Regulatory Requirements on PV (General)

Embed Size (px)

Citation preview

  • 8/11/2019 Regulatory Requirements on PV (General)

    1/52

  • 8/11/2019 Regulatory Requirements on PV (General)

    2/52

    OUTLINE

    History

    Law and Regulations

    Principle

    The 3 approaches

    Option 1, 2 or 3? PIC/S

    Typical Content of Process Validation

    Re-validation

    Common Mistake P3.4 Process Validation

    Guidelines & References

  • 8/11/2019 Regulatory Requirements on PV (General)

    3/52

    WHY PV?:- HISTORY

    1963 :FD&C were approved; Process Validation has been a legal requirement.

  • 8/11/2019 Regulatory Requirements on PV (General)

    4/52

    WHY PV? :- SAMPLING

    Pharmaceutical Process Validation 3rdEd. Robert A Nash

  • 8/11/2019 Regulatory Requirements on PV (General)

    5/52

    LAW AND REGULATIONS

    Poison Act 1952

    Sales of Drug Act 1952

    Control of Drugs andCosmetics Regulations

    1984

  • 8/11/2019 Regulatory Requirements on PV (General)

    6/52

    WHAT THE GUIDELINES SAY ON PV?

  • 8/11/2019 Regulatory Requirements on PV (General)

    7/52

    PRINCIPLE

    a. PIC/S

    PI 006-3 (25 September 2007)

    6.1 Principle

    PV is the means of ensuring, and providing

    documentary evidence that processes (within

    their specified design parameters) are capableof repeatedly and reliably producing a finished

    product of the required quality.

  • 8/11/2019 Regulatory Requirements on PV (General)

    8/52

    PRINCIPLE

    b. ASEAN Guidelines on Process validation

    PV is a means of ensuring that manufacturing

    processes are capable of consistently

    producing a finished product of the required

    quality.

    It involves providing documentary evidence

    that the key steps in the manufacturing process

    are consistent and reproducible.

  • 8/11/2019 Regulatory Requirements on PV (General)

    9/52

    PRINCIPLE

    c. EMEA

    Note for Guidance on Process Validation. (1stMarch2001)

    Validation is the act of demonstrating anddocumenting that a procedure operates effectively.

    PV is the means of ensuring the providingdocumentary evidence that the processes (withintheir specified parameters) are capable ofconsistently producing a finished product of the

    required quality.

  • 8/11/2019 Regulatory Requirements on PV (General)

    10/52

    PRINCIPLE

    d. CDER: Guideline on General Principles of

    Process Validation (May 1987)

    PV is establishing documented evidence which

    provides a high degree of assurance that a

    specific process will consistently produce a

    product meeting its pre-determinedspecifications and quality characteristics.

  • 8/11/2019 Regulatory Requirements on PV (General)

    11/52

    ALL GUIDELINES AGREED THAT PV MEANS

    Process which are Reliable, Repeatable, &under control

    Repeatable (Normally 3 consecutivebatches)

    Must investigate failures

    The rationale should be documented ifexperimental method is changed

    document deviations, decisions and reasoning

    Does not improve processes

    Should not validate bad processes

    11

  • 8/11/2019 Regulatory Requirements on PV (General)

    12/52

    Prospective Validation

    Concurrent Validation

    Retrospective Validation

  • 8/11/2019 Regulatory Requirements on PV (General)

    13/52

    PROSPECTIVE VALIDATION

    PIC/S: PI 006-3. Clauses

    6.3.3: Document elements:

    a. A description of the process

    b. A description of the experiment.

    c. Details of the equipment/facilities to be used (including measuring/recording equipment)

    together with its calibration status.d. The variables to be monitored.

    e. The samples to be takenwhere when, how and how many.

    f. The product performance characteristic/attributes to be monitored, together with the testmethod.

    g. The acceptable limits.

    h. Time Schedules

    i. Personnel responsibilities.

    j. Details of methods for recording and evaluating results, including statistical analysis.

    6.3.4: - All equipment, the production environment and analytical test methods to be usedhave been fully validated (IQ/OQ).

    - Staff have been properly trained.

  • 8/11/2019 Regulatory Requirements on PV (General)

    14/52

    PROSPECTIVE VALIDATION. (CONTINUED)

    6.3.6: - Sufficient number of runs and observation.

    - Generally accept 3 consecutive batches.

    6.3.7: - Batches made should be the same size as full scale production.

    6.3.8: - Extensive testing should be performed on the product at various stages.- Detailed testing should be done on the final product and its package.

    6.3.9: - DOCUMENT it and include it in Validation report!

    a. A description of the process.

    b. Detailed Summary of results (in-process, final testing, including failed test). Rawdata or reference of sources.

    c. Additional work or deviation should be noted and explained.

    d. A review and comparison with those expected.

    e. Formal acceptance/rejection of the work by the team/persons.

  • 8/11/2019 Regulatory Requirements on PV (General)

    15/52

    CONCURRENT VALIDATION

    Clause 6.4.4 Documentation requirements are the same as

    specified for Prospective Validation

    and the testing to be carried out in-process and onthe finished product will be as specified in approvedprotocols.

    The completed protocols and reports should bereviewed and approved before product is release forsale or supply.

  • 8/11/2019 Regulatory Requirements on PV (General)

    16/52

    CONCURRENT VALIDATION

    Acceptable in the case of orphan drugs,

    when the number of production batches per

    year is expected to be low.

    Should seek prior consent from DRA.

  • 8/11/2019 Regulatory Requirements on PV (General)

    17/52

    RETROSPECTIVE VALIDATION

    Can be performed for existing non-sterileproductswhich already in the market for some time.

    Involves trend analysis of Historical manufacturingand QC data.

    Must meet following condition.

    i. No change in formulation.

    ii. No change in manufacturing process or analytical

    method.iii. No change in equipment or site(s) of manufacturing

    iv. CpK >1.33 based on 1020 batches

  • 8/11/2019 Regulatory Requirements on PV (General)

    18/52

  • 8/11/2019 Regulatory Requirements on PV (General)

    19/52

    PROCESS VALIDATION CHALLENGES THE

    Facility

    Environment

    Services & Utilities Equipment and machines

    Personnel

    Standard Procedures and Operatingconditions (the process)

    19

  • 8/11/2019 Regulatory Requirements on PV (General)

    20/52

    TYPICAL CONTENT OF PVROBERT A NASH; PHARMACEUTICAL PROCESS VALIDATION 3RDED.

    Safety Instruction

    Environmental Restriction

    Equipment

    Raw Materials

    Process Flow Charts

    Critical Process Parameters & Related means of controls Responsibilities of each participating group

    Cleaning validation & verification requirements

    Master batch component; percentage by weight

    Production batch component

    Process batch record

    Product testing

    Formulation

    Validation sampling & testing

    Definition of validation criteria.

    20

  • 8/11/2019 Regulatory Requirements on PV (General)

    21/52

    ASEAN GUIDELINE:

    CONTENT OF VALIDATION (SCHEME)

    a) A short Description of the manufacturing process in a schematic

    drawing or flow chart.

    b) A summary of critical process, control variables and justification for

    their selection.

    c) Finished Product specification

    d) Details analytical methods (reference to the dossier)

    e) In process control proposed and with acceptance criteria.

    f) Additional testing intended to be carried out (eg with proposed

    acceptance criteria and analytical validation appropriate).

    g) Sampling Planwhere, when and how samples are taken.

    h) Details of method for recording and evaluation of results.

    i) Proposed time frames for carrying out the studies.

    21

    22

  • 8/11/2019 Regulatory Requirements on PV (General)

    22/52

    ASEAN GUIDELINE:

    CONTENT OF VALIDATION (REPORT)

    a) Summary

    b) Introduction

    c) Batches used for Validation

    d) Manufacturing Equipment

    e) Critical Process Steps and parameters

    f) Acceptance criteria.

    g) Sampling Plan

    h) Tabulation of test results.

    i) Batch Analysis

    j) Evaluation of Data, and where applicable. Including statisticalprocess control analysis.

    k) Evaluation of data including comparison against acceptance criteria.

    l) Discussion on deviations and out of specification results.

    m) Conclusion and recommendation.

    22

  • 8/11/2019 Regulatory Requirements on PV (General)

    23/52

    PROCESS VALIDATION SCHEME

    Information RemarkShort description of the Process. -summary of the critical processing steps

    -critical parameters to be monitored during

    validation.

    Finished product specification - release

    Details of analytical methods. - References to the dossier

    In Process Controls proposed with acceptance

    criteria.

    Additional testing intended to be carried out. -Proposed acceptance criteria

    -Analytical validation

    Sampling Plan -Where, when and how the samples are taken.

    Details of method for recording and evaluation

    of results.

    Proposed timeframe

  • 8/11/2019 Regulatory Requirements on PV (General)

    24/52

  • 8/11/2019 Regulatory Requirements on PV (General)

    25/52

    OPTION (ASEAN GUIDELINES)

    Option Documentation

    Option 1 i. Validation report for 3 consecutive batches

    Option 2 i. Pharmaceutical Development report.

    ii. Validation report on 1 pilot batch OR

    Validation scheme.iii. Commitment to conduct Validation study.

    Option 3 i. Validation document from reference country.

    ii. Commitment to conduct validation study.

    Pilot Batch:

    10% of commercial batch, OR 100,000s OR whichever is higher.

    Retrospective:Previous data of 1020 consecutive batches.

  • 8/11/2019 Regulatory Requirements on PV (General)

    26/52

    27

  • 8/11/2019 Regulatory Requirements on PV (General)

    27/52

    PRE-REQUISITES FOR PROCESS VALIDATION

    Facility and controlled environment(s) -

    qualified.

    Critical services and Utilities - qualified.

    Equipment -calibrated and qualified. GMP-related computer system - qualified.

    Test method - validated.

    Personnel - trained.

    Master batch documentation -approved for

    use.

    Critical process parameters - known and

    documented.

    27

    28

  • 8/11/2019 Regulatory Requirements on PV (General)

    28/52

    VALIDATION

    Exercise 1 You are given a tablet

    manufacturing flow chart

    to study,.

    I. List the critical steps that arerequired to be validated

    II. List the critical equipment

    required to be qualified

    III. Identify the variables and

    construct a table as directedIV. Discuss Worst Case scenario

    for this process.

    28

    29

  • 8/11/2019 Regulatory Requirements on PV (General)

    29/52

    I) CRITICAL STEP

    29

    30

  • 8/11/2019 Regulatory Requirements on PV (General)

    30/52

    B) CRITICAL EQUIPMENT

    No Equipment Model Type Qualification

    Status

    1 Granulator MG300 300L DQ-IQ-OQ-PQ

    2 Fluidized Bed Dryer FBD01 - DQ-IQ-OQ-PQ

    3 Cube Blender CB250 250L DQ-IQ-OQ-PQ

    4 Compression CMB4 Rotary 25

    station

    DQ-IQ-OQ

    5 Coater Thai

    Coater

    60 DQ-IQ-OQ-PQ

    30

    31

  • 8/11/2019 Regulatory Requirements on PV (General)

    31/52

    PROCESS VARIABLEINPUT: Critical process

    Parameters

    Process OUTPUTS: Critical

    Quality Attributes

    (Variables)

    i. Speed,

    ii. Fluid amount,

    iii. Time,

    iv. Sieve Diameter,

    Blend & Wt Granulation LODGranules Uniformity

    i. Air temp,

    ii. Product Temp,

    iii. Time

    Fluid Bed Dryer Particle sizeLOD

    i. Blender dimension,

    ii. Speed, load, time,Blending Blend uniformity

    Flow properties

    i. Comp. Speed,

    ii. Force,

    iii. Feed rate

    Compression Weight controlDisintegration/Hardness,

    Assay

    Etc,i. Inlet temp,

    ii. Bed Temp,

    iii. Exhaust Temp.

    iv. Coating Pan RPM,

    v. Nozzles No.

    vi. Spraying rate.

    vii. Spray rate,

    Coating Appearance,Dimension,

    Dissolution rate

    Weight,

    Hardness

    Assay,

    Etc.

    31

    32

  • 8/11/2019 Regulatory Requirements on PV (General)

    32/52

    C) WORST CASE SCENARIOProcess INPUT: Critical process

    Parameters

    Min Max

    Blend & Wt

    Granulation

    i. Speed,

    ii. Fluid amount,iii. Time,

    iv. Sieve Diameter,

    200rpm

    5L 20minute

    300rpm

    6L 30 minute

    Fluid Bed

    Dryer

    i. Air temp,

    ii. Product Temp,

    iii. Time

    55-75oC

    2hrs

    55-75oC

    4 hrs

    Blendingi. Blender dimension,

    ii. Speed, load,

    iii. time,

    iv. Holding time

    5 minute 10 minute

    Compression i. Comp. Speed,ii. Force,

    iii. Feed rate

    iv. Holding time

    300rpm

    12 tonnes

    400rpm

    40 tonnes

    Coating i. Inlet temp,ii. Bed Temp,

    iii. Exhaust Temp.

    iv. Coating Pan RPM,

    v. Nozzles No.

    vi. Spraying rate.

    vii. Spray rate,

    viii. Holding time

    55 deg C

    40 rpm

    1 Liter per hr.

    70 deg C

    50 rpm

    2 liter per hr

    32

  • 8/11/2019 Regulatory Requirements on PV (General)

    33/52

  • 8/11/2019 Regulatory Requirements on PV (General)

    34/52

    CHANGE CONTROL RE-VALIDATION

    A repeat of the process validation to provide an

    assurance that changes in process/equipment

    introduced in accordance with change control

    procedures do not adversely affect process

    characteristics and product quality.

    PIC/S Code of GMP Annex 15 Glossary

    34

  • 8/11/2019 Regulatory Requirements on PV (General)

    35/52

    RE-VALIDATION DUE TO CHANGES

    a) Manufacturing Process Change to Master Processing Instructions (Methods)

    b) Formulation Change of Bill of Materials, formulation or batches proportions

    Change in raw material suppliers or components

    c) Equipment Significant alteration to processing equipment

    Introduction of new equipment or utilities

    e) Environment Significant change in processing conditions or environment

    After extensive preventive or running maintenance work.

    f)

    Methods & Specifications Major changes in quality control methods or specifications If in-process or quality control results are outside pre-set limits.

    If in-process or quality control data indicates a significant process shift or change in processcapability.

    35

  • 8/11/2019 Regulatory Requirements on PV (General)

    36/52

    PIC/S PI 006-3 CLAUSE 6.7.4

    Changes that are likely to require Re-Validation are as follows:a) Changes of Raw Materials (physical properties such as density,

    viscosity, particle size distribution may affect the process or product.

    b) Change of starting material manufacturer.

    c) Changes of Packaging material (e.g.: substituting plastic for glass).

    d) Changes in the process (E.g.: mixing times, drying temperatures),e) Changes in the equipment (E.g.: addition of automatic detection

    systems). Changes of equipment which involved the replacement ofequipment on a like for like basis would not normally require re-validation.

    f) Production area and support system changes (e.g.: rearrangement of

    areas, new water treatment method).g) Transfer of process to another site.

    h) Unexpected changes (e.g.: those observed during self inspection orduring routine analysis of process trend data).

  • 8/11/2019 Regulatory Requirements on PV (General)

    37/52

    COMMON MISTAKE

    Frequency

    Criticality

    A B

    C D

  • 8/11/2019 Regulatory Requirements on PV (General)

    38/52

    A) ALWAYS BUT NOT CRITICAL

    Type ExampleMissing information. -Pre-requisite status?

    -Raw Material, Packaging Material, Equipment,

    Facilities, Operators?

    -Location & Address,

    -Missing pages

    -Blur & Low resolution document.

    Typo error. -Color description,

    -Parameters, (Temp, time, etc)

    -Instruction,

    Wrong document. -Different strength.-Old processes.

    -Old/Different Plant

    Incomplete Document -Protocol not submitted

    -Report/Summary not submitted

  • 8/11/2019 Regulatory Requirements on PV (General)

    39/52

    B) SELDOM AND NOT CRITICAL

    Type ExampleSubmitting unnecessary

    documents.

    -DQ, IQ, OQ.

    -Media Fill Report for terminal process.

  • 8/11/2019 Regulatory Requirements on PV (General)

    40/52

    C) SELDOM AND CRITICAL

    Type Example-Totally different process. -Wet granulation Vs. Dry granulation.

    -Different media fill approach

    (powder filling vs. liquid filling)

    - Poor GMP practices. -Poor aseptic control.

    -Renovated plant.

    - Unjustified PV approach. - Retrospective or Concurrent instead of Prospective.

    - Different Formulation -New formulation.-Different product strength

    -Different coating material.

    -Different ingredients quantity.

  • 8/11/2019 Regulatory Requirements on PV (General)

    41/52

    D) ALWAYS AND CRITICAL

    Type Example

    -Re-validation condition -

    -Inconsistency with proposed

    manufacturing process.

    - Load, Speed, Temperature, time, distance, holding time,

    pressure, etc.

    - Undocumented important evidence. -Observed Equipment/process parameters

    -In-Process Manufacturing

    -Different equipment -Type of blender,

    -Load size,

    -Single punch vs. Rotary Punch

    -Different materials. -Unapproved sources.

    -Unapproved Documents. -Signature,

    -Conclusion

    -Different product Specification - Color, dimension,

  • 8/11/2019 Regulatory Requirements on PV (General)

    42/52

  • 8/11/2019 Regulatory Requirements on PV (General)

    43/52

    DO CGMPS REQUIRE THREE SUCCESSFUL PROCESS VALIDATION BATCHES BEFORE A NEW ACTIVE

    PHARMACEUTICAL INGREDIENT API) OR A FINISHED DRUG PRODUCT IS RELEASED FOR DISTRIBUTION?

    Sources: http://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm124782.htm

    No. Neither the CGMP regulations nor FDA policy specifies a minimum number of batches to

    validate a manufacturing process. The current industry guidance on APIs (see ICH Q7Afor APIs)also does not specify a specific number of batches for process validation.

    FDA recognizes that validating a manufacturing process, or a change to a process, cannot bereduced to so simplistic a formula as the completion of three successful full scale batches. Theagency acknowledges that the idea of three validation batches has become prevalent, in partdue to language in its own guidance documents. However, FDA is now clarifying currentexpectations on process validation. The 1987 Guideline of General Principles of ProcessValidationis currently being revised to address this issue. The emphasis for demonstratingvalidated processes is placed on the manufacturers process design and development studies inaddition to its demonstration of reproducibility at scale, a goal that has always been expected.

    However, a minimum number of conformance (a.k.a. validation) batchesnecessary to validate the manufacturing processes is not specified.

    The manufacturer is expected to have a sound rationale for its choices in thisregard.

    The agency encourages the use of science based approaches to processvalidation.

    http://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm124782.htmhttp://www.fda.gov/cder/guidance/4286fnl.htmhttp://www.fda.gov/cder/guidance/4286fnl.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm124782.htm
  • 8/11/2019 Regulatory Requirements on PV (General)

    44/52

    CURRENT & FUTURE?

    Cleaning Validation

    Computer & Software Validation

    Modern Process

    Glove Box Isolators

    Restricted Access Barrier System (RABs)

    Blow, Fill and Seal / Form, Fill & Seal

    Robotic controlled

    Worldwide Harmonization

  • 8/11/2019 Regulatory Requirements on PV (General)

    45/52

    Market holder responsibilities1. Option & Approach selection.

    2. Document Submission

    3. Details of Validation

  • 8/11/2019 Regulatory Requirements on PV (General)

    46/52

    1. OPTION AND APPROACH.

    Option ASEAN Guidelines Process Validation Approach

    Option 1i. Validation Report for 3 consecutive batches.

    Prospective Validation 3 consecutive successful batches or more

    Option 2

    i. Pharmaceutical Development report.ii. Validation report on 1 pilot batch OR

    Validation scheme.

    iii. Commitment to conduct Validation study.

    Concurrent Validation

    3 consecutive batches or more

    Option 3i. Validation Document from reference country.

    ii. Commitment To conduct Validation Study

    Retrospective Validation Previous data of 10-20* consecutive batches

    *ASEAN Guidelines On Process validation

  • 8/11/2019 Regulatory Requirements on PV (General)

    47/52

    2. DOCUMENT SUBMISSION

    Document Checkbox RemarkA Development Pharmaceutical Report Option 2

    B Validation Scheme / Protocol

    C Validation ReportPilot Batch

    Full production batch

    Option 2

    Option 1

    D Supporting documents.

    Cleaning validation

  • 8/11/2019 Regulatory Requirements on PV (General)

    48/52

    3. DETAILS OF VALIDATION

    a) Know your product.

    b) Know the Validation details. Approach : Prospective / Concurrent / Retrospective ?.

    Product ,

    Name,

    Strength,

    Dosage

    Form

    Primary

    Packing

    Proposed

    Commercial

    Batch size

    Manufacturer Country

    No Batch

    No

    Mfg Date Batch Type Validated

    Batch Size

    Manufacturer Country

    Experiment?

    Pilot?

    Commercial?

  • 8/11/2019 Regulatory Requirements on PV (General)

    49/52

    Question:

    If the validation data submitted for 3 consecutive production batches

    showed that they fully comply with specifications but do not fulfil the

    process validation acceptance criteria, would they be approved formarketing?

    Answer

    The onus is on the manufacturer to ensure that the manufacturing process is

    well controlled prior to manufacturing the batches for marketing. The

    manufacturer should provide justification for not meeting the acceptance criteria

    of process validation and may need to re-validate the process before releasing

    the said product batches which meet the quality specification for sale.

    Sources:ASEAN Guidelines on Process Validation (Q&A)http://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files

    _guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdf

    http://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdfhttp://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdfhttp://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdfhttp://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdf
  • 8/11/2019 Regulatory Requirements on PV (General)

    50/52

    REFERENCES

    A) PIC/S: http://www.picscheme.org

    e.g.: i) PI 006-3 : Recommendations on Validation Master Plan Intallation and OperationalQualification Non Sterile Process Validation Cleaning validation

    ii) PI 007-1: Recommendation on Validation of Aseptic Processes

    iii) PI 009-8 (Annexes)

    B) EMEA: http://www.tga.gov.au/docs/html/euguide/euad_qual.htm#qualitymedicinal

    e.g.: i) Note for Guidance on Process validation

    C) Singapore (HSA):

    http://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/GMP/guidelines.html

    e.g.: i) Non Sterile Process Validation

    ii) Validation of Aseptic Process iii) Validation of Terminal Moist Heat Sterilization

    http://www.picscheme.org/http://www.tga.gov.au/docs/html/euguide/euad_qual.htmhttp://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/GMP/guidelines.htmlhttp://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/GMP/guidelines.htmlhttp://www.tga.gov.au/docs/html/euguide/euad_qual.htmhttp://www.picscheme.org/
  • 8/11/2019 Regulatory Requirements on PV (General)

    51/52

    REFERENCES

    D) ASEAN: http://www.bpfk.gov.my/

    E.g.: i) ASEAN Guideline on Process Validation (29 KB)ii)ASEAN Guideline on Process Validation Q&A

    http://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/western_medicines/guidelines.html

    E) FDA/CDER

    http://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm064971.htm

    eg: i) General Principles of Process Validation

    ii) Sterile Drug Products Produced by Aseptic Processing - cGMP

    F) International Conference on Harmonisation - Quality (ICH-Q)

    http://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm065005.htm

    eg: i) Q7A Good Manufacturing Practice Guidance for Active Pharmaceutical Ingredients

    ii) Q8(R1) Pharmaceutical Development Revision 1

    iii) Q9 Quality Risk Management

    iv) Q10 Pharmaceutical Quality System

    G) Global Harmonization task Force

    http://www.bpfk.gov.my/http://202.144.202.76/bpfk/view_file.cfm?fileid=204http://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdfhttp://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/western_medicines/guidelines.htmlhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm064971.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm064971.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm065005.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm065005.htmhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073497.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073507.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073511.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073517.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073517.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073511.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073511.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073507.pdfhttp://www.fda.gov/downloads/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm073497.pdfhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm065005.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm065005.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm064971.htmhttp://www.fda.gov/Drugs/GuidanceComplianceRegulatoryInformation/Guidances/ucm064971.htmhttp://www.hsa.gov.sg/publish/hsaportal/en/health_products_regulation/western_medicines/guidelines.htmlhttp://www.hsa.gov.sg/publish/etc/medialib/hsa_library/health_products_regulation/western_medicines/files_guidelines.Par.20042.File.dat/ASEAN_Guideline_on_Process_Validation_Q&A_Version2_Jul07.pdfhttp://202.144.202.76/bpfk/view_file.cfm?fileid=204http://202.144.202.76/bpfk/view_file.cfm?fileid=204http://202.144.202.76/bpfk/view_file.cfm?fileid=204http://www.bpfk.gov.my/
  • 8/11/2019 Regulatory Requirements on PV (General)

    52/52

    [email protected]

    THANK YOU