contamination- Shaft protected against corrosion with
split bolted stainless steel sleeve and HVOF coating
- Thordon SXL bearing easily replaced or inspected using tapered keyset
12
Case Study #2 – Kaplan Turbine
Case Study #2 – Kapan Turbine
13
How to Approach a Bearing Conversion1. Feasibility Review Identify refurbishments planned in next 1 – 5 years? Any problems with turbine guide bearing and/or shaft seals? Is there any regulatory concern with use of existing oil bearings?
2. Collect Data & Rough Scoping Gather drawings, unit technical data, sealed water pressure, etc. Work with partner(s) to determine rough concept design
3. Prepare Specifications, Gather Quotes, Initiate Work Seek bids from interested suppliers, finalize contract details,
award contract4. Implement Solution Remove old components, install new components, verify
clearances, test water system, commission & re-start unit
14
Greg Auger, P. Eng. - Hydro Business Unit [email protected]
+1 (705) 955-0235 mobile
Thanks to supporting workshops for photos & background!
www.pedrotec.com www.echelanthor.com
www.jobsonitalia.com www.milsatrillo.com
Thank You!